Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
R E T H I N K I N G I - 9 4
MnPASS Connections CORSIM Analysis
16
Appendix T16 | 1
APPENDIX T16 - MNPASS CONNECTIONS
CORISM ANALYSIS
Introduction
Since 2016, MnDOT has been working with neighborhoods, community groups, district councils, local
governments and others interested in the future of I-94 between St. Paul and Minneapolis in an effort to
plan for transportation changes on and along the freeway. This effort is known as Rethinking I-94. The
work described in this technical memorandum was conducted as part of the initial phase of Rethinking
I-94 conducted between 2016 and 2018.
This memorandum documents an evaluation of potential MnPASS connections to downtown
Minneapolis and Saint Paul using CORSIM. As documented in the Rethinking I-94: MnPASS Connections
Concepts – Local System Considerations Concept Development and Analysis Technical Memorandum,
Option M1 (Minneapolis) and Options S1 and S5 (St. Paul) were determined to be the most promising
and were recommended to be carried forward for consideration as the study progresses into the
environmental phase. Options M1 and S1 were analyzed in more detail to better understand how the
MnPASS termini will impact I-94. This process is preliminary and will require additional analysis as the
study moves forward into the environmental phase.
A separate analysis using a Dynamic Traffic Assignment (DTA) modeling approach was also conducted
(Appendix T19). Results of these two efforts should be considered together as part of the next phase.
No Build Conditions
No build conditions were analyzed to establish a baseline to compare the impacts associated with the
addition of a MnPASS lane. No Build calibrated CORSIM Version 6.3 models used for the Spot Mobility
analysis were used as a base for this analysis. The westbound model limits extend from Snelling Avenue
to Broadway Avenue and include the I-35W Commons area. The AM (5:00 to 11:00 a.m.) and PM (1:00
to 7:00 p.m.) peak periods were analyzed. The eastbound model limits extend from Snelling Avenue to
Highway 61 and include the I-35E Commons area. The PM (2:00 to7:00 p.m.) peak period was analyzed.
The modeling limits and times were selected to capture locations and time periods that experience
reoccurring congestion.
CORSIM model outputs include VHT, VMT, and average speed on I-94. To make an accurate comparison
between existing no build conditions and MnPASS conditions, the VHT and VMT for trips that are
attracted to I-94 due to the addition of the MnPASS lane have been estimated using the Twin Cities
Regional Travel Demand Model. The VHT for the attracted trips was represented by multiplying the
number of trips by the average travel time for each trip on I-94. This assumes that the travel time for the
trips that would be attracted to I-94 under the MnPASS scenario is similar to the existing travel time on
I-94. The VMT for the additional trips was represented by multiplying the number of trips by the length
Appendix T16 | 2
that each trip is on I-94. The net change in the off-system VHT and VMT was added to the existing VMT
and VHT to make an accurate comparison.
WESTBOUND I-94 (SNELLING AVENUE TO BROADWAY AVENUE)
Table 1 summarizes the VHT and VMT for westbound I-94 between Snelling Avenue and Broadway
Avenue for the AM (5:00 to 11:00 a.m.) and PM (1:00 to 7:00 p.m.) peak periods. It also includes the
assumed off-system VHT and VMT. Figures 1 and 2 illustrate the average speed on westbound I-94
during the AM and PM peak periods.
TABLE 1 – NO BUILD CONDITIONS – WESTBOUND I -94 PEAK PERIOD VHT AND VMT SUMMARY
Scenario VHT VMT
AM
Peak Period
PM
Peak Period
AM
Peak Period
PM
Peak Period
No Build Conditions
(Modeled)
6,075 8,425 260,500 284,500
Assumed Off-System 275 575 12,000 19,500
Total 6,350 9,000 272,500 304,000
Appendix T16 | 3
F IGURE 1 – NO BUILD CONDITIONS – WESTBOUND I -94 AVERAGE S PEED (AM PEAK PERIOD)
Results from the analysis indicate poor operations at the following locations:
Congestion develops at the I-94 Tunnel and extends through the I-35W Commons (1-3 Hours)
Congestion develops at the weave section between Cretin Avenue and TH 280 and extends
through Snelling Avenue (2-3 Hours)
Appendix T16 | 4
F IGURE 2 – NO BUILD CONDITIONS – WESTBOUND I -94 AVERAGE S PEED (PM PEAK PERIOD)
Results from the analysis indicate poor operations at the following locations:
Congestion develops at the I-94 Tunnel and extends through the I-35W Commons to Huron
Boulevard (3-5 Hours)
Congestion develops at the weave section between Cretin Avenue and TH 280 and extends to
east of Cretin Avenue (1-3 Hours)
EASTBOUND I-94 (SNELLING AVENUE TO HIGHWAY 61)
Table 3 summarizes the VHT and VMT for eastbound I-94 between Snelling Avenue and Highway 61 for
the PM (2:00 to 7:00 p.m.) peak period. It also includes the assumed off-system VHT and VMT. Figure 3
illustrates the average speed on eastbound I-94 during the p.m. peak period.
Appendix T16 | 5
TABLE 3 – NO BUILD CONDITIONS – EASTBOUND I -94 PM PEAK PERIOD VHT AND VMT SUMMARY
Scenario VHT VMT
PM
Peak Period
PM
Peak Period
No Build Conditions (Modeled) 6,025 274,500
Assumed Off-System 250 11,500
Total 6,275 286,000
F IGURE 3 – NO BUILD CONDITIONS – EAST BOUND I -94 AVERAGE S PEED (PM PEAK PERIOD)
Results from the analysis indicate poor operations at the following locations:
Congestion develops at TH 52 and extends through the I-35E Commons to Lexington Avenue
(1-4 Hours)
Appendix T16 | 6
Build MnPASS Conditions
The Twin Cities Regional Travel Demand Model was used to develop a traffic volume set with an
assumed MnPASS lane between Minneapolis and St. Paul. Table 4 and Table 5 show the increase in
daily, a.m. peak hour, and p.m. peak hour traffic volumes for westbound and eastbound I-94 within the
modeling limits. The max target volume for the MnPASS lane was 1,465 vehicles per hour (vph) in the
westbound direction and 1,385 vph in the eastbound direction.
TABLE 4 – WESTBOUND I -94 – MODELED INCREASE IN TRAFFIC VOLUMES WITH ADDED MNPASS L ANE
I-94 Segment Daily Delta AM Peak Hour
Delta
PM Peak Hour
Delta
5th Street/10th Street to TH 280 6,650 555 635
Huron Boulevard to Riverside/25th Avenue 6,750 565 635
Riverside/25th Avenue to Cedar Avenue 6,750 555 640
Cedar Avenue to 7th Street 6,650 550 635
7th Street to I-35W South 3,000 270 435
Appendix T16 | 7
TABLE 5 – EASTBOUND I -94 – MODELED INCREASE IN TRAFFIC VOLUMES WITH ADDED MNPASS L ANE
I-94 Segment Daily Delta PM Peak Hour
Delta
Snelling Avenue to Lexington Parkway 6,400 525
Lexington Parkway to Dale Street 5,950 475
Dale Street to Marion Street/Kellogg Boulevard 5,500 440
Marion Kellogg Boulevard to 5th Street 5,250 425
5th Street to I-35E 1,575 165
WESTBOUND I-94 (SNELLING AVENUE TO BROADWAY AVENUE)
Option M1 (shown in Figure 4) assumes that the MnPASS lane will terminate at a direct connection to
Minneapolis using a new ramp to 7th Street. For this analysis, the westbound entrance ramp from
TH 280 was assumed to be on the right side of westbound I-94. Table 6 summarizes the VHT and VMT
for westbound I-94 between Snelling Avenue and Broadway Avenue. Figures 5 and 6 illustrate the
average speed on westbound I-94 during the a.m. and p.m. peak periods.
F IGURE 4 – OPT ION M1 – MNPASS RAMPS AT 6TH ST ./7 TH STREET IN MINNEAP OLIS
(PREL IMINARY CONCEPT DRAWING ONLY)
Appendix T16 | 8
TABLE 6 – OPTION M1 WESTBOUND I -94 PEAK PERIOD VHT AND VMT SUMMARY
Scenario VHT VMT
AM
Peak Period
PM
Peak Period
AM
Peak Period
PM
Peak Period
MnPASS Conditions
(Modeled)
6,300 9,625 272,500 304,000
F IGURE 5 – BUILD MNPASS CONDITIONS – WESTBOUND I -94 AVERAGE S PEED (AM PEAK PERIOD)
Appendix T16 | 9
Results from the analysis indicate poor operations at the following locations:
Congestion develops at the I-94 Tunnel and extends through the I-35W Commons to Huron
Boulevard (1-3 Hours)
Congestion develops at the weave section between Cretin Avenue and TH 280 to extends to east
of Cretin Avenue (2 Hours)
F IGURE 6 – BUILD MNPASS CONDITI ONS – WESTBOUND I -94 AVERAGE SPEED ( PM PEAK PERIOD)
Results from the analysis indicate poor operations at the following locations:
Congestion develops at the I-94 Tunnel and extends through the I-35W Commons to
Huron Boulevard (3-5 Hours)
Congestion develops at the weave section between Cretin Avenue and TH 280 (1-2 Hours)
Appendix T16 | 10
EASTBOUND I-94 (SNELLING AVENUE TO HIGHWAY 61)
Options S1 (shown in Figure 7) assumes that the MnPASS lane will terminate at a direct connection to
Saint Paul using a new ramp to 5th Street. Table 7 summarizes the VHT and VMT for eastbound I-94
between Snelling Avenue and Highway 61. Figures 8 illustrates the average speed on eastbound I-94
during the p.m. peak period.
F IGURE 7 – OPT ION S1 – MNPASS RAMPS AT 5TH ST ./6TH STREET IN SA INT PAUL (PREL IMINARY CONCEPT DRAWING ONLY)
TABLE 7 – OPTIONS S1 AND S5 EASTBOUND I -94 VHT AND VMT SUMMARY
Scenario VHT VMT
PM Peak Period PM Peak Period
MnPASS Conditions (Modeled) 6,950 286,000
Appendix T16 | 11
F IGURE 8 – BUILD MNPASS CONDITI ONS – EASTBOUND I -94 AVERAGE SPEED (PM PEAK PERIOD)
Results from the analysis indicate poor operations at the following locations:
Congestion develops at TH 52 and extends through the I-35E Commons to Lexington Avenue
(1-5 Hours)
Appendix T16 | 12
Summary and Considerations
TRAFFIC VOLUMES
The traffic volume set developed using the Twin Cities Regional Travel Demand Model indicates that the
added MnPASS lane would attract an additional 6,650 to 6,750 vehicles per day (550-640 during the
peak hours) in the westbound direction and 5,250 to 6,400 vehicles per day (425-525 during the p.m.
peak hour) in the eastbound direction between downtown Minneapolis and Saint Paul. However, these
additional trips would not all be destined for downtown Minneapolis and downtown Saint Paul.
Approximately 3,000 daily trips (270-435 during the peak hours) would be destined for west of the
downtown Minneapolis direct connection and approximately 1,575 daily trips (165 during the p.m. peak
hour) would be destined for east of the downtown Saint Paul direct connection. The assumed max
volume for the MnPASS lane was 1,465 vehicles per hour (vph) in the westbound direction and 1,385
vph in the eastbound direction.
VHT/VMT
Table 8 and Table 9 show the VHT and VMT under both no build and build MnPASS scenarios. Results of
the analysis indicate that the addition of a MnPASS lane with the M1 connection option in Minneapolis
would result in an increase of 625 VHT during the PM (2:00-7:00 p.m.) peak period and the S1
connection option in Saint Paul would result in an increase of 675 VHT during the PM peak period. This
equates to an annual increase in VHT of 162,500 in the westbound direction and 175,500 in the
westbound direction.
TABLE 8 – WESTBOUND I -94 VHT AND VMT SUMMARY
Scenario VHT VMT
AM
Peak Period
PM
Peak Period
AM
Peak Period
PM
Peak Period
No Build Conditions
(Modeled + Assumed Off-
System)
6,350 9,000 272,500 304,000
MnPASS Conditions 6,300 9,625 272,500 304,500
Net Change -50 625 No Change No Change
Appendix T16 | 13
TABLE 9 – EASTBOUND I -94 VHT AND VMT SUMMARY
Scenario VHT VMT
PM PM
No Build Conditions
(Modeled + Assumed Off-
System)
6,275 286,000
MnPASS Conditions 6,950
286,000
Net Change 675
No Change
AVERAGE SPEED
Figure 9 and Figure 10 illustrate the average speed on westbound I-94 near the downtown Minneapolis
connection during the AM and PM peak periods under no build conditions and build MnPASS conditions.
During the AM and PM peak periods, congestion improves under the build MnPASS scenario near
TH 280, but gets worse through the I-35W Commons. This is due to the increased demand in the I-35W
Commons and vehicles exiting the MnPASS lane to travel beyond the downtown connection.
Appendix T16 | 14
F IGURE 9 – WESTBOUND AVERGE SPEED COMPARISON (AM PE AK PERIOD)
F IGURE 10 – WESTBOUND AVERGE SPEED COMPA RISON (PM PEAK PERIO D)
Appendix T16 | 15
Figure 11 illustrates the average speed on eastbound I-94 near the downtown Saint Paul connection
during the PM peak period under no build conditions and build MnPASS conditions. Congestion gets
worse under the build MnPASS conditions due to increased demand through the I-35E commons and
vehicles exiting the MnPASS lane to travel beyond the downtown connection
F IGURE 11 – EASTBOUND AVERG E SPEED COMPARISON ( PM PEAK PERIOD
CONSIDERATIONS
Results of the analysis indicate that the addition of a MnPASS lane with the M1 connection option in
Minneapolis and the S1 connection option in Saint Paul will result in an increase in VHT during the p.m.
peak periods with congestion occurring for longer durations of time compared to no build conditions.
Additional analysis which includes the extension of the MnPASS lane to the add-lane at the southbound
I-35W off-ramp in the westbound direction and to I-35E in the eastbound direction should be considered
as potential mitigation for these impacts as this study moves forward into the environmental.
Prepared by: SRF Consulting Group, Inc.