Summary Report on Phase Two Consultation_FINAL

Embed Size (px)

Citation preview

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    1/74

    A

    Thames Tunnel

    Thames TunnelSummary report on

    phase two consultationMay 2012

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    2/74

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    3/74

    1

    Thames TunnelSummary report on

    phase two consultationMay 2012

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    4/74

    Phase two consultation / Summary report 2

    Contents

    Foreword 4

    1 Introduction 51.1 The project 5

    1.2 Phase two consultation 51.3 Feedback received 7

    2 Need, solution, tunnel route andalignment 8

    2.1 Introduction 82.2 The need to signicantly reduce

    the amount o sewage enteringthe River Thames 8

    2.3 The tunnel as the right solution 92.4 Tunnel route 10

    2.5 Alignment o the Abbey Mills route 102.6 Our view o the way orward 11

    3 Other comments 11

    4 The sites 12

    5 Acton Storm Tanks 12

    6 Hammersmith Pumping Station 14

    7 Barn Elms 16

    8 Putney Bridge Foreshore 19

    9 Dormay Street 21

    10 King Georges Park 23

    11 Carnwath Road Riverside 28

    12 Falconbrook Pumping Station 28

    13 Cremorne Whar Depot 30

    14 Chelsea Embankment Foreshore 34

    15 Kirtling Street 35

    16 Heathwall Pumping Station 37

    17 Albert Embankment Foreshore 39

    18 Victoria Embankment Foreshore 41

    19 Blackriars Bridge Foreshore 43

    20 Shad Thames Pumping Station 45

    21 Chambers Whar 47

    22 Earl Pumping Station 50

    23 Deptord Church Street 5224 Greenwich Pumping Station 54

    25 King Edward Memorial Park Foreshore 56

    26 Bekesbourne Street 59

    27 Abbey Mills Pumping Station 61

    28 Beckton Sewage Treatment Works 63

    29 Jews Row 64

    30 Other works 6531 Consultation process 6531.1 Introduction 6531.2 Attendance at exhibitions 6531.3 Feedback on consultation inormation 6631.4 Feedback on the consultation process 6631.5 Our view o the way orward 67

    32 Conclusions and next steps 6732.1 Introduction 6732.2 The need, solution, tunnel route

    and alignment 6732.3 Outcomes or the preerred sites 6832.4 Next steps 68

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    5/74

    3

    Table 2.1 Statutory consultees and local

    authorities who provided eedback on

    the need or the project 8

    Table 2.2 Statutory consultees and local

    authorities who provided eedback onthe proposed solution 9

    Table 2.3 Statutory consultees and local

    authorities who provided eedback on

    our preerence or the Abbey Mills route 10

    Table 2.4 Local authorities who provided

    eedback on the alignment o the

    Abbey Mills route 11

    Table 5.1 Statutory consultees and local

    authorities who provided eedback

    on Acton Storm Tanks 13

    Table 6.1 Statutory consultees and localauthorities who provided eedback

    on Hammersmith Pumping Station 17

    Table 7.1 Statutory consultees and local

    authorities who provided eedback

    on Barn Elms 17

    Table 8.1 Statutory consultees and local

    authorities who provided eedback

    on Putney Bridge Foreshore 19

    Table 9.1 Statutory consultees and local

    authorities who provided eedback

    on Dormay Street 22Table 10.1 Statutory consultees and local authorities

    commenting on King Georges Park 24

    Table 11.1 Statutory consultees and local

    authorities who provided eedback

    on Carnwath Road Riverside 26

    Table 12.1 Statutory consultees and local

    authorities who provided eedback on

    Falconbrook Pumping Station Riverside 29

    Table 13.1 Statutory consultees and local

    authorities who provided eedback

    on Cremorne Whar Depot 31

    Table 14.1 Statutory consultees and local

    authorities who provided eedback

    on Chelsea Embankment Foreshore 33

    Table 15.1 Statutory consultees and local

    authorities who provided eedback

    on Kirtling Street 35

    Table 16.1 Statutory consultees and local

    authorities who provided eedback

    on Heathwall Pumping Station 37

    Table 17.1 Statutory consultees and local

    authorities who provided eedbackon Albert Embankment Foreshore 39

    Table 18.1 Statutory consultees and local

    authorities who provided eedback

    on Victoria Embankment Foreshore 41

    Table 19.1 Statutory consultees and local

    authorities who provided eedbackon Blackriars Bridge Foreshore 43

    Table 20.1 Statutory consultees and local

    authorities who provided eedback on

    Shad Thames Pumping Station 46

    Table 21.1 Statutory consultees and local

    authorities who provided eedback

    on Chambers Whar 47

    Table 22.1 Statutory consultees and local

    authorities who provided eedback

    on Earl Pumping Station 50

    Table 23.1 Statutory consultees and localauthorities who provided eedback

    on Deptord Church Street 52

    Table 24.1 Statutory consultees and local

    authorities who provided eedback

    on Greenwich Pumping Station 54

    Table 25.1 Statutory consultees and local

    authorities who provided eedback on

    King Edward Memorial Park Foreshore 57

    Table 26.1 Statutory consultees and local

    authorities who provided eedback

    on Bekesbourne Street 59Table 27.1 Statutory consultees and local

    authorities who provided eedback

    on Abbey Mills Pumping Station 61

    Table 28.1 Statutory consultees and local

    authorities who provided eedback on

    Beckton Sewage Treatment Works 53

    Table 30.1 Statutory consultees who provided

    eedback on Other works 65

    Table 31.1 Attendance at exhibitions during

    phase two consultation (question 15) 65

    Table 31.2 Do you think you have been provided

    with enough inormation and consultation

    material on the project to enable you to

    comment? (question 16) 66

    Table 31.3 Other comments on the

    Thames Tunnel project consultation

    process (question 17) 66

    List of tables

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    6/74

    Phase two consultation / Summary report 4

    Foreword

    Thank you to everyone who took the trouble and timeto take part in this consultation and have their say on

    our proposals. We welcome the on-going dialogue withresidents, community and campaign groups, businesses,organisations and boroughs. All the inormationreceived is invaluable to us as we continue to developthe design o this critical inrastructure project.

    Your ideas, views and inormation received during ourphase two consultation will support our aim to ensurethe nal design is the best solution to this problem,providing value or money with the least disruptionto Londoners and this vibrant, world-leading city.

    Importantly, we have been provided with manyopportunities not only to address local groups,but also to talk to you individually about the needor the Thames Tunnel project. Finding constructionsites to support the project in a densely populatedcity was never going to be an easy task. In the phasetwo consultation we were able to provide much moredetailed inormation on our proposals and discuss howthe project could aect you. We have listened and,wherever possible, we have acted on your eedback.

    This report is just a summary o your eedback.Our responses to your detailed comments can be

    ound in the Main and Supplementary reports onphase two consultation. We expect to carry out ourSection 48 publicity later this year when we will publishour proposed application or development consentor the project. You will have at least six weeks tomake any comments.

    We welcome the support we have received or ourproposals and we also understand where concernshave been raised. We know there are dicult decisionsto take and we are making every eort to limit the

    impacts on communities and the environment as aras we can.

    We are keen to keep talking to you, so i you haveany questions or concerns, please get in touch.

    Richard Aylard CVO

    External Aairs &Sustainability Director

    Phil Stride

    Head o London TidewayTunnels

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    7/74

    5

    1. Introduction

    1.1 The project

    1.1.1 The Thames Tunnel project is needed to help

    substantially reduce the amount o untreatedsewage which enters the River Thames whenthe sewerage system exceeds its capacity.Projected population growth and new buildingsadd to the need urgently to address this problem.We are proposing to build the Thames Tunnel(the project) to capture the untreated sewagebeore it enters the River Thames. This willbring long-term benets or the environmentand people who use the river.

    1.1.2 The project will help ensure that the UK complieswith the EU Urban Waste Water TreatmentDirective, and assist in meeting the objectiveso the EU Water Framework Directive.

    1.1.3 It is expected that the Thames Tunnel projectwill shortly be designated a nationallysignicant inrastructure project that is subjectto the provisions o the Planning Act 2008.We are thereore ollowing the requirementso this Act and associated guidance, in so ar

    as we are able to.

    1.1.4 Beore we submit a Development ConsentOrder (DCO) application or the project,we want to understand the views o statutoryconsultees, local authorities, landowners andcommunity consultees. We have carried outour phase two consultation in accordancewith Sections 42 and 47 o the Planning Act2008. Our phase two consultation, whichwe undertook between 4 November 2011

    and 10 February 2012, provided a secondopportunity or us to gather eedback.All the comments received have been careullyconsidered and, where possible, we will takethese into account as design developmentor the project continues.

    1.1.5 Our Report on phase two consultation sets outthe process we ollowed in order to carry outour phase two consultation and analyse theeedback received. It sets out the eedback

    we received together with our response to thecomments raised.

    1.1.6 The Report on phase two consultation is inthree parts:

    this summary report, a non-technicalsummary o eedback received, which identiesthe main eedback raised

    the main report (including appendices), whichprovides an overview o the supportive andneutral eedback comments made, togetherwith objections, issues and concerns raised,and provides our responses to these issues

    the supplementary report, which sets outcomprehensively and in detail all the eedbackcomments received, and our responses.

    1.1.7 This summary report provides an overview o

    the eedback received. Given the volume oresponses received, each chapter within thisreport identies the key or main points raised.As set out above, the Main and Supplementaryreports on phase two consultation providemore detail on the eedback received andour responses to the comments made.

    1.2 Phase two consultation

    What we consulted on

    1.2.1 During phase two consultation, we consulted on:

    the need or the project, including whethera tunnel is the most appropriate solution

    our preerred tunnel route, including thedetailed alignment o the tunnel

    our preerred sites or the construction andpermanent works

    detailed proposals or our preerred sites,which take into account the results o our

    phase one consultation and urther, moredetailed, technical work undertaken

    the eects o the project, as reported in ourPreliminary environmental information report.

    Whom we consulted

    1.2.2 In accordance with Sections 42 and 47 o the2008 Act, and as set out in our Statementof community consultation (SOCC), we haveconsulted with the ollowing groups:

    statutory consultees

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    8/74

    Phase two consultation / Summary report 6

    local authorities, including potentially directlyaected local authorities and authorities thatare adjacent to local authorities where wepropose to undertake works

    landowners, including property owners and

    lessees o shortlisted sites, and occupiers oproperties above and adjacent to the potentialtunnel routes

    community consultees, including the generalpublic, local property owners/occupiers,local businesses, community representativesand groups.

    1.2.3 In anticipation that the project will becomea nationally signicant inrastructure project,on 2 November 2011, we notied the

    Inrastructure Planning Commission oour intention to submit an application ordevelopment consent or the project andwe supplied our consultation materials to theCommission as i Section 46 o the PlanningAct 2008 applied. We also conrmed thatwe propose to provide an environmentalstatement in respect o the project as parto the application or development consentor the project as i Regulation 6(1)(b) o theInrastructure Planning (Environmental ImpactAssessment) Regulations 2009 applied.

    How we consulted

    1.2.4 Beore starting our phase two consultation,we re-consulted with local authorities andstatutory consultees on our drat revisedSOCC and Community consultation strategy.We published the SOCC in the London EveningStandardon 4 November 2011.

    1.2.5 We sent out over 129,000 letters to properties

    located a minimum o 250m rom theboundary o each preerred and shortlisted siteand within a broad corridor along the preerredtunnel route. The boundary was appliedfexibly, according to the scale and nature othe proposed works and taking into accountthe characteristics o the surrounding area.The letters set out our proposals, gave detailso exhibitions and contained a languagetranslation sheet, which provided details

    on the language line services.

    1.2.6 To publicise our consultation we also:

    placed advertisements in local newspapers(in addition to the London Evening Standardon 4 November 2011)

    posted site notices in the vicinity o each o our

    preerred sites. These contained a site locationmap and described our proposals or the site

    distributed leafets to all properties with a letterbox (businesses and residences) within 250mo each preerred site and, where our preerredsite has changed since phase one consultation,to all the shortlisted sites as well. We deliveredthese in advance o each local exhibition heldin that area.

    1.2.7 For our phase two consultation we: held 57 days o exhibitions at 23 venues

    provided inormation about ourproposals on our project website(www.thamestunnelconsultation.co.uk)

    provided a ree phone number(0800 0721 086) or any questions,as well as a translation service

    at the request o community groups, we

    attended 48 meetings to discuss our proposals

    we also produced project inormation paperson our proposals. These were available on ourwebsite and at exhibitions, local libraries andtown halls. The project inormation paperscovered topics such as options to reduce sewageentering the River Thames, tunnel route optionsand the proposed depth o the tunnel

    Site inormation papers were also availableor our preerred sites. These set out:

    | why a worksite is needed in theproposed location

    | the shortlisted sites we have considered,including justication or our preerred site

    | activities to be undertaken at eachphase o construction

    | the potential eects o our works duringconstruction and how we propose to

    address them| the design o our permanent works

    | the potential eects o our worksduring operation and how we proposeto address them.

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    9/74

    7

    1.2.8 We sought to ensure that it was equallypossible or everyone to respond to ourconsultation and oered a range o solutionsor people requiring assistance. For example,consultation inormation was available in largeprint, braille or audio ormat upon request.

    Our Customer Centre oered a telephoneservice to translate consultation materials intoany language on request. The language linewas used by those with an interest in theproject to translate the consultation materialinto a number o languages.

    1.2.9 We conducted a health and saety audit onpotential exhibition venues to ensure that asuitable balance was struck between accessto the buildings and proximity to the residents

    wishing to attend. All the exhibition locationsthat we used were accessible. Sta memberswere in attendance to acilitate access andassist the public.

    1.2.10 Feedback could be submitted by means opaper or electronic eedback orms and byletter or email.

    1.2.11 We have ollowed, and in many casesexceeded best practice, guidance and relevantlegal requirements when undertaking thisphase o consultation.

    1.2.12 We responded to individual written queries andphone calls through phase two consultation.Our Customer Centre handled over 900 phonecalls and 850 written queries, in addition toeedback orms received.

    1.2.13 We were responsive to requests or additionalexhibitions, holding a urther seven days oexhibitions at three venues, in addition to

    those set out in our SOCC.

    1.3 Feedback received

    1.3.1 A total o 6,019 respondents providedeedback to our phase two consultationwith a total o 6,553 responses received:

    Resident gives

    eedback at

    Deptord Church

    Street Exhibition

    Key:

    Statutory consultees Local authorities Landowners

    Community consultees* Petitions

    * Community consultees as dened by Section 47 o the Planning Act 2008 weresub-divided into urther categories within question A o the eedback orm. The gurecombines those respondents who answered as local residents, organisation or other.

    1.3.2 The respondents provided eedback in theollowing ways:

    Key:

    Feedback orms (online & hardcopy)

    Correspondence Petitions

    How we analysed the eedback received

    1.3.3 We anticipated that a signicant amounto eedback would be submitted. As a result,we considered that a thematic approach to

    analysing responses would be best since itwould provide a structure against which toanalyse all the eedback received.

    5,841

    131

    17

    21

    9

    4,636

    1,374

    9

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    10/74

    Phase two consultation / Summary report 8

    1.3.4 We have broadly analysed eedback againstthe questions in the eedback orm. Anexception to this was where it was clearthat the comments made in response to aparticular question actually related to anotherpart or a question within the same part o

    the eedback orm. This approach allowedeedback comments o a similar nature tobe grouped and presented together.

    1.3.5 The eedback comments were urthergrouped by the theme(s) that they related to,which included transport, air quality and noiseand vibration themes, or example. Feedbackwas also categorised depending on whetherthe eedback raised supportive and neutralcomments or objections, issues and concerns.

    1.3.6 The unique ID number o each respondentwas recorded with every comment; thisenabled us to systematically identiy whenthe same comment was made by more thanone respondent and present the volumeo eedback received on each theme.

    1.3.7 We have sought to take account o allresponses, whether or not they were in theminority, to ensure a air representation o theull range o comments received. As such, wehave not presented the proportions or numbero respondents who made comments in avouror against a particular solution or thematicissue in this report. However, the numbers orespondents who commented on particularissues are identied in the Supplementaryreport on phase two consultation.

    1.3.8 For urther detail on how we analysed theeedback received, reer to section 3.2 othe Main report on phase two consultation.

    2. Need, solution, tunnelroute and alignment

    2.1 Introduction

    2.1.1 We asked or views on the need to reduce theamount o sewage entering the River Thames,a tunnel as the proposed solution, our preerred

    tunnel route and the proposed tunnelalignment.

    2.2 The need to signifcantly reducethe amount o sewage entering theRiver Thames

    Number o respondents

    2.2.1 A total o 674 respondents provided

    comments on the need or the project.The respondents comprised:

    Key:

    Statutory consultees Local authorities Landowners

    Community consultees Petitions (0)

    2.2.2 Table 2.1 identies the statutory consulteesand local authorities who provided eedbackon need or the project.

    Statutory consultees Local authorities

    Consumer Council or Water

    Orange Telecom

    London Borough oHammersmith and Fulham

    London Borough o Southwark

    Royal Borough o Greenwich

    Sevenoaks District Council

    Table 2.1 Statutory consultees and local authoritieswho provided eedback on the need or the project

    Putney Bridge CSO

    612

    56

    4

    2

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    11/74

    9

    Feedback comments on the need tosignicantly reduce the amount o sewageentering the River Thames

    2.2.3 Main supportive and neutral eedbackcomments raised by respondents included:

    agreement that London needs to reducethe amount o untreated sewage enteringthe River Thames, in particular or theenvironmental and recreational benetsthis would bring

    there is a need to update and uture prooour sewerage inrastructure

    the issue should be addressed as soon as possible

    although the project was supported in principle,

    concerns were raised in relation to theproposed solution, tunnel route and proposedsites and the eects that will arise romaddressing the problem.

    2.2.4 Main objections, issues and concerns raisedby respondents included:

    disagreement that there is a need toreduce the amount o sewage enteringthe River Thames

    more inormation should be provided onthe extent o the problem; the need is notsuciently evidenced

    consider that water quality in the River Thameshas already improved signicantly/it is notclear that there is a problem with water quality

    whether the project is necessary given thatthe requency o overfows and volume o thedischarge is low

    the costs associated with addressing this problemneed to be proportionate to the benets.

    2.3 The tunnel as the right solution

    Number o respondents

    2.3.1 A total o 2,854 respondents providedcomments on a tunnel as the right solution.The respondents comprised:

    Key:

    Statutory consultees Local authorities Landowners

    Community consultees Petitions

    2.3.2 Table 2.2 identies the statutory consulteesand local authorities who provided eedbackon a tunnel as the right solution.

    Statutory consultees Local authorities

    Consumer Council or Water

    Crown Estate

    English Heritage

    London Councils

    Greater London Authority

    NATS En Route Saeguarding

    NHS Barking and Dagenham

    Orange Telecom

    The Highways Authority

    London Borough o

    Hammersmith and FulhamLondon Borough o RichmondUpon Thames

    London Borough o Ealing

    Royal Borough o Greenwich

    London Borough o Southwark

    London Borough o WalthamForest

    Sevenoaks District Council

    Table 2.2 Statutory consultees and local authorities

    who provided eedback on the proposed solution

    Feedback comments on the tunnel as theright solution

    2.3.3 The main supportive and neutral eedbackcomment raised by respondents includedagreement that the tunnel is the right solution.

    2.3.4 Main objections, issues and concerns raised byrespondents included:

    disagree that the tunnel is the right solution

    unsure whether the tunnel is the right solution,how eective it will be and whether it onlytreats the symptoms but not the problem itsel

    2,785

    52

    7

    9

    1

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    12/74

    Phase two consultation / Summary report 10

    concerns that once the tunnel is operational,raw sewage will still enter the River Thames,despite the huge cost and disruption

    query the reasons or choosing a tunnel as thesolution and how this is evidenced, including

    the need or urther work to demonstrate thatthe tunnel is the right solution

    concerns regarding the costs o the projectand how it will be unded, including queriesregarding the eects on customers bills.

    2.4 Tunnel route

    Number o respondents

    2.4.1 A total o 268 respondents provided comments

    on the tunnel route. The respondents comprised:

    Key:

    Statutory consultees Local authorities Landowners

    Community consultees Petitions (0)

    2.4.2 Table 2.3 identies the statutory consulteesand local authorities who provided eedbackon the tunnel route.

    Statutory consultees Local authorities

    English Heritage

    Orange Telecom

    London Borough o Ealing

    London Borough oHammersmith and Fulham

    Table 2.3 Statutory consultees and local authorities

    who provided eedback on our preerence or the

    Abbey Mills route

    Feedback comments on the tunnel route

    2.4.3 Main supportive and neutral eedbackcomments raised by respondents included:

    support or the:

    |

    Abbey Mills route| long connection tunnel connecting

    Greenwich Pumping Station, DeptordChurch Street and Earl Pumping Stationto the main tunnel at Chambers Whar

    | extension o the main tunnel toActon Storm Tanks.

    the tunnel is the most practical and cost-eective solution

    support the tunnel route, but do not agreewith proposed sites.

    2.4.4 Main objections, issues and concerns raisedby respondents included:

    disagree with the preerred tunnel route

    cost should not be the only determining actor

    more inormation requested on the route

    suggested modications to the Abbey Mills

    route and an independent review.

    2.5 Alignment o the Abbey Mills route

    2.5.1 A total o 173 respondents providedcomments on the tunnel alignment.The respondents comprised:

    Key:

    Statutory consultees (0) Local authorities Landowners

    Community consultees Petitions (0)

    237

    27

    2

    2

    150

    21

    2

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    13/74

    11

    2.5.2 Table 2.4 identies the local authorities whoprovided eedback on the tunnel alignment.

    Local authorities

    London Borough o Ealing

    London Borough o Tower Hamlets

    Table 2.4 Local authorities who provided eedback

    on the alignment o the Abbey Mills route

    Feedback comments on the tunnel alignment

    2.5.3 The main supportive and neutral eedbackcomment raised by respondents includedagreement that the proposed tunnelalignment was the least disruptive.

    2.5.4 Main objections, issues and concerns raised

    by respondents included:

    disagree with the preerred tunnel alignmentas it aects too many residents

    more inormation requested on the alignment

    concerns regarding the eect on buildingsand above and below ground inrastructure.Also concerns regarding the need to minimisepossible settlement, subsidence, damage andconstruction eects associated with tunnelling

    under residential properties and to old andsensitive structures

    suggestions or amendments to the constructionmethod, including ewer main tunnel drive sitesand using dierent tunnel boring machines.

    2.6 Our view o the way orward

    2.6.1 We recognise that some respondents haveconcerns about the need or the project andwhether a tunnel is the most appropriate

    solution. We have given careul considerationto these comments and reviewed the detailedevidence contained in the Needs report.We still believe that it is essential to reduce theamount o sewage entering the River Thamesand that a tunnel represents the best way toachieve this.

    2.6.2 Some o the concerns raised included detailedcomments on the design and constructiono the tunnel. These will, insoar as possible,

    be taken into account as the design o thetunnel progresses.

    2.6.3 We recognise that some respondents haveconcerns about our preerence or theAbbey Mills route and its alignment and preeralternative routes. Having considered thecomments received, we still consider that AbbeyMills remains the most appropriate route and

    we thereore intend to pursue this option. As thedesign o the tunnel progresses, we will continueto rene its alignment and will discuss thisurther with the relevant stakeholders.

    3. Other comments

    3.1.1 We also received eedback that relates to othermatters not directly related to the questions

    in our eedback orm.

    3.1.2 Main supportive and neutral eedbackcomments raised by respondents included:

    support or the anticipated level o job creationassociated with the project

    support or the revised air managementstrategy to avoid odour rom tunnel operationsand the associated reduction in the heighto the ventilation columns

    support or the approach to environmentalassessment, including the decision hierarchy,food risk studies and consideration o impactsand opportunities, at individual sites andproject-wide

    welcome the reduction in the number ooreshore sites with permanent structures.

    3.1.3 Main objections, issues and concerns raisedby respondents included:

    the approach to environmental assessment,including the topics to be reported in theenvironmental statement, the level o detail tobe assessed, and the need to mitigate eects

    the process that the Thames Tunnel project isollowing, including how the proposal will bedetermined and the role o local authorities

    the approach to assessing transport impacts

    the eects arising rom construction o

    the project

    detailed comments on technical documents andthe content o the proposed DCO application.

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    14/74

    Phase two consultation / Summary report 12

    Our view o the way orward

    3.1.4 We will take into account the detailedcomments that have been received as theproject develops. This includes reviewing thecomments received on the PEIR and related

    documents as part o the environmentalimpact assessment process to ensure that,where appropriate, they are taken ully intoaccount in the preparation o theEnvironmental Statement.

    3.1.5 We will continue to work with stakeholders,in relation to the permanent design andappearance o our sites as part o our designdevelopment. The ideas, views and inormationreceived during our phase two consultation will

    help to ensure the nal design is the optimumsolution or each o our sites, and best meetsthe needs o local communities.

    .

    4. The sites

    4.1.1 Most o the eedback that we received ocussedon the preerred sites on the Abbey Mills routewhich is summarised in this report. We also

    received some comments regarding theshortlisted sites that we had considered. Detailso the eedback received in respect o theshortlisted sites is set out in the Supplementaryreport on phase two consultation.

    4.1.2 We sought eedback on the ollowing mattersin relation to each site:

    views on whether our preerred site is appropriate

    whether an alternative site should be used and

    i so, which whether we have identied the key issues

    during the construction phase and appropriatemeasures to address them

    our proposed design

    whether we have identied the key issuesduring the operational phase and appropriatemeasures to address them.

    4.1.3 Chapters ve to 30 set out who has provided

    eedback on our preerred sites, their viewson our choice o site, and the main objections,concerns, and issues raised and supportive

    and neutral eedback comments received oreach site. We also set out our view o the wayorward. For detailed eedback commentsraised in relation to each o our preerred sites,reer to the Supplementary report on phasetwo consultation.

    4.1.4 In light o the eedback that we have received,we believe that no new inormation has beenhighlighted that would change the conclusionso our site selection process to date. The sitesthat we consulted on at phase two thereoreremain our preerred sites to construct theThames Tunnel.

    5. Acton Storm Tanks

    5.1.1 We are proposing to use parts o our existingpumping station and storm water tanks site orour construction works and to accommodatethe permanent building and structures requiredto operate the main tunnel. The site wouldreceive the main tunnel rom Carnwath RoadRiverside and connect the existing local CSO,known as the Acton Storm Relie CSO, to themain tunnel.

    Number o respondents

    5.1.2 A total o 37 respondents provided comments onActon Storm Tanks. The respondents comprised:

    Key:

    Statutory consultees Local authorities LandownersCommunity consultees Petitions (0)

    26

    4

    2

    5

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    15/74

    13

    Statutory consultees Local authorities

    Design Council CABE

    Consumer Council or Water

    English Heritage

    Environment Agency

    Greater London Authority

    London Borough o Ealing

    London Borough oHammersmith and Fulham

    Table 5.1 Statutory consultees and local authorities

    who provided eedback on Acton Storm Tanks

    Feedback on the selection and use o ourpreerred site

    Site selection and alternative sites5.1.3 Main supportive and neutral eedback

    comments raised by respondents included:

    support use o this site, including changing the

    use o the site since phase one consultation

    the site is more suitable than any shortlistedor alternative sites.

    5.1.4 Main objections, issues and concerns raisedby respondents included:

    reasons or selecting this preerred site arefawed/questionable; the site has only beenchosen because it is owned by Thames Wateror the associated cost benets, rather than

    being the best site rom a technical point o view

    the scale o eects on the local area andcommunity resulting rom the selectiono this site is unacceptable/has not beenproperly considered

    alternative site suggestions, included ActonPark Industrial Estate and Barn Elms.

    Management o construction works5.1.5 Main supportive and neutral eedback

    comments raised by respondents included: proposed site access and construction trac

    routes, in particular use o Warple Way,Canham Road and Stanley Gardens areappropriate

    proposed working hours are reasonable.

    5.1.6 Main objections, issues and concerns raisedby respondents included:

    concerns regarding the eects o construction

    trac on the loss o on-street car parking atWarple Way, Stanley Gardens and CanhamRoad and residential amenity

    concerns regarding odour, air quality and generalpollution during construction and how this wouldbe managed in order to protect amenity

    concerns regarding the uture use o the widerActon Storm Tanks site

    concerns regarding proposed working hours,including the potential or 24-hour working,and transparency regarding extended workinghours

    concerns regarding noise and vibration romconstruction trac and general vibrationassociated with the works, including theneed to provide mitigation, such as soundattenuation measures

    concern regarding the eect on qualityo lie and the proximity o the proposedwork to residential areas.

    Permanent design and appearance5.1.7 Main supportive and neutral eedback

    comments raised by respondents included:

    support or decommissioning the storm tanksand lling them with construction spoil

    the proposals will allow the public ootpathto be widened

    use o brick which is an appropriate and robustmaterial that matches the main material usedin the locality well.

    5.1.8 Main objections, issues and concerns raisedby respondents included:

    the ventilation column(s) are too low/smalland should be increased to above roo levelto avoid any odour emission issues

    the permanent buildings and structures arelocated too close to residential properties/should not be located in residential or builtup areas

    need more inormation on proposals, includingwhat is proposed or the rest o the site;conrmation as to whether the public willbe given access to the site; and whether theremaining storm tanks can be used or suracewater storage to help alleviate associated

    issues in west London.

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    16/74

    Phase two consultation / Summary report 14

    Management o operational eects5.1.9 No main supportive and neutral eedback

    comments, as dened in paragraph 1.1.7,were received.

    5.1.10 Main objections, issues and concerns raised by

    respondents included: concerns regarding the eect o odour arising

    rom operation o the tunnel and therequirement to incorporate contingencymeasures in case the technology proposeddoes not unction as stated

    require site management to control parkingassociated with maintenance works.

    Our view o the way orward

    5.1.11 We have received a range o eedback on ourproposals or this site, including supportiveand neutral comments and objections, issuesand concerns. We have taken all commentsreceived into account in accordance with therequirements o the Planning Act 2008.

    5.1.12 In light o the eedback that we have received,we believe that no new inormation has beenhighlighted that would change the conclusionso our site selection process to date. ActonStorm Tanks thereore remains our preerredsite to intercept the Acton Storm Relie CSOand receive the main tunnel rom CarnwathRoad Riverside. Additionally, no newinormation or issues have been identied thatwould undamentally change our proposals orthis site. Thereore we will continue to developthe proposals or this site that we published atphase two consultation.

    5.1.13 The eedback we have received included

    detailed comments on the construction andoperational eects o the proposeddevelopment and the measures we proposeto reduce and manage those eects. Detailedcomments were also made on our proposalsor the permanent design and appearanceo the site. Having regard to the eedbackreceived we are continuing to rene ourdetailed proposals or this site to improve thedesign and reduce the impacts on the local

    community and environment. Currently weare considering the ollowing changes to thelayout and/or appearance o our proposals:

    replacement o the proposed ventilationbuilding with a smaller an structure and ltersthat would be located in Storm Tanks 5 and6 with the shat

    relocation o the ventilation column so it is

    adjacent to Storm Tanks 5 and 6 widening o the ootpath on the southern

    side o Canham Road

    options or replacement parking.

    5.1.14 In our Statement of community consultationwe recognised that we may need to amendour scheme ollowing phase two consultationand that i changes came orward we wouldconsider whether targeted consultation is

    appropriate. We do not consider that thedegree o change in relation to this site or theeect on the local community would aectthe nature o the comments received duringphase two consultation in such a way as torequire urther consultation. On that basis,a round o targeted consultation on ourproposals or this site is not considerednecessary. We will progress with preparationo our application or a development consentorder and will incorporate the changes

    reerred to in paragraph 5.1.13 i urther workdemonstrates that this is appropriate. Weintend to publicise our proposed application inaccordance with Section 48 o the PlanningAct 2008 later in 2012. Full details o ourproposed scheme will be set out in our DCOapplication and accompanying documents.

    6. Hammersmith

    Pumping Station6.1.1 We are proposing to use part o our existing

    pumping station and part o a currently vacantsite known as Hammersmith Embankment/Fulham Reach at the corner o ChancellorsRoad and Distillery Road or our constructionworks and to accommodate the permanentstructures required to operate the main tunnel.The site would be used to connect the existing

    local CSO, known as the HammersmithPumping Station CSO, to the main tunnel.

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    17/74

    15

    Number o respondents

    6.1.2 A total o 36 respondents provided commentson our Hammersmith Pumping Station site.The respondents comprised:

    Key:

    Statutory consultees Local authorities Landowners (0)

    Community consultees Petitions (0)

    Statutory consultees Local authorities

    Design Council CABE

    Consumer Council or Water

    English Heritage

    Environment Agency

    Greater London Authority

    National Grid

    London Borough oHammersmith and Fulham

    Table 6.1 Statutory consultees and local authorities

    who provided eedback on Hammersmith

    Pumping Station

    Feedback on the selection and use o ourpreerred site

    Site selection and alternative sites6.1.3 Main supportive and neutral eedback

    comments raised by respondents included:

    support or the use o the preerred site; inparticular the use o a land-based site on landowned by Thames Water

    the site is more suitable than any shortlisted oralternative sites because it is browneld; it isalready an operational site and it is available

    or development

    qualied support or the preerred site subjectto appropriate assessment and mitigation anddemonstration that it is necessary.

    6.1.4 Main objections, issues and concerns raisedby respondents included:

    there are other more suitable alternative sitesavailable in the local area/alternative sites havenot been properly explored, including St Pauls

    Playing Fields across the River Thames site selection should avoid sites in residential

    or densely populated areas

    alternative site suggestions, included urtherupstream and south o the River Thames.

    Management o construction works6.1.5 Main supportive and neutral eedback

    comments raised by respondents included:

    the proposal will support redevelopment

    o the site and/or surrounding area

    the necessary works at this site can becoordinated with the phased mixed usedevelopment by St George plc o theHammersmith Embankment/FulhamReach site.

    6.1.6 Main objections, issues and concerns raisedby respondents included:

    construction trac will exacerbate existing

    trac congestion on Fulham Palace Road(A219) and Hammersmith Gyratory

    use the river rather than road to transportconstruction materials and spoil, includingconsolidation centres at nearby barge/railserved sites

    compatibility with existing planning permissionadjacent to/in the vicinity o the site.

    Permanent design and appearance

    6.1.7 The main supportive and neutral eedbackcomment raised by respondents was thatthe design proposals are acceptable.

    6.1.8 The main objection, issue and concern raisedby respondents was that the proposals areunimaginative/bland, and should beenvironmentally riendly.

    Management o operational eects6.1.9 The main supportive and neutral eedback

    comment raised by respondents was that

    the proposals would ensure that odour issatisactorily managed.

    29

    6

    1

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    18/74

    Phase two consultation / Summary report 16

    6.1.10 The main objection, issue and concern raisedby respondents was in relation to the eect oodour arising rom the operation o the tunneland the need to monitor the eects.

    Our view o the way orward

    6.1.11 We have received a range o eedback on ourproposals or this site, including supportiveand neutral comments and objections, issuesand concerns. We have taken all commentsreceived into account in accordance with therequirements o the Planning Act 2008.

    6.1.12 In light o the eedback that we have received,we believe that no new inormation hasbeen highlighted that would change the

    conclusions o our site selection process todate. Hammersmith Pumping Stationthereore remains our preerred site tointercept the Hammersmith Pumping StationCSO. Additionally, no new inormation orissues have been identied that wouldundamentally change our proposals or thissite. Thereore we will continue to develop theproposals or this site that we published atphase two consultation.

    6.1.13 The eedback we have received includeddetailed comments on the construction andoperational eects o the proposeddevelopment and the measures we proposeto reduce and manage those eects. Detailedcomments were also made on our proposalsor the permanent design and appearanceo the site. Having regard to the eedbackreceived we are continuing to rene ourdetailed proposals or this site to improve thedesign and reduce the impacts on the local

    community and environment. Currently we areconsidering whether it is easible to locate allabove ground structures proposed at phasetwo consultation within the HammersmithPumping Station building or compound,with the exception o minor structures.

    6.1.14 We will also continue to engage with thedevelopers o Hammersmith Embankment/Fulham Reach site to ensure that our proposalscan be accommodated with their proposalsor this site.

    6.1.15 In our Statement of community consultationwe recognised that we may need to amendour scheme ollowing phase two consultationand that i changes came orward we wouldconsider whether targeted consultation isappropriate. We do not consider that thedegree o change in relation to this site or theeect on the local community would aectthe nature o the comments received duringphase two consultation in such a way as torequire urther consultation. On that basis,

    a round o targeted consultation on ourproposals or this site is not considerednecessary. We will progress with preparationo our application or a development consentorder and will incorporate the changes reerredto in paragraphs 6.1.13-14 i urther workdemonstrates that this is appropriate. Weintend to publicise our proposed applicationin accordance with Section 48 o the PlanningAct 2008 later in 2012. Full details o ourproposed scheme will be set out in our DCOapplication and accompanying documents.

    7. Barn Elms

    7.1.1 We are proposing to use the south easterncorner o the Barn Elms Schools Sports Centreor our construction works and toaccommodate the permanent structures

    required to operate the main tunnel. The sitewould be used to connect the existing localCSO, known as the West Putney Storm RelieCSO, to the main tunnel.

    Number o respondents

    7.1.2 A total o 387 respondents provided commentson Barn Elms. The respondents comprised:

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    19/74

    17

    Key:

    Statutory consultees Local authorities Landowners

    Community consultees Petitions (0)

    Statutory consultees Local authorities

    Design Council CABE

    Consumer Council or Water

    English Heritage

    Environment Agency

    Greater London Authority

    London Borough oRichmond Upon Thames

    London Borough oWandsworth

    Table 7.1 Statutory consultees and local authorities

    who provided eedback on Barn Elms

    7.1.3 We note that a number o eedback commentswere received in relation to the use o this siteas a main tunnel drive site. These commentshave been reported in chapter 11, as they reerto the use o Barn Elms as an alternative maintunnel drive site to Carnwath Road Riverside.

    Feedback on the selection and use o ourpreerred site

    Site selection and alternative sites7.1.4 Main supportive and neutral eedback

    comments raised by respondents included:

    support or the use o the site

    support or the changes to the proposed use othe preerred site since phase one consultation;it would have less impact on the riverside andreduces the potential impacts on aboveground heritage assets, notable views and the

    community

    the site is a suitable size and/or has sucientcapacity to accommodate the proposals

    support or changes to the extent o thepreerred site since phase one consultation,in particular the move to locate this site awayrom the River Thames, resulting in a reductiono impacts on the Thames environment

    site should also be selected as a main tunneldrive site.

    7.1.5 Main objections, issues and concerns raisedby respondents included:

    object to use o the site/consider that the siteis unsuitable

    should use/consider an alternative site/thereare other more suitable alternative sites in thelocal area

    unclear that clear that West Putney StormRelie CSO needs to be connected to the maintunnel

    should not use greeneld sites/avoid sites inclose proximity to sensitive receptors includingthe Wetlands Centre, sites o special scienticinterest, primary schools and social housing.The use o browneld sites should be prioritised

    alternative site suggestions, included CarnwathRoad Riverside or alternative browneld sites.

    Barn Elms Exhibition

    374

    6

    2

    5

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    20/74

    Phase two consultation / Summary report 18

    Management o construction works7.1.6 Main supportive and neutral eedback

    comments raised by respondents included:

    supportive or the changes to the constructionprogramme since phase one consultation

    support or the use o screening duringconstruction

    temporary loss o open space is acceptable,as there would be minimal damage to thegreeneld site

    the preerred site is the least disruptive optionor the local community

    the proposals will ensure that the Thames Pathis kept open.

    7.1.7 Main objections, issues and concerns raisedby respondents included:

    concerns regarding proposed site access,including access through the sports elds andcommon land alongside the Beverley Brook

    provide an alternative construction trac routeto and rom the site

    concerns regarding noise, vibration, dust,dirt and air pollution arising rom constructionactivities and the eect o constructiontrac emissions on air quality and amenity

    restrict or limit working hours whenconstruction and related vehicles can accesslocal roads including at school opening andclosing times

    the construction programme is unclear, toolong and concerns regarding the duration oconstruction. The project should minimise the

    extent and duration o construction works.Permanent design and appearance

    7.1.8 Main supportive and neutral eedbackcomments raised by respondents included:

    the design/proposals are good

    support or design proposals as limited landtake, no ventilation towers, the opportunity orthe structures to become objects o interest.

    7.1.9 Main objections, issues and concerns raised

    by respondents included:

    consideration o the site design, includingthe scale o the permanent buildings andstructures, with a preerence or a design inthe orm o grass mounds

    concerns regarding uture maintenance o thehabitat wall/use o habitat walls

    the proposals are not in keeping with thenatural environment o Barn Elms and its localarchitecture. As currently proposed, the plans

    are too dominant and intrusive and should bereduced in scale. Proposals should be inkeeping with and blend into the character othe local area in order to minimise visual impact

    the design should incorporate appropriatescreening and landscaping.

    Management o operational eects7.1.10 Main supportive and neutral eedback

    comments raised by respondents included:

    the proposals will ensure that odour issatisactorily managed and mitigationproposed to address permanent air qualityand odour issues is satisactory

    support or eorts to minimise the long-termimpacts to biodiversity and secure improvements.

    7.1.11 Main objections, issues and concerns raisedby respondents included:

    the proposed site access is unsuitable and analternative could be provided, e.g QueenElizabeth Walk, which would reduce thepotential risk o vehicle accidents at thisrecreational site

    concerns regarding potential air quality andthat odour eects will be greater than thoseset out in the consultation material.

    Our view o the way orward

    7.1.12 We have received a range o eedback on our

    proposals or this site, including supportive andneutral comments and objections, issues andconcerns. We have taken all commentsreceived into account in accordance with therequirements o the Planning Act 2008.

    7.1.13 In light o the eedback that we have received,we believe that no new inormation has beenhighlighted that would change the conclusionso our site selection process to date. Barn Elmsthereore remains our preerred site to intercept

    the West Putney Storm Relie CSO.

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    21/74

    19

    7.1.14 The eedback we have received includeddetailed comments on the construction andoperational eects o the proposeddevelopment and the measures we proposeto reduce and manage those eects. Detailedcomments were also made on our proposals

    or the permanent design and appearanceo the site. Having regard to the eedbackreceived we are continuing to rene ourdetailed proposals or this site to improve thedesign and reduce the impacts on the localcommunity and environment. Currently weare considering the ollowing changes to thelayout and/or appearance o our proposals:

    an alternative site access road

    amendments to the scale and design o thepermanent structures.

    7.1.15 In our Statement of community consultationwe recognised that we may need to amendour scheme ollowing phase two consultationand that i changes came orward we wouldconsider whether targeted consultation isappropriate. We consider that the degree ochange and the eect on the local communitymay aect the nature o the comments madeduring phase two consultation as the changeswe are considering may aect a dierentsection o the community. On that basis, around o targeted consultation on our revisedproposals or this site will begin on 6 June 2012and close on 4 July 2012. Any commentsreceived in response to our targetedconsultation will be taken into account inpreparing our application or a developmentconsent order. We intend to publicise ourproposed application in accordance with

    Section 48 o the Planning Act 2008 laterin 2012. Full details o our proposed schemewill be set out in our DCO application andaccompanying documents.

    8. Putney Bridge Foreshore

    8.1.1 We are proposing to use the oreshore o theRiver Thames, to the west o Putney Bridge, or

    our construction works and to accommodatethe permanent structures required to operatethe main tunnel. The site would be used toconnect the existing local CSO, known as thePutney Bridge CSO, to the main tunnel.

    Number o respondents

    8.1.2 A total o 171 respondents provided commentson Putney Bridge Foreshore. The respondentscomprised:

    Key:

    Statutory consultees Local authorities Landowners

    Community consultees Petitions (0)

    Statutory consultees Local authorities

    Design Council CABE

    Consumer Council or WaterEnglish Heritage

    Environment Agency

    Greater London Authority

    Port o London Authority

    London Borough oWandsworth

    Table 8.1 Statutory consultees and local authorities

    who provided eedback on Putney Bridge Foreshore

    Feedback on the selection and use o ourpreerred site

    Site selection and alternative sites8.1.3 Main supportive and neutral eedback

    comments raised by respondents included:

    support or the use o the preerred site/proposed site is the most suitable location

    the preerred site is more suitable than anyalternative or shortlisted sites as it wouldcause less disruption to the local area andhas better access

    support or changes to the extent o thepreerred site since phase one consultation.

    6

    3

    161

    1

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    22/74

    Phase two consultation / Summary report 20

    8.1.4 Main objections, issues and concerns raisedby respondents included:

    opposition in principle to the use o anyoreshore structures along the tidal Thames,as this is likely to lead to a number o

    detrimental eects o food risk management,biodiversity and recreation

    concerns that the scale o eects on thelocal area and community resulting rom theselection o this site is unacceptable / has notbeen properly considered

    site selection should avoid sites adjacent to orcontaining heritage assets

    do not support changes to the extent o the

    preerred site since phase one consultation/donot support the specic location o the site

    query why shortlisted sites have not beenidentied

    alternative sites suggested, including Foreshore,adjacent to Putney Bridge and St MarysChurch and Carnwath Road Riverside.

    Putney Exhibition

    Management o construction works8.1.5 Main supportive and neutral eedback

    comments raised by respondents included:

    it is an improvement on the site layout shownat phase one consultation

    a temporary slipway will be installed giventhe prominence o river use at this location

    the site is a suitable distance away rom

    residential areas support or the proposed use o barges to

    transport materials; ewer barges will be usingPutney Bridge.

    8.1.6 Main objections, issues and concerns raisedby respondents included:

    the temporary slipway must be appropriateor the vessels using it and should be realignedby 180 degrees and moved eastwards o the

    existing hardstanding outside Chas Newensacility

    Putney Drawdock needs to be retained withthe acility to allow vessels to load alongsideduring construction; the alternative o includingWatermans Green in the site compound wouldminimise temporary encroachment into theRiver Thames

    explore alternative methods o abrication

    the eect o construction lighting on qualityo lie

    concerns regarding dust, dirt, noise, vibrationand general air pollution eects arising romconstruction activities and the eect oconstruction trac emissions on air qualityand residential amenity given the proximityto residential properties

    at our years, the construction programmeis too long

    the eect o construction activities on localheritage and listed structures

    the eect on river navigation and recreationalriver users (including the impact on the boatrace and other events) and the eect o bargemovements on river navigation and leisureriver users

    concerns regarding potential structuraldamage including to Putney Whar

    use river to transport more/all constructionmaterials and spoil.

    Permanent design and appearance8.1.7 Main supportive and neutral eedback

    comments raised by respondents included:

    support or the design proposals

    there is a good appreciation o the uniquecharacter o this site and the design recognisesits current role as a place o gathering

    the decision to site the promontory upstreamrom the bridge has allowed the slipway tobe retained; support the simple, orthogonalgeometry o its design

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    23/74

    21

    the idea o a permanent whar betweenPutney Pier and Putney Bridge is a good one.

    8.1.8 Main objections, issues and concerns raisedby respondents included:

    the proposals are not in keeping with/do not

    enhance and/or will have a negative eect onthe character or appearance o the local area

    the structure(s) within the oreshore o theRiver Thames are too large/there should beno structures in the oreshore

    object to attaching a second column to PutneyBridge; a metre high wall juxtaposed with theslipway is unacceptable

    the size o permanent buildings and structures

    should be reduced.

    Management o operational eects8.1.9 The main supportive and neutral eedback

    comment raised by respondents was thatthe proposals would ensure that odour issatisactorily managed.

    8.1.10 The main objection, issue and concern raisedby respondents was in relation to the eecto odour and air quality arising rom theoperation o the tunnel upon residentialamenity.

    Our view o the way orward

    8.1.11 We have received a range o eedback onour proposals or this site, including supportiveand neutral comments and objections, issuesand concerns. We have taken all commentsreceived into account in accordance withthe requirements o the Planning Act 2008.

    8.1.12 In light o the eedback that we have received,we believe that no new inormation has beenhighlighted that would change the conclusionso our site selection process to date. PutneyBridge Foreshore thereore remains our preerredsite to intercept the Putney Bridge CSO.

    8.1.13 The eedback we have received includeddetailed comments on the constructionand operational eects o the proposeddevelopment and the measures we propose

    to reduce and manage those eects.Detailed comments were also made on ourproposals or the permanent design andappearance o the site. Having regard to theeedback received we are continuing to rene

    our detailed proposals or this site to improvethe design and reduce the impacts on the localcommunity and environment. Currently weare considering the ollowing changes to thelayout and/or appearance o our proposals:

    improvements to the permanent design andlayout o our proposals, specically the locationo the permanent works and the shape o theoreshore structure

    the nature and location o the temporaryreplacement slipway

    whether it would be possible to make urtheruse o the river or the transport o shat andshort tunnel excavated materials in order toreduce the number o lorries on local roads.

    8.1.14 In our Statement of community consultationwe recognised that we may need to amendour scheme ollowing phase two consultationand that i changes came orward we wouldconsider whether targeted consultation isappropriate. We consider that the degree ochange and the eect on the local communitymay aect the nature o the comments madeduring phase two consultation as the changeswe are considering may aect a dierent

    section o the community. On that basis,a round o targeted consultation on our revisedproposals or this site will begin on 6 June 2012and close on 4 July 2012. Any commentsreceived in response to our targetedconsultation will be taken into account inpreparing our application or a developmentconsent order. We intend to publicise ourproposed application in accordance withSection 48 o the Planning Act 2008 laterin 2012. Full details o our proposed scheme

    will be set out in our DCO application andaccompanying documents.

    9. Dormay Street

    9.1.1 We are proposing to use land o DormayStreet or our construction works and toaccommodate the permanent structures

    required to operate the main tunnel. The sitewould be used to connect the existing localCSO, known as the Frogmore Storm Relie Bell Lane Creek CSO, to the main tunnel.This site would also be used to drive a long

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    24/74

    Phase two consultation / Summary report 22

    connection tunnel (known as the Frogmoreconnection tunnel) southwards to KingGeorges Park and northwards to CarnwathRoad Riverside, to connect the CSOs atDormay Street and King Georges Park tothe main tunnel

    Number o respondents

    9.1.2 A total o 19 respondents provided commentson Dormay Street. The respondents comprised:

    Key:

    Statutory consultees Local authorities Landowners (0)

    Community consultees Petitions (0)

    Statutory consultees Local authorities

    Design Council CABE

    Consumer Council or Water

    English Heritage

    Environment Agency

    Greater London Authority

    London Borough oWandsworth

    Table 9.1 Statutory consultees and local authorities

    who provided eedback on Dormay Street

    Feedback on the selection and use o ourpreerred site

    Site selection and alternative sites9.1.3 Main supportive and neutral eedback

    comments raised by respondents included:

    support or the identication o a newpreerred site since phase one consultation/thepreerred site is more suitable than the site put

    orward at phase one consultation

    support or the use o site/Dormay Streetis the most suitable site

    qualied support subject to suitablearrangements being put in place with theLondon Borough o Wandsworth to managethe impacts on the councils depot.

    9.1.4 Main objections, issues and concerns raised

    by respondents included: One o the shortlisted sites is more suitable;

    qualied support or shortlisted LondonBorough o Wandsworth Depot (site 2); it hasslightly greater archaeological potential thanthe preerred site, but will otherwise have asimilar impact on heritage assets

    Management o construction works9.1.5 No main supportive or neutral eedback

    comments, as dened in paragraph 1.1.7,

    were received.

    9.1.6 Main objections, issues and concerns raisedby respondents included:

    use the river rather than road to transportconstruction materials and spoil, includingconsolidation centres at nearby barge/railserved sites or Smugglers Way Whar.Investigate the potential or transhipmentrom sites with no proposed barge movements

    proposals will result in river erosion and scourassociated with any piling required to constructa Bailey Bridge to span across Bell Lane Creek

    minimise scour eects by either avoidingin-channel structures which reduce conveyanceand/or adversely aect hydraulics. I thisis not possible, then any structures should beminimised to reduce impact, rather thanrelying on mitigation through hard engineeringtechniques such as gabions

    need to agree modications to the design othe Dormay Street/Armoury Way junction.

    Permanent design and appearance9.1.7 No main supportive or neutral eedback

    comments, as dened in paragraph 1.1.7,were received.

    9.1.8 The main objection, issue and concern raisedby respondents was the need to improve orcreate new ootpaths and cycle ways as part o

    the design, including a new riverside walk (4mwide) on the south side o Bell Lane Creek tothe Causeway Island.

    13

    1

    5

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    25/74

    23

    Management o operational eects9.1.9 The main supportive and neutral eedback

    comment raised by respondents was supportor the eorts to minimise the long-termimpacts to biodiversity and secureimprovements.

    9.1.10 No main objections, issues or concerns, asdened in paragraph 1.1.7, were receivedobjections, issues and concerns were raised:

    Our view o the way orward

    9.1.11 We have received a range o eedback on ourproposals or this site, including supportiveand neutral comments and objections, issuesand concerns. We have taken all comments

    received into account in accordance with therequirements o the Planning Act 2008.

    9.1.12 In light o the eedback that we have received,we believe that no new inormation has beenhighlighted that would change the conclusionso our site selection process to date. DormayStreet thereore remains our preerred site tointercept the Frogmore Storm Relie Bell LaneCreek CSO and drive the Frogmore connectiontunnel southwards to King Georges Park andnorthwards to Carnwath Road Riverside, toconnect the CSOs at Dormay Street and KingGeorges Park to the main tunnel. Additionally,no new inormation or issues have beenidentied that would undamentally changeour proposals or this site. Thereore we willcontinue to develop the proposals or this sitethat we published at phase two consultation.

    9.1.13 The eedback we have received includeddetailed comments on the construction andoperational eects o the proposed

    development and the measures we proposeto reduce and manage those eects. Detailedcomments were also made on our proposalsor the permanent design and appearanceo the site. Having regard to the eedbackreceived we are continuing to rene ourdetailed proposals or this site to improve thedesign and reduce the impacts on the localcommunity and environment. Currently weare considering the ollowing changes to the

    layout and/or appearance o our proposals:

    relocating our permanent works, so that theyare set by back 4m rom Bell Lane Creek.This means that our proposals do notprejudice the potential uture developmento a riverside walkway

    redesigning our temporary bridge to removethe piles or supports in the Creek, so the bridgewill now have a clear span

    temporary junction improvements at ArmouryWay, Dormay Street and The Causeway toaccommodate construction trac.

    9.1.14 In our Statement of community consultationwe recognised that we may need to amendour scheme ollowing phase two consultationand that i changes came orward we would

    consider whether targeted consultation isappropriate. We do not consider that thedegree o change in relation to this site or theeect on the local community would aectthe nature o the comments received duringphase two consultation in such a way as torequire urther consultation. On that basis,a round o targeted consultation on ourproposals or this site is not considerednecessary. We will progress with preparationo our application or a development consentorder and will incorporate the changes reerredto in paragraph 9.1.13 i urther workdemonstrates that this is appropriate. Weintend to publicise our proposed applicationin accordance with Section 48 o the PlanningAct 2008 later in 2012. Full details o ourproposed scheme will be set out in our DCOapplication and accompanying documents.

    10. King Georges Park

    10.1.1 We are proposing to use the northern cornero King Georges Park or our constructionworks and to accommodate the permanentstructures required to operate the main tunnel.The site would be used to connect the existinglocal CSO, known as Frogmore Storm Relie Buckhold Road CSO, to the main tunnel via along connection tunnel, known as the Frogmore

    connection tunnel. We would need a worksite toreceive the Frogmore connection tunnel, whichwould be driven rom Dormay Street.

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    26/74

    Phase two consultation / Summary report 24

    Number o respondents

    10.1.2 A total o 40 respondents provided commentson King Georges Park. The respondentscomprised:

    Key:

    Statutory consultees Local authorities Landowners

    Community consultees Petitions (0)

    Statutory consultees Local authorities

    Design Council CABE

    Consumer Council or Water

    English Heritage

    Environment Agency

    Greater London Authority

    London Borough oWandsworth

    Table 10.1 Statutory consultees and local authorities

    commenting on King Georges Park

    Feedback on the selection and use o ourpreerred site

    Site selection and alternative sites

    10.1.3 Main supportive and neutral eedbackcomments raised by respondents included:

    support or the use o site/consider that KingGeorges Park is the most suitable site andreception site

    support or changes to the extent o thepreerred site since phase one consultation;the construction impact on the park hasbeen reduced.

    10.1.4 Main objections, issues and concerns raisedby respondents included:

    object to the use o the site/consider thatsite is unsuitable

    query why shortlisted sites have not beenidentied

    site selection should use/prioritise browneldsites/avoid greeneld sites and avoid sites inresidential and/or densely populated areas

    alternative site suggestions, included KimberRoad playing elds and Dormay Street.

    Management o construction works10.1.5 Main supportive and neutral eedback

    comments raised by respondents included:

    support or the retention and replacemento trees; pleased that the black poplar willbe preserved

    the temporary loss o open space is acceptable.

    10.1.6 Main objections, issues and concerns raised byrespondents included:

    concerns regarding overnight/weekend/24-hour working hours/ construction seven daysa week and the eect on quality o lie

    concerns regarding dust, dirt, noise, vibrationarising rom construction activities andconstruction trac and the eect on qualityo lie and residential amenity

    concerns regarding the temporary losso public open space, which is a valuablerecreational amenity and is designated asMetropolitan Open Land, in an area thathas a shortage o public open space andprivate gardens.

    Permanent design and appearance10.1.7 No main supportive or neutral eedback

    comments, as dened in paragraph 1.1.7,were received.

    10.1.8 Main objections, issues and concerns raisedby respondents included:

    investigate the potential impacts on foodstorage in the park

    historic gates and railings should be protected,preserved and re-used in the park

    discussions need to take place regarding thepotential relocation o the park entrance to the

    corner o Buckhold Road and Neville Gill Close.The design team should anticipate how theproposals could accommodate such a move.

    29

    5

    5

    1

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    27/74

    25

    Management o operational eects10.1.9 The main supportive and neutral eedback

    comment raised by respondents was supportor the eorts to minimise the long-termimpacts to biodiversity and secureimprovements.

    10.1.10 Main objections, issues and concerns raisedby respondents included:

    access will be required to the lake outfowor weekly maintenance

    require level or level and volume or volumecompensation or any losses in the fuvialone per cent CC foodplain extent.

    Our view o the way orward

    10.1.11 We have received a range o eedback onour proposals or this site, including supportiveand neutral comments and objections, issuesand concerns. We have taken all commentsreceived into account in accordance with therequirements o the Planning Act 2008.

    10.1.12 In light o the eedback that we have received,we believe that no new inormation has beenhighlighted that would change the conclusionso our site selection process to date. KingGeorges Park thereore remains our preerredsite to intercept the Frogmore Storm Relie Buckhold Road CSO and receive theFrogmore connection tunnel, which wouldbe driven rom Dormay Street. Additionally,no new inormation or issues have beenidentied that would undamentally changeour proposals or this site. Thereore we willcontinue to develop the proposals or this sitethat we published at phase two consultation.

    10.1.13 The eedback we have received includeddetailed comments on the constructionand operational eects o the proposeddevelopment and the measures we proposeto reduce and manage those eects. Detailedcomments were also made on our proposalsor the permanent design and appearance othe site. Having regard to the eedbackreceived and taking account o ongoingtechnical work, we are considering our detailed

    design or this site which may lead to changesto the layout and/or appearance o ourproposals.

    These would improve the design and reducethe impacts on the local community andenvironment. Currently we are considering theollowing changes to our proposals or this site:

    incorporation o food alleviation measures

    creating new pedestrian entrances to thenorth, west and/or east o our proposed sitewhich enables us to reduce the extent ohardstanding at the existing entrance toKing Georges Park and replace it with newsot landscaping

    how we can re-use the existing historic gateswithin the park.

    10.1.14 We are also continuing to develop our detailed

    landscaping proposals or this site, inconsultation with our stakeholders.

    10.1.15 In our Statement of community consultationwe recognised that we may need to amendour scheme ollowing phase two consultationand that i changes came orward we wouldconsider whether targeted consultation isappropriate. We do not consider that thedegree o change in relation to this site or theeect on the local community would aectthe nature o the comments received duringphase two consultation in such a way as torequire urther consultation. On that basis,a round o targeted consultation on ourproposals or this site is not considerednecessary. We will progress with preparation oour application or a development consentorder and will incorporate the changes reerredto in paragraphs 10.1.13 -14, i urther workdemonstrates that this is appropriate. Weintend to publicise our proposed application in

    accordance with Section 48 o the PlanningAct 2008 later in 2012. Full details o ourproposed scheme will be set out in our DCOapplication and accompanying documents.

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    28/74

    Phase two consultation / Summary report 26

    11. Carnwath Road Riverside

    11.1.1 We are proposing to use the land to the southo Carnwath Road and in the oreshore o the

    River Thames or our construction works and toaccommodate the permanent building andstructures required to operate the main tunnel.The site would be used to drive the main tunnelto Acton Storm Tanks and receive the maintunnel rom Kirtling Street. We would also needa worksite to receive a long connection tunnel,which would be driven rom Dormay Street andknown as the Frogmore connection tunnel.This will connect the existing local CSOs atDormay Street and King Georges Park to the

    main tunnel rom the site at Dormay Street.

    Number o respondents

    11.1.2 A total o 3,138 respondents providedcomments on Carnwath Road Riverside.The respondents comprised:

    Key:

    Statutory consultees Local authorities Landowners

    Community consultees Petitions

    Statutory consultees Local authorities

    Design Council CABE

    Consumer Council or Water

    English Heritage

    Environment Agency

    Greater London Authority

    London CouncilsPort o London Authority

    London Borough oHammersmith and Fulham

    London Borough o RichmondUpon Thames

    London Borough oWandsworth

    Table 11.1 Statutory consultees and local authorities

    who provided eedback on Carnwath Road Riverside

    Feedback on the selection and use o ourpreerred site

    Site selection and alternative sites11.1.3 Main supportive and neutral eedback

    comments raised by respondents included:

    support or the use o the preerred site

    support or the identication o a newpreerred site since phase one consultation/thepreerred site is more suitable than the site putorward at phase one consultation

    the site is a browneld site which is vacant/derelict/available or redevelopment.

    11.1.4 Main objections, issues and concerns raised byrespondents included:

    object to the use o site/consider that the site isunsuitable

    should use/consider an alternative site. Siteselection should avoid densely populated orresidential areas; site is close to sensitivereceptors, including schools and nurseries,commercially established areas

    selection o this preerred site has been poorlyjustied/inadequately explained or is fawed/

    questionable. Reasons included: the impact ouse o this site has been underestimated andwould cost too much

    the scale o eects on the local area andcommunity resulting rom the selection o thissite is unacceptable

    the preerred site put orward at phase oneconsultation, Barn Elms, is more suitable as itwould have less impact on the local area andwould enable CSO interception and tunnelling

    activities to be undertaken at the same site.The reasons or changing the preerred sitesince phase one consultation are unclear

    the site is too small and does not havesucient capacity to accommodate theproposals

    site selection has been infuenced by pressurerom politicians, celebrities and Non-Governmental Organisations

    alternative site suggestions, included Barn Elmsand Kirtling Street/Battersea Power Station/Nine Elms/Battersea.

    3,105

    21

    3

    7

    2

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    29/74

    27

    impact o the proposals on the regenerationopportunity at Fulham Riverside.

    Management o construction works

    11.1.5 Main supportive and neutral eedbackcomments raised by respondents included:

    impacts on air quality will be less severebecause the site is already located on abusy road

    the site will have less environmental/ecologicalimpact and will result in ew/ewer treesbeing lost

    the preerred site is the least disruptive optionor the local community

    the impact o the eects has been properlyaddressed as part o the phase twoconsultation

    the proposals will improve the image andcharacter o the area.

    Carnwath Road Exhibition

    11.1.6 Main objections, issues and concerns raised by

    respondents included:

    concerns regarding the duration oconstruction and working hours, including lightpollution given 24-hour works at this site andthe eect on residential amenity and health

    concerns regarding noise and vibration romconstruction works in a residential area andeects on amenity and health given theproximity o the works to neighbouring

    residents and schools in terms o disruption concerns regarding the eects on the

    regeneration o the local area, including thepotential or redevelopment o the site and theeects on local businesses, economy and jobs

    concerns regarding potential landcontamination and potential or health eects

    construction trac will exacerbate existingcongestion and aect access to amenities andresidential amenity. Local roads are unsuitable

    or use by construction vehicles and concernsregarding the eect o trac on residentialamenity and the saety o other road users,including children, pedestrians and cyclists.

    Permanent design and appearance

    11.1.7 No main supportive and neutral eedbackcomments, as dened in paragraph 1.1.7, werereceived.

    11.1.8 The main objection, issue and concern raised

    by respondents relates to the scale and designo the proposed above ground structures,including the ventilation columns, and theeect on the surrounding area.

    Management o operational eects11.1.9 Main supportive and neutral eedback

    comments raised by respondents included:

    the proposals will ensure that odour issatisactorily managed and mitigationproposed to address permanent air quality

    and odour issues is satisactory

    not concerned by the permanent relocationo Carnwath Road Industrial Estate

    the proposals will improve the image andcharacter o the area.

    11.1.10 Main objections, issues and concerns raisedby respondents included:

    concerns regarding odour rom the operationo the tunnel and the eect on residential

    amenity and quality o lie

    the visual eect o permanent buildings andstructures on the character o the local areaand the eect on uture regeneration o thewider area.

    Our view o the way orward

    11.1.11 We have received a range o eedback on ourproposals or this site, including supportive

    and neutral comments and objections, issuesand concerns. We have taken all commentsreceived into account in accordance with therequirements o the Planning Act 2008.

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    30/74

    Phase two consultation / Summary report 28

    11.1.12 In light o the eedback that we have received,we believe that no new inormation has beenhighlighted that would change the conclusionso our site selection process to date. CarnwathRoad Riverside thereore remains our preerredsite to drive the main tunnel to Acton Storm

    Tanks and receive the main tunnel rom KirtlingStreet; and to receive the Frogmore connectiontunnel, driven rom Dormay Street. Additionally,no new inormation or issues have beenidentied that would undamentally changeour proposals or this site. Thereore we willcontinue to develop the proposals or this sitethat we published at phase two consultation.

    11.1.13 The eedback we have received includeddetailed comments on the construction and

    operational eects o the proposeddevelopment and the measures we propose toreduce and manage those eects. Detailedcomments were also made on our proposalsor the permanent design and appearance othe site. Having regard to the eedbackreceived we are continuing to rene ourdetailed proposals or this site to improve thedesign and reduce the impacts on the localcommunity and environment. Currently we areconsidering the ollowing changes to thelayout and/or appearance o our proposals:

    replacement o the proposed ventilationbuilding with a smaller an structure and lters

    relocation o the permanent above groundstructures to the eastern side o Whin Wharwhere they will provide a buer to thesaeguarded Hurlingham Whar, and areduction in the height o these buildings toapproximately 3.5 metres

    relocation and redesign o the ventilationcolumn so it is also located at the eastern edgeo Whin Whar and by the river

    provision o an area o landscaped open spacein part o the western section o the site with ariverside walkway

    whether it would be possible to make urtheruse o the river or the import o sand andaggregates or secondary tunnel lining in order

    to reduce the number o lorries on local roads.

    11.1.14 In our Statement of community consultationwe recognised that we may need to amendour scheme ollowing phase two consultationand that i changes came orward we wouldconsider whether targeted consultation isappropriate. We do not consider that the

    degree o change in relation to this site or theeect on the local community would aectthe nature o the comments received duringphase two consultation in such a way as torequire urther consultation. On that basis,a round o targeted consultation on ourproposals or this site is not considerednecessary. We will progress with preparation oour application or a development consentorder and will incorporate the changes

    reerred to in paragraph 11.1.13, i urther workdemonstrates that this is appropriate. Weintend to publicise our proposed application inaccordance with Section 48 o the PlanningAct 2008 later in 2012. Full details o ourproposed scheme will be set out in our DCOapplication and accompanying documents.

    12. FalconbrookPumping Station

    12.1.1 We are proposing to use our existing pumpingstation and adjacent disused toilet block orour construction works and to accommodatethe permanent structures required to operatethe main tunnel. The site would be used toconnect the existing local CSO, known as theFalconbrook Pumping Station CSO, to the maintunnel.

    Number o respondents12.1.2 A total o 22 respondents provided comments

    on Falconbrook Pumping Station site. Therespondents comprised:

  • 7/31/2019 Summary Report on Phase Two Consultation_FINAL

    31/74

    29

    Key:

    Statutory consultees Local authorities Landowners (0)

    Community consultees Petitions (0)

    Statutory consultees Local authorities

    Design Council CABE

    Consumer Council or Water

    English Heritage

    Greater London Authority

    London Borough oWandsworth

    Table 12.1 Statutory consultees and local authorities

    who provided eedback on Falconbrook Pumping

    Station Riverside

    Feedback on the selection and use o ourpreerred site

    Site selection and alternative sites12.1.3 Main supportive and neutral eedback

    comments raised by respondents included:

    support or the identication o a newpreerred site since phase one consultation.

    The preerred site is more suitable because ithas ewer impacts and enables theredevelopment o Bridges Court Car Park

    agree that Falconbrook Pumping Station CSOneeds to be intercepted, and that theFalconbrook Pumping Station site is a suitablelocation rom which to do so

    the site is already an operational ThamesWater site/is owned by Tham