Magnificent Seven Final demonstration 16.3.2005. T-76.115 Project Review. Agenda. Product presentation (5 min) Overview Customer benefits Demo (20 min) Project evaluation (10 min) Project planning Implementation 1 Implementation 2 Finalization & Delivery Summary Future work - PowerPoint PPT Presentation
Citation preview
T-76.115 Project Review
Magnificent SevenFinal demonstration
16.3.2005
2
T-76.115 Project ReviewT-76.115 Project Review
Agenda
Product presentation (5 min) Overview Customer benefits
Demo (20 min) Project evaluation (10 min)
Project planning Implementation 1 Implementation 2 Finalization & Delivery Summary Future work
Discussion and questions (5 min)
3
T-76.115 Project ReviewT-76.115 Project Review
Product presentation
4
T-76.115 Project ReviewT-76.115 Project Review
Product presentationOverview
IRMii is an information resource management software, which can be used to manage any type of resources.
Based on an old tool (IRM). Essentially made for Nokia Networks to manage computer-related resources.
Interface between customers-lab personnel. Reporting tool of resource availability and other related information. Resource tracking
IRMii
Customer
Administrator
HTTP
5
T-76.115 Project ReviewT-76.115 Project Review
Product presentationBenefits
Good control over resource usage Good customer-administrator interaction Any resources can be managed Easy to learn Easy to use Integrated into Nokia intranet
Uses Nokia LDAP Nokia look&feel
Implementation Modular Easy to maintain Easy to develop further
Extended accessibility for customers myirm myprogramme Easy to follow what is happening
6
T-76.115 Project ReviewT-76.115 Project Review
Demonstration
20 min
7
T-76.115 Project ReviewT-76.115 Project Review
Project evaluation
8
T-76.115 Project ReviewT-76.115 Project Review
Project evaluationProject planning
First meetings with the customer to discuss the project domain. Setup of infrastructure
Development platforms Documentation system Et cetera
Documented work practices Deliverables
Project plan Requirements document Use cases
Problems Unbalanced working hours Slow start with PEAR learning Requirements not studied enough Installation of old IRM
9
T-76.115 Project ReviewT-76.115 Project Review
Project evaluationImplementation1
System architectural work done. Minor testing done. Deliverables
Technical specification Test plan and QA plan Demonstration version of IRMii
Problems Requirements changing. Everyone still not understanding the system. GUI specifications not done. Installation of IRM
10
T-76.115 Project ReviewT-76.115 Project Review
Project evaluationImplementation2
Most of implementation done. Extraordinary work done despite materialized risks and problems. Testing Deliverables
Test cases Test log Test report Peer test plan Database migration plan User’s and administrator’s guide First version of IRMii
Problems Lack of motivation Slow progress Hour usage
11
T-76.115 Project ReviewT-76.115 Project Review
Project evaluationFinalization & Delivery
Finalization of system Testing and bug fixing Peer-testing Deliverables
Final report Final version of IRMii
Problems Too few hours to do any new implementation
12
T-76.115 Project ReviewT-76.115 Project Review
Project evaluationSummary – customer goals
Goals of the customer 8 goals have been met:
IRM as baseline Fully-functional core system Modular and extendable implementation Source code follows conventions GUI uses Nokia guidelines Intranet-integrated authentication mechanism Integrated customer front-end and administrator back-end Migration plan for old data
1 goal still to be verified by the customer: Light-weight and minimal overhead
1 goal not completely met: Well-documented
13
T-76.115 Project ReviewT-76.115 Project Review
Project evaluationSummary - requirements
Total 129 requirements of which 101 implemented. Most requirements have been implemented and verified A couple mandatory still not implemented, but they should maybe had
been lower priority requirements. Unbalanced prioritization
“impossible” to divide them in any other way. IRM as baseline
14
T-76.115 Project ReviewT-76.115 Project Review
Project evaluationSummary – quality assurance
12755 lines of code 7200 lines of comments
Only three bugs open 46 bugs closed
Quality assurance OK
All bugs Open bugs
15
T-76.115 Project ReviewT-76.115 Project Review
Project evaluationFuture work
Real-environment deployment will determine the level of quality.
What would be nice? Searching/sorting functionalities Reports Notifications and announcements Binary attachments Fine-tuning the code Event logging (Automated) unit testing for all classes and GUIs Documentation for users, administrators and developers Roll-back option for actions (undo) Knowledge base add-on
Thanks toOur customerOur mentor
Course personnel