Swyd Comm Std

  • Upload
    sam

  • View
    223

  • Download
    0

Embed Size (px)

Citation preview

  • 7/31/2019 Swyd Comm Std

    1/14

    May 24, 2012 PMI Revision 00 1

  • 7/31/2019 Swyd Comm Std

    2/14

    May 24, 2012 PMI Revision 00 2

    Presentation outline

    Switchyard: Purpose and main parts Pre- Commissioning Requirement Switchyard Equipment Commissioning process:

    Circuit Breaker

    Isolator pantograph and line isolator CT CVT Lightening Arrestor (LA)

    Earth Switch Integrated checks Conclusion

  • 7/31/2019 Swyd Comm Std

    3/14

    May 24, 2012 PMI Revision 00 3

    SWITCHYARD

    Purpose :

    Transmit the electricity generated up to load centre

    Proper control and protection

    Communication

    Exchange of power in emergency Main parts :

    Control room

    Relay room

    EHV yard

    Compressor room, battery room,

  • 7/31/2019 Swyd Comm Std

    4/14

    May 24, 2012 PMI Revision 00 4

    Switchyard Commissioning includes :

    Indoor & Outdoor equipments

    Control circuit, logics , interlocks, indication

    Protection schemes

    Metering schemes

    Associated equipments like batteries, Compressors etc

    Improper commissioning may lead to :

    Outage of equipments, resulting in to huge financial loss,

    System Disturbance or even grid collapse

    Safety hazard

  • 7/31/2019 Swyd Comm Std

    5/14

    May 24, 2012 PMI Revision 00 5

    BEFORE DOING ANY WORK

    ENSURE THAT THE EQUIPMENT IS PROPERLYENSURE THAT THE EQUIPMENT IS PROPERLYISOLATED FROM SUPPLY AND EARTHED.ISOLATED FROM SUPPLY AND EARTHED.

    ALSO, THE BAY NO / CONTROL PANEL NO. ISALSO, THE BAY NO / CONTROL PANEL NO. IS

    CORRECTLY IDENTIFIEDCORRECTLY IDENTIFIED..

  • 7/31/2019 Swyd Comm Std

    6/14

    May 24, 2012 PMI Revision 00 6

    Nomenclature criteria Schematic drawings Scope of work and time schedule Safety Clearance and permit system Civil work Lighting and earthing system

    Availability of : Power supply Skilled / unskilled manpower Testing and commissioning equipments Drawings, schematic diagrams and technical Literature Spares

    Cable schedules and proper termination Fuse ratings and Relay setting calculation

    PRE- COMMISSIONING REQUIREMENT

  • 7/31/2019 Swyd Comm Std

    7/14

    May 24, 2012 PMI Revision 00 7

    SWITCHYARD EQUIPMENTS COMMISSIONING

    CIRCUIT BREAKER

    General Checks :Erection work completed, clearance receivedCompressed air system available, Check air leakagesCleaning and tightness of fasteners, insulators. Check earthing connections done

    Check operating mechanism and alignment Check aux. contacts, coil healthiness and control wiring Check hand valves, drain plugs, pr. Relief valve, pr. Gauge etc Check ac and dc supply, control wiring and relays, timers, indications, Check safety valve operation Contact resistance measurement

    Other checks to specific type of circuit bkr ( e.g. pressure test for ABCB)Functional checks :Close & open time; anti pumping operation, pole discrepancy , manualand protection trip, interlocks

  • 7/31/2019 Swyd Comm Std

    8/14

    May 24, 2012 PMI Revision 00 8

    Physical inspection :. Foundation bolts, insulator supporting bolts etctightened

    Erection work completed. Cleaning of insulators, corona rings etc. Lubrication of all moving parts. Proper earthing of structure base, operating mech box, Mechanical interlock between isolator and earth switch. IR value bet. current carrying parts and earth (5KV megger) Contact resistance

    Functional checks : Local and remote operation, indication

    Thermal Overload : Check after a number of operations Electrical interlock between isolator and circuit breaker. On / Off timing, Limit switches, aux contacts

    SWITCHYARD EQUIPMENTS COMMISSIONING

    ISOLATORS

  • 7/31/2019 Swyd Comm Std

    9/14

    May 24, 2012 PMI Revision 00 9

    SWITCHYARD EQUIPMENTS COMMISSIONING

    Physical Inspection : Cleaning &Tightness of terminals, earthing connections, corona rings Check the name plate details Oil level OK, no oil leakage Check external wiring

    I R value (5KV megger) : Pri - E, Pri - Sec (500 v megger): Sec - Sec of other cores

    Winding resistance Primary injection Polarity

    Secondary injection Magnetising characteristics and knee point

  • 7/31/2019 Swyd Comm Std

    10/14

    May 24, 2012 PMI Revision 00 10

    SWITCHYARD EQUIPMENTS COMMISSIONING

    CAPACITOR VOLTAGE TRANSFORMERS

    Safety checks: Erection work completed and HV terminal is earthed Physical Inspection :

    Cleaning &Tightness of terminals, earthing connections, corona rings etc Check the name plate details Oil level OK, no oil leakage

    Check external wiring I R value

    (5KV megger) : Pri - E, Pri - Sec (500 v megger): Sec - Sec of other cores

    Winding resistance Ratio Test

    Polarity

  • 7/31/2019 Swyd Comm Std

    11/14

    May 24, 2012 PMI Revision 00 11

    SWITCHYARD EQUIPMENTS COMMISSIONING

    Physical inspection, cleaning and tightness, operating mechanism and

    alignment

    IR value between top and earth, every stack and earth

    Contact resistance.

    Operating checks and interlocks

  • 7/31/2019 Swyd Comm Std

    12/14

    May 24, 2012 PMI Revision 00 12

    SWITCHYARD EQUIPMENTS COMMISSIONING

    Battery room : Cleaning, ventilation, fire protection system, distilled and

    running water, floor and walls to be acid resistant, safety equipments

    e.g. goggles, aprons, gloves torch etc to be made available.

    Battery cells : no leakage of electrolyte, vent and caps Ok, polaritycorrect, inter cell links tightened and greased, electrolyte level and sp

    gravity ok,

    Charging and discharging cycle as per manufacturers recommendation.

    Capacity test

  • 7/31/2019 Swyd Comm Std

    13/14

    May 24, 2012 PMI Revision 00 13

    Original equipment quality + good commissioning

    = trouble free performance year after year

    Commissioning results to be interpreted considering Manufacturers specifications

    Trends

    Limitations of sampling and measurement

    External factors like temp. humidity etc

    SWITCHYARD EQUIPMENTS COMMISSIONING

  • 7/31/2019 Swyd Comm Std

    14/14

    May 24, 2012 PMI Revision 00 14