STT rack space needs. educated guess of STT requirements. TC is asking for. a) How many U rack space do you need at the detector? b) How many U rack space do you need in the supply level (E10) and the DAQ/readout level (E20) of the counting house? - PowerPoint PPT Presentation

Citation preview

Page 1: STT rack space needs

STT rack space needs

educated guess of STT requirements

Page 2: STT rack space needs

TC is asking for

a) How many U rack space do you need at the detector?

b) How many U rack space do you need in the supply level (E10) and the DAQ/readout level (E20) of the counting house?

c) Do you need any equipment close to the detector in non-standard (non-rack) housings? At which minimal distance to your detector and with which dimensions?

The dead line to provide info is next TB in Bochum

Page 3: STT rack space needs
Page 4: STT rack space needs

STT numbers

xy-view

4636 Straw tubes arranged in planar layers (24-27)

Time readout (isochrone radius) drift time ~ 200 ns (B=2T) req. electronic resolution < 1 ns sensitivity (threshold) ~ 2 fC

Amplitude readout (energy loss) Straw tube capacitance: ~ 10-15 pF (9 pF/m) impedance: 373 Ώ inductance:1.24 μH/m Gas volume: ~ 1040 l mixture 90Ar + 10CO2

Page 5: STT rack space needs

Readout scheme

FE

DB

FEE anlog: • Preamp+ Shaper+ BLR + Discriminator Analog output needed for dE/dx measurement?

Digital Boards:

• Multihit TDC: Time measurement + TimeOverThreshold (TOT) for charge measurement OR/AND analog signal processing via FADC

• Zero suppression & Hit detection. Slow /Run/Data flow control

Data Concentration :

• gathering and sorting of hits marked by time stamps in epoques (i.e 500 s bunch)

• nGbit/s Optical serial link

Located on the STT

Located on racks outside

Page 6: STT rack space needs

FEE Boards

Tentative layout of FEE boards.Total # 592 includes some spare channel.

Cooling is not yet excluded.

Page 7: STT rack space needs

Digital+Concentration Boards

5x Lattice ECP3 150 FPGAs • 4 edge devices up to 60 TDC ch• 1 central for control • Flash ROMs for each

• 4x 208pin QMS connectors Small Addons

• 2x80pin connectors Large Addon (i.e. ADC)

24 TRBs will instrument all STT

These functions are implemented in TRBv3.

Which kind of Crates? 9U, 6U How many?

Page 8: STT rack space needs

HV system• Based on Wiener Mpod (8U) - universal multi-channel LV/ HV power supply

system- Controller with Ethernet, CANbus, USB interface, and interlock; - Web-ready and TCP/IP communication via SNMP,

OPC server;- LabView software support;- LV and HV modules freely combinable; - High Voltage modules (ISEG) with 8, 16, 32 channels

of from 500V to 10kV, floating or common ground; - Low Voltage floating modules with 8 channels of 10A /

50W max. with 8V, 16V, 30V, 60V ranges- PXI platform from National Instruments as I/O Controller- Embedded controllers with Intel CPUs, hard drive, memory, Ethernet, video, serial, USB, GPIB;- OS support: Windows, LabView Real-time, Linux;- more than 1500 PXI products (Multifun. DAQ, FPGA)

How much space?

Page 9: STT rack space needs

Slow ControlsARM-processors (CPU based on simplified instruction sets) will control different field points (gas/pressure controllers, temp. sensors, etc. )

Page 10: STT rack space needs

DCS and HV systemsRegarding rack space for the DCS and HV System:

- ethernet switch: 1 U- epics gateway server : 2U- NI PXI Crate: 4U- MPOD Bin: 9U________________total: 16U

Page 11: STT rack space needs

Cables and supply lines- The STT readout ASIC will provide LVDS differential outputs. - It will have 8 channels/chip and 2 control lines. Therefore for each chip we will

need a 10 pairs flat cable.Total # of flat cables is 296x2. These cables should be connected to patch-panels locate outside the magnet ~1240mmx1200mmx150mm - For the gas we foresee 24 gas supply lines, 224 gas pipes (in-/outlet).- We need also 40 HV cables.

- How many control lines for temperature and pressure? - Threshold setting and test pulses for FEE are already included?

Page 12: STT rack space needs

Timeline and Milestones• Prototype/Pre-series testing complete, production

readiness • Mass production• Ready for installation• Ready for beam (commissioning)

20142015-201620172018