Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Technical Assistance Consultant’s Report
This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents. (For project preparatory technical assistance: All the views expressed herein may not be incorporated into the proposed project’s design.
Project Number: 46486 March 2016
Republic of the Union of Myanmar: Enhancing the Power Sector’s Legal and Regulatory Framework (Financed by the Government of Norway)
Prepared by DFDL Thailand
For the Ministry of Electricity and Energy
Financed by the
Government of Norway
MYANMAR
Enhancing Power Sector’s
Legal and Regulatory Framework
FINAL REPORT
TA-8469 MYA
Contract No. 110892-S52300
DFDL Thailand
(46486-001)
Prepared by:
Robert Fitzgibbons Jr. (DFDL)
Audray Souche (DFDL)
Matthew Christensen (DFDL)
William Derbyshire (ECA)
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 2
APPRECIATION
The DFDL Consulting Team wish to record its appreciation of the support from ADB staff, in particular Chi Nai
Chong, James Liston, Jong-Inn Kim, and Christine Samaniego and the hospitality and efforts of the Ministry of
Electric Power, in particular U Khin Maung Win, the then Director General of the Department of Electric Policy
a d Pla i g DEPP a d the p i e o ta t at the Mi ist of Ele t i Po e , Deput Di e to Ge e al of DEPP, Daw Mi Mi Khaing (and her team), H.E., Deputy Minister U Aung Than Oo, and H.E. Deputy Minister U
Maw Thar Htwe. Personal thanks are due to U Aung Win Kyaw our ADB project coordinator, Audray Souche,
Matthew Cristianson and Viacheslav Baksheev of DFDL, the Honorable David Butcher, and the staff of the
Ministry of Electric Power too numerous to list all individually.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 3
ABBREVIATIONS
ADB Asian Development Bank
ARR Allowed Revenue Requirement
BOT Build, Operate, Transfer
DEP Department of Electric Power
DG Director General
DRD Department of Rural Development
ERC Electricity Regulatory Commission
ESE Electricity Supply Enterprise
IFC International Finance Corporation
IPP Independent Power Producer
JICA Japan International Cooperation Agency
KW Kilowatt
MAI Ministry of Agriculture and Irrigation
MEPE
MIC
Myanma Electric Power Enterprise
Myanmar Investment Commission
MLFRD Ministry of Livestock, Fisheries, and Rural Development
MOE Ministry of Energy
MOEP Ministry of Electric Power
MOF Ministry of Finance
MOST Ministry of Science and Technology
MOU Memorandum of Understanding
MW Megawatt
NEMC National Energy Management Committee
NEP National Electrification Plan
NPV Net Present Value
O&M Operation & Management
PPA Power Purchase Agreement
REMC Rural Electrification Management Committee
REWSC Rural Electrification and Water Supply Committee
RFP Request for Proposal
RFQ Request for Qualification
SHS Solar Home Systems
SPP Small Power Producer
TOR Terms of Reference
USD United States Dollar
VEC Village Electrification Committee
YESC Yangon Electricity Supply Corporation
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 4
TABLE OF CONTENTS
Executive Summary 6
Chapter 1: Introduction 10
1.1 Background 10
1.2 Terms of Reference 10
1.3 Work Effort and Product 13
1.4 References, Definitions and Capitalized Terms 15
Chapter 2: Preparation of New Electricity Law 16 (Phase 1 - Tasks 1&2)
2.1 Initial Assessment 16
2.2 Major Identified Shortcomings 17
2.3 Reactions to Identified Shortcoming 19
2.4 Review of Subsequent Drafts of New Electricity Law 20
2.5 Analysis and Assessment of New Electricity Law 20
Chapter 3: Electricity Rules to Implement New Electricity Law and
to Establish Electricity Regulatory Commission (Phase 2 - Task 1) 23
3.1 Initial Assessment 23
3.2 Defining the Content of Electricity Rules 23
3.3 Regulatory Features from International Best Practices 27
3.4 Electricity Rules Drafting Effort 30
3.5 Initial Version of Draft Electricity Rules 30
3.6 Implementation of Electricity Law 31
3.7 Establishment of the Electricity Regulatory Commission (ERC) 34
3.8 Redress of Shortcomings of New Electricity Law 37
3.9 First Electricity Law Workshop 38
3.10 Reaction of Other Union Government Institutions 38
3.11 Second Electricity Law Workshop 38
3.12 Final Version of Electricity Rules 38
3.13 Analysis and Assessment 39
Chapter 4: Preparation of Power Sector Supporting Regulations 42 (Phase 2 – Tasks 2&3 and Phase 3)
4.1 Initial Assessment 42
4.2 Task Revisions Due to ERC Exclusion from Regulation 42
4.3 Status of Supporting Regulations 43
4.3.1 MOEP Filing Procedures Regulations 43
4.3.2 MOEP Permitting Regulations 45
4.3.3 MOEP Tariff Regulations 50
4.3.4 MOEP Investments, Power Procurement, and Resource Acquisition Regulations 53
4.3.5 MOEP Competitive Tenders and Solicitations Regulations 57
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 5
4.3.6 ERC Procedures 63
4.4 Analysis and Assessment 66
Chapter 5: Preparation of Rural Electrification Law and Implementing Regulations 72 (Phase 1- Task 2 and Phase 2- Task 2)
5.1 Initial Assessment 72
5.2 Background 73
5.3 Challenges and Impediments to Rural Electrification 74
5.4 Recommended Content for New Rural Electrification Law 78
5.4.1 Objectives 78
5.4.4 Establishment of Lead Government Institution 78
5.4.5 Establishment of Executive Secretariat 80
5.4.6 Requirements for the National Rural Electrification Master Plan 81
5.4.7 Coordinating Tariffs with Funding of Rural Electrification 81
5.4.9 Directive to Revise Program for Household Electrification 81
5.4.10 ESE and YESC: Cost Recovery, Subsidies and Connection Costs 81
5.5 Rural Electrification Programs 82
5.5.3 Small Power Producers and Distributors (Grid Connected or Isolated) 82
5.5.27 Distribution Sub-Franchises and Subcontractors 86
5.6 Rural Electrification Fund 89
5.7 Rural Electrification Finance Corporation 90
5.8 Investment Promotion Privileges 90
Chapter 6: Conclusions- Looking Forward 91
6.1 Additional Regulations 91
6.2 Internal Regulatory Organization, Process and Procedures 91
6.3 Human Capacity Building 91
6.4 Rural Electrification Law 92
Appendices
A: Terms of Reference
B: New Electricity Law
C: Rural Electrification Law
D: Electricity Rules
E: Requested Regulations and ERC Rules
F: Work Products (English)
G: Work Products (Myanmar)
H: Inception Report
I: Interim Report
J: DFDL Consulting Team CVs
(available upon request)
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 6
Executive Summary
This Project is the result of the request of the Government of the Republic of the Union of Myanmar for the
Asian Development Bank (ADB) and the Government of Norway to assist the Ministry of Electric Power (MOEP)
to prepare a new electricity law and subsidiary legal instruments to enhance the legal and regulatory framework
for the Myanmar power sector which reflects current international standards and enables the introduction of
an electricity regulator and corresponding institutional arrangements. The key objective of enhancing the legal
a d egulato f a e o k is to suppo t the go e e t s efo age da fo the po e se to i p o idi g an improved regulatory framework to support the gradual restructuring of the power sector; (ii) encouraging
greater private sector participation in power sector projects and enabling third-party network access; (iii)
establishing and implementing rural electrification programs; and (iv) introducing an electricity regulator
consistent with internationally recognized best practices.
The technical assistance provided pursuant to this Project was divided into four components, and the key
findings are set forth below.
Assisting the Preparation of the New Electricity Law
At the initiation of this Project in February 2014, a draft of the new Electricity Law had already been prepared
under the supervision of the Minister of the MOEP, submitted to the Office of the Attorney General for
comments, approved by the Cabinet, and submitted to Parliament. The first task of the DFDL Consulting Team
was to prepare extensive comments on the draft Law identifying potential shortcomings and proposing
revisions thereto intended to reflect international best practices.
Most notably, the draft Law; (i) misallocated regulatory responsibilities; (ii) set forth insufficient regulatory
authority; (iii) failed to include pre-established standards to govern regulatory decisions; (iv) provided
inadequate details regarding permitting and the formation of the regulatory Institution; and (v) did not provide
meaningful appeals of regulatory decisions. However, MOEP management declined to propose any changes to
the draft Law since its enactment was imminent and the foregoing shortcomings were included in the new
Electricity Law.
Nonetheless, the new Electricity Law enacted in October 2014 represents a significant step towards the
establishment of an effective legal and regulatory framework for the Myanmar power sector. Notably, the new
Law provides for the establishment of the Electricity Regulatory Commission (ERC). The new Law provides the
legal basis for the corporatization and privatization of state-owned power sector enterprises such as the
Electricity Supply Enterprise (ESE) and the Myanmar Electric Power Enterprise (MEPE). In addition, the new
Law clarifies jurisdictional boundaries for regulatory responsibilities between the various levels of government,
and establishes a permitting regime to control participation in and structure of the power sector. The new
Electricity Law creates a solid foundation to support the issuance and application of rules and regulations that
will provide context to the Law itself.
Further, the shortcomings identified with the new Electricity Law were redressed through the Electricity Rules
and implementing regulations issued by the MOEP, currently awaiting Parliamentary approval, with one notable
exception. This exception is the requirement for MOEP regulatory decisions to be submitted for approval by
the Union Government as being the sole avenue for appeals and redress until the Electricity Law is revised.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 7
Preparation of the Electricity Rules and the Establishment of the ERC
The draft Electricity Rules submitted to Parliament for approval will, upon their enactment, constitute a second
and perhaps even more significant step forwards, laying a solid legal foundation for effective power sector
regulation. The Electricity Rules will help establish the basic framework for the regulation of the Myanmar
power sector.
The Electricity Rules establish a permitting regime through which MOEP will control participation in the power
sector with defined service obligations for each type of power sector participant. The permitting regime is
designed to be flexible in order to enable future power sector structural reforms to be easily implemented. In
addition, the authority and regulatory responsibilities of MOEP are significantly expanded to include the
regulation of financial activities and organizational affairs, technical and industry standards, codes of conduct,
the forecasting of load growth, least-cost resource planning, and investment planning and resource
procurement, thus ensuring that MOEP has the required tools to protect the power sector against monopolistic
abuses.
Transparency and predictability are promoted in the Electricity Rules through the requirement that all MOEP
regulatory decisions are to be in written form setting forth their factual and legal basis, and the specification
for pre-established standards to govern all significant regulatory decisions, including permit issuances, tariff
determinations and regulatory approvals of financial activities, mergers and corporate reorganizations,
investment and resource acquisition, power procurement and power purchase agreements.
Importantly, the Electricity Rules provide greater detail regarding the processes and requirements applicable
to tariff determinations by basing them upon expressly stated principles and standards; most notably to allow
the recovery of all costs incurred in meeting demonstrated customer needs, and that the rate of return on
power sector capital investments are to be at a level that promotes investments in equipment and facilities.
Notwithstanding the significant benefits that will be achieved by the Electricity Rules, notable shortcomings of
significance remain, the most important being the absence of any mechanism by which the ERC can become
involved in performing regulation. In addition, unlike for the ERC, the Electricity Rules do not set forth any
requirements regarding the regulatory organization, process, and procedures for the MOEP. Thus, by
consolidating all regulatory tasks with the MOEP instead of with the ERC, the process for regulation by MOEP
will be left entirely unregulated with no safeguards to promote transparency and accountability. The basic
foundation of the MOEP internal organization, process, and procedures by which the MOEP will perform its
regulatory tasks should be established and in place before MOEP commences with the performance of its
regulatory responsibilities.
Preparation of the Power Sector Supporting Regulations
Six regulations were selected for prioritized preparation. These efforts resulted in a core set of workable
regulations that support the operationalization of the MOEP regulatory functions, and in several regards include
features that will move M a a s power sector regulation closer to international best practices.
Filing Procedures. The draft MOEP filing regulations address all of the elements of regulatory proceedings, and,
along with the other regulations, are intentionally simple to minimize confusion and maximize effective
application. The draft regulations include features consistent with international best practices, such as the
publication of notices of all regulatory filings, an opportunity for members of the public who could be adversely
affected to participate in regulatory proceedings, and the possibility of a public hearing regarding disputes as
to material facts. These features should help to improve the transparency of MOEP regulation.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 8
Permitting Regulations. The draft MOEP permitting regulations address applications for, revisions and
modifications, and suspensions and revocations of Permits. These regulations set forth the form for Permit
applications and the information required to be provided for in; (i) all Permit applications; (ii) applications for
each type of Permit and each type of Electricity Related Works; (iii) applications involving both existing and new
power facilities; and (iv) applications for each type of power facility, including thermal and hydro power
generation, transmission and distribution.
Two features are particularly noteworthy for private developers. First, the promotion of transparency. If the
MOEP intends to deny a permit application, the applicant must be granted an opportunity to present to the
MOEP the reasons its application should not be denied. Second, Permits are prohibited from being issued until
the applicant has obtained all requisite governmental approvals, and for generation Permits, the execution of
a pre-approved power purchase agreement.
Tariff Regulations. The draft tariff regulations set forth formulas by which tariffs are to be determined for each
type power sector activity and each type power generation technology while providing the details to establish
revenue requirements, permissible returns on equity, and the other relevant cost categories. Sufficient
flexibility is incorporated for revisions as experience with tariff regulation is gained. The principles governing
tariff determinations are intended to assure power sector participants of the opportunity to recover all
prudently incurred costs and to earn sufficient revenue to promote investments and incentivize improvements.
With two exceptions, the draft tariff regulations create a general prohibition against cross-subsidies. Existing
cross-subsidies from non-household to household customers are required by the draft tariff regulations to be
phased out gradually.
Investment, Power Procurement and Resource Acquisition Regulations. The draft regulations regarding
investments, power procurement and resource acquisitions are intended to help ensure power sector
participants obtain the resources and facilities required to satisfy their respective service obligations at lowest
reasonable cost, and promote efficient and coordinated planning for the power sector. Acknowledging
implementation difficulties associated with these objectives, the Electricity Rules require the MOEP to develop
a forecasting methodology and guidance thereon to be applied by power sector participants, and to annually
prepare a National Power Development Plan with which the investment, power procurement and resource
acquisition plans of power sector participants must be demonstrated to be consistent.
Competitive Tender Regulations. The draft regulations on competitive tenders and solicitations set forth a
bidding regime alled a “ iss halle ge, hi h is designed to put unsolicited projects up for competitive bid;
whereby such projects can be awarded to a party other than the original proponent of the project provided the
winning bidder pays compensation to the proponent equal to the amount of compensation the proponent
would have had with the MOEP. Eligible projects are required to have been assessed by the MOEP and then
designated for development by competitive tender.
ERC Procedural Regulations. The draft ERC procedural regulations essentially combine into a single document
the rules related to the ERC that were omitted from the final version of the Electricity Rules submitted to
Parliament. There is no doubt as to the likely effectiveness of these draft regulations had the ERC been given a
role in performing regulatory tasks. These draft procedures have limited significance as long as the ERC remains
uninvolved in regulation. However, once the ERC assumes some regulatory responsibilities, these draft
regulations will again become of paramount importance.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 9
Preparation of the Rural Electrification Law
The Myanmar National Electrification Plan (NEP) sets forth the commitment to achieve a 100% household
electrification rate by 2030, but with less than one-third of households electrified to date, this is a daunting
challenge. To address this challenge, this Project required the preparation of a draft Rural Electrification Law.
Efforts to draft the Rural Electrification Law focused on reforms to promote and accelerate rural electrification
by most notably; identifying a government institution to lead rural electrification efforts, increasing the grid-
based electrification efficiency and allowing private sector participation, supporting the implementation of
mini-grids, and designing sustainable household electrification programs.
It is recommended that an institutional structure be established to coordinate government funding to support
rural electrification. As part of this structure, a government institution should be established to receive all
government funds for electrification, and through which all government financial support would be dispersed.
The new Rural Electrification Law should specify the sources of that funding and how those funds are intended
to be used. Finally, to enable debt financing of off-grid electrification projects by local communities and the
private sector, serious consideration should be given to the creation of a government corporation to finance
rural electrification projects at concessionary rates. Ideally, both national and international funding sources
would be allocated to this corporation, which would then extend financing to projects based upon established
criteria.
Two types of electrification programs to promote private sector participation in rural electrification should be
endorsed by the new Rural Electrification Law. The first is a Small Power Producer and Distributor program
whereby private investment in mini-grids and off-grid generation is encouraged and promoted by relaxed
regulatory requirements. A prerequisite for success of such a program is permitting the prices charged to
consumers served by very small and off-grid power projects, such as mini-grids, to exceed the regulated prices
charged to consumers connected to the national grid. The second is a Distribution Sub-Franchises and
Subcontractors program, which focuses on accelerating the rate of grid connections by using sub-franchises and
subcontracts to attract private investments in new or upgraded distribution networks.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 10
Chapter 1
Introduction
1.1 Background
1.1.1 Project Scope: The Government of the Union of the Republic of Myanmar recognized that the laws and
rules governing the Myanmar power sector (the Electricity Act, 1948, as amended in 1967, the
Myanmar Electricity Law, 1984, and the Electricity Rules, 1985) needed revision to address the
challenges and difficulties facing the Myanmar power sector.
1.1.2 The Government of the Republic of the Union of Myanmar, therefore, requested the assistance of the
Asian Development Bank (ADB) and the Government of Norway to assist the Ministry of Electric Power
(MOEP) to prepare the legal instruments needed to enhance the legal and regulatory framework for
the Myanmar power sector. The objective of this project was for the regulatory framework to reflect
current international standards and to create an enabling framework for introducing an electricity
regulator and corresponding institutional arrangements.
1.1.3 Consulting Team: On 20 February 2014, the ADB and DFDL Thailand executed a contract whereby the
DFDL Consulting Team, consisted of Mr. Robert Fitzgibbons (International Regulatory Expert and Team
Leader), Ms. Thida Aye (National Regulatory Expert), Mr. John Diecker (International Power Engineer)
and Ms. Tan Tan Win (National Power Engineer), was appointed to advise and assist the Government
of the Republic of the Union of Myanmar to establish an effective legal and regulatory framework for
the Myanmar power sector and to assist the acceleration of rural electrification the P oje t . In
order to enhance the substance of the MOEP tariff regulations to be prepared, International Economist
William Derbyshire was added to the project team. In addition, Mr. Ah Lonn Maung, a senior Myanmar
lawyer with DFDL who worked for many years with the Union Office of the Attorney General in
Myanmar was, for health reasons, substituted for Ms. Thida Aye partway through the Project.
1.1.4 Project Commencement: The DFDL Consulting Team commenced performance of the Project on 3
March 2014, as required by the Terms of Reference (TOR), within 15 calendar days following the ADB
issuance of the Notice to Proceed on 25 February 2014. This report covers all works performed between
the date of the Notice to Proceed and final expiration of the ADB Contract for the Project on 28 February
2016.
1.1.5 Original Contract Term: According to the TOR, this Project was divided into three phases. Phases One
and Two were to be completed within 12 calendar months from the date of issuance of the Notice to
Proceed. Phase Three was initially planned to commence after the draft Rural Electrification Law had
been completed.
1.2 Terms of Reference
The complete text of the Terms of Reference (TOR) for this Project is attached hereto as Appendix A.
The following summarizes the performance tasks that were required to be performed by the DFDL
Consulting Team under the TOR.
1.2.1 Phase 1 - Task 1: Review of existing ADB materials, including works under the regional TA for Enhancing
Effective Regulation of Water and Energy Utilities and to conduct workshops to present and assess
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 11
relevant regulatory reform models potentially applicable in Myanmar. The work performed included
the following:
1.2.2 Review of the ADB s M a a E e g “e to I itial Assess e t, the Ele t i it A t as a e ded in 1967), the Myanmar Electricity Law (1984), Electricity Rules (1985), the draft electricity law 2013, and
other government plans; and to undertake research on existing electricity law and regulatory
structures;
1.2.3 Based on item (a), to prepare presentation materials for consultations, subsequent discussions, and
workshops involving civil society stakeholders, government officials, and development partners to
highlight 3- possi le egulato efo odels f o the egio , e.g., f o the Lao People s De o ati Republic, Malaysia, Thailand, and Viet Nam, and to present an appropriate model for Myanmar
government officials to consider, if needed;
1.2.4 Incorporation of provisions for the draft Electricity Law, such as (i) overall control and operation of
electricity in the country; (ii) establishment of an electricity regulator; (iii) private sector participation
in both large-scale generation and small-scale off-grid projects for rural electrification; (iv) cross-border
power trading, (v) third-party access to the grid; (vi) Permits for private sector participation and
contractual arrangements between the government, operators, and service providers; and (vii) a review
of themes such as public–private partnerships, community participation in electricity supply as part of
renewable energy, feed-in tariffs, demand-based management, and energy efficiency; and
1.2.5 To hold consultations and subsequent discussions and workshops with civil society stakeholders,
government officials, and development partners regarding electricity sector issues to ensure that their
views were taken into account when considering appropriate policy measures.
1.2.6 Phase 1 - Task 2: Review of e isti g ate ials o M a a s e e g se to , esea h of other relevant
materials, and to conduct workshops to assess possible models of rural electrification for Myanmar to
propose a new rural electrification law and corresponding implementing regulations. The work
performed included the following:
1.2.7 Review of ADB reports and energy sector assessments and to undertake background research on rural
ele t ifi atio odels i B azil, the People s ‘epu li of Chi a, the Lao People s De o ati ‘epu li , the Philippines, and Viet Nam. Based on this review and research work, to conduct a workshop to
highlight two or three possible models of rural electrification that may be appropriate in the Myanmar
context;
1.2.8 Once the government selected a rural electrification model, draft the regulations and implementing
guidelines for rural electrification;
1.2.9 To enable local authorities to invest in small grids and to enable rural electrification within their
franchise areas, or to allow private companies to invest in localized generation and distribution; and
1.2.10 To propose a new rural electrification law and corresponding implementing regulations suitable to
Myanmar.
1.2.11 Phase 2 – Task 1: Phase 2 covered the preparation of the implementing regulations for a revised
Electricity Law and draft Rural Electrification Law; development of a competitive power market as a
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 12
long-range goal; and identification of institutional arrangements and roles for the location, structure,
and staffing of the Electricity Regulatory Commission (ERC).
1.2.12 To assist the Ministry of Electric Power (MOEP) in preparing the implementing regulations to facilitate
implementation of the revised Electricity Law; including translation into the local language; various civil
society consultations; and subsequent discussions and workshops involving civil society stakeholders,
government officials, and development partners to meet the requirements of the government and
Parliament.
1.2.13 Phase 2 – Task 2: To assist the MOEP in preparing the implementing regulations for the proposed Rural
Electrification Law, including translation into the local language; and to hold civil society consultations
and subsequent discussions and workshops involving civil society stakeholders, government officials,
and development partners to meet the requirements of the government and Parliament.
1.2.14 Phase 2 – Task 3: To discuss the appropriate transparent regulatory reform model in long-range terms,
this included the following issues:
1.2.15 The purpose of the law, i.e., to govern and establish a framework for the supply of electric power; and
the principles of the law, including operations in the electricity industry and activities of Permits in the
provision of electricity services; the establishment of favourable conditions for investments in, and
commercial operation of, the electric power industry; regulation of the supply of electric power;
promotion of the rights of consumers to receive reliable and adequate power services at reasonable
cost; establishment of competition; the granting of rights and obligations; the penalizing of suppliers
and consumers of electricity, the public, and land owners in relation to electricity and supply facilities;
establishment of the ERC; establishment of a rural electrification agency of Myanmar, if needed, or to
suggest other appropriate structures to promote rural electrification and regulate third party access to
the transmission network; contractual arrangements between the government and state-owned
enterprises or provincial bodies; environmental and social considerations; and the use of land.
1.2.16 The framework for electric power supply and services, including the designation of an authority for
policy making; the use of primary energy sources; the regulatory responsibilities of the ERC; the
operational responsibilities of the MOEP (generation), the Yangon Electricity Supply Board, the
Electricity Supply Enterprise, and the Myanmar Electricity Transmission Enterprise, and any permitted
independent power producer; the overall basis for power conservation; and policy and regulation of
the supply of electric power services throughout Myanmar.
1.2.17 Institutional arrangements necessary for undertaking electricity operations and the roles and
responsibilities between the central government and provincial and local authorities as applicable.
1.2.18 Institutional arrangements for the establishment of the ERC as an independent regulatory agency, with
transparency (public disclosure requirements); public participation (in regulatory decision making);
accountability (to Parliament and through reports); and credibility, legitimacy, and integrity. The ERC
was to have rights and obligations to regulate access to electricity the service quality of electricity
providers; transmission tariffs; mechanisms for electricity pricing decisions; licensing, including the
issue, revision, revocation, or denial of Permits; accounting and reporting; efficiency; financial
performance; investment and maintenance; equity (affordability, access, and quality); environmental
sustainability, and was to include as required any renewable energy issues; and market composition
and competition.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 13
1.2.19 Third-party access to the electricity transmission network and principles for permitting private sector
participation in electricity generation.
1.2.20 Phase 3: Phase 3 covered the drafting of implementing guidelines including the proposed location,
staffing, and budget, as well as regulations for the institutional arrangements necessary for the
establishment of the ERA. Phase 3 was to commence after the draft rural electrification law had been
completed and preliminary requirements for establishing the ERC had been identified.
1.2.21 The implementing guidelines and regulations were to include a tariff-setting formula and tariff structure
for different categories of consumers; procedures for granting and issuance of Permits, conditions for
the granting and removal of Permits; the management of grid codes; the rights and obligations of
electricity providers and users; consumer complaints; theft and illegal connections; connections and
disconnections; safety and technical standards; competition in generation; renewable energy and
demand and supply-side management for utility operators; requirements for major electrical work,
including maintenance; licensing of electricians, including the establishment of offenses and penalties;
rights to access generators and end-use s p ope t ; t a spa e a d dis losu e sta da ds; a d othe matters relevant to the Electricity Act 1948.
1.3 Work Effort and Product
1.3.1 A total of 26 person-months of consultancy inputs were envisaged to complete Phases 1 and 2 of this
project, comprising of 13 person-months of international consultant inputs and 13 person-months of
national consultant inputs. The work scope, schedule and program implemented by the DFDL
Consulting Team followed the work program set forth in the original tender proposal and memorialized
in the TOR with two exceptions.
1.3.2 Expedited Efforts on New Electricity Law: At the time the DFDL bid proposal was submitted to ADB, it
was projected that at least three to six months would be required for the DFDL Consulting Team to
participate meaningfully in the development of the new Electricity Law. However, by the time the DFDL
Team commenced performance of this project on 3 March 2014, a draft of the new Electricity Law had
already been prepared and submitted to Parliament. In fact, MOEP management thought that
enactment of the new Electricity Law was imminent and would take place within the next few weeks.
1.3.3 Gi e the ad a ed state of the Pa lia e t s o side atio of the d aft Ele t i it La , the ADB a d the Myanmar Ministry of Electric Power (MOEP) decided that the work on identifying the deficiencies
of the draft Electricity Law should be given the highest priority with suggested revisions thereto to be
completed within one month from project commencement. The DFDL Consulting Team provided its
comments and made a presentation on the major deficiencies of the draft Electricity Law to the MOEP
and ADB at the kick-off meeting for this project held on 17 March 2014. In October 2014 the new
Electricity Law was enacted, and was virtually identical to the draft Electricity Law that the DFDL
Consulting Team had commented upon the preceding March.
1.3.4 ADB determined that the DFDL Co sulti g Tea s performance of work related to the draft Electricity
Law as set forth in Phase 1-Task 1 and Phase 2-Task 3 of the TOR was satisfactorily completed upon the
enactment of the new Electricity Law. The new Electricity Law, as enacted, is attached hereto as
Appendix B.
1.3.4 Impediments to Efforts on Rural Electrification: DFDL s effo ts o the ‘u al Ele t ifi atio La were
originally expected to start in June 2014 with recommendations as to content of new law and subject
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 14
matter of its implementing regulations to be prepared by the end of September 2014. However,
performance of this task was handicapped by the low priority placed on this task by the MOEP and the
failure of the Government to satisfy its commitment made in November 2014 to designate a
counterpart within the Government to work with the DFDL Consulting Team.
1.3.5 Despite this context, the DFDL Consulting Team prepared and delivered to MOEP in February 2015 a
memorandum setting forth the DFDL recommendations for the content of the new Rural Electrification
Law and a draft of the new law. The ADB shortly thereafter concluded that drafting the implementing
regulations for a new Rural Electrification Law was not practical since the MOEP and the Government
had not decided on the substance of the new law.
1.3.6 Due to the foregoing factors, the ADB in late February 2015 deemed DFDL performance of work related
to rural electrification as set forth in the TOR (Phase 1-Task 2) and Phase 2-Task 2) to have been
satisfactorily completed. Nonetheless, to address the questions and comments from the ADB received
by the DFDL Consulting Team in September 2015, the foregoing work product was revised as of October
2015 and is attached hereto as Appendix C.
1.3.7 Despite the foregoing tasks having been deemed complete by the ADB, to reignite interest in the rural
electrification efforts of the DFDL Consulting Team and the draft Rural Electrification Law, it was
suggested by the ADB that a Rural Electrification Workshop be held for the relevant government
ministries and other stakeholders. MOEP considered the timing of the workshop, planned for 25
February 2016, to be inappropriate due to the then transition phase from the old to the new
government. The workshop was deferred.
1.3.8 First Contract Extension: Due to unforeseen delays in scheduling meetings with and receiving required
approvals from MOEP regarding the Electricity Rules, there was not enough time during the original 12
month contract term to complete work on the Electricity Rules. In addition, the MOEP focus on Phase
3 efforts to prepare the regulations required to establish an effective regulatory framework for the
Myanmar power sector was indeed initiated as the original term of this Project was drawing to a close
in March 2015.
1.3.9 After the MOEP, ADB and the DFDL Consulting Team reached agreement as to the need to prioritize
the preparation of certain key regulations, the Director General (DG) of the Department of Electric
Power (DEP) requested the ADB contract with DFDL to be extended until 30 September 2015 to assist
the MOEP in finalizing the Electricity Rules, and in ensuring that the preparation of the key regulations
is completed.
1.3.10 Work on the Electricity Rules was completed in July 2015 and submitted in late November 2015 for
review and approval by the Parliament. The Electricity Rules as submitted to Parliament in November
2015 are attached hereto as Appendix D.
1.3.11 Second Contract Extension: The contract term was extended for an additional five months until 28
February 2016 to ensure the completion of all work, including key regulations, by 31 December 2015
and the completion of the rural electrification workshop by 28 February 2016.
1.3.12 Items 1-8 of Appendix E set forth the remainder of the work products required by the TOR, which include
the six key regulations addressing performance of the most important regulatory tasks that the Steering
Committee has reviewed and found acceptable (Items 1-6), and the two further regulations whose
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 15
preparation was requested by the Steering Committee but subsequently deemed not of immediate
interest (Items 7-8).
1.4 References, Definitions and Capitalized Terms
1.4.1 This report is made with reference to the various deliverables, including memorandum and draft rules
and regulations, which were produced by the DFDL Consulting Team in its performance of the Project.
Copies of the relevant key deliverables are attached as appendixes hereto.
1.4.2 Unless otherwise specifically defined in this report, capitalized terms shall have the meaning ascribed
thereto in the deliverable with reference to which the relevant sections of this report are made.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 16
Chapter 2
Preparation of New Electricity Law (Phase 1 – Tasks 1 & 2)
2.1 Initial Assessment
2.1.1 As oted a o e, due to the ad a ed state of the Pa lia e t s o side atio of the d aft Ele t i it Law, the DFDL Consulting Team was directed by the ADB and MOEP to give top priority to identifying
the deficiencies of the draft Electricity Law and to recommend revisions thereto. The DFDL Consulting
Team was given one month to complete this task. Initially, the proposal submitted by the DFDL
Consulting Team in relation to the performance of the Project expected that three to six months would
be needed to develop consensus as to the content of the new rules and regulations by which (i) the
new Electricity Law would be implemented; (ii) the Electricity Regulatory Commission would be
established, and (iii) the shortcomings in the draft Electricity Law warranting redress.
2.1.2 To evaluate the strength and weaknesses of an electricity law, it is important to consider the subject
law from several perspectives. First, the subject law should be evaluated for consistency with the
Go e e t s poli o je ti es ega di g further power sector reforms. Second, the subject law should
be reviewed to determine whether it provides the legal basis for the intended power sector reforms.
Third, the subject law needs to be reviewed to determine whether it establishes a regulatory framework
and a regulatory institution that are consistent with international best practices.
2.1.3 Importantly, the DFDL Consulting Team had to perform their first assessment of the draft Electricity
Law before being able to access, review and digest the written materials on the Myanmar power sector
and the status of power sector reforms referenced in the TOR. As a result, the draft of the new law was
unable to be evaluated for consistency with government power sector policies and its provision of the
legal bases for further power sector reforms. The initial assessment of the draft Electricity Law
therefore focused exclusively on whether the legal and regulatory framework to be established by the
draft law satisfied i te atio al est p a ti es.
2.1.4 International Best Practices: Regulation and regulatory institutions are generally viewed as those
features of regulatory regimes which promote:
2.1.5 Transparency. Transparency refers to regulatory features that enable regulated entities, consumers
and the general public to observe the processes and procedures by which regulatory decisions are made
and understand the basis for the regulatory actions taken.
2.1.6 Regulatory Independence. Regulatory independence means that responsibility for regulating the power
sector is given to a government institution with technical capabilities that is not a political institution or
part thereof, and is otherwise insulated from political directives and pressures.
2.1.7 Comprehensive Scope. The scope of the regulation must be sufficiently broad so that the regulatory
institution is able to protect against monopolistic abuses by those power sector entities with captive
customers, such as the national transmission entity, distribution entities and retail power suppliers.
Such abuse can arise in a variety of forms, including setting prices above competitive levels, reducing
costs by reducing the quality of maintenance and on-site inventory of spare parts, or by means of
engagement in non-core businesses with losses being passed through to consumers. The regulatory
institution must have the tools to protect against abuse in whatever form it takes.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 17
2.1.8 Predictability. Predictability means that power sector participants, whose interests can be affected by
regulation, are able to predict the results of regulatory actions and decisions with reasonable certainty.
Such predictability is generally accepted as a prerequisite for obtaining meaningful private sector
participation in power sectors. Absent predictability, the risk of regulatory uncertainty may impede
private sector investment.
2.1.9 Accountability. The fact that regulatory institutions should be independent does not mean that they
are not accountable for their regulatory actions and decisions. Such accountability provides power
sector stakeholders with confidence in the quality of regulatory decisions.
2.1.10 Globally, it is now commonly accepted among power sector entities, governments and international
bilateral and multilateral organizations that regulatory frameworks that include the foregoing
characteristics operate more effectively and with greater private sector confidence and public support.1
2.2 Major Identified Shortcomings
2.2.1 Applying the forgoing, the DFDL Consulting Team identified major failures of the draft Electricity Law to
conform to international best practices. The DFDL Consulting Team summarized these deficiencies in
an annotated version of the draft Electricity Law the D aft with its comments thereon set forth in a
cover memorandum. See Items 1 and 2 of Appendix F. Most notably:
2.2.2 Misallocation of Regulatory Responsibilities and Policy Formulation. The Draft contradicts international
best practices by assigning all regulatory tasks and responsibilities to MOEP and not the regulatory
authority. Thus, regulation is to be performed by an institution that is not independent and is subject
to political objectives, pressures and directives.
2.2.3 Insufficient Scope of Regulatory Authority. The Draft only expressly authorizes the MOEP to perform
two key regulatory tasks: permitting (licensing) of power sector entities to participate in the Myanmar
power sector and the determination of power sector tariffs. However, these two regulatory tasks are
not sufficiently comprehensive to provide the MOEP all of the regulatory tools required to prevent all
forms of potential monopolistic abuse in the power sector.
2.2.4 Overly Broad Breadth of Regulation. Electricity Related Business is defined very broadly in the Draft
and could result in power sector regulation being extended to virtually all persons whose business
involves some element of the electric power industry. As defined, power sector regulation would apply
to businesses that provide products and/or services which are not monopolistic in nature, including
companies which perform feasibility studies, sub-contractors that perform EPC related services, and
those companies that design and manufacture electrical equipment used to generate, transmit and/or
distribute electric power.
2.2.5 The wide breadth of power sector regulation that will result from the broad definition of Electricity
Related Business is not consistent with the international best practice of limiting power sector
regulation to businesses that are monopolistic (transmission and distribution) or operate within non-
competitive markets (generation). Companies that are not monopolistic in nature or which otherwise
operate within a competitive environment should not be subject to such regulation.
1 “ee Best P a ti es Guide: I ple e ti g Po e “e to ‘efo pu lished the I stitute of I te atio al Edu atio a d the Regulatory Assistance Project on behalf of the US Agency for International Development (2000).
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 18
2.2.6 No Requirements Regarding Regulatory Process and Procedures. Transparency of regulation may be
limited by the failure of the Draft to address the processes and procedures by which regulatory actions
and decisions are taken by the MOEP and the Electricity Regulatory Commission (ERC).
2.2.7 Insufficient Specification of Standards and Criteria. To promote transparency, predictability and
accountability most legal and regulatory regimes set forth pre-established and well-publicized
standards that govern important regulatory decisions and actions. The transparency, predictability and
accountability of the regulatory regime for Myanmar will be undermined by the failure of the new
Electricity Law to include such standards. The one exception to this is the standard set forth for tariff
determinations in Section 3(f) of the Draft, which requires tariffs to be consistent with the modern age.
2.2.8 Inadequate Details Regarding Permitting. Clause 16 and the remaining clauses thereafter of the Draft
do not set forth any licensing standards, requirements or processes by which permitting decisions are
to be made. Similarly Clause 17 of the draft Electricity Law does not set forth any factors to be taken
into account when determining the length of the permit terms for different types of electric power
services and other electricity-related works.
2.2.9 Potentially Insufficient Authority to Regulate Power Tariffs. The efe e e to the o su e in Clause
34 of the Draft is problematic in that it may too narrowly limit the types of tariffs that are subject to
MOEP regulation. An Electric Power Consumer is defined by the Draft as, a person, who obtains and
consumes e lectr ic power in accordance with the existing laws, hi h is more commonly defined
globally as a retail consumer. By inserting this term in this provision, the authority to regulate tariffs
under the Draft would appear to be limited to the tariffs charged only to retail customers.
2.2.10 Yet there are other monopolistic services for which tariffs will require regulation; including power sales
from generation plants not made under competitive circumstances, transmission and interconnection
services, bulk power sales to the distribution entities, and, once retail competition becomes realistic,
distribution wire services. The legal and regulatory framework to be implemented for the Myanmar
power sector should include a mechanism by which MOEP is able to regulate and revise the tariffs for
all monopolistic electric power service.
2.2.11 Absence of Requirements Regarding Revisions to Power Tariffs. Clauses 34 and 35 of the draft Electricity
Law provide for revisions to power tariffs. These provisions are appropriate because tariffs for
monopolistic electric power services must evolve to reflect changes in the costs of providing such
services. One of the hallmarks of a successful regulatory framework is a process and procedures for
revising tariffs that provide power sector entities, electricity consumers, the financial community and
the general public confidence that revisions to tariffs will be made on a principled basis by means of a
transparent and predictable process for which the institution regulating tariffs is accountable. However,
the draft Electricity Law does not set forth any details or requirements regarding the revision of tariffs.
The requirements, process and procedures by which power tariffs are to be revised are not addressed
by the Draft.
2.2.12 Consistency of Regional, State and Local Tariffs with MOEP Regulated Tariffs. Clause 35 of the draft
Electricity Law authorizes, through coordination with the MOEP, Region and State governments,
Leading Body of Self-Administered Divisions, and Self-Administered Zones to prescribe the electricity
rates for power generation and distribution in their respective regions under their own arrangements
for regional electric power systems. This provision gives these governmental institutions the ability to
establish tariffs for electric power generation and distribution that are specific to their respective
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 19
regions. This grant of authority suggests that these governmental institutions can establish tariffs that
are different from and inconsistent with the electricity rates for consumers that are currently uniformly
applied across Myanmar. The draft Electricity Law does not address how the coordination of tariff
determinations is to be achieved.
2.2.13 Limited Details on Formation and Operation of Regulatory Institution. The aspiration to transparency
and predictability of the regulatory regime for Myanmar will be undermined by the failure of the Draft
to set forth key institutional arrangements required to establish and manage the operations of
regulatory institutions, which include the qualification for and appointment of regulators, processes
and procedures for reaching regulatory decisions, and the procedures for handling different types of
regulatory filings.
2.2.14 Failure to Address Private Party Rights to Acquire Land. Clause 10 of the draft Electricity Law authorizes
government institutions to acquire land and to construct and extend transmission and distribution
facilities. However, Clause 10 and the rest of the draft Electricity Law does not address how privately
owned companies are to acquire land required for power projects or to construct and extend
transmission and distribution facilities which, notwithstanding intended private ownership, are for the
benefit of the public.
2.2.15 This is a significant discrepancy in the treatment of government institutions and the private sector that
could become problematic now that the private sector has been permitted to invest in generation,
transmission and distribution facilities.
2.2.16 Absence of Appellate Process and Forum. The Draft is weak on measures to hold regulatory institutions
accountable for regulatory actions and decisions. Accountability is most effective by means of judicial
appeals or other similar processes. The provision for appeals in Chapter 15 of the draft Electricity Law
is limited to appeals of decisions regarding payment of damages and compensation under Chapter 14.
The draft Electricity Law does not provide for appeals against other regulatory decisions and actions to
be taken by the MOEP and the ERC.
2.2.17 The Draft does require regulatory actions and decisions of the MOEP to be submitted to the Union
Government for approval. The need to obtain such approval and the latitude of the Union Government
to reject actions and decisions taken by the MOEP can be characterized as a form of appeal that ensures
the accountability of the MOEP. However, this arrangement is not sufficient because such reviews of
MOEP regulatory decisions and actions are taken by the Union Government (the Cabinet), which is a
political institution that is highly likely to review regulatory decisions and actions based upon political
objectives and pressures.
2.3 Reactions to Identified Shortcomings
2.3.1 MOEP: The annotation and memorandum on the deficiencies of the draft Electricity Law were delivered
and presented to the MOEP and ADB at the kick-off meeting for this Project held on 17 March 2014 in
the MOEP offices. Although the Deputy Minister of MOEP appeared to be sympathetic to the need to
address these deficiencies through revisions to the draft law, we understand that it was ultimately
difficult for the MOEP to propose any significant revisions to the draft law to Parliament due to the
imminence of its enactment.
2.3.2 The Deputy Minister of the MOEP observed that the only way to make changes to the draft law at this
late date would be for the ADB and the other donor organizations to talk directly to members of
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 20
Parliament to explain why the changes were needed, and the consequences likely to result if the draft
Electricity Law is not revised.
2.3.3 ADB: The DFDL Consulting Team presented the results of its analysis of the draft Electricity Law to the
meeting of the Electric Power Sector Working Group (consisting of representatives of ADB, the World
Bank, IFC, and JICA) held at the MOEP on 19 March 2014. The analysis of the draft Electricity Law
commanded significant attention among the donor organizations in attendance.
2.3.4 As a result of this attention, Mr. Chai-nai Chong from the ADB then requested that Mr. Fitzgibbons and
Mr. David Butcher, another ADB-provided consultant for MOEP, prepare a presentation for key
members of the Parliament regarding necessary revisions to the draft Electricity Law. It was agreed that
only the most necessary revisions would be proposed to Parliament. The Parliament presentation was
provided to the MOEP and ADB on 22 March 2014. A copy is included herein as Item 3 of Appendix F.
2.3.5 IFC: Mr. Fitzgibbons and Ms. Thida Aye met with representatives of the IFC to obtain the views of its
representatives on the draft Electricity Law. The IFC representatives concluded that the draft Electricity
Law contained significant deficiencies and consideration was required of the need for revisions.
2.3.6 The deficiencies of greatest concern to the IFC included: (1) the specification of a principle for tariff
determinations that is difficult to understand and with little bearing on cost recovery and power sector investments; (2) the failure to address the appropriate circumstances for suspension or revocation of
power sector permits; (3) the absence of any details as to the service obligations of the Yangon
Electricity Supply Corporation (YESC) and its rights to procure power from the Myanma Electric Power
Enterprise (MEPE) and other power sources; (4) the failure to address revisions to power sector
Permits; and (5) the lack of an appeal process by which regulatory decisions could be challenged.
2.4 Review of Subsequent Drafts of New Electricity Law
2.4.1 The DFDL Team translated, reviewed, and commented upon two further drafts of the new Electricity
Law before it was ultimately enacted in October 2014. See Items 4-6 of Appendix F. A memorandum
summarizing the deficiencies of the two additional drafts was delivered to the MOEP and ADB on 19
September. See Item 7 of Appendix F. Both drafts were substantively virtually identical to the draft first
reviewed by the DFDL Consulting Team in March 2014.
2.4.2 Ultimately, the deficiencies in the Draft that were first identified in March 2014 were carried forward
into subsequent drafts and into the new Electricity Law as finally adopted by the Parliament.
2.5 Analysis and Assessment of New Electricity Law
2.5.1 The enactment of the Electricity Law on 24 October 2014 the Ne Ele t i it La was a significant
achievement given the lack of local experience and familiarity with economic regulation and regulatory
institutions. The new Electricity Law is a big step towards the establishment of an effective legal and
regulatory framework for the Myanmar power sector.
2.5.2 Notable Advances of New Electricity Law:
The DFDL Consulting Team identified the following key advances in the New Electricity Law:
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 21
a. Acknowledgement of the importance of regulation by its mandate to establish the Electricity
Regulatory Commission (ERC);
b. Sections 8(c) authorizes the MOEP, Region and State governments to regulate the permitting of
electricity related businesses and tariff determinations;
c. Section 8 also provides the legal basis for the corporatization and privatization of government
power sector enterprises, such as the Electricity Supply Enterprise (ESE) and the Myanma Electric
Power Enterprise (MEPE). With the approval of the Union Government, Sections 8(c) and (e)
provide for the conversion of government enterprises first into electric power supply boards,
thereafter into electric power supply corporations, and finally converted into a public-owned
corporation to operate commercially.
d. Clarifies the jurisdictional boundaries between the MOEP, Region and State governments, with
Region and State governments responsible for the regulation of power projects no larger than 30
MW and not connected to the national grid;
e. Authorizes the MOEP to establish standards for power sector entities;
f. Establishes a permitting regime to control the entry and exit of participants in the Myanmar power
sector;
g. Sections 12, 13 and 14 authorize the MOEP and other permitting institutions to supervise, issue and
revoke permits to local and foreign investors that desire to engage in Electricity Related Works;
h. Section 16(a) requires the MOEP and other government institutions, in their deliberations as to
whether or not to issue a Permit, to examine applicants based upon their performance and financial
capabilities, and the prospects for the issuance of Permits to foster competition;
i. Section 22(a) requires any Persons issued with Permits to take responsibility for damages and
injuries which, according to the law, are a result of their own negligence;
j. Section 38 renders the MOEP decisions final and conclusive as to the results of inspections for
compliance with electrical norms;
k. Section 41 grants MOEP the right, with the consent of the Union Government, to prescribe
electricity rates for consumers connected to national grid and for Region or State governments to
prescribe the electricity rates for electric power generation and distribution in their respective
regions not connected to the national grid;
l. Section 50 requires a Person issued with a Permit to not sell, mortgage, lease, exchange, or use any
other method to transfer the Permit or the whole or part of Energy Related Works for which the
Permit was issued without the permission of MOEP or other relevant permitting institutions; and
m. The MOEP has the right to take a number of administrative actions if the Permit holder breaches
the conditions contained in the Permit or any order or directive issued by the relevant ministry or
is convicted of having committed any offence under this law.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 22
2.5.3 Limited Content of the New Electricity Law:
2.5.4 Generally, although the content of the new Electricity Law is more limited than is usual for electricity
laws, the Electricity Law nonetheless establishes a solid and workable foundation able to support the
issuance and application of rules and regulation that will provide context otherwise missing from the
Electricity Law itself.
2.5.5 As long as the content of the Electricity Rules are consistent with the spirit of, and not contrary to, the
substance of the new Electricity Law, and is ot i o siste t ith the go e e t s po e se to reform objectives, adding regulatory requirements and content in the Electricity Rules and
implementing regulation should not raise any objections.
2.5.6 The limited content and broad breadth of the Electricity Law provides certain advantages in using the
Electricity Rules and implementing regulations to add to the legal and regulatory framework for the
Myanmar power sector omitted from the Electricity Law, and to address other shortcomings as
identified by the DFDL Consulting Team in the rounds of review and comments on the three drafts of
the Electricity Law.
2.5.7 The limited content of the Electricity Law reduces the probability that the content and regulatory
features being added by the Electricity Rules are contrary to the substance of the new Electricity Law.
Also, the breadth of the Electricity Law will likely ensure that any content or regulatory features being
added to the Electrical Rules will be related in some fashion to topics included within the scope of
matters relevant to the Electricity Law.
2.5.8 Remaining Deficiencies in New Electricity Law:
2.5.9 The DFDL Consulting Team has determined that all of the deficiencies of the Electricity Law identified
in 2014 were able to be remedied through the Electricity Rules and implementing regulations able to
be issued by the MOEP with two notable exceptions.
2.5.10 The first exception is the assignment by Section 3 of the Electricity Law of all regulatory tasks to MOEP
and not the ERC. Although the problems with this misallocation of regulatory responsibilities may be
able to be mitigated by means of adequate drafting of the Electricity Rules, such responsibilities are
unable to be transferred to the ERC until such time as the Electricity Law is either repealed or revised
to permit such a transfer.
2.5.11 The absence of a transfer mechanism is notable given that the explanation that was most often
articulated by the MOEP management in support of the misallocation of regulatory responsibilities was
that the ERC would be unable to properly perform such regulatory tasks in a timely fashion due to lack
of required expertise, experience and resources in general. Although the foregoing explanation is a
reflection of a practical current reality, the eventual accrual of relevant regulatory experience and
expertise by the ERC should result in the regulatory responsibilities shifting from MOEP to the ERC.
Nonetheless, the Electricity Law does not allow such a transfer.
2.5.12 The second exception is the requirement for MOEP regulatory actions and decisions to be submitted
for approval by the Union Government. Although problems may be able to be mitigated if the Union
Government is willing to refrain from using regulation to pursue political objectives and using political
pressure to influence regulatory decisions, appeals to the Union Government remain the sole avenue
for redress unless the Electricity Law is revised.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 23
Chapter 3
Electricity Rules to Implement New Electricity Law and to Establish
Electricity Regulatory Commission
(Phase 2 - Task 1)
3.1 Initial Assessment
3.1.1 Phase 2 of the TOR required the DFDL Consulting Team to assist the MOEP to prepare the rules to
implement the New Electricity Law and to establish the Electricity Regulatory Commission. However,
the New Electricity Law provided little to no guidance on the desired structure of the Myanmar power
sector or the desired design of the regulatory framework, as set forth in the TOR of this project, other
than mandating the establishment of a regulatory commission with no regulatory responsibilities,
requiring the permitting of power sector participation, and the assignment of regulatory tasks including
permitting and tariff determinations to MOEP.
3.1.2 The draft MOEP Action Plan provided some additional, yet still insufficient, details as to those power
sector reforms intended to be implemented. The outputs of the draft MOEP Action Plan included
implementation of independent power producer (IPP) schemes using methods similar to neighboring
countries (i.e., competitive bidding); preparation of the Energy Development Plan and Energy Security
Policy; efficient and environmentally friendly use of energy resources; p es i ing p i i g structure
(tariffs) for electricity, petroleum products and metals; and the preparation of transmission and
distribution codes.
3.2 Defining the Content of Electricity Rules
3.2.1 A consensus therefore was needed as to the content for the Electricity Rules intended to implement
the New Electricity Law and to better establish the foundation for an effective regulatory regime for
the Myanmar power sector. Consensus was forged based upon: (i) an identification of the institutional
and regulatory features required to support expected power sector reforms; (ii) an endorsement of
specific power sector reforms; (iii) the acceptance of regulatory features based upon international best
practices to redress deficiencies in the Electricity Law as previously identified; and (iv) requirements to
govern the establishment the ERC.
3.2.2 To obtain the guidance needed in order to identify the regulations and institutional arrangements
required to implement the future Electricity Law and establish the ERC, the DFDL Consulting Team first
reviewed relevant literature, reports and assessments prepared by or for MOEP, the ADB, the World
Bank, the IFC and other international institutions. By obtaining a better understanding of the issues
facing the Myanmar power sector, the potential content for the Electricity Rules can be identified for
discussion with the Steering Committee, by focusing on the legal support, institutional arrangements
and regulatory framework needed to support implementation of power sector reforms.
3.2.3 The results of this review and analysis are set forth in a memoranda entitled Characteristics of and
Problems Facing the Myanmar Power Sector Ap il , a d Po e “e to ‘efo s a d ‘e uisite La s, ‘egulatio s a d I stitutio al A a ge e ts Ma . See Items 8 and 9 of Appendix F.
3.2.4 Annex A of Memorandum "Power Sector Reforms and Requisite Laws, Regulations and Institutional
Arrangements identified several problems for the Myanmar power sector that warrant governmental
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 24
attention. Annex B of this Memorandum identified the specific reforms that the Myanmar government
has endorsed or which have been often employed internationally to address the comparable challenges
and problems. Annex C of this Memorandum identified the regulations and institutional arrangements
required to support the reforms identified in Annex B.
3.2.5 In regards to the allocation of power sector responsibilities across governmental institutions, interviews
were conducted with the Ministry of Mines; Ministry of Finance; Ministry of Science and Technology;
Ministry of Livestock, Fisheries and Rural Development; Ministry of Environment, Conservation and
Forestry; Department of Electric Power; ESE; and private subcontractors of ESE in Mandalay. Minutes
of these interviews are set forth in Item 10 of Appendix F.
3.2.6 The foregoing information was presented to the Steering Committee to focus discussion on the
institutional and regulatory features required to implement the power sector reforms that global
experience suggests are highly relevant for Myanmar. The specific reforms together with the
institutional and regulatory features employed internationally to support such reforms, and our
recommendations to the Steering Committee are set forth in the following Table:
Table 3.2 Common International Reforms and Supportive Regulatory Arrangements
Problems
Common
International
Reforms
Support for Institutional
and Regulatory
Arrangements
DFDL Recommendation
Government
managed
Vertically
Integrated
Power Sector
Separate
management,
policy
formation, and
regulation.
Restructure so
generation,
transmission,
and
distribution
services are
performed by
separate
entities.
Implement
reforms to
foster
competitive
markets.
No strategic plan for
restructuring the power
sector set forth by the
Union Government.
The Electricity Rules should establish a
permitting program and process that will
reinforce and support the structural changes
already being implemented, but which can
implement more dramatic structural reforms if
desired.
No need to address more aggressive structural
reforms and the creation of competitive
markets.
Insufficient
Revenue to
Support
Power Sector
Require cost
reflective
tariffs
Tariff regulation requiring
cost reflection, cost
recovery, and a return on
Electricity Rules to establish tariff policy
requiring tariffs to permit cost recovery and
returns on investment sufficient to finance
investments in new assets. Also must include
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 25
Problems
Common
International
Reforms
Support for Institutional
and Regulatory
Arrangements
DFDL Recommendation
investment sufficient to
finance sector.
principles and standards for tariff
determination.
Establish
transparent
and
predictable
process for
determining
and revising
tariffs.
Well defined regulatory
process for tariff
determinations that
provides for public
participation.
Electricity Rules should establish transparent
and predictable process for review, approval
and revisions to power sector tariffs.
Establish
process that
provides relief
quickly.
Allow tariff increases
requested to become
effective subject to
refund.
Electricity Rules or tariff regulations should
permit proposed tariff increase to become
effective subject to refund.
Permit market
based rates
when
determined
competitively.
Permit and/or require use
of competitive tenders for
new generation.
Establish competitive
generation, wholesale,
and retail power markets.
Allow or require use of competitive tenders
to acquire electric power from new
generation.
No need to address creation of competitive
wholesale and retail markets, but framework
must be flexible for further reforms in future.
Diversion of
Domestic
Power Supply
for Export
Require
government
approval to
export electric
power or
natural gas
abroad.
New Electricity Law or
Union Regulations should:
(1). Designate MOE,
MOEP or ERC as
responsible to review and
approve power exports;
(2). State the applied
criteria to approve power
exports (e.g. consistent
with NEP and National
Power Supply Plan).
Pre-specified and publicly available criteria to
approve power exports as authorized by MoE,
MOEP, or ERC.
Export applications should be part of
formulating NEP or National Power Supply
Plan or considered individually at highest level.
Approvals of individual exports should
require certification that export is consistent
with NEP or National Power Supply Plan.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 26
Problems
Common
International
Reforms
Support for Institutional
and Regulatory
Arrangements
DFDL Recommendation
Inefficient
and Non-
Commercial
Management
of Power
Sector
Corporatization
and
privatization.
Separate utility activities
performed by
government into separate
legal entities charged with
operating on a
commercial basis.
Ownership of such
entities should be
exercised by MoF.
Management of
operations to be
separated and insulated
from political institution.
Imposition of
requirements to foster
commercial management;
such as a Board of
Directors and financial
audits.
Eventual privatization in
whole or in part.
Electricity Law provides legal basis for
converting Ministry departments into power
supply boards and then to corporations able
to be privatized.
Electricity Rules to assign MoF to exercise
government ownership interests in such
entities.
All MOEP departments responsible for power
sector operations should be corporatized.
Electricity Rules to endorse managerial
compensation based on commercial
performance of power sector enterprises.
Inefficient
Operations
Formulate,
apply, and
enforce
performance
standards and
operating
requirements
in accordance
with
international
best practices.
Regulatory institution to
Impose performance and
technical standards
Electricity Rules to authorize ERC to establish
and enforce performance and technical
standards.
Electricity Rules to establish process and
procedures for (1) filing of service complaints
with the ERC, and (2) ERC investigations into
violations of legal and regulatory
requirements.
Electricity Rules to authorize MOEP to impose
sanctions for violations
Sub-optimal
Mix and
Amount of
Generation
Resource
Require
forecasting of
load growth
and least-cost
power
procurement
and resource
acquisition.
Power sector entities to
be required to engage in
least-cost power supply
planning consistent with
international best
practices.
Union or Ministry
Regulations to set
requirements applicable
to least-cost power
Power sector entities to be required by
Electricity Rules to prepare forecasts and least
cost resource investment plans on annual and
multi-year basis for MOEP approval.
Such plans to set out the needed power
supply, investments, and other major
expenditures required to satisfy service
obligations in Permits.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 27
Problems
Common
International
Reforms
Support for Institutional
and Regulatory
Arrangements
DFDL Recommendation
supply planning and to
submit results to the
ministry.
MOEP to evaluate whether plans are
consistent with National Power Supply Plan
and NEP.
Reticence of
private sector
investment
due to
concerns
Issue policies
on IPPs and
private sector
participation.
Government to set IPP
policy that addresses
private sector concerns
with power sector
investments; particularly
in permitted security
packages, royalties, and
guarantees.
No need for Electricity Rules to address
private sector concerns. Government has
authority to address such concerns, and they
are beyond the authority of MOEP.
Electricity Rules can permit/require use of
competitive tenders to procure power from
private generation projects. Setting forth
requirements for competitive tenders with
models will expand private participation.
Cumbersome
and confusing
Project
approval
Process
Simplify
project
approvals and
negotiations,
clarify legal
uncertainties,
and reduce red
tape
One-Stop shop;
streamline approval
process, endorse security
arrangements, and
confirm corporatized
entities are government
liabilities.
No need for the Electricity Rules to address
project approval process. Government has
authority to address such concerns and most
beyond the authority of the MOEP.
3.3 Regulatory Features from International Best Practices
3.3.1 After obtaining an agreement from the Steering Committee on the content of the Electricity Rules, the
DFDL Consulting Team then turned its focus to obtaining a consensus on what the Electricity Rules
needed to address to establish the ERC. To prepare for this discussion and in appreciation of the forms
of regulation employed in other countries, on 20 June 2014 the DFDL Consulting Team, together with
Mr. David Butcher, an ADB consultant advising MOEP on commercial and management matters, made
a presentation to the Steering Committee on possible structures for the Myanmar power sector. See
Items 25 and 26 of Appendix F.
3.3.2 To achieve the foregoing objective, the DFDL Consulting Team focused on the power sector regulatory
institutions of five relevant regional countries. Specifically, the DFDL Consulting Team reviewed and
analyzed over eighty different features of the regulatory framework and regulatory institutions of
Cambodia, Malaysia, Pakistan, Thailand and Vietnam. The results of this review are set forth in a
memorandum entitled a Comparison of Key Features of Regional Power Sector Regulatory Institutions
dated 20 June 2014. See Item 11 of Appendix F. This memorandum compared, contrasted and made
recommendations as to the regulatory and institutional arrangements and practices drawn from the
regulatory frameworks of these five countries.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 28
International Best Practices Presentation and Consultation
3.3.3 As required by Phase 1-Task 2 of the TOR, during 2-4 August 2014 the DFDL Consulting Team gave a
presentation to the Steering Committee on the power sector legal and regulatory frameworks of the
foregoing five relevant countries, identification of the features thereof which reflect international best
practices and recommendations as to the appropriate regulatory model for Myanmar.
3.3.4 Following this presentation the DFDL Consulting Team spent three days meeting with the DG of the
Department of Electric Power (DEP) and the Steering Committee to discuss the advantages and
disadvantages of regulatory and institutional features used in other countries as recommended in the
Me o a du o the Comparison of Regional Regulatory Models and Selection of Preferred Model .
3.3.5 After extensive discussion, a consensus developed as to the desired content of the Electricity Rules
regarding the establishment of the ERC. The DFDL Consulting Team prepared and distributed to MOEP
and the Steering Committee a summary of the many features agreed upon as appropriate content of
the Electricity Rules. The Steering Committee tentatively concluded that approximately forty of the
regulatory features drawn from the international examples should be implemented in Myanmar. Most
notably:
Table 3.3 Key International Regulatory Features
Authority of
Chairman
The Notification to establish the ERC to define responsibilities of a strong Chairman.
Chairman to: (1) set agenda and schedule meetings, (2) preside over meetings with the
casting vote, (3) appoint Commission Officers and the Administrative Manager, (5)
prioritize work efforts, (6) be responsible for management and administration of
Commission, (7) prepare annual budget for consideration by ERC Members.
Staggered and
Fixed Terms
The Notification to establish fixed and 5 year staggered terms, limited to two
appointments.
Removal Removal to require: (1) factual determination of conviction of a criminal offense, (2)
mental or physical incapacity, (3) serious violation of any employment or stock
ownership restriction, and (4) abandonment of duties.
ERC Internal Structure and Procedures
Regulatory
Decisions
Electricity Rules to require all regulatory decisions to be in writing and set forth legal
and factual basis for decision.
Meetings The Notification to establish the ERC to specify: (1) quorum requirements, (2) votes
e ui ed fo affi ati e de isio s a d a tio s to e take , a d Chai a s asti g ote, (3) requirements regarding meeting notices, including public notices, and (4) whether
meetings must be open to public.
Internal
Organization
and Procedures
Electricity Rules should specify: (1) officers, (2) ERC Departments, (3) Member support
staff, and (4) minimum procedural requirements.
Regulatory Tasks
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 29
Tariffs
Tariff Principles Electricity Rules should specify pinciples required to be applied in tariff determinations.
Retail Tariffs Deviations/abandonment of uniform national retail tariffs needs to be permitted.
Permitting
Permit
Conditions
Electricity Rules to define initial, service obligations and specify minimum conditions to
be included in each type of Permit.
Issuance Electricity Rules to set forth: (1) the types of Permits able to be issued by MOEP upon
recommendation of ERC and the service obligations associated therewith, (2)
standards for issuance, denial revision, and revocation of Permits, and (3) mandatory
Permit conditions, including types of performance standards for each type of Permit.
Modifications Electricity Rules to set forth the grounds for and requirements governing MOEP/ERC
unilateral revision of Permits, including compensation payment for divested assets.
Power Procurement and Investments
Power
Procurement
and Contracts
Electricity Rules to prohibit: (1) procurement of power from new IPPs unless the result
of competitive power solicitations programs (approved by MOEP upon ERC
recommendation), and (2) recovery of power procurement cost if incurred pursuant to
power purchase agreements not approved by MOEP.
Power Imports
and Exports
Electricity Rules to require approval of MOEP for power exports and imports. MOEP to
consider: (1) the safety, reliability and stability of national electric system, and (2)
impact of proposed import or export on consumers and national electricity security.
National Power
Development
Plans
Electricity Rules to require MOEP to prepare multi-year national power development
plan for submission for the approval of the Cabinet, which shall be annually updated by
MOEP and approved by Cabinet annually.
Investment and
Power
Acquisition Plan
Electricity Rules to require national transmission and distribution power sector entities
to each prepare an annual investment and development plan for approval of MOEP.
Financing
Financing
Activity
Electricity Rules to require national transmission and distribution power sector entities
to obtain MOEP approval of major financing activity.
Service Quality
Standards
Electricity Rules to require performance standards for generation, transmission and
distribution that are to be included as conditions in Permits.
Corporate Activity
Mergers and
Corporate
Reorganization
Electricity Rules to prohibit reorganizations, mergers and major acquisition or sale of
assets or securities without prior approval of MOEP.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 30
3.3.6 Importantly, the discussions held on 2-4 August 2014 recognized that there were significant
inconsistencies between the draft Electricity Law and the content to implement the new Electricity Law
and establish the ERC on which there had been preliminarily agreement. The DFDL Consulting Team
was instructed to address these inconsistencies when drafting the Electricity Rules.
3.4 Electricity Rules Drafting Effort
3.4.1 The first complete draft of the proposed Electricity Rules reflecting the preliminary agreements reached
was delivered to the MOEP on 31 August 2014. The Myanmar translation of these draft regulations
was delivered to the MOEP on 1 September 2014. A revised memorandum summarizing the content
the draft Rules with references to the preliminary agreements reached with the DG and the Steering
Committee on the appropriate content for such rules is set forth as the Agreed Content Referenced to
Draft Regulations to Establish Electricity Regulatory Commission 4 September 2014). See Item 12 of
Appendix F.
3.4.2 Per the instruction on 3 November 2014 from Deputy Minister U Aung Than Oo (DG of DEP), U Khin
Maung Win (Deputy DG of DEP), Daw Mi Mi Khaing, Mr. Jong-Inn Kim (ADB) and Mr. Rehan Kausar
(ADB), the DFDL Consulting Team met each week with the DG and Steering Committee to conduct a
line by line review and make revisions as required to finalize the first draft of the Electricity Rules
beginning on 8 November 2014 and continuing through 16 January 2015. The summary of this meeting
on 3 November 2014 is set forth as Item 13 of Appendix F.
3.4.3 During this review period, the DFDL Consulting Team met with the DG and the Steering Committee nine
times to review and revise in detail the draft Electricity Rules. Minutes of each such work session are
attached hereto as Item 14 of Appendix F.
3.4.4 On 9-11 and 15-16 January 2015, the DFDL Consulting Team met with the DG and the Steering
Committee to finalize the draft Electricity Rules. Over these five days, the Steering Committee and the
DFDL Consulting Team reviewed the draft Electricity Rules rule by rule using the updated side-by-side
comparison (Item 15 of Appendix F) of the English and Myanmar versions of the draft Rules to address
any outstanding questions, concerns and requests for clarification.
3.4.5 On 18 January 2015, the DFDL Consulting Team delivered to the DG the finalized English version of the
draft Electricity Rules. A copy of this revised draft is attached hereto as Item 16 of Appendix F. The
Steering Committee then internally revised the Myanmar version of the Electricity Rules and submitted
the changes to the DFDL Consulting Team on 22 January 2015 the I itial Ve sio . In addition, the
DFDL Consulting Team also prepared a memorandum detailing suggested further revisions to the Initial
Version. See Item 17 of Appendix F.
3.4.6 The Initial Version of the Electricity Rules was then distributed to other Union government ministries
and institutions for their review and comment, including the Office of the Attorney General, the
Ministry of Finance, the Ministry of Energy, the Ministry of Industry, and the Ministry of Science and
Technology.
3.5 Initial Version of Draft Electricity Rules
3.5.1 The Initial Version comprehensively addresses the implementation of the new Electricity Law and the
establishment of the Electricity Regulatory Commission. The Initial Version is based largely on the
tentative conclusions reached by the DG and the Steering Committee in early August 2015 and seeks
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 31
to address key deficiencies of the new Electricity Law that were earlier identified; most notably that the
revised draft of the new Electricity Law vested all regulatory functions with the MOEP and not with the
Electricity Regulatory Commission.
3.5.2 Importantly, other than the deletion of the provisions referencing the ERC, the establishment and
organization of the ERC, and ERC involvement in regulation, all of the other provisions of the Initial
Version as discussed below were included in the final version of the Electricity Rules that have been
submitted to Parliament for approval as required for issuance.
3.6 Implementation of New Electricity Law
3.6.1 Clear Specification of Ministry Power and Functions. The Initial Version significantly expanded the
number of regulatory tasks to be performed by the MOEP far beyond the tasks assigned to the MOEP
by the new Electricity Law. In addition to permitting and tariff determinations, the MOEP will most
notably become responsible for:
a. Review and approval of forecasts and multi-year least-cost power development plans that maintain
consistency with the current national electric power development plans;
b. Review and approve investment, power procurement and resource acquisition plans based on
po e se to e tities espe ti e least cost investment and power procurement plans;
c. Review and approval of financial activities and organizational affairs to protect against such
activities and affairs adversely impacting the capabilities of power sector entities to satisfy
their respective obligations;
d. Promulgate technical and performance standards for each category of power sector entity;
e. Resolve grievances against and disputes involving permitted power sector entities;
f. Enforce legal, regulatory and contractual requirements and prescribe fines for violations of such
requirements; and
g. Propose and/or implement market rules and revise Permits as required to effect power sector
structural reforms as directed by the Union Government; subject to the payment of appropriate
compensation for any divested assets.
3.6.2 Other Ministry Responsibilities: The MOEP is also required to:
a. Develop methodologies for forecasting and least-cost planning and provide guidance to power
sector entities in this regard; and
b. Prepare multi-year national electric power development plans for submission for the approval by
the Union Government; such plans are to be based o MOEP s o least-cost planning and are to
focus on the investments required to ensure long term balance between reliable electric power
supply and electric load.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 32
3.6.3 Requirements for Written Regulatory Decisions: Regulatory actions and decisions required for the
MOEP are to be in written form and are to explain the legal and factual basis in support of the
regulatory action or decision being taken.
3.6.4 ERC Integration into Regulatory Process: The Initial Version seeks to redress the misallocation of
regulatory responsibilities and tasks to MOEP by increasing the regulatory responsibilities of the ERC
without altering the assignment of all regulatory tasks to MOEP. The Initial Version requires decisions
of the MOEP to be based upon recommendations (in the form of draft decisions) prepared and
proposed by the ERC. The MOEP may only approve, reject or revise such recommendations due to (i)
inadequate legal and/or factual justification; (ii) misstatement or omission of material facts; (iii)
misinterpretation of legal and regulatory requirements; (iv) arbitrary reasoning; or (v) otherwise being
contrary to the public interest. The processing of filings and all other work required to perform
regulatory tasks will be performed by the ERC.
3.6.5 Power Sector Permitting Regime: The Electricity Law contemplates a permitting process by which market
entry will be controlled by the MOEP, but the Electricity Law provides few of the details required to
establish a workable and effective permitting regime.
3.6.6 Mandatory Permits. The Electricity Rules prohibit persons from engaging in Electricity Related Works
without having obtained a Permit. The Electricity Rules provide clear jurisdictional boundaries between
the authority of the MOEP as a Union ministry, State and Region governments, and local governments.
3.6.7 Types of Permits. The Initial Version identifies the types of Permits that the MOEP is able to issue. For
each type of Permit able to be issued by the MOEP, the Electricity Rules (i) specify the content of Permit
applications and the eligibility requirements applicable thereto; (ii) specify permit content; (iii) define
the applicable service obligations; and (iv) vests the MOEP with the authority to revise Permits
unilaterally in order to implement power sector reforms, as directed by law or the Union Government,
provided that compensation must be paid for divested assets.
3.6.8 Eligibility. Permits are only to be issued to persons that have demonstrated their capabilities to comply
with the requirements of their respective permit. The Initial Version and the final version of the draft
Electricity Rules specified the factors to be considered by the MOEP in evaluating permit applications,
including (i) the business, engineering, managerial and technical capabilities and expertise; (ii) the
financial wherewithal of applicants; (iii) the capability of applicants to comply with permit conditions
and all applicable legal and regulatory requirements; (iv) the capability of applicants to comply with
prudent utility practices, the grid code, the distribution code, and applicable industry codes of conduct
and industry standards.
3.6.9 In both the Initial Version and the final version of the draft Electricity Rules, MOEP is authorized to deny
Permits if it concludes that the investments associated with the subject Permit application are not
justifiable in view of the needs of the power sector or where the applicant has not demonstrated
capacbility for the proposed facility or system.
3.6.10 Financial Security. The Initial Version permits the MOEP to require a bond or other form of financial
security necessary to ensure satisfaction of service obligations set forth in pursuant to this l aw and
the conditions of the Permit, including the payment of Permit fees.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 33
3.6.11 Applicable Laws. The Initial Version requires all Persons issued with a Permit to comply with applicable
Law and regulatory requirements, all applicable environmental requirements, applicable codes and
performance standards.
3.6.12 Suspension and Revocation. The Initial Version allows for MOEP to suspend and revoke Permits in order
to enforce the stated requirements. Where suspended or revoked, Permitted Persons may be required
to undertake actions to maintain continuous operations for the equipment and facilities.
3.6.13 MOEP Regulations. The Initial Version authorizes MOEP to issue regulations regarding the applications
for, issuance of, revisions and modifications to, and suspensions and revocation of Permits. These
regulations are to specify the form and content of Permit applications, filing requirements, evidentiary
support, documentation needs, and procedures specific to licensing.
3.6.14 Tariff Regulation: The Electricity Rules provide greater detail as to the processes and requirements
applicable to tariff determinations by the MOEP.
3.6.15 Filing of tariffs. Every Permitted Person shall have tariffs for its permitted power sector activity
approved by the MOEP with the consent of the Union Government. Tariffs proposed shall become
effective sixty (60) days after being filed with the ERC subject to refund of the amount by which the
tariff filed for approval exceeds the tariff approved by the Union Government.
3.6.16 Tariff Principles and Standards. The Electricity Rules require that tariffs are to be based upon the
expressly stated principles and standards, most notably:
a. Allow recovery of all costs prudently incurred to meet the demonstrated needs of their
customers;
b. Result in rate of returns on the power sector capital investments commensurated to that
earned on investments of comparable risk, and promotes investments in equipment and
facilities required for Permitted Persons to satisfy their respective service obligations;
c. Allow deviation from nationally uniform tariffs in order to, to the extent feasible, reflect the
full cost of providing electric power and other electric power related services to classes of
customers with similar service requirements;
d. Reflect the quantity of peak, average, or overall usage of electric power at different times,
seasons, time of day or year, the types of services purchased, or other similar factors; and
e. Provide reasonable transition periods to implement tariff increases in order to minimize
public opposition to such adjustments.
3.6.17 Non-Cost Based Tariffs. The Electricity Rules permit MOEP approval of non-cost based tariffs
determined by negotiations within competitive power markets or circumstances; such as tariffs
established by a bona fide competitive power solicitations approved by the MOEP.
3.6.18 Notice of General Rate Changes. Applications for tariff changes must include a comparison of the
existing tariff design and the proposed tariff design on the basis of the categories of consumers likely
to be affected by a tariff modification.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 34
3.6.19 ERC Recommendations. Electricity Rules permit the ERC to make recommendations to the MOEP
regarding tariffs. Ministry shall issue regulations regarding the applications for tariff approvals, the
review and consideration of proposed tariffs and proposed tariff methodologies. The regulation shall
specify the form and content of tariff applications, filing requirements, evidentiary support,
documentation needs, and procedures specific to tariffs.
3.6.20 Investment and Power Acquisition Programs. Electricity Rules require Permitted Person with captive
customers to prepare annually their respective investment and power acquisition programs and to file
them to obtain MOEP approval.
3.6.21 Power Purchases and Procurement. Regulations to be issued by the Ministry shall specify the
requirements for obtaining approval of power purchase agreements and competitive power solicitation
programs. Approval of power purchase agreements must be consistent with least cost procurement of
power supplies to be approved by the MOEP.
3.6.22 Prohibitions. The Initial Version prohibited Permitted Persons from (i) purchasing electric power from
new IPPs unless such purchases are the result of competitive power solicitations programs approved
by the Ministry; and (ii) recovery of power procurement costs if incurred pursuant to power purchase
agreements not approved by Ministry.
3.6.23 Financing Arrangements. Financing activities are required by the Initial Version to be made prudently
and on commercially reasonable terms and conditions.
3.6.24 Corporate Mergers and Restructuring. Prior approval of the MOEP will be required by the Initial Version
to undertake a merger or a major acquisition or sale of facilities.
3.6.25 Performance Standards. The MOEP is required by the Initial Version to prescribe performance
standards for all types of permitted power sector activities. The Initial Version sets forth the types of
performance standards required for each type of Permit. The Electricity Rules also allow MOEP to tailor
project specific standards when the subject projects are unable to meet the generic performance
standards of industry wide applications.
3.6.26 Safety Inspections and Registration. Electricity Rules prohibit major electrical facilities from being
operated unless such facilities have been inspected for compliance with technical and safety
requirements by the Inspection Department of the Ministry of Industry and obtained a compliance
certificate therefrom.
3.7 Establishment of the Electricity Regulatory Commission (ERC)
3.7.1 The Initial Version also sets forth the basic elements of a regulatory framework by which the Electricity
Regulatory Commission can be established. Again, the Initial Version is based largely on the tentative
conclusions reached by the DG and the Steering Committee during the review and discussion of
international experience in early August 2015. For the most part, the DG and Steering Committee
agreed that the following design, structure and regulatory features are warranted to improve the
transparency, independence, effectiveness, predictability and accountability of the Myanmar power
sector regulation.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 35
ERC Structure:
3.7.2 The Initial Version contemplates a multi-member commission with members appointed for fixed five-
year terms that is a separate entity independent from the MOEP and charged with making its decisions
by means of majority votes taken on proposed written decisions at pre-noticed meetings open to public
observation. Decisions by the E‘C efe ed to as the Commission i the I itial Ve sio a d i this section of report) are required to be in writing and to include an explanation of legal and factual basis
for decision.
3.7.3 The Initial Version addresses the (i) location of the ERC within the Union Government; (ii) tenure,
qualifications and appointment of commission members; (iii) decision-making authority and processes,
such as quorum requirements and decisions to be taken by majority vote; (iv) requirements regarding
ERC organization, including authority of the ERC Chairman; (v) requirements to promote the autonomy
and independence of ERC; and (vi) requirements to ensure the accountability of the ERC. More
specifically:
a. Independence and Autonomy. The Initial Version mandates that the ERC shall perform its duties
and functions independent from the Ministry and free from Ministry directives and instructions.
b. Appointment. Appointments are to be made by the President. The Preisdent and the other
Members are to be eminent professionals of known integrity and competence with experience in
law, business, engineering, finance, accounting, economics and/or business management in
regards to the electric power industry of at least fifteen years for the Chairman and ten years for
other Members.
Chairman and other Members may only be removed from office by the President upon a factual
determination by appropriate factual tribunal of (i) a conviction of a criminal offense; (ii) mental or
physical incapacity; (iii) serious violation of any employment or stock ownership restriction; or (iv)
are found to have seriously neglected or abandoned his or her duties.
c. Secretariat. The Secretariat comprises the administrative and professional staff and employees,
physical plant, facilities and equipment required to support ERC activities. The Secretariat provides
professional and technical support for actions and decisions to be taken by the Commission,
including the preparation of recommendations as to regulatory actions that the Commission
proposes to be taken by the Ministry.
d. ERC Departments. The Secretariat shall be organized with departments that shall be the
espo si ilit of offi e s E‘C Offi e s appoi ted a d ho se e at the pleasu e of the Chairman, with a (i) legal department that is the responsibility of the General Counsel; (ii) an
economics department that is the responsibility of the Director General-Economic Policy; and (iii)
an engineering and technical support department that is the responsibility of the Director General-
Technical and Engineering.
e. Accounts. The Electricity Rules authorizes the ERC to open and maintain bank accounts in its own
name.
f. Budget Process. The annual budget for the activities and operating expenses of the ERC shall
prepare, for each financial year, the annual budget of its anticipated operating costs that sets forth
all of the E‘C s e pe ted e e ues a d e pe ses.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 36
g. Funding Sources. The operations and activities of the ERC shall be funded, at least initially, from (i)
grants from the Union Government in the form of funds annually authorized and appropriated by
the Parliament; and (ii) fees and fines collected from Permits by the ERC as prescribed from time to
time.
h. ERC Reports. The Initial Version requires the Commission to prepare and submit to the Union
Government a report, within a defined period following the end of its fiscal year, on the conduct if
its activities and the state of the Myanmar power sector that identifies the ownership, operation,
management, efficiency and control of electric power facilities, amount of transmission and
generation capacity, present and future demand of electricity, cost of electric power services
and other matters relating to electric power services.
3.7.4 ERC Administration, Process and Procedures:
a. Authority of Chairman. The Chairman shall (i) set the agenda and schedule of the Commission
meetings; (ii) preside over Commission meetings with a casting vote; (iii) hire the Executive
Secretary and the ERC Officers; (iv) prioritize work efforts; (v) be responsible for management and
administration of the Secretariat; and (vi) prepare the annual ERC budget for consideration and
approval by the Commission.
b. Meeting Notices. The Chairman shall provide each Member and the public at least ten days advance
written notice of the date, time and location of each meeting of the Commission, together with a list
of all matters to be considered by the Commission at each such meeting.
c. Quorum. A majority of five of the seven Commission Members shall constitute a quorum. Members
can attend meetings of the Commission in person, by phone or by proxy. Properly executed proxies
must be delivered to the Executive Secretary prior the beginning of Commission meetings.
d. Affirmative Votes. Decisions of the Commission shall be taken by a majority of the Members
present at properly convened Commission meetings. In case of a tie vote, the Chairman or the
designated presiding Member will cast the deciding vote.
e. Meeting Minutes. Minutes shall be kept of all Commission meetings in a form that has been
approved by the Commission.
f. Commission Decisions. All orders, determinations and decisions of the Commission, including
the recommendations proposed to the Ministry by the Commission, shall be in writing and shall (i)
set forth the legal and factual basis in support of such decisions; and (ii) register and record the
vote cast by the Chairman and the other Members. Members who opposed decisions taken by the
Commission may attach to such decisions their written dissents explaining their opposition.
g. Public Notices and Public Participation. The ERC shall provide written and electronic notices of (i) all
filings, applications and petitions filed with the ERC requesting regulatory actions or decisions to be
taken by the Ministry; (ii) initiation of Permit specific investigations and inquiries; and (iii) the
intention of the Commission to promulgate general orders or rules and regulations of industry-wide
applicability and effect.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 37
h. Public Attendance and Observation. Any meeting or discussion of three or more Members shall be
publicly noticed and open to public attendance and observation.
3.8 Redress of Shortcomings of New Electricity Law
The Initial Version addresses virtually all of the deficiencies identified with the new Electricity Law.
Specifically:
3.8.1 The Initial Version integrates the ERC into the regulatory process by requiring the MOEP to make
regulatory decisions based upon recommendations prepared by the ERC.
3.8.2 Scope of MOEP Regulatory Authority. Concerns were originally raised about the limited scope of the
regulatory authority that has been given to MOEP. The two defined regulatory tasks are not sufficiently
comprehensive to provide the MOEP all of the regulatory tools required to prevent monopolistic abuse
in all of its forms. Concerns with the limited scope of regulation assigned to the MOEP by the Electricity
Law have been addressed by the significant expansion of the regulatory tasks assigned to the MOEP by
the Electricity Rules.
3.8.3 Pre-established Standards to Govern Key Regulatory Decisions. To promote transparency,
predictability and accountability, most legal and regulatory regimes set forth pre-established well-
publicized standards to govern important regulatory decisions and actions. Concerns about such
standards not being included in the Electricity Law have been addressed by the Electricity Rules by
setting forth pre-established standards that will govern regulatory decisions on permit issuances, tariff
determinations and regulatory approvals of financial activities, mergers and corporate reorganizations,
investment and resource acquisition, and power procurement and power purchase agreements.
3.8.4 No Requirements Regarding Regulatory Process and Procedures. Transparency of regulation may be
limited by the failure of the Electricity Law to address the processes and procedures by which regulatory
actions and decisions are made by the MOEP and the ERC. As of the date of this report, it does not seem
that the MOEP envisages addressing its internal processes and procedures by regulation.
3.8.5 Inadequate Details Regarding Permitting. The draft Electricity Law does not set forth any standards or
requirements or the process by which permitting decisions are to be made. Concerns about this lack of
details will be addressed by the permitting details provided by the Electricity Rules.
3.8.6 Confirm MOEP Authority to Regulate Tariffs. Confirmation of MOEP authority to regulate all types of
tariffs and not just retail tariffs is provided by the Ele t i it ‘ules o e detailed spe ifi atio of MOEP s responsibilities regarding tariffs.
3.8.7 Requirements Regarding Tariff Revisions. Another hallmark of a successful regulatory framework is the
process and procedures for revising tariffs that provides power sector entities, electricity consumers,
the financial community and the general public confidence that revisions to tariffs will be made on a
principled basis by means of a transparent and predictable process for which the institution regulating
tariffs is accountable. The New Electricity Law does not set forth any details or requirements regarding
revisions of tariffs. However, the Electricity Rules provide some detail as to the process and procedures
by which tariffs are to be revised.
3.8.8 Absence of Appellate Process and Forum. The provision for appeals in Chapter 15 of the draft Electricity
Law is limited to appeals of decisions regarding payment of damages and compensation under Chapter
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 38
14. The draft Electricity Law does not provide for appeals of other regulatory decisions and actions to
be taken by MOEP. Instead, all MOEP regulatory decisions are subject to the approval of the Union
Government. This is perhaps the only deficiency identified with the New Electricity Law that cannot be
redressed or mitigated by the Electricity Rules.
3.9 First Electricity Law Workshop
3.9.1 On 25 March 2015 a workshop was held in Naypyitaw, Myanmar to facilitate review and comments on
the draft Electricity Rules from MOEP and other Union Government ministries and institutions. The
presentation made by the DFDL Consulting Team is attached hereto at Item 18 of Appendix F.
3.10 Reaction of Other Union Ministries and Government Institutions
3.10.1 On 9 May 2015, the MOEP held a meeting with the other Union Government institutions to discuss
their respective reviews and comments on the Initial Version. Thereafter, the Steering Committee
reviewed all of the comments received, but few changes were made to the draft Electricity Rules.
3.10.2 The one exception were the comments and suggested revisions proposed by the Ministry of Industry.
The comments of the Ministry of Industry focused on technical and safety inspections of power sector
facilities, electrical appliances and power sector equipment operations and operators. Virtually all of
the revisions proposed by the Ministry of Industry were incorporated into the draft Electricity Rules.
3.10.3 On 15-16 June 2015, the DFDL Consulting Team met with the DG of the DEP to assist him in preparing
for meetings with the MOEP Minister and other government officials on the draft Electricity Rules.
3.11 Second Electricity Law Workshop
3.11.1 A second workshop was held on 6 July 2015 to present the Electricity Law and draft Electricity Rules to
the international donor organizations and government institutions other than MOEP. This workshop
covered presentations by (i) DFDL on summary of the Electricity Law, draft rules and regulations, and
contents of proposed Rural Electrification Law; and (ii) Public Private Partnership consultant Deloitte
on legal concerns by private investors. The presentation given by the DFDL Consulting Team is attached
hereto as Item 19 of Appendix F.
3.12 Final Version of Electricity Rules
3.12.1 On 18 June 2015, the DFDL Consulting Team met with the DG of the DEP to be informed of the results
of the MOEP Mi iste s e ie of the d aft Ele t i it ‘ules. At this meeting the DFDL Consulting Team
was instructed by direction of the MOEP Minister to (i) assign all regulatory tasks to the MOEP for which
it will be solely responsible; (ii) extract the ERC from any involvement in regulatory tasks; (iii) extract
from the draft Electricity Rules all rules involving or referencing the ERC.
3.12.2 As directed by the MOEP Minister, the draft Electricity Rules were revised with all regulatory tasks to
be performed by MOEP and with no involvement on the part of the ERC. All rules regarding the ERC
and its composition, organization, structure, process and procedures have been eliminated from the
Electricity Rules. Rules regarding the ERC were to be separately compiled.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 39
3.12.3 No further action on the separately compiled ERC related rules was taken by the Steering Committee
as they were no longer of immediate importance and were most likely to be finalized by a government
institution other than the MOEP.
3.12.4 In addition to the extraction of the ERC from the Electricity Rules, only two other material revisions
were made to the Initial Version. First, as noted above, the Ministry of Industry made valuable
suggestions as to additional language needed to be added to the Electricity Rules regarding inspections.
The language suggested by the Ministry of Industry has for the most part been incorporated into the
Electricity Rules.
3.12.5 Second, the Initial Version was revised to add three additional types of Permits that the MOEP is
authorized to issue. These three additional Permits are for (i) power exports and imports; (ii) special
purpose transmission facilities; and (iii) distribution and retail supply franchises. For each of these three
new types of Permits, language was added to the Electricity Rules as to the content of permit
applications and the service obligations associated therewith. These changes together constitute the
Fi al Ve sio of the Ele t i it ‘ules.
3.12.6 The Final Version of the draft Electricity Rules was approved by the Union Government and thereafter
submitted to Parliament in November 2015. Under Myanmar law, if the Parliament does not object to
the draft Electricity Rules within 90 days of its receipt of the draft Rules, the Electricity Rules will become
effective.
3.13 Analysis and Assessment
Significance of Electricity Rules:
3.13.1 As described in detail above, issuance of the draft Electricity Rules submitted to Parliament for approval
will constitute a significant step forwards, laying a solid legal foundation for effective power sector
regulation. The Electricity Rules will help establish the basic framework for the regulation of the
Myanmar power sector.
3.13.2 The Electricity Rules will establish a permitting regime through which MOEP will control entry and
participation in the power sector and define the service obligations of each type of power sector
participant. For each type of power sector participant, the Electricity Rules (i) specify the content of
Permit applications and the eligibility requirements applicable thereto; (ii) specify permit content; (iii)
define the applicable service obligations; and (iv) vests the MOEP with the authority to revise Permits
unilaterally in order to implement power sector reforms.
3.13.3 The permitting regime is thus designed to be flexible in order to enable power sector structural reforms
to be easily implemented by MOEP unilateral revisions of Permits. The definitions of respective service
obligations should promote coordination and confirm the structure to which the power sector is to
evolve.
3.13.4 The Electricity Rules significantly expand the regulatory responsibilities of the MOEP and include the
regulation of financial activities and organizational affairs, technical and industry standards, codes of
conduct, the forecasting of load growth, least cost resource planning and investment planning and
resource procurement. The expansion of the regulatory tasks assigned to the MOEP ensures that the
MOEP has the tools it requires to protect against monopolistic abuses in any form.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 40
3.13.5 Transparency of regulation will be fostered by the requirement in the Electricity Rules that all regulatory
decisions of the MOEP be in written form and set forth the factual and legal basis for the regulatory
decisions being rendered. Transparency and predictability will also be promoted by its clarification of
the requirements applicable to specific regulatory tasks and its specification of pre-established
standards to govern all significant regulatory decisions, including permit issuances, tariff
determinations and regulatory approvals of financial activities, mergers and corporate reorganizations,
investment and resource acquisition, power procurement and power purchase agreements. These
measures will help to install public confidence that the regulatory decisions of the MOEP will be made
on a principled basis and will increase the transparency of tariff regulation.
3.13.6 Importantly, the Electricity Rules provide greater detail as to the processes and requirements applicable
to tariff determinations by MOEP. The Electricity Rules require that tariffs be based upon expressly
stated principles and standards; most notably to allow recovery of all costs prudently incurred to meet
the demonstrated needs of their customers and that result in rate of returns on power sector capital
investments which promote investments in equipment and facilities required for Permitted Persons to
satisfy their respective service obligations. In addition, tariffs proposed for MOEP approval shall become
effective sixty (60) days after being filed, subject to refund of the amount by which the tariff filed for
approval exceeds the tariff approved by the Union Government.
Remaining Shortcomings:
3.13.7 Notwithstanding the significant benefits that will be achieved by the Electricity Rules as submitted to
the Parliament, there remain a few outstanding shortcomings. Consolidating all regulatory tasks with
the MOEP and eliminating all rules referencing the ERC will result in the process of regulation by MOEP
not itself being subject to any regulation. There are no requirements in the Electricity Rules regarding
the regulatory organization, process and procedures of the MOEP. In other words, the MOEP regulation
is not transparent and could possibly become a black box when viewed from the perspective of power
sector participants and the general public. However, this shortcoming should be addressed in part by
the regulations able to be issued by the MOEP.
3.13.8 As reported above, the draft Electricity Rules submitted to the Parliament for approval addressed
virtually all of the deficiencies identified with the new Electricity Law with two exceptions.
3.13.9 First, the draft Electricity Rules cannot address the absence of an opportunity for meaningful appeals
of MOEP regulatory decisions. The provision for appeals in Chapter 15 of the new Electricity Law is
limited to appeals of decisions regarding payment of damages and compensation under Chapter 14.
The draft Electricity Law does not provide for appeals of other regulatory decisions. Instead, all MOEP
regulatory decisions are subject to the approval of the Union Government. Establishing the opportunity
for such appeals is beyond the legally permissible scope of what can be addressed by the issuance of
rules and regulations.
3.13.10 Second, the draft Electricity Rules submitted to Parliament for approval did not include any mechanism
by which the ERC can become involved in performing regulation in any form. The Initial Version of the
draft Electricity Rules included a requirement for MOEP to render regulatory decisions based on the
written ERC recommendations coupled with the restriction that the MOEP must approve the ERC
written recommendations as its own decision absent misapplication of law or material facts. This
requirement was not included in the final version of the draft Electricity Rules submitted to Parliament,
and this absence resulted in the MOEP being solely responsible for regulation.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 41
3.13.11 However, the absence of this language does not render the MOEP unable to integrate the ERC into the
regulatory process. Indeed, there is nothing in the new Electricity Law or the draft Electricity Rules that
would bar the MOEP from establishing the same working arrangement as would have resulted from the
Initial Version language that was removed from the draft Electricity Rules submitted to Parliament.
3.13.12 This result can be achieved by means of the MOEP requesting the ERC for written recommendations
regarding specific decisions and tasks assigned to the MOEP. Achievement of this result will be best
reached gradually, with requested recommendations proceeding from the easy to the more
challenging. In addition, once established, the capabilities of the ERC can be enhanced by seconding
MOEP employees to this new organization to serve as regulatory staff for reasonable periods of time.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 42
Chapter 4
Preparation of Power Sector Supporting Regulations (Phase 2 – Tasks 2&3 and Phase 3)
4.1 Initial Assessment
4.1.1 The DFDL Consulting Team was charged by the TOR and the extension of the ADB Contract to assist the
MOEP to prepare key high priority secondary regulations that need to be issued in order for regulation
of the Myanmar power sector to become operational.
4.1.2 As the original twelve month term of this Project drew to a close in early 2015, the DG of the DEP
informed the DFDL Consulting Team that the MOEP will continue to need assistance beyond the
expiration of the original contract term in order for the MOEP to finalize the draft Electricity Rules, and
requested the DFDL Consulting Team to start working on the regulations required to be prescribed for
the ERC to become operational.
4.1.3 To assist the MOEP in defining the scope of this effort, the DFDL Consulting Team prepared a list of
seventeen regulations required by the new Electricity Law and, once prescribed, the Electricity Rules.
The DFDL Consulting Team also identified the regulations most likely to be required for the ERC to
become operational and prioritized the order in which such regulations should be prepared. Copies of
these communications are attached hereto as Item 20 of Appendix F.
4.1.4 The ADB agreed to a six month extension of the contract term in order to assist the MOEP to prepare
six sets of prioritized regulations. Specifically, the MOEP and ADB agreed that the DFDL Consulting Team
would prepare the regulations for (i) permitting; (ii) tariff determinations; (iii) competitive power
solicitations; (iv) regulatory approvals of power purchases and power purchase agreements; (v)
regulatory approvals of investments and resource acquisitions; and (vi) ERC internal organization,
process and procedures.
4.1.5 It was agreed that a draft of each regulation would be prepared by the DFDL Consulting Team based
upon relevant international examples and experience and then distributed to the MOEP for line-by-line
review, explanation, discussion and revision; noting that finalization of each regulation would likely
require multiple rounds of MOEP review and revision. Work on the regulations was initiated in early
April 2015 with the DG of the DEP and the Steering Committee directing the DFDL Consulting Team to
give top priority to the preparation of the regulation on ERC internal organization, process and
procedures.
4.2 Revisions Due To ERC Exclusion from Regulation
4.2.1 When the six regulations were selected for prioritized preparation and work on these regulations was
initiated in April 2015, the Initial Version of the draft Electricity Rules was still current, and
contemplated the ERC having a significant role in the performance of regulatory tasks. As such, the
draft regulation on ERC internal organization, process and procedures delivered to the DG of the DEP
and the Steering Committee on 6 September 2015 focused on regulatory features and requirements
intended to enhance the transparency, independence, and accountability of regulation by the ERC. A
copy of this draft regulation is attached hereto as Item 21 of Appendix F.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 43
4.2.2 More specifically, the draft regulation on ERC internal organization, process and procedures addressed
(i) the ERC internal organization; (ii) the process and procedures for accepting and acting upon requests
for regulatory decisions and actions; (iii) allocation of responsibilities across the internal ERC
organization; (iv) the requirements regarding public notices of regulatory proceedings, proposed
decisions and regulatory actions; and (v) the permitted means for public participation.
4.2.3 However, the DG of the DEP and the Steering Committee decided not to pursue the preparation of the
draft regulation on ERC internal organization, process and procedures any further since this draft
regulation was no longer of immediate importance. As with the ERC related rules extracted from the
Final Version of the draft Electricity Rules, the revision of the draft Electricity Rules to assign sole
responsibility for regulatory tasks to the MOEP and to eliminate the ERC from the regulatory process
rendered the draft regulation on ERC internal organization, process and procedures largely irrelevant.
4.2.4 The draft regulation on ERC internal organization, process and procedures and the ERC related rules
extracted from the draft Electricity Rules set forth requirements to govern the ERC regulatory process
a d the E‘C s pe fo a e of egulato tasks, Since there is no ERC regulatory process and the ERC is
not involved in the performance of regulatory tasks, the relevant requirements as set forth in such rules
and regulations have no operative effect. Instead, the focus of the process-related regulations
requiring preparation shifted from the ERC to the MOEP. The scope of the regulations to be prepared
by the DFDL Consulting Team therefore expanded to include regulations on the internal organization,
process and procedures of the MOEP and MOEP filing procedures.
4.3 Status of Supporting Regulations
MOEP Regulations on Filing Procedures:
4.3.1 The Electricity Law and the draft Electricity Rules, once effective, will result in the ERC having no
involvement in the regulatory process, with the MOEP given sole responsibility for all regulatory tasks.
The institutional and procedural requirements included in the draft of the Electricity Rules presented
at the March 2015 First Electricity Law Workshop intended to apply international best practices to
promote transparency, independence, and predictability of power sector regulation. However, the
institutional and procedural requirements recommended focused exclusively on the ERC. These
provisions were dropped from the Electricity Rules without analogous requirements being added to
govern regulation by the MOEP.
4.3.2 To redress this imbalance, the DFDL Consulting Team prepared a draft regulation for the consideration
of the DG of the DEP and the Steering Committee that addressed the internal MOEP regulatory
organization, process and procedures. See Item 1 of Appendix E. It appeared that the details about how
the MOEP will regulate were not considerd as a priority and relevant governmental counterparts did
not give this draft regulation further consideration except for that portion of the draft regulation that
governs the procedures for making filings requesting regulatory action from the MOEP, such as
applications for permits, tariff determinations, enforcement of regulatory requirements, required
regulatory approvals or other regulatory actions.
4.3.3 To reduce complexity, other than for those requirements specific to particular regulatory tasks as set
forth in the relevant regulations, the filing procedures set forth in theses draft regulations are intended
to apply to all MOEP regulatory filings.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 44
The following summarizes the substance of these draft filing regulations.
4.3.4 Definitions. The draft filing regulations attempt to address potential confusion by limiting definitions
to terms not already defined by the Electricity Law and the Electricity Rules. Importantly, the definitions
i lude a defi itio of pu li do u e ts hi h ill e ui e all o -confidential information to be
placed in a public document room to be located at a time at which the public is able to identify and
access such information.
4.3.5 Applications. The draft filing regulations require all requests for regulator action to be initiated by the
filing with the MOEP of an application that satisfies certain specified content requirements. All
applications must:
i. state the name and address of the applicant, the reason for the application, and an
identification of any Permits already issued to such applicant;
ii. include all the documentation and information identified as relevant to the requested
regulation and in other MOEP regulations; and
iii. include a summary of evidence supporting the regulatory action requested.
4.3.6 Content Review and Initiation of Regulatory Proceedings. Upon being filed, the MOEP shall examine the
application to see that it satisfies and conforms to the content requirements applicable to such
application. If incomplete or not in conformity, the application shall be returned to the applicant
together with directions to amend and re-file. If determined to be complete and in conformity, the
MOEP shall accept the application for filing and the regulatory proceeding regarding such application
shall be deemed to be initiated on the date the application is so accepted. See Paragraph 5 and 6 of
Item 1 Appendix E.
4.3.7 Public Notification and Interventions. Importantly, the draft filing regulations provide an opportunity
for interested members of the public to participate in regulatory proceedings. Within ten days of the
date of the acceptance of an application for filing by the MOEP, the MOEP is required to issue a public
notification of such filing. See Paragraph 7 of Item 1 Appendix E. Any person may file a request to
participate in the subject regulatory proceeding within fifteen dates of the date of the public filing
notification. Such requests shall state the reasons for requesting participation and an explanation as
to how such person could be adversely affected by the requested regulatory action or the regulatory
decision that could result. See Paragraph 8 of Item 1 Appendix E.
4.3.8 The applicant is then to be provided an opportunity to respond to such requests for participation.
Within ten days of the last date on which an intervention request was able to be filed, the MOEP shall
determine which members of the public are to be permitted to participate. The draft regulations only
permit participation by those members of the public that could be adversely affected by the requested
regulatory action or potential regulatory decision. See Paragraphs 8(c) and 10(a) of Item 1 Appendix E.
4.3.9 Public Hearings. Also within ten days of the last date on which an intervention request was able to be
filed, the MOEP is to determine whether a public hearing is required. The draft regulations state that
consideration is required as to whether a public hearing is required to arrive at a just and reasonable
result, and that the use of public hearings should be limited to circumstances involving disputes on
material facts. The draft regulations permit the use of a variety of hearing forms. See Paragraph 9 of
Item 1 Appendix E.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 45
4.3.10 The draft regulations specify that the director of the MOEP department to which the subject regulatory
proceeding is assigned shall serve as the presiding officer for any public hearing to be held. The
presiding officer shall determine the form of and procedures for the public hearing and frame the issues
to be addressed in the public hearing and may permit cross-examination. See Paragraphs 10(a), (b) and
(c) of Item 1 Appendix E.
4.3.11 Within twenty days of the public hearing being declared closed, the presiding officer shall submit to
MOEP a written summary of the evidence obtained during the public hearing. Importantly, the
presiding officer will have the benefit of the opinions of parties to the proceeding who may, under the
draft regulations, file their own respective written summaries of the information obtained during the
public hearing within twenty days of the public hearing being declared closed. See Paragraph 10(d) of
Item 1 Appendix E.
4.3.12 MOEP Decisions and Reconsideration Requests. The draft regulations require that the MOEP render
regulatory decisions within 120 days of the date on which the relevant applications were accepted for
filing. See Paragraph 12 of Item 1 Appendix E. Within ten days of a final decision by the MOEP, a party
in the regulatory proceeding may file a request for the MOEP to reconsider its decision. Such a request
must specify in detail the basis warranting such reconsideration. The other parties to the specific
regulatory proceeding shall be afforded ten days to address such request for reconsideration. See
Paragraphs 13(a), (b) and (c) of Item 1 Appendix E.
4.3.13 The MOEP is required by the draft regulations to render a decision regarding the reconsideration
request within thirty days of receipt of the reconsideration request. The MOEP may deny the request
or, if it determines reconsideration is warranted and its decision needs to be revised, the MOEP shall
issue is a new decision setting forth the legal and factual basis in support of such revision. See Paragraph
13(d) of Item 1 Appendix E.
MOEP Permitting Regulations:
4.3.14 The Electricity Law mandates a permitting regime by which market entry into the power sector will be
able to be controlled by the MOEP and the Electricity Rules, and provides many of the details not
addressed by the Electricity Law. The difficulty of structuring the permitting regime is in the need for the
permitting regime to be sufficiently flexible to accommodate the ultimate structure desired for the
Myanmar power sector and support the evolution of the power sector already underway, yet able to be
utilized to implement more dramatic structural reforms that may be pursued by the Government at a
later date.
4.3.15 In this regard, although the Electricity Rules provide a solid foundation for the permitting regime
mandated by the Electricity Law, the Electricity Rules are not sufficient to create a workable and
effective permitting regime.
4.3.16 The Electricity Rules acknowledge and provide for the subsidiary legal instruments required to provide
such details. Indeed, the Electricity Rules authorize the MOEP to issue regulations regarding the
applications for, issuance of, revisions and modifications to, and suspensions and revocation of Permits.
The Electricity Rules require the permitting regulations to be issued by the MOEP to specify the form
and content of Permit applications, filing requirements, evidentiary support, documentation needs, and
procedures specific to licensing.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 46
4.3.17 The DG of the DEP and the Steering Committee expended considerable efforts to prepare the draft
permitting regulations involving at least twelve rounds of review and revision over a period of almost
six months. The final version of the draft permitting regulations with which the DFDL Consulting Team
assisted preparation is attached hereto as Item 2 of Appendix E. The following summarizes, by Part, the
substance of these draft permitting regulations.
Part I- Permit Applications:
4.3.18 Permit Applicants. The draft permitting regulations require applicants for Permits to demonstrate that
they satisfy the requirements of Rule 73 of the Electricity Rules, that is, that they have demonstrated
their capabilities to provide the Electricity Related Works that are the subject of their requested Permit
and are able to comply with all legal, regulatory and Permit conditions applicable thereto. The draft
permitting regulations also require that Permit applicants demonstrate that the plant, equipment and
facilities are consistent with National Energy Power Development Plan. See Sections 5 and 9 of Item 2
Appendix E.
4.3.19 The draft permitting regulations set forth the form for Permit applications and the information required
to be provided for in (i) all Permit applications; (ii) applications for each type of Permit and each type
of Electricity Related Works; (iii) applications involving both existing and new power facilities; and (iv)
applications for each type of power facility, including thermal and hydro power generation,
transmission and distribution. See Paragraphs 6, 7, 8, and Schedules 2, 3 and 4 of Item 2 Appendix E.
4.3.20 Evidentiary support and documentation to include:
a. Evidence of the availability of adequate financial and technical resources to implement successfully
the subject project;
b. Technical and financial proposals for the operation, planning and development of the subject
project; and
c. In the case of a new facility, a feasibility study of the project, setting forth in reasonable detail:
the type, technology, model, technical details and design of the facilities and equipment to be
part of the subject project;
the expected life of the subject project;
the location of the subject project and the outer boundaries within which project facilities are
to be installed and operated;
the type and details of the services proposed to be provided; and
a prospectus.
4.3.21 Application Process and Procedures. In the event that the MOEP intends to deny an application, the
MOEP is required by the draft permitting regulations to give the applicant an opportunity to make a
presentation as to the reasons its application should not be denied. The draft permitting regulations
require that the MOEP makes a decision on Permit applications within 28 days after the date of the
Permit application, provided such period shall exclude any time taken by the applicant to make such a
presentation. See Paragraph 11 of Item 2 Appendix E.
4.3.22 Prerequisites for Permit Issuance. The draft permitting regulations prohibits Permits from being issued
and becoming effective until such time as the applicant has obtained all requisite approvals, and (i) for
generation Permits, execution of a Power Purchase Agreement (PPA) as pre-approved by MOEP; (ii) for
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 47
transmission and distribution and distribution franchises, MOEP approval of system improvement,
system development, loss reduction and financing plans; and (iii) for distribution franchises, execution
of a MOEP distribution contract. MOEP approved samples for a thermal PPA and distribution franchise
contract are to be appended to the draft permitting regulations. See Paragraph 12 of Item 2 Appendix
E. The model thermal PPA is to be included, but it is not yet possible to set forth a form of the PPA that
would be acceptable to the MOEP since not a single long term PPA has been executed and successfully
debt financed on a limited recourse basis.
4.3.23 The Electricity Rules will authorize the MOEP to o ditio the issua e of Pe its upo appli a ts provision of financial security to ensure satisfaction of service obligations and other requirements and
conditions as set forth in the Permits. The draft permitting regulations further authorize the MOEP to
require Permitted Persons to post additional security against repetition of the violation of law and/or
regulatory requirements. See Paragraph 32(c) of Item 2 Appendix E.
Part II- Permit Content:
4.3.24 Identity and Authorized Activity. Each Permit is required to identify the identity and main office of the
Permitted Person and the Electricity Related Works in which the Permitted Person is authorized to
engage. See Paragraph 13 of Item 2 Appendix E.
4.3.25 Term, Expiration and Renewal. The draft permitting regulations require Permits to specify the duration
of their term and the permissible bases for obtaining term extensions. The draft permitting regulations
specify different terms for different types of Permits and, for some Permits, the duration of the term
may be required to be revised as the structure of the power sector changes. See Paragraph 14 of Item
2 Appendix E.
4.3.26 Under the draft permitting regulations:
a. the terms of generation permits are to equal the duration of the corresponding PPAs or otherwise
the expected commercial life of the generation plant the subject of such permit;
b. the terms of Permits for transmission and distribution are to be perpetual;
c. the terms of Permits for wholesale power supply shall be perpetual until such time as there is more
than one Permitted Person authorized to supply power at wholesale to Permitted Persons engaged
in retail power supply;
d. the terms of Permits for retail power supply shall be perpetual until such time as the distribution
network business is no longer consolidated with retail power supply;
e. the terms of Permits for imports/exports shall be for the duration of the transaction authorized by
such Permits; and
f. the terms for distribution franchises shall be as determined by the MOEP. See Paragraph 14 of Item
2 Appendix E.
4.3.27 Upon expiration of the Permit term, unless otherwise extended, the original Permitted Persons must
transfer the equipment and facilities that are subject of the Permit to either the MOEP or to a third
party designated by the MOEP. The prior Permitted Person is to be paid compensation for the project
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 48
assets transferred either as originally agreed with the MOEP or, in the absence of such an agreement,
equal to the depreciated book value of the transferred project assets.
4.3.28 Service Authorization and Obligations. The draft permitting regulations do not expressly set forth the
service obligations of Permitted Persons other than to require Permitted Persons to engage in
Electricity Related Works on an economical, reliable and continuous basis. Permitted Persons are
permitted to interrupt service in case of theft, non-payment of bills or to address emergencies or
threats to public health, system reliability, or as otherwise directed by the MOEP. See Paragraph 16 of
Item 2 Appendix E.
4.3.29 Instead, the draft permitting regulations provide for the MOEP to issue Permits for Permitted Persons
to grant the exclusive right to engage in the different types of Electricity Related Works within
geographical territories and in accordance with service obligations specified in such Permits. The draft
permitting regulations clearly contemplate the text of Permits to expand and better define the scope
of authorization to engage in Electricity Related Works and the service obligations required of
Permitted Persons under each type of Permit.
4.3.30 To ensure achievement of this expectation, the DG of the DEP and the Steering Committee, with the
assistance of the DFDL Consulting Team, prepared samples for each type of Permit that is to be attached
to the permitting regulations. These sample permits set forth in greater detail the scope of such service
authorizations and obligations. These sample Permits are attached to the draft permitting regulations
as Annexes C through J of Item 2 Appendix E.
4.3.31 The service obligations associated with each type of Permit have been drafted to reflect the services
e ui ed to e p o ided Pe itted Pe so s u de the po e se to s u e t st u tu e a d its
current evolution towards reliance on a single buyer that purchases all generated power, and is the sole
source of wholesale power for multiple distribution companies who have an exclusive right to sell
power to their respective retail consumers. However, the sample Permits also include clauses that
indicate how the service obligations will need to be revised upon the introduction of a competitive
wholesale market with multiple power suppliers competing to sell power to multiple distribution
entities.
4.3.32 General Conditions for All Permits. The draft permitting regulations sets forth legal and regulatory
requirements applicable to all Permitted Persons. All Permitted Persons must (i) obtain MOEP approval
to undertake financings, re-financings and financial restructuring; and (ii) maintain their respective
books and records for the term of their respective Permits. See Paragraphs 19 and 23 of Item 2 Appendix
E.
4.3.33 All Permitted Persons are prohibited from providing Electricity Related Services to any customer on
terms and conditions materially more or less favorable than provided to comparable customers. See
Paragraph 24(a) of Item 2 Appendix E. Permitted Persons are also prohibited from directly or indirectly
having a beneficial interest in other Permitted Persons engaged in Electricity Related Works in which
they are not permitted to engage. See Paragraph 24(b) of Item 2 Appendix E.
4.3.34 The draft permitting regulations also impose certain requirements on Permitted Persons other than
those Permitted Persons engaged in wholesale and retail power supply. These requirements include (i)
the design, operation, maintenance and repair of equipment and facilities in accordance with prudent
utility practices, the grid code, and all applicable laws; (ii) to locate, construct, operate, maintain and
repair power generation so as to not endanger employees and the public health and safety; and (iii) to
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 49
develop and implement arrangements to ensure the safety of its operations and the continuity of and
security of electric power from generation facilities. See Paragraphs 20, 21, and 22 of Item 2 Appendix
E.
Part III - Permit Modifications and Revisions:
4.3.35 Discretionary Modifications. The draft permitting regulations allow Permitted Persons and the MOEP
to propose revisions to Permits. Applications for Permit modifications are to set forth the text of the
requested modification, include a statement in support of the requested modification and a statement
as to the impact the proposed modification is likely to have on tariffs, quality of service, and
performance of the Permitted Person. See Paragraphs 25 of Item 2 Appendix E.
4.3.36 The draft regulations allow MOEP to modify Permits if, in the opinion of the MOEP, such modifications,
(i) will not adversely affect the performance of its service obligations by the Permitted Person; (ii) is
likely to be beneficial to consumers; or (iii) is reasonably necessary for the Permitted Person to
effectively and efficiently perform its service obligations. See Paragraph 26 of Item 2 Appendix E.
4.3.37 Mandatory Modifications. The draft permitting regulations authorize the MOEP to revise Permits as
required to effect and reinforce power sector structural reforms approved by the Union Government.
This provision is critically important to providing a permitting regime that can be used to adjust service
obligations to implement power sector structural reforms. See Paragraph 29 of Item 2 Appendix E.
4.3.38 Revisions to Permits and the service obligations, and the imposition of new business prohibitions, could
have significant adverse financial effects on Permitted Persons, such as the required divestiture of
assets. Importantly, the draft permitting regulations provide the foregoing flexibility regarding Permit
modifications without addressing the financial impact of such revisions on those Permitted Persons
whose Permits are revised. The DFDL Consulting Team suggested to include a requirement for
Permitted Persons to be paid compensation for assets required to be divested that would have provided
significant financial protection to Permitted Persons, but such protection has not thus far been included
in either the draft Electricity Rules or the draft permitting regulations.
Part IV- Administration:
4.3.39 Inspections and Investigations. Permitted Persons will be required by the draft permitting regulations
to make their facilities, books and records available for inspection by the MOEP and the General
Inspector during normal business hours upon reasonable advance notice. The draft permitting
regulations will require Permitted Persons to cooperate with any investigation initiated by the MOEP,
including the provision of any information requested by the MOEP. See Paragraph 31 of Item 2
Appendix E.
4.3.40 Enforcement. In regards to enforcement, Section 38 of the Electricity Law only states that the MOEP
may take the following administrative actions against Permitted Persons who fail to adhere to
applicable regulations or fail to adhere to any orders and directives or is found guilty of committing any
offence under this law: (i) impose a fine; (ii) suspension of a Permit for a limited time; and (iii) Permit
revocation.
4.3.41 The Electricity Rules state little more than the Electricity Law, but importantly, Section 98 of the
Electricity Rules prohibits the MOEP from taking any regulatory enforcement action until the subject
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 50
Permitted Person is informed in writing of the alleged violation and is requested to provide an
explanation.
4.3.42 In accordance with Rule 99 of the Electricity Rules, the MOEP, upon recommendations of the ERC and
with the approval of the Union Government, is to issue regulations that prescribe regulatory
enforcement procedures. As per this Rule, the draft permitting regulations are to provide the subject
Permitted Person (i) an opportunity to explain the alleged violation; (ii) a reasonable period of time to
remedy such violation; and (iii) if not remedied within a reasonable period of time, procedures for
imposing sanctions and financial penalties. The permissible sanctions identified by Rule 100 of the
Electricity Rules include, (i) provision of additional financial security against repeat violations; (ii)
financial penalties; (iii) permit suspension and revocation; and (iv) referral for civil or criminal
prosecution.
4.3.43 The draft permitting regulations break enforcement action into two stages. The first stage follows that
once the subject Permitted Person has been given an opportunity to provide a written explanation and
to remedy the subject violation, the MOEP may direct appropriate corrective action to be taken and/or
modify the subject Permit to address the cause of such violation or to prevent the violation from being
repeated.
4.3.44 The second stage involves the imposition of sanctions and penalties. The draft permitting regulations
authorize (i) the imposition of financial penalties; (ii) Permit suspension; (iii) Permit revocation; and (iv)
referral by the MOEP to appropriate government authorities for civil and criminal prosecution.
4.3.45 Upon Permit termination or expiration, Section 10 of the Electricity Law requires the Permitted Person
to transfer the business in its original form, or in accordance with the conditions agreed upon at the
time of original issuance of the Permit, to such other Permitted Person.
Part V- Miscellaneous:
4.3.46 Sample Permits. The draft permitting regulations are intended to include sample Permits for each type
of Permit that will be attached as Appendices to the permitting regulations. See Paragraph 34 of Item
2 Appendix E. Draft sample Permits are included as Annexes C through J of Item 2 Appendix E.
MOEP Tariff Regulations:
4.3.47 The Electricity Law and the draft Electricity Rules give authority to the Union Government to determine
tariffs for grid-connected electricity supplies and to Regional and State Governments and leading bodies
of Self-Administered Divisions and Zones for the determination of tariffs for off-grid supplies. The
Electricity Tariff Regulations give effect to this authority by setting out the methodologies and processes
for the submission of proposed tariffs and their review and approval by the Ministry.
4.3.48 The development of the regulations started with a mission by the DFDL Consulting Team to the MOEP
on 1-4 September 2015. During this visit, the objectives and scope of the regulations were discussed
and agreed. A workshop to confirm these agreements was held for MOEP participants on 4 September
2015.
4.3.49 Of particular note is that it was agreed that the regulations need to provide a detailed framework for
calculations, given the lack of familiarity in Myanmar with tariff regulation, but also to incorporate
flexibility to update the assumptions and input values used as experience in their application is gained.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 51
This was achieved by placing many key variables related to the calculations into orders to be issued by
the MOEP under the Regulations themselves and, therefore, allowing these to be amended without the
need for Parliamentary approval (as is required for the Regulations).
4.3.50 Subsequent to the workshop, draft regulations were prepared and translated. These were reviewed on
a line-by-line basis with the MOEP during missions by the DFDL Consulting Team from 29 September to
2 October 2015, 13-14 October 2015, 8-10 December 2015 and 22-24 December 2015.2 Between
missions, the draft regulations were revised as necessary to incorporate comments received.
4.3.51 The final draft regulations were submitted in English and translated versions on 24 December 2015 for
MOEP s i te al o sultatio p o esses. A plai la guage su a guide to the egulatio s as also provided at the same time. The following summarizes the substance of these draft regulations as set
forth in Item 3 of Appendix E.
4.3.52 Applicable tariffs. The Regulations apply to tariffs charged for the sale of electricity by Permitted
Persons to another Permitted Person or to electricity customers. A separate tariff applies for each
Permitted Activity, whether or not these form part of the same legal entity. A separate tariff also applies
for each generating facility, even if these are owned by the same Permitted Person.
4.3.53 A number of tariffs are exempt from the Regulations as they are set and approved under legislation or
processes outside the Regulations. These are tariffs set under existing contracts; competitive
procurements or other approved market-based mechanisms; Government-to-Government
agreements; and other laws and regulations, including feed-in-tariffs and similar support schemes for
renewable energy generation. Tariffs demonstrated to have been established under competitive
circumstances shall be approved by the MOEP without the need for cost justification. Importantly, the
fact that wholesale power tariffs charged by power generators can be approved without cost
justification does not mean that such power sales and the applicable tariffs are not the subject of
regulatory review from the perspective of power purchasers who resell such power to their captive
customers. Captive customers of wholesale power purchasers must be protected against having to pay
the increased costs of imprudent power purchases.
4.3.54 In accordance with the Electricity Law, determining methodologies for setting off-grid tariffs and
approval of these tariffs are the responsibilities of Regional and State Governments and leading bodies
of Self-Administered Divisions and Zones. However, proposed off-grid tariffs must be sent to the
Ministry for review and comment prior to being approved.
4.3.55 Principles. The Regulations require that tariffs follow the principles set out in the Electricity Law and, in
addition, that they promote investments and provide incentives for improvements in the efficiency and
quality of electricity supply. The Regulations also create a general prohibition on cross-subsidies with
the exceptions that rising block tariffs may be applied for households and a uniform national retail tariff,
which requires cross-subsidies between customers of different Permitted Suppliers, may be applied.
Existing cross-subsidies from non-household to household customers must be phased out gradually to
avoid large and sudden changes in tariffs.
4.3.56 Allowed revenues. An Allowed Revenue Requirement (ARR) is calculated annually by each Permitted
Person in accordance with the Regulations and proposed to the Ministry for approval. Following
approval, the ARR is used to determine the tariffs to be charged, which are set to recover the approved
2 Travel time is not included.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 52
ARR. The ARR is calculated as the sum of Allowed costs, Annual cost adjustments, which compensate
for differences between allowed and actual costs in the previous year due to matters outside the
control of the Permitted Person and Annual revenue adjustments, which compensate Permitted
Suppliers and Franchisees for differences between ARR and actual revenues earned in the previous year
due to differences between actual and forecast volumes sold.
4.3.57 Allowed costs for generation, transmission and distribution / retail supply are the sum of fuel costs
(generation only), non-fuel operating costs, debt interest costs, return on equity, foreign exchange
losses, depreciation and corporate income tax. Suppliers are also allowed to recover the costs of power
purchases from the Wholesale Power Supplier (single buyer) and a bad debts allowance. The allowed
costs of the Wholesale Power Supplier are calculated as the sum of power purchase costs plus
transmission costs plus a wholesale margin which recovers its own costs and the costs of working
capital.
4.3.58 Power purchase costs and fuel costs for generators are approved annually using an energy balance
prepared by the Wholesale Power Supplier and approved by the Ministry. Other operating costs are
approved based on business plans submitted by the relevant Permitted Persons. Approvals will initially
be made annually but the Regulations allow for a move to multi-year tariffs in the future.
4.3.59 The return on equity is determined by the Ministry. The Regulations provide that the minimum return
on equity for state-owned enterprises is the minimum deposit rate issued by the Central Bank of
Myanmar and the minimum return allowed for private enterprises is five percentage points (5%) above
this level.
4.3.60 Tariffs. Following approval of their ARR for the next year, Permitted Persons involved in generation,
wholesale supply and electricity transmission calculate tariffs to recover the approved ARR, following
the principles and methodologies set out in the Regulations. Where a uniform national retail tariff
applies then the Ministry will determine the retail tariffs to be applied. To do so, it will apply a table of
allocation factors issued by the Ministry. The table shows the tariff to be applied to each customer
category as a ratio to the average retail tariff.
4.3.61 For thermal generators, separate energy and capacity charges are calculated. The capacity charge is
only paid when generating capacity is available. Therefore, generators have an incentive to be available
for more hours than their availability target in order to earn extra revenue.
4.3.62 For hydro generators, firm and secondary energy charges are applied. This mechanism shares the risk
between the generator and customers of whether a year is below or above-average hydrology (rainfall)
conditions.
4.3.63 For wind and solar generators whose tariffs are not set under other regulations, a flat energy charge is
applied. This places the risk of uncertainty over output on the generator rather than on customers.
4.3.64 The wholesale tariff charged by the Wholesale Power Supplier to Permitted Suppliers is used to create
a cross-subsidy between Permitted Suppliers and, thereby, allow the application of a uniform national
retail tariff. The wholesale tariff charged to each Permitted Supplier is equal to an adjusted wholesale
tariff for that Permitted Supplier plus a surcharge where actual distribution losses exceed allowed
values (meaning additional energy must be purchased to make up the difference). The adjusted
wholesale tariff differs between Permitted Suppliers with those who have higher revenues and lower
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 53
costs paying a higher wholesale tariff to allow a lower tariff, offsetting differences in revenues and
costs, to be charged to other suppliers.
MOEP Regulations on Investments, Power Procurement and Resource Acquisition:
4.3.65 The New Electricity Law does not address the topics of forecasting and power sector planning in regards
to investment, power procurement and resource acquisition even though there appears to be a
common perception that the problems facing the Myanmar power sector have resulted from, or been
exacerbated by, the lack of forecasting and limited power sector planning. The focus and efforts of the
MOEP and other government institutions have been, and continue to be, on individual projects on a
project by project basis. This is typical of countries with state-owned industries managed by
administrative directives implementing central government planning intended to control allocation of
national resources ithout a kets i te fe e e.
4.3.66 Nonetheless, imposing regulatory requirements that will transition power sector participants into the
performance of forecasting and least cost planning is certainly consistent with the objective of the
Ele t i it La to achieve further development in electric power sector, to meet the national electricity
needs and to administer the electricity related businesses through effective and systematic
ad i istratio i li e ith the Go er e t s poli ies. See Section 3(a) of Appendix B.
4.3.67 Electricity Rules: Requirements and Guidance. In contrast, the Draft Electricity Rules require annual
forecasting and power sector planning, and yield significant guidance as to how such requirements are
to be implemented. The draft Electricity Rules requires the MOEP to prepare methodologies for
forecasting power needs, least cost investment, and power procurement planning, and to provide
guidance thereon. See Rule 2(b)(iii) of Appendix C.
4.3.68 The MOEP is also required by the draft Electricity Rules to annually prepare a multi-year National Power
Development Plan for review and approval by the Union Government, which shall be updated and
approved by the Union Government annually. National Power Development Plans are required to focus
on ensuring long term balance between reliable electricity supply and electricity usage. See Rules
2(b)(x) and 2(b)(xii) of Appendix C respectively.
4.3.69 The draft Electricity Rules require all Permitted Persons to prepare and submit annually their respective
forecasts for MOEP approval. Permitted Persons with Retail Power Supply are to forecast the load
growth of their Full Requirements Customers. See Rule 2(b)(iv) and 48(a) of Appendix C respectively.
4.3.70 Permitted Persons who are issued the National Transmission Permit and Distribution Permits are
required by the draft Electricity Rules to prepare and submit annually their expansion of investment
and additional power acquisition program for MOEP approval. See Rules 28 & 42 of Appendix C.
Investment and power procurement plans may only be approved if they are demonstrated to be least-
cost, consistent with the National Electric Power Development Plan, and to satisfaction of their
respective service obligations in accordance with prudent practices. See Rules 2(b)(iv) and 2(b)(v) of
Appendix C.
4.3.71 Under the Electricity Rules, the MOEP may only approve PPAs and the issuance of Permits for
generation if they are determined by MOEP to be consistent with least cost power procurement. See
Rules 2(b)(xiv) and 15(c) of Appendix C. In addition, Permitted Persons are prohibited from purchasing
power from new IPPs unless such purchases are the result of competitive power solicitation programs
approved by MOEP. See Rule 77 of Appendix C
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 54
4.3.72 Regulation Objectives: Scope and Purpose. The draft regulations on MOEP approval of investment,
power procurement and resource acquisition plans (hereafte efe ed to as d aft esou e a uisitio egulatio s states that these egulatio s a e, to p ote t Capti e Custo e s su je ti g fo e asti g
and resource procurement planning decisions of Permitted Persons with Captive Customers to
egulatio . These egulatio s a e also stated as i te ded, to protect against capital investments and
power procurement inconsistent with the needs of the Myanmar power sector and the welfare of
ele t i it o su e s. See Section 3 of Item 4 Appendix E. This protection has two dimensions that
must be addressed by these draft regulations.
4.3.73 First, these regulations need to be structured to help prevent Permitted Persons with Captive
Customers from passing through to such customers the increased costs of poor management, such as
the increased costs associated with (i) availability reductions and inefficient heat rates due to sub-par
maintenance practices; (ii) cost over-runs and construction delays due to deficient design, poor
planning, poor construction management, and defective implementation of quality assurance
programs; and (iii) production delays and interruptions due to fuel supply problems and failures to
comply with applicable environmental, health and safety legal requirements.
4.3.74 Second, these regulations must establish the process and procedures that will result in the coordinated
and efficient formulation of a comprehensive least cost national plan that focuses on the need for, and
prioritizes, power sector investments to achieve a long term balance between reliable electricity supply
and electricity usage. This task will become progressively more difficult as the structure of the Myanmar
power sector moves away from being government-owned and vertically integrated within the MOEP to
a more disaggregated industry structure with a mix of private and government owned generation
plants, a separate enterprise responsible for the national transmission grid, one wholesale power
supplier serving as the Single Buyer, and a sole supplier to multiple privately owned and government
owned distribution companies.
Forecasting
4.3.75 Scope of Application: With one exception, the draft resource acquisition regulations requires all
Permitted Persons to forecast annually, for a minimum of five years, the growth in electric load and
electric power needs in accordance with methodology and guidance provided by MOEP. See Section
5(a)&(b) of Item 4 Appendix E. Permitted Persons authorized to engage in Distribution and Retail Power
Supply are not required to perform forecasts for so long as they remain captive customers of only one
source of wholesale power. Under such circumstances, that sole supplier of wholesale power shall
forecast load growth for all of its captive customers, specifically load growth for the service territories
of Permitted Persons authorized to engage in Retail Power Supply. See Sections 5(e)(ii) and 5(e)(i) of
Item 4 Appendix E respectively.
4.3.76 Interim Methodology: Until the Ministry has issued its forecasting methodology and guidance on same,
forecasting will involve simple expansions of supply side resources and the MOEP shall approve
forecasts if it concludes that, (i) the methodology used was reasonable and properly performed; and
(ii) the assumptions underlying the forecasts appear reasonable and not imprudent. See Section 5(c)(i)
of Item 4 Appendix E.
4.3.77 Integrated Resource Planning: At such time as the MOEP issues its forecasting methodology and
guidance thereon, forecasting will thereafter be considered Integrated Resource Planning. Forecasts of
total electricity demand should be disaggregated by sector, end-use, technology, and customer classes.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 55
Based on these end-use demand break-downs and existing electric demand forecasts, disaggregated
projections of future levels of energy service growth are made. See Section 5(d) of Item 4 Appendix E.
4.3.78 Standard for Approval: MOEP shall approve forecasts performed in accordance with the forecast
methodology and guidance issued by the MOEP without obvious flaw or error. Departures from the
Mi ist s ethodolog a d guida e a e a epta le fo a demonstrable good cause. See Section 7 of
Item 4 Appendix E.
Investments, Power Procurement and Resource Acquisition Plans
4.3.79 Preparation: Permitted Persons who have Captive Customers are required by the draft resource
acquisition regulations to prepare annually for review and approval an Investment, Power
Procurement and Resource Acquisition Plan which sets forth the actions planned to be taken by such
Permitted Persons to satisfy forecasted growth in demand, and to otherwise satisfy their respective
service obligations. See Section 9(a) of Item 4 Appendix E.
4.3.80 Investment, Power Procurement and Resource Acquisition Plans are required by the draft resource
acquisition regulations to address a ten year period with significant details for the first two years.
Investment, Power Procurement and Resource Acquisition Plans are to, (i) identify the optimal
combination of actions required to be taken by Permitted Persons with Captive Customers to be able
to satisfy their respective service obligations at least cost; and (ii) demonstrate to consistency with the
National Electric Power Development Plan to the satisfaction of MOEP. See Section 9(b) of Item 4
Appendix E.
4.3.81 Investment, Power Procurement and Resource Acquisition Plans are required by the draft resource
acquisition regulations to include lists of all wholesale power sources and supply that have thus far
been approved by MOEP for the applicant and any revisions thereto proposed by applicant as required
for the applicant to satisfy its needs for power at least, and to comply with its service obligations. See
Section 10(b)(i) of Item 4 Appendix E.
4.3.82 Standard for Approval: MOEP shall approve Investment, Power Procurement and Resource Acquisition
Plans proposed by Permitted Persons with Captive Customers based upon demonstrated consistency
with the National Electric Power Development Plan, long term balance between reliable power supply
and usage, and satisfaction of their respective service obligations at least cost. See Section 17 of Item
4 Appendix E.
4.3.83 Filing Requirements: Applications for MOEP approval of Investment, Power Procurement and
Resource Acquisition Plans are required by the draft resource acquisition regulations to include the ten
items identified in Section 11 of the regulations. The items required to be filed include, (i) a summary
of actions to be undertaken by the applicant per the Investment, Power Procurement and Resource
Acquisition Plan; (ii) an identification of all supply side and demand side options and the economic
assumptions considered in the preparation of the Investment, Power Procurement and Resource
Acquisition Plan; (iii) an explanation of the methodology used to prepare the Investment, Power
Procurement and Resource Acquisition Plan; and (iv) a summary of the impact the subject Investment,
Power Procurement and Resource Acquisition Plans is expected to have on the appli a t s ta iffs. See
Section 11 of Item 4 Appendix E.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 56
Power Procurement Permission
4.3.84 MOEP Permission: When the national transmission company or a Permitted Person engaged in
distribution and retail power supply (after becoming responsible for forecasting load growth when
such Permitted Person can purchase power from multiple wholesale power suppliers) determines that
it needs an additional source or supply of power to satisfy its service obligations, and upon its
selection of a specific power source or power supply as offering the best effective price obtainable,
that Permitted Person may request the Ministry to grant it permission to procure power from that
source or supply of power. However, MOEP permission to procure power from a specific power source
or supply of power is not necessary if that specific source or supply of power was identified as MOEP
approved in a Power Development Plan included in an Investment, Power Procurement and Recourse
Acquisition Plan approved by the Ministry within the last five (5) years. See Section 15 of Item 4
Appendix E.
4.3.85 Standard for Approval: MOEP shall grant its permission for the applicant to procure power from a
specific power source or supply of power and to negotiate a power acquisition contract to meet load
growth or reduce power purchase costs upon its determination as to the prudence of the proposed
procurement. See Section 17 of Item 4 Appendix E.
Project Specific Power Procurement
4.3.86 MOEP Approval Forums: The draft resource acquisition regulations permit requests for MOEP approval
of specific sources or supply of power to either be included in applications for MOEP approval of
Investment, Power Procurement and Resource Acquisition Plans or submitted separately with MOEP.
See Section 19 of Item 4 Appendix E.
4.3.87 Filing Requirements: The draft resource acquisition regulations require applications for MOEP approval
of power procurement from a specific power plant to include a term sheet or comparable document
setting forth key commercial understandings. See Section 20 of Item 4 Appendix E.
4.3.88 Standard for Approval: MOEP shall approve a proposed procurement of power from a specific power
plant once it is satisfied that the proposed procurement meets the appli a t s se vice obligations at
least cost and in accordance with prudent utility practices. See Section 21 of Item 4 Appendix E.
Power Purchase Agreements
4.3.89 MOEP Approval Required: Power purchase agreements to which a Permitted Person with Captive
Customers proposes to become a party shall obtain MOEP approval before such agreements can be
executed by said Permitted Persons. See Section 23 of Item 4 Appendix E.
4.3.90 Filing Requirement: Applications for Ministry approval of a power purchase agreement shall include a
statement providing justification for the rates, terms and conditions proposed to be agreed to under
the power purchase agreement. See Section 24 of Item 4 Appendix E.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 57
MOEP Regulations on Competitive Tenders and Solicitations:
4.3.91 The new Electricity Law did not address the topic of competitive procurement of new generation and
wholesale power supply. Nonetheless, competitive solicitations are certainly consistent with the
o je ti es of the Ele t i it La to encourage local and foreign investment in the power sector, to
create a conducive environment for private investment, the eatio of transparent and appropriate
rules and regulations to prescribe electricity rates , a d the sha i g of i fo atio go e e t departments with private organizations and private investors with the general public to create public
awareness and transparency.
4.3.92 The importance of competitive procurement of new generation and new sources of wholesale power
supply is globally recognized. This recognition is the likely genesis of the prohibition in the draft
Electricity Rules against buying power from new IPPs unless such purchases resulted from competitive
power solicitation programs are approved by the MOEP. See Rule 77 of Appendix D. This prohibition is
probably the reason for extending the high priority for preparation to regulations on competitive
solicitations.
4.3.93 Once tasked with the preparation of these regulations, the DFDL Consulting Team was informed that
the ADB had retained Deloitte Touche to prepare guidance on competitive bidding. After meeting with
Deloitte and the DFDL Consulting Team, the ADB decided that drafting of the competitive bidding
regulations should await receipt of the guidance being prepared by Deloitte.
4.3.94 Two features of the guidance on competitive bidding that was prepared by Deloitte were discussed by
the DFDL Consulting Team. First, the guidance focused exclusively on a form of competitive bidding
able to impose competitive discipline on unsolicited power projects. This would have typically, in our
experience of competitive bidding guidance, included other scenarios. Second, during the initial
reading, the basis for awarding projects between the original project proponents and competitors
seemed simplified and could result in non-optimal project selection.
4.3.95 Upon further discussion and reflection from the DFDL Consulting Team, the exclusive focus of the
guideli es o this o e fo of o petiti e iddi g ost ofte efe ed to as a “ iss Challe ge as the correct approach. Under this type of bidding program, the project proponent enters into a
memorandum of understanding (MOU) that permits the proponent to conduct the feasibility study,
preliminary environmental assessments, and the requisite site studies. The MOU also sets forth the
budget for this development work and the agreement for the project proponent to transfer this
i telle tual p ope t to a othe de elope , if that othe de elope s p oje t p oposal is supe io to the propone t s p oposal a d the othe de elope akes pa e t to the p opo e t of the a ou t of the development budget set forth in the MOU which authorized the original proponent to perform the
feasibility study.
4.3.96 The MOEP appears swamped with unsolicited proposals that need to be processed and evaluated. The
processing and extensive negotiations required for unsolicited projects prolong project development
and increases project costs. Furthermore, there is no baseline against which the subject power
purchases can be evaluated. Finally, absent competitive pressures, there is no assurance that the power
purchased is priced at the lowest reasonable cost.
4.3.97 Given the limited resources and experience of the MOEP and the Government with IPPs and
competitive bidding, had the guidance from Deloitte addressed other forms of competitive tenders,
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 58
this would likely have caused confusion and would certainly have extended the time required to finalize
these draft bidding regulations.
4.3.98 Following the instructions of the ADB to draft these regulations in accordance with the content of the
guidance prepared by Deloitte, the draft bidding regulations were prepared and delivered to the DG of
the DEP for review by and discussions with the Steering Committee. Such review and discussions took
place during the second week of November 2015. Significant efforts on behalf of the DG and the
Steering Committee enabled two rounds of review and revisions to be concluded, and the draft
regulation to be nearly finalized by 31 December 2015.
The final version of the draft regulations on competitive solicitation/tenders is set forth as Item 5 of
Appendix E hereto. The following is a brief summary of the content of these draft regulations.
Part I- Scope of Bidding Regulations:
4.3.99 Eligible Projects. Subject to certain exceptions, all Eligible Projects for which pre-tendering activities by
the proponents of unsolicited projects are subject to competitive tenders. See Section 3.1 of Item 5
Appendix E.
4.3.100 Eligible Projects shall exclude those power plants which (i) the Union Government determines should
not be subject to competitive tender, and (ii) new or strategic technologies that have been exempted
from bidding by the MOEP. See Sections 3.2 and 3.4 of Item 5 Appendix E respectively.
4.3.101 Unsolicited proposals for power plants involving long term contractual power purchase obligations for
which an MOU with the MOEP providing for the performance of a feasibility study have been executed
by the date of the notification of these regulations are not be subject to competitive tenders. See
Section 3.1 of Item 5 Appendix E.
4.3.102 Eligible Projects must have been assessed by the MOEP and considered technically feasible and
consistent with Myanmar power sector master plan. See Section 4(b) of Item 5 Appendix E.
4.3.103 Joint MOEP Shareholding. Projects under joint shareholding with the MOEP shall require joint venture
(JV) agreements to be executed with MOEP and engineering, procurement and construction (EPC)
contracts (as well as operation and maintenance contracts, where applicable), to be tendered through
transparent, international competitive bidding processes. See Section 3.3 of Item 5 Appendix E.
Part II- Eligible Projects: Identification and Approvals:
4.3.104 Designation for Competitive Tenders. Construction, expansion and modernization of grid-connected
power projects larger than 30 MW of any of the eight different types of generation plants identified in
Section 4(a) of these draft bidding regulations shall be considered an Eligible Project. See Section 4(a)
of Item 5 Appendix E.
4.3.105 The MOEP shall designate those Eligible Projects that are to be considered for development by
competitive tender based upon an MOEP assessment technical feasibility and consistency with the
Myanmar power sector master plan. See Section 4(aa) of Item 5 Appendix E.
4.3.106 Budget Requirements for Pre-tendering Works. MOEP to identify the budget requirements of the
proponent of the unsolicited project for pre-tendering activities including performance of the feasibility
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 59
study, preliminary environmental assessment, and those studies regarding site identification,
rehabilitation, resettlement and obtaining necessary consents and clearances. The budget for pre-
tendering activities shall be specified in the MOU executed with MOEP which authorizes the proponent
to perform the feasibility study. See Section 4(bb) of Item 5 Appendix E.
Part III- Bid Process Management:
4.3.107 Bid Process. Eligible Projects shall be undertaken for competitive bidding on a Build, Operate, Transfer
(BOT) basis. See Section 4(dd) of Item 5 Appendix E.
4.3.108 The bidding process shall be conducted by way of standard international power industry practices for
competitive solicitations for power procurement from privately owned power plants. See Section 6(b)
of Item 5 Appendix E.
4.3.109 The draft bidding regulations permit the use of stage or two stage bidding processes. In the two stage
process, the first solicitation (the Request for Qualifications) solicits potential bidders who are
interested in submitting a project proposal and is willing to submit its qualifications in support of its
inclusion on the shortlist of companies that will be permitted to submit a project proposal. See Section
6(b) of Item 5 Appendix E.
4.3.110 Bid Process Management. The draft bidding regulations would require proponents of unsolicited
projects to execute MOUs with the MOEP to obtain authorization to perform their respective feasibility
studies. These MOUs would also specify (i) the budget for the feasibility study and other pre-tendering
works, and (ii) importantly, the amount of compensation required to be paid to the proponent in the
event the subject unsolicited project is not awarded to the winning proposal and not to the Proponent.
See Sections 4(bb) and 6(a) of Item 5 Appendix E.
4.3.111 The MOEP cannot initiate a competitive tender for an Eligible Project that is an unsolicited project until
the proponent of the unsolicited project completes the feasibility study and other pre-tendering works
set forth in the relevant MOU executed with the MOEP. See Section 4(bb) of Item 5 Appendix E.
4.3.112 Upon completion of pre-tendering activities by the proponent of an unsolicited project approved as an
Eligible Project, such project shall be subjected to competitive tender. See Section 4(cc) of Item 5
Appendix E.
4.3.113 The Ministry shall be required to publish notice of competitive tenders in at least two (2) national
e spape s, t o i te atio al E glish e spape s, the Mi ist s e site a d othe p i t/digital media, as it deems fit, inviting participation from prospective bidders. See Section 6(b) of Item 5
Appendix E.
4.3.114 The Request for Qualification (RFQ) stage shall provide persons interested in qualification to raise
questions and obtain answers regarding project details and qualifications requirements by means of
electronic communications with the MOEP. The expressions of interest and qualifications received in
the RFQ stage shall be opened at the notified time in the presence of representatives of the bidders
who wish to attend. See Section 6(e)&(f) of Item 5 Appendix E.
4.3.115 The Request for Proposal (RFP), the project feasibility report and other development studies and
documentation prepared by the proponent of the unsolicited project, the amount of compensation to
be paid to the project proponent if the subject project is awarded to a third party, and the standard bid
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 60
documentation prepared by the MOEP in accordance with the requirements of these regulations
project documentation shall be distributed to the shortlisted Bidders. See Section 6(c)&(h) of Item 5
Appendix E.
4.3.116 Proposals submitted by bidders in response to the RFP shall be comprised of the Technical Bid and the
Financial Bid. The RFP stage shall provide for a pre-bid conference to inform the bidders about the
selection process and the finer details about the project. See Section 6(c)&(i) of Item 5 Appendix E. The
Ministry shall instruct the Bid Evaluation of the shortlisted Bidders whose Non-Financial Bid stands
responsive. See Section 6(i)(3) of Item 5 Appendix E.
4.3.117 Selection Process. The process for selection of the successful bidder shall be based on the methodology
specified in Section 10 of these regulations. The evaluation of the Financial Bid shall be guided by the
following:
a. The aggregate of the components of the Capacity Charges (investment charges and fixed
component of O&M charges) shall be computed for each year;
b. The Net P ese t Value NPV of the agg egate o po e t shall e o puted fo ea h ea based on the discount rate specified in the RFP from the estimated date of commissioning;
c. The NPV shall then be discounted to arrive at the levelized component of the Capacity Charges;
d. Similarly, the levelized component of Notional Fuel charges (in case of coal and gas based plants)
and fixed O&M Charges shall be computed.
See Section 10(a) of Item 5 Appendix E.
4.3.117 The financial bid of a bidder shall be rejected if it contains deviation from the tender conditions specified
in the RFP. The final levelized tariff shall comprise of the summation of the levelized components of
the Capacity Charges, Variable O&M Charges and Notional Fuel Charges (for coal and gas based plants).
See Section 10(b) of Item 5 Appendix E.
4.3.118 The bidder with the lowest levelized tariff shall be declared as the successful bidder by the Selection
Committee. In case of a tie, the financial qualification requirement of Net worth of the Bidder shall be
considered and the tied Bidder with the higher Net worth shall be declared as the successful Bidder.
See Section 10(c)&(d) of Item 5 Appendix E.
4.3.119 Selection Committee. The Selection Committee shall shortlist the Bidders for the RFP stage based upon
the responses received in the RFQ stage. See Section 6(g) of Item 5 Appendix E.
4.3.120 For so long as the MOEP is responsible for implementation of the bidding process required by these
regulations, the Selection Committee shall issue letters of award. See Section 5(d) of Item 5 Appendix
E.
4.3.121 The Selection Committee shall have the power to approve successful bidders based on the criteria
formulated as set forth in RFPs. See Section 6(f) of Item 5 Appendix E.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 61
4.3.122 The Selection Committee reserves the right to reject any or all the bids for any reason and waive any
minor defects therein. In all matters related tote bid evaluation and the selection of bidder, the decision
of the Selection Committee shall be final and binding. See Section 10(f) of Item 5 Appendix E.
Part IV- Preparatory Activities:
4.3.123 Before the MOEP initiates a competitive tender for an Eligible Project, the following key preparatory
activities shall either have been either initiated or completed, as applicable: (i) completion of the
standard bid documentation in accordance with the requirements of these regulations; (ii) the site
identification and land-related clearances by the project proponent; (iii) the environmental assessment
for the subject power plant by the project proponent, and (iv) approval of the use of forest land, fuel
arrangements, water arrangements, and other requisite governmental approvals for the subject power
plant as required by applicable law. See Section 7(a) of Item 5 Appendix E.
4.3.124 Standard Bidding Documents: MOEP shall prepare the project specific bid documents (RFQ, RFP and
PPA) in accordance with these regulations. Project specific bid documents shall contain inter alia the
following information: (i) bid evaluation methodology and selection process; (ii) minimum design and
performance standards for the subject power plant, including minimum functional specifications; (iii)
draft power purchase agreement setting forth the key commercial terms and contractual arrangements
and the respective roles and responsibilities of the parties thereto; (iv) instructions to potential bidders
related to meeting the qualification criteria, submission of bids and the selection criteria and process;
(v) the requisite bid formats for the Request for Qualification (RFQ) and, the Request for Proposal (RFP)
stages; and (vi) key timelines for each stage of the bid process.
4.3.125 Requests for Qualifications (RFQ): RFQs all specify the amount of contracted capacity proposed,
including the specific unit size, technology type and a flexibility to operate within a range of specified
capacity. See Section 7(b) of Item 5 Appendix E. RFQs shall set forth project specific details related to
site, status update on key preparatory activities as specified these regulations. RFQs shall set forth the
following information:
a. The term for PPA with the standard term of 15 years for natural gas fired power plants and 25
years in case of coal-based plants, with variations permitted as per the sector requirements as
determined by MOEP;
b. Minimum qualification criteria: These shall pertain and include but not limited to the
following: See Section 7(b)(4) of Item 5 Appendix E.
Legal Requirement: International firms may be allowed to participate.
Technical Requirement: Experience in (i) development and successful
commissioning of similar projects conducted in the last seven years; (ii)
operations and for similar capacities. In addition to the requirement, individual
capacity (MW) of at least one unit size shall be specified to be met as the
minimum size of each project; and
Financial Requirement: Net worth criteria of a minimum of 0.25 million USD/MW
in any of the last three financial years. Methodology for computation of NPV
worth shall be clearly specified in RFQs.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 62
c. Specific forms are to be provided by MOEP for submission of responses to RFQs, including
o e i g lette , po e of atto e , o so tiu ag ee e t, o e ship st u tu e, idde s undertakings, technical and financial criteria. Finally, the bidding regulation sets forth
evaluation criteria and the process for RFQ responses and procedures of shortlisting of
qualified bidders for RFP stage. See Section 7(b)(7) of Item 5 Appendix E.
4.3.126 Requests for Proposals (RFPs): RFPs shall include: (i) conditions precedent for signing or effectiveness
of the PPA, including submission of performance guarantee and execution of share purchase
agreement; (ii) specific formats related to Power of Attorney, Board of Directors resolutions, bid bond,
undertakings, and financial bid; and (iii) procedures regarding submission of bids and the evaluation of
bid. See Section 7(c) of Item 5 Appendix E.
4.3.127 Power Purchase Agreements (PPAs): The PPAs to be included in the standard bidding documents are
required by the draft bidding regulations to address twenty contractual topics identified by these
regulations as key obligations. All twenty of these key obligations are standard topics commonly
addressed in long term PPAs typically used for power plants with limited recourse debt financing.
Part V- Contract Award:
4.3.128 Upon the selection of the preferred bidder, the proponent of the unsolicited project shall be informed
of the terms, conditions and tariff offered by the preferred bidder and the proponent of the unsolicited
project may match such offer. If the proponent of the unsolicited project elects in writing not to match
the offer of the preferred bidder, the subject project shall be awarded to the proponent.
4.3.129 If the proponent of the unsolicited project fails to elect in writing to match the offer of the preferred
bidder within thirty (30) days of being informed of the terms, conditions and money offered by the
preferred bidder, the subject project shall be awarded to the preferred bidder subject to the
requirement that the preferred bidder to pay compensation to the proponent as specified in MOU for
the subject project executed by the proponent. See Section 11(a) of Item 5 Appendix E.
4.3.130 If the preferred bidder is awarded the subject project, the preferred bidder shall submit the
performance security within the period of time stipulated in the relevant PPA, failing which its Letter of
Award may be cancelled and its bid security forfeited. If the preferred bidder is awarded the subject
project, the preferred bidder shall cause the PPA for the subject project to be executed within 60 days
of its receipt of the Letter of Award and provide the performance security in accordance the terms of
the subject PPA, failing which its Letter of Award may be cancelled, its bid security forfeited and another
bidder may still be selected instead. See Section 11(d) of Item 5 Appendix E.
Part VI- Solicited Generation Capacity and Power Projects:
4.3.131 Solicited Projects. Generation capacity and power plant additions that are Eligible Projects but do not
involve unsolicited projects from which electric power is to be procured by the MOEP or Permitted
Persons shall be selected by means of competitive tenders. See Section 12 of Item 5 Appendix E.
4.3.132 Direct negotiation for power procurement not involving unsolicited projects shall be resorted to under
the following conditions by the Selection Committee: (i) if, after notification of RFQ, only one bidder
submit the response to RFQ and is found to be meeting the qualification requirements; (ii) if, after
notification of RFQ, more than one bidder submits the response to RFQ, but only one bidder is found
to satisfy the qualification requirements; (iii) if, after issuance of RFP, only one bidder submits the bid
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 63
and is found to satisfy the requirements of the RFP; or (iv) if, after issuance of the RFP, more than one
Bidder submits a bid proposal, but only one bid proposal is determined to satisfy the requirements of
the RFP. See Section 13(a) of Item 5 Appendix E.
ERC Procedures:
4.3.133 When the project contract was extended for the first time until 30 September 2015, the selection of
the six regulations for prioritized preparation was based in large part upon the assumption that the
Electricity Rules would reintegrate the ERC into the regulatory process, and that the provisions in the
draft Electricity Rules addressing the internal organization, procedures and process for the ERC to be
set forth in the Electricity Rules would need to be supplemented by more detailed regulations.
4.3.134 Accordingly, when work began on these six regulations in April 2015, the preparation of the regulations
to govern the internal structure, process and procedures of the ERC remained a top priority. Indeed,
the DG of the DEP identified the ERC regulations as having the highest priority behind finalization of the
Electricity Rules. As such, the draft regulation on ERC internal organization, process and procedures
delivered to the DG and the Steering Committee focused on regulatory features and requirements
intended to enhance the transparency, independence, and accountability of regulation by the ERC. A
copy of this draft regulation is attached hereto as Item 6 of Appendix E.
4.3.135 As explained above, by the time the draft ERC regulations were ready for review and discussion with
the Steering Committee, the Minister of the MOEP had given instructions to eliminate the ERC related
provisions from the draft Electricity Rules and to concentrate all regulatory tasks and responsibilities
within the MOEP. Elimination of the ERC from the regulatory process rendered the draft regulation on
ERC internal organization, process and procedures largely irrelevant. Further, the DG indicated that the
MOEP will not be involved in issuing the rules and procedures that will govern the activities of the ERC.
All work related to ERC process and procedures were indefinitely suspended.
4.3.136 However, in late October 2015, the DG and the Steering Committee determined that although the
MOEP is unlikely to be involved in the issuing of the rules and procedures for the ERC, the difficulties
facing the establishment of the ERC would be reduced if MOEP work on the ERC organization and
internal rules and procedures could be completed, and a finalized package provided to whatever
government institution is ultimately assigned responsibility for prescribing such regulations. Work on
the draft regulations on the ERC processes and procedures then resumed.
4.3.137 The revised draft of the ERC processes and procedures essentially combined, in a single document, all
of the rules of the Initial Version of the Electricity Rules related to the ERC that had been deleted from
the Electricity Rules. Given the lack of immediate importance regarding these regulations, the DG and
the Steering Committee spent less effort on the ERC processes and procedures. These processes and
procedures were renamed the ERC Procedures since the ERC does not have the authority to issue rules
and regulations. The final version of the draft ERC Procedures are attached hereto as Item 6 of Appendix
E. The following summarizes the substance of these draft ERC procedures.
ERC Organization:
Composition and Appointment
4.3.138 The Electricity Law requires the Union Government to establish the ERC as a commission comprised of
a Chairman and four to six Commission Members, With two or three exceptions, the Chairman and the
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 64
Commission Members shall serve initial five year terms.
4.3.139 The draft ERC Procedures would require the initial term of two or three Commission Members to be
limited to three years, with all subsequent terms of Commission Members consisting of five year terms
The draft ERC Procedures would limit Commission Members to two appointments. See Section 3(b) of
Item 6 Appendix E.
4.3.140 The Chairman and the other Commission Members shall be employed full time and are to be eminent
professionals of known integrity and competence with experience in law, business, engineering,
finance, accounting, economics, business management or administrative management. In addition, the
draft ERC Procedures would require the Chairman and Commission Members to have at least five (5)
years and three years of experience, respectively, in the electric power business. See Section 3(d)&(e)
of Item 6 Appendix E.
4.3.141 The Chairman and other Commission Members shall not have any other employment for any other
activities directly or indirectly related electric power business. While employed at the Commission, the
Chairman, Commission Members, and Commission employees (and their spouses, children and parents)
shall not enter into the employ of any Permitted Person or permitted electricity related business. In
addition the ERC Procedures will prohibit the foregoing persons from, (i) serving as consultants to or
hold advisory positions thereto; and (ii) owning stocks or bonds of, or have any pecuniary or financial
interest in any Permitted Person.
Chairman
4.3.142 The draft ERC Procedures would assign the Chairman the following powers and duties: (i) set the
agenda and schedule Commission meetings; (ii) preside over Commission meetings; (iii) casting vote
to be used when there is an equality of votes; (iv) hire the Commission Secretary and the Commission
Officers; (v) determine the employment terms and conditions of the Commission Secretary and other
Commission Officers in consultation with other Members; (vi) prioritize work efforts and functions; (vii)
be responsible for supervising the management and administration of the Commission Office; (viii)
preparation of the annual budget for consideration and approval of the Commission; and (ix) designate
in writing another Member to fulfill temporarily some of the duties otherwise the responsibility of the
Chairman. See Section 4 of Item 6 Appendix E.
Dismissal
4.3.143 The Chairman and other Members shall be dismissed from office under following situations: (i)
conviction of a criminal offense; (ii) mental or physical incapacity; (iii) serious violation of restriction
regarding conflicts of interest; and (iv) seriously neglected or abandoned his or her duties. See Section
5 of Item 6 Appendix E.
Commission Office
4.3.144 The Commission Office comprises the administrative and professional staff and employees, physical
plant, facilities and equipment required to support Commission activities. The organization and
functioning of the Commission Office shall be determined by the Commission.
4.3.145 The Commission Office is to (i) provide professional and technical support to the ERC; (ii) establish and
maintain public records; and (iii) house a legal department, economics department, engineering and
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 65
technical support department, and an administrative and management department. The draft ERC
Procedures allow the Chairman to establish such new departments as the Chairman may deem
necessary. The draft ERC Procedures would require the Chairman and the Commission Officers to
employ administrative and professional staff solely on the basis of merit.
ERC Responsibilities:
ERC Functions and Duties
4.3.146 The draft ERC Procedures acknowledges that the Commission shall need to perform the functions and
duties prescribed in Section 5 of the Electricity Law. As requested by the Union Government, the ERC
shall review and make substantive comments to the Union Government on MOEP regulatory decisions
for the approval of the Union Government. In addition, as requested by the MOEP, the Commission
shall provide written advice and opinions on fixing and amending tariffs and matters related to the
power sector and power sector regulation. Finally, the ERC is to prepare and advice regarding new
methodologies for determining tariffs for consideration by the Union Government, the Ministry, other
Permitting Authorities, Permitted Persons and other interested Persons. See Section 7 of Item 6
Appendix E.
Independence and Autonomy
4.3.147 The draft ERC Procedures would require the Commission to perform its duties and functions
independent from the Ministry, which include opening and maintaining a bank account in its own
name, and preparing an annual budget for its activities and operating expenses for submission to the
Ministry of Finance.
Financial Reports
4.3.148 The Commission shall prepare annual financial statements, which are to be audited, no later than one
month after the end of each financial year. Within one month after such auditing, the Commission shall
submit all reports to the Union Government and make available for public review.
Commission Reports
4.3.149 The Commission shall submit, to the Union Government, a business report every (6) months which shall
include, (i) the affairs conducted for that year and anticipated developments for the following year;
and (ii) the state of electricity-related works within Myanmar.
ERC Meetings and Procedures:
4.3.150 Advance Notice and Agenda: The Chairman shall provide each Commission Member at least ten
(10) days advance written notice of the date, time and location of each meeting of the Commission,
together with a list of all matters to be considered by the Commission.
4.3.151 Quorum and Voting: A majority (above 50 percent) of the Commission Members shall constitute a
quorum, and decisions shall be taken by majority votes of the Commission Members present at duly
constituted meetings of the Commission.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 66
4.3.152 Commission Decisions: All orders, determinations and decisions of the Commission shall be made in
writing and shall set forth the legal and factual basis in support of such decisions.
4.3.153 Public Attendance: All meetings of the Commission shall be publicly noticed and open to public
attendance and observation.
4.4 Analysis and Assessment
4.4.1 The six draft regulations prepared on a prioritized basis represent a considerable effort on the part of
the DG and the Steering Committee over the last nine months. These efforts have been fruitful,
resulting in regulations which are, for the most part, ready for issuance, workable and able to support
MOEP regulation becoming operational. Also, in several regards, the draft regulations include features
that will move power sector regulation closer to international best practices.
Filing Regulations:
4.4.2 The draft filing regulations are ready for issuance and are complete in that they address all of the
elements of regulatory proceedings. The draft regulations have been intentionally kept basic and simple
in order to minimize confusion and reduce the difficulties of application when first applied. The draft
regulations include features consistent with international best practices, such as the publication of
notices of all regulatory filings, an opportunity for members of the public who could be adversely
affected to participate in regulatory proceedings, and the possibility of a public hearing regarding
disputes as to material facts as necessary to arrive at a just and reasonable result. These features should
help to improve the transparency of MOEP regulation.
4.4.3 The only possible shortcomings of the draft filing regulations are for the requirements for the MOEP to
render regulatory decisions (i) within 120 days of the date on which the relevant applications were
accepted for filing; and (ii) regarding reconsideration requests within 30 days of the receipt of such
requests. These deadlines seem overly ambitious and should be revised to provide more realistic
deadlines.
Permitting Regulations:
4.4.4 The draft permitting regulations are also ready for issuance and are complete in that they address
applications for, revisions and modifications, and suspensions and revocations of Permits, as required
by Rule 80 of the Electricity Rules. The draft regulations have also been intentionally kept as simple as
possible to minimize confusion and reduce the difficulties of application when first applied.
4.4.5 The draft permitting regulations set forth the form for Permit applications and the information required
to be provided for in (i) all Permit applications; (ii) applications for each type of Permit and each type
of Electricity Related Works; (iii) applications involving both existing and new power facilities; and (iv)
applications for each type of power facility, including thermal and hydro power generation,
transmission and distribution.
4.4.6 From the perspective of private developers, there are two features that are particularly noteworthy.
First, transparency of regulation is promoted by the requirement that the MOEP, if it intends to deny a
permit application, is required to give the applicant an opportunity to make a presentation to the MOEP
as to the reasons its application should not be denied. Second, the draft permitting regulations prohibits
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 67
Permits from being issued and becoming effective until such time as the applicant has obtained all
requisite governmental approvals, and for generation Permits, execution of a power purchase
agreement pre-approved by MOEP.
4.4.7 The draft regulations set forth requirements that apply to all types of permitted power sector
participants as well as requirements specific to one or two types of participation. The draft regulations
further elaborates on the service obligations of power sector participations by means of the terms set
forth in the sample permits attached to the draft regulations.
4.4.8 In regards to enforcement, the draft permitting regulations break enforcement action into two stages.
The first stage follows the subject Permitted Person. After having been given an opportunity to provide
a written explanation and to remedy the subject violation, the MOEP may be directed to take
appropriate corrective action by another department of MOEP and/or to modify the subject Permit to
address the cause of such violation so as to prevent the violation from being repeated. The second
stage involves the imposition of sanctions and penalties. The draft permitting regulations authorize (i)
the imposition of financial penalties; (ii) Permit suspension; (iii) Permit revocation; and (iv) referral by
the MOEP to the appropriate government authorities or civil and criminal prosecution.
4.4.9 Overall, the draft permitting regulations comprehensively address this topic with sufficient detail and
flexibility to be effective, workable, and provide the ability to adjust permits as required in order to
support the ongoing evolution of the structure of the power sector and the possibility of more
aggressive structural reforms that may be pursued in the future. In this regard, the one shortcoming of
the draft regulation is the omission of any requirement to pay compensation to power sector
participants who are adversely impacted by permit revisions made by the MOEP to implement
government mandated structural reforms.
4.4.10 However, to minimize the adverse financial effects on Permitted Persons of unilateral modifications of
Permits to implement government policies on power sector structural reforms, a requirement should
added to the draft permitting regulations that requires Permitted Persons to be paid compensation for
the assets that are to be divested to achieve the power sector structure desired by the Union
Go e e t. “u h a e ui e e t ould alle iate p i ate i esto s o e s ega di g the legal
authority of MOEP to unilaterally revise Permits.
4.4.11 Such a requirement for the payment of compensation would be similar to the requirements already set
forth in the new Electricity Law which require payment of compensation, (i) when the National
Transmission acquires special transmission facilities once such special transmission facilities become
connected directly or indirectly with the national transmission system; and (ii) when a Permit either
expires or is prematurely terminated and the Permitted Person who has lost the Permit must transfer
facilities and equipment to the new Permitted Person who has assumed responsibility for the Electricity
Related Works in which the prior Permitted Person had been engaged.
Tariff Regulations:
4.4.12 The draft tariff regulations are also ready for issuance and are complete. As agreed with the DG of the
DEP and the Steering Committee, the draft tariff regulations provide a detailed and comprehensive
framework for tariff calculations. The draft tariff regulations set forth formulas by which tariffs are to
be determined for each type power sector activity and for each type power generation technology. The
draft tariff regulations provide the details needed to establish revenue requirements, permissible
returns on equity, and the other cost categories of relevance to tariff calculations.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 68
4.4.13 Of particular note, to accommodate the current lack of familiarity in Myanmar with tariff regulation,
the draft tariff regulations incorporate sufficient flexibility for assumptions and input values initially
specified to be revised as experience with tariff regulation is gained. This was achieved by specifying
many of the key variables for the calculation of tariffs into orders to be issued by MOEP, thus allowing
revisions of such key variables without having to obtain Parliamentary approval, as would be required
to modify regulations.
4.4.14 The draft tariff regulations elaborate on the principles governing tariff determinations that are intended
to assure power sector participants of the opportunity to recover all prudently incurred costs and to
earn sufficient revenue promote investments and incentivize efficiency and quality improvements in
the power supply. With two exceptions, the draft tariff regulations create a general prohibition against
cross-subsidies. Existing cross-subsidies from non-household to household customers are required by
the draft tariff regulations to be phased out gradually.
4.4.15 The two exceptions to the foregoing prohibition are the permitted use of rising block tariffs for
households and a uniform national retail tariff. The cross-subsidies between customers of different
retail power suppliers required to sustain uniform retail power tariffs is to be achieved by charging
different wholesale power supply tariffs to different retail power suppliers. The adjusted wholesale
tariff differs between retail power suppliers with higher revenues and lower costs paying a higher
wholesale tariff to allow a lower wholesale tariffs for retail power suppliers lower revenues and higher
costs.
4.4.16 The draft tariff regulations have also been intentionally kept as simple as possible to minimize confusion
and reduce the difficulties of application when first applied. Overall, the draft tariff regulations
comprehensively address this topic with sufficient detail and flexibility for tariff regulation to be
workable and effective. The detail in the draft proposed tariff regulation as to how each type of tariff is
to be calculated will improve the transparency of the tariff regulation; which should overtime engender
increased public confidence and willingness to accept raising tariffs as tariffs are increased to costs of
electric power supply an service.
Investments, Power Procurement and Resource Acquisition Regulations
4.4.17 The draft regulations regarding investments, power procurement and resource acquisitions are
intended to transition power sector participants into the performance of forecasting, least cost
planning, and acquisition of assets and resources required to satisfy their respective service obligations.
This transition is to achieve the two objectives of, (i) helping to ensure power sector participants obtain
the resources and facilities required to satisfy their respective service obligations at lowest reasonable
cost; and (ii) promoting efficient and coordinated planning for the power sector.
4.4.18 These objectives are to be achieved by these draft regulations requiring most all power sector
participants to annually forecast future growth in demand for their respective electric power services
and, for those participants with captive customers, requiring, (i) the annual preparation of a multiyear
Investment, Power Procurement and Resource Acquisition Plan for MOEP review and approval; (ii)
MOEP permission to procure power from a specific source or supply of power; and (iii) obtain MOEP
approval of power purchase agreements before execution.
4.4.19 The draft regulations acknowledge the difficulties associated with the implementation of the foregoing
requirements. The Electricity Rules require MOEP to, (i) develop a forecasting methodology and
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 69
guidance thereon to be applied by power sector participants; and (ii) annually prepare the National
Power Development Plan with which the investment, power procurement and resource acquisition
plans of power sector participants must be demonstrated to be consistent.
4.4.20 However, until MOEP has issued its forecasting methodology and guidance, forecasting by power sector
participants will involve simple expansions of supply side resources, and the MOEP shall approve
forecasts if it concludes that, (i) the methodology used was reasonable and properly performed; and
(ii) the assumptions underlying the forecasts appear reasonable and not imprudent. At such time as the
MOEP issues its forecasting methodology and guidance thereon, forecasting will thereafter be based
on Integrated Resource Planning.
4.4.21 The filing requirements and standards governing MOEP approvals specified in these draft regulations
should over time achieve the objective of helping to ensure power sector participants obtain the
resources and facilities required to satisfy their respective service obligations at lowest reasonable cost.
4.4.22 However, the capability of these regulations to achieve coordinated, efficient and comprehensive
planning for the power sector is more problematic. To achieve this objective would require the
establishment of a sequential and iterative process with procedures that integrate forecasting and
resource planning performed by multiple power sector participants. Other than requiring all forecasts
and resource acquisitions to be filed with MOEP annually before 31 October, these draft regulations do
not address the process and procedures to be followed by power sector participants in performing
forecasting and resource planning. However, this shortcoming needs not delay issuance of these
regulations. Communication among power sector participants responsible for transmission,
distribution and purchasing power from generators that remain government-owned should mitigate
the risks associated with the lack of regulatory mechanisms to achieve coordinated and integrated
planning for the power sector.
Competitive Tenders and Solicitations Regulations
4.4.23 The draft competitive tenders and solicitations regulations are based upon guidance on implementing
competitive bidding for power projects specifically tailored to Myanmar as prepared by Deloitte
Touche. Notwithstanding time constraints due to delayed receipt of this guidance, the DG and Steering
Committee produced draft regulations that would set forth a workable bidding regime able to impose
competitive discipline on unsolicited projects and their proponents. The type of bidding regime to be
e plo ed is alled a “wiss challenge, a d is desig ed to put unsolicited projects up for competitive
bid; whereby such projects can be awarded to a party other than the original proponent of the project
provided the winning bidder pays compensation to the proponent equal to the amount of
compensation the proponent would have had to agree to when it signed the MOU with MOEP.
4.4.24 The bidding regime that would be put into place by these regulations would key off of unsolicited
eligi le p oje ts. Eligi le projects are required to have been assessed by the MOEP and, if considered
technically feasible and consistent with Myanmar power sector master plan, are designated by MOEP
to be considered for development by competitive tender.
4.4.25 The p o ess fo dete i i g that a p oje t is eligi le a d desig ated the MOEP as appropriate for
development of by competitive tender needs to be completed early in the project development effort,
since the amount of compensation to be paid to the proponent, if the subject project is awarded to
another person, must be set forth in the MOU to be executed by the project proponent to obtain
authorization to proceed with the feasibility study and the performance of other pre-tendering works.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 70
4.4.26 Transparency of regulation and private sector participation in the power sector will be advanced by the
requirement in the draft tenders and solicitations regulations for the Ministry to publish notice of
competitive tenders in at least two national newspapers, two international English newspapers, the
Minist s e site a d othe print and digital media, as it deems fit, thus inviting participation from
prospective bidders.
4.4.27 These draft competitive tenders and solicitations regulations would require the RFP, the project
feasibility report and other development studies and documentation prepared by the proponent of the
unsolicited project, the amount of compensation to be paid to the project proponent if the subject
project is awarded to a third party, and the standard bid documentation prepared by the MOEP to be
distributed to all of the shortlisted bidders.
4.4.28 Upon the selection of the preferred bidder, the proponent of the unsolicited project shall be informed
of the terms, conditions and tariff offered by the preferred bidder and the proponent of the unsolicited
project may match such offer. If the proponent of the unsolicited project fails to elect in writing to
match the offer of the preferred bidder, the subject project shall be awarded to the preferred bidder
subject to the requirement that the preferred bidder pay compensation to the proponent as specified
in MOU.
4.4.29 As is evident from the foregoing, the draft competitive tenders and solicitations regulations are
comprehensive and workable, but should still more properly be viewed as a work in progress that
requires some refinements ideally before these regulations are issued and become operational.
4.4.30 First, process and procedures need to be put into place for obtaining projects from the MOEP such as
(i) determination that a u soli ited p oje t is eligi le , a d ii) after completion of the pre-tendering
o ks of the p oje t p opo e t, desig atio that the u soli ited eligi le p oje t is appropriate for
development by competitive tender. It is critically important to define the process for obtaining a
dete i atio that a p oje t is eligi le, as any delays caused by confusion as to the process would
likely lengthen the approval period and increase the project development costs.
4.4.31 Second, guidance needs to be provided as to how the amount of compensation to be paid to the
proponent, if the project is granted to a third party, is to be determined to limit the period of time
required for project proponents and the MOEP to negotiate the compensation amount to be set forth
in the MOUs to be executed by MOEP and project proponents.
4.4.32 Third, the draft competitive tenders and solicitations regulations require bidding proposals to be
submitted in two parts, a technical proposal and a financial proposal. However, clarification is required
as to the basis for evaluating both types of proposals, and how the evaluation of both types of proposals
are to be integrated together in order to select the preferred proposal.
ERC Procedures
4.4.33 The draft ERC Procedures essentially combine into a single document the rules related to the ERC that
were included in the Initial Version of the Electricity Rules but were deleted from the final version
submitted to Parliament for approval. These draft rules reflect the significant efforts required in
preparing the Initial Version of the Electricity Rules. There is no doubt as to the likely effectiveness of
these draft procedures had the ERC been given a role in performing regulatory tasks. However, these
draft procedures have limited significance as long as the ERC remains uninvolved in regulation.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 71
4.4.34 However, it would be a mistake to forget these draft procedures since they will again become important
once the ERC is involved in performing regulation; as would be the case if MOEP requests
recommendations from the ERC on regulatory actions or decisions to be taken by MOEP.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 72
Chapter 5
Preparation of Rural Electrification Law and Implementing Regulations (Phase 1- Task 2 and Phase 2- Task 2)
5.1 Initial Assessment
5.1.1 The DFDL Consulting Team has been charged by the TOR to prepare a Rural Electrification Law and its
implementation regulations in order to accelerate rural electrification in Myanmar. Work on the Rural
Electrification Law was initiated during the fourth month of the Project. Initial efforts focused on
identifying, (i) the Myanmar governmental institutions involved in rural electrification; (ii) past
Myanmar governmental efforts regarding rural electrification; (iii) problems encountered with rural
electrification within Myanmar; and (iv) successful rural electrification efforts in other countries. Efforts
also included identifying rural electrification laws from those countries that have achieved success at
accelerating rural electrification.
5.1.2 As related above, the efforts of the DFDL Co sulti g Tea s ega di g the Rural Electrification Law have
been handicapped by the low priority placed on this task by the MOEP and the difficulty failure of the
Government to to designate a counterpart within the government to work with the DFDL Consulting
Team. Nonetheless, notwithstanding the difficulties encountered, the DFDL Consulting Team had
prepared and delivered to the MOEP and the ADB in mid-February 2015 the following work products:
a. Memorandum on Options for Rural Electrification Based on Foreign Experience of Selected
Countries; See Item 22 of Appendix F
b. Memorandum on Challenges of Rural Electrification on Myanmar, Reform Objectives and
Recommendations as to the Content of the Rural Electrification Law; See Item 23 of Appendix F;
and
c. Memorandum of a Country Comparison Matrix of Rural Electrification Reforms and Projects. See
Item 24 of Appendix F.
5.1.3 The ADB shortly thereafter concluded that drafting the implementing regulations for a new Rural
Electrification Law was not practical since the MOEP and the Government had not decided on the
substance of the new law.
5.1.4 Due to the foregoing factors, the ADB in late February 2015 deemed DFDL performance of work related
to rural electrification as set forth in the TOR (Phase 1-Task 2) and Phase 2-Task 2) to have been
satisfactorily completed. Nonetheless, to address the questions and comments from the ADB, received
by the DFDL Consulting Team in September 2015, the foregoing work product was revised as of October
2015 and is attached hereto as Appendix C.
5.1.5 Despite the foregoing tasks having been deemed complete by the ADB, to reignite interest in the rural
electrification efforts of the DFDL Consulting Team and the draft Rural Electrification Law, it was
suggested by the ADB that a Rural Electrification Workshop be held for the relevant government
ministries and other stakeholders.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 73
This workshop was intended to focus the relevant government ministries and other stakeholders on
the electrification report and the draft Rural Electrification Law prepared by the DDL Consulting Team
to initiate ta diologue regarding the need for and content of such a law. This workshop was tentatively
scheduled for 25 February 2016 as the final task for this Project. However, the change in the
goveerment, the need to appoint new Ministers, and the retirement of the DG of the Department of
Electric Policy of MOEP required this workshop to be postponed until later in 2016. The presentations
prepared to be given by the DFDL Consulting Team at this third workshop are set forth as Items 27 and
28 of Appendix F.
5.2 Background
5.2.1 The Myanmar National Electrification Plan (NEP) sets forth the commitment of the Myanmar
Go e e t to ele t if % of M a a s households . With o l app o i atel % of the households having been electrified to date, this is a daunting challenge. In its report to the World Bank
e titled M a a National Electrification Plan ‘oad ap a d I est e t P ospe tus dated Jul the Castalia ‘epo t , Castalia epo ted that to a hie e this o je ti e o e tha . illio
households would need to be electrified by grid extensions over the next 16 years; together with
another app o i atel , te po a p e-ele t ifi atio o e tio s ade th ough i i-grid
and household installations of solar panels.
5.2.2 Recent experience in other countries demonstrates that the most effective and efficient way to
achieving a rapid increase in electrification is through a coordinated sector-wide approach. Although
the consensus remains that most connections will be the result of grid extensions, virtually every
country for which electrification remains a top priority has or is revising its efforts based upon the
conclusion that greater access to grid-based electrification is best accomplished using a sector wide
approach combining a centralized and a decentralized track. The key features of a sector-wide
programmatic approach are:
a. Organize rural electrification around a comprehensive technically least-cost plan for grid, mini-grid
and individual household-level connections. In practice, this means ensuring that the plan is
constantly updated and refined, and that actual projects follow the plan, in terms of what, where
and when gets built;
b. Funding flows must be predictable. For the technical plan, there must be a clear, comprehensive
and multi-year funding and financing plan. The institutions implementing the program must all play
their role in ensuring that the flow of funds keeps the program moving. This will require a high
degree of coordination with direct involvement by key political decision-makers;
c. Plan implementation must be standardized and simplified, so that procurement and other
necessary activities can be carried out without delay and at low transaction costs;
d. Must be able to utilize private and community resources.
5.2.3 Institutions will play a critical role in shaping how the NEP will be delivered. In particular, institutions
need to be designed to ensure, (i) there are sufficient funds flowing into the overall electrification
program; (ii) there is coordination of funding, such that funding is reaching projects that are prioritized
on a least-cost basis, being built efficiently and are achieving social objectives; and (iii) a clear pathway
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 74
for private sector participation within that framework will be necessary to increase the probability of
sufficient funding and efficient implementation.
5.3 Challenges and Impediments to Rural Electrification
5.3.1 A key question requiring an answer is wherther enactment of a rural electrification law is really
necessary. The DFDL Co sulti g Tea s assess e t of this uestio is that a e u al ele t ifi atio law is not required for electrification to be accelerated by the participation of private investors. The
DFDL Consulting Team believes that an Small Power Producer (SPP) Program can be established by
MOEP without any new legislation. However, based on a review of the literature, reports, assessments
together with discussions with the MOEP, the Ministry of Livestock, Fisheries and Rural Development
(MLFRD), and other government institutions and international bilateral and multilateral organizations,
the DFDL Consulting Team concurs with the Castalia Report that successful implementation of a sector
wide approach will require fundamental institutional reforms and comprehensive solutions of a nature
which requires a statutory mandate.
Lack of Communication and Coordination between Government Institutions:
5.3.2 The Castalia Report concluded that the Myanmar government is not institutionally equipped to
implement rural electrification on a programmatic sector wide basis. Multiple government institutions
are responsible for different aspects of rural electrification, including the MOEP, the MLFRD, the
Ministry of Energy (MOE), the Ministry of Agricultural and Irrigation (MAI), the Ministry of Science and
Technology (MOST) and Region and State governments. The ESE of the MOEP does extension of existing
lines while the Department of Rural Development of MLFRD does off-grid housing, and Region and State
governments are responsible for the generation facilities less than 30 MW not connected to the
national grid. Communication and coordination among these government institutions is reportedly
weak to non-existent.
5.3.3 The Myanmar Government has sought to address this lack of communication through the
establishment of ministerial committees, including the National Energy Management Committee
(NEMC), which is charged with drafting energy regulations, developing short and long-term energy
plans, and adopting pricing policies across all energy sectors, and the Rural Electrification and Water
Supply Committee (REWSC), which is to take the lead and develop targets for all power sector entities
able to develop and implement rural energy projects. These committees are comprised of
representatives of the various ministries which have electrification-related responsibilities.
5.3.4 However, these ministerial committees appear to be ill-suited to provide the coordination and control
required to implement rural electrification on a programmatic sector wide basis. Sector wide
coordination requires the capability to revise and re-prioritize the activities and budgets of the
individual ministries responsible for electrification. REWSC and other ministerial committees are not
able to serve this function.
No Mechanism for Coordinating Planning and Funding Decisions:
5.3.5 There is no institutional mechanism that pulls together the various funding and financing sources into
a cohesive and comprehensive program and allocates the resources available to the government on a
prioritized basis among the different programs through which the government is pursuing rural
electrification.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 75
5.3.6 Decisions about setting electricity tariffs and the funding of grid extension by ESE and other
electrification efforts are not coordinated. Tariffs are not linked to the costs of expanding electricity
services and electrification. Decisions on matters that should be taken together, such as the amount of
revenue required, the acceptability of tariff levels, and the financial conditions of the power sector, are
taken in isolation from each other. Government institutions separately decide the amount of funds
available for capital investment based upon their respective then current fiscal constraints.
5.3.7 As noted in the Castalia Report, the Government has limited mechanisms to assess and prioritize
various contributions it makes to the overall sector development. Although the Ministry of Finance
would appear to be the logical choice for assuming such responsibility, the Castalia Report concluded
that since the Ministry of Finance has different erti al udget appro als for ea h i istry ith funding for various aspects of electrification spread across different ministry budgets, it is difficult for
the Ministry of Finance to form a comprehensive view of how various activities contribute to the overall
program.
5.3.8 I additio , [s]ince Union and Regional Government budgets are formed separately, and since there
are barriers to coordination between Regional and Union budgets (for example, Union funding has to
be spent via Union-level procurement agencies and cannot be channelled [sic] to locally implemented
projects), there is considerable risk that local and Union-level electrification projects could be at cross-
purposes to each other.
5.3.9 In sum, existing government institutions and rural electrification efforts are based upon project-by-
project reviews. This focus needs to be shifted away reviews towards a comprehensive sector wide
e ie of the go e e t s u al ele t ifi atio effo ts. To a hie e this efo us e ui es i teg ating
technical planning with the formulation and management of a financial plan which consolidates all
government financial support for rural electrification and allocates such financial support across all
government rural electrification programs on a prioritized basis to achieve sector wide objectives,
preferably in accordance with the principles of least cost.
Lack of Rural Electrification Master Plans:
5.3.10 Myanmar approved the NEP at the end of 2014. However this plan is not complete. First, the NEP needs
to prioritize household and mini-grid installations in addition to grid extensions. Second, the NEP does
not assign connection targets to those power sector entities responsible for such connections. Third,
the NEP does not address the financial resources available for electrification and how such financial
resources should be allocated among the electrification programs. Such plans need to be prepared each
year. It is unclear whether the Government has personnel able to prepare such plans.
ESE and YESC Ill-equipped to Accelerate Grid Extensions:
5.3.11 The reports reviewed suggest that ESE and YESC in their current form are unlikely to achieve higher
rates of electrification due to the following factors:
a. Limited Operational Flexibility and Ability to Plan. The Castalia Report concluded that the
Accounting Policies for State-Owned Enterprises (2012) require key spending decisions to be
included in the Union budget and deprives ESE and YESC of the freedom needed to manage their
balance sheets.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 76
b. Limited Performance Incentives. State-owned enterprises implement state budgets and directives
and are not commercially motivated. Since they are not driven by commercial objectives, ESE is not
susceptible to performance incentives to increase the efficiency of electrification.
c. Limited to No Access to Debt Financing. Apart from limited access to public sector loans, ESE and
YESC, prior to its corporation, cannot obtain debt financing.
d. Uncertain Recovery of Electrification Costs. Although enactment of the new Electricity Law and
prescription of its implementing rules may improve the situation, there is as of yet no assurance
that ESE and YESC can charge cost reflective tariffs and will be able to recover the costs of
accelerating grid extensions. The requirement for parliamentary approval of tariffs creates
considerable uncertainty year to year as costs to ESE and YESC are unable to be recovered by means
of retail power sales, and there is no mechanism to ensure the government will provide subsidies
to cover revenue shortfalls due to the incurrence of electrification costs not recovered from retail
power sales.
Thus, electrification by means of grid extensions by ESE and YESC can only be implemented at a
pace that reflects the pace at which the Union Government provides financial support in the form
of subsidies to ESE and YESC for such activities.
Household Electrification Not Prioritized and Unlikely Sustainable.
5.3.12 The M a a Go e e t s off-grid electrification efforts are currently limited to household-level
solar electrification implemented through the Department of Rural Development (DRD) of the MLFRD.
Under this program, solar home systems are granted to recipients with a 100% subsidy being provided.
The DRD undertakes contracts with private companies to install village-level solar home systems (SHS)
and to provide training to local people for the utilization of the system.
5.3.13 Studies and reports regarding household level electrification programs in a number of countries
indicate several factors that are important to improving efficiency and sustainability of such efforts.
These factors include (i) households incurring a percentage of the costs of the installation and operation
of household systems; (ii) generation of sufficient revenue to contribute to on-going costs and to be
financially sustainable; (iii) such programs being designed so that once installed, the household systems
continue to operate as designed; and (iv) targeting such programs to those areas where household level
electrification is the most economic electrification option.
Absence of Union Government Support for Mini-Grids.
5.3.14 At present, other than the single 10 kW micro-hydropower project developed by the DRD of MLFRD
and further plans to implement 129 micro-hydropower and eight biomass projects this year, there are
no government programs to support the installation of mini-grids, a d o ea s to e su e that bottom
up efforts regarding mini-grids are implemented consistent with least cost rural electrification.
Furthermore, as noted in the Castalia Report, since there is no standard format or process for
developing mini-g ids, e e p oje t effe ti el has to e-i e t the heel a d o e up ith its o institutional design, technical plans, legal documentation and financial proposal.
5.3.15 In light of the small size of mini-grids, the transaction costs associated with the lack of a standardized
format and process quickly erodes the profit margins on these projects rendering investment
uneconomic. Also, the absence of a Union Government program for mini-grids means that there is no
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 77
mechanism for the Union Government to support the development of off-grid mini-grids. This is a
significant oversight given the expectation that even with the successful achievement of the
Go e e t s a itious p og a of electrification by grid extensions; more than one million
households will not be viably connected to the grid for at least a decade or more.
No Bottom-Up Rural Electrification Projects or Programs.
5.3.16 As with many countries, the Union Government has implemented a national electrification strategy
that relies almost entirely on extensions of existing medium voltage transmission and distribution lines
by the MOEP. The current rural electrification strateg thus ep ese ts solel a top do approach,
or centralized track for electrification, because only central government institutions are responsible for
electrification.
5.3.17 By contrast, the decentralized track is a bottom-up approach because electrification projects are
generally carried out through the efforts of non-governmental entities, such as cooperatives,
community user groups, or private entrepreneurs, and are organized at the community level outside
the planning efforts of the central government. The lack of any bottom-up program results in lost
opportunities to yield the benefits from community initiatives and private sector participation in rural
electrification.
Lack of Debt Financing for Rural Electrification Projects.
5.3.18 The capability to obtain debt financing for rural electrification from both private and public sources is
severely constrained. The government does not provide loans for the development of rural
electrification projects by local communities, private companies or non-governmental organizations.
5.3.19 In regards to private sources of financing, the reports reviewed by the DFDL Consulting Team noted
that the following factors limit the availability of debt financing: (i) the limited development of the
Myanmar banking system; (ii) the unavailability of loans for periods longer than 2 to 3 years; (iii) the
difficulties of refinancing debt; (iv) the lack of experience of Myanmar banks with the use of project
finance for infrastructure projects; and (v) the lack of interest of international commercial lenders for
rural electrification without significant power sector structural reforms, such as commercialization of
MEPE and ESE and the creation of an effective power sector regulatory authority. These constraints
taken together mean that debt financing to reduce the costs of rural electrification, particularly with
regards to connection costs, cannot be utilized.
Lack of Training for Local Communities.
5.3.20 Installment and operating of solar panels and wind turbines needs prior training. The Castalia Report
estimates both the private and public sectors in Myanmar are likely to be short of approximately 1,000
trained electrical workers required for the implementation of any electrification plan. Castalia
estimates that it will take up to two years to train the required personnel, with ongoing commitment
to training in the future. Capacity building of rural communities, including training, may allow the
establishment of more mini-grids in rural area and overall increase of the rural electrification rate.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 78
5.4 Recommended Content for New Rural Electrification Law
Objectives:
5.4.1 A coherent, comprehensive and coordinated rural electrification program needs to be formulated and
implemented to address the foregoing challenges. To achieve this result, the following four objectives
should be the focus of reforms intended to promote and accelerate rural electrification:
a. A Union Government institution is needed that will take lead responsibility and control of rural
electrification programs and efforts;
b. Grid-based electrification, by extension of the national grid, needs to be made more efficient and
allow private sector participation;
c. Support for the implementation of mini-grids should be increased and must be better coordinated,
both to achieve the benefits of standardization and to ensure that money follows appropriate
projects;
d. Household level electrification programs require reform to make implementation more
sustainable and efficient.
5.4.2 The reforms and content for the Rural Electrification Law recommended below are all targeted to
achieving the foregoing objectives. The reforms and content recommended are not novel or unique to
Myanmar, but are rather drawn from literature, reports and assessments regarding rural electrification
in other Asian and African countries facing electrification challenges comparable to electrification
challenges in Myanmar.
5.4.3 In these countries, the consensus is that the following institutional reforms have contributed
significantly to the accelerated pace and success of electrification. By way of examples, Items 23 and
24 of Appendix F identify those reforms that have been successfully implemented in other Asian and
African countries most comparable to the following recommendations:
Establishment of Lead Government Institution Responsible for Rural Electrification
5.4.4 As noted above, communication and coordination among the multiple government institutions who
have responsibilities for rural electrification is quite weak in Myanmar. Also, the Go e e t s efforts
to address this problem through the creation of ministerial committees have proven to be largely
ineffective. Ideally, this problem should be solved by creating a new ministerial level government
institution that would be responsible for all rural electrification efforts. However, all of the reports on
government policies on rural electrification state that the government is not willing to create such an
institution.
a. As such, to address this problem, the new Rural Electrification Law should alternatively create
or upgrade an existing ministerial committee to be the lead government institution responsible
for rural electrification. This government institution needs to be able to render the decisions
required to coordinate, prioritize and supervise all aspects of electrification.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 79
b. The new Rural Electrification Law should restructure any ministerial committee to be an
institution focused on making such decisions with the statutory authority, sufficient resources,
and sufficient politi al pull to ensure that these tasks are achieved.
c. The new Rural Electrification Law should establish this government institution within the Offices
of the Vice President and define the authority, and responsibilities of this government institution
with specific reference to the activities of all the other government institutions assigned rural
electrification responsibilities, including the relevant Union ministries (such as MOEP, DRD, MOST)
and State and Region governments.
d. The new Rural Electrification Law should assign to this government institution the following
responsibilities:
i. The annual formulation of the National Rural Electrification Master Plan (including budget,
funding sources and allocation of government financial assistance) for submission to
Parliament;
ii. Prioritization of rural electrification efforts of other government institutions (such as MOEP
and DRD) in coordination with State and Region governments;
iii. Based upon information provided by MOEP, annually identify those townships and villages
that are expected to become connected to the national grid over the next five and ten years;
iv. Annually set targets for each of the immediately following five years for the connections to
be made by ESE ad YESC by means if grid extensions;
v. Establish government policies regarding financial support for rural electrification in the
aggregate and for individual programs and identify the anticipated sources of funding
therefore;
vi. Supervise the administration by its Executive Secretariat of the Rural Electrification Fund;
vii. Recommend tariffs to the MOEP for on grid SPP power sales to MEPE, YESC and ESE and retail
power sales by isolated SPPs;
viii. Serve as the main point of contact with international donors;
ix. Establish SPP eligibility criteria;
x. Establish eligibility criteria for obtaining government financial assistance; and
xi. Establish and implement a public awareness campaign to enhance support of the rural
electrification programs.
e. There are only two candidates for the ministerial committee to be designated to coordinate and
direct all electrification efforts, the National Energy Management Committee and the National
Electrification Executive Committee. We recommend that the National Electrification Executive
Committee be so designated. The scope of the responsibilities already assigned to the National
Energy Management Committee is already overwhelming and rural electrification would likely not
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 80
get the atte tio this topi a a ts gi e the go e e t s o it e t to ele t ifi atio . Also, importantly, the National Energy Management Committee is not structured to render difficult
decisions on any kind of a timely or predictable basis. The size of the membership of the National
Energy Management Committee is simply too large to make decisions other than on the basis of
consensus. There are therefore no procedures for making formal decisions.
f. Given the high profile of the National Energy Management Committee, fundamental revisions to
the structure and procedures are highly likely to be resisted. In contrast, resistance to modifying,
by the Rural Electrification Law, the structure and procedures of the National Electrification
Executive Committee (referred to for the balance of this ‘epo t as the Co ittee , should e less so.
g. To render the Committee capable of making decisions, the Rural Electrification Law should specify
Committee membership of no more than eleven members comprising of, (i) the Chairman,
appointed by the Office of the Vice President, (ii) the Director General of the Executive Secretariat,
and representatives of (iii) the Ministry of Electric Power, (iv) the Department of Rural
Development, (v) Ministry of Energy, (vi) Ministry of Finance, (vii) the Energy Development
Committee on behalf of the National Energy Management Committee, (viii) the State government
with the lowest percentage of electrification, (ix) the Region government with the lowest
percentage of electrification, (x) local communities appointed by the Offices of the Vice President,
and (xi) equity and debt financial institution.
h. The Rural Electrification Law should also define the quorum required for Committee meetings to
be held and the voting requirements for rendering affirmative decisions. It is recommended that a
quorum of six members present in person, by phone or by proxy to properly hold a meeting of the
Committee with affirmative decisions of the Committee requiring a majority of the members
attending duly constituted Committee meetings.
Establishment of Executive Secretariat:
5.4.5 The new Rural Electrification Law should establish a well-resourced government institution (an
E e uti e “e eta iat to p o ide the p ofessio al a d ad i ist ati e staff e ui ed to suppo t the activities of the Committee. The new law should specify the responsibilities of this office.
a. These responsibilities should include: (i) after consulting with relevant power sector stakeholders
(including international donor institutions) and relevant governmental institutions (including State
and Region governments, MOEP, DRD, ESE and YESC) and information requested of same by this
office, prepare drafts of all documents required to be prescribed by that ministerial committee,
including the annual National Rural Electrification Master Plan and required the eligibility criteria;
(ii) administer the Rural Electricity Fund; (iii) prepare tariff proposals for that ministerial committee
to submit for consideration by the MOEP; and (iv) to undertake the coordination function. The
Executive Secretariat must be able to work directly with all relevant institutions, such as MOEP,
DRD and ERC. M a a s de elop e t pa t e s should o side p o idi g su sta tial te h i al assistance funding to supports the Executive Secretariat.
b. The Executive Secretariat could be an enhanced version of the DRD or be located within the Office
of the Vice President. Locating the office withi Vi e P eside t Offi e is p efe ed because an
enhanced DRD would be accountable to both its Ministry and the Committee established by the
new law as the lead government institution for electrification; whose interests may differ.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 81
Requirements for Preparation of the Annual National Rural Electrification Master Plan:
5.4.6 The new Rural Electrification Law should specify how the annual National Rural Electrification Master
Plan is to be prepared. The requirements set forth in the new law would address: (i) both process and
substantive content; (ii) the prioritization of grid extensions, mini-grid installations and household
electrification based upon least cost; and (iii) amount and sources of funding. The requirements
regarding process are to specify how State, Region and local governments will be integrated into the
formulation of the National Rural Electrification Master Plan.
Coordinating Tariffs with Funding of Rural Electrification:
5.4.7 There is no institutional structure for coordinating decisions about setting electricity tariffs and the
electrification objectives. Decisions on matters that should be taken together (such as the amount of
revenue required, the acceptability of tariff levels, and the financial conditions of the power sector) are
taken in isolation from each other. Government institutions separately decide how much capital
investment is possible in the sector on the basis of its current fiscal constraint.
5.4.8 The new Rural Electrification Law could require the MOEP to take these factors into account in
determining tariffs. Also, the new law should authorize and perhaps require the ministerial committee
established by the new law, as the lead government institution for electrification, to submit to the
MOEP recommendations as to appropriate tariffs required to achieve electrification objectives.
Directive to Revise Program for Household Electrification:
5.4.9 The Government needs to move the household electrification program from the relatively
unsustainable giveaway of solar systems to an arrangement where customers are provided with energy
supply by firms that maintain and operate household and village systems. Customers would pay for the
energy they receive. Private providers would use revenue to cover the costs of maintenance. The
Government would provide subsidies to ensure that tariff revenues are sufficient to cover the costs of
the p i ate ope ato . “u h a shift ill e pa ti ula l i po ta t to suppo t the p e-electrificatio program.
ESE and YESC: Cost Recovery, Subsidies and Connection Costs
5.4.10 The most important reforms required are the corporatization and commercialization of YESC and ESE,
their ability to collect and retain revenue, the funding of connections, and the implementation of cost-
reflective tariffs. These reforms are required for YESC and ESE to operate as independent commercial
entities able to conduct financing operations on their own balance sheets and able to make
independent decisions about staffing levels, pay and other resources. These reforms are beyond the
scope of a new law on rural electrification. However, statutory change does not appear to be necessary
as the Government appears to have already initiated these reforms with its corporatization of YESC, the
enactment of the new Electricity Law expressly authorizing corporatization of government power
institutions, and the mandate to establish the ERC.
5.4.11 Nonetheless, the Castalia Report and other literature reviewed recommend that the following more
modest reforms can be achieved by the new Rural Electrification Law. The new law could require that:
a. consumers be allowed to pay off connection costs over a number of years rather than having to
paid at one time;
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 82
b. the cost of electrification incurred by YESC and ESE to be recovered each year by the revenue
generated by retail tariffs combined with government subsidies. This could be achieved by first
determining the cost of service of electrification for ESE and YESC, then determining the percentage
of such costs that are to be recovered through retail tariffs, with the balance of such costs covered
by means of an annual subsidy payment from the Government. There are precedents in other
countries for this approach;
c. the cost of new connections to e i luded o the utilities ala e sheet a d, he it e o es possible, debt financed rather than funded either entirely by connection fees charged consumers
o E“E s a d YE“C s o esou es; a d
d. short-term changes to be made to the budgeting process for YESC and ESE to facilitate more
independent commercial decision-making and to encourage and enable both to borrow on the
basis of their balance sheets, including five-year budgets for ESE and YESC in line with the rural
electrification plan, so that the utilities can commence medium-term planning.
5.5 Rural Electrification Programs
5.5.1 These programs are designed to foster the participation of communities and the private sector in
electrification, particularly but not limited to isolated grids. The private sector is already involved in
delivery of distribution and retail power sales.
5.5.2 Two types of programs should be mandated by the new Rural Electrification Law: (i) Small Power
Producers and Distributors; and (ii) Distribution Sub-Franchises and Subcontractors.
Small Power Producers and Distributors Program (Grid Connected or Isolated)
5.5.3 The first program, the Small Power Producers and Distributors (SPP) Program, could accelerate the
development of micro-grids, particularly those that are electrically isolated. Although only a very small
percentage of households are so remote that grid extension will never be an economically viable
approach for electrification, electrically isolated mini-grids are expected to play an important (although
temporary) role for townships and villages that must wait years to obtain electrical access by means of
the national grid.
5.5.4 In a growing number of developing countries, SPP programs are emerging as a meaningful complement
to grid extensions as a means to accelerate rural electrification by promoting both, (i) the addition of
needed new generating capacity; and (ii) the establishment of electrically isolated mini-grids that will
serve consumers until such time as such consumers can access electric power by means of grid
extensions.3
3 For an excellent summaries of SPP regulatory options for Myanmar and the characteristics of Small Power Producer
programs throughout the developing world and the regulatory issues to be confronted in establishing and implementing
su h p og a s, please efe to, espe ti el , “PP ‘egulato F a e o k Optio s i M a a , Fi al ‘epo t to the International Finance Corporation, by Chris Greacen (July 2014) and F o the Botto Up- How Small Power Producers
and Mini-g ids a deli e Ele t ifi atio a d ‘e e a le E e g i Af i a by Bernard Tenenbaum, Chris Greacen, Tilak
Siyambalapitya and James Knuckles, published by the World Bank (2014).
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 83
5.5.5 Initially, SPP programs begin as a mean to encourage the use of renewable resources and particular
technologies. Development of such projects is promoted by the establishment of a legal and regulatory
framework which extends certain privileges to projects below a threshold size that use renewable fuels
or favored technologies. The privileges extended to such projects typically include:
a. an obligation on the part the local electric utility to purchase from such SPP projects all the power
such projects are able to generate at pre-specified prices that either reflect the avoided cost of the
purchasing utility (the price of power that such a utility would otherwise have to purchase or
generate if it had not purchased power from the SPP project) or reflect the generic cost of
producing power using the technologies used by the SPPs. In some countries, the purchasing utility
pays a levelized avoided cost and SPPs receive a stable technology-specific tariff with the difference
covered by funds committed by international donors;
b. streamlined regulation with minimal qualification requirements, standardized permits, minimal
service obligations, and no cost service regulation,
c. standardized documentation, including standardized power purchase agreements; and
d. the granting of certain financial investment promotional privileges, such as tax holidays, tax
reductions, tax credits, and exemptions from import duties and taxes.
5.5.6 More recently, SPP programs have been tailored to promote community and private sector investment
in off-grid mini-grids and grid extensions to implement rural electrification, particularly in regards to
electronically isolated mini-grids. This has been achieved by providing flexibility in the prices for power
charged to the customers of SPPs, the use of standardized power sales agreements between SPP
distributors and the communities they serve, and keeping regulation streamlined.
5.5.7 Indeed, those countries that are more concerned with extending rural electrification than with
promoting the use of renewable resources, SPP privileges are extended to all power projects below a
threshold size regardless of the fuels and technologies used by such projects. Indeed, the scope of
privleges extended to each project varies based upon project size. Table 5.5 sets forth the allocation of
SPP bebefits recommended for Myanmar.
SPP Program Qualifications:
Size Thresholds.
Table 5.5 Recommended Allocation of SPP Benefits
Project Size Grid
Location
Permitting
Authority
Tariff Basis
Larger than 30 MW On Grid MOEP Avoided Cost of Purchasing Utility or Generic Standardized Cost
Reflective Technology Specific Tariffs.
Larger than 30 MW Off Grid MOEP Generic Standardized Cost Reflective Technology Specific Tariffs.
Larger than 10 MW
but not larger than
30 MW.
On Grid MOEP Avoided Cost of Purchasing Utility or Generic Standardized Cost
Reflective Technology Specific Tariffs.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 84
Larger than 10 MW
but not larger than
30 MW.
Off Grid State and
Region
Governments
Generic Standardized Cost Reflective Technology Specific Tariffs.
Larger than 1 MW
but not larger than
10 MW.
On Grid MOEP Avoided Cost of Purchasing Utility or Generic Standardized Cost
Reflective Technology Specific Tariffs.
Larger than 1 MW
but not larger than
10 MW.
Off Grid Township
Governments
Consideration to be given to exempting from regulation negotiated
tariffs for projects with demonstrated community support.
Tariffs for SPP Projects not exempt from regulation to be Generic
Standardized Cost Reflective Technology Specific Tariffs.
Not Larger than 1
MW.
On and
Off Grid
Township
Governments
Tariffs established by negotiations and not regulation.
5.5.8 A key question is what should be the threshold size for qualification as an SPP project. The threshold
will depend upon whether the purposes to be served by the SPP program are limited to the promotion
of small power projects or include the promotion of renewable energy and the characteristics specific
to each power system.
5.5.9 For programs whose purpose is to promote electrification, the thresholds are smaller to reflect the load
SPPs are expected to serve in rural environments. For programs that are intended to promote the use
of renewable fuels and technology, the thresholds are set higher to maximize the substitution of such
fuels and technologies for fossil fuels, yet small enough for SPPs not to cause system operational
problems. The reason for permitting projects that are grid connected or larger than 30 MW is that
electrification by means of grid extensions cn be implemented by private investors; so that the rol of
private investors is not limitd to off-grid electrification.
5.5.10 System operational problems caused by the characteristics of specific projects are more likely to occur
as project size increases relative to the size of the power system. It is common to restrict the permissible
size of SPP projects to avoid project specific operational impacts.
Qualifying Fuels and Technologies.
5.5.11 SPPs focused on expanding rural electrification are typically able to use any fuel or technology without
restriction. However, for SPPs intended to promote use of renewable resources and technologies,
decisions are needed as to what and fuels and technologies are to be preferred. A determination is
also required as to whether projects which use a combination of preferred resources and technologies
and fossil fuels are to be permitted.4
5.5.12 To ensure consistency with the operations of the power system, it is not uncommon for generic
technical standards and requirements to be specified on a technology specific basis. Inspection and
certification that projects satisfy the foregoing requirements and qualify as SPPs will be required.
Grid Connection Capability.
4 In his report to the IFC on the options for SPPs in Myanmar, Chris Gleason reports that with steep reductions in the cost
of solar photovoltaic in the past several years, is it is cost-effective to consider upgrading Myanmar s 78 MW of stand-
alone diesel generators to become hybrid solar/diesel systems with battery storage. See “PP ‘egulato F a e o k Optio s i M a a , Fi al ‘epo t to the I te atio al Fi a e Co po atio Jul at page .
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 85
5.5.13 To facilitate grid extension and minimize inconvenience and cost, off grid distribution facilities, which
are likely to still be in use when SPPs that distribute and sell power to retail consumers (SPP Distributors)
become interconnected with the national grid. Such distribution facilities should be initially designed
and installed ready to become interconnected with the national grid. This will avoid consumers having
to pay for the original distribution facilities and then having to pay again to upgrade or replace such
equipment with equipment compatible with the grid. The cost of originally designing and installing
distribution facilities compatible with grid interconnection is estimated to only increase the cost of
distribution facilities by ten percent.
5.5.14 The key determinant regarding whether to install grid connection compatible equipment is apparently
not the size of the distribution network or mini grid, but rather the expected useful life of the off-grid
distribution facilities and the number of years before grid extension and connection is realistically
expected. If the useful life of the off-grid distribution facilities is shorter that the period preceding grid
interconnection, then installation of grid-compatible equipment is not economically viable.
Power Sales Price.
5.5.15 Another key question is what price SPP Distributors can charge to the retail consumers they intend to
serve. Retail power tariffs for off-grid and on-grid SPPs should reflect the costs of installing and
operating such SPPs. The answer to this question depends in part upon the size of the power project
and whether the project is off-grid or on-grid.
5.5.16 For the most part, the power sales price for very small and off-grid projects is left to negotiations
between the project sponsors (such as investors in the mini-grids) and the communities that they intend
to serve. Under such circumstances, the regulatory issue is whether very small and isolated mini-grids
are permitted to charge prices greater than the regulated retail prices charged to consumers that are
connected to the national grid.
5.5.17 A pre-requisite for success of such programs appears to be permitting the prices charged to consumers
served by very small and off-grid power projects (such as off system mini-grids) to exceed the
regulated prices charged to consumers that are connected to the national grid.
5.5.18 For very small off-grid SPPs, there should be a threshold (1 MW and below) below which retail power
tariffs are not regulated. For larger off-grid SPPs, but no larger than 10 MW, serious consideration
should be given to exempting retail power tariffs from regulation for power sold by off-grid SPPs for
which community support has been demonstrated by means of a Memorandum of Understanding or
retail power sales agreement between the relevant SPP and village electrification committees (VECs).
This is unless a specified percentage of the retail consumers to be served by that off-system SPP file
written protests with the relevant State or Regional government.
5.5.19 On-grid SPPs typically sell their power to their local utility at pre-specified prices that either reflect the
avoided cost of the purchasing utility (the price of power that such utility would otherwise have to
purchase or generate if it had not purchased power from the SPP project) or reflect the generic cost of
producing power using the technologies of the SPPs. Thus, although regulated, tariffs for power sales
by SPPs are not based upon the costs of each SPP. This approach provides significant advantages to
SPP projects by eliminating the need for project sponsors to negotiate with purchasing utilities project
specific tariffs. Also, since tariffs are not based upon the costs of each SPP project, efficiency
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 86
improvements in construction and operations directly improve profitability without the threat of
regulatory reductions in power sales tariffs.
Regulatory Policies.
5.5.20 To encourage SPPs, the Rural Electrification Law could also mandate the implementation of the
following policies in the regulation of the electric power sector under the Electricity Law, 2014 and the
Electricity Rules, 2015:
a. allow retail tariffs of SPPs to exceed the uniform national retail tariff if required to recover
investments in SPPs;
b. allow different retail tariffs to be applied to different customer classes of an SPP in order to permit
cross-subsidization between customer classes;
c. allow SPPs to make retail power sales to industrial and commercial retail consumers without
regulatory review and approval.
Interconnection of Off-Grid SPP Distributors.
5.5.21 A critical question is what happens when the consumers served by off-system SPPs become connected
with the national grid, and can then purchase power on-grid electricity at a price below what they were
paying to the SPP Distributors. In the event that the retail price charged by the off-system SPP exceeds
the retail prices charged to consumers connected to the grid, as is most likely to be the case,
interconnection by grid extensions could result in the SPP being left without a market for its produced
power. The possibility of such stranded investments could dissuade private investors from investing in
off-system SPPs.
5.5.22 The solution to this problem is for the legal framework put into place for the SPP programs to include
rules that address what is to occur when off-system SPP Distributors become connected to the national
grid. Most commonly, investors in off-grid SPPs are protected against the possibility of stranded
generation investments by an obligation on the part of the purchasing distribution utility to either, (i)
purchase the SPP power previously sold to SPP retail customers at the tariff previously paid by such
retail customers; or (ii) purchase SPP generation assets for compensation equal to book value. Attempts
may be made to reduce the financial obligations of the purchasing distribution utility by requiring SPPs
to explore alternative means to recover the remaining value of their SPP generation assets, such as
sales of such assets to third parties.
5.5.23 SPP investments in distribution facilities are not so problematic. Either the purchasing distribution
utility will purchase such facilities from SPPs or the SPPs will retain such distribution facilities and
become distribution utilities that buy power from the grid, and then resells such power to their its retail
customers. However, for the transition to go smoothly, SPPs should be required to build their
distribution facilities in accordance with pre-specified technical standards and requirements that
ensure that such facilities will be able to be interconnected with the national grid without technical
difficulties or excessive costs.
5.5.24 In sum, the new Rural Electrification Law should mandate the implementation of a SPP program that is
targeted to encouraging community and private sector investment in rural electrification and the
development of renewable resources and technologies. Our memorandum to the Director General of
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 87
the Department of Electric Power in MOEP dated 16 February 2015 compares the rural electrification
programs of selected countries set forth several recommendations as to the content of an SPP program
for Myanmar.
5.5.25 These recommendations are set forth in Item 24 of Appendix F. Importantly, the manner in which such
an SPP program is implemented will need to be consistent with the authority the new Electricity Law
that gives State and Regional governments the power to permit and regulate tariffs of off-grid small (up
to 10MW) and medium (10-30 MW) power projects. This should be achievable.
5.5.26 One viable approach would be for the MOEP and the MLFRD, under the supervision and direction of
the Committee, to prescribe standardized rules and standardized documentation to be used by State
and Region governments for off-grid SPPs, MOEP for on-grid SPPs, and for MOEP and DRD to provide
consultation services as appropriate to assist State and Regional governments.
Distribution Sub-Franchises and Subcontractors.
5.5.27 The second program focuses on accelerating the rate of grid connections by using sub-franchises and
subcontracts to attract private investment in distribution networks. This recommendation simply
expands the scope of private sector participation in distribution that is already becoming a reality.
5.5.28 Private companies as subcontractors of ESE are already involved in delivery of distribution services in
several Mandalay townships using leased distribution facilities with private companies engaging in
retail power sales, distribution service, billing and collection. Also, the Government has leased facilities
to support privately developed micro-grids. Expanding the role of the private sector in distribution
could significantly increase the speed of electrification.
5.5.29 In addition to private participation in the ownership of YESC and ESE, there are two other ways to
involve the private sector to development of distribution networks.
Subcontracts.
5.5.30 Private companies could assume responsibility for distribution networks by entering into sub-contracts
with YESC or ESE. The service obligations of the subcontractor, in terms of building and maintaining
distribution facilities and their provision of distribution and retail power service, should be set forth in
its subcontract with YESC or ESE. Such subcontractors should be reviewed and approved by MOEP and
ERC. If this approach is pursued, implementing rules will be needed to address the content of the
subcontracts and, the process by which subcontractors are selected. One topic that would be required
to be addressed is the respective responsibilities and liabilities of ESE and subcontractors for
subcontractor violations of legal requirements, Permit conditions and poor performance.
Sub-franchises.
5.5.31 Alternatively, private companies could be granted sub-franchises to provide distribution services within
defined geographic territories by means of a combination of distribution franchise permits issued by
MOEP and subcontracts with YESC or ESE. By issuance of such permits, such companies would become
Permitted Persons and subject to regulation as distribution companies to the same extent as ESE and
YESC.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 88
Distribution Requirements.
5.5.32 Regardless of which approach is used, the following is required:
a. regulatory oversight to ensure distribution franchisees has the technical, managerial and financial
capabilities to provide distribution services and satisfy their legal and contractual obligations;
b. legal instruments, such as franchise permits and the subcontracts with YESC and ESE, to specify the
service obligations of the distribution franchisees, which include achievement of a defined number
of connections over a specified period of time, compliance with specified service standards, and
satisfaction of contractual obligations set forth in the relevant subcontract with YESC or ESE;
c. tariff arrangements and duration of franchise terms are to provide distribution franchisees the
opportunity to recover their respective distribution investments, operating costs, and the costs of
power procured to serve retail consumers.
5.5.33 Under franchise sub-contracts already in effect, YESC and ESE sell power to distribution franchisees at
prices below the retail tariff charged to consumers. The margin between the price charged to the
distribution franchisees and the retail tariffs charged to consumers is intended to provide the
distribution franchisees the revenue required for such franchisees, in combination with cost savings to
be achieved through improved efficiency and reductions in losses, to recover their respective
distribution investments and costs.
5.5.34 Since the required investments and operating costs are specific to each franchise territory, the price for
power sold to distribution franchisees will vary from franchisee to franchisee, even though the retail
tariffs to consumers may remain uniform. It has been recommended that the term of franchises should
be fifteen years to enable distribution franchisees to recover their distribution investments.
5.5.35 To the extent practical, distribution franchises should be required to be selected on a competitive basis.
For example, competition could be based upon the size of the margin between the power price to be
charged to the distribution franchisee and retail power tariffs, with commitments to reduce losses and
the number of connections to be achieved.
5.5.36 As to which of the foregoing two approaches is preferable, sub-franchising appears more attractive for
the government than subcontracting. Although the subcontractor may have to obtain a permit to
engage in distribution from MOEP, the regulation and specification of responsibilities of the private
company providing distribution is more direct and clear with sub-franchising.
5.5.37 Importantly, a new Rural Electrification Law need not directly address this topic. Distribution franchising
is already occurring. Indeed the regulations on the permitting of Permitted Persons are under
preparation by the MOEP and are intended to establish such a program and the requirements
applicable thereto. Therefore, for purposes of the implementation of distribution franchising, little
appears to be required of a Rural Electrification Law.
5.5.38 To foster the introduction of competition into the Myanmar power sector, the new Rural Electrification
Law should require distribution franchises, once determined by the MOEP to be practical and beneficial,
to be awarded by a competitive process. The process should be approved and the implementation
supervised by the MOEP.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 89
5.5.39 However, although little may be required of the new Rural Electrification Law in regards to the
implementation of distribution franchising, the success of using distribution franchises to promote rural
electrification may depend on such a new law. Using distribution franchises to accelerate electrification
is depe de t upo su h f a hisees a ilit to o o o e to fu d dist i utio i est e ts. The Castalia Report explained that since the roll out program designed to achieve the Myanmar
go e e t s ele t ifi atio o je ti es is ased upo % fi a i g th ough o essio al fi a i g, there needs to be a mechanism for on-lending of concessional finance to distribution franchisees.
Although not strictly necessary, legislative endorsement of such on-lending will facilitate the
implementation of such a mechanism. The creation of such an on-lending institution is set forth below.
5.6 Rural Electrification Fund
5.6.1 As noted above, there is insufficient coordination of funding of electrification. The new Rural
Electrification Law should establish the institutional structure required to coordinate the allocation of
a government fund to support financing of rural electrifi atio the Fu d . As pa t of this i stitutio al structure, the new law should establish a government institution that would receive all government
funds for electrification, and through which all government financial support would be dispersed. This
responsibility should be assigned to the ministerial committee to serve as the lead government
institution for electrification, and assisted by the Executive Secretariat as recommended above.
This ministerial committee would establish the priorities for government funding of rural
electrification and the criteria to be applied in qualifying for such financial assistance. The fund would
be administered by the Executive Secretariat.
5.6.2 The new Rural Electrification Law shall specify the sources of funding for the Fund. It is recommended
that the sources of funding for the Fund should consist of: (i) annual budgetary allocation from
Parliament; (ii) contributions from international financial organizations, multilateral and bilateral
agencies and other development partners; (iii) from levies of up to three to five percent on the retail
power sales, as determined by the ministerial committee given lead responsibility for electrification, in
consultation with the MOEP, the ERC DRD and the Ministry of Finance; and (iv) fees in respect of
programs, publications, seminars, consultancy services and other services provided by the REMC
Secretariat.
5.6.3 The new Rural Electrification Law should also specify how the Fund is intended to be used. It is
recommended that the Fund be used to finance: (i) the capital cost of rural electrification grid extension
and off-grid electrification; (ii) the capital cost of solar home system equipment to be acquired for public
institutions; (iii) operational and maintenance costs of rural electrification projects, to the extent to
which it makes the projects viable; (iv) provision of credit guarantees for the capital cost of solar home
system equipment other than those to be acquired by a concessionaire; (v) any monetary contribution
required to be made by the Government for the implementation and execution of a donor-funded rural
electrification projects; (vi) the administrative expenses associated with the execution of the duties and
functions and responsibilities of the ministerial committee given lead responsibility for electrification,
the Executive Secretariat recommended above, and the management of the Fund; (vii) research and
consultancy assignments related to rural electrification; (viii) expenses for credit guarantee funds
management; and (ix) compensation for ESE acquisition of off-grid installations once connected to the
national grid.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 90
5.7 Rural Electrification Finance Corporation
5.7.1 To enable debt financing of off-grid electrification projects by local communities and the private sector,
the new Rural Electrification Law should be set up a government corporation to finance rural
electrification projects at concessionary rates. Again, the corporation would be supervised by the
Committee assisted by the Executive Secretariat.
5.7.2 National funds and international funding would be provided to this corporation. This new financing
institution would extend financing to projects based upon criteria established by the Committee given
lead responsibility for electrification and the Executive Secretariat.
5.8 Investment Promotional Privileges
5.8.1 Consideration should be given to having the new Rural Electrification Law give the Myanmar Investment
Commission (MIC) the authority to grant SPPs promotional privileges beyond those currently able to be
granted by the MIC. Such additional privileges would only be granted upon petition to the MIC by the
DRD for off-grid SPPs and MOEP for on-grid SPPs. Such petitions would need to certify that the
particular SPP would significantly benefit the country and that granting the additional promotional
privileges is required for the project to be economically viable.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 91
Chapter 6
Conclusions- Looking Forward
Noting the many successes of the Project, the work required to establish an effective regulatory regime
for the Myanmar power sector is far from being completed. The following are the recommendations of
the DFDL Consulting Team as to the next steps that need to be taken.
6.1 Additional Regulations
6.1.1 The six regulations prepared on a prioritized basis were selected from seventeen regulations that were
identified in late January 2015 as required for the regulatory structure to become fully operational.
Eleven of the seventeen regulations previously identified as required remain yet to be prepared.
Drafting of these remaining regulations needs to be prioritized and, once prioritized, drafting should be
initiated. In terms of priorities, higher priority should be assigned to the regulations on, (i) performance
standards; (ii) compensation for damages; (iii) finalization of the Grid and Distribution Codes; and (iv)
the Consumers Manual. However, addressing the outstanding matters regarding the draft competitive
tenders and solicitations regulations should be given top priority, and the draft of this regulation should
be finalized first.
6.2 Internal Regulatory Organization, Process and Procedures
6.2.1 The MOEP successor needs to establish its internal organization, process and procedures by which the
MOEP will perform regulatory tasks of quality and on a timely basis. The deferral of the review by the
DG and the Steering Committee of the draft regulations on internal MOEP organization and procedures
prepared by the DFDL Consulting Team does not eliminate the need for such internal MOEP regulatory
organization, process and procedures.
6.2.2 The basics of the internal organization, process and procedures of MOEP should be in place before
MOEP successor commences performance of its regulatory responsibilities. To do otherwise is likely to
result in incorrect or incomplete regulatory filings being made, and the MOEP successor processing
such filings on an ad-hoc basis; thus resulting in confusion, delayed decision-making and a lack of quality
control over regulatory decisions. A consultant or advisor should be made available to assist the MOEP
in this endeavor. Ideally, the resident advisor that is recommended immediately below should be able
to provide such assistance.
6.3 Human Capacity Building
6.3.1 Successful regulation requires knowledgeable and experienced management and professional staff.
Given the current lack of regulatory knowledge and experience within the MOEP, learning and training
will initially be primarily achieved on the job, which, although practical, may result in its own set of
challenges. However, investing in education and training can accelerate the learning curve and help to
avoid repeating costly mistakes. It is often much more cost effective to bring trainers on location.
Ideally, the internal regulatory consultant recommended above would also be able to give
presentations and workshops on a regular basis on regulatory topics relevant to the responsibilities and
operations of the MOEP.
E ha i g Po e “e to s Legal a d ‘egulato F a e o k | Fe ua 92
6.4 Rural Electrification Law
6.4.1 To further enhance the legal structure surrounding rural electrification, the next step to be taken is to
establish a Steering Committee charged with producing a consensus-driven draft of a Rural
Electrification Law. The Chairman of the Steering Committee should be someone from the executive
management of the MLFRD or another Ministry with responsibilities regarding rural electrification.
Unless there is a complete change in the position of MOEP successor towards rural electrification, a
representative of the MOEP successor should not chair this Steering Committee.
6.4.2 It is recommended that the Steering Committee should first focus on trying to forge a consensus on the
desired content for the new Rural Electrification Law. In this regard, the report on rural electrification
and the draft for the new Rural Electrification Law prepared by the DFDL Consulting Team, together
with any other drafts for an electrification law that may have also been prepared, should be distributed
to the Steering Committee for purposes of fostering a meaningful dialogue among the members of the
Steering Committee. After determining the content of the new law, the Steering Committee will be
responsible for drafting the new law.
6.4.3 The probability of timely success of this effort would be significantly improved if the Steering
Committee obtained access to an outside consultant who can help manage discussion among the
Steering Committee, give advice regarding relevant international experiences, and assist in the drafting
of the new law.
6.4.4 It is also important to note that not all of the reforms recommended in the report prepared by the DFDL
Consulting Team as appropriate content for the new electrification law in fact need the enactment of
legislation to be implemented. For example, delegations by distribution companies (ESE and YESC) of
responsibility for the operations of the distribution networks and retail power sales at the township
level being delegated to privately owned companies, without any legislative endorsement of this new
practice.
6.4.5 The DFDL Consulting Team has concluded that new legislation is not required for an Small Power
Program commonly referred to as an SPP Program to be established as recommended in Chapter 5
above. There is no impediment to the MOEP successor immediately initiating preparation and
implementation of such an SPP Program. Again, the probability of timely success of this effort would
also be significantly improved by providing an international regulatory expert who can assist in the
design and the drafting of the regulations implementing the SPP Program. Ideally again, the internal
consultant that is recommended above to be made available to the MOEP regarding regulation would
also have experience in SPP Programs, and could also assist regarding the implementation of the SPP
Program.