Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Tamar Lake Inc. Incorporation Number IA 10501
Email: [email protected]
Web: www.tamarlake.com.au
Ross Ambrose Scott Anthony Charles Booth Errol Stewart Kevin French
Peter Thyne Ralph Norton Ted Pedley Mike Steele David Vautin
David Youngman Jack Bain Tim Dowling Tony Gray Andrew Lovitt
Bob Ruddick Alec Purves Stu Cottrell Denis Tucker Bill Woolcock
Phil Frith Craig Yates Richard Matson Marcos Ambrose Ross Peck
Robin Frith Barry Larter Martin Rees Tim Lack Peter Keam
Scott Bell
Rob Dowling
Robert Dutton
Sam Tucker
John Scott
Jim Dennis
Ian Goninin
Peter Watt
John Ferrall
John Dingemanse
Anna Lovitt Ben Lovitt Brian Faulkner Jan Pesl Joanne Larter
Nicolas d’Emden
Tamar Lake Feasibility Report Small Lake Concept
March 2020
Key Finding:
The Tamar Lake project is a transformative project that provides the
community with a substantial reduction in sediment deposits in the
Upper Reaches and protection against sea level rise in the Launceston
area, while also providing the stimulus for huge economic benefits
through greatly improved aesthetic presentation and aquatic amenity of
the Tamar.
Home Point with freshwater flowing one way downstream This is what a Tamar Lake would look like
Founding Members
Page 2 of 14 Tamar Lake Feasibility – Small lake option concept - January 2020
Introduction
After 9 years of intensive research, the private investment of over $500K into consultant studies, and
hundreds of man-days of in-kind contributions by members and consultants, the not-for-profit,
member funded Tamar Lake Inc. in February 2019 delivered to the community a complete report
into the Feasibility of the Tamar Lake project assuming a barrage forming a large freshwater lake
enclosing 70% of the Tamar Estuary was constructed near Point Rapid at the South end of Long
Reach.
While Tamar Lake Inc. still considers this the ideal solution to sediment accumulation in the Upper
Reaches with new sediment passing through the lake and into Bass Strait, feedback from the
community suggests we consider a smaller lake option with a barrage located Just South of
Freshwater Point.
The purpose of this document is to explore this small lake concept using the experience and results
obtained from all the modelling done for the large lake project.
Principal Goals of the Tamar Lake project While this transformative project will provide a range of major benefits to Northern Tasmania, the
principal goals of this study are to show the feasibility of the installation of a barrage:
1. Substantially reducing sediment deposition in the upper reaches of the Tamar –
short term goal
2. Provide protection of the low-lying areas of the greater Launceston Municipality
from sea level rise
Sediment Accumulation in the Upper Reaches 1 – cause and effect
Cause Previous studies, carried out for the local Authorities over the last 50 years, had identified that the
accumulation of silt flowing into the Tamar from the South and North Esk catchments, is deposited
in the flocculation zone between Tamar Island and Freshwater Point, then is “pumped” upstream to
the Home Reach/Yacht Basin area by the asymmetrical tidal action, particularly in the summer
periods of low flows down the South Esk.
All the studies carried out for the local Authorities have confirmed that new silt from the catchment
is entering the Tamar at the average rate of 152,000 cubic metres per annum from the North and
South Esk rivers, of which 46% deposits in the Yacht Basin and Home Reach, and the balance further
downstream.
With the entrance to the Trevallyn power station penstock situated 2 metres below the top of the
33-metre-high Trevallyn Dam, except in times of flood topping the dam the only sediment entering
the Tamar from the South Esk catchments is the fine particle silt in suspension in the fresh water,
with the coarser sand and gravels trapped behind the dam in the bottom of Trevallyn Lake.
They would cause great damage to the turbines if sand and gravel passed through the Power
Station.
1 The Upper Reaches of the Tamar include the Yacht Basin, Home Reach and the lower reaches of the North Esk river
Page 3 of 14 Tamar Lake Feasibility – Small lake option concept - January 2020
Installing a barrage (special type of weir with gates to release the water; not a dam) moves the
flocculation zone downstream the barrage and removes any asymmetrical tidal action from the
upstream zone.
Effect
The effect of the barrage will be to form a freshwater lake behind the barrage with water flowing in
one direction from the entrance to the Tamar of the Tailrace, Cataract Gorge and North Esk.
The volume of freshwater from these sources has been measured at between 1500 and 4000 GL
(1.5x109 to 4.0x109 cubic metres) per annum depending on rainfall in the catchments. This averages
out at between 50 and 126 cubic metres per second, most of which flows out through the Trevallyn
Power tailrace.
The effect of this one-way flow of the freshwater is to carry the fine particle sediment in suspension in the freshwater to the barrage and through the flood gates. Downstream the barrage the freshwater has the potential to mix with the salt laden tidal water and cause the sediment to flocculate and deposit on the bed of the river in this new flocculation zone. Studies carried out for Tamar Lake Inc, has confirmed that this change will greatly reduce the deposition of new silt in the Upper Reaches, and with the long term scouring of residual silt by flood waters, there will be a net export of silt beyond the barrage with each major flood event.
The studies have confirmed that provided the freshwater is released on an ebb tide, the flocculation zone will be moved further downstream. How much further downstream before the sediment accumulates on the floor of the estuary will depend on the strength of the freshwater flows. Tamar Lake modelling assumed a water release twice per day on each ebb tide; but there is scope to model the effect of higher rates of flow with water releases far less frequently.
The studies also show that over time, with each major flood event that tops the Trevallyn Dam, residual silt on the bed of Home Reach/Yacht Basin will be eroded downstream, never to return because of the removal of the asymmetric tide. Mechanical agitation in the form of raking could be used to increase the rate of erosion of this residual silt.
Alternative Barrage Locations
This study initially considered two locations on the Tamar River for the installation of the barrage: Point Rapid at the South end of Long Reach near Bell Bay Port, and Freshwater Point at Legana. Let’s call the lakes formed behind the barrages as the small lake and the large lake, with the freshwater storage volume behind the small lake approximately 40 GL and the large lake 450 GL.
2. Barrage near Point Rapid
Freshwater Point initially appeared to be the logical location from the point of view of the ecology
and the fact that the river is substantially fresh from Freshwater Point South to the Yacht Basin as
shown in the salinity profile in Figure 3. below, limiting ecological change.
1. Barrage near Freshwater Point
Page 4 of 14 Tamar Lake Feasibility – Small lake option concept - January 2020
3. Salinity profile of the Tamar Estuary from Low Head to the Yacht Basin
However, our barrage designers expressed concern that the geology of this area (mostly a 16m thick
mud base) and the width of the river may make the construction of the barrage gates and the ship
lock too expensive and exacerbate flood levels in Launceston.
In addition, the community at that stage were concerned that installing a barrage in this location
would simply move the sediment accumulation down river beyond the barrage (Not necessarily a
bad thing if the sediment accumulates where it does little harm and has a much larger area in which
to spread).
Small Lake Barrage – Construction considerations
For the review of the site for a barrage for the small lake option, we were fortunate to obtain, pro
bono, a brief review of the possible construction issues of this site by a well credentialed Civil
Engineer, John Bower, who is normally resident in Queensland but has strong Tasmanian
connections and has been a supporter of the Tamar Lake concept for many years.
John’s notes on the review are shown in Appendix A in which he also draws a strong parallel with the
construction challenges of the Marina Barrage in Singapore which has a similar channel width of 350
metres and depth as the Freshwater Point site shown in Figure 1. above.
An article on the construction of the Marina Barrage may be viewed at
https://www.scribd.com/doc/66032092/Marina-Barrage-Unique-3-in-1-Project.
Page 5 of 14 Tamar Lake Feasibility – Small lake option concept - January 2020
The barrage design carried out by C D M Smith for the barrage at Point Rapid to accommodate a
one in 200 year flood event of 4000 m3 /s without any detrimental flood effects in Launceston,
provided for 10 flood gates each 35m wide and 5 metres deep and a ship lock 8m wide giving a total
width of around 400 metres.
Conceptually, it would appear that this design could be accommodated across the width at the
location shown above using the same construction techniques used for the Marina Barrage, but this
will need to be confirmed by an engineering firm for construction design and the same flood
modelling as carried out for the large lake.
Sedimentation Summary
Both barrage locations will substantially reduce new sediment accumulations in the Upper Reaches,
with the accumulation zone moving to the Rosevears/Dilston area with the barrage at Freshwater
Point, and out to Bass Strait with the barrage at Point Rapid.
Full sediment transport and accumulation modelling studies will need to be carried out for the full
length of the Tamar to show the change in locations and accumulation rates compared with the
current tidal situation.
Sea Level Rise – Protection of the low-lying areas of Launceston
Both barrage locations will protect the low-lying areas of Launceston against a Sea Level rise of up to
0.8 metre.
Page 6 of 14 Tamar Lake Feasibility – Small lake option concept - January 2020
Which Location? See table 4. below for a summary of the benefits and disadvantages of each location.
It was decided that because of cost; the potential for a substantial percentage of the sediment
entering the Tamar being transported in suspension directly for deposit in Bass Strait and the
potential for flood mitigation instead of exacerbation, that Tamar Lake Inc. would carry out detailed
studies on the technical, environmental, economic and funding feasibility with the barrage at Point
Rapid.
Feature Freshwater Point location Long Reach location
Sediment
accumulation
Greatly reduced sediment accumulation
upstream in the Yacht Basin/Lower North
Esk and Home Reach areas
Sediment accumulation moved
downstream between barrage and
Whirlpool Reach; probable flocculation
and asymmetric tide in this area
Greatly reduced sediment
accumulation upstream
Very little new sediment accumulation
between barrage and Bass Strait;
elimination of flocculation and
asymmetric tide
Turbidity Low turbidity in the lake; some increased
turbidity downstream due to flocculation
Low turbidity between Yacht Basin and
Bass Strait
Navigation Assume single lock for leisure craft, 5
metres depth in lake: same as Long Reach
lake
5 metres depth from Seaport to Bass
Strait through a lock
Ecology Minimal change, particularly for migratory
birds and aquatic life
Very significant change but no listed
species threatened
Flooding This is the big question – can a barrage be
designed in this location that has no
detrimental effect on 200-year flood
events in Launceston
Flood studies show no detrimental
effect with a 45 GL buffer providing
the opportunity to reduce flood levels
Barrage cost 400 metres span, but unknown foundation
for construction, most likely a thick silt bed
800 metres span constructed on rock
foundations
Economic
benefits
Launceston would have the same aesthetic
and aquatic benefits as the larger lake, but
Tamar Valley irrigation benefits would be
reduced
Major irrigated agricultural benefits
Water
quality
This is the major benefit over Long Reach,
as the much larger rate of the lake
flushing, and shallow water depth would
limit algal bloom growth
There is seasonal potential for algal
blooms to form just upstream of the
barrage. This needs more study.
Freshwater Adequate freshwater upstream of the barrage,
but would need to be piped to the larger
irrigable areas downstream of the barrage
Almost unlimited freshwater availability
along the 60 km length of the lake, and
particularly adjacent to the Bell Bay
Industrial zone
Sea Level rise
protection
Will protect Launceston against sea level rise of
up to 0.8 metres
Will protect Launceston against sea level
rise of up to 0.8 metres
4. Table showing benefits and disadvantages of the alternative barrage locations
Page 7 of 14 Tamar Lake Feasibility – Small lake option concept - January 2020
Forecast feasibility findings for the small lake construction
With a barrage installed at the Freshwater Point location shown in Figure 1. above, a medium sized,
constant level, freshwater reservoir of approximately 45,000 ML is formed behind the barrage.
Environmental Impact
Based on the modelling carried out for the large lake option, the following benefits are expected
when a full feasibility study is carried out on the small lake option.
• Ecology
The current ecology of the area south of the Freshwater Point barrage location is principally
a freshwater ecology and with the formation of the freshwater lake, it is expected that
change in the ecology will be minimal.
• Sediment Management
With the movement of the flocculation zone to downstream the barrage in the much wider
and deeper section of the Tamar between Rosevears and the Batman Bridge, and sediment
flowing in suspension in the freshwater flowing one way through the lake, it is expected
there will be very limited new sediment deposition in the lake occupying the Upper Reaches
of the Tamar, depending on the strength of water flows from the catchment.
With limited new sediment deposition in the lake, it is expected that results will show a net
migration of the sediment load out of the lake with each significant flood flow event. This
will be particularly noticeable in the Yacht Basin/Lower North Esk/Home Reach section of
the lake.
• Water Turbidity
The current muddy water appearance in the area from the St Leonards weir on the North
Esk to Freshwater Point, including the Yacht Basin and Home Reach, will transition within 12
months into the same clear water clarity as the Trevallyn Lake.
6. Fresh, low turbidity water entering the Tamar from the Tailrace
• Water Quality – catchment sourced and normal STP discharges
The water quality in the Yacht Basin/Home Reach area will, within 12 months, be greatly
improved with pollutants flowing one way downstream from the Tailrace instead of being
“pumped” upstream into the Home Reach/Yacht basin area.
With the removal of the asymmetrical tidal action from the Upper Reaches, 80% of all new
pollutants entering the Tamar down the Tailrace, or from the sewage treatment plants at Ti
Tree bend and Riverside flow one way downstream from the Tailrace.
5. What the Tamar Lake will look like with freshwater flowing from the catchment
Page 8 of 14 Tamar Lake Feasibility – Small lake option concept - January 2020
• Water Quality – upstream the barrage As with any large body of constrained freshwater fed from a large rural and urban catchment area, Tamar Lake will have the potential for algal blooms to form on the surface of the lake during the warmer days of mid to late summer. Tamar Lake studies have shown that this has the potential to be a serious problem in the large and deep lake with the barrage at Point Rapid, but is unlikely to be a major problem in the much smaller and shallower lake with the barrage at Freshwater point.
Lake Burley Griffin in Canberra is a prominent example of this situation.
• Rice Grass Eradication
The pest rice grass, introduced in 1947, has spread in the area between Freshwater Point
and the Batman bridge to cover 415 ha of terraces and marsh islands that has reduced the
utility value and aesthetic appeal of the shoreline.
The small lake will have no effect on the rice grass, and it will continue to propagate.
Page 9 of 14 Tamar Lake Feasibility – Small lake option concept - January 2020
Technical • Flood Mitigation
The effect on flood levels in Launceston in the small lake environment are unknown at this stage with the blocking of the incoming tide having a mitigating effect but there will be no significant buffer to manage levels and the ability to design and install barrage gates that offer no additional resistance to flood flows has not yet been determined.
• Freshwater Supply With a freshwater storage volume of 450 GL in the large lake and 40 GL in the small lake, and an annual input flow of between 1500 and 4000 GL from a catchment of approximately 20% of the area of Tasmania, the large lake opens up huge opportunities for commercial development in the industrial, agricultural, residential, and tourism sectors of the economy. The small lake greatly enhances the aesthetic presentation and aquatic amenity of the Tamar for the residents and tourists visiting Launceston and could also provide an additional freshwater source for the new Tamar Irrigation scheme shown below and potentially for the planned Hydrogen production plant at Bell Bay.
7. Tamar Valley Irrigation Scheme
• Marine Navigation – transition from Low Head to Launceston
With a ship lock in the barrage, and a permanent 24/7 high water level, a minimum
navigation depth of 5m will enable private and commercial vessels, including large tour
boats, to transition the Tamar from Low Head to the Launceston Seaport at any time of the
day or night.
Page 10 of 14 Tamar Lake Feasibility – Small lake option concept - January 2020
Economic • Tourism
With clean, green, low pollution freshwater and a permanent high tide in the Upper Reaches, the potential exists for Launceston and the whole Tamar Valley to become a mecca for all forms of aquatic sports, and new tourism property developments on the banks of the reservoir. The greatly improved aesthetic presentation of Home Reach, the Yacht Basin and the North Esk can only greatly enhance the returns on the investments being made in the relocation of UTas to Inveresk, and any other new developments planned for the Launceston CBD.
• Recreational Fishing With the installation of the barrage, flathead and snapper fishing will be limited to the estuarine section of the Tamar, but the freshwater reservoir opens up opportunities for both freshwater recreational fishing and aquaculture developments.
• Economic Growth Very conservative economic studies carried out for Tamar Lake forecast an additional growth in Gross Regional Product of 10% in the 15 years post barrage construction due to the formation of Tamar Lake. This looked at only the growth in the tourism and agriculture sectors, but, in the case of the large lake, it is also expected that the industrial and commercial sectors, particularly in the Bell Bay/George Town area, will also gain a large economic benefit.
Funding
Value capture funding methods Acknowledging the significant level of funding required to implement the project, Tamar Lake Inc. commissioned AECOM in February 2017 to estimate the potential for value capture funding methods to contribute to the funding of the Tamar Lake project.
Value capture funding methods are a relatively new concept in Australia. Traditional approaches to funding methods for new or improved infrastructure have used funds entirely sourced out of general taxation revenue, meaning all taxpayers share the burden of paying for the infrastructure despite the fact that many of them will not use or directly benefit.
By identifying and quantifying the value created from the development of the new infrastructure, and connecting it with the costs of the infrastructure, value capture mechanisms can help deliver projects through a fairer business model.
• AECOM conclusions
The report prepared for Tamar Lake Inc. by AECOM concluded:
Given the current indicated construction cost of $320 million, the benefits to property values alone from the project greatly exceed its costs:
• The uplift in median residential property values in Launceston, within 1km of the Tamar Lake shoreline, following construction of the Project and stabilisation of values is conservatively estimated to be $1 billion.
• The uplift in median unimproved commercial land values in the Launceston CBD within 500m of the riverfront following construction of the Project and stabilisation of values is estimated to be $434m.
AECOM identified the following potential value capture funding methodologies to be applied to the Tamar Lake project:
• Selling development rights and / or density above existing zoning controls.
• Sale of government-owned land that is enhanced or made developable by the project.
Page 11 of 14 Tamar Lake Feasibility – Small lake option concept - January 2020
• Captured through public taxation system such as land tax, council rates and stamp duty, and possibly captured through sharing value uplift with surrounding landowners.
The encouraging outputs from this AECOM study support further work being undertaken into the application of value capture funding to the Tamar Lake project. Tamar Lake Inc. would recommend this work be included in the broader socio-economic study that would be initiated as part of preparation of formal business case for the development of the Tamar Lake.
The Choices
The abandonment by the Launceston City Council of the raking program in the Yacht Basin/Lower
North Esk/Home Reach segments of the river, and the acknowledgment by the Council that
increased flow rates down the gorge does little to mobilise sediment deposits out of the Home
Reach/Yacht Basin area, has left the Council without a solution to the continued build-up of
sediment deposits in this area which have detrimental effects on flood levels and navigation in the
Upper Reaches.
While it is acknowledged that the Council are seeking specialist opinions on how to manage the
continued build-ups of sediments in this area, Tamar Lake Inc. believes it has only two options:
• Over the next 30 years spend many millions of dollars of taxpayer revenue, without any
substantial direct boost to the economy, on a dredging program to maintain navigation
depth and maintain the current level of flood protection.
• Implement the Tamar Lake plan in the short term for an investment of up to $500 million (of
which 30 to 50 % could be privately funded), and provide the foundation for a huge short
and long term boost to the economy in the tourism, agriculture, industrial and commercial
sectors, with the formation of a freshwater, low pollution, low turbidity lake, with limited
new silt deposition and the gradual erosion of residual silt over time.
Conclusion
In producing this report, the executive and members of Tamar Lake Inc. have invested their time and
cash over 7 years, with no expectation of any return, in pursuit of a solution to what has been
acknowledged by almost all residents of Launceston as a totally unacceptable situation.
This situation has been brought about by the initial siting of Launceston at the confluence of the
Tamar and South and North Esk rivers; poor land management since European settlement by
farmers and loggers in the catchments; watercourse width and depth reductions both by natural
sediment infilling and the community’s infilling and bank modification of areas around Home Point
and Royal Park; and to an antiquated sewage treatment and stormwater system that has not kept up
to modern standards for effluent discharge and urban runoff.
With the release of this report, the altruistic investment by the members of Tamar Lake Inc. has
been completed. If a State Authority is nominated or formed to manage all aspects of the Tamar
Valley health and amenity, and funding is provided to that Authority to carry out the planning and
approvals process, all the reports commissioned by Tamar Lake Inc. will be made available to the
Authority at no cost to that body.
With the environmental, lifestyle and economic benefits that would accrue to the Northern
Tasmania community with the implementation of the Tamar Lake plan, there is no reason why all
three major parties in the State Parliament would not support a proposal to fund the planning and
approvals stage.
Page 12 of 14 Tamar Lake Feasibility – Small lake option concept - January 2020
What is Tamar Lake’s Position going forward?
Having completed these feasibility studies, the members of Tamar Lake Inc., while convinced that
this is the right solution for Northern Tasmania, would not expect unqualified support from the
community until the full business case and Environmental Impact Statement (EIS) have been
prepared and presented to stakeholders and the community.
Page 13 of 14 Tamar Lake Feasibility – Small lake option concept - January 2020
Appendix A In your email of the 28th you mentioned that “The key issue is whether a barrage can be economically constructed at Freshwater Point that has no detrimental effect on flood levels in Launceston”. In your most recent Overview you have stated that “our barrage designers expressed concern that the geology of this area (mostly a 16m thick mud base) and the width of the river may make the construction of the barrage gates and the ship lock too expensive and exacerbate flood levels in Launceston”. In Figure 1 of the Overview, you have shown a barrage location at what looks like “Dog Point” on the River Tamar chart – see extract below. The width at this location scales at about 380 m and the maximum depth is in the order of about 10-12 m below chart datum which is stated as being approximately the level of the lowest astronomical tide (LAT). Based on the “Preliminary Estimates of Spillway Widths” contained in the BMT WBM report Tamar Lake Preliminary Technical Assessment, dated February 2012, the gates of the barrage would need to extend most if not all of the width of the river at this location. Hence, I assume the concern about the width of the river mentioned above.
Figure 1 - Extract Hydrographic Chart Aus 168 River Tamar
My view is that the barrage would need to be designed to pass the required flood event (200-year ARI?). I suspect that this criterion is likely to control the overall geometry and gate opening sizes (both height and width) of gates etc. Whilst this may not be that difficult to achieve for the full width of the barrage, since the BMT WBM spillway width of 300 m (Table 5-1 of their Feb. 2012 report) would fit at this location, the barrage would need to be constructed in stages which quite possibly would represent the greatest risk.
Page 14 of 14 Tamar Lake Feasibility – Small lake option concept - January 2020
I believe the Marina Barrage in Singapore offers some quite good parallels. I have sent through a separate copy of an article from Structural Engineering International which provides some useful information. Similarities between Freshwater Point and Marina Barrage are:
• Similar overall width – Marina Barrage 350 m with 9 x 30 m wide gates (no lock).
• Similar tidal range although Launceston is about a 4 m variation compared with 3 m at Singapore.
• Possible broadly similar soft ground conditions – in Singapore the whole structure sits on bored piers down to a depth of 74 m. Hopefully a Freshwater Point location would not need piles this deep.
• Constructed in two stages as detailed in the Structural Engineering International article. I suspect any meaningful assessment of a Freshwater Point location would need to consider construction staging. This might mean that the overall width of the structure needs to increase from what is possible at the narrowest location. Assuming two stages I suspect the total construction period would be 2-3 years, so the risk of a major flood during this period would not be insignificant. Figure 2 shows a highly idealised concept as to how staging might be possible. This would involve moving the barrage slightly further upstream from the minimum width at Dog Point. This might involve building cofferdams similar to Singapore and then determining the width and depth of channel required to pass the required flood flow past this with the required channel maintained by dredging during the construction period. Stage 2 would be a mirror of this with likely associated dredging as well. Moving the location slightly also provides more “space” for the lock. This is very conceptual and should not be taken too literally but I have prepared this to simply demonstrate a concept.
Figure 2 - Possible Stage 1 Construction Concept Any hydraulic modelling, in my opinion, would need to consider:
i. Capacity to pass required flood event with final configuration of the barrage + lock. ii. Capacity to pass required flood event(s) during construction staging with associated temporary channel dredging to maintain required waterway area and depth.
Prepared by: John Bower Brisbane 2 January 2020