task 1.33_5

Embed Size (px)

Citation preview

  • 8/13/2019 task 1.33_5

    1/101

    1

    Independent Cost Estimates

    ForHST Trimaran Trailer Ship

    May 30, 2009

    For

    CSC - Advanced Marine Center&

    Center for the Commercial Deployment ofTransportation Technologies (CCDoTT)

    Based on a concept design and costing input from

    Herbert Engineering Corp.

  • 8/13/2019 task 1.33_5

    2/101

    2

    2

    PERCEPTIONis a registered trademark of SPAR Associates, Inc. ESTI-MATE, MAT-PAC,WORK-PAC, andPERT-PAC are trademarks of SPAR.

    PERCEPTION

    Trade Secrets and Proprietary PropertiesOf

    SPAR Associates, Inc.Annapolis, MD 21401

  • 8/13/2019 task 1.33_5

    3/101

    3

    3

    Table of Contents

    1.0 Introduction ................................................................................................................... 52.0 The Cost Estimates ..................................................................................................... 15

    2.1 Cost Estimate Work Breakdown Structure ............................................................. 15

    2.1.1 Non-Recurring Costs ....................................................................................... 152.1.2 Recurring Costs ................................................................................................ 182.1.3 Program Schedule ............................................................................................ 252.1.4 Series Construction Programs .......................................................................... 292.1.5 Management Costs & Fees .............................................................................. 312.1.6 Cost Risk .......................................................................................................... 322.1.7 Labor Rates ...................................................................................................... 352.1.8 Material Costs .................................................................................................. 352.1.9 Profit ................................................................................................................ 362.1.10 Transport Factors ........................................................................................... 362.1.12 National Defense Funding (NDF) .................................................................. 37

    2.1.13 Extended Modularization Build Strategy Cost Benefits ................................ 39

    2.1.14 Required Freight Rate .................................................................................... 433.0 Basis for the Cost Estimate ......................................................................................... 52

    3.1 Cost Estimating Methodology ................................................................................ 533.2 Impact of Build Strategy on Cost............................................................................ 55

    3.2.1 Modern Shipbuilding Build Strategy ............................................................... 563.2.2 Modular Construction ...................................................................................... 573.2.3 Outfitted Hull Block Construction ................................................................... 583.2.4 Extended Shipbuilding Modules ...................................................................... 60

    3.3 Generic Shipyard Costs........................................................................................... 633.4 Shipyard Productivity Factors................................................................................. 64

    3.4.1 Extended Modularized Equipment & Outfit Option ........................................ 693.5 Generic Material Costs ........................................................................................... 71

    3.5.1 Adjusting Generic Material Costs for Type Contract ...................................... 713.5.2 Material Cost Escalation/De-Escalation .......................................................... 72

    3.6 Cost Risk ................................................................................................................. 733.6.1 Cost Risk of the Production Estimate Data.......................................................... 743.6.2 Predicting Production Overlap Rework Costs ..................................................... 763.6.3 Estimating Cost Risk of Overlap Rework ............................................................ 783.6.4 Estimating Cost Risk of Shipbuilder Inexperience .............................................. 803.6.5 Estimating Cost Risk of Engineering Quality ...................................................... 833.6.6 Estimating Cost Risk Due to Tight Production Schedule .................................... 863.6.7 Cost Risk on Follow Ship Programs .................................................................... 873.6.8 Cost Risk versus Contingency ............................................................................. 87

    4.0 Non-Recurring Detail Production Engineering and Planning .................................... 884.1 U.S. Navy Ships Non-Recurring Costs ................................................................. 884.2 Commercial Non-Recurring Costs .......................................................................... 89

    5.0 Manpower Requirements ............................................................................................ 916.0 Follow Ship Cost Estimates ........................................................................................ 94

    6.1 Labor Cost Learning ............................................................................................... 94

  • 8/13/2019 task 1.33_5

    4/101

    4

    4

    6.2 Material Cost Learning (Discounts)........................................................................ 957.0 Commercial Prime Contractor Management Plan ...................................................... 96Appendix A: OUTLINE SPECIFICATION FOR HST-160x53 TRAILER SHIP ........... 98

    Principal Dimensions: ................................................................................................... 98Propulsion: .................................................................................................................... 98

    Electrical Power: ........................................................................................................... 98General Arrangement: ................................................................................................... 99Hull Structure: ............................................................................................................... 99Lightship Weight Estimate (metric tonnes): ................................................................. 99Capacities: ................................................................................................................... 100

  • 8/13/2019 task 1.33_5

    5/101

    5

    5

    1.0 Introduction

    The High-Speed Trimaran (HST) Trailer Ship study has been conducted under a Centerfor the Commercial Deployment of Transportation Technologies (CCDoTT) funding andHigh Speed Ship technology development program. The Navy Strategic Mobility &

    Combat Logistics Office (OPNAVN42) is the primary stakeholder of CCDoTT, andCSC-AMC is the prime contractor.

    The HST design team, which is led by CSC/Advanced Marine Center and HerbertEngineering Corp., has designed the ship to be able to serve in the American MarineHighway system to carry domestic trailer traffic between ports along the U.S. coast lines.This is a Dual-Use design that also addresses the Navys need for a troop, equipment andother logistics support transport ship to combat theatres around the world on an as neededbasis.

    SPAR Associates, Inc. produced this report to estimate the design and construction costs

    for two trailer ship designs: a Pure Commercial HST140-53 design and a Dual-UseHST160-53 (Figures 1.0-1 through 1.0-5). The Dual-Use design is somewhat larger insize than the pure commercial ship to accommodate greater fuel capacities for trans-oceanic military service and higher-than-commercial speeds. The Dual-Use design haslarger 53 foot trailer capacity of 160 versus 139 for the Pure commercial Design.

    The reason for estimating these two designs is to determine the ship construction costs ofthe Dual-Use ship to meet National Defense Funding (NDF) features required to supportthe Dual-Use use in Sealift transportation missions. Section 2.1.12 offers estimates in thisregard.

    The estimates were all developed using SPARsESTI-MATEcost model modified fortrimarans. The estimates assume that design and detailed engineering will be performedby an expert naval architecture and marine engineering company. The construction isassumed to be performed by a commercially competitive mid-tiered or big six yard U.S.shipbuilder using modern hull block construction methods.

    A third estimate of the Dual-Use design also has been provided in Section 2.1.13 tosimulate additional construction cost savings possible from the application of extendedmodular construction approach to ship equipment and outfit components. This approachexpands upon hull block construction by outsourcing selected major hull blocks formanufacturing, assembly and outfitting. In addition, design and construction of

    equipment and various outfit components are outsourced for modular fabrication andassembly so that these modules can be readily installed later at the assembly yard on unit,on block and/or on board. Such an approach requires a carefully planned and executedengineering process in order for the modules to be quickly, easily installed and integratedwith other ship systems and infrastructures. Further discussions of these methods areprovided in Section 3.2.4. While some may argue that extended modularization is notcurrently possible due to virtually no vendor infrastructure and too few other series shipprograms needed to support the added engineering efforts. Nevertheless, U.S.

  • 8/13/2019 task 1.33_5

    6/101

    6

    6

    shipbuilders need to at least begin pursuing this approach. It is being aggressivelyexploited by European shipbuilders with sizeable cost savings benefits resulting.

  • 8/13/2019 task 1.33_5

    7/101

    7

    Figure 1.0-1: Dual-Use HST160-53General Arrangement: Profile & Cargo D

  • 8/13/2019 task 1.33_5

    8/101

  • 8/13/2019 task 1.33_5

    9/101

    Figure 1.0-3: Dual-Use HST160-53Machinery Arrangement

  • 8/13/2019 task 1.33_5

    10/101

    Figure 1.0-4: Dual-Use HST160-53Machinery Arrangement

  • 8/13/2019 task 1.33_5

    11/101

    Figure 1.0-5: Dual-Use HST160-53Machinery Arrangement

  • 8/13/2019 task 1.33_5

    12/101

    12

    The cost model utilizes basic ship design characteristics of structures; propulsionsystems; electrical generation and distribution systems; electronics and communicationssystems; auxiliary and outfit systems.

    Figure 1.0-6 presents principal characteristics of the Dual-UseHST160-53 used in the

    ESTI-MATEcost analysis. Final ship hull lengths and beams are slightly different basedon the calculation refinements made in task 3. These refinements do not alter the costestimates.

    Main Hull:

    LOA, Length Overall M 195.00

    LWL, Length Waterline M 179.40

    Beam, Molded M 15.00

    Depth, Molded M 21.00

    Draft, Design Full Load, Molded M 7.50

    Cubic Number (LWL x Beam x Depth) CUNO(M) 58,545

    SVI, Ship Volume Indicator (LWL x Beam x Draft) CUM 20,909

    Cb, Block Coefficient COEF 0.520

    SDI, Ship Displacement Indicator (Cb x SVI) CUM 10,872

    Total Full Load Displacement (Main Hull Only) MTONs 13,084

    Machinery Spaces:

    Volume of Machinery Space (Not incl. Uptakes) CUM 12,763

    Super Structure:

    Super Structure Deck Area SQM 5,111

    Volume of Super Structure (Incl. Storage Spaces Below) CUM 17,887

    Cargo Areas:

    Number Decks Below Weather Deck 2.00

    Total Areas of Cargo Decks OMS SQM 8,550

    Volume Cargo Decks OMS CUM 29,925

    Average Deck Heights M 5.00

    Side Hull:

    LOA, Length Overall M 101.00

    LWL, Length Waterline M 92.92

    Beam, Molded M 5.30

    Depth, Molded M 21.00

    Draft, Design Full Load, Molded M 7.50Cubic Number (Depth) CUNO(M) 10,342

    SVI, Ship Volume Indicator (LWL x Beam x Draft) CUM 3,694

    Cb, Block Coefficient COEF 0.486

    SDI, Ship Displacement Indicator (2 x Cb x SVI) CUM 3,588

    Total Full Load Displacement (Both Side Hulls) MTONs 3,944

  • 8/13/2019 task 1.33_5

    13/101

    13

    13

    Max Beam Overall at Deck: M 35.40

    Equivalent Beam: M 20.55

    Combined Total Cubic Number (Combined Total): CUNO(M) 72,516

    Combined Cb, Block Coefficient: Cb 0.432

    Combined Ship Displacement Indicator, SDI: 13,186

    ACCOMMODATIONS

    Ship's Crew Number (MSC) CREW 20

    Commissioned Officers PAX -

    Non-Commissioned Officers PAX -

    Enlisted PAX -

    Troop Force PAX -

    Overnight Passengers PAX -

    PAX Daytrippers PAX -

    Total 20

    Figure 1.0-6: Dual-Use HST160-53-High-Speed Trimaran Trailer Ship

    Figure 1.0-7 presents weight and displacement characteristics of theDual-Use HST160-53.

    Displacement:

    Total Displacement at Full Load Draft MTON 17,011

    Total Displacement at Full Load Draft CUM 16,593

    Light Ship Weight MTON 10,599

    Light Ship Weight CUM 10,338

    Fuel & Load Items MTON 3,520

    Fuel & Load Items CUM 3,433

    Total Payload Displacement MTON 2,892

    Total Payload Displacement CUM 2,821

    CARGO CAPACITY

    Designed Deck Space per MTON Cargo SQFT/MTON -

    Designed Deck Space per MTON Cargo SQM/MTON -

    Required Cargo Deck Space SQM -

    Number of TEUs TEU 400

    Number of Vehicles at Capacity NO. 160

    Average Weight per Vehicle MTON/EA 20.00

    Average Deck Space per Vehicle SQM -

    Liquid Cargo Capacity CUM -

  • 8/13/2019 task 1.33_5

    14/101

    14

    14

    BBL -

    Figure 1.0-7: Dual-Use HST160-53-High-Speed Trimaran Trailer Ship Weights &Displacements

    Figure 1.0-8 provides theDual-Use HST160-53light ship weights for each SWBS Group.

    SWBS Group Weights Computed

    1 Hull MTONS 7,200 Includes masts, foundations, stacks, ramps, etc.

    2 Propulsion MTONS 1508Includes all propulsions systems, shafting, gearboxes, thrusters, etc.

    3 Electrical MTONS 493Includes generators, transformers, batteries,panels, lighting, & distribution systems

    4 Electronics & Navigation MTONS 35

    5 Auxiliary Systems MTONS 698 Includes all HVAC, piping, & deck machinery

    6 Outfit & Furnishings MTONS 334 Includes all hull outfit items & paint

    7 Armament MTONS - Misc. armament foundations, small arms, etc. only

    Total: 10,,267

    Figure 1.0-8: Dual-Use HST160-53-High-Speed Trimaran Trailer Ship Light ShipWeights

  • 8/13/2019 task 1.33_5

    15/101

    15

    15

    2.0 The Cost Estimates

    The following describes the cost estimates for the two HST designs.

    2.1 Cost Estimate Work Breakdown Structure

    Two separate estimates were produced for the design and construction costs for twotrailer ship designs: a Pure Commercial HT140-53 design and a Dual-Use HST160-53.

    The cost model uses as its basis cost data, (cost estimating relations or CERs) that isapplicable to a generic mid-tier commercial U.S. shipyard. These costs are adjusted forproductivity and pricing differences for shipbuilding companies expected to undertakeconstruction of these vessels.

    To approximate costs at time of actual construction, all cost and pricing has beendeveloped in 2009 U.S. dollars.

    The cost estimate is broken down into four (4) major cost categories:

    1. Non-Recurring Design, Production Engineering & Detail Planning Costs2. Recurring Construction Costs3. Management Fees (Option for managing a virtual shipbuilding approach)4. Cost Risk

    2.1.1 Non-Recurring Costs

    The non-recurring costs include design development, detail design, engineering andproduction planning.

    The cost model includes the following activities as non-recurring costs:

    1. Preliminary Design & Design Validation2. Detail Functional Engineering3. Detail Transitional (Production) Engineering & Construction Drawings/Shipyard

    Instructions, Including Lofting

    4. Detail Production Planning5. Purchase Specifications & Support6. Detail Engineering Management

    The cost model develops the non-recurring labor estimates based on a percentage of leadship production hours. Section 4 describes this process in more detail. For theconventional hull block construction scenarios, the non-recurring labor hours wereestimated at 30% of the production hours.

  • 8/13/2019 task 1.33_5

    16/101

    16

    16

    Figure 2.1-1 presents the non-recurring labor hours estimates.

    1

    ,504

    25

    ,863

    252

    ,617

    23

    ,683

    6,0

    15

    3

    ,007

    9,7

    74

    12

    ,029

    2

    ,003

    34

    ,446

    336

    ,453

    31

    ,543

    8,0

    11

    4

    ,005

    13

    ,018

    16

    ,022

    50,000

    100,000

    150,000

    200,000

    250,000

    300,000

    350,000

    400,000

    C 14053

    C

    D 16053

    C

    Figure 2.1-1: Estimated Non-Recurring Labor Hours

    Figures 2.1-2 presents the non-recurring cost estimates for each of the HST designs.

  • 8/13/2019 task 1.33_5

    17/101

    17

    17

    Figure 2.1-2: Estimated Non-Recurring Costs for Conventional Hull BlockConstruction Build Strategy

    The non-recurring cost estimates are based on the assumption that the HST designs arerelatively simple and straight forward. Outfitting is not expected to be exotic or complexwith the exception of the propulsion systems. The commercial shipbuilder is expected tohave a lower non-recurring cost compared to a military design and should follow closelycommercial design and engineering practices.

    The cost model places costs for producing jigs and templates, etc. also under this Non-Recurring Production Engineering and Detail Planning.

    The non-recurring cost estimates further assume that production engineering will befocused on ways to simplify the manufacturing and building processes. This engineeringeffort can capitalize on engineering and production standards in order to exploit the costsaving benefits of repeatable interim production products. For example, the side hulls arealmost identical.

    $52

    $70

    $

    $10

    $20

    $30

    $40

    $50

    $60

    $70

    $80

    C 14053

    C B C

    D 16053 C

    B C

    2009$

    E C

  • 8/13/2019 task 1.33_5

    18/101

    18

    18

    The estimates also assume that detail production planning is of a high level thateffectively schedules work at the earliest, most productive stages of construction (i.e.,pre-outfitted hull blocks) consistent with available facilities, material and qualitytechnical and engineering information. The scheduling will effectively coordinate all ofresource requirements throughout the various stages of construction.

    2.1.2 Recurring Costs

    Recurring costs include all basic construction costs for each ship. For series shipconstruction programs, costs are estimated for follow-on ships by applying estimatedlearning curve factors for labor and potential material cost savings. Refer to Chapter 6,Follow Ship Cost Estimates.

    The recurring cost estimate is broken down into cost categories similar to the NavysShip Work Breakdown Structure (SWBS), Figure 2.1-3. Differences lie primarily in

    SWBS 200 which carries only propulsion machinery items and their installation(including electric drive components and systems). Piping systems for propulsion arecataloged under SWBS 500 for auxiliary systems along with all other piping systems forthe ship.

    100 Hull200 Propulsion300 Electrical400 Electronics & Navigation500 Auxiliary Systems600 Outfit & Furnishings700 Armament

    800 Technical Support900 Shipyard Services

    1000 Contingency Margin, Insurance & Extras

    Figure 2.1-3: Recurring Cost Estimate Work Breakdown Structure

    SWBS 100: Normally, the cost model requires structural weights to be summarized bymajor structural components (i.e., production interim products): decks, double bottoms,side shells, frames, transverse and longitudinal bulkheads, superstructure, etc. Each ofthese components have different manufacturing and assembly characteristics (i.e., requiredifferent production processes), and therefore each can be assigned different costestimating relationships (CERs). Material costs also will vary depending upon thematerials used (mild steel, high strength steel aluminum, composites, etc.)

    As discussed in Section 3.4, Shipyard Productivity Factors, the structural CERs aremodified with appropriate productivity factors developed for each type of ship builder.The CERs also will be modified for the overall size of the hull to account for the general

  • 8/13/2019 task 1.33_5

    19/101

    19

    19

    tendency that larger hulls are less expensive to build on a structural weight basis (somemeasured economy of scale).

    The cost model places all structural work, including ramps, foundations, masts, andstacks under SWBS Group 100.

    Structural material costs are estimated on the basis of weight and type. The unit cost,however, is increased by 35% to account for material transportation (about 10%), scrap(typically 12%-16% to as much as 25% for structures with much shape andcomplexities), welding materials and gases (7%-8%), and classification society fees(about 1%). Figure 2.1-4 presents the steel prices and allowances used for the HSTestimates.

    Figure 2.1-4: Steel Prices & Allowances Used for HST Estimates

    SWBS 200: Somewhat divergent from the U.S. Navys SWBS, the cost model places allpiping and ventilation systems under SWBS Group 500 (Auxiliary Systems). Therefore,Propulsion Support Systems (SWBS 250-259) & Fuel/Lube Support (SWBS 260-269)were moved to SWBS Group 500.

    SWBS 200 also includes primary costs for electric drive systems, if applicable, such asdiesel generators, electric motors, pods, etc.

    In addition, costs for thrusters, if applicable, also are included under the cost modelsSWBS 200.

    SWBS 300carries all electric generation equipment for ship services (not forpropulsion), as well as all electrical distributed systems, lighting, etc. The cost modelestimates electrical costs based on the type of electrical generation system, includingemergency generation, and the power output (kW).

    For combatant type ships, the cost model has options to reflect the assumption that theelectrical distribution costs are considerably higher, by factors of about three-five times

  • 8/13/2019 task 1.33_5

    20/101

    20

    20

    that for a commercial vessel. This assumption accommodates added costs for shockrequirements and for power redundancy required for complex combatants.

    SWBS 400: The cost model offers essentially two levels of electronics: standard

    electronics, communications and control systems for commercial ships and variouselements of C4ISR for military ships.

    SWBS 500: The cost model includes the following auxiliary systems plus others:

    Fans, duct work, & HVAC All piping systems, including piping support systems for main propulsion (lube

    oil, etc.)

    Anchor/mooring systems & deck machinery Cargo cranes

    For combatant type ships, the cost model has options to reflect the assumption that pipingsystems costs are higher than for commercial vessels. This assumption accommodatesadded costs for shock requirements.

    SWBS 600: The cost model includes the following in SWBS Group 600, Outfit &Furnishings Systems plus other relevant outfit systems:

    Paint Hand rails, stanchions, & walkways

    Floors, ladders, grates Life boats, rafts Insulation Metal doors, sheathing & bulkheads Accommodations outfit & furnishings

    The cost estimates do not include costs for load items, fuels, lubricating fluids, etc.

    SWBS 700: CERs are available to a limited extent for weapons systems, mostly for their

    foundations. For the DUAL-USE HST160-53, the cost model has not estimated the costsfor armaments.

    SWBS 800: U.S. Navy contracts catalog both recurring and non-recurring technical coststogether under SWBS 800. Therefore, the majority of engineering costs appear for thelead ship. The cost model, instead, catalogs only the recurring costs under SWBS 800

  • 8/13/2019 task 1.33_5

    21/101

    21

    21

    and catalogs non-recurring costs under a separate project WBS. This separation allowsthe non-recurring costs to be easily allocated to all ships of a series program.

    Technical Services, includes only technical support for minor change orders and finetuning of production engineering and planning after non-recurring activities are complete.

    For both HST160-53 designs, the assumed percentage of total production labor hours(SWBS Groups 100-700) for shipyard technical support services was set at 8%.

    SWBS 900: For shipyard production support services, a figure of 20% of productionlabor hours (SWBS Groups 100-700) was used for the estimate. This is a figure notatypical of North American commercial yard that employ reasonable control over thislevel of effort and follows a regimen that minimizes unnecessary costs. A majorcomponent of this cost lies in supervision and production control.

    For the conventional hull block construction scenario, no costs have been estimated fortransportation of hull modules to a central erection site. However, for the extended

    modularization scenario, costs are estimated to load/barge/unload the side hulls anddeckhouse structures at the final assembly yard. The estimates reflect a one-piecejoining method for final hull block erection. Design and construction of special erectionsite equipment such as float barges, etc. are not included as it is assumed that the shipsize is not so large as to present special erection and launching operations.

    For both scenarios, no costs are estimated for ultimate delivery to a location away fromthe shipyard.

    The cost model places costs for producing jigs and templates, etc. under the Non-Recurring Detail Production Engineering and Planning described above.

    General support costs, a difficult source of cost to control because it is mostly level ofeffort, can be reduced.

    1. Early stage outfitting (on unit and on block) eliminates considerable support costsrequired for on board outfit efforts.

    2. Early stage outfitting minimizing or eliminating scaffolding and related supportcosts.

    3. Improved material flow to work areas minimizes material transport costs.4. Higher level of work skills and higher quality of production engineering reduces

    supervision and quality assurance costs.

    SWB 1000: The cost model uses an additional SWBS group outside normal U.S. Navypractice. The additional SWBS 1000 is used for costs outside those for production andtechnical/shipyard services (ABS, financing fees and MARAD title XI when applicable,etc.) and for various shipbuilding risk insurance costs, warranty bonds, etc. This SWBSgroup also includes a contingency cost item for change orders and for yet-undefined shipsystem requirements.

  • 8/13/2019 task 1.33_5

    22/101

    22

    22

    Figures 2.1-5A and 2.1-5B summarize the lead ship cost estimates for the two HSTdesigns.

  • 8/13/2019 task 1.33_5

    23/101

  • 8/13/2019 task 1.33_5

    24/101

  • 8/13/2019 task 1.33_5

    25/101

  • 8/13/2019 task 1.33_5

    26/101

    26

    2.1.-6: Dual-Use HST160-53-High-Speed Trimaran Trailer Ship Construction S

  • 8/13/2019 task 1.33_5

    27/101

    27

    A cross-check of whether or not this schedule is reasonable is reflected in the estimatedmanpower requirements (See Section 6).

    Figure 2.1-7a illustrates that these estimated manpower requirement figures are well

    within reasonable levels available for design and construction of a ship of this size.Figure 2.1-7b shows estimated production manpower requirements.

    Figure 2.1-7a: Combined Non-Recurring and Lead Ship Recurring Manpower

    Requirements for Conventional Hull Block Construction of Dual-Use HST160-53

  • 8/13/2019 task 1.33_5

    28/101

    28

    28

    Figure 2.1-7b: Estimated Lead Ship Production Manpower Requirements for

    Conventional Hull Block Construction of Dual-Use HST160-53

  • 8/13/2019 task 1.33_5

    29/101

    29

    2.1.4 Series Construction Programs

    Follow ships of a series ship production program typically experience a progression of

    relative cost reductions as each ship unit is produced. Figure 2.1-8 presents constructioncosts for a series sp production program estimated for the Dual-Use HST60-53. An 85%learning curve has been applied for labor with the exception that the 2

    ndship of the series

    has been restrained to leaning of only 97%. A 95% learning (discount) has been appliedto material costs. All cost figures are provided in 2009 U.S. dollars. Effects ofinflation/deflation have not been applied, and their effects upon ship costs are assumed tobe included as an additional contact allowance.

    Details of the application of learning curves for series ship programs are provided inSection 7.

    Figure 2.1-8: Construction Costs for Series Ship Production, Dual-Use HT60-53

  • 8/13/2019 task 1.33_5

    30/101

    30

    30

    Figure 2.1-9 provides averaged estimates that allocate non-recurring costs across thenumber of ships in a series. This chart shows both should costs and should cost plusestimated total risk cost.

    The should cost equates to the likely price bid by a skilled and experience engineering

    firm and a well organized shipbuilder experienced with successfully executing modernhull block construction methods. These are should prices applicable for what weshould expect from U.S. companies. Should prices from foreign world classshipbuilders should be expected to be considerably lower due to their greater levels ofproductivity and their abilities to purchase equipment and materials at prices lower thanwhat we typically expect here in the U.S.

    Another way of visualizing the should cost prices is to envision the price bid by acommercially competitive U.S. shipyard experienced in pre-outfitted hull block assemblydesign and construction methods. This bid price would consider

    a) The assumed need for the shipbuilding contract,b) Include allowances for controllable and carefully managed shipbuilding risksc) Assume a well managed yard building to a well engineered and comprehensive

    detail design.

    Section 2.1.6 describes in more detail a breakdown of cost risk. The primary elements ofthis total risk will depend upon the relative skills and experience of the engineering andof the shipbuilder. Recent examples of serious budget problems with both commercialand naval construction programs have, in large measure, been reflected in the estimatesof the risk figures. The more skilled and experienced the contractor, the lower one wouldexpect the actual risk to be. Each contractor will likely assess its own levels of risk andprice its bid accordingly. Therefore, the illustrated range between should cost and whatincludes total risk is where bids are likely to fall.

  • 8/13/2019 task 1.33_5

    31/101

    31

    31

    Figure 2.1-9: Average Design & Build Costs for Conventional Hull Block

    Construction of Dual-Use HST160-53

    Details of cost risk are provided in Sections 2.1.6 and 3.6.

    2.1.5 Management Costs & Fees

    For a successful virtual shipbuilding approach that promises significant cost savings,there will be a critical need for advanced planning of both engineering and productionprocesses to ensure that subcontractors are well organized and their schedules closelysynchronized and supervised. As an alternative to having the prime assembly shipyard

    being the over arching program manager, the extended modular construction approachhas its estimate including an additional cost for a professional program managementteam. Section 7 describes a possible expert program management team.

  • 8/13/2019 task 1.33_5

    32/101

    32

    32

    2.1.6 Cost Risk

    The estimates provide should costs as well as estimates of cost risk.

    Figures 2.1-10 and 2.1-11 present breakdowns of cost risk as estimated for the Dual-UseHST160-53. Recently, there have been a number of occasions whereby both engineeringand shipbuilder cost and schedule performance has been less than desirable resulting incontracts significantly over budget and schedule. The high levels of estimated cost riskfor these build strategies reflect current performance difficulties in the industry at large.

    However, the breakdowns of cost risk provide some clarity and focus into whereimprovements need to be made to reduce cost risk.

    Figure 2.1-10: Estimated Lead Ship Total Price with Cost Risk for Conventional

    Hull Block Construction Build Strategy for Dual-Use HT160-53

    $70

    $233

    $30$0

    $49

    $98

    $2

    $

    $100

    $200

    $300

    $400

    $500

    $600

    A:

    E & C 2009$

    E. C

    E. E C

    E. E C

    E. C

    E. CE C

    E. C

    D, E &

  • 8/13/2019 task 1.33_5

    33/101

    33

    33

    Figure 2.1-11: Estimated Cost Risk for Conventional Hull Block Construction Build

    Strategy, Dual-Us HST160-53

    With an estimated little overlap of engineering and production, the cost risk for reworkdue to an overlap should be relatively small. Also, the build schedule is not aggressive,so the cost risk due to cramped scheduling also should be minimal.

    Risk here defines a range of costs above the should cost to reflect what a shipbuildermay require in his bid to accommodate a number of adverse variables:

    Costs, such as those estimated for equipment and materials, may become greaterdue to economic uncertainties, currency fluctuations, etc.

    The shipbuilder may exact a high degree of rework due to having too much detailengineering not being complete in time to support an efficient production

    schedule The bidding yard may expect higher costs due to the fact that the yard may have

    little actual experience building a ship of this type. In addition, production mayno longer enjoy having a highly skilled work force.

    A detail engineering effort that has not performed well often results in muchhigher production costs and schedule delays.

    If the production schedule is too short, requiring higher than normal levels ofresources to manage can result in higher costs in production.

  • 8/13/2019 task 1.33_5

    34/101

    34

    34

    Details of the cost risk estimates are provided in Section 3.6.

    Figure 2.1-13 presents a range of potential lead ship costs (including non-recurring costs)for the Dual-Use HST160-53 design:

    Minimum costs that does not include any risk nor a 10% contingency forunknown ship systems, etc.

    Should costs that include the 10% contingency, but no risk. Estimated maximum cost that includes contingency plus 100% estimated risk. More likely maximum cost that included contingency plus 67% estimated risk.

    The cost at 100% risk hopefully is not likely. According to generalized probabilitytheory, 67% of the total risk can relate to an 80% probability. By identifying the majorareas for cost risk, efforts should focus on working to eliminate them. Only then will acontract opportunity have more potential for success, and less potential for ultimate

    failure should the risks not be accommodated nor remediated.

    Figure 2.1-13: Range of Potential Costs for Lead Ship, Dual-Use HST160-5

  • 8/13/2019 task 1.33_5

    35/101

    35

    35

    2.1.7 Labor Rates

    The following labor & overhead rates (Figure 2.1-14) are used for the estimates. Theaverage U.S. shipyard production 2009 wage rate is based on wage data obtained fromthe U.S. Bureau of Labor Statistics. Technical and detail engineering wages rates were

    estimated by applying the wage ratio (120.4%) of average U.S. technical to shipyardproduction wages as measured by the U.S. Department of Commerce

    1, December 1,

    2003.

    The fully burdened wage rates are assumed to include fringe benefits

    Overhead is applied only to shipyard labor. Profit is not included in any labor rates, butapplied separately (see Section 2.1.9 below).

    Non-Recurring Engineering LaborCommercial Ship

    Builder

    Senior Professional/Manager $ 143.77

    Engineer $ 128.35

    Designer/Draftsperson/Planner $ 96.04

    Clerical $ 61.62

    Contingency (weighted average) $ 119.02

    Shipyard Recurring LaborCommercial Ship

    Builder

    Technical Wage/Hour $ 24.56

    Production Wage/Hour $ 20.47

    Overhead 125%

    Technical Wage/Hour w/OH $ 55.26Production Wage/Hour w/OH $ 46.05

    Figure 2.1-14: Applied 2009 US$ Labor & Overhead Rates

    The above labor rates do not include any profit which is added afterwards as described inSection 2.1.9.

    2.1.8 Material Costs

    All HST160-53material has been assumed to be of commercial grade and have beenestimated for the year 2009. Section 3.5 describes the processes within the cost modelfor escalating costs for a common year estimates.

    1U.S. DOC/BIS TSV Site Survey Data, dated December 1, 2003.

  • 8/13/2019 task 1.33_5

    36/101

    36

    36

    A 10% mark-up (general and administrative costs) was applied to the material costestimates. This mark-up includes any burden rate applied by the shipyard, but does notinclude any profit which is added afterwards as described in Section 2.1.9.

    2.1.9 Profit

    From 1999-2000, U.S. shipbuilders reported profits of over 11%. For the HSTestimates, a profit rate of 12% was used. Profit is applied to all costs: labor, material,subcontracted services, overhead and material G&A costs.

    2.1.10 Transport Factors

    Transport factors measure cargo crying capacity versus ship speed and propulsion power.

    The greater the factor, the greater the capacity to carry cargo t higher rates of speedwithout an adverse penalty for power, which is a measure of cost. The following formulais one of several that define a transport factor:

    Transport Factor = [Payload x Speed]/HP/550

    Figure 2.1-15 presents transport factors for the two HST ship designs.

    Figure 2.1-15: HST Transport Factors

    Figure 2.1-16 shows the average ship cost per transport factor, which decreases for largership construction programs.

    12.79

    10.37

    15.78

    2.004.006.008.00

    10.0012.0014.0016.00

    18.00

    D 160

    53 C

    B

    C 26

    D 160

    53 C

    B

    C 30

    C

    14053

    C

    B C

    26

    D F

  • 8/13/2019 task 1.33_5

    37/101

    37

    37

    Figure 2.1-16: Comparing Average Ship Cost per Transport Factor

    2.1.12 National Defense Funding (NDF)

    The estimated lead ship costs for the Dual-Use and for the Pure Commercial designs are

    compared in Figure 2.1-17.

    Figure 2.1-18 compares potential NDF for average series ship costs at different levels ofcost risk.

    $29

    $25$23

    $22$21 $21 $20 $20

    $24

    $20$19

    $18 $17 $17 $16 $16

    $14$12

    $11 $10 $10 $10 $10 $9

    $

    $5

    $10

    $15

    $20

    $25

    $30

    $35

    1 2 3 4 5 6 7 8

    A C/ F 2009$

    F = //550

    D 16053 C B C 30

    D 16053 C B C 26

    C 14053 C B C 26

  • 8/13/2019 task 1.33_5

    38/101

    38

    38

    Figure 2.1-17: Comparing Lead Ship Costs

    Figure 2.1-18: Potential NDF for Series Ship Production Programs

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    $

    %

    %

  • 8/13/2019 task 1.33_5

    39/101

  • 8/13/2019 task 1.33_5

    40/101

    40

    40

    Figure 2.1-20 provides the cost estimate for the modularized Dual-Use H60-53. Sizeablecost savings are very possible over conventional outfitting. The estimate assumesmaximum modularization, which at present is not possible. However, benefits should be

    recognized even if only selected modules are developed.

    It should be expected that lower costs would be realized by outsourcing modules tovendors that specialize in manufacturing and assembling selected equipment andcomponents. Some cost reductions should also be realizable if the modules weredeveloped by the shipbuilder using internal resources.

  • 8/13/2019 task 1.33_5

    41/101

  • 8/13/2019 task 1.33_5

    42/101

    42

    Figure 2.1-21 presents verged costs to build series ships of the Dual-Use design using thefull extended modulizaion approach.

    $294

    $250

    $

    230

    $2

    19

    $21

    1

    $205

    $201

    $197

    $426

    $361

    $319

    $297

    $282

    $271

    $264

    $257

    $0

    $50

    $100

    $150

    $200

    $250

    $300

    $350

    $400

    $450

    1 2 3 4 5 6 7 8

    A

    C

    D

    &B

    A C 2009$

    & ,

    Figure 2.1-21: Averaged per Ship Costs for Dual-Use Design Using Maximum

    Extended Modularizing of Design and Construction

  • 8/13/2019 task 1.33_5

    43/101

  • 8/13/2019 task 1.33_5

    44/101

    44

    Voyage Segment

    Distance in

    Nautical Miles

    At Sea

    Speed

    Time

    Interval Time

    Start Arrive at Fall River 8:00 AM

    Dock+Unload + Load+Undock at FallRiver i.e. .5+3+3+.5 hrs = 7.00 3:00 PM

    Fall River to Newport, RI 16 12.0 1.33 4:20 PM

    Newport, RI to Sea Buoy 5 15.0 0.33 4:40 PM

    Sea Buoy to Port Canaveral 905 22.9 39.59 8:15 AM

    Port Canaveral sea buoy to terminal 16 12.0 1.33 9:35 AM

    Dock+Unload + Load+Undock at

    Canaveral i.e. .5+3+3+.5 hrs = 7.00 4:35 PM

    Port Canaveral terminal to sea buoy 16 12.0 1.33 5:55 PM

    Port Canaveral to Newport, RI sea buoy 905 24.9 36.41 6:20 AM

    Newport, RI to Sea Buoy 5 15.0 0.33 6:40 A

    Newport, RI to Fall River 16 12.0 1.33 8:00 A

    TOTALS 0.0 96.00

    Figure 2.1.23: U.S. East Coast Trade Route

  • 8/13/2019 task 1.33_5

    45/101

    45

    The Required Freight Rate (RFR) was developed under the following assumption:

    Number of Ships Built: 4 Maximum of 8 for this analysis

    Total Price per Ship: 231,805,011$

    Difference Dual-Use less Pure

    Commercial Designs 64,671,836$ Total NDF

    Credits for 21 extra trailer capacity (8,488,178)$ 56,183,657$

    Net Owner's Asset Value 175,621,353$ 7,024,854$ per year

    Total Cost of Money per Ship: 95,889,259$ 3,835,570$ per year

    Sub-Total: 271,510,612$ 10,860,424$ per year

    Anticipated Life of Ship: 25 Years

    Salvage/Sale Value at Life End: 2,433,057$ 1.05% Total Acq. Price

    Average Annualized Capital Cost: 10,763,102$

    Laydays & Repair Days per Annum 9.00 Days

    Total Days per Round Trip 4.00 Days RoundedTotal Round Trips per Annum: 89.00 Trips

    Payload MTONs per Annum: 512,640 MTONs

    Vehicles per Annum: 25,632 EA 20.00 MTON/EA

    Figure 2.1-24: General Operating Scenario for Trade Route

    Financing arrangements have been developed under the following scenario:

    MarAd required equity portion: 12.50% 21,952,669$

    Principle % Interest Years PMTS/Year Tot. Int.

    Equity Portion 21,952,669$ 28.0% - 0 $0

    Finance Plan A 153,668,684$ 5.2% 25 1 ($95,889,259)

    Finance Plan B -$ 0.0% - 1 $0

    Finance Plan C -$ 0.0% - 1 $0

    175,621,353 ($95,889,259)

    Figure 2.1-25: Estimated Financing Arrangements

    Figures 2.1-26 and 2.1-27 summarize the estimated annual operating costs (90% round

    the clock servicing). Fuel cost applied is $485/mt.

  • 8/13/2019 task 1.33_5

    46/101

  • 8/13/2019 task 1.33_5

    47/101

    47

    47

    Figure 2.1-28 breaks down the average required right rate per trailer for transit betweenFall River, MA and Port Canaveral, FL.

    $419.91

    $239.81

    $898.71

    $175.56

    $415.93

    $300.00

    $67.83

    $87.07

    $

    $500

    $1,000

    $1,500

    $2,000

    $2,500

    $3,000

    1

    F

    (C/

    )

    F BC

    (F , A C, F)

    , &

    C

    &

    DD D

    C & C

    C C

    Figure 2.1-28: Required Freight Rate per Trailer

    Figures 2.1-29 and 2.1-30 break down the required freight rate on a basis of an equivalentcost per statute mile.

  • 8/13/2019 task 1.33_5

    48/101

    48

    48

    $0.38

    $0.22

    $0.81

    $0.16

    $0.38

    $0.27

    $0.06

    $0.08

    $

    $0.50

    $1.00

    $1.50

    $2.00

    $2.50

    $3.00

    1

    F

    /

    , &

    C

    &

    DD D C

    & C

    C C

    F C

    E

    C C

    Figure 2.1-29: Required Freight Rate per Statute Mile

  • 8/13/2019 task 1.33_5

    49/101

    49

    49

    15% 9%

    33%

    6%

    15%

    11%

    1%1% 3%3% 3%

    F

    /

    C C

    E

    F C

    C C

    & C

    DD D C

    &

    C, &

    Figure 2.1-30: Required Freight Rate per Statute Mile

    The figures above all are based on 100% full load of 160 trailers and a fuel cost of $400per metric ton.

    Figures 2.1-31 and 2.1-32 illustrate the effect of fuel cost and percentage of full load onrequired freight rates.

  • 8/13/2019 task 1.33_5

    50/101

    50

    50

    = 1.665 + 1,688.167

    = 1.000

    = 1.855 + 1,839.833

    = 1.000

    = 2.085 + 2,033.167

    = 1.000

    $2,000

    $2,200

    $2,400

    $2,600

    $2,800

    $3,000

    $3,200

    $3,400

    $3,600

    $300 $350 $400 $450 $500 $550 $600 $650 $700 $750

    E2009

    $/

    A F C 2009 $/

    F F C

    Figure 2.1-31: Fuel Cost versus Required Freight Rate per Trailer Haul

    = 0.001 + 1.523

    = 1.000

    = 0.002 + 1.660

    = 1.000

    = 0.002 + 1.836

    = 1.000

    $0.00

    $0.50

    $1.00

    $1.50

    $2.00

    $2.50

    $3.00

    $3.50

    $300 $350 $400 $450 $500 $550 $600 $650 $700 $750

    E2009

    $/

    A F C 2009 $/

    F F C

    Figure 2.1-32: Fuel Cost versus Required Freight Rate per Statute Mile

  • 8/13/2019 task 1.33_5

    51/101

    51

    51

    Figure 2.1-33 presents the worksheet used to determine port costs. It is based onpublished rates from Port of Canaveral, FL. Costs to load and unload trailers wereestimated at a labor rate of $48/hour and applied to the number of trailers

    loaded/unloaded over the seven hour time period. This figure is probably on the highside as not all trucks would be required to wait the full amount of time to load/unload.

    These same costs were applied to the Fall River, MA port, for which rates were notimminently available.

    0 0

    Trailers 144 144

    2,880 3,175

    195 640

    0 0

    ' 7.5 24.6063

    . = 3/2.833 3143 1,111

    . 89.00 / 7

    C, F

    Mooring Fee -$ -$

    Harbor Master -$ 186$ 186$ 185.66$ 2000

    Cargo Warfage - Trailers -$ 7,873$ 7,873$ 2.48$

    Cago Warfage - TEUs -$ -$ $ 23.20$ 28.98$ 450

    Dockage -$ 4,875$ 4,875$ 4,874.54$ 24

    Loading/Unloading Costs - Trailers -$ 48,384$ 48,384$ $48

    Loading/Unloading Costs - TEUs -$ -$ $

    Tolls -$ -$

    Pilotage based on LOA -$ 308$ 308$ 12.50$ 12

    Pilotage based on GRT -$ 70$ 70$ 0.0280$ 2500

    Tugs -$ 23$ 23$ 2,025$ Agency Fees -$ -$

    Homeland Security Fees -$ -$

    Outside Storage Trailers (2 days) -$ 885$ 885$ 2.09$ 15

    Outside Storage TEUs (2 days) -$ -$ $ 1.85$

    Sanitary Waste Removal -$ 13$ 13$ 1,125$

    Oil Waste Removal -$ 13$ 13$ 1,125$

    Stevedoing Services -$ 19$ 19$ 1,700$

    Fresh Water -$ -$ $ 1,125$

    Fresh Water Hookup -$ -$ $ 50.66$

    Other Port Expenses -$ -$

    Total Port Costs: 62,647$

    435.05$

    Figure 2.1-33: Estimated Port Costs

    Drayage costs to truck trailers to/from the port to local destination (assumed 50 mileseach way) was based on a trucking freight rate of $3.00 per mile.

  • 8/13/2019 task 1.33_5

    52/101

    52

    52

    3.0 Basis for the Cost Estimate

    SPARs cost estimates are generated from developed cost models. Each cost model istailored to a specific hull form (mono-hull, catamaran, trimaran, etc.) and usually to aspecific performance category (slow, medium and high speed). Models also can vary foraccommodating special equipment and mission requirements.

    The cost models approach for an estimate is based first upon the composition of thehulls structural components (decks, bulkheads, shell, double bottoms, etc.), and thenupon the ship systems (mechanical, piping, electrical, HVAC, etc.) in the design andupon other ship characteristics. Factors considered and applied if relevant are the generalbuild strategy for on-unit, on-block and on-board construction; the type of shipyard andits established product line, its facilities and production capabilities; and the expectedcompetence of the shipyard to plan and manage its resources, costs and schedules.

    The methods used for modeling the ship design costs are described in SPARspublication entitled Shipyard Cost Estimating.

    Each cost model employs a comprehensive set of Cost Estimating Relationship, or CERs.They reside on SPARs estimating system called PERCEPTION ESTI-MATE andrepresent a wide cross-section of current and historical shipyard construction costs atmany levels of detail. Adjustments can be made as necessary to reflect differing shipyardproductivity factors, construction methods and material costs. These CERs, whileparametric in nature, focus on a specific area of cost (labor and material) and eachreflects the specific material and the manufacturing and assembly processes required.

    Specialized CERs focus on structural component fabrication, assembly and erection, forinstallation of propulsion systems, and for various support activities, etc. The CERs arebased on a many different metrics, such as weld length, deck area, compartment volumes,number of crew (by type crew), kW of propulsion (by type), etc. Hull structuralcomponent costs are based upon component weight by type of structure and material.

    The cost estimates, applicable to a lead ship, are believed to be fair representations ofanticipated true costs based upon the design information provided. Material costs allhave been adjusted to reflect a common year value. This assumes that for a multi-yearprogram, appropriate contract escalation clauses have been defined to index actual costsrelative to the base year.

    Variations due to specific materials, equipment models and configurations, and vendorpricing methods should be expected.

    The cost estimates assume ship delivery at the final assembly construction yard and donot include any subsequent transportation costs to another site or other ancillary itemcosts as discussed above. Also, for the commercial shipbuilder, the cost estimateincludes typical builders risk insurance and added costs for warranty bonds as are typical

  • 8/13/2019 task 1.33_5

    53/101

    53

    53

    of commercial shipbuilding contracts (these costs are not included in the estimates for theDual-Use and combatant shipbuilders.

    Finally, the estimates are based upon typical contract cost and schedule performance forthe three types of shipbuilders for both non-recurring engineering and production.

    3.1 Cost Estimating Methodology

    The SPAR method of cost estimating differs significantly from the way that the U.S.Navy does its estimating. The U.S. Navy largely develops its estimates based on similarhull forms and design specifications. Then, for similar hull forms, system costs areestimated based on weight and weight alone, although some adjustment factors are oftenapplied. The primary problems with this weight-based method of estimating are thefollowing:

    It cannot easily estimate cost differentials below gross levels of the workbreakdown structure (WBS). This precludes the method from being useful fortrade-off studies of designs, materials, and manufacturing Processes.

    It cannot estimate cost differentials of outfit work performed at differentstages of construction: on unit, on block and on board. Various establishedrules of thumb indicate that these cost differentials can vary from 300% to500% or more.

    It cannot estimate cost differentials due to configuration complexity, such ascompartment density or location on board the ship (par. ex., confining engineroom installation versus easily accessible weather deck installation).

    It cannot estimate cost differentials due to orientation of work (par. ex., less

    productive over head work versus more productive down hand work). It cannot estimate cost differentials due to changes in build strategy, including

    outsourcing the manufacturing of selected components to more productive,less costly vendors and suppliers.

    Since it operates mostly at high levels of the WBS, it cannot easily translate orsegment costs from one type of ship to another, particularly ship types andhull forms not yet developed and built.

    SPARs cost models, on the other hand, are based mostly on ship characteristics andvarious system components that make up the ship design. There are components that areequally applicable for almost any ship type but will vary for size and capacity. Examples

    are major equipment modules (propulsion, electric generation, etc.). Other examples ofcommon components can be seen in certain functional areas like berthing, galley andmess.

    Some of SPARs Cost Estimating Relationships (CERs) are based on weight, such as theships structural components. For most estimating applications, the hull andsuperstructure weight is broken down by type hull block such as decks, transverse andlongitudinal bulkheads, superstructure, double bottoms, side shells, bulwarks, etc., Each

  • 8/13/2019 task 1.33_5

    54/101

    54

    54

    block type carries a different CER, mostly for labor, since each requires a different set ofmanufacturing and assembly Processes; therefore each type has its own cost on a per tonbasis. However, structural materials also can vary from component to component, suchas high strength steel for high stress areas or armor protection, light aluminum orcomposite materials for superstructures, etc. and the CERs address these differing

    requirements.

    For estimating applications where the structural definition is less detailed, the costmodels use more global CERs based mostly on similar hull forms, such as typical mono-hulls, high-speed catamarans, etc. However, SPAR cost estimators also can apply theirown judgment factors to these CERs in order to address non-typical differences thatmight be apparent in the specific design at hand.

    The structural CERs that SPAR has developed over the years were derived from datacollected and analyzed by SPARs shipyard planning and resource management systemcalled PERCEPTION2. PERCEPTIONenables the shipyard to catalog each structural

    component by block type and the CERs are generated automatically. The system reportsaccommodate not only steel structures, but other materials as well.

    Other CERs are based not on equipment specifications or weight, but other designcharacteristics, for example:

    Deck Area: paint, deck covering, fire main, etc. Compartment Volume: cable, hangers, lighting in accommodations areas Cubic Number (LOA x Breadth x Depth): general electrical cable, general

    paint, non-accommodations lighting, selected engine room pumps &equipment, anchor & mooring gear, etc.

    Power Requirements (kW): fuel, lube oil, seawater cooling, engine roomventilation, etc. Crew size & Type: berthing, galley & mess, accommodations metal

    sheathing, doors, etc.

    Other Number Counts: life rafts, vehicle tie-downs, TEU cell-guides, etc. Production Labor Hours: production support services, technical support,

    etc.

    When used during the shipbuilding Process, PERCEPTIONprovides return cost detailsand summaries for these other CERs. The CERs have been sanitized as best that can bedone so that they are not contaminated by added costs of rework and change orders.

    SPARs production system, PERCEPTION, breaks out all rework and change order costsfrom costs regarded as normal for the assigned budget.

    PERCEPTIONalso manages purchase orders and material control functions, with reportsat all levels of detail.

    2PERCEPTIONhas been installed at a number of different shipyards, all commercial, in the U.S. andCanada since the late 1970s through to today.

  • 8/13/2019 task 1.33_5

    55/101

    55

    55

    PERCEPTION, however, is not the exclusive source of cost model CERs, among themare direct price quotations from vendors. SPARs cost libraries are maintained (expandedand updated) on a regular basis.

    3.2 Impact of Build Strategy on Cost

    The cost estimates assume that the shipyard performs the majority of work in-house.However, some trade-offs should be expected between shipyard labor and out-sourcedsubcontracting (make or buy) when the ship construction is actually planned andexecuted. These options are likely to include the manufacturing of outfit systems, butcould include outfitted hull modules as well. Such trade-offs would likely be reflected inshipyard accounting systems as lower shipyard labor hours (and costs), but highermaterial and subcontract costs. Only detail knowledge of the shipyards specific buildstrategy would permit a cost estimate to reflect changes in costs due to these

    considerations. However, in SPARs experience, such trade-offs often do notsignificantly impact the relative quality or accuracy of our cost estimates, unless theoutsourced component manufacturing and assembly can be performed by competitive,commercially-oriented vendors that can distinguish their cost benefits over equivalentinternal shipyard production costs including the added costs for transporting componentsfrom the vendor site to the shipyard.

    A specific exception to this is the cost estimate for non-recurring design and engineering,which can be estimated as though it was out-sourced by smaller shipbuilders. For suchcircumstances these costs may be higher, but they also may well result in lowerproduction costs. The cost models provided options for alternative engineering solutions.

    The cost estimates assume that the construction will be performed using hull blockconstruction techniques. The estimate for the first hull assumes adequate design,planning and production engineering has been provided for some outfitting of hull blocksprior to erection, particularly with regard to major piping systems. Other equipment andmulti-systems outfit modules may be included in the lead ship building plan, but it isassumed to be not extensive for the lead ship; therefore, any cost benefits potential fromthese construction methods have minimal impact upon the cost estimates. Someshipyards have a high pre-outfitting goal for the first ship, but this is a real challenge andis not always achieved. Variations from this build strategy can be reflected by modifyingthe cost model productivity factors.

    For follow ships of a series, more extensive applications of outfitted hull blocks andequipment/systems modules are assumed to be included in the build strategy. Costsavings from such improving production methods are reflected in the application oflearning curves as discussed in Section 6.0, Follow Ship Cost Estimate.

    Finally, how a contract is structured for cash flow is very relevant to ship building cost.Contract payment schedules that do not support modern manufacturing cost savings

  • 8/13/2019 task 1.33_5

    56/101

    56

    56

    methods can lead to less productive build strategies. For example, requiring a milestonepayment based upon completion of hull blocks erected may force the shipyard tominimize cost savings from on-block outfit as a sacrifice to expedite the schedule forerection work and ensuring an earlier milestone payment.

    3.2.1 Modern Shipbuilding Build Strategy

    Shipyards around the world generally fall into several categories from world class to notso world class. World-class shipyards can be characterized as technologicallyprogressive, not only in the ship types they build, but more in the way they build ships,both commercial and naval (combatants & auxiliaries). Other yards not so characterizedmore typically build ships like they always have using legacy methods that by todaysstandards are much less efficient. Unless they have established a niche market thatfeatures relatively low tech ship products, their operations are less competitive in bothcost and time to build the more complex ship designs.

    World-class shipyards have been exploiting build strategies that have enabled them todramatically lower their costs, improve construction quality and extend ship designfeatures and capabilities. These strategies fall into the following general categories:

    1. Improved manufacturing & assembly methodsa. Pre-outfitted hull block constructionb. Outfitted equipment & systems modulesc. Group technology manufacturing methodsd. Improved assembly technologiese. Cross-trade work agreements

    f. Outsourcing specialty workg. Reduced non-value added labor costsh. Minimized/elimination of expensive stagingi. Minimized worker walking timej. Increased under-cover assembly operations

    2. Improved procurement & material controla. Near-in-time procurement schedulingb. Improved vendor relations & pricing agreementsc. Material work order kittingd. Standardized material parts & components

    e. Material buffer storage nearer to worksites

    3. Improved business processesa. Streamlined & integrated departmental business process managementb. Improved labor/material/subcontractor planning & schedulingc. Timely & accurate progress, cost & earned value reportingd. Improved cost estimating & faster RFP responsese. Improved progress & cost management metrics

  • 8/13/2019 task 1.33_5

    57/101

  • 8/13/2019 task 1.33_5

    58/101

    58

    58

    This build strategy culminates in exploiting the cost-savings benefits of modularconstruction techniques. Modules can be developed in a wide variety of ways: outfit andequipment modules, hull assembly blocks, and outfitted hull blocks.

    Outfit and equipment systems can be designed and assembled as a completemodule that then can be installed either on hull blocks prior to erection orinstalled later on-board. Such modules are called outfit-on-units.

    Hull block assembly is the process of building the hull structure in modularform of building blocks. This assembly method replaces older methods thatbuilt structures on the building ways from the inside out (traditional stickbuilding). Hull block construction saves time because it can be performedmuch more easily and with less expensive material handling and workeraccess costs.

    By outfitting hull block assemblies, productivity can be enhanced even further.On-block work can be 30%-50% less expensive in labor costs than equivalent

    work done on-board ship.

    3.2.3 Outfitted Hull Block Construction

    Hull block construction is the method of building the ship structure by erectablefabricated and assembled structural components (blocks). Pre-outfitted hull blockconstruction is the process of adding outfit materials (equipment and/or ship systems) tothe hull blocks prior to erection. Pre-outfitting hull blocks can significantly reduce

    assembly costs when compared to performing the same assembly work on-board the ship.

    Figure 3.2-1: Sample Hull Equipment Block

  • 8/13/2019 task 1.33_5

    59/101

    59

    59

    A successful hull block construction program can be made even more successful with theapplication of group technology manufacturing, zone outfit work organization, and theprinciples of lean design.

    Group technology manufacturing is the organizing of similar work so that it canbe processed together to gain the cost savings potential of batch manufacturing.Group technology manufacturing can be applied not only to parts fabrication, butalso to assembly and installation processes.

    Zone outfitting, a variation of group technology manufacturing, is the method oforganizing work within specific physical spaces by work type to achieve the costand time savings potential. An example of zone outfit work organization is theinstallation of piping systems in a specified area prior to the installation of otheroutfit systems (such as electrical trays, HVAC duct, etc.) that might conflict or

    interfere with overall work progress.

    Hull block construction is typically planned and managed not only by individualblocks, but also by the manufacturing processes of the interim stages ofconstruction: steel preparation (wheelabrate, prime, trim), fabrication (NC parts,end cuts, bending, rolling, etc.), sub-assembly, assembly, erection, and on-shipweld-out. Obviously different blocks will have a different costs depending uponthe manufacturing processes required for its fabrication and construction.

    Blocks generally can be categorized by block type. This means blocks that gothrough the same set of manufacturing and assembly processes can be identified

    as belonging to the same block type. Each block type will have a different unitcost compared to other block types. Flat panels, for example, can be processed onautomated panel lines and are less expensive ton for ton than 3D curved blocksthat require more time and effort and cannot be manufactured using the samedegree of automation.

    A ship is composed of a variety of blocks and block types, depending upon thesize and type of ship being built. A ship having little hull shape should beexpected to cost less per ton than a ship of the same size with considerable hullshape. Flat-sided parallel mid-bodies are easier to build than ships with finer hullforms and shape.

    Lean Ship Design is a design philosophy that focuses on making the ship designas simple and as easy to build without compromising upon design function andpossibly enhancing design performance. Lean design, as espoused by many otherindustries, attempts to eliminate as many different components, parts, andcomplexities as can be done. Lean design also attempts to capitalize on the use ofrepeatable interim products, within any ship design, and reduce costs accordingly.

  • 8/13/2019 task 1.33_5

    60/101

    60

    60

    3.2.4 Extended Shipbuilding Modules

    Shipbuilding modules may take on almost any number of types and extents. Hull blocksare modules that, as described above, benefit from reduced costs compared to older stick-built methods of assembly at the building ways. Outfitting these hull blocks offers

    further cost savings by allowing outfitting to occur at earlier stages of construction wherework can be focused on a platen rather than occurring later on board.

    Other types of modules carry the concept of early stage construction cost savings evenfurther. On unit outfit may be as small as a single piece of equipment mounted on itsfoundation and ready to install on block or on board. Or, on unit outfit can be a complexassembly of equipment, piping, electrical and other systems all pre-mounted on a supportstructure.

    The following are good candidates for modular construction:1. Propulsion plant & auxiliary systems modules

    2. Electric generator modules3. Accommodations modules4. Masts & stacks5. Deck & cargo system modules6. Hull blocks

    Modules can cover a very wide spectrum of applications, sizes, and systems. Modulescan include one or more pieces of equipment and machinery with foundations and othersupport structures; they may include sections of multiple ship systems such as piping,ventilation duct, local electrical systems, etc. Modules may be installed on othermodules, on hull blocks and on-board.

    However, modularizing an engine room by simply cutting it into modules is not the rightsolution. This approach typically generates additional pipe, structures and equipment,plus additional weight, which at least partially offsets the benefits gained bymodularizing.4

    The following figures illustrate examples where equipment and system modules havebeen successfully developed by various European shipbuilders (for example, ScheldeNaval Shipbuilding, Blohm & Voss Gmbh, Abeking & Rasmussen). These samples wereobtained from the Ship Design and Research Centre S.A., Gdansk, Poland,Modularization in Ship Equipment, Intermodul s/03/G,

    http://www.cto.gda.pl/index.php?id=232&L=1

    Modularization is being applied almost universally throughout the European shipbuildingindustry. Thyssen Nordseewrke Shipyard, for example, has made it possible to produce

    4Markku Kanerva, Modern Competitive Ship Construction, Deltamarin LTD, SOBENA 2004, Rio deJaneiro, Brazil

  • 8/13/2019 task 1.33_5

    61/101

    an almost entirely equippedinstall it in the ship hull. It iproducers outside the shipyaroom, are purchased ready-m

    This expands the level of cothe latter make more and moshipbuilder with reduced costo specialized module manufbusiness and is more likely ttheir costs and advance their

    Figure 3.

    ngine room in the assembly halls and then trancommon practice that modules are made by spd. Some modules, like fuel booster blocks forade for installation at the shipyard.

    peration between the shipyard and the cooperate ship parts. These relationships no doubt bens and reduced product delivery schedules. By

    acturers, the supply chain obtains more opportuinvest in improving their own levels of produc

    technologies for better product quality and capa

    -2: Sample Equipment & Outfit Modules

    61

    61

    port andcialized

    he engine

    ing firms asfit theutsourcingities for

    tivity, lowerbility.

  • 8/13/2019 task 1.33_5

    62/101

    Figure 3.2-

    New Construction Benefits

    1. Shorten ship construc2. Shortened time saves3. Mass production of

    efficiencies gained iftypes and classes.

    4. Modules can be builtintegrated shipyard thbusiness. This can lemore development re

    5. Lead ship costs shoul

    of other systems subj6. Lower cost means m7. Eventually, standardi

    and engineering.

    3: Sample Machinery Equipment Modules

    from Extended Modularization:

    tion time with modules built in parallel.cost with lower overhead, less impact of inflati

    odules saves cost from learning effects. Additimodules are standardized and applicable to mul

    by a competitive industry that does not rely onat is less productive more opportunities for sad to greater participation of supplier base thatsponsibilities to improve quality and reduce cosd be lower because modular approach is less int

    ct to change orders.re products can be built for available funds.

    zed modules can lead to lower costs for non-rec

    62

    62

    nonaltiple ship

    he fullyaller

    an assumes further.er-dependent

    rring design

  • 8/13/2019 task 1.33_5

    63/101

    63

    63

    Ship Maintenance Benefits from Extended Modularization

    1. Modules can be easily removed from onboard and repaired in shop2. Maintenance of modules on-shore less costly than on-board

    3. Faster turn-around time to repair/replace modules4. Even faster turn-around with Swap-out/Swap-in scenario of selected modules5. Increase fleet operation time6. Decrease time in shipyard for repairs and overahauls

    Other industries have long exploited the benefits of modular construction:1. Aircraft F4 began modularization; F35 extensive use of modules2. Cars parts and components, often interchangeable between different models3. Home appliances parts and components

    There are precautions that must be taken in order to minimize failures in applying

    modular construction techniques:1. Requires better than normal engineering2. Requires better than normal quality assurance3. Requires higher level of design standards to minimize interferences and

    disconnects.

    3.3 Generic Shipyard Costs

    The underlying cost estimating relationships (CERs) used in the Cost Model apply to ageneric mid-size commercial U.S. shipyard having reasonably productive manufacturing

    and assembly facilities, and technical and management competence. The CERs are basedupon a comprehensive analysis of U.S. shipbuilding costs gathered from SPARsworking experience with a variety of shipyards, large and small, commercial and navalcontractors. As noted earlier, the cost model outputs were adjusted as necessary to reflectcurrent shipbuilding practices and costs.

    It is assumed that the generic commercial U.S. yard extensively employs modernmethods of work organization and has competent worker and management skillscomparable with internationally competitive shipyards. The approach to ship design andconstruction is partially based on insights obtained in a comprehensive evaluation ofnorthern European shipyards.

    The generic shipyard is assumed to have the following general operating characteristics:

    Current technology CAD and resource planning and management systems. Moderate levels of pre-outfitted hull block and modular construction N/C plasma plate cutting Automated panel line Covered hull block assembly hall

  • 8/13/2019 task 1.33_5

    64/101

    64

    64

    Hull block shot blast and painting facilities Steel manufacturing capacity of approximately 20,000 MTONs (steel or

    equivalent) per annum.

    These characteristics apply generally to mid-tiered U.S. commercial shipbuilders.

    The cost estimates assume that the construction will be performed using hull blockconstruction techniques. Some outfitting of hull blocks prior to erection is expected,particularly with regard to major piping systems.

    The cost estimate assumes cost savings are obtained by painting hull blocks prior toerection, after which remaining painting (60% of the total) is performed on board.

    Other equipment and multi-systems outfit modules may be included in the building plan,but they are not expected to be exploited extensively for the lead ship.

    Learning curves are used for follow ship estimates and assume that additionalengineering will result in increasingly more outfitting of hull blocks prior to erection andmore applications of outfit modules.

    3.4 Shipyard Productivity Factors

    When estimating cost, there are a number of issues that need to be considered.

    While there is a concept of a standard cost for performing a specific element of work, theactual cost will always vary depending who, when and where the work is to be

    performed. A shipyard that has the right equipment and facilities, a skilled work force, acompetent plan and management team will almost always perform the work more quicklyand less expensively than the shipyard that is compromised in one or more of these areas.In addition, a standard cost may identify expected costs for work under normalcircumstances, but the actual cost will likely be higher if the work area is congested,confined and/or difficult to reach.

    There are other technical issues that need to be considered. Working to a poorlyengineered design will always be more costly than working to one that is well done andeasier to build. An extension to this is whether or not technical information is readilyavailable when the work is scheduled to begin. For example, if technical information is

    not available at early stages of construction, when work can be performed moreefficiently, the work will need to be scheduled later in time when efficiency is less likely,often by cost factors of 3-5 times. Such savings from early stage construction is theobjective for on-unit and on-block outfitting versus on-board outfitting when work carriesa much higher burden of lost productivity.

    Therefore, for a cost estimate to be realistic the following issues need to be consideredand their effects included:

  • 8/13/2019 task 1.33_5

    65/101

    65

    65

    1. Available & capable facilities2. Experienced & skillful work force3. Good planning & early stage outfit scheduling4. Experienced and competent management

    5. Efficient business practices6. Quality design and engineering7. Minimum change orders

    It is assumed that rework is not included in a cost estimate except as a consideration forcost risk. Owner changes can impact costs too, but they should be covered with a setaside budget or decided later as a subsequent renegotiation of the scope of work.

    All of the above issues influence the relative level of productivity for the shipbuilderworking on a given contract.

    The cost models provide for several types of productivity factors.

    1. For technical support2. For structural manufacturing and assembly work3. For outfit manufacturing and assembly work4. For material costs

    Therefore, the acquisition costs will be influenced by where the ship is to be built and tospecific contractual requirements. The cost model provides indications of cost differencesbetween shipyards of various sizes and the impact upon higher costs expected fromshipyards building naval ships.

    For the notional shipyard, each of the above productivity factors equal 1.00. For a lessproductive shipyard, the factors increase greater than 1.00. For more productiveshipyards, the factors are less than 1.00.

    As prime contractor for the U.S. Navys Product Oriented Design and Construction(PODAC) Cost Model in the late 1990s, SPAR researched relative productivities of anumber of U.S. shipyards. Its findings are summarized in Figures 3.4-1 and 3.4-2. Thestudy also compared data SPAR had obtained from various commercial shipyards (SPARshipyard clients) and from data collected from several projects involving NorthernEuropean shipyards. Additional productivity factors were compiled and reported by P.C.Koenig, H. Narita, and K. Baba for East Asia5.

    5Shipbuilding Productivity Rates of Change in East Asia, SNAME Journal of Ship Production, February2003.

  • 8/13/2019 task 1.33_5

    66/101

    66

    66

    Figure 3.4-1: Relative Productivity for Steel Fabrication & Assembly

    Figure 3.4-2: Relative Productivity for Typical Outfit Work

    Structural Work Labor Hour Factor

    (By Type Shipyard)

    5.00

    2.50

    1.701.90

    0.90 1.000.76 0.71

    -

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    Combatants

    (Very Large)

    Combatants

    (Large)

    Dual-Use

    Non-

    combatants

    (Large)

    Dual-Use

    Non-

    combatants

    (Mid-Size)

    US Modern

    Commercial

    (Large)

    US Modern

    Commercial

    (Mid-Size)

    Northern

    European

    (Large)

    Korean

    (Large)

    LaborCostFactor

    Outfit Work Labor Hour Factor

    (By Type Shipyard)

    1.00

    1.24

    1.56

    0.33

    0.20

    0.99

    0.28

    -

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    1.4

    1.6

    1.8

    US

    Commercial

    Shipyard

    General

    Productivity

    US Dual-Use

    Shipyard

    General

    Productivity

    US Naval

    Combatant

    Yard General

    Productivity

    Northern

    European

    (Large) 2002

    Japan 2002 China 2002 South Korean

    (Large) 2002

    LaborCostFactor

  • 8/13/2019 task 1.33_5

    67/101

    67

    67

    Other organizations have attempted to measure relative shipbuilding productivity usingan approach called compensated gross tons, or CGT.

    Adopted in the 1960s by the Organization for Economic Cooperation and Development

    (OECD), CGT is a normalized measure that allows the work content (per unit of volume)of different types of ships to be compared on the same basis. CGT-based calculations canbe used to make high-level cost estimates, to compare shipyard performance (eventhough they may be building different types and sizes of ships, and to set targets forshipyard performance.

    NOTE: CGT is not an exact science, and its ability to compare cost performance acrossdifferent sizes and types of ships must be regarded as very approximate. The approachconsiders all costs, labor and material lumped together.

    It should be recognized that productivity of U.S. shipyards building Navy ships has

    proved to be much more than a 37% premium over equivalent commercial practices. Themethods for developing CGT for warships is still not fully understood, while the PODACresults are based on more in-depth analysis of actual shipyard return costs.

    Figure 3.4-3 provides a spectrum of productivity factors from various studies using theCGT approach.

  • 8/13/2019 task 1.33_5

    68/101

    68

    Figure 3.4-3: Approximate Worldwide Shipbuilding Productivity Factors

    0.2042 0

    .3960

    0.1

    573 0

    .3583

    0

    .2427

    0.3

    831

    0.3

    563

    0.2

    672

    0.3

    678

    0.4

    344

    0.2

    986

    0.4

    431

    0.9

    564

    0.4

    259

    1.1

    294

    0.4

    431

    0.8

    449

    0.4

    104

    0.4

    290

    0 3 0 1 3

    -

    0.20

    0.40

    0.60

    0.80

    1.00

    1.20

    1.40

    1.60

    1.80

    SPARPro

    duc

    tiv

    ity

    Fac

    tor-

    Re

    lative

    toU

    .S.

    Mid-S

    izeC

    ommerc

    ial

    (Lower

    th

    eFac

    tor,

    the

    Grea

    ter

    the

    Pro

    duc

    tivi

    ty)

    Productivity Factors

  • 8/13/2019 task 1.33_5

    69/101

    69

    SPARs cost model also takes into account the overall size of the ship, as larger ships aretypically less expensive due to economies of scale to build on a structural cost per tonbasis than smaller ships of the same hull form and relative complexity.

    3.4.1 Extended Modularized Equipment & Outfit Option

    As discussed earlier in Section 3.3, the cost models standard CERs are based on anotional U.S. commercial shipyard (productivity factors for structural and outfit work =1.0). The notional U.S. commercial shipyard is assumed to build using conventional, butlimited pre-outfitted hull blocks and few on-unit modules. The user can adjust theseproductivity factors for a specific type yard and/or for a specific anticipated buildstrategy.Section 3.2 describes the concept of extended modularization in ship design and

    construction to equipment and outfit components promises a number of cost savingsbenefits. SPAR cost models provide the option for estimating cost savings fromimplementing extended modularization. The cost model breaks down the standard CERcosts into two categories:

    1. Labor hours that can be allocated to manufacturing and assembling modules; and2. Labor hours required to integrate the module with other ship systems and

    interfaces.

    While these cost models use the shipbuilders labor rates for the manufacturing andassembly of modules, the user most likely will specify that the production hours for this

    work be of a higher level of productivity than what the shipyard normally can beexpected to produce. For example, if the notional U.S. commercial shipbuilder has aproductivity factor of 1.0, the productivity factor for module manufacturing and assemblywork should be expected to be something less than 1.0.

    The cost models assume that productivity factors applied to the labor hours estimated forinstalling the modules are what is defined for the shipbuilder.

    The process by which the cost model separates the labor hours is based from studiesmade by a Canadian yard in the mid-1980s that experimented with various modularconstruction techniques and proved conclusively that cost saving benefits are very real.

    Depending on the type of module, its equipment and systems, the cost model estimatesthe number of hours for the module fabrication and assembly work as a percentage of thetotal conventional standard hours (% Total Modularized in Figure 3.4-56), from 20% to100%. The actual labor hours spent doing the modular fabrication and assembly work issimply the percent of the standard CER hours allocated for modules times the improved

    6The factors presented in Figure 3.4-5 are stored in the cost model Module Factors worksheet and canbe modified to suit the users own preferences.

  • 8/13/2019 task 1.33_5

    70/101

    70

    70

    productivity factor for modular work. The estimates assume that on-unit factors apply formanufacturing most modules.

    % Total Onboard On Block On Unit

    Work Type Modularized Factor Factor Factor

    Piping - OMS 85.00% 1.000 0.530 0.280HVAC - Rectangual Duct 85.00% 1.000 0.800 0.400

    HVAC - Spiral Duct 85.00% 1.000 0.650 0.325

    HVAC - Fans 85.00% 1.000 0.650 0.325

    HVAC - Air Handlers 85.00% 1.000 0.800 0.400

    HVAC - Spools 85.00% 1.000 0.650 0.325

    HVAC - Fire Dampers 85.00% 1.000 0.750 0.375

    Electric Cable (Local) 85.00% 1.000 0.500 0.200

    Auxiliaries - IMS 85.00% 1.000 0.650 0.325

    Piping - IMS 85.00% 1.000 0.800 0.400

    Cable Trays - IMS 85.00% 1.000 0.800 0.400

    Staging - IMS 85.00% 1.000 0.800 0.400

    Exhaust Casing - IMS 95.00% 1.000 0.500 0.500

    Casing Vent Trunk 95.00% 1.000 0.500 0.500

    Foundations 100.00% 1.000 0.830 0.390Seats - IMS 100.00% 1.000 0.750 0.375

    Paint - Excluding Block Paint 85.00% 1.000 0.690 0.170

    Paint - Block Paint 40.00% 1.000 0.800

    Paint - Unit Paint 20.00% 1.000 0.500

    Propulsion Machinery 90.0% 1.000 0.700

    Outfit Machinery 90.0% 1.000 0.500 0.250

    Electronics 85.00% 1.000 0.300

    Outfit Equipment 85.00% 0.300

    Armament 85.00% 0.300

    Structures 85.00% variable variable

    Cable, Machinery Spaces 80.00% 0.50

    Cable, Accommodations Spaces 80.00% 0.50

    Cable, Superstructure 80.00% 0.50

    Cable, Exterior Decks 50.00% 0.85

    Figure 3.4-5: Selected Productivity Factors Used for On-Block and On-Unit Work

    % Total Modularization = Estimated Maximum Percentage of Work that can beModularized beyond conventional methods.

    Onboard Factor = Maximum Labor Cost at Onboard Stage of Construction On Block Factor = Percentage Labor Cost for On-Block Work Relative to

    Onboard Cost

    On Unit Factor = Percentage Labor Cost for On-Unit Work Relative toOnboard Cost

  • 8/13/2019 task 1.33_5

    71/101

    71

    71

    3.5 Generic Material Costs

    Underlying generic material costs of the cost model assume commercial-gradeshipbuilding materials and management methods. Variations due to specific materials,equipment models and configurations, and vendor pricing methods should be expected.

    Foreign acquired equipment is subject to changes in exchange rates, which are oftendifferent from