Upload
hoangdan
View
214
Download
0
Embed Size (px)
Citation preview
Study on Private-Initiative Infrastructure Projects
in Developing Countries in FY2007
Study on Coal-fired Thermal Power Projects in Southern
Vietnam
SUMMARY
March 2008
Electric Power Development Co.,Ltd.
(J-POWER)
1 Background of the Project
MP6 for developing power plants and transmission lines from 2006 to 2015 was approved by the
Prime Minister on the 18th of July in 2007. The MP6 is the power generation plan which was
drawn up to ensure the supply of electricity enough to meet the demand of electricity, which is
expected to increase at the annual rate of 17% (or 20%), based on the GDP growth of 8.5 to 9%
(or higher). To satisfy rapid electricity demand, many power stations, especially coal fired thermal,
will be developed near future.
And these electric power development projects will require an enormous amount of capitals, and
the MP6 may not probably be financially accomplished in the conventional way in which EVN
has developed most of the power projects planned in master plan. Therefore, the Vietnamese
government expects to entrust the development of power plants to the other state owned
companies, the joint stock companies between EVN and the other state owned companies, or
foreign companies.
The development of coal-fired thermal power plant projects will be promoted in the south part of
Vietnam. The sites have been presented in the MP6. In these power plant sites, however, the site
conditions, especially port conditions are not favorable at all as, if coal imports are supposed. In
the other words, it is considered that the construction of breakwater dams and the development of
ports such as dredging navigation channel are more or less required at each of the coal-fired
thermal power plant sites in the south part of Vietnam, as selected in the MP6.
Thus, it is supposed that the coal-fired thermal power plant development plan in the south area
will require a great amount of capitals for port development projects such as the construction of
breakwater dams and dredging navigation channel. However, the power tariffs that are lower in
Vietnam than in the neighboring Southeast Asian countries may be a difficult obstacle that
prevents overseas companies from making investments in electric power generation projects.
To improve the environment where private companies can easily participate in the investment
projects for the construction of coal-fired thermal power plants in Vietnam, therefore, this survey
draws up the basic plan of coal center (C/C) and reviews the basic plan of combined electric
power plant and public port development investments in order to make recommendations on the
scheme to reduce the construction cost for common infrastructures including the related port
development projects, as included in the electric power tariffs, by the investments made by private
capitals in electric power plant projects as well as the construction of call centers in the same sites,
which is required for the electric power development in the south part of Vietnam.
Coal fired thermal power projects listed in 6th Master Plan are shown in below table.
2 Basic Approach of Project
Table 1 is development schedule on coal fired thermal power projects in southern Vietnam
Table 1 Development Schedule on Coal fired thermal power projects in southern Vietnam
Installed Capacity (MW) Project Phase Unit Owner
2011 2012 2013 2014 2015 2016 2017 2018
Vinh Tan I #1 CSG/BOT 600 I #2 CSG/BOT 600 II #1 EVN 600 II #2 EVN 600 III #1 EVN 1,000 III #2 EVN 1,000
Son My #1 BOO/BOT 600 #2 BOO/BOT 600 #3 BOO/BOT 600 #4 BOO/BOT 600
Tra Vinh I #1 EVN 600 I #2 EVN 600 II #1 EVN 600 II #2 EVN 600 III #1 EVN 1,000 III #2 EVN 1,000
Soc Trang I #1 EVN 600 I #2 EVN 600 II #1 EVN 600 II #2 EVN 600 III #1 EVN 1,000 III #2 EVN 1,000
Kien I #1 BOO/BOT 600 I #2 BOO/BOT 600 II #1 BOO/BOT 600 II #2 BOO/BOT 600 III #1 BOO/BOT 1,000 III #2 BOO/BOT 1,000
Source: MP6
Because there is no coal mine in southern Vietnam, basically importing coal from Indonesia,
Australia and others is considered as fuel for above power projects in southern area. Especially
Soc Trang project and Tra Vinh project cannot receive imported coal directly from overseas to
project site by large scale coal vessel due to topographical condition in that site. And so those
power stations need a coal center where imported coal is transshipped from large size vessels to
small size vessels.
In selecting a project site of coal center, we considered that Son My site has a possibility to
become one of the reasonable sites for coal center based on following criteria
In this study, we decided to drew up basic plan that coal center and power stations is developed at
same location in Son My
Criteria on site selection of coal center
− Close to power stations which are supplied with coal
− Located next to power stations or other industries
− Better port condition
3 Outline of Project
(1) Son My site
The Son My site has two original project sites: one is the site selected by EVN (PECC2) under the
MP6, and the other one is the alternative site recommended by the Binh Thuan province.
The chapter considers the optimal site position and the layout of the complex facilities by using
the currently available information from the viewpoints of the construction and operation of the
Complex considering the above original two sites.
Recommendation Site by BinhThuan Province
Original Site planned by EVN
Fig. 1 Original Project Site Planned by EVN and the Alternative Site Recommended by
Binh Thuan Province
(2) Outline of Coal Center
The coal center considered in this study will be designed to supply the Soc Trang and Tra Vinh
projects. Each has a planned power generation output of 4,400 MW for a combined total of 8,800
MW, which will require about 22.1 million tons of coal for power generation as shown below. If a
single coal center is to handle all such amount, various problems will occur: that is, limitations on
the vessels’ coal loading capacity for supply to power plants imposed by the draft limit set by the
Mekong (the Hau River), which situation would require a huge number of coal vessels to shuttle
between the coal center and power plants; such a large number of vessels and voyages would
make any ship and navigation management unrealistic for a port. Another problem would be the
centralization of coal center operations at one place, which will not be desirable from the
viewpoint of energy security. So we decided that the coal center under study should be of a size
that is capable of handling the amount of coal to cover up to Phase 2 of the Soc Trang and Tra
Vinh projects.
(3) Outline of Son My Power Plant
Son My Power Project has 4,400MW (or 3,600MW) capacity which consists of three phases. The
project is built by BOO/BOT project as coal-fired thermal power complex and will be operated
from 2012 annually. For the Son My power plant, it would be advisable to utilize the
once-through type of boiler with super-critical technology.
(4) Outline of Port Plan and Total Layout
The areas needed for the land facilities of the Complex are:
Power Plants: Approx. 70 to 80 ha (per one plant of 1,200MW to 2,000MW)
Coal Center: Approx. 80ha (30 days’ storage of coal for 4,800MW power plant)
Furthermore, big and deep sea port, which has about -15m depth, into which 70,000DWT coal
transportation vessel can enter is needed offshore. Based on the results of the above review, the
layout of the Complex can be planned as shown in Fig.2 and 3.
Fig. 2 Overall Layout of Son My Complex (Coal Center and Coal Thermal Power Station)
Fig. 3 Overall Layout of the Complex (Magnified View)
(5) Total Project Cost
(a) Funding Source
The scheme combined public funding project and private funding project, is explained as an
effective solution to develop larger scale infrastructure project, such as the project at Son My, with
enhancing private investment. The scheme in this report is that coal centre and common
infrastructure, such as port development and land reclamation, are developed by Vietnam
government, like EVN, with public fund such as ODA fund and, on the other hand, power stations
are developed by private fund based on BOT/BOO.
Table 2 shows an idea of funding source divided into public funding section and private funding
section.
Table 2 An idea of Funding by Public Part and Private Part
By Public fund By private fund Port facilities
− Dredging of Navigation Channel − Breakwater dam
Land reclamation − Revetment − Land filling − Common Road
Coal center facilities − Coal storage yard − Coal handling equipment − Coal loading equipment
Power Station (P/S) − Equipment of P/S − Coal storage yard (for P/S) − Coal handling equipment (P/S) − Coal unloading berth(for P/S) − Ash disposal yard − Road (for P/S)
(b) Total Project Cost
Table 3 is construction cost of public funding section
Table 3 Construction Cost of Public Funding Section (Unit: US$ mil)
Item Construction Cost
Port Development 270
Land Reclamation and Road 300
Coal Centre Facilities 400
Total 970
Table 4 and 5 is results of estimated construction cost.
Table 4 Estimated Construction Cost per kWh
Classification Super Critical
Civil and Building 220
Turbine and Balance of Plant 335
Boiler and Auxiliary of Boiler 550
Coal Feeder Facility 80
Measurement Facility 25
Generator and Electric Device 90
Total 1,300
Table 5 Construction Cost (600MW x 2 Units)
Classification Super Critical
Civil and Building 264,000
Turbine and Balance of Plant 402,000
Boiler and Auxiliary of Boiler 660,000
Coal Feeder Facility 96,000
Measurement Facility 30,000
Generator and Electric Device 108,000
Total 1,560,000
(6) Outline of Financial and Economic Study
This study considers Son My thermal power plant which is a target of private investments.
(a) Total Project Cost
Table 6 is the breakdown of the total project cost.
Table 6 Total Estimated Project Cost
Items Cost
EPC Cost US$ 1,560 mil.
Interest During Construction, Contingency, Development Cost, Others
US$ 470 mil.
Total US$ 2,030 mil.
(b) Fuel Cost
We have calculated the fuel cost by plant efficiency and current Indonesian coal price. We have
assumed the same inflation rate applied for other O&M cost.
(c) Operation and Maintenance cost other than fuel cost
Including the regular maintenance cost, we have assumed approximately 3% (including staff cost)
of the EPC cost as rough estimate for O&M cost per year.
Table shows the base case EIRR resulted (calculation made for 30year of operation period).
Table 7 Sensitivity of EIRR
Item Result
EIRR 15.00%
Table 8 shows result of sensitivities.
Table 8 Result of Sensitivities
Detail of sensitivities EIRR
Base case 15.00%
5% increase in O&M cost 14.81%
10% increase in O&M cost 14.61%
1.0% increase in interest rate 14.38%
5% increase in EPC cost 13.93%
5% increase in coal price 13.97%
By this analysis, we can understand that increase in EPC cost and coal price will give more
significant impact to the project economics, as compared to the increase in O&M cost. Action to
avoid cost overrun during the construction and appropriate measures for coal price fluctuation are,
therefore, essential.
(7) Environmental and Social Study
Following counter measures should be carried out for the environmental and social impacts due to
development and operation of a coal thermal power plant.
(a) Counter Measure for Emission Gas
Table 9 is standard emission value of the coal-fired thermal power plant.
Table 9 Standard Emission Value of the Coal-fired Thermal Power Plant
Item Criterion Regulation after K factor is corrected Son My Site (Designed)
NO2 (mg/m3N) 650 455 Less than 450 SO2 (mg/m3N) 500 350 Less than 350 SPM (mg/m3N) 200 140 Less than 50
Source: ENTEC Report
- NO2
It is considered that low-NOx burners can reduce the emissions of NOx to the level of
150-400 ppm
- SO2
It is estimated that these desulfurizers will be able to limit the emission at the outlet of a
chimney to the level of 103.6 – 207.2 mg/m3N (at the desulfurizing efficiency of 80 to 90%),
which satisfies the emission standard of 350 mg/Nm3.
- SPM
EP may limit the emissions of soot and dust at the EP outlet to the level of max. 180mg/m3N.
(b) Counter Measure for Waste Water
- Wastewaters from the power plant
To take the measures to improve the quality of wastewater from the power plant premises, it
is planned to provide the plants with the synthetic wastewater treatment equipment and the
circulation system to recycle the slurry water used for ash transfer. The general wastewater
such as rainwater will be treated in accordance with the national wastewater standards and
released into drainage canals.
- Cooling water
To release the cooling water used by condensers from the cooling water systems, it will be
necessary to take the appropriate measures against warm water and drained water. To
minimize the influences of the wastewater on the ecosystem in seawater areas, the
appropriate measures will be taken to keep the temperature difference between the taken
water and the released water below 7 °C.
(c) Counter measure for dispersion of coal dust
To prevent the dispersion of coal dust in the environment, it will be necessary to take the
appropriate measures using any water spraying equipment and wind barriers. When coal is
transported (by any means such as belt conveyer) in the projected power plant premises, it will be
also necessary to take the appropriate measures against the dispersion of coal dust and the drop of
coal. The Project plans to install shield fences, anti-dispersion equipment (such as sprinklers),
conveyor covers.
(d) Counter measure on vibration
The ordinary noises produced by heavy equipment such as generators and turbines may be
reduced to 65dBA around the boundaries of power plant sites by installing the equipment indoors.
The non-ordinary noises produced by devices such as safety valves may be reduced to a certain
extent by taking the appropriate measures using devices such as silencers or shields.
4 Project Implementation Schedule
Table 10 and Table 11 are Project Implementation Schedule.
Table 10 Preliminary Schedule
No. Item Start date End date Period
1 Engineering work (basic study, design concept
and financial model) 2008/10 2009/3 6 months
2 Pre Environmental Impact Assessment
(Pre-EIA) 2008/10 2009/3 6 months
3
Submission and provisional approval of the
Project by Ministry of Industry and Trade
(MIT) and Peoples Committee (PC)
2009/4 2009/6 3 months
4 Engineering work (detail) and EIA 2009/7 2010/3 9 months
5 Approval of Government and PC 2010/1 2010/6 6 months
6 Negotiation and signing of Power Purchase
Agreement (PPA) with EVN 2010/3 2011/2 12 months
7 Negotiation and signing of Coal Supply and
Transportation Agreement (CSTA) 2010/7 2010/12 6 months
8 Preparation, negotiation and signing of O&M
Agreement 2010/7 2010/12 6 months
9 EPC bidding, Negotiation and Agreements 2010/3 2011/2 12 months
10 Negotiation of Financing Models and
Agreements with Lenders 2010/4 2011/3 12 months
Table 11 Milestone of EPC Works Schedule
No. Item Start date Unit 1 Unit 2
1 EPC contract and design of the main EPC
work
Unit1: 2011/3
Unit2: 2011/9 0 month (Base)
2 Civil work and Piling works for power
house building work
Unit1: 2011/7
Unit2: 2012/1 4 months 10 months
3 Structural steel erection Unit1: 2012/8
Unit2: 2012/1217 months 23 months
4 Boiler Hydrostatic Unit1: 2013/11
Unit2: 2014/5 32 months 38 months
5 Power Receiving Unit1: 2014/2
Unit2: 2014/8 35 months 41 months
6 Boiler Initial Firing Unit1: 2014/8
Unit2: 2015/2 41 months 47 months
7 Initial Steam Admission to Turbine Unit1: 2014/10
Unit2: 2015/4 43 months 49 months
8 Synchronization and Commissioning Work Unit1: 2014/11
Unit2: 2015/5 44 months 50 months
9 Commercial operation date Unit1: 2015/3
Unit2: 2015/9 48 months 54 months
10 Final Certificate after two years
maintenance guaranteed period
Unit1: 2017/3
Unit2: 2017/9 72 months 78 months
5 Project Implementation Scheme
Fig 4 shows one of the expected project schemes in case of IPP project which foreign companies
can invest.
PORT OWNER(EVN/Coal Center)
* MOI : Ministry of Industry* EVN : Electricity of Vietnam* MOF : Ministry of Finance* JBIC : Japan Bank for International Cooperation
EVNP/S PROJECT OWNER
( Shareholders )
Japanese Co. Others
EPC Contract
Completion Guarantee
Power Purchase Agreement
Implementation AgreementImplementation Agreement
Reputable
Manufactures
Loan Agreement
Multilateral Financial Institutes
JBIC Loan Agreement
Commercial BanksLoan Agreement
MOI
Imported Coal
Companies
O&M
Government of Vietnam
Fuel Supply Agreement
O&M Contract
Government Related
Key Agreement
Guarantee
(Overseas Investment Loan)
Governmental Guarantee UndertakingIn-Direct Guarantee
Port Lease Agreement
JBICLoan Agreement
Yen Loan (ODA)Yen Loan (ODA)
Private Sector
Public Sector
Fig. 4 Project Implementation Scheme
The scheme shows that the project company which is established by Japanese companies and
other foreign companies or Vietnamese local companies, raises fund based on project finance
from JBIC, the export credit agencies, the multilateral development banks or other commercial
banks. And the company executes to construct and operates power station and earns profits by
wholesaling electricity generated from the power station to EVN.
Port uses pay the port administrative company the fee of port developed by public fund.
6 Technical Advantage of Japanese Company
(1) Participation as an Investor
It is estimated that the yearly growth rate of electricity demand in Vietnam is more than 17%. To
satisfy such rapidly increasing demand, it is necessary to reduce the time to develop the power
stations as possible. It is thought that PPP scheme, which combines public funds for building
common infrastructure and funds for constructing power plant, can contribute developing
effectively infrastructures in Vietnam. This report proposes the scheme which can execute the port
and coal center development in power project site by utilizing public funds.
(2) Participation as EPC contractor (Equipment supplier) and Port Constructor
Chinese boiler manufactures are recently expanding to overseas projects. But if the project
decides to use Indonesian and Australian coal for fuel, it is considered that Japanese boiler
manufactures have advantages to supply their equipment because only some Japanese and Korean
companies have track records to supply the boiler which can burn such type of coal and has been
operated for long term. This project requires quickly developing large and deep port which can
accept large coal vessels, and artificially reclaiming land from the sea. However there are not so
many projects of large port construction in Vietnam and Vietnamese local companies don’t have
much experience in such large scale port construction projects. From this point of view, it is
considered that Japanese construction companies which have much experience have advantages in
participating in such port construction.
(3) Participation as Operator
If the power project in Vietnam installs high technology like Super Critical technology, it is
expected that Japanese companies which have much experience to operate such high technology
plants have advantage to participate the project as plant operator. Japanese company also can
contribute Vietnam by utilizing simulator for coal fired thermal power plant.
(4) Participation as Coal Procurement
Vietnam has been a traditionally coal-exporting country, and has no experience in importing coal
from foreign countries. It means that the country lacks an appropriate means to procure coal in the
international market, and participating in the market as a newcomer will be extremely difficult.
On the other hand, Japan has many years of experience in importing steam or coking coal. As of
2005 Japan is the world’s greatest coal importer. Japanese companies should therefore be able to
help Vietnam procure coal worldwide.