- 1 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

IEEE

Substation Committee

K2 TF1 of the GIS Subcommittee

GIS/GIL/SF6-Tutorials

Page 2: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 2 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

IEEE

Gas Insulated Switchgear (GIS)

Design and Development

Page 3: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 3 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Introduction to GISTypical Air Insulated Substation 345/230/115kV

Page 4: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 4 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Introduction to GISTypical Gas Insulated Substation 345/115kV

Page 5: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 5 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Introduction to GISCable Feeder Unit

Mechanism Housing

Page 6: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 6 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Introduction to GISDimension ComparisonGIS Technology

SF6 used as the Insulating Media

Reduced Clearances- 345 kV AIS 4.6 m (15 feet)- 345 kV GIS 380 mm (15 inches)

Page 7: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 7 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Introduction to GISView into Bus Bar: Conductor/Enclosure Dimension

Page 8: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 8 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Introduction to GISClassic Single Phase Enclosure of GIS

CableConnection

DisconnectorCurrent TransformerCircuit Breaker

Busbar DisconnectorCurrent TransformerCircuit Breaker

Page 9: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 9 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Introduction to GISMidway Sunset Sunoco Cogen 242 kV GIS

4

242 kV

2000 A

40 kA

No. of breakers

Rated voltage

Rated current

Rated short-circuit current

1988Supply year

Page 10: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 10 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Introduction to GISAdvanced Three Phase GIS 72.5 to 145 kV

Page 11: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 11 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Design Features

GIS technology: compact, low-life cycle cost andmodular for indoor and outdoor applications

Modular Design,Factory pre-assembled and tested units

Space requirement less than 20 % of comparable AIS

Safety (enclosed energized components)

Continous Monitoring of SF6 Densitity

Sealed for Operating Life > 50 years

Major inspection: not before 25 years 1)

1) Is influenced by the operation duties

Page 12: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 12 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Design Features

GIS technology: compact, low-life cycle cost andmodular for indoor and outdoor applications

Corrosion-resistant

Low fault-probability / high availability

Protected against aggressive environmental conditions

Seismic resistant

Low EMF and susceptibility to EMC

Page 13: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 13 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Design FeaturesSpace Savings

Space Reductionappr. 70 %

Previous

Afterwards

Retrofit of an existing AIS

Substation byCompact

Substation

145 kV/31,5 kA, 4000 A

Page 14: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 14 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Design FeaturesModular Structure

Page 15: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 15 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

IEEE

Gas Insulated Switchgear (GIS)

History

Page 16: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 16 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Steps of DevelopmentMore than 40 Years of Experience

• 1960 : Start of fundamental studies in research and development of SF6-technology

• 1968 : Delivery of first GIS

• 1974 : Delivery of first 420 kV GIL Gas-Insulated Busbar (GIL)

• 1976 : Delivery of first 550 kV GIS

• 1979 : Delivery of first 800 kV GIS

• 1995 : First 420 kV circuit-breaker with only one interruptingchamber per pole

more than 200.000 bay-years of operation

more than 20.000 bays in over 2.000 substations installed world-wide

Page 17: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 17 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Steps of DevelopmentEvolution of GIS Design

550 kV from1983345 kV from 1970

230 kV from 1995

Page 18: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 18 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Steps of DevelopmentProgress of GIS Development (145 kV)

0

10

20

30

40

50

60

70

80

90

100

110

68 70 72 74 76 78 80 82 84 86 88 90 92 94 96 98Year

[%]

Size of buildingSpace requirementShipping volume

Page 19: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 19 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

IEEE

Gas Insulated Switchgear (GIS)

Manufacturing

Page 20: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 20 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Manufacturing ProcessGIS Factory

Production of maincomponents:

Insulating Parts/Vessels/ Drive

Components

• Assembly(Clean area)

• Test Lab• Training Center

Page 21: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 21 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Manufacturing ProcessInsulating Parts: Cast Resin

preparationof electrodes

vacuumcasting

Page 22: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 22 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Manufacturing ProcessPrefabrication – Housings/Components (2)

TestingPressure and Gas Tightness

Routine Test with Helium

Page 23: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 23 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Manufacturing ProcessGIS Hydro Static Factory Testing

Page 24: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 24 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Manufacturing ProcessPreassembly – Interrupter Units

PreassemblyExample:

GIS-interrupter unit 420 kV

Page 25: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 25 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Manufacturing ProcessPreassembly – Hydraulic Drive Unit

Preassemblypreassembled and

pretested components

Example:• hydraulic drive for

GIS 420 kV

Page 26: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 26 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Manufacturing ProcessAssembly – Main Assembly Hall

Main Assemblycircuit-breakerand switchgear

assembly„clean room“

Example:• GIS Bays 245 kV

Page 27: Substation Committee K2 TF1 of the GIS Subcommittee …sites.ieee.org/pes-resource-center/files/2014/02/PESGM2006P-000434.… · Substation Committee K2 TF1 of the GIS ... Gas Insulated

- 27 -

IEEE/PES Substation Committee - GIS Subcommittee

GIS

IEEE/PES Substation Committee - GIS Subcommittee

Thank you for your attention!

Any Questions?