Upload
mikeengineering
View
22
Download
1
Embed Size (px)
DESCRIPTION
Concrete T- beam Design Example From Nilson, Design of Concrete Structures 14th ed.
Citation preview
1Ex 5.3
Integrated Design of T-beamNilson, Darwin and Dolan
2004
T-Beam Design Floor system consists of single span T-beams 8
ft on centers supported by 12 in. masonry walls spaced at 25 ft between inside faces.
A 5 in. monolithic slab carries a uniformly distributed service load of 165 psf.
The T-beams in addition to its own weight must carry two concentrated 16,000 lb equipment loads over the stem of the T-beam 3 ft from the span centerline as shown.
Complete design of the T beams using fc = 4000 psi and bars with 60,000 psi yield stress
Description Steps in Design
Size beam for shear Calculate loads Find effective width Find As and select steel Bar cut-off Design shear steel Add cut-off shear steel
Span
Effective Span Clear span + depth not
exceeding c/c distance Beam web estimated as
12 x 24 Smaller is 26 ft
Dead Load The beam supports its own weight and that of
the slab spanning 8 ft between the beams It is easier to determine this load from:
Weight of 8ft slab section Weight of beam section below the slab. This has the
dimensions 12 x (24 5) = 12 x 19 in
2Calculation of Dead Load Weight of 8 ft section of
slab: (5/12) x 150 x 8 = 500 lb/ft
Weight of beam section (12 x 19)/144 x 150 =
237.5 lb/ft
Total dead load = 737.5 lb/ft
The book answer is 740 lb/ft since they rounded up 437.5 lb/ft to 440 lb/ft
Live Load
Live load consists of a 165 psf distributed load and two symmetric 16,000 lb equipment loads 3 ft from the center line
Pu = 1.6 x 16,000 = 25,600 lb
Calculation of wu Distributed Live Load
Intensity x tributary width 165 x 8 = 1320 lb/ft
Distributed Dead Load 737.5 lb/ft We will round up to 740
lb/ft to be consistent with book
wu = 1.2wd + 1.6wl= 1.2(740)+1.6(1320)= 3 k/ft
Shear Diagram
Sizing beam for shear
The web dimensions are sized based on shear.
Vumax = Pu + wuL/2 = 25.6 + 13(3)= 64.6k Vu@d is at distance d from the face of the
support. Book assumes d = 20 in (2 layers of steel for 24 in depth). The wall is 12 in wide, so the distance is 6 in + 20 in = 26 in
Vu@d = 64.6 3 (26/12) = 58.1 kips
Sizing beam for shear - 2
Assume Vs = 2Vc, so Vn = (Vc + 2Vc) Solve for bwd
3Vc = 6fcbwd = 58.1 kips bwd = 58.1/(6 x 0.75)4000 = 204 in2
Select bw = 12 in. and d = 18 in. Overall depth is 18 + 4 = 22 in. < 24 in. Assumed dead load is not revised
3Design for Flexure
Calculate effective width, bE Calculate Mu Calculate As Select steel
Calculate Effective Width
bE is least of: L/4 26/4 = 6.5 ft = 78 in 16hf + bw 16 x 5 + 12 = 92 in centerline spacing 8 ft = 96 in
Least is 78 in
Calculate Mu Simply supported beam with uniformly
distributed load (3 k/ft) and two symmetric point loads (25.6k) located 10 ft from the supports
Mu = wuL2/8 + Pu x 10 ft= 3(262)/8 + 25.6(10)= 253.5 + 256 = 509.5 ft k say 510 k-ft
Calculate As Since the flange is 78 in. wide and 5 in.
deep, it is unlikely to be a true T For T-beams, the approximate lever arm is
taken as 0.95d = 0.95(18) = 17.1 in (see MacGregor & Wight 2005)
As = Mu/fy x lever arm = 510 x 12/(0.9)(60)(17.1) = 6.62 in2
This is close to book value of 6.60 in2
Select Steel
Four # 9 (As = 4 in2) and 4 # 8 (3.16 in2) to provide a total area of 7.16 in2 (the book value is 7.14 in2)
Steel will be arranged in two rows, each row containing 2 #9s and 2 #8s.
Bar Cut-off
At the simple support, the moment is zero so the steel can be reduced
ACI requires at least 1/3rd of the steel to continue over the supports.
In this example, 50% (the entire top row) is cut off
4Detailing Location of Cut-Off
Find capacity of beam with the bottom steel layer (2 # 9s and 2 # 8s)
As = 7.16/2 = 3.58 in2 (book uses 3.57 in2) d = h - 1.5 in cover - 3/8 in cg of #9 & 8 bars
= 22 1.5 0.375 (1.128+1)/2= 19.06 in.
Residual Moment Capacity
inbf
fAa
ec
ys 81.078485.0
6058.385.0 '
===
kftadfAM ysn === 300121)
281.006.19(6058.390.0)
2(
Mn = 300/ = 333 ft-k
Map Location of Cut-off
Let x = distance from support where Mu = 300 ft-k (residual capacity)
Equate residual capacity = Rx wux2/2 64.6x 3x2/2 = 300
x = 5.3 ft from the support
Cut-off
Extend by larger of d or 12db d is 18 in. or 1.5 ft 12db = 12 x (1.128) = 13.54 in Here we are using the larger #9 bar since the
entire row is stopped. Otherwise use the diameter of the bar that is cutoff
Larger is 1.5 ft
Development Length
Because of the large concentrated load, check development length from that location
Check if simplified form can be used Clear cover > db, (1.5 + 0.375)/1.128 = 1.66db Clear spacing > db
[12 2 x (1.5+0.38+1.13(#9 bar) +1.0 (#8 bar)]3 = 1.33 in
minimum stirrups (will be provided) OK
5Calculate ld
ftorindf
fb
c
etyd 42.453400020
13.1000,6020
==
= l
Comment
Bars must be continued 3 + 4.42 = 7.42 ft past the mid-span point
The theoretical cutoff point is 5.3 ft. The bars must be extended by 1.5 ft so that the actual cutoff point is 5.3 -1.5 = 3.8 ft from the support.
Bottom layer
Extend 3 in. from the end of the beam
Positive Moment Anchorage
Since the positive moment rises more rapidly than the linear variation in development length an additional check regarding bar size is needed
Positive Moment Check
OKinVMl au
nd 8336.64
123333.13.1 =+=+ l 8.503.2775.0 6.58 ==sV 7.48.50 )18)(60)(22.0( === syvV dfAs Shear values from loadsBook
calculates first spacing at the maximum shear not at d
9 in
Least of
d/2
24 in
Avfy/50bw8.8726.840.68 ft
No more calculations needed since required spacing exceeds ACI maximum of 9 in
12.6418.834.610 ft
6.8334.846.66 ft
.5.5542.852.64 ft
58.6@ d
d = 18 + 6 = 24 in
CommentsMaximum spacing,
in.
Spacing, #3 U in
Vs = Vu/-VcVuSection
Shear Design
6Assigned Spacing
45 in5 spaces @ 9 in
9 ft 7 in from face of support
115 in Total
40 in8 spaces @ 5 in
This is the book spacing. We could have used a different spacing
28 in7 spaces @ 4 in
At s/2 rounded down2 in1 space @ 2 in
CommentsDistance from left support
Spacing
Extra Shear at Cut-Off
Since the shear at the cut-off location 51.7k (4.3 ft from support center is 64.6 3 x 4.3 = 51.7) > 3/4Vn (0.75 x 56.1 = 42) [ for s=5, Vs = 47.5; Vc = 27.3], additional stirrups are needed over a distance d (13.5 in. from the end of the discontinued steel)
Extra Steel Details
Spacing = d/8b = 18/(8 x ) = 4.5 in. Required Av = 60bws/fy
= 60 x 12 x 4.5/60000 = 0.054 in2
Provide 4#3 U, Av =0.22 in2 OK
Reinforcement Detail
Summary
The top layer is cutoff 3.8 ft or 45.6 in. from the center line of the support. The drawing shows 3 ft 4 in or 40 in from the face of the support
Additional 4 No 3 U stirrups are provided over the 3/4d or 13.5 in from the ends of the discontinued bars
Comment
It would have been easier to continue the bars. However, if there were a number of repetitions, it would be worthwhile to cut the bars off
There are design aids that simplify the cut-off calculations, e.g. MacGregor and Wight