Upload
vuongkhanh
View
216
Download
2
Embed Size (px)
Citation preview
Practice Standard for
EARNED VALUEMANAGEMENT
Project Management Institute
Global
Project Management Institute
Practice Standard forEarned Value Management
Practice Standard for Earned Value ManagementISBN: 1-930699-42-5
Published by: Project Management Institute, Inc.Four Campus BoulevardNewtown Square, Pennsylvania 19073-3299 USA.Phone: 610-356-4600 / Internet: www.pmi.org
Cover and interior design: Automated Graphic Systems, Inc.
©2005 Project Management Institute, Inc. All rights reserved.
‘‘PMI’’, the PMI logo, ‘‘PMP’’, the PMP logos, ‘‘PMBOK’’, ‘‘Project Management Journal’’, ‘‘PM Network’’, and PMI Today logo areregistered marks of Project Management Institute, Inc. For a comprehensive list of PMI marks, contact the PMI Legal Department.
PMI Publications welcomes corrections and comments on its books. Please feel free to send comments on typographical, formatting, orother errors. Simply make a copy of the relevant page of the book, mark the error, and send it to: Book Editor, PMI Publications, FourCampus Boulevard, Newtown Square, PA 19073-3299 USA, or e-mail: [email protected].
PMI books are available at special quantity discounts to use as premiums and sales promotions, or for use in corporate trainingprograms, as well as other educational programs. For more information, please write to Bookstore Administrator, PMI Publications, FourCampus Boulevard, Newtown Square, PA 19073-3299 USA, or e-mail: [email protected]. Or contact your local bookstore.
Printed in the United States of America. No part of this work may be reproduced or transmitted in any form or by any means, electronic,manual, photocopying, recording, or by any information storage and retrieval system, without prior written permission of the publisher.
The paper used in this book complies with the Permanent Paper Standard issued by the National Information Standards Organization(Z39.48–1984).
10 9 8 7 6 5 4 3 2 1
Contents
Preface ............................................................................................................................... viiChapter 1—Introduction ........................................................................................................1
1.1 The Role of Earned Value Management ................................................................11.2 EVM and the Project Management Process ..........................................................2
Chapter 2—Basic Elements of Earned Value Management ......................................................72.1 Descriptions of the Basic EVM Elements ..............................................................7
Planned Value ..............................................................................................7Earned Value ................................................................................................8Actual Cost ...................................................................................................8
2.2 Derivations of the Basic EVM Elements ................................................................9Planned Value ..............................................................................................9Earned Value Measurement Techniques .........................................................9Earned Value ..............................................................................................12Actual Cost .................................................................................................13
2.3 Putting it All Together ........................................................................................13Chapter 3—EVM Performance Analysis and Forecasting .......................................................15
3.1 Schedule Analysis and Forecasting (How are we doing timewise?) .......................17Schedule Variance (Are we ahead or behind schedule?) ................................17Schedule Performance Index (How efficiently are we using time?) ..................17Time Estimate at Completion (When are we likely to finish work?) ..................17
3.2 Cost Analysis and Forecasting (How are we doing costwise?) ..............................18Cost Variance (Are we under or over our budget?) .........................................18Cost Performance Index (How efficiently are we using our resources?) ...........19To-Complete Performance Index (How efficiently must we use our remaining
resources?) .............................................................................................19Estimate at Completion (What is the project likely to cost?) ..........................19Variance at Completion (Will we be under or over budget?) ............................19Estimate to Complete (What will the remaining work cost?) ...........................20
3.3 Management by Exception .................................................................................20Chapter 4—Guidance for the Use of Key EVM Practices .......................................................23
4.1 Establish a Performance Measurement Baseline ................................................23Decompose Work Scope to a Manageable Level ...........................................23Assign Unambiguous Management Responsibility .........................................24Develop Time-Phased Budget for Each Work Task .........................................24Select Earned Value Measurement Techniques for All Tasks .........................24Maintain Integrity of Performance Measurement Baseline throughout the
Project ....................................................................................................244.2 Measure and Analyze Performance Against the Baseline .....................................24
Record Resource Usage During Project Execution ..........................................24Objectively Measure the Physical Work Progress ...........................................25Credit Earned Value According to Earned Value Techniques ...........................25Analyze and Forecast Cost/Schedule Performance ........................................25Report Performance Problems and/or Take Action ........................................25
Appendix A—Guidelines for a Project Management Institute Practice Standard ....................27Appendix B—Evolution of PMI’s Practice Standard For EVM .................................................29
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA iii
iv ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Appendix C—Contributors and Reviewers of the Practice Standard for Earned ValueManagement ..................................................................................................33
C.1 Practice Standard for Earned Value Management Project Core Team ....................33C.2 Practice Standard for Earned Value Management Project Contributors .................34C.3 Practice Standard for Earned Value Management Project Team Members .............34C.4 Final Exposure Draft Reviewers and Contributors ................................................35C.5 PMI Project Management Standards Program Member Advisory Group .................36C.6 Production Staff ................................................................................................36
Appendix D—Additional Sources of Information ....................................................................37Publications ................................................................................................37Organizations ..............................................................................................38Education and Training ................................................................................38
Appendix E—Reviews of Selected Books on EVM .................................................................39Earned Value Project Management, Second Edition .......................................39Project Management Using Earned Value ......................................................41Fundamentals of Project Performance Measurement, Fourth Edition ...............42Project Management: The CommonSense Approach: Using Earned Value to
Balance the Triple Constraint ...................................................................44
..............................................................................................................................49GlossaryReferences ..........................................................................................................................47
Index by Keyword ................................................................................................................51
List of Figures
Figure 1-1: EVM and Project Management ...............................................................................2Figure 1-2: EVM and the Basic PM Process .............................................................................3Figure 1-3: Control Account Matrix ..........................................................................................3Box 1-1: Scaling EVM to Fit Varying Situations ........................................................................4Figure 1-4: Work Plan—Gantt (Bar) Chart ................................................................................5Figure 1-5: Performance Measurement Baseline (PMB) ............................................................5Figure 2-1: Cumulative Planned Value for Project EZ ................................................................8Figure 2-2: Cumulative Planned Value and Earned Value for Project EZ .....................................8Figure 2-3: Cumulative Planned Value, Earned Value and Actual Cost for Project EZ ..................9Figure 2-4: Work Plan for Project EZ ......................................................................................10Figure 2-5: Earned Value Measurement Techniques ...............................................................10Figure 2-6: Work Plan and Status for Project EZ (As of April 30) .............................................12Figure 2-7: Cumulative Planned Value, Earned Value, and Actual Cost for Project EZ
(As of April 30) ...................................................................................................14Figure 3-1: EVM Performance Measures ...............................................................................16Figure 3-2: EVM and Basic Project Management Questions ....................................................16Figure 3-3: Interpretations of Basic EVM Performance Measures ............................................16Box 3-1: Time-Based Schedule Measures—An Emerging EVM Practice ...................................18Box 3-2: Alternative Calculations of Estimate at Completion (EAC) ..........................................21Box 3-3: Performance Reporting ...........................................................................................22
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA v
Preface
The Practice Standard for Earned Value Management (EVM) has been developed as asupplement to A Guide to the Project Management Body of Knowledge (PMBOK� Guide).The Practice Standard for EVM is designed to provide readers who are familiar withthe PMBOK� Guide with a fundamental understanding of the principles of EVM andits role in facilitating effective project management.
The Practice Standard for EVM assumes that the reader has a basic working knowl-edge of Project Management Process Groups, Knowledge Areas, and other key conceptssuch as work breakdown structures (WBS) and critical path method (CPM) scheduling,as outlined in the PMBOK� Guide. If that is not the case, it is recommended that thereader undertake a review of the PMBOK� Guide before reading the Practice Standardfor EVM.
The Practice Standard for EVM is organized as follows:Introduction. A brief overview of EVM, highlighting the key management questionsEVM can help answer and exploring where EVM fits into the project manage-ment universe.
Basic Elements of Earned Value Management. This section discusses the threecornerstones of EVM: Planned Value (PV), Earned Value (EV), and Actual Cost(AC). It examines how these three data points are determined and how they relateto one another.
EVM Performance Analysis and Forecasting. This section describes variances, indi-ces, and forecasts that can be developed using Planned Value (PV), Earned Value(EV), and Actual Cost (AC). The chapter also examines how these variances, indices,and forecasts can be used to answer essential management questions.
Guidance for the Use of Key EVM Practices. This section outlines basic EVM prac-tices in their project management context and shows how EVM practices facilitateproject planning and control for better management of project cost and scheduleperformance.
Glossary. This section provides concise definitions of key terms used throughoutthis Practice Standard. Most of these terms also appear in the PMBOK� Guide—ThirdEdition’s glossary. Note, however, that many of the PMBOK� Guide’s definitions arebroader and more inclusive, since they apply beyond the scope of the PracticeStandard for Earned Value Management.
Appendices. These offer additional sources of EVM concepts and methods for furtherstudy and information related to the development of the Practice Standard.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA vii
Chapter 1
Introduction
1.1 THE ROLE OF EARNED VALUE MANAGEMENTFeedback is critical to the success of any project. Timely and targeted feedback canenable project managers to identify problems early and make adjustments that cankeep a project on time and on budget.
Earned Value Management (EVM) has proven itself to be one of the most effectiveperformance measurement and feedback tools for managing projects. It enables man-agers to close the loop in the plan-do-check-act management cycle.
EVM has been called ‘‘management with the lights on’’ because it can help clearlyand objectively illuminate where a project is and where it is going—as compared towhere it was supposed to be and where it was supposed to be going. EVM uses thefundamental principle that patterns and trends in the past can be good predictors ofthe future.
EVM provides organizations with the methodology needed to integrate the manage-ment of project scope, schedule, and cost. EVM can play a crucial role in answeringmanagement questions that are critical to the success of every project, such as:● Are we ahead of or behind schedule?● How efficiently are we using our time?● When is the project likely to be completed?● Are we currently under or over our budget?● How efficiently are we using our resources?● What is the remaining work likely to cost?● What is the entire project likely to cost?● How much will we be under or over budget at the end?
If the application of EVM to a project reveals that the project is behind scheduleor over budget, the project manager can use the EVM methodology to help identify:● Where problems are occurring● Whether the problems are critical or not● What it will take to get the project back on track.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 1
Chapter 1—Introduction
2 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
1.2 EVM AND THE PROJECT MANAGEMENT PROCESSThe effective use of EVM requires that it is used on projects where the principles ofgood project management, as outlined in A Guide to the Project Management Body ofKnowledge (PMBOK� Guide), are being applied. To establish a basic foundation forunderstanding EVM’s role in effective project management, it is important that weexamine the relationship between EVM and the PMBOK� Guide’s Project ManagementProcess Groups and Knowledge Areas.
Project management is primarily a matter of planning, executing, and controllingwork. Figure 1-1 indicates the areas of project management to which EVM is fundamen-tally most applicable.
Figure 1-1. EVM and Project Management
Project planning is mostly a matter of determining:● What work must be done (scope) and in what pieces (work breakdown structure)● Who is going to perform and manage the work (responsibility assignment matrix)● When the work is going to be done (schedule)● How much labor, materials, and related resources the work is going to require (cost).
Project execution is primarily a matter of doing the planned work and keepingworkers and managers informed.
Project control focuses mostly on monitoring and reporting the execution of projectmanagement plans related to scope, schedule, and cost, along with quality and risk.In other words, project control is a process for keeping work performance and resultswithin a tolerable range of the work plan.
As a performance management methodology, EVM adds some critical practices tothe project management process. These practices occur primarily in the areas of projectplanning and control, and are related to the goal of measuring, analyzing, forecasting,and reporting cost and schedule performance data for evaluation and action by work-ers, managers, and other key stakeholders. See Figure 1-2.
Chapter 1—Introduction
Figure 1-2. EVM and the Basic PM Process
During the project planning process, EVM requires the establishment of a perfor-mance measurement baseline (PMB). This requirement amplifies the importance ofproject planning principles, especially those related to scope, schedule, and cost. EVMelevates the need for project work to be executable and manageable, and for theworkers and managers to be held responsible and accountable for the project’s perfor-mance.
Project work needs to be broken down—using a work breakdown structure—intoexecutable tasks and manageable elements often called control accounts. Either anindividual or a team needs to manage each of the work elements. All of the workneeds to be assigned to the workforce for execution using an organization breakdownstructure (OBS). See Figure 1-3 and Box 1-1.
Figure 1-3. Control Account Matrix
Project work needs to be logically scheduled and resourced in a work plan; thework scope, schedule, and cost need to be integrated and recorded in a time-phasedbudget known as a performance measurement baseline (PMB). Figure 1-4 illustratesa hypothetical work plan with a Gantt (bar) chart, to which earned value measurement
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 3
Chapter 1—Introduction
4 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
techniques (described in Chapter 2) have been added. Figure 1-5 displays the PMBfor the hypothetical work plan (also described in Chapter 2).
In the planning process, the means for assessing physical work progress and assign-ing budgetary earned value also needs to be established. In addition to routine projectmanagement planning, earned value measurement techniques are selected andapplied for each work task, based on scope, schedule, and cost considerations.
In the project execution process, EVM requires the recording of resource utilization(i.e., labor, materials, and the like) for the work performed within each of the workelements included in the project management plan. In other words, actual costs needto be captured in such a way that permits their comparison with the performancemeasurement baseline.
Chapter 1—Introduction
Figure 1-4. Work Plan—Gantt (Bar) Chart
Figure 1-5. Performance Measurement Baseline (PMB)
In the project control process, EVM requires that physical work progress be assessedand budgetary earned value be credited (using the selected earned value measurementtechniques), as prescribed in the project management plan. With this earned valuedata, the planned value data from the performance measurement baseline, and theactual cost data from the project cost tracking system, the project team can performEVM analysis at the control account and other levels of the project work breakdownstructure, and report the EVM results as needed.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 5
Chapter 1—Introduction
6 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
In summary, EVM strategically augments good project management to facilitatethe planning and control of cost and schedule performance. The key practices ofEVM include:● Establish a performance measurement baseline (PMB)
� Decompose work scope to a manageable level� Assign unambiguous management responsibility� Develop a time-phased budget for each work task� Select EV measurement techniques for all tasks� Maintain integrity of PMB throughout the project.
● Measure and analyze performance against the baseline� Record resource usage during project execution� Objectively measure the physical work progress� Credit EV according to EV techniques� Analyze and forecast cost/schedule performance� Report performance problems and/or take action.
Chapter 2 provides a detailed explanation of the three basic elements of EVM:Planned Value, Earned Value, and Actual Cost.
Chapter 2
Basic Elements of EarnedValue Management
As indicated in Chapter 1, Earned Value Management (EVM) relies on three keydata points:● Planned Value● Earned Value● Actual Cost
This chapter describes each of these data points and discusses how they are derived.Throughout this chapter and the next, Project EZ is presented as an example tohelp explain these data points and other essential elements of EVM. Project EZ is ahypothetical project that could represent any type of project: for example, the buildingof a house, development of a new software program, or production of an airplane.The fundamentals of EVM are the same, regardless of the type or size of project towhich they are being applied.
2.1 DESCRIPTIONS OF THE BASIC EVM ELEMENTS
Planned ValuePlanned Value (PV) describes how far along project work is supposed to be at anygiven point in the project schedule. It is a numeric reflection of the budgeted workthat is scheduled to be performed, and it is the established baseline (also known asthe performance measurement baseline, or PMB) against which the actual progressof the project is measured. Once established, this baseline may only change to reflectcost and schedule changes necessitated by changes in the scope of work. Also knownas the Budgeted Cost of Work Scheduled (BCWS), Planned Value is usually chartedshowing the cumulative resources budgeted across the project schedule. Figure 2-1shows the Planned Value S-Curve for Project EZ.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 7
Chapter 2—Basic Elements of Earned Value Management
8 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Figure 2-1. Cumulative Planned Value for Project EZ
Earned ValueEarned Value (EV) is a snapshot of work progress at a given point in time. Also knownas the Budgeted Cost of Work Performed (BCWP), it reflects the amount of work thathas actually been accomplished to date (or in a given time period), expressed as theplanned value for that work. Figure 2-2 shows the Earned Value for Project EZ at thefour-month mark, and indicates that less work than planned has been accomplished.
Figure 2-2. Cumulative Planned Value and Earned Value for Project EZ
Actual CostActual Cost (AC), also known as the Actual Cost of Work Performed (ACWP), is anindication of the level of resources that have been expended to achieve the actualwork performed to date (or in a given time period). Figure 2-3 shows the Actual Costfor Project EZ at the four-month mark, and indicates that the organization has spentless than it planned to spend to achieve the work performed to date.
Chapter 2—Basic Elements of Earned Value Management
Figure 2-3. Cumulative Planned Value, Earned Value and Actual Cost for Project EZ
2.2 DERIVATIONS OF THE BASIC EVM ELEMENTS
Planned ValueThe work plan for Project EZ, shown in Figure 2-4 is the basis for the Planned Valueand the performance measurement baseline for the project (see Figure 2-1). This workplan establishes a time-phased budget for each task in the project. For example, Task2 has a budget of 48 resource units, which are phased over a four-month period. Theplan for Task 2 calls for varying increments of Planned Value to be earned in eachmonth of the task. As the planned work is accomplished, its budgeted cost becomesEarned Value.
Tasks may be planned and measured in whatever resource units are most suitableto the work, including labor hours, material quantities, and the monetary equivalent ofthese resources. As discussed in the next section, however, performance managementworks best when the physical progress of work is objectively planned and measured.The techniques used in EVM to achieve this goal are Earned Value measurementtechniques (sometimes called earning and crediting methods).
Earned Value Measurement Techniques
Earned Value is a measure of work performed. Techniques for measuring work per-formed are selected during project planning and are the basis for performance mea-surement during project execution and control. Earned Value (EV) techniques shouldbe selected based on key attributes of the work, primarily 1) the duration of the effortand 2) the tangibility of its product.
The performance of separate and distinct work effort that is related to the completionof specific and tangible end products or services, and which can be directly plannedand measured, is called discrete effort. In comparison, effort applied to project workthat is not readily divisible into discrete efforts for that work, but which is related indirect proportion to measurable discrete work efforts, is called apportioned effort,and support-type activity that does not produce definitive end products is referredto as level of effort.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 9
Chapter 2—Basic Elements of Earned Value Management
10 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Figure 2-4. Work Plan for Project EZ
Work performance is measured periodically, such as weekly or monthly. The EVtechnique selected for measuring the performance of discrete effort will depend onits duration and the number of measurement periods it spans. Discrete efforts thatspan one to two periods are often measured with fixed formula techniques, where afixed percentage of work performance is credited at the start of the work and theremaining percentage is credited at the completion of the work. Discrete efforts oflonger duration (greater than two periods) are measured with other techniques, includ-ing those known as weighted milestone and percent complete.
The above guidelines for selecting EV measurement techniques are outlined inFigure 2-5, and some of the most common techniques are described in the paragraphsthat follow.
Figure 2-5. Earned Value Measurement Techniques
Chapter 2—Basic Elements of Earned Value Management
Fixed Formula
A typical example of fixed formula is the 50/50 technique. With this method, 50percent of the work is credited as complete for the measurement period in which thework begins, regardless of how much work has actually been accomplished. Theremaining 50 percent is credited when the work is completed. Other variations of thefixed formula method include 25/75 and 0/100. Fixed formula techniques are mosteffectively used on small, short-duration tasks.
In Figure 2-4, the 50/50 technique has been selected to determine Earned Valuefor Tasks 1 and 6 of Project EZ. The 25/75 technique has been selected to determineEarned Value for Task 3 of Project EZ, and 0/100 has been selected for Task 4.
Weighted Milestone
The weighted milestone technique divides the work to be completed into segments,each ending with an observable milestone; it then assigns a value to the achievementof each milestone. The weighted milestone technique is more suitable for longerduration tasks having intermediate, tangible outcomes. In Figure 2-4, the weightedmilestone technique has been used for Tasks 2 and 5 of Project EZ.
Percent Complete
The percent complete technique is among the simplest and easiest, but can be themost subjective of the Earned Value measurement techniques if there are no objectiveindicators to back it up. This is the case when, at each measurement period, theresponsible worker or manager makes an estimate of the percentage of the workcomplete. These estimates are usually for the cumulative progress made against theplan for each task. However, if there are objective indicators that can be used to arriveat the percent complete (for example, number of units of product completed dividedby the total number of units to be completed), then this can be a more useful technique.
Apportioned Effort
If a task has a direct, supportive relationship to another task that has its own EarnedValue, the value for the support task may be determined based on (or apportionedto) the Earned Value of the reference base activity. Examples of proportional tasksinclude quality assurance and inspection activities.
For instance, in Figure 2-4, Task 2 of Project EZ might have a quality assurancefunction associated with it. Using the apportioned effort technique, the project man-ager might determine that the Planned Value for the quality assurance task is 10percent of the value of the main task. The total apportioned Planned Value for thequality assurance effort related to Task 2, therefore, would be 4.8 or 10 percent of 48(which is the Planned Value for Task 2). Earned Value for each measurement periodwould be assigned for the quality assurance component in direct proportion to theEarned Value assigned for Task 2.
Level of Effort
Some project activities do not produce tangible outcomes that can be measuredobjectively. Examples include project management and operating a project technicallibrary. These activities consume project resources and should be included in EVMplanning and measurement. In these cases, the level of effort (LOE) technique is used
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 11
Chapter 2—Basic Elements of Earned Value Management
12 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
for determining Earned Value. A Planned Value is assigned to each LOE task for eachmeasurement period. This Planned Value is automatically credited as the Earned Valueat the end of the measurement period.
LOE should be used only when the task does not lend itself to a technique thatactually measures physical work progress. LOE tasks have no schedule variance andbias the project data toward an on-schedule condition. They also can reflect misleadingcost variances if they are not executed with the human resources on whom the costestimates and planned values in the performance measurement baseline are based.
Earned ValueWhile value is planned and measured using the Earned Value techniques outlinedabove, value is earned by accomplishing the planned work. Earned Value is creditedwhen progress is demonstrated in accordance with the Earned Value techniqueselected for the planned work. For discrete work, observable evidence of a tangibleproduct or progress is required.
The status of Project EZ after four months is presented in Figure 2-6. This progressreport indicates that all of the work planned for Task 1 has been accomplished. Thisdiscrete work was planned and measured using the 50/50 EV technique. The workwas credited with an Earned Value of 6 by demonstrating physical and objective
Figure 2-6. Work Plan and Status for Project EZ (As of April 30)
Chapter 2—Basic Elements of Earned Value Management
evidence that the task began in January, and it earned the remaining value of 6 inFebruary by demonstrating completion of the work in the same manner.
Task 2 of Project EZ is discrete work that was planned and measured using theweighted or valued milestone measurement technique. The progress report in Figure2-6 shows that some of the work planned for completion by the end of April has notbeen accomplished. Two of the three scheduled milestones for Task 2 (those in Febru-ary through April) have been reached, but the third milestone has not, and the PlannedValue for that intermediate product has not been credited. To receive the Earned Valuefor the first two milestones required observable evidence of those tangible outcomes.
Actual CostTo determine Actual Cost, an organization needs to have in place a system for trackingcosts over time and by project component. The sophistication and complexity of thissystem will vary by organization and project, but, at a minimum, some type of costtracking system must be in place that can tie costs to the plan and to the way EarnedValue is credited.
The status of Project EZ in Figure 2-6 shows that, although no Earned Value wascredited for Task 2 in April, some costs were reflected for that month, which put thetask and the project over budget at the end of April, as the Actual Cost exceeded theEarned Value (see also Figure 2-3).
2.3 PUTTING IT ALL TOGETHEROnce Planned Value, Earned Value, and Actual Cost have been determined, a managercan use these data points to analyze where a project is and forecast where it is headed.Chapter 3 looks at EVM analysis and forecasting techniques using the Planned Value,Earned Value, and Actual Cost for Project EZ after four months, as shown in Figure2-7.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 13
Chapter 2—Basic Elements of Earned Value Management
14 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Figure 2-7. Cumulative Planned Value, Earned Value, and Actual Cost for Project EZ(As of April 30)
Chapter 3
EVM Performance Analysisand Forecasting
Chapter 2 introduced the three cornerstones of Earned Value Management (EVM):● Planned Value● Earned Value● Actual Cost
This chapter examines how the data points of Planned Value (PV), Earned Value(EV), and Actual Cost (AC) can be used to analyze the current status of a project andforecast its likely future. EVM looks at project performance for the current period andat cumulative performance to date. EVM is described and illustrated here in terms ofcumulative data, using the Project EZ data displayed in Figure 2-7.
This chapter introduces a fourth data point, Budget at Completion (BAC), whichis the final data point on the performance measurement baseline (PMB). Budget atCompletion represents the total Planned Value for the project. For Project EZ, theBAC is 150.
In this chapter, we will examine:● Variances: Schedule Variance (SV); Cost Variance (CV); and Variance at Comple-
tion (VAC)● Indices: Schedule Performance Index (SPI); Cost Performance Index (CPI); and To-
Complete Performance Index (TCPI)● Forecasts: Time Estimate at Completion (EACt); Estimate at Completion (EAC); and
Estimate to Complete (ETC)
Figure 3-1 shows the relationships among the basic EVM performance measures.These variances, indices, and forecasts can be used to answer the key project
management questions raised in Chapter 1. Figure 3-2 shows the relationship betweenthose project management questions and the EVM performance measures.
Figure 3-3 shows what EVM performance measures indicate about a project inregard to its planned work schedule and resource budget.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 15
Chapter 3—EVM Performance Analysis and Forecasting
16 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Figure 3-1. EVM Performance Measures
Figure 3-2. EVM and Basic Project Management Questions
Figure 3-3. Interpretations of Basic EVM Performance Measures
Chapter 3—EVM Performance Analysis and Forecasting
3.1 SCHEDULE ANALYSIS AND FORECASTING(How are we doing timewise?)
Schedule Variance (Are we ahead or behind schedule?)The Schedule Variance (SV) determines whether a project is ahead of or behindschedule. It is calculated by subtracting the Planned Value (PV) from the EarnedValue (EV). A positive value indicates a favorable condition and a negative valueindicates an unfavorable condition. For Project EZ:
SV � EV � PV � 32 � 48 � �16 {unfavorable}
The Schedule Variance can be expressed as a percentage by dividing the ScheduleVariance (SV) by the Planned Value (PV):
SV% � SV / PV � �16 / 48 � �33% {unfavorable}
In other words, the project is 33 percent behind schedule, meaning that 33 percentof the planned work has not been accomplished (see Box 3-1).
Schedule Performance Index (How efficiently are we using time?)The Schedule Performance Index (SPI) indicates how efficiently the project team isusing its time. SPI is calculated by dividing the Earned Value (EV) by the PlannedValue (PV). For Project EZ:
SPI � EV / PV � 32 / 48 � 0.67 {unfavorable}
This Schedule Performance Index indicates that—on average—for each 8-hour dayworked on the project, only 5 hours and 20 minutes worth of the planned work isbeing performed; that is, work is being accomplished at 67 percent efficiency.
Time Estimate at Completion (When are we likely to finish work?)Using the Schedule Performance Index (SPI) and the average Planned Value (PV)per unit of time, the project team can generate a rough estimate of when the projectwill be completed, if current trends continue, compared to when it was originallysupposed to be completed (see Box 3-1). For Project EZ:
EACt � (BAC/SPI)/(BAC/months) � (150/0.6667)/(150/12) � 18 months
The originally estimated completion time for the project was 12 months, so theproject manager now knows that if work continues at the current rate the project willtake six months longer than originally planned. It is important to note that this methodgenerates a fairly rough estimate and must always be compared with the status reflectedby a time-based schedule method such as critical path method. It is possible that anearned value analysis could show no schedule variance and yet the project is stillbehind schedule; for example, when tasks that are planned to be completed in thefuture are performed ahead of tasks on the critical path.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 17
Chapter 3—EVM Performance Analysis and Forecasting
18 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
3.2 COST ANALYSIS AND FORECASTING (How are we doing costwise?)
Cost Variance (Are we under or over our budget?)A project’s Cost Variance (CV) shows whether a project is under or over budget. Thismeasure is determined by subtracting the Actual Cost (AC) from the Earned Value(EV). The CV for the Project EZ example shows:
CV � EV � AC � 32 � 40 � �8 {unfavorable}
This number can be expressed as a percentage by dividing the Cost Variance (CV)by the Earned Value (EV).
CV% � CV / EV � �8 / 32 � �25% {unfavorable}
In other words, to date, the project is 25 percent over budget for the work performed.
Chapter 3—EVM Performance Analysis and Forecasting
Cost Performance Index (How efficiently are we using our resources?)Earned Value and Actual Cost can also be used to calculate the cumulative CostPerformance Index (CPI), which is one of the clearest indicators of the cumulativecost efficiency of a project. CPI gauges how efficiently the team is using its resources.It is determined by dividing the Earned Value (EV) by the Actual Cost (AC). In regardsto Project EZ, the CPI is:
CPI � EV / AC � 32 / 40 � 0.80 � 0.80 {unfavorable}
Translated into dollars, this means that Project EZ has a cost efficiency that providesUS $0.80 worth of work for every project dollar spent to date.
To-Complete Performance Index (How efficiently must we use our remainingresources?)Another very useful index is the To-Complete Performance Index (TCPI), which helpsthe team determine the efficiency that must be achieved on the remaining work fora project to meet a specified endpoint, such as the Budget at Completion (BAC) orthe team’s revised Estimate at Completion (EAC) (see the following discussions ofEAC and ETC). The TCPI for achieving the BAC is calculated by dividing the workremaining by the budget remaining as follows:
TCPI � (BAC � EV) / (BAC � AC) � (150 � 32) / (150 � 40) � 1.07
This means that for Project EZ to achieve the BAC, performance must improve froma CPI of 0.80 to a TCPI of 1.07 for performance of the remaining work.
Estimate at Completion (What is the project likely to cost?)The calculated Estimate at Completion (EAC) projects for the team the final cost ofthe project if current performance trends continue. One common method for calculat-ing the EAC is to divide the Budget at Completion (BAC) by the cumulative CostPerformance Index (CPI). For Project EZ, this is:
EAC � BAC / CPI � 150 / 0.80 � 187.50
This forecasting formula assumes that the cumulative performance reflected in theCPI is likely to continue for the duration of the project. Other formulas used to forecastcost at completion with earned value data are outlined in Box 3-2. Estimates basedon project team and management analysis of remaining work are discussed in thefollowing section on Estimate to Complete (ETC).
Variance at Completion (Will we be under or over budget?)With the EAC figure in hand, the manager can now compute the cost Variance atCompletion (VAC), which shows the team whether the project will finish under orover budget, by subtracting the EAC from the BAC. For Project EZ, this is:
VAC � BAC � EAC � 150 � 187.50 � �37.50
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 19
Chapter 3—EVM Performance Analysis and Forecasting
20 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
In other words, if current trends continue, the project will cost an additional 37.50units worth of resources than originally planned. This can be expressed as a percentageby dividing VAC by BAC.
VAC% � VAC / BAC � �37.50 / 150 � �25%
Estimate to Complete (What will the remaining work cost?)There are two ways to develop the Estimate to Complete (ETC), which shows what
the remaining work will cost. One way is a management ETC developed by workersand/or managers based on an analysis of the remaining work. The management ETCcan be added to the Actual Cost (AC) to derive the management Estimate at Comple-tion (EAC) of the total cost of the project at completion.
EAC � AC � ETC � 40 ? � ?
As a check on these management estimates, organizations can use a calculated ETCbased on the efficiency-to-date measured by the CPI. The calculated ETC can beused to determine the calculated Estimate at Completion (EAC), which the team cancompare with the management EAC. For Project EZ, the ETC and EAC are calculatedas follows:
ETC � (BAC � EV) / CPI � (150 � 32) / 0.80 � 147.50
EAC � AC � ETC � 40 147.50 � 187.50
Note that this EAC formula is equivalent to the following (see Box 3-2):
EAC � AC � [(BAC � EV) / CPI] � BAC / CPI
3.3 MANAGEMENT BY EXCEPTIONEVM provides an organization with the capability of practicing ‘‘management-by-exception’’ on its projects. This practice contributes greatly to the efficiency andeffectiveness of project management, by allowing managers and others to focus onproject execution and invoke control actions only when and where they are needed.EVM performance measures, used in conjunction with the project work breakdownstructure (WBS), provide the objective data needed to practice ‘‘management-by-exception.’’
Using EVM, an organization can establish acceptable levels of performance for aproject and its work tasks. Variance percentages and efficiency indices are most oftenused. For instance, an organization may consider a Cost Variance (CV) of plus orminus 10 percent to be an acceptable range of variance from the project managementplan. In this case, no management action would be taken except when and where aCV falls outside of this acceptable range. While a negative variance is potentiallyproblematic, a positive variance may represent an opportunity.
Because EVM occurs first at the task level, where the scope, schedule, and cost ofwork are planned and controlled, ‘‘management-by-exception’’ also starts at this level.Managers use EVM performance measures to determine whether action thresholdshave been reached for their tasks and control accounts. And with the use of a work
Chapter 3—EVM Performance Analysis and Forecasting
breakdown structure, which ties the tasks and control accounts of a project together,EVM and ‘‘management-by-exception’’ can be used at any level of the project (speci-fied in the WBS).
While variance and efficiency thresholds are commonly used in EVM, trends in theperformance measures for a project can help a project manager decipher or anticipatea potential performance problem. For instance, a cumulative Cost Performance Index(CPI) that is within an acceptable range, but has been trending down toward theefficiency threshold for several measurement periods, may be cause for some concernand prompt an examination of the underlying cause of the trend. If the trend is seenat the project level, a WBS will enable the manager to ’’drill down’’ to lower levels tosee what underlies the trend.
Graphs of variance and efficiency data are helpful tools in performing this kind ofEarned Value analysis. Plotting the CV percentage or the CPI over time, for example,will indicate their values and show their trends. Computer software, especially some
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 21
Chapter 3—EVM Performance Analysis and Forecasting
22 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
developed specifically for project management and EVM, is capable of producingsuch graphs. Box 3-3 outlines other basic kinds of performance management andreporting displays that are frequently used in EVM. Appendix E provides additionalsources of information on EVM concepts, methods, and practices.
Chapter 4
Guidance for the Use of KeyEVM Practices
Earned Value Management (EVM) strategically augments good project managementwith key practices that facilitate the planning and control of cost and schedule perfor-mance. This chapter outlines guiding principles for using these key EVM practices,which were introduced in Chapter 1. The following outline shows the interdependenceof the fundamental practices of EVM and project management.● Establish a performance measurement baseline (PMB)
� Decompose work scope to a manageable level� Assign unambiguous management responsibility� Develop a time-phased budget for each work task� Select EV measurement techniques for all tasks� Maintain integrity of PMB throughout the project.
● Measure and analyze performance against the baseline� Record resource usage during project execution� Objectively measure the physical work progress� Credit earned value according to EV techniques� Analyze and forecast cost/schedule performance� Report performance problems and/or take action.
4.1 ESTABLISH A PERFORMANCE MEASUREMENT BASELINE
Decompose Work Scope to a Manageable LevelAll project work must be executed, and effective and efficient execution requiresplanning and control. Most work scopes are broken down for optimal planning, execu-tion, and control. EVM requires that scope, schedule, and resources (i.e., cost) bemanaged as integrated parts of project work. This integration occurs at the task oractivity level where physical work is performed. Work scope (tasks or activities) towhich EVM is applied is grouped into control accounts for integrated management.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 23
Chapter 4—Guidance for the Use of Key EVM Practices
24 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Assign Unambiguous Management ResponsibilityAll project work must be managed; its execution must be planned and controlled.Integrated management of work scope, schedule, and cost requires that a single indi-vidual or product delivery team be held responsible and accountable for the workgrouped in each control account. An individual or team can be responsible for morethan one control account, but each control account must be managed by only onecontrol account manager or team.
Develop Time-Phased Budget for Each Work TaskThe full scope of work for each task or activity must be scheduled and resourced. Thisresults in a time-phased budget, which integrates the scope, schedule, and cost forthe work (task or activity). In EVM, these time-phased budgets are the Planned Value(PV) for the work, and represent its performance measurement baseline (PMB). Thevertical integration of a work breakdown structure (WBS) facilitates aggregation ofthese time-phased budgets to higher levels including the control account, the project,and levels in between.
Select Earned Value Measurement Techniques for All TasksIn EVM, the progress of all work must be measured. Measuring the amount of workscope completed is planned at the task level in conjunction with the performancemeasurement baseline. An EV technique is selected for each task based on the temporaland physical qualities of the work. Objective measurement of physical progress ontasks with tangible outcomes is superior to all other measurements. Subjective assess-ments of progress are considered inferior. Tasks that can be completed in one progress-reporting period require only one measurement and are preferred. Tasks that spanseveral reporting periods should be measured objectively with milestones representingintermediate, tangible outcomes.
Maintain Integrity of Performance Measurement Baseline throughout theProjectThe four key practices above are interdependent and should be undertaken in concertto establish a realistic and durable performance measurement baseline. Once thebaseline is established, its integrity as an integrated measurement tool—relating scope,schedule, and cost—should be strictly maintained. There are two basic reasons tochange the performance measurement baseline: 1) If the work scope is changed, thenthe estimated cost and possibly the schedule will change, and all of these changesneed to be reflected in a revised baseline. 2) If poor performance in the past is renderingthe baseline worthless as a tool for measuring present performance, then a revisedbaseline may be justified.
4.2 MEASURE AND ANALYZE PERFORMANCE AGAINST THE BASELINE
Record Resource Usage During Project ExecutionIn EVM, the costs associated with the performance of work scope must be recordedon a regular basis. Costs should be measured at the level at which work scope, schedule,
Chapter 4—Guidance for the Use of Key EVM Practices
and cost are integrated in the time-phased budgets of the performance measurementbaseline. The lower the level of cost measurement, the higher the level of rigor atwhich cost performance can be managed. If resource usage can be recorded only ata higher level of work scope, the vertical integration afforded by the project workbreakdown structure will facilitate cost performance management at that higher level.While monetary costs are the common denominator for resources used on mostprojects (and are therefore preferred), some projects—and some tasks within a proj-ect—may find the use of labor hours or material quantities to be adequate or prefer-able.
Objectively Measure the Physical Work ProgressEVM strives to objectively measure the physical progress of work. The more thistechnique achieves this goal, the better it performs its role of performance managementand the more it contributes to effective project management. Projects vary a lot inregard to the physical qualities of their work. For example, most construction projectsconsist largely of tangible products, which can be readily and directly measured. Manyresearch projects, however, yield only intangible outcomes until their final productemerges at the end. Although objective measures of physical progress are vastly pre-ferred, some measure of work scope accomplishment, including a subjective assess-ment of progress, is better than none at all.
Credit Earned Value According to Earned Value TechniquesPhysical work progress on tasks is credited in terms of predetermined techniques thatare selected during project planning and are included in the performance measure-ment plans for the tasks. Adherence to the measurement plans during project executionassures that assessments of work progress yield earned values that can be comparedwith the planned values and the actual costs for the task. It also assures that earnedvalues are credited in the same measurement units used to establish planned valuesand record actual costs (labor hours, material quantities, or their monetary value).
Analyze and Forecast Cost/Schedule PerformanceCost and schedule performance should be measured and analyzed as feasible withregularity and intensity consistent with project management need including the magni-tude of performance risk. Analysis should be progressive and should follow the princi-ple of management by exception. Variance thresholds should be established in theplanning phase and should be used to guide the examination of performance. Taskswhose performance falls within the prescribed tolerance range should not requireadditional scrutiny. However, when performance data at higher levels of the workbreakdown structure are reviewed, caution should be exercised because compensatinggood performance can mask poor performance at lower levels. The function of EVMforecasts is to compare their objective values with management estimates offered byproject delivery team members.
Report Performance Problems and/or Take ActionThe goal of EVM is better cost and schedule performance in the accomplishment ofwork scope. But performance is not simply a function of execution; it depends also onthe quality of planning and control. EVM data do not reveal the causes of performance.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 25
Chapter 4—Guidance for the Use of Key EVM Practices
26 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Project managers and others must decide where the problems lie and what actionsto take or recommend. Poor execution may call for recovery, while poor planning maycall for replanning. It is critical that EVM provide the best possible feedback to thosewho must make the decisions and take the actions. Simple metrics alone may not beenough, especially if decisions and actions appear to be warranted. Patterns and trendsin periodic and cumulative data should be displayed in tables and graphs for review,and explanations and interpretations should be provided by the managers having thatinformation and insight.
Appendix A
Guidelines for a ProjectManagement InstitutePractice Standard
● Each practice standard provides guidelines on the mechanics (e.g., basics, funda-mentals, step-by-step usage guide, how it operates) of some significant process(inputs, tools and techniques, or outputs) that is relevant to a project manager.
● A practice standard does not necessarily mirror the life-cycle phases of many proj-ects. However, an individual practice standard may be applicable to the completionof one or more phases within a project.
● A practice standard does not necessarily mirror the Knowledge Areas within AGuide to the Project Management Body of Knowledge (PMBOK� Guide), althoughan individual practice standard will provide sufficient detail and background forone or more of the inputs, tools and techniques, and/or outputs. Therefore, practicestandards are not required to use the name of any Knowledge Area.
● Each practice standard should include information on what the significant processis and does, why it is significant, when it should be performed and, if necessaryfor further clarification, who should perform it.
● Each practice standard should include information that is accepted and applicablefor most projects most of the time within the project management community.Processes that are generally restricted or applicable to one industry, country, orcompanion profession (i.e., an application area) may be included as an appendixfor informational purpose, rather than as part of the practice standard. With strongsupport and evidence, an application area-specific process may be considered asan extension of a practice standard, in the same manner as extensions to the PMBOK�
Guide are considered.● Each practice standard will benefit from the inclusion of examples and templates
in the appendices. It is best when such examples or templates include a discussionof their strengths and weaknesses. To put such a discussion in its appropriatecontext, the standard may include a background discussion. The examples andtemplates featured should be aligned with the relevant information that appearsin the standard or other appendices.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 27
Appendix A—Guidelines for a Project Management Institute Practice Standard
28 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
● All practice standards will be written in the same general style and format, inaccordance with PMI’s preferred style manual.
● Each practice standard project will assess the need to align with or reference otherpractice standards.
● Each practice standard will be consistent with the current edition of thePMBOK� Guide.
● Each practice standard is intended to be more prescriptive than the current editionof the PMBOK� Guide.
Appendix B
Evolution of PMI’s PracticeStandard For EVM
Recognizing the need for global guidance on Earned Value Management beyond thatincluded in A Guide to the Project Management Body of Knowledge (PMBOK� Guide),the Project Management Institute (PMI) initiated its second practice standard projectin 2001 and invited the PMI College of Performance Management (PMI-CPM) toassume a leadership role. PMI-CPM accepted the invitation and agreed to contributeboth knowledge and financial resources to help make the project a success. It wasagreed that the PMI-CPM Vice President of Professional Development, Dr. John Singley,PMP, would serve as Project Manager of PMI’s Practice Standard for Earned ValueManagement.
During the first year of the project, a project charter was developed, team memberswere recruited, and a preliminary draft of the Practice Standard For Earned ValueManagement was prepared. The project team was comprised of about 30 PMI members,most of whom were PMI-CPM members. During that year, the team held severalmeetings and working sessions, and by the end of the first six months, the team haddeveloped an outline of the Practice Standard. Small writing teams were formed andgiven the charge of preparing the first draft. By the end of the year, a preliminarydraft of the Practice Standard was distributed to the whole team for review. A teammeeting was held to gather and discuss recommendations.
Although the outline for the Practice Standard aligned it with the PMBOK� Guideand focused its content on those essentials of Earned Value that contribute to goodproject management, it was the opinion of most team members reviewing the prelimi-nary draft that it went beyond the guidance provided by the outline and lacked thedesired focus on essentials. The President of PMI-CPM, Mr. Wayne Abba, agreeingwith the team’s assessment of the preliminary draft, presented a compelling recom-mendation to return to the intent of the outline and align the Practice Standard withthe PMBOK� Guide. The assembled team members agreed with this objective, butexpressed varying opinions about the ways to achieve Mr. Abba’s recommendation.
The Project Manager decided on a course of action: The two writing teams wereasked to finish any remaining work on their drafts (without making any major revi-sions), and submit them to the Project Manager for editing. With the help of anindependent, professional editor, the project team attempted—during the summerand fall of 2002—to reshape and revise the preliminary draft of the Practice Standard.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 29
Appendix B—Evolution of PMI’s Practice Standard For EVM
30 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
The results of this effort were not satisfactory; the edited Practice Standard appearedto mimic the structure and content of the PMBOK� Guide. It became apparent thata different approach was required.
At about this same time, the Practice Standard project team began to grow signifi-cantly, adding many new members who wanted to contribute to the development ofthe Practice Standard. (By February 2003, the end of the second year of the project,the team had grown to about 80 members; during the course of the project’s thirdyear, team membership peaked at about 145 individuals.) On the recommendation ofthe PMI Standards Program Manager, Mr. Steve Fahrenkrog, the Project Manager ofthe Practice Standard prepared an article for the March 2003 issue of PMI Today. Thisarticle reaffirmed PMI’s vision for the Practice Standard and renewed the projectteam’s commitment to realizing this vision.
To meet the challenge of writing a standard containing universal guidance for aglobal community of project management practitioners, a new and different approachwas adopted: the Project Manager hired a ghost writer to prepare a series of draftsthat the more than 100 members on the project team would each review. Capitalizingon the expert knowledge captured in the earlier drafts of the Practice Standard, thewriter composed a rough draft and distributed it—in June 2003—to the project teamfor review. Comments and recommendations were collected from the project team’smembers. The writer revised the draft Practice Standard to reflect accepted recommen-dations; the Project Manager distributed this revised draft—in August 2003—to theproject team for review. This process was repeated four times. The third draft, com-pleted in October 2003, was submitted to the PMI Standards Program Team.
The third draft of the Practice Standard was revised by the writer to incorporaterecommendations of the PMI Standards Program Team, as well as recommendationsfrom the Practice Standard Project Team (which, as noted earlier, had expanded toinclude about 145 members). Throughout the entire review-revise process, a concertedeffort was made to stand by the vision for the Practice Standard and to focus onproviding universal guidance for a global audience. In early January 2004, the ProjectManager submitted to PMI for publication as an exposure draft, a fourth, 30-page-long draft of the new Practice Standard. In February 2004, PMI posted the new draftPractice Standard on its Web site for a 60-day period of review by the project manage-ment community. PMI invited reviewers to submit their recommendations.
The exposure process, which included special invitations to independent EarnedValue Management experts (who had not participated in the Practice Standard project),yielded 280 recommendations. Four small project teams were formed to help with theprocess of adjudicating the recommendations. During the summer and fall of 2004,the Standard’s Project Manager and writer used accepted recommendations to revisethe exposure draft into the final draft of the Practice Standard. In October 2004, theProject Manager submitted the final draft to PMI for publication.
From the beginning of the project to its end, PMI has recognized its challenge ofdeveloping the Practice Standard for Earned Value Management to provide projectmanagement practitioners with a better focus on the essentials of Earned Value Man-agement that apply to most projects most of the time. The best-known practice ofEarned Value Management matured over a period of 30 years in the United Statesand allied countries through its application on large defense systems contracts. Mostof the literature on Earned Value Management and most of its professionally activecommunity is grounded in that experience. Guidance for the practice of Earned ValueManagement, written and followed by that community, is comprehensive projectmanagement guidance with Earned Value seamlessly incorporated. PMI’s challenge
Appendix B—Evolution of PMI’s Practice Standard For EVM
in writing this Practice Standard has been to transcend that experience, extract theessence of Earned Value, and align it with the PMBOK� Guide, so that it applies tomost projects most of the time. PMI believes that it has been successful, and it hopesthat you agree.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 31
Appendix C
Contributors and Reviewers ofthe Practice Standard for EarnedValue Management
C.1 PRACTICE STANDARD FOR EARNED VALUE MANAGEMENTPROJECT CORE TEAMThe following individuals served as members and were contributors of text or concepts,and as Co-Leaders within the Project Core Team (PCT):John Singley, PhD, PMP, Project ManagerWayne F. AbbaHenry F. GarciaJames J. GasbarroMichael Hatfield, PMPEleanor HauptJames T. HeiresGeorge H. HopmanGrace Li, PMPSusan M. MacAndrew, PMPWilliam J. MooreJerry L. Partridge, PMPPaul Solomon, PMPPamela Stevenson, PMPLaurence A. StoneRay W. Stratton, PMPGeorge R. Stumpf, PEPatrick Weaver, PMPTammo T. Wilkens, PMPJames Wrisley
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 33
Appendix C—Contributors and Reviewers of the Practice Standard for Earned Value Management
34 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
C.2 PRACTICE STANDARD FOR EARNED VALUE MANAGEMENTPROJECT CONTRIBUTORSIn addition to those listed above, the following Practice Standard for Earned ValueManagement Project Team Members were contributors of text or concepts, or providedrecommendations on drafts of the Practice Standard for Earned Value Management:Keith Adams Dinesh Shenoy Kudige, PMPCarolos Alvarado, PMP William B. Kuffner, PMPHeather R. Austin, PMP Grant D. Lawes, PMPRamanan Balakrishna Guilherme Lima, PMPAimee E. Bickers, PMP Marilyn S. McCauleyWilliam A. Brantley, PMP Fred H. Martin, PMPMichael Brennan, PMP Jon Mihalic, PMPTom Butcher Brian P. Miller, PMPJohn P. Buziak Takeshi NishiRichard Carpendale Shawn Nisenboim, PMPLloyd L. Carter Linda NobelEric Christoph Toru Nohzawa, PMPAnita Cukr, PMP Carlo Notari, PMPRobert L. Cutler, PMP Per Nylander, PMPPeter Deacon, PMP David J. Oberg, PMPAlfred S. DeLucia Enyinna C. Okorafor, PMPCharlotte DiCenzo Ranjit R. Pradhan, PMPJohn Dreyer Girish Raghavan, PMPRaphael M. Dua Uday Rangaswamy, PMPEdward Farkas, PMP Raju (Narsing V.N.) Rao, PMPRocky Galletta Jennifer A. Read, PMPLeon S. Green, PMP Nicholas F. RussoWilliam W. Gundrum, PMP Seymour SamuelsBernard A. Homes, PMP Nancy Slater, PMPSrinivas Iyengar Harry I. SparrowHuda Juma, PMP Rikard Stadler, PMPAadham G. Junaidallah Patricia A.TisoneCarl Karshagen, PMP David M. TreacyAmit Kaul Lien B. Vu, PMPSung-Kyum Kim, PMP Lucia WongTerry Koch, PMP Thomas Wuttke, PMPPrasad S. Kodukula, PMP
C.3 PRACTICE STANDARD FOR EARNED VALUE MANAGEMENTPROJECT TEAM MEMBERSIn addition to those listed above, the following Practice Standard for Earned ValueManagement Project Team Members performed reviews of drafts of the Practice Stan-dard for Earned Value Management:Yassir Thiab Afaneh, PMP Takahiko Kuki, PMPStephane Jean Albecq Lee R. Lambert, PMPRey A. Aquino, PMP Craig Letavec, PMPRodrigo Ariza, PMP Robert Matthams, PMPMohammed Aziz, PMP James McGee
Appendix C—Contributors and Reviewers of the Practice Standard for Earned Value Management
Vikas Bakshi Marissa MearnsMichael Blankenstein, PMP Nimsih MehtaNimish Bodalia, PMP Carolyn MelvinThomas D. Burford, PMP Myles D. MillerGustavo A. Carnero Garapati Nageshbabu, PMPKen Chew, PMP Takeshi NishiAnthony Corridore, PMP Morgan NorrisDarren Dalcher Christopher Pillow, PMPChayan Dasgupta, PMP Piotr PlenkiewiczSegundino de La Fuente Javier PuenteAnderson C. de Menezes S.K. Raman, PMPAlphonso Dinson, PMP Ashok RanadeMeri Duncanson Gary William Reading, PMPGregory W. Ennis Christine A. ReidGeraldo Julio Filho Susan F. Rinaldi, PMPCarolyn Francis, PMP Antonio RosselloFred Galione Shahid SaiyadRajeev Gard, PMP Tridibesh Satpathy, PMPWilliam Green, PMP Barry E. SchulerRakesh Gupta, PMP Vinod K. Singh, PMPMary Hogue, PMP Henry B. Smith, PMPFredrik Holm, PMP Jay Smyth, PMPMatthew Hurly, PMP Andrew Tam, PMPMuhammad Ilyas Lisa Tang, PMPIris Wang Michael Tatu, PMPAamir Jelani Ravi Kiran Vadlamudi, PMPKriste Jordan, PMP Thierry Vanden Broeck, PMPNitin A. Joshi Louis C. Ware, PMPDilip K. Kajgaonkar, PMP Warren K. Williams, PMPSlava Khusid
C.4 FINAL EXPOSURE DRAFT REVIEWERS AND CONTRIBUTORSIn addition to team members, the following individuals provided recommendations forimproving the Exposure Draft of the Practice Standard for Earned Value Management:Yassir T. Afaneh, PMP David JacobOndiappan Arivazhagan, PMP Wendy J. King, PMPRobert F. Babb, PMP Robert LeeVanita Chandan Batra, PMP Wei Lee, PMPJohn Michael Boudreau, PMP Enrique Lopez-Mingueza, PMPDavid S. Christensen Isabella Elizabeth Nizza, PMPJohn E. Cormier, PMP Kazuhiko Okubo, PMPKei Deguchi, PMP Miguel Saenz de Viguera, PMPDan Dorion Judy Van MeterWilliam Dowhaniuk, PMP Chris Van Slyke, PMPDiego H. Escobar Ricardo Viana Vargas, PMPQuentin Fleming David Violette, PMPGary Humphreys Patrick Weaver, PMPJohn Hunter, PMP Kimalie Sue Webb, PMP
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 35
Appendix C—Contributors and Reviewers of the Practice Standard for Earned Value Management
36 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
C.5 PMI PROJECT MANAGEMENT STANDARDS PROGRAM MEMBERADVISORY GROUPThe following individuals served as members of the PMI Standards Program MemberAdvisory Group during development of the Practice Standard for Earned Value Manage-ment:Julia M. Bednar, PMPSergio R. CoronadoJ. Brian Hobbs, PMPCarol Holliday, PMPThomas KuriharaAsbjorn Rolstadas, PhDBobbye Underwood, PMPDave Violette, MPM, PMP
C.6 PRODUCTION STAFFSpecial mention is due to the following employees of PMI:Dottie Nichols, PMP—Manager, StandardsSteven L. Fahrenkrog, PMP—Director, Knowledge DeliveryKristin L. Wright—Standards Project SpecialistRichard E. Schwartz—Product EditorBarbara Walsh—Publications PlannerDan Goldfischer—Editor-in-Chief
Appendix D
Additional Sources ofInformation
This standard focuses on the fundamentals of Earned Value Management that can beapplied to most projects most of the time. It does not address specifics that applyonly to particular situations, such as government contracts—with the budgeting,accounting, and reporting requirements common to these contracts. This standardalso avoids describing concepts, methods, and practices that are commonly consideredto be central to project management, such as scoping and scheduling—except whenthese vary to enable the use of Earned Value Management. Readers are encouragedto pursue the subject of Earned Value Management beyond the fundamentals pre-sented in this standard. To facilitate and encourage further study, PMI offers its readersthe following basic guide to additional sources.
PublicationsTo learn about project management in general, PMI recommends:● Project Management Institute. (2004). A guide to the project management body of
knowledge (3rd ed.). Newtown Square, PA: Project Management Institute.
To acquire details on the subject of the work breakdown structure, PMI suggests:● Project Management Institute. (2002). PMI practice standard for work breakdown
structures. Newtown Square, PA: Project Management Institute.
PMI commissioned reviews of the following books on Earned Value, which appear inAppendix E:● Fleming, Q. W., & Koppelman, J. M. (2000). Earned value project management (2nd
ed.) Upper Darby, PA: Project Management Institute.● Humphreys & Associates, Inc. (2002). Project management using earned value.● Kemps, R. R. (2000). Fundamentals of project performance measurement.● Lambert, L. R., & Lambert, E. (2000). Project management: The commonsense
approach. Columbus, OH: LCG Publishing.Other available standards and guides include:
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 37
Appendix D—Additional Sources of Information
38 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
● American National Standards Institute/Electronic Industries Alliance. (1998). Earnedvalue management systems. Arlington, VA: Electronic Industries Alliance. (ANSI-EIA-748-98)
● Earned Value Management Committee, Council of Standards Australia. (2003). Proj-ect performance measurement using earned value. Sydney: Standards Australia Inter-national, LTD. (AS4817)
● The Association for Project Management. (2002). Earned value management APMguideline for the UK. Buckinghamshire, UK: The Association for Project Manage-ment.
An extensive bibliography on Earned Value is available at this Web site:● http://www.suu.edu/faculty/christensend/ev-bib.html
OrganizationsThe following organizations are recommended sources of information:● The Project Management Institute (PMI)
http://www.pmi.org/info/default.asp● The PMI College of Performance Management
http://www.pmi-cpm.org/● The PMI College of Scheduling
http://www.pmicos.org/
Education and TrainingFor opportunities in this area, consult the organizations above and the PMI R.E.P. Pro-gram:● http://www.pmi.org/info/PDC REPOverviewFile.asp?nav�0406
Appendix E
Reviews of Selected Bookson EVM
The following information lists PMI-commissioned reviews of books on Earned ValueManagement (EVM):● Fleming, Q. W., & Koppelman, J. M. (2000). Earned value project management (2nd
ed.). Upper Darby, PA: Project Management Institute.● Humphreys & Associates, Inc. (2002). Project management using earned value.
Orange, CA: Humphreys & Associates, Inc.● Kemps, R. R. (2000). Fundamentals of project performance measurement. Orange,
CA: Humphreys & Associates, Inc.● Lambert, L. R., & Lambert, E. (2000). Project management: The commonsense
approach. Columbus, OH: LCG Publishing.
Earned Value Project Management, Second Edition
by Quentin W. Fleming and Joel M. Koppelman
Project Management Institute, 2000, ISBN: 1-880410-27-3, paperback, 224 pp.
Reviewed by Kenneth H. Rose, PMP, Book Review Editor, Project Management Journal
Earned Value Management is a simple, powerful technique for measuring projectperformance and projecting final results that is often overlooked or even avoided byproject managers. It is required on many government contracts; but its historicallyarcane and ponderous terminology has made it almost an anathema in commercialcontexts. In their updated second edition of Earned Value Project Management, Quen-tin W. Fleming and Joel M. Koppelman address the benefits of Earned Value Manage-ment in a way intended to simplify application processes and make it accessible tothe masses.
The book begins with an illuminating Once upon a time. . . story about a projectmanager facing a challenging task. The scenario will seem familiar to many readers.So much so, in fact, that readers will find it hard to miss the beneficial role of EarnedValue Management in achieving project goals. This opening approach — differentfrom a dry recitation of facts and figures — does much to bring readers on boardand provides a performance-based reason for careful study of what follows.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 39
Appendix E—Reviews of Selected Books on EVM
40 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Thankfully, this book is not yet another listing of almost identical formulas andacronyms to be memorized by obedient readers. First, the gobbledygook acronymsof times past have been replaced by the more contemporary and user-friendly termsof planned value, earned value, and actual cost. (Though in some places, the authorsuse both old and new terminology, probably as a means of transition for experiencedreaders.) These authors seem to strive for establishing a common understanding anddisclosing concepts and goals, an approach that allows the formulas they discuss toclearly take shape in the reader’s mind.
The authors make a strong case for the need for Earned Value Management bydescribing a commonly used evaluation device, the spending plan. A typical spendingplan compares budget to actual expenditures, but does not offer a clue about theactual work that was accomplished as compared to what should have been accom-plished. This is the essence of Earned Value Management: a three-way comparisonshowing work to be done (in terms of expected cost), actual work completed (in termsof expected cost), and actual work completed (in terms of actual cost). These threedata elements allow a project manager to determine variances in both schedule andcost and to make reasonable estimates of schedule and cost at completion.
Fleming and Koppelman offer ten basic benefits of employing Earned Value Man-agement. They then use these as a foundation for developing a simplified form andapproach that may be integrated with other, traditional tools. They show that a workbreakdown structure (WBS) is essential for defining tasks and managing scope. Thisleads naturally to planning and scheduling, also essential for effective application ofthe technique. A third step, estimating and allocating resources, allows completion ofdetailed control accounts (formerly known as cost accounts), which are a distinguishingmark of an Earned Value Management system. This information forms the foundationof the project baseline, against which all future performance will be measured.
Quantifying subsequent work in baseline dollars and then calculating the cost ofthat work allows a project manager to gauge progress against planned schedule andplanned cost. This information is far more meaningful and valuable than that foundin a typical spending plan. The authors describe eight different methods for measuringperformance using earned value methods. Control account plans are an essentialelement in Earned Value Management and the authors provide as examples specificinformation related to high technology, architectural, and software projects.
This book brims with practical guidance and advice. For example, the authors statethat cost performance tends to remain stable after 15–20 percent of the project iscomplete. They show that the schedule performance index (SPI) is important duringearly project phases, less important closer to completion. They also note that CPIshould be watched more closely than SPI because negative positions are more difficultto correct; cost overruns can be improved, but usually not fully recovered. The authorsalso address the forecasting of final costs and schedule results, doing so in a discussionon the three critical factors that influence project performance outcomes.
While Earned Value Management may be essential—or even required—for largecost-reimbursement contracts, its full and formal requirements are not necessary insmaller or firm-fixed price agreements where its benefits should not go untapped.The book closes with 10 basic steps for applying Earned Value Management in justabout any project environment.
Earned Value Project Management does not, by the authors’ own declaration, offeranything really new. Rather, it examines an existing technique and transforms it intosomething more user-friendly—something more useful to those who need it. It is abasic resource—perhaps even the best currently available—that will benefit all projectmanagement professionals.
Appendix E—Reviews of Selected Books on EVM
Project Management Using Earned Value
Humphreys & Associates, Inc.
Humphreys & Associates, Inc., 2002, ISBN: 0970861400, hardcover, 926 pp.
Reviewed by Kenneth H. Rose, PMP, Book Review Editor, Project Management Journal
Earned Value Management is a subject that often receives stand-alone treatmentin either a brief book or a separate chapter in a larger text. Humphreys & Associates,a project and program management consulting firm in Orange, CA, USA, takes adifferent approach in their massive Project Management Using Earned Value. The bookprovides a comprehensive, whole-cloth view of project management with earned valuewoven into the fabric, showing how earned value is an integrated part of good projectmanagement, not an applique to be pasted on when needed or convenient.
‘‘Massive’’ is an understatement. The book is formidable: 8.511-inch format,almost 2 inches thick, and weighing in at 6 pounds. It is more suited to library shelvesthan the desks or briefcases of busy project managers. But its cumbersome size shrinksto irrelevance when readers first open it and discover its immense value.
The book is designed as an instructional aid, probably more for hands-on seminarsthan formal academic settings. Text is written in a direct, speak-to-the-reader stylethat makes complex topics comfortable and easy to understand. Each chapter endswith a series of review questions and a parallel series of true-false questions. Bothare useful. The former allows exploration and tests deep understanding; the latteremphasizes single points of information that should be assimilated and retained.Solutions appear at the end of the book in a section that provides brief discussion ofthe review questions and correct information for the ‘‘false’’ questions.
The book’s 39 chapters are divided into five parts. Part 1 comprises five chaptersthat introduce the concept of earned value and describe the WBS and its role as thefoundation of Earned Value Management; it also links risk, organizational responsibilit-ies, and work teams. Readers will immediately see that this is not a descriptive textthat aims to tell them about earned value. It is an immersion text that enables readersto experience earned value through a rich collection of case studies.
The individual case studies—44 in all—are not toy scenarios created to fit the text,but rather real-world examples from consulting experience. The documents and datawill have a familiar feel to many readers as they arise from general practice, not froman individual author’s personal view. Case studies are challenging and sometimescomplex. The publisher offers complete solutions on its Web site, providing individualPDF files and a zip file of the collected set that may be downloaded as readers choose.
Part 1 introduces a flowchart of a 15-step process for earned value project manage-ment. The chart reappears throughout the book as a graphic guide to readers thatshows where they are in the process as they progress through the technical information.Each of the five parts ends with a quiz of variable length that reinforces learning.Answers to quiz questions are also provided in the back of the book.
Comprising 15 chapters, part 2, ‘‘Scheduling,’’ is the longest in the book. Theoverall length reflects the critical role of scheduling in project planning. The numberof chapters reflects the publisher’s wise design that focuses on the chapter as thebasic unit of organization for major teaching points. Readers will encounter bite-sizeelements that are easily taken in and logically linked to each other. Textbook discus-sions on scheduling often get cut short—several pages of explanation, a couple ofdiagrams, and then on to the next topic. Not so here. Readers march through almost300 pages of progressive concepts and case studies that address not only the usualbasics, but also the practical procedures that make things work.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 41
Appendix E—Reviews of Selected Books on EVM
42 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Part 3 presents the estimating process in eight chapters. Readers will not miss theimportance of this critical step to Earned Value Management. A realistic estimate isthe foundation of successful Earned Value Management—the data element that, whenadded to the equation, makes sense of traditional comparisons of budgeted to actualcosts. The case studies are particularly useful in clarifying what otherwise might be‘‘smoke-and-mirrors’’ in an often theoretical discussion.
Earned value methods are the focus of part 4. The discussion begins with the usualdisclosure of the shortcomings of the budget-actuals approach. A following, simpleexample of building a brick wall makes clear the superiority of the earned valueapproach. This is where most books stop, leaving the reader to figure out exactly whatto do next. But here, it is only the beginning. Readers move through the minefieldsof measuring accomplishments, establishing performance measurement baselines,collecting actual cost data, analyzing data, and taking corrective actions. Safely through,readers will feel confident that they can determine when and how to apply EarnedValue Management in their projects. To guide readers in the final step of application,part 5 addresses implementation as a single chapter and case study.
Project management is not easy. Success depends on many factors, including realis-tic schedules, accurate cost estimates, and well understood risks. In addition, successdepends on effectively measuring work progress. Project Management Using EarnedValue provides the means to acquire this ability and apply it in the project world.
Fundamentals of Project Performance Measurement, Fourth Edition
By Robert R. Kemps, updated by Gary C. Humphreys
Humphreys & Associates, Inc., 2004, ISBN: 0912495219, hardcover, 129 pp.
Reviewed by Kenneth H. Rose, PMP, Book Review Editor, Project Management Journal
Earned Value Management is not the center of the universe. Though it may seemso from all the hype in project management literature, it is just a part—albeit animportant one—of a larger whole. Robert R. Kemps makes this clear in Fundamentalsof Project Performance Measurement, first published in 1996 and now it its fourthupdated edition.
What Kemps makes clear is that measuring project performance is a complex taskinvolving many interrelated and progressive steps. Earned Value Management is apowerful, essential element, but it is not an end in itself. Other books discuss earnedvalue in glorious detail. Kemps weaves it into a broader discussion that focuses onconcepts rather than formulas. It is earned value without the onerous acronyms.
Kemps begins by describing performance measurement as a method for comparingactual performance to a baseline plan. He shows the typical chart that compares actualcosts to the approved budget and points out the inherent shortsightedness of thisview. This is one of the rare occasions where he uses the terms and acronyms forbudgeted cost of work scheduled, budgeted cost of work performed, and actual costof work performed. Having established, in a traditional way, the need for a differentmethod of measurement, Kemps proceeds in a nontraditional way, eschewing thehow-to formulas in favor of a better understanding of what to do and why.
Understanding the full scope of the project is the first step toward effective perfor-mance measurement. Kemps describes the work breakdown structure as a means ofdefining project work and, once completed, a framework for integrating managementsubsystems and accumulating performance information. Linking this to an organiza-
Appendix E—Reviews of Selected Books on EVM
tional breakdown structure is an essential step — and one that must be carefullyperformed — that produces control accounts, the basic level of work measurement.
At this point in the book, readers will probably have noticed another standoutfeature of Kemps approach: the ease with which the information may be taken in.Kemps lays out a step-by-step journey in brief chapters that address a single subject.In addition, his writing style is simple and direct. Satisfied readers may well wonderwhy all books are not written this way.
Moving forward with scheduling and budgeting, Kemps emphasizes the importanceof vertical and horizontal traceability; that is, the linkage of scheduled tasks from topto bottom and from beginning to end. In the budgeting discussion, readers shouldnote the definition of management reserve. This term seems not to have a universalmeaning in project management literature. Readers should be aware of the way Kempsuses it.
While establishing the project baseline is a difficult and time-consuming task, it isalso a critical step in gaining a realistic view of what lies ahead. Kemps cautions readersabout external budgeting decisions made without regard to their effect on individualprojects: these often lead to much grief in schedule slippage and cost overruns.
Although detailed planning produces work packages (a defined task or set of tasksthat have a completed product or end result), the author points out that this notalways that simple. Work packages may encompass a variety of time spans. Somework, such as general project management, may not be amenable to packaging. Suchwork must be captured by either separate level-of-effort accounting or apportioningto affected work packages.
‘‘The key to performance measurement is the objective assessment of work inprogress,’’ (p. 43) says the author in the beginning of his discussion on earned value.He describes the difficulties associated with measuring work of different kinds anddifferent durations, of reinforcing the role of control accounts, work packages, account-ing systems, and data collection in achieving meaning measures.
Chapter 11, ‘‘Estimating Cost at Completion,’’ stands out as being centrally impor-tant. Kemps emphasizes that cost estimates must not be structured to fit some prede-termined, politically saleable number. Now, earned value arises as a comprehensivemethod for measuring progress. The author also points out that the numbers resultingfrom earned value analysis are not sacrosanct. Rather, they should be used as a sanitycheck within wider consideration of other types of estimates.
Since projects are not carved in stone when initial planning is complete, Kempsreminds readers that change—both internally and externally generated—is inevitable.Changes, he explains, must be managed and baselines must be adjusted to avoiddownstream surprises, adding that maintaining the baseline is probably the mostdifficult aspect of performance measurement. Kemps suggests that measuring perfor-mance against a goal rather than a total authorized budget may be a more practicalapproach, if the customer agrees.
Kemps addresses the matter of external reporting in some detail. His view that workbreakdown structures generally expand at a one-to-six rate is a helpful heuristic indetermining the level of reporting. A level too low may result in so much varianceanalysis and so much time required for explanations that the process encumbersrather than enables management. Kemps suggests reports in column format, differentfrom the S-curves usually encountered in project management literature. He alsosuggests a baseline report that will disclose any rubber baseline problems—thosebaseline adjustments that result from using future funds to solve current problems.
The author also discusses the more usual S-curve reports, but ties in two others:one for showing cost and schedule variance trends, and one for showing actual versus
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 43
Appendix E—Reviews of Selected Books on EVM
44 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
projected performance. Kemps wraps things up in a final chapter that reviews theU.S. Department of Defense’s Earned Value Management Systems Guidelines.
Fundamentals of Project Performance Measurement delivers exactly what its titledescribes. It is not a collection of acronyms and formulas. It is a logically progressivepresentation of concepts and offers a general approach. Before applying specificearned value techniques, readers should understand what these techniques are allabout. This book is the place to start.
Project Management: The CommonSense Approach: Using Earned Value to Balancethe Triple Constraint
By Lee R. Lambert and Erin Lambert
LCG Publishing, 2000, ISBN: 0962639788, paperback, 136 pp.
Reviewed by Kenneth H. Rose, PMP, Book Review Editor, Project Management Journal
For many, Earned Value Management can be a matter of great mystery. New con-cepts and obscure formulas tumble together in an avalanche of acronyms. Lee andErin Lambert have brought a welcome degree of clarity and simplicity to this topic intheir brief book Project Management: The CommonSense Approach.
This dandy little book is appropriately subtitled, Using Earned Value to Balance theTriple Constraint. Simple and direct, brief and to the point, the book takes readersright to the heart of Earned Value Management. It shows readers how a few simplecalculations can disclose project actual status and overcome the inaccuracies or exag-gerations of a more subjective approach.
While the calculations may be simple, the foundation is not. Successful applicationof Earned Value Management depends on careful planning and controlled implemen-tation, all based on complete understanding of the concepts. The authors give consider-able attention to the necessary foundation before providing the formulas.
This highly readable book follows a bullet point format with information in concisestatements that readers may easily grasp. Cartoons, sprinkled liberally throughout thetext, illuminate key points and provide a bit of levity to what otherwise could be adeadly dull subject. A recurring cartoon character heralds the delivery of ‘‘CommonSense’’—short, pithy paragraphs that present basic truths to be remembered andapplied.
Readers learn early that Earned Value Management begins with project planning. Itcannot be tagged on to a project midstream; it must be an integral part of requirementsdefinition, planning, and data gathering. Readers also learn the key role played bycontrol accounts, something the authors reinforce throughout the text.
But control accounts do not stand alone. Work packages are the discrete, welldefined work elements that are the basis for measurement and the source of essentialdata. The book includes a couple of clear graphics that display the relationships androles of work packages and control accounts.
In the early part of the book, the authors wisely chose to introduce the conceptsand define the terms in general language without the appearance of the associatedformulas. This approach allows readers to get the concepts before they have to dealwith the math.
Work authorization and flow is a critical factor in managing control accounts, butit is an end-of-line process. The authors show the whole picture, starting right at thetop, so that readers will understand the larger context of Earned Value Management.One of the first points of ‘‘Common Sense’’ gently warns readers to adopt good
Appendix E—Reviews of Selected Books on EVM
planning and accurate progress measuring techniques. Other, more subjective tech-niques will not release the full potential of Earned Value Management. A discussionof budgets and cost accumulation completes the review of essential elements.
Performance measurement is the thorny subject in any earned value implementa-tion. This is where the smoke and mirrors usually appear. The book describes severaldifferent methods for determining work completion status. Some are simple, somecomplex. The authors suggest an innovative approach that may be applied to projectswith a high research component, bringing the benefits of Earned Value Managementto an area where it has been historically ignored.
Data from performance measurement lead to variances—differences between whatwas planned and what was done. This is the focus of Earned Value Management. Theauthors give examples and explain a variety of conditions that may be of interest orconcern to project managers. Another ‘‘Common Sense’’ point comes in to advisereaders to evaluate earned value data in the context of the project network diagram.Schedule variances off the critical path may indicate a proper use of float, not aperformance problem.
Finally, the formulas appear. Because of all the preparation, they come in as anatural next step, not a new source of anxiety and confusion. Readers may well wonderwhat all the fuss was about. At this point, it all seems pretty straightforward. One lastbit of ‘‘Common Sense’’ reminds readers that materials accounting can be a sourceof disconnect in Earned Value Management. The authors provide several options formaterials accounting that will meet various project situations.
In closing the book, the authors make the point that training is essential and thatit should be applied near the time of use and consider actual project data if possible.They also provide an extensive discussion on selecting project software that may besomething of a non sequitur but still generally useful. Of certain value is the appendixof guidelines for applying Earned Value Management. It gives readers a practicalframework for using what they have learned.
Earned Value Management: The CommonSense Approach may not be the mostimpressive looking book on the shelf. It won’t win any prizes for weight or numberof pages. It offers something more important. Its brevity and unique approach providea degree of value matched by few others. If you are just starting Earned Value Manage-ment, start here. If you are midstream in implementation, read this book, digest itscontents, and you may find some simple solutions to problems that have been blockingyour way.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 45
References
Project Management Institute. (2004). A guide to the project management body ofknowledge (3rd ed.). Newtown Square, PA: Project Management Institute.
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 47
Glossary
Actual Cost (AC). Total costs actually incurred and recorded in accomplishing work performed duringa given time period. (Note: The PMBOK� Guide definition for this term is broader and moreinclusive in that it applies beyond the scope of the Practice Standard for Earned ValueManagement.)
Actual Cost of Work Performed (ACWP). See Actual Cost (AC).Apportioned Effort (AE). Effort applied to project work that is not readily divisible into discrete efforts
for that work, but which is related in direct proportion to measurable discrete work efforts.Contrast with Discrete Effort.
Budget at Completion (BAC). The sum of all the budgets established for the work to be performedon the project. The total planned value for the project. (Note: The PMBOK� Guide definitionfor this term is broader and more inclusive in that it applies beyond the scope of the PracticeStandard for Earned Value Management.)
Budgeted Cost of Work Performed (BCWP). See Earned Value (EV).Budgeted Cost of Work Scheduled (BCWS). See Planned Value (PV).Control Account. A management control point where scope, budget (resource plans), actual cost,
and schedule are integrated and compared to earned value for performance measurement.Control accounts are placed at selected management points (specific components at selectedlevels) of the work breakdown structure. (Note: The PMBOK� Guide definition for this term isbroader and more inclusive in that it applies beyond the scope of the Practice Standard forEarned Value Management.)
Cost Performance Index (CPI). A measure of cost efficiency on a project. It is the ratio of earnedvalue (EV) to actual costs (AC). CPI � EV divided by AC. A value equal to or greater than oneindicates a favorable condition and a value less than one indicates an unfavorable condition.
Cost Variance (CV). A measure of cost performance on a project. It is the algebraic differencebetween earned value (EV) and actual cost (AC). CV � EV minus AC. A positive value indicatesa favorable condition and a negative value indicates an unfavorable condition.
Discrete Effort. Work effort that is separate, distinct, and related to the completion of specific endproducts or services, and that can be directly planned and measured. (Note: The PMBOK�Guide definition for this term is broader and more inclusive in that it applies beyond the scopeof the Practice Standard for Earned Value Management.)
Earned Value (EV). The value of work performed expressed in terms of the budget assigned to thatwork. Also referred to as the Budgeted Cost of Work Performed (BCWP). (Note: The PMBOK�Guide definition for this term is broader and more inclusive in that it applies beyond the scopeof the Practice Standard for Earned Value Management.)
Earned Value Technique (EVT). A technique or method for measuring the performance of work, andused to establish the performance measurement baseline (PMB). (Note: The PMBOK� Guidedefinition for this term is broader and more inclusive in that it applies beyond the scope ofthe Practice Standard for Earned Value Management.)
Estimate at Completion (EAC). The expected total cost of completing project work. EAC is equal tothe actual cost (AC) plus the estimate to complete (ETC) for all of the remaining work. TheEAC may be calculated based on performance to date or estimated by the project team basedon other factors. (Note: The PMBOK� Guide definition for this term is broader and moreinclusive in that it applies beyond the scope of the Practice Standard for Earned ValueManagement.)
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 49
Glossary
50 ©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Estimate to Complete (ETC). The estimated cost of completing the remaining work. (Note: ThePMBOK� Guide definition for this term is broader and more inclusive in that it applies beyondthe scope of the Practice Standard for Earned Value Management.)
Level of Effort (LOE). Support-type activity (e.g., seller or customer liaison, project cost accounting,project management), which does not produce definitive end products. (Note: The PMBOK�Guide definition for this term is broader and more inclusive in that it applies beyond the scopeof the Practice Standard for Earned Value Management.)
Management by Exception. A management technique that emphasizes attention to performancebehavior that falls outside of some predetermined range of normal or expected outcomes.This technique is characterized by containment and conservatism.
Organizational Breakdown Structure (OBS). A hierarchically organized depiction of the project organi-zation arranged so as to relate the work to the performing organizational units. (SometimesOBS is written as Organization Breakdown Structure with the same definition.) (Note: ThePMBOK� Guide definition for this term is broader and more inclusive in that it applies beyondthe scope of the Practice Standard for Earned Value Management.)
Performance Measurement Baseline (PMB). An approved, integrated scope-schedule-cost planfor the project work against which project execution is compared to measure and manageperformance. (Note: The PMBOK� Guide definition for this term is broader and more inclusivein that it applies beyond the scope of the Practice Standard for Earned Value Management.)
Physical Work Progress. The amount of work physically completed on the project or task. This maybe different from the amount of effort or money expended on the project or task. Predeterminedtechniques of claiming physical work progress that were selected during project planning areused to credit Earned Value when work is partially complete at the time of progress reporting.
Planned Value (PV). The authorized budget assigned to the scheduled work to be accomplished.Also referred to as the budgeted cost of work scheduled (BCWS). (Note: The PMBOK� Guidedefinition for this term is broader and more inclusive in that it applies beyond the scope ofthe Practice Standard for Earned Value Management.)
Responsibility Assignment Matrix (RAM). A structure that relates the project organizational break-down structure to the work breakdown structure to help ensure that each component of theproject’s scope of work is assigned to a responsible person/team.
Schedule Performance Index (SPI). A measure of schedule efficiency on a project. It is the ratio ofearned value (EV) to planned value (PV). The SPI � EV divided by PV. An SPI equal to orgreater than one indicates a favorable condition and a value of less than one indicates anunfavorable condition.
Schedule Variance (SV). A measure of schedule performance on a project. It is the algebraicdifference between the earned value (EV) and the planned value (PV). SV � EV minus PV.(Note: The PMBOK� Guide definition for this term is broader and more inclusive in that itapplies beyond the scope of the Practice Standard for Earned Value Management.
S-Curve. Graphic display of cumulative costs, labor hours, percentage of work, or other quantities,plotted against time. Used to depict Planned Value, Earned Value, and Actual Cost of projectwork. (Note: The PMBOK� Guide definition for this term is broader and more inclusive in thatit applies beyond the scope of the Practice Standard for Earned Value Management.)
Time-Phase Budget. A project budget that identifies how much money or labor is to be expendedon each task for each time period (e.g., month) in the project schedule (see Planned Value).
To-Complete Performance Index (TCPI). The calculated projection of cost performance that mustbe achieved on remaining work to meet a specified goal, such as the BAC or the managementEAC. For example: To-Complete Performance Index � (remaining work) / (budget remaining)� (BAC � EV) / (BAC � AC).
Variance at Completion (VAC). The difference between the total budget assigned to a project(BAC) and the total cost estimate at completion (EAC). Variance at Completion � Budgetat Completion � Estimate at Completion. It represents the amount of expected overrunor underrun.
Variance Threshold. A predetermined range of normal outcomes that is determined during theplanning process and sets the boundaries within which the team practices managementby exception.
Index by Keyword
Actual Cost ................................................................................ 4-9, 13-15, 18-20, 25, 40, 42Actual Cost of Work Performed ........................................................................................8, 42Apportioned Effort ............................................................................................................9, 11Budget at Completion ....................................................................................................15, 19Budgeted Cost of Work Performed ...................................................................................8, 42Budgeted Cost of Work Scheduled ...................................................................................7, 42Control Account ......................................................................... 3, 5, 20-21, 23-24, 40, 43-44Cost Performance Index ...........................................................................................15, 19, 21Cost Variance ....................................................................................................12, 15, 18, 20Critical Path ..................................................................................................................17, 45Discrete Effort ..................................................................................................................9-10Earned Value ........................................................ 4-9, 11-15, 17-19, 21, 23, 25, 29-31, 37-45Earned Value Management ................................................... 1, 7, 15, 23, 29-30, 33-42, 44-45Earned Value Measurement Techniques ...............................................................3-5, 9-10, 24Earned Value Technique .................................................................................................25, 44Estimate at Completion ............................................................................................15, 19-20Estimate to Complete ...............................................................................................15, 19-20Fixed Formula .................................................................................................................10-11Level of Effort ..................................................................................................................9, 11Management-by-Exception ..............................................................................................20-21Organizational Breakdown Structure .....................................................................................42Percent Complete ...........................................................................................................10-11Performance Measurement Baseline ..................................................3-7, 9, 12, 15, 23-25, 42Performance Reporting ........................................................................................................22Physical Work Progress ....................................................................................4-6, 12, 23, 25Planned Value ................................................................................... 5-9, 11-15, 17, 24-25, 40Project ................................................................................................. 1-31, 33-34, 36-45, 47Responsibility Assignment Matrix ..........................................................................................2S-Curve .................................................................................................................................7Schedule Performance Index ....................................................................................15, 17, 40Schedule Variance .......................................................................................12, 15, 17, 43, 45Time Estimate at Completion .........................................................................................15, 17Time-Phased Budget ...........................................................................................3, 6, 9, 23-25To-Complete Performance Index ...........................................................................................22Variance at Completion ..................................................................................................15, 19Variance Threshold ..............................................................................................................25Weighted Milestone ........................................................................................................10-11Work Breakdown Structure ..................................................... 2-3, 5, 20, 24-25, 37, 40, 42-43Work Scope .................................................................................................................3, 6, 23
©2005 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 51
As a project management professional, it is critical to know the answers to questionssuch as: are we ahead of or behind schedule, are we under or over budget, and what isthe remaining work likely to cost? While identifying issues such as these is critical to aproject’s success, it is even more critical as a project manager to be able to identify wherethe problems are occurring, how critical the problems are, and what it will take to getthe project back on track.
This is where Earned Value Management (EVM) methodology can fill a vital need.
The Practice Standard for Earned Value Management expands on the earned valueinformation in A Guide to the Project Management Body of Knowledge (PMBOK®
Guide) – Third Edition. EVM is often referred to as “management with the lights on”because it helps objectively and succinctly identify where a project is and where it isgoing. The methodology incorporates project scope, schedule and costs, and the processis applicable across many Knowledge Areas and Process Groups.
Practice Standard for Earned Value Management expands the available resources onthe use of EVM for medium and smaller projects – while still being relevant for largerprojects. The Practice Standard is intended to guide project management practitionerswho are familiar with EVM, as well as novices. It also provides insight and detailed expla-nation of the basic elements of EVM, and demonstrates how to scale EVM to fit varyingproject sizes and situations. When used in concert with good project management prin-ciples, the EVM methodology will provide greater return on any project and results thatwill directly benefit your organization.
Project Management InstituteFour Campus BoulevardNewtown Square, PA 19073-3299 USAwww.pmibookstore.org
Putting the power of Earned Value Management to work for your organization…
Project Management Institute
Practice Standard for Earned Value ManagementUS $44.95