Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Chapter 7
Technical Performance Based Earned Value as aManagement Tool for Engineering Projects
José Ignacio Muñoz Hernández,José Ramón Otegui Olaso and Julen Rubio Gómez
Additional information is available at the end of the chapter
http://dx.doi.org/10.5772/54497
1. Introduction
In the project management, one of the keys for the project success is the control of the projectin terms of performance, progress and cost. The first practice to control a project is just checkingthe financial reporting and therefore the project control is only based on the cost control(budgeted versus actual incurred cost). But the experience, especially from projects that failed,shows that a more efficient project management requires controlling also the project perform‐ance and scheduling besides the cost.
The Earned Value Management (EVM) is a methodology that integrates the management ofproject scope, schedule and cost. It has been widely and successfully used for over 40 yearsand it should apply to any project, large or small, at any industry. The interest about the EVMhas increased in the last ten years and a substantial amount of research has been carried outregarding the EVM, generating new extensions of the methodology and specific applications.In parallel, many guidelines and rules have been published to implement properly the EVM,coming mainly from the U.S. Government who originally developed the EVM, but not only,because also the ANSI organization has established a standard defining the EVM.
The contribution of this work is twofold. First of all, it aims to identify the principal lines ofresearch in the project management control using earned value management across theacademic research and organizations practice. Following, the attention is focused on thecharacteristics of one of these research lines, the PBEV. This extension pretends to be not onlyan EVM parameters enhancement but a complete managing system based on the technicalperformance, which could be a useful EVM improvement to be used in engines engineeringprojects where the technical objectives are the main target. Secondly, it lies in the intention of
© 2013 Hernández et al.; licensee InTech. This is an open access article distributed under the terms of theCreative Commons Attribution License (http://creativecommons.org/licenses/by/3.0), which permitsunrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
this work to evaluate the applicability and the efficiency of the PBEV with two case studies oftwo real-life engineering projects of combustion engines development for energy generationapplications.
2. Earned value management
2.1. EVM standard
Basically, the EVM requires a fixed point-of-reference, given by the project baseline scheduleand the budget at completion (BAC), in order to periodically measure the project performancealong the life of the project. Project performance, both in terms of time and costs, is determinedby comparing the three key parameters of the EVM, planned value (PV), actual costs (AC) andearned value (EV), resulting in performance variances known as schedule variance (SV=EV-PV) and cost variance (CV=EV-AC) and performance indexes as the schedule performanceindex (SPI=EV/PV) and the cost performance index (CPI=EV/AC). See [4] and [5]. Figure 1shows the EVM key parameters.
Figure 1. EVM key parameters.
For a better understanding of the state of the art of the EVM it is necessary to know its origins,widely commented in [1] and [2], and the official sources of EVM guidelines and standards.
The earned value concept originally came from industrial engineers in factories in the early1900s who for years have employed a three-dimensional approach to assess true “cost-performance” efficiencies. To assess their cost performance, they compared their earnedstandards (the physical factory output) against the actual cost incurred. Then, they comparedtheir earned standards to the original planned standards (the physical work they planned to
Engineering Management144
accomplish) to assess the schedule results. These efforts provided earned value in its most basicform. Most important, the industrial engineers defined a cost variance as the differencebetween the actual costs spent and the earned standards in the factory. This definition of a costvariance is perhaps the indication to determine whether one uses the earned-value concept.Later on, in 1965 the United States Air force acquisition managers defined 35 criteria whichcapture the essence of earned value management. Two years later the U.S. Department ofDefense (DoD) adopted these same criteria as part of their Cost/Schedule Control SystemsCriteria (C/SCSC). Then, in 1996, after a rewrite of the C/SCSC 35 criteria by private industry,the DoD accepted the rewording of this criteria under a new title called Earned Value Man‐agement System (EVMS), and the total number of criteria was reduced to 32. In 1998, NationalDefense Industrial Association (NDIA) obtained acceptance of the Earned Value ManagementSystem in the form of the American National Standards Institute, termed the ANSI/EIA-748Standard, see [3]. From this on, many research lines have been developed trying to improvethe EVM, and they are commented in the following point.
2.2. EVM further research lines
As mentioned in the introduction, the use of EVM and parts of it, or tailoring it to specificsituations continue to grow and a substantial amount of research is being carried out. The maininvestigations could be grouped at least in six big research lines as follows.
1. EVM and fuzzy determination of EV. One of the major difficulties in the determina‐tion of EV is the evaluation of in-process work. There are some techniques toquantify the accomplished work and some of them propose fuzzy techniques. Asexplained in [6] and [7].
2. EVM forecast accuracy. Some studies about EVM are focusing on the improvement of theaccuracy of EVM to calculate forecasts of project cost and schedule at completion. Seereferences [8], [9] and [10]
3. EVM and Earned Schedule. Another object of studies is an enhancement to Earned ValueManagement, called Earned Schedule that appeared in 2003. This method propose theparameters of the EVM in terms of time instead of cost, and it could be postulated to givemore forecasting accuracy in the latest stages of the project. See [11]. The author of thisresearch line criticized the use of the classic SV and SPI metrics since they give false andunreliable time forecasts near the end of the project. Instead, he provided a time-basedmeasure to overcome this unreliable behavior of the SV and SPI indicators. This earnedschedule method relies on similar principles than the earned value method, but translatesthe monetary metrics into a time dimension. He reformulated the time performancemeasures SV and SPI to SV(t) and SPI(t) (where the t between brackets is used to distin‐guish with the original performance measures) and has shown that they have a reliablebehavior along the whole life of the project. Since its introduction, a considerable streamof publications on the project time performance measurement and/or the earned scheduleconcept has been published in the academic literature. Statistical validation of the timeperformance indicators and stability studies on empirical data can be found in [12].
Technical Performance Based Earned Value as a Management Tool for Engineering Projectshttp://dx.doi.org/10.5772/54497
145
4. EVM to integrate risk management. There are project tools for risk analysis mainly focusedon network based techniques, such as, CPM (Critical Path Method) and PERT (ProgramEvaluation and Review Technique) and others based in statistical probabilities likeMontecarlo Simulations. Nevertheless, EVM contains no guidelines on risk management.Therefore, some investigations are conducting to integrate risk analysis in the EVM. First,including risk management activities in the WBS (Work Breakdown Structure) and secondconsidering that Estimated at Completion (EAC) should be based on both project per‐formance and quantified risk assessments. Other investigations try to combine the riskanalysis tool results, for example Montecarlo simulations, with EVM metrics. See [13].
5. EVM to integrate quality. The quality of the product must be tracked in an engineering projectto evaluate the success or failure of the product. Some studies are proposing to apply a qualityfactor to the EV, such as, reducing the EV when poor quality occurs. See [14].
6. EVM to integrate technical performance. In engineering projects not only cost andschedule must be tracked but also the technical performance. Further investigations arebeing done to integrate technical requirements accomplishment with EVM. One proposalis an EVM extension called Performed-Based Earned Value (PBEV). See [15-18].
This last extension of the EVM integrating the technical performance, the PBEV, will be deeplyanalyzed in the following points due to it is not only a new manner of measuring the earnedvalue but it is an entire management system which include concepts and procedures to managethe technical issues that could enhance the engineering projects in general. Therefore, it willbe studied its suitability to engine engineering projects.
Figure 2. EVM evolution and research lines.
3. PBEV: The EVM extension focusing on technical performance
3.1. PBEV introduction
The Performance Based Earned Value (PBEV) is an enhancement to the EVM standard thatovercomes the standard´s shortcomings with regard to measuring technical performance and
Engineering Management146
quality because it is based on standards and models for systems engineering, softwareengineering, and project management. The distinguishing feature of PBEV is its focus on thecustomer requirements. PBEV provides principles and guidance for cost effective processesthat specify the most effective measures of cost, schedule, and product quality performance.
The PBEV has been formulated by the author Paul J. Solomon, see [16], whom experience atprograms management and concretely with the EMVS explains the origin of the PBEV.Solomon manages the EVM for Northrop Grumman Corporation, Integrated Systems and hehas participated in programs for the U.S. Government as the B-2 Bomber, Global Hawk andF-35 Joint Strike Fighter. He is on the board of the National Defense Industrial Association,Program Management Systems Subcommittee that authored ANSI/EIA-748.
3.2. EVM shortcomings
The cancellation of the US Navy’s A-12 Avenger stealth aircraft program in January 1991resulted in research during the 1990s, which investigated the reliability of EVM cost predictionand the project management failures in accurately reporting project performance, using U.S.Department of Defense (DOD) project data. These research findings have come to be regardedas generally applicable across all project types using EVM across multiple industry sectors.The U.S. Government Accountability Office (GAO), for example, studied failures in acquisitionof weapons systems and information technology systems. Some report of the GAO concludedthat DOD paid billions in award and incentive fees regardless the contractors not held costgoals, schedule goals and the program did not capture early on the warnings needed toeffectively manage program risk. The GAO concluded that, if EVM is not properly imple‐mented, the data may be inaccurate and misleading.
The EVM standard, which is formulated in the ANSI/EIA Standard-748-A-1998, has significantshortcomings with regard to measuring technical performance and quality. First, the EVMSstandard states that EV is a measurement of the quantity of work accomplished and that thequality and technical content of work performed are controlled by other processes. A programmanager should ensure that EV is also a measurement of the product quality and technicalmaturity of the evolving work products instead of just the quantity of work accomplished.Second, the EVMS principles address only the project work scope. EVMS ignores the productscope and product requirements. Third, EVM is perceived to be a risk management tool.However, EVMS was not designed to manage risk and does not even mention the subject.
Thus, the EVM will provide more reliable information for analysis and decision-making if theEVM guidelines are augmented by guidance regarding maintaining the technical baseline,measuring technical performance, and managing risk.
3.3. U.S. DOD policy and industrial standards
Most of the guidelines and best practices for planning and measuring the technical perform‐ance considering also the EVM are provided by two sources: the U.S. Department of Defense(DOD) and some industrial standards.
Technical Performance Based Earned Value as a Management Tool for Engineering Projectshttp://dx.doi.org/10.5772/54497
147
First of this sources, the U.S. DOD, issued an acquisition policy which states that programsimplement Systems Engineering Plans (SEP). DOD also published guides to implement thepolicy, such as:
1. The Defense Acquisition Guidebook (DAG).
2. The Systems Engineering Plan Preparation Guide (SEPPG).
3. The Work Breakdown Structure Handbook (MIL-HDBK-881A (WBS))
4. The Integrated Master Plan (IMP).
5. The Integrated Master Schedule (IMS) Preparation and Use Guide.
6. The DOD guides refer also to EVMS. See [19].
These guides show the enormous importance that the U.S. DOD gives to measuring technicalperformance, hence, according to U.S. DOD it should be one of the parameters to control duringproject progress. See [20] and [21].
The second source of guidelines for planning and measuring the technical performance aresome industry and professional standards, that have been incorporating the technical per‐formance accomplishment for the project control and they have been at the same time sourcesthemselves for defining the DOD policy, as well as:
1. The Institute of Electrical and Electronics Engineers (IEEE) 1220.
2. EIA 632.
3. “A Guide to the Project Management Body of Knowledge” (PMBOK). See [22] and [23].
4. Capability Maturity Model Integration (CMMI). See [24].
In the following points are explained the main concepts defined by the U.S. DOD guidelinesand the industrial standards that are used by the PBEV. Figure 3 shows the guidelines andstandards and their sources for technical performance treatment at projects.
Figure 3. Guidelines and standards to manage technical performance.
Engineering Management148
3.4. PBEV guidelines
The PBEV is a set of principles and guidelines that specify the most effective measures of cost,schedule, and product quality performance. It has several characteristics that distinguish itfrom standard EVMS:
• Plan is driven by product quality requirements, not work requirements.
• Focuses on technical maturity and quality, in addition to work.
• Focuses on progress toward meeting success criteria of technical reviews.
• Adheres to standards and models for SE, software engineering, and project management.
• Provides smart work package planning.
• Enables insightful variance analysis.
• Ensures a lean and cost-effective approach.
• Enables scalable scope and complexity depending on risk.
• Integrates risk management activities with the performance measurement baseline.
• Integrates risk management outcomes with the Estimate at Completion.
PBEV augments EVMS with 4 additional principles and 16 guidelines. The following are PBEVprinciples that set it apart from EVMS:
1. Product scope and quality. Integrate product scope and quality requirements into theperformance measurement baseline. This principle focuses on customer satisfaction,which is based on delivery of a product that meets its quality requirements and is withinthe cost and schedule objectives.
2. Product quality requirements. Specify performance toward satisfying product qualityrequirements as a base measure of earned value. A product quality requirement is acharacteristic of a product that is mandatory in order for the product to meet verifiedcustomer needs.
3. Risk management integration. Integrate risk management with EVM.
4. Tailor PBEV. Tailor the application of PBEV according to the risk.
And the PBEV guidelines are listed following.
1. Establish product quality requirements and allocate these to product components.
2. Maintain bidirectional traceability of product and product component quality require‐ments among the project plans, work packages, planning packages, and work products.
3. Identify changes that need to be made to the project plans, work packages, planningpackages, and work products resulting from changes to the products qualityrequirements.
Technical Performance Based Earned Value as a Management Tool for Engineering Projectshttp://dx.doi.org/10.5772/54497
149
4. Define the information need and objective to measure progress toward satisfying productquality requirements.
5. Specify work products and performance-based measures of progress for satisfyingproduct quality requirements as base measures of earned value.
6. Specify operational definitions for the base measures of earned value, stated in precise,unambiguous terms that address communication and repeatability.
7. Identify event-based success criteria for technical reviews that include developmentmaturity to date and the products´s ability to satisfy product quality requirements.
8. Establish time-phased planned values for measures of progress toward meeting productquality requirements, dates of frequency for checking progress, and dates when fullconformance will be met.
9. Allocate budget in discrete work packages to measures of progress toward meetingproduct quality requirements.
10. Compare the amount of planned budget and the amount of budget earned for achievingprogress toward meeting product quality requirements.
11. Use Level of Effort method to plan work that is measurable, but is not a measure ofprogress toward satisfying product quality requirements, final cost objectives, or finalschedule objectives
12. Perform more effective variance analysis by segregating discrete effort from Level ofEffort.
13. Identify changes that need to be made to the project plans, work packages, planningpackages, and work products resulting from responses to risks.
14. Develop revised estimates of costs at completion based on risk quantification.
15. Apply PBEV coverage to the whole work breakdown structure or just to the higher riskcomponents.
16. Apply PBEV throughout the whole system development life cycle or initiate afterrequirements development.
3.5. PBEV concepts
The PBEV feeds on concepts from the U.S. DOD guidelines and industrial standards mentionedabove. In the following points are explained in detail the main concepts used in the PBEVcoming from those sources, such as, the Systems Engineering Plan (SEP), the products metricsand quality, the success criteria, the Technical Performance Measurements (TPM) andCapability Maturity Model Integration (CMMI). The concepts that feed the PBEV are shownin figure 4.
Engineering Management150
TPM
PBEV
CMMI
PRODUCT METRICS &
QUALITY
SUCCESS CRITERIA
SEP
Figure 4. The concepts that feeds the PBEV
1. Systems Engineering Plan (SEP)
The purpose of the Systems Engineering Plan (SEP) is to help programs develop their SystemsEngineering (SE) approach, providing a firm and well-documented technical foundation forthe program. The SEP is a living document in which periodic updates capture the program’scurrent status and evolving SE implementation and its relationship with the overall programmanagement effort. Although the detailed content of each SEP is customized according to theparticulars of a program and each update may vary depending on the program’s acquisitionphase, using a common framework encourages sound technical planning throughout theprogram’s life cycle. The emphasis should be on the rigor of the technical planning as capturedin the SEP, not on the SEP itself. The SEP also serves as a common reference to achieve sharedstakeholder insight regarding a program’s planned technical approach. It provides a docu‐mented understanding of how the program will accommodate cost, schedule, performance,and sustainment trades; the expected products of the SE effort; and how these products willcontribute to program decision making.
Technical Performance Based Earned Value as a Management Tool for Engineering Projectshttp://dx.doi.org/10.5772/54497
151
• Products metrics and quality
The IEEE 1220 and the EIA 632 have similar guidance regarding product metrics andquality. Product metrics allow assessment of the product´s ability to satisfy requirementsand to evaluate the evolving product quality against planned or expected values. Ofequal importance are a disciplined requirements traceability process and a requirementstraceability database.
• Success criteria
The standards discuss the importance of holding technical reviews at various stages ofdevelopment to assure that all success criteria have been met. IEEE 1220 provides successcriteria to be used at major technical reviews. For example some of the success criteria for apreliminary design review are the following:
i. Prior completion of subsystem reviews.
ii. Determine whether total system approach to detailed design satisfies the systembaseline.
iii. Unacceptable risks are mitigated.
iv. Issues for all subsystems, products, and life-cycle processes are resolved.
The success criteria should be defined in a SEP or other technical plan. The customer shouldreview this plan with the supplier and reach agreement on the success criteria to be used attechnical reviews.
• Technical Performance Measurement (TPM)
Technical Performance Measurement (TPM) are defined and evaluated to assess how well asystem is achieving its performance requirements. TPM uses actual or predicted values fromengineering measurements, test, experiments, or prototypes. IEEE 1220, EIA 632 and “A Guideto the Project Management Body of Knowledge” (PMBOK guide) provide similar guidancefor TPM planning and measurement and for integrating TPM and EVM.
• Capability Maturity Model Integration (CMMI)
The CMMI provides many practices that augment the EVMS guidelines. CMMI also listsTypical Work Products (TWPs) within process areas. To ensure traceability of product qualityrequirements to work tasks and work products, these TWPs, or similar artifacts, should be theoutcome of work packages. Here are some TWPs in CMMI.
TWPs include the following:
i. Product-component requirements.
ii. Activities diagrams and use cases.
iii. Verification criteria used to ensure requirements have been achieved.
iv. Exit and entry criteria for work products.
Engineering Management152
3.6. PBEV pros and cons
Following are listed the advantages and disadvantages of the PBEV that it has been used alsoin the following case studies analyzed during this work.
The main PBEV pros are:
• It integrates effectively the technical performance with the cost and schedule control.
• It collects the best practices of the U.S. DOD guides and industry and professional standardsrelated with project management and then apply the EVM.
• It is based on client or product requirements.
By the other hand, the PBEV could have the following cons:
• It gives a very large methodology to implement to be able to integrate the technical per‐formance in the project management control but there is no mention to any parameter, ormetric definition to implement easily that allows calculating EVM variances or indexes withresults of technical performance status.
• It only influences somehow the work breakdown structure but not the EVM metrics.
• The customer should review the SE plan with the supplier and reach agreement on thesuccess criteria to be used at technical reviews. It would be more objective to define atechnical parameter to evaluate success criteria, as for example, the strength safety marginof a mechanical part.
4. PBEV model adaptation to industrial production environment
They have been performed two case studies of the applicability and the efficiency of the EVMstandard and one of its extensions, the PBEV which is based on technical performance, for theengines engineering projects control in the energy field.
4.1. Type of projects analyzed
They have been analyzed two real-life projects of engine engineering in the energy fieldperformed between 2004 and 2005 by a company dedicated to the development and manu‐facturing of combustion engines for power generation.
These projects are characterized by including the typical phases of the industrial engineeringprojects, such as, the concept design phase, detailed design phase, simulation, prototyping,testing and launch mass production, where the level of compliance of the technical objectivesis strongly important besides the cost and scheduling control. The two projects analyzed arealso featured by the fact that they are large projects in the energy field as they have budgetsof several million euros, durations between 2-4 years and the risk of developing new productsfor the market. The large size of the projects makes the breakdown structure of the tasks (WBS)to be also quite large. Another property that characterizes these two projects, and in general
Technical Performance Based Earned Value as a Management Tool for Engineering Projectshttp://dx.doi.org/10.5772/54497
153
all the engine development projects in the energy field, is that they are pretty similar to enginedevelopment projects in the automotive field since the product is similar. Therefore, theengines made for energy field are fed with many of the technologies used in automotive field,as well as, with the methodologies and requirements to create new products that meet themarket requirements. The competitiveness for obtain improved technical results makes thatin both, energy projects and automotive projects, the technical objectives are a critical param‐eter to control for the project, just with the costs and the schedule. Hence, the PBEV could bea suitable and useful tool for integrating scope, schedule, cost and technical performance inthese projects. Moreover, in both fields, energy and automotive, the continuous technologyevolution makes the technical objectives to be overpassed from one project to the following.For that reason is a real-life practice in these fields that at new product development projects,with the existing technology in that moment, that, if the technical objectives are not met butthey are inside of an allowable range, the project could be accepted with penalties.
In summary, the projects analyzed with PBEV are characterized for being classical industrialengineering projects with large size of the WBS, also for having the technical performance asa key parameter to control where the technical objective could be in a range of tolerance foraccept the successful of the project. The project number 1 consists on the development of a newengine of higher efficiency and power than the existing ones in the company and the projectnumber 2 was dedicated to development a new injection system for the current engines. Figure5 shows the type of engine developed in project 1 and 2.
Figure 5. Type of projects analysed: engine engineering projects
Engineering Management154
4.2. Project information
The project 1 began in January 2004 and was delayed one year by material procurementproblems but once they were negotiated new deadlines with suppliers in 2005 was launchedagain and began an overall tracking of the technical targets, cost and schedule. In this project,the engineering consultancy delivered a design that was slightly below the technical targetsof engine performance and efficiency, which was penalized in his fees. The engine efficiencytarget was 42% but an engine with 40% was obtained. Finally, the project was completed inJanuary 2008, bringing to the market the new engine with a very good acceptance and overallrating of satisfactory.
Regarding the project 2, it began also in 2005 and although the design and material procure‐ment were on time, the project turned 180º in 2007 when it was found that to accomplish thetechnical targets of the new injection system it was necessary to implement a technology 10times more expensive than originally planned. This event made management direction to stopthe project after making a rough estimation of the overall cost of the project with the imple‐mentation of the new technology.
From these two project data, here is proposed to apply the PBEV to analyze if it is possible toreport the status of the project in time, cost and technical compliance, to predict future states.
In the two projects analyzed the available information during the duration of all the projectwas the following documents and reports.
a. A project specification document which collects all the technical specifications to meetwith contractual nature.
b. A Statement Of Work (SOW) document which collects the definition of all the tasks to beperformed in the project and has contractual nature.
c. The initial baseline schedule in an MS project file. It is detailed with several tasks levelsand including the starting and finishing dates, as well as, the dependences between them.
d. The total budget of the project made at the beginning of the project and broken down ingeneral spending issues. The general spending issues are the following six: material costs,the tooling investments, engineering hours, outsourcing expert consultancy supporthours, testing costs, and trips. Intermediate budget estimation was not performed duringthe project progress.
e. The general accounting of the project with the invoiced costs per month. They are availablethe figures of monthly costs of the general issues.
f. A monthly report with the technical, economical and scheduling tracing. The technical partof the report included a list of all manufacturing drawings and the testing results. Figure 6shows engine control units screen where technical parameters are monitored, as for example,the engine performance. These technical values are the reference to check the technicalaccomplishment. The economical part of the report included cost monthly figures of thegeneral spending issues collected from the invoices. The scheduling part of the reportincluded approximate deadlines for the critical tasks but not a detailed scheduling track.
Technical Performance Based Earned Value as a Management Tool for Engineering Projectshttp://dx.doi.org/10.5772/54497
155
Figure 6. Engine control unit monitoring engine performance
4.3. Methodology
Due to fact that the available data in the two projects analyzed are the initial budget, accumu‐lated costs and the engineering hours accumulated only for the higher level of the WBS, theEVM is applied only at this top level. This way of controlling is called top-down project control.According to reference [13], the EVM offers calculation methods yielding reliable results onhigher WBS levels, which greatly simplify final duration and completion date forecasting.These early warning signals, if analyzed properly, define the need to eventually go down intolower WBS levels when action thresholds are exceeded. In conjunction with the projectschedule, it allows taking corrective actions on those activities which are in trouble (especiallythose tasks which are on the critical path).
The methodology used to implement the EVM based on technical performance in the twoprojects under study has two steps. The first step is to apply the EVM standard and check ifthe results are consistent. The second step is to apply the PBEV through the use of penalties inthe obtained EV when the technical requirements are not met and check if the results areconsistent with the reality of the project. An objectively way of establish the penalties dependson the technical parameter selected to control and on the technical performance measurement,
Engineering Management156
therefore, it depends on the internal mechanisms of each company to evaluate the objectivescompliance as explained in reference [16].
To carry on the first step, this is to apply the EVM standard on the two projects, from theavailable data, one begins by determining the values of the three basic parameters of the EVM,and this is, PV, AC and EV. Because PV is not available monthly, it is considered the hypothesisof distributing uniformly the initial budget between the months of the project, and then thePV accumulated is lineal. The figures of the monthly AC are available in the project data.Finally, to calculate the EV, the engineering hours performed are taken as the indicator of workaccomplished. And from the 3 basic parameters they are calculated the Cost and ScheduleVariances (CV and SV) and the Cost and Schedule Performance Indices (CPI and SPI) to checkif the results of de EVM are consistent.
To implement the second step, this is to calculate the PBEV, a reduction of the EV is appliedin the monthly work accomplished when the technical objectives are not met, so in this way itis shown that the project is farther from the objectives and then from finish than planned.
Yes
No
Yes
APPLY EVM
APPLY PBEV
WBS
PROJECT TECHNICALCONTROL
AC,PV,EV
OK
OK
EV PENALIZED
No
PROJECT DATA
Figure 7. Methodology to apply PBEV to engine engineering projects.
Technical Performance Based Earned Value as a Management Tool for Engineering Projectshttp://dx.doi.org/10.5772/54497
157
5. Case studies: Applying PBEV to engine engineering projects
5.1. Research questions
The two case studies carried out with engine engineering projects have been raised as a seriesof research questions to be answered in order to draw conclusions. The research questions arethe following:
• Q1: Is it possible to apply the EVM standard to engines engineering projects only with thedata that is usually controlled in such projects?
• Q2: Is it possible to apply the PBEV to engines engineering projects?
• Q3: Does the PBEV capture the real project progress in engines engineering projects withonly the project information available?
• Q4: Is it useful the information resulting from the PBEV to take decisions in the engineengineering projects?
5.2. Results
In this point are summarized the two case studies results. Table 2 shows the project 1 cumu‐lative cost data. The Budget At Completion (BAC) for project 1 was 2.427.950 euros. The costsand BAC are used as input to calculate the EVM and the PBEV parameters which are shownin table 2.
PROJECT 1 - CUMULATIVE COST DATA (€)
ITEM Oct-07 Jun-08 Aug-08 Nov-08 Dec-08
MATERIALS 416.686 444.229 445.059 471.645 472.736
INVESTMENT 279.356 279.356 279.356 279.356 279.356
LABOR HOURS 308.880 400.650 424.890 474.750 487.560
TESTING HOURS 2.935 4.036 4.353 4.688 4.688
ENGINEERING
OUTSOURCING1.443.296 1.522.324 1.522.605 1.526.015 1.526.015
TRIPS 13.021 16.435 16.435 22.524 22.730
TOTAL 2.464.174 2.667.030 2.692.698 2.778.978 2.793.085
Table 1. Project 1 cumulative cost data in euros.
Engineering Management158
PROJECT 1 - EVM AND PBEV CALCULATED PARAMETERS
PARAMETER Oct-07 Jun-08 Aug-08 Nov-08 Dec-08
PV 1.824.282 2.169.235 2.255.473 2.384.831 2.427.950
AC 2.464.174 2.667.030 2.692.698 2.778.978 2.793.085
EV 1.538.160 1.995.156 2.115.866 2.364.159 2.427.950
CV -926.014 -671.874 -576.832 -414.819 -365.135
SV -286.122 -174.079 -139.607 -20.672 0
CPI 0,62 0,75 0,79 0,85 0,87
SPI 0,84 0,92 0,94 0,99 1,00
PBEV 1.300.000 1.600.000 1.700.000 1.900.000 2.000.000
Table 2. Project 1 EVM and PBEV calculated parameters.
Figure 8 shows the calculated EVM parameters and figure 9 shows the calculated PBEV againstthe EVM for project 1.
Engineering Management 16
Figure 8 shows the calculated EVM parameters and figure 9 shows the calculated PBEV 1 against the EVM for project 1. 2
3
Figure 8. Project 1 calculated EVM parameters AC, PV, EV. 4
5
Figure 9. Project 1 EVM versus PBEV. 6
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
Dec‐05 May‐06 Oct‐06 Mar‐07 Aug‐07 Jan‐08 Jun‐08 Nov‐08
Cost (€)
Time (months)
AC PV EV
0
20
40
60
80
100
120
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
Dec‐05 May‐06 Oct‐06 Mar‐07 Aug‐07 Jan‐08 Jun‐08 Nov‐08
% objectives compliance
Cost (€)
Time (months)
AC PV EV
PBEV EV max EV min
Figure 8. Project 1 calculated EVM parameters AC, PV, EV.
Technical Performance Based Earned Value as a Management Tool for Engineering Projectshttp://dx.doi.org/10.5772/54497
159
Engineering Management 16
Figure 8 shows the calculated EVM parameters and figure 9 shows the calculated PBEV 1 against the EVM for project 1. 2
3
Figure 8. Project 1 calculated EVM parameters AC, PV, EV. 4
5
Figure 9. Project 1 EVM versus PBEV. 6
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
Dec‐05 May‐06 Oct‐06 Mar‐07 Aug‐07 Jan‐08 Jun‐08 Nov‐08
Cost (€)
Time (months)
AC PV EV
0
20
40
60
80
100
120
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
Dec‐05 May‐06 Oct‐06 Mar‐07 Aug‐07 Jan‐08 Jun‐08 Nov‐08
% objectives compliance
Cost (€)
Time (months)
AC PV EV
PBEV EV max EV min
Figure 9. Project 1 EVM versus PBEV.
Following is explained the calculation of the points of figure 9. Let instant time June 2008, forexample, the Actual Cost, AC, is 2.667.030€, which is a project data defined in table 1. ThePlanned Value, PV, is the proportional part of the total budget, BAC, corresponding to themonth 30, that is June 2008, over the total number of months of the project which is 36 fromDecember 2005 to December 2008. Previously, to the initial BAC of the 2004 which was a projectinput data of 2.427.950€ is subtracted the costs from 2004 to 2005 of 875.661€ to consider theinitial BAC updated to 2005 because in this year the project was launched again after a delayan all the project data start in 2005. The Earned Value, EV, is calculated with the rate laborhours at June 2008 over the total labor hours multiply by the BAC, resulting in 1.995.156 €. Forcalculating the PBEV it is considered a penalty of 25% in the EV because the engine efficiencytarget of 42% is not achieved and instead of that is obtained 40%.
Table 3 shows the project 2 cumulative cost data. The Budget At Completion (BAC) for project2 was 2.616.831 euros. The costs and BAC are used as input to calculate the EVM and the PBEVparameters which are shown in table 4.
PROJECT 2 - CUMULATIVE COST DATA (€)
ITEM Jan-07 Feb-07 Mar-07 Apr-07 May-07
MATERIALS 297.018 298.606 315.487 315.742 324.575
INVESTMENT 54.467 54.467 54.467 54.467 54.467
LABOR HOURS 307.170 320.940 338.220 346.530 366.480
TESTING HOURS 111.854 126.781 138.642 147.510 159.630
ENGINEERING OUTSOURCING 139.290 139.290 139.290 139.290 139.290
TRIPS 18.770 18.770 18.770 18.770 19.370
FUEL 2.822 3.000 3.256 3.408 3.986
TOTAL 931.391 961.854 1.008.132 1.025.717 1.067.798
Table 3. Project 2 cumulative cost data in euros.
Engineering Management160
PROJECT 2 - EVM AND PBEV CALCULATED PARAMETERS
PARAMETER Jan-07 Feb-07 Mar-07 Apr-07 May-07
PV 2.030.091 2.176.776 2.323.461 2.470.146 2.616.831
AC 931.391 961.854 1.008.132 1.025.717 1.067.798
EV 307.170 320.940 338.220 346.530 366.480
CV -624.221 -640.914 -669.912 -679.187 -701.318
SV -1.722.921 -1.855.836 -1.985.241 -2.123.616 -2.250.351
CPI 0,33 0,33 0,34 0,34 0,34
SPI 0,15 0,15 0,15 0,14 0,14
PBEV 300.000 300.000 300.000 300.000 300.000
Table 4. Project 2 EVM and PBEV calculated parameters.
Figure 10 shows the calculated EVM parameters and figure 11 shows the calculated PBEVagainst the EVM for project 2.
Engineering Management 18
1
Figure 10. Project 2 calculated EVM parameters AC, PV, EV. 2
3
Figure 11. Project 2 EVM versus PBEV. 4
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
Dec‐05 Mar‐06 Jun‐06 Sep‐06 Dec‐06 Mar‐07
Cost (€)
Time (months)
AC PV EV
0
20
40
60
80
100
120
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
Dec‐05 Mar‐06 Jun‐06 Sep‐06 Dec‐06 Mar‐07
% Objectives compliance
Cost (€)
Time (months)
AC PV EV
PBEV EV max EV minFigure 10. Project 2 calculated EVM parameters AC, PV, EV.
Technical Performance Based Earned Value as a Management Tool for Engineering Projectshttp://dx.doi.org/10.5772/54497
161
Engineering Management 18
1
Figure 10. Project 2 calculated EVM parameters AC, PV, EV. 2
3
Figure 11. Project 2 EVM versus PBEV. 4
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
Dec‐05 Mar‐06 Jun‐06 Sep‐06 Dec‐06 Mar‐07
Cost (€)
Time (months)
AC PV EV
0
20
40
60
80
100
120
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
Dec‐05 Mar‐06 Jun‐06 Sep‐06 Dec‐06 Mar‐07
% Objectives compliance
Cost (€)
Time (months)
AC PV EV
PBEV EV max EV min
Figure 11. Project 2 EVM versus PBEV.
Now, it is possible to give answers to the proposed questions.
• Q1: The results presented in figures 8 and 10 show that it is possible to apply the EVM tothe higher level of the WBS in projects where the only information is the monthly accountingand the work progress, so the EVM parameters could be obtained and a project control withEVM is possible. For checking that the obtained values for AC, PV and EV are consistentwith the EVM, it could be checked that in general when a project is finished satisfactorilythe SV is zero and the SPI is 1, due to the fact that at the end of the project the earned valuewill match with the planned value. For the project 1, which finished satisfactorily, at the endof the project the EV fitted with the PV and therefore the SV is zero and the SPI is 1, as canbe seen in table 2. By the other hand, for the project 2, which was intentionally terminatedby the managing director, the EV does not reach the PV and thus, the SV never becomeszero and the SPI does not tend to 1. The EVM application in both projects is consistent withEVM rules and with the reality of the projects.
• Q2: The result of PBEV presented in figures 9 and 11 shows that, once the EVM is applied, isalso applicable the PBEV if they are defined penalties for when the technical targets are notfully accomplished. The manner to quantify the penalties depends on each company’s internalprocedure and his technical performance measurements, as it is mentioned in [16]. For theproject 1, after applying the PBEV criteria, which means a reduction in the EV value becausein this project was established an engine efficiency of 42% and it reached only to 40%, theobtained PBEV is still inside an admissible range of objectives accomplishment and thus it isaccepted the engine with performance 40% to be released. In the case of the project 2, theapplication of the PBEV is also possible but it has not much influence because of the projectcircumstance of have been stopped by Managing Director. Thus, this project had not time tocorrect the situation even the PBEV gives a more realistic status of objectives accomplishment.
Engineering Management162
• Q3: As the PBEV using the EV with penalty adjust the real situation of the projectintegrating technical targets, cost and schedule, it captures properly the real situation inan engine development project where the accomplishment of the technical targets is akey parameter.
• Q4: The PBEV gives useful information for the project control and helps to the decisionmaking process regarding the technical targets compliance besides the cost and schedulingcontrol. The proposed EV with penalty in the PBEV reduce the EV near the end of the projectand this implies to take a decision between accepting the project finish with the obtainedtechnical results under the objectives or the necessity of continue the project until theobjectives are achieved.
6. Conclusions
The following conclusions could be extracted from the present work.
• The EVM method to project control has been widely extended in the last ten years and asubstantial amount of research has been generated in academic literature and industrialguidelines to evaluate the method and proposing extensions to improve it.
• The research regarding the EVM could be classified in six main research lines accordingwith this work. The research lines try to enhance the EVM adding to it concepts, such as,the product quality, the project risk analysis, the technical performance, a fuzzy determi‐nation of the EV, or analysing for example the EVM forecast accuracy, or even, there is aresearch line, the Earned Schedule, that proposes another point of view for the EVM in termsof time instead of costs.
• One of the most complete extensions of the EVM is the PBEV, that is not only a new EVMmetric to evaluate the technical performance but a complete system of guidelines for projectmanagement that integrates the technical performance measurement in all the projectmanagement procedures including the EVM.
• The PBEV could be applied to industrial projects such as engine engineering projects in theenergy field and it could be applied at the top level of the project WBS.
• The case study number 1 shows that PBEV allows capturing the real project status includingthe technical performance. In this case, the PBEV reduce the EV near the end of the projectand this implies to take a decision between accepting the project finish with the obtainedtechnical results under the objectives or the necessity of continue the project until the reachthe objectives.
• The case study number 2 shows that PBEV could be applied to a project that finishdramatically but it does not contribute significantly to give early warnings of thehealth of the project if the project finished by other issue regardless the technicalperformance.
Technical Performance Based Earned Value as a Management Tool for Engineering Projectshttp://dx.doi.org/10.5772/54497
163
7. Future research
In a complementary way to the PBEV that considers EV with penalty when the technical targetis not achieved, it could be proposed other penalties in the PBEV variables, such as, the penaltyto the AC to capture the reduction in supplier’s fees when the technical targets are not met orwhen the project suffers an unexpected increase in the cost of any task or component. This ACwith penalty could be an improvement in the project management as a tool also for riskmanagement.
The future research in general will include probably new metrics in the EVM methodology totake into account issues like risk analysis or quality and technical performance for a moreefficient project control. By the moment, these issues depend on the practitioners, to beincluded in the project scheduling by means of milestones which is quite subjective.
Moreover, the combination of other project management techniques with EVM is also a goodpractice that is under developing by some authors.
Which it is sure is that the EVM will take place as a common tool in the project managementas Gantt did in the past because it is easy, quick, an efficient.
Author details
José Ignacio Muñoz Hernández1, José Ramón Otegui Olaso2 and Julen Rubio Gómez3
*Address all correspondence to: [email protected]
1 University of Castilla-La Mancha UCLM, Spain
2 University of the Basque Country UPV/EHU, Spain
3 Dresser-Rand Inc., U.S.A.
References
[1] Fleming Q, Koppelman J. Earned Value Project Management. The Journal of DefenseSoftware Engineering 1998.
[2] Kwak Y, Anbari F. History, Practices, and Future of Earned Value Management inGovernment: Perspectives from NASA. Project Management Journal 2012;43(1) 77-90.
[3] American National Standards Institute. Earned Value Management Systems. ANSI/EIA-748-A-1998. 1998.
[4] Anbari F. Earned Value Project Management Method and Extensions. Project Manage‐ment Journal 2003;34(4) 12-23.
Engineering Management164
[5] Fleming Q, Koppelman J. Start with “Simple” Earned Value…on All Your Projects. TheMeasurable News 2006.
[6] Moslemi L, Shadrokh S, Salehipour A. A fuzzy approach for the earned value man‐agement. International Journal of Project Management 2011;29(6) 764-772.
[7] Noori S, Bagherpour M, Zorriasatine F. Designing a control mechanism for productionplanning problems by means of earned value analysis. Journal of Applied Sciences2008;8(18) 3221-3227.
[8] Vanhoucke M, Vandevoorde S. Earned Value Forecast Accuracy and Activity Critical‐ity. The Measurable News, 2008; 13-16.
[9] Fleming Q, Koppelman J. The Two Most Useful Earned Value Metrics: the CPI and theTCPI. The Journal of Defense Software Engineering 2009.
[10] Pajares J, López-Paredes A. An extension of the EVM analysis for project monitoring:The Cost Control Index and the Schedule Control Index. International Journal of ProjectManagement 2011;29(5) 615-621.
[11] Lipke W. Shedule Is Different. The Measurable News 2003; 31-34.
[12] Lipke W, Zwikael O, Henderson K, Anbari F. Prediction of Project Outcome: Theapplication of Statistical Methods to Earned Value Management and Earned SchedulePerformance Indexes. International Journal of Project Management 2009;27(4) 400-407.
[13] Vanhoucke M. Measuring the Efficiency of Project Control Using Ficticious andEmpirical Project Data. International Journal of Project Management 2011; To Ap‐pear(2) 252-263.
[14] Xu J. Project Integrated Management Based on Quality Earned Value. Proceedings ofthe 2nd International Conference on Information Science and Engineering 2010; 432-435.
[15] Solomon P. Practical Software Measurement, Performance-Based Earned Value. TheJournal of Defense Software Engineering 2001.
[16] Solomon P. Performance-Based Earned Value. The Journal of Defense SoftwareEngineering 2005.
[17] Solomon P. Practical Performance-Based Earned Value. The Journal of DefenseSoftware Engineering 2006.
[18] Solomon P. Integrating Systems Engineering with Earned Value Management. TheMeasurable News 2008; 4.
[19] DOD Earned Value Management Implementation Guide. U.S. Department of Defense.http://www.acq.osd.mil/evm/resources/guidance-references.shtml (accessed 10February 2012).
[20] Humphreys and Associates. http://www.humphreys-assoc.com/evms/evms-imple‐mentation-ta-a-18.html (accessed 17 February 2012).
Technical Performance Based Earned Value as a Management Tool for Engineering Projectshttp://dx.doi.org/10.5772/54497
165
[21] National Aeronautics and Space Administration. NASA. http://evm.nasa.gov (accessed3 February 2012).
[22] PMBOK, 2004. A guide to the Project Management Body of knowledge. ProjectManagement Institute; 2004.
[23] PMI, 2005. The Practice Standard for Earned Value Management. Project ManagementInstitute; 2005.
[24] Kerzner H. Project Management. A Systems Approach to Planning, Scheduling andControlling. John Wiley and sons 2003.
Engineering Management166