4
insw.com/sfs | [email protected] | 1800 414 020 xxxxx Sydney Football Stadium Redevelopment Project update – July 2020 Construction update Works at the SFS site are progressing to schedule. Work completed to date includes: Approximately 15 percent of piling is complete. There have been 30,000 tonnes of earthworks completed. The occupational hygienist continues to oversee remediation of the site as per the remediation action plan. The Paddington Lane retaining wall is approximately 30 percent complete and progressing well. The permanent inground services have commenced on site and are estimated to be complete in October 2020. Upcoming works The project is entering what is considered ‘stage three’ under the Construction Management Plan, which involves work to build the structure from the basement to the concourse level. Over the coming months, work will include: Earthworks and piling will continue until late 2020. There are now three piling rigs on site. Works on the Paddington Lane retaining wall are continuing and expected to finish in August. Concrete slabs on ground will commence in August with concrete form work (jump forms) established

Sydney Football Stadium Redevelopmentinfrastructure.nsw.gov.au/media/2565/sfs_project-update_july_web.pdf · Sydney Football Stadium Redevelopment Project update – July 2020 Construction

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Sydney Football Stadium Redevelopmentinfrastructure.nsw.gov.au/media/2565/sfs_project-update_july_web.pdf · Sydney Football Stadium Redevelopment Project update – July 2020 Construction

insw.com/sfs | [email protected] | 1800 414 020

xxxxx

Sydney Football Stadium RedevelopmentProject update – July 2020

Construction updateWorks at the SFS site are progressing to schedule. Work completed to date includes:

— Approximately 15 percent of piling is complete.

— There have been 30,000 tonnes of earthworks completed.

— The occupational hygienist continues to oversee remediation of the site as per the remediation action plan.

— The Paddington Lane retaining wall is approximately 30 percent complete and progressing well.

— The permanent inground services have commenced on site and are estimated to be complete in October 2020.

Upcoming worksThe project is entering what is considered ‘stage three’ under the Construction Management Plan, which involves work to build the structure from the basement to the concourse level. Over the coming months, work will include:

— Earthworks and piling will continue until late 2020. There are now three piling rigs on site.

— Works on the Paddington Lane retaining wall are continuing and expected to finish in August.

— Concrete slabs on ground will commence in August with concrete form work (jump forms) established

Page 2: Sydney Football Stadium Redevelopmentinfrastructure.nsw.gov.au/media/2565/sfs_project-update_july_web.pdf · Sydney Football Stadium Redevelopment Project update – July 2020 Construction

Sydney Football Stadium Redevelopment | July 2020

insw.com/sfs | [email protected] | 1800 414 020

Hours of operation The project continues to utilise extended working hours under the Environmental Planning and Assessment (COVID-19 Development – Construction Work Days) Order 2020. Current working hours are:

Monday to Friday: 7am – 6pm

Saturday: 7am – 6pm

Sunday: 8am – 3pm

Online community webinar We’re hosting regular community information sessions throughout the delivery of the project. These sessions offer an opportunity for the community to ask questions of the project team and our technical experts, learn more about the project and provide important feedback. While social distancing restrictions in relation to Covid-19 remain in place, we will continue to hold online community forums to keep you updated.

The next forum will be held online:

Tuesday 14 July 2020, 6pm-7:30pm

To reserve your place, please email [email protected] by 10 July 2020.

Page 3: Sydney Football Stadium Redevelopmentinfrastructure.nsw.gov.au/media/2565/sfs_project-update_july_web.pdf · Sydney Football Stadium Redevelopment Project update – July 2020 Construction

insw.com/sfs | [email protected] | 1800 414 020

Design refinements The design of the stadium has been enhanced through the detailed design process. However, the overall height and shape has remained in line with the approved Development Application.

The main changes of note are illustrated in the updated design of the new stadium’s main entry from Driver Avenue.

— The brick walls have been reduced in size to add a more human scale and folded down on the ends to provide a stronger visual link to the landscaping on top.

— The materials used for the walls have changed and are similar to the existing brick wall that runs down Driver Ave to the SCG – creating a strong visual connection.

Sydney Football Stadium Redevelopment | July 2020

Page 4: Sydney Football Stadium Redevelopmentinfrastructure.nsw.gov.au/media/2565/sfs_project-update_july_web.pdf · Sydney Football Stadium Redevelopment Project update – July 2020 Construction

Sydney Football Stadium Redevelopment | July 2020

insw.com/sfs | [email protected] | 1800 414 020

View of the wall looking south-east

A map from 1917 showing the location of the sandstone wall (R 13260-1630 Plan of the Road (1917)

The wall as part of the Sydney Showground & Cricket Grounds – RAHS Adastra Aerial Photography Collection

Want to know more about the project?If you have any questions, please don’t hesitate to contact us:

 1800 414 020     [email protected]     insw.com/sfs

Archaeological find at the SFS site During Stage 1 demolition works, a large sandstone wall, estimated to have been built over 100 years ago, was uncovered in the western section of the site.

Following a formal assessment and report by archaeologists, the wall was identified to be a substantial structure made from dressed sandstone blocks in a coursed ashlar masonry form.

According to the project archaeologists, the wall appears on the 1917 plan below as a boundary of a former road and is likely to have been constructed between 1898 and 1917 and not part of the former military rifle range associated with Victoria Barracks. This area at various times had a garden, Engineering Corps buildings and a cricket ground associated with the military barracks.

It is likely that the road was formed sometime after 1896, when the entrance from Moore Park Road to Sydney Common was expanded into a link road. While the road was originally surveyed as one chain wide, it appears that by

1917 a decision had been made to narrow the road to “a vehicle width” (half a chain) with the unwanted section of the road (the northern half) being added to the grant of the Athletic Sports Ground.

A wall is visible in roughly the same location on a number of 1930 era oblique aerial archival images and on the 1943 aerial archival images. Presumably, it was mostly removed when the former Sydney Football stadium was first constructed in 1988.

The wall was exposed, surveyed and recorded in accordance with the recommendations of the project archaeologists and has now been removed so that Stage 2 works can continue in the area.

The project team is exploring the feasibility of reusing some of the sandstone that was salvaged in the stadium landscaping.