Presentation outline
Switchyard: Purpose and main parts Pre- Commissioning Requirement Switchyard Equipment Commissioning process:
Circuit Breaker
Isolator pantograph and line isolator CT CVT Lightening Arrestor (LA)
Earth Switch Integrated checks Conclusion
7/31/2019 Swyd Comm Std
3/14
May 24, 2012 PMI Revision 00 3
SWITCHYARD
Purpose :
Transmit the electricity generated up to load centre
Proper control and protection
Communication
Exchange of power in emergency Main parts :
Control room
Relay room
EHV yard
Compressor room, battery room,
7/31/2019 Swyd Comm Std
4/14
May 24, 2012 PMI Revision 00 4
Switchyard Commissioning includes :
Indoor & Outdoor equipments
Control circuit, logics , interlocks, indication
Protection schemes
Metering schemes
Associated equipments like batteries, Compressors etc
Improper commissioning may lead to :
Outage of equipments, resulting in to huge financial loss,
System Disturbance or even grid collapse
Safety hazard
7/31/2019 Swyd Comm Std
5/14
May 24, 2012 PMI Revision 00 5
BEFORE DOING ANY WORK
ENSURE THAT THE EQUIPMENT IS PROPERLYENSURE THAT THE EQUIPMENT IS PROPERLYISOLATED FROM SUPPLY AND EARTHED.ISOLATED FROM SUPPLY AND EARTHED.
ALSO, THE BAY NO / CONTROL PANEL NO. ISALSO, THE BAY NO / CONTROL PANEL NO. IS
CORRECTLY IDENTIFIEDCORRECTLY IDENTIFIED..
7/31/2019 Swyd Comm Std
6/14
May 24, 2012 PMI Revision 00 6
Nomenclature criteria Schematic drawings Scope of work and time schedule Safety Clearance and permit system Civil work Lighting and earthing system
Availability of : Power supply Skilled / unskilled manpower Testing and commissioning equipments Drawings, schematic diagrams and technical Literature Spares
Cable schedules and proper termination Fuse ratings and Relay setting calculation
PRE- COMMISSIONING REQUIREMENT
7/31/2019 Swyd Comm Std
7/14
May 24, 2012 PMI Revision 00 7
SWITCHYARD EQUIPMENTS COMMISSIONING
CIRCUIT BREAKER
General Checks :Erection work completed, clearance receivedCompressed air system available, Check air leakagesCleaning and tightness of fasteners, insulators. Check earthing connections done
Check operating mechanism and alignment Check aux. contacts, coil healthiness and control wiring Check hand valves, drain plugs, pr. Relief valve, pr. Gauge etc Check ac and dc supply, control wiring and relays, timers, indications, Check safety valve operation Contact resistance measurement
Other checks to specific type of circuit bkr ( e.g. pressure test for ABCB)Functional checks :Close & open time; anti pumping operation, pole discrepancy , manualand protection trip, interlocks
7/31/2019 Swyd Comm Std
8/14
May 24, 2012 PMI Revision 00 8
Physical inspection :. Foundation bolts, insulator supporting bolts etctightened
Erection work completed. Cleaning of insulators, corona rings etc. Lubrication of all moving parts. Proper earthing of structure base, operating mech box, Mechanical interlock between isolator and earth switch. IR value bet. current carrying parts and earth (5KV megger) Contact resistance
Functional checks : Local and remote operation, indication
Thermal Overload : Check after a number of operations Electrical interlock between isolator and circuit breaker. On / Off timing, Limit switches, aux contacts
SWITCHYARD EQUIPMENTS COMMISSIONING
ISOLATORS
7/31/2019 Swyd Comm Std
9/14
May 24, 2012 PMI Revision 00 9
SWITCHYARD EQUIPMENTS COMMISSIONING
Physical Inspection : Cleaning &Tightness of terminals, earthing connections, corona rings Check the name plate details Oil level OK, no oil leakage Check external wiring
I R value (5KV megger) : Pri - E, Pri - Sec (500 v megger): Sec - Sec of other cores
Winding resistance Primary injection Polarity
Secondary injection Magnetising characteristics and knee point
7/31/2019 Swyd Comm Std
10/14
May 24, 2012 PMI Revision 00 10
SWITCHYARD EQUIPMENTS COMMISSIONING
CAPACITOR VOLTAGE TRANSFORMERS
Safety checks: Erection work completed and HV terminal is earthed Physical Inspection :
Cleaning &Tightness of terminals, earthing connections, corona rings etc Check the name plate details Oil level OK, no oil leakage
Check external wiring I R value
(5KV megger) : Pri - E, Pri - Sec (500 v megger): Sec - Sec of other cores
Winding resistance Ratio Test
Polarity
7/31/2019 Swyd Comm Std
11/14
May 24, 2012 PMI Revision 00 11
SWITCHYARD EQUIPMENTS COMMISSIONING
Physical inspection, cleaning and tightness, operating mechanism and
alignment
IR value between top and earth, every stack and earth
Contact resistance.
Operating checks and interlocks
7/31/2019 Swyd Comm Std
12/14
May 24, 2012 PMI Revision 00 12
SWITCHYARD EQUIPMENTS COMMISSIONING
Battery room : Cleaning, ventilation, fire protection system, distilled and
running water, floor and walls to be acid resistant, safety equipments
e.g. goggles, aprons, gloves torch etc to be made available.
Battery cells : no leakage of electrolyte, vent and caps Ok, polaritycorrect, inter cell links tightened and greased, electrolyte level and sp
gravity ok,
Charging and discharging cycle as per manufacturers recommendation.
Capacity test
7/31/2019 Swyd Comm Std
13/14
May 24, 2012 PMI Revision 00 13
Original equipment quality + good commissioning
= trouble free performance year after year
Commissioning results to be interpreted considering Manufacturers specifications
Trends
Limitations of sampling and measurement
External factors like temp. humidity etc
SWITCHYARD EQUIPMENTS COMMISSIONING