If you can't read please download the document
Upload
hatram
View
219
Download
0
Embed Size (px)
Citation preview
STORMWATER MASTER PLANSTORMWATER MASTER PLAN
CITY OF FORT WALTON BEACHCITY OF FORT WALTON BEACH107 Miracle Strip Parkway SW107 Miracle Strip Parkway SW
Fort Walton Beach, FL 32548Fort Walton Beach, FL 32548
STORMWATER MASTER PLANSTORMWATER MASTER PLAN
FINAL DRAFTFINAL DRAFT
JULY JULY 20132013
1545 Raymond Diehl Rd, Suite 200
Tallahassee, Florida 32308
T: 850.222.0334 F: 850.561.0205
HMM Project No. 297786
TABLE OF CONTENTS
1
Section Page Number
1.0 Executive Summary.. 1
2.0 Introduction 4
2.1 Project Background.. 4
2.2 Goals and Objectives 4
3.0 Model Development. 7
3.1 Model Platform 7
3.2 Data Gap Identification.. 11
3.3 Model Construction.11
3.4 Basin Delineation 12
3.5 Hydrologic Model.. 14
3.6 Hydraulic Model.. 16
3.7 Water Quality... 17
4.0 System Flood Analysis. 18
5.0 Design Alternative Development 21
5.1 System Improvements Methodology.. 21
5.2 Proposed System Improvements .. 21
5.3 Conceptual Cost Estimates.. 46
5.4 Evaluation Matrix.. 48
5.5 Improvement Priority 50
6.0 Rehabilitation and Replacement. 52
7.0 Capital Improvements Plan (CIP).55
8.0 Funding and Recommendations.. 57
8.1 Funding. 57
8.2 Recommendations. 58
Appendix A HEC-RAS to InfoSWMM Conversion Methodology
Appendix B Data Gap Analysis Document
Appendix C Flood Analysis Document
Appendix D Maps
Appendix E HGL Profiles and Junction Graphs
Appendix F Project Conceptual Cost Estimates
Appendix G Project Evaluation Matrix
Appendix H Rehabilitation and Replacement Pipe List
EXECUTIVE SUMMARY
2
1.0 EXECUTIVE SUMMARY
This report presents the City of Fort Walton Beach Stormwater Master Plan. The report
describes the review and analysis of the Citys stormwater infrastructure conducted by Hatch
Mott MacDonald (HMM) and includes recommendations for improvements. The primary
objective of the study was to develop a document to be used as guidance for eliminating or
reducing flooding within the City in consideration of health and safety. A second phase of the
Master Plan will be completed at a later date which will address Water Quality.
A summary of the efforts undertaken to complete the master plan process is as follows:
The InfoSWMM modeling software was selected for use in this master planning effort, per HMMs recommendation to City staff, after evaluation of multiple software
platforms.
HMM reviewed the Citys GIS data and made recommendations to improve model performance and ease of data transfer.
Field work was performed by both HMM and City staff to obtain missing data identified by HMM.
The model was constructed to include inlets, junction boxes, drainage ditches, pipes that are 15-inches in diameter or larger, stormwater basins, and rainfall data for storm
events up to and including the 100 yr-24hr storm event.
The City of Fort Walton Beachs InfoSWMM stormwater system model represents a valid working model of the existing system as of May 2012 along with the proposed
improvements. All model entities are matched one-to-one with the Citys GIS, where
possible.
Initial flood analysis discovered flooding in several areas throughout the City.
System improvements, based on the 25-yr critical storm event, were proposed to increase the conveyance system capacity to eliminate or reduce system flooding.
A flood reduction analysis was performed to identify the percent of flood reduction that would be achieved during the 100-yr critical storm event based on completion of the
improvements to eliminate flooding during the 25-yr storm event.
A conceptual cost estimate was developed for the areas with proposed system improvements. The cost estimates include a 35% construction contingency and 10%
engineering & administration fee.
An evaluation matrix was created to establish priorities for each area of proposed improvement based on key criteria established by HMM and City staff.
A Rehabilitation and Replacement (R&R) analysis was completed on the existing stormwater conveyance system to determine maintenance priorities. The analysis
included pipe material, age, diameter, conflicts, and conceptual costs.
A 25 Year Capital Improvements Plan (CIP) was developed based on 5 year improvement periods and a budget of $500,000 per year.
EXECUTIVE SUMMARY
3
There are 85 recommended improvements which are identified and discussed in Section 5.2 of
this report. Also, a summary of the recommended improvements is provided in Table 7.1,
which is prioritized and includes estimated costs. Appendix H includes a spreadsheet for 2,360
pipe segments which have been prioritized for maintenance consideration. Recommendations
are provided in Section 8.0, which generally include:
1. Implement the proposed system improvements as identified in the Capital Improvement Plan (Table 7.1) as funding allows. The list of improvement projects is prioritized and
should be used as guidance. There are circumstances, such as change in conditions,
development, and property damage, which may justify a change in the order of
implementation.
2. Implement a maintenance program for the proposed rehabilitation and replacement of storm water pipe as identified in the Pipe Maintenance Schedule included in Appendix
H. The list of maintenance projects is prioritized and should be used as guidance. When
practical, the maintenance projects should be coordinated with other construction
projects to prevent an area from being damaged twice and to reduce construction cost.
3. Update the models physical data and operating scenario(s) to reflect evolving system
conditions and operating protocol(s). Consider including additional County and FDOT
stormwater data in the model as it becomes available.
4. Utilize the InfoSWMM software to include the Water Quality component of the
stormwater system. Use the water quality data to seek grant opportunities.
5. Develop a model maintenance guideline to ensure modifications are uniformly made to
the model by all whose use of the model is authorized by the City. This protocol should
also contain procedures to ensure the model is able to seamlessly update the Citys GIS
data as applicable, and vice-versa.
6. Update the stormwater master plan in five (5) year increments.
INTRODUCTION
4
2.0 INTRODUCTION
2.1 Project Background
The City of Fort Walton Beach is located in southern Okaloosa County, Florida. The City has a
population of approximately 19,500 people and includes a total area of 8.2 square miles
according to the United States Census Bureau. Of the 8.2 square miles, 7.4 square miles is land
and the remaining 0.8 square miles is water. The City limits are divided into two separate
sections with the area in between belonging to Okaloosa County. The southern area of the City
is generally located along the Gulf of Mexico and Cinco Bayou with elevations ranging from sea
level to elevation 40. The northern area of the City is generally located along Bass Lake and
Dons Bayou to the Lewis Turner Boulevard area with elevations ranging from sea level to
elevation 74. A map of the city limits is included as Figure 2.1.
During certain storm events, flooding occurs in areas along the coast, streams, and streets
within the City, resulting in flood damage that impacts homes and businesses. As the City
continues to develop, flood impacts will increase due to additional runoff generated as a result
of increased urbanization.
As a result of the flood impacts, the City decided to proceed with a stormwater master plan
development that would have specific goals and objectives in place to target and eliminate /
reduce flooding.
2.2 Goals and Objectives
This report describes the review and analyses conducted by Hatch Mott MacDonald (HMM) on
the Citys stormwater infrastructure. The primary objectives of the study include the following:
1. Develop a large scale hydraulic and hydrologic model of the existing stormwater
infrastructure.
2. Analyze the existing infrastructure during the 10, 25, 50, and 100 year critical storm
frequencies to identify areas prone to flooding.
3. Develop design alternatives, where practical, for the areas prone to flooding to
determine necessary improvements required.
4. Provide opinions of probable cost for each design alternative.
5. Evaluate each design alternative based on established ranking criteria for inclusion in
the Citys Capital Improvements Plan (CIP).
6. Develop a comprehensive stormwater master plan document.
INTRODUCTION
5
The original project goals were altered slightly based on software limitations within InfoSWMM.
Many of the goals focus upon flood levels. The base InfoSWMM software does not provide
actual flood levels outside of the conveyance system. Due to this limitation, HMM and the City
adjusted the goals to focus on eliminating flooding completely where practical and otherwise
reducing flooding as much as possible.
INTRODUCTION FIGURE 2.1
6
MODEL DEVELOPMENT
7
3.0 MODEL DEVELOPMENT
3.1 Model Platform
At the City of Fort Walton Beachs invitation, on October 13, 2011, representatives from
Bentley Systems, Inc., and Innovyze, Inc., made presentations showcasing the features of their
respective stormwater modeling applications:
Bentley: SewerGEMS
Innovyze: InfoSWMM and InfoWorks ICM
Based on the information relayed during the presentations, answers to follow-up questions by
representatives from each vendor, feedback from City staff, and HMMs experience with these
platforms, HMM developed a comparison summary (see Table 3.1) that lists the advantages
and disadvantages of each program.
MODEL DEVELOPMENT
8
TABLE 3.1
COMPARISON OF STORMWATER MODELING SOFTWARE
Bentley SewerGEMS, Innovyze InfoWorks ICM, Innovyze InfoSWMM
System Advantages Disadvantages
Client familiarity with Bentley productsManual mods to RTK tables required for
model calibration
Bentley's support and training programs
seem preferable to Client
Manual catchment/ sub-catchment
delineation required (via ArcGIS tools)
Bentley bundles other Haestad/ Bentley
products within SewerGEMS
Does not model sediment transport as
part of water quality analysis
More output graph features than those
contained in MS Excel2D flood boundary mapping not available
Scenario/ Alternative setup and
management is more intuitive (HMM's
experience)
No built-in tools for importing HEC-RAS
data files or transects
Capability to run in "stand-alone" mode
No additional licenses required by HMM
to perform project modeling
Includes 2D flood boundary mapping Most expensive alternative
Utilizes ArcGIS layers/ shapefiles for data
import
Manual mods to RTK tables required for
model calibration
Combines functionality of InfoWorks CS
and InfoWorks RS
Additional hardware requirements for
optimum performance (e.g., 64-bit, multi-
processor O/ S with GPU capability)
Marketed solely as "stand-alone" program
Built-in Sub-catchment Boundary
Delineation Manager (works with
ArcGIS' Spatial Analyst)
More cumbersome Active Facility/
Topology, and Data Set/ Alternative
management (HMM's experience)Available 2D module for flood boundary
mapping Requires user knowledgable of both
modeling & GIS (no "stand-alone" mode)
InfoSWMM Exchange Menu option for
direct import of HEC-RAS transect data2D module requires separate license/
maintenance agreement
Built-in sediment transport modeling
capabilities via Water Quality Simulation
Options
Innovyze has troublesome output Graph
Control Manager (HMM's experience), but
plans to upgrade in 2012
Built-in Calibrator extension No online training/ webinars offered
Bentley
SewerGEMS v8i SELECT Series 2 (for
ArcGIS v10)
* Includes the following InfoSWMM Suite Extensions: Calibrator, DWF Allocator, Designer, Conduit Storage Synthesizer,
Subcatchment Manager, Risk Assessment Manager. Includes the above InfoSWMM Suite Extensions plus these InfoSWMM ExecuOve Suite Modules: Pond Design
Manager, NetVIEW, RDII Analyst.
FEATURES
Innovyze
InfoSWMM Suite *
InfoSWMM Exec Suite
InfoSWMM 2D
(for ArcGIS v10)
Innovyze
InfoWorks ICM
("stand-alone" only)
MODEL DEVELOPMENT
9
Some key features of InfoSWMM which SewerGEMS currently lacked were noted as follows:
1. Calibrator extension
2. Sub-catchment boundary delineation tool
3. Sediment transport modeling capability
4. Rainfall Derived Infiltration Inflow (RDII) Analyst
The features of the Citys stormwater geodatabase can be mapped one-to-one for creating a
stormwater model in either InfoSWMM or SewerGEMS; this is not possible within InfoWorks
ICM, as this program runs strictly in stand-alone mode.
It should be noted that there was no completely automated method for importing Okaloosa
Countys existing HEC-RAS stormwater model data into any of these platforms; however, the
latest version of InfoSWMM will allow transects to be imported from a HEC-RAS geometry file.
This geometry file is generated via HEC-RAS using the output data from an applicable model
run. ArcGIS tools can then be used to generate a geodatabase mirroring the physical and
geometric characteristics of the existing HEC-RAS stormwater model (see Appendix A for
detailed HEC-RAS to InfoSWMM conversion methodology).
HMM also presented a matrix of costs associated with each potential software package and
combinations thereof as shown in Table 3.2. This matrix included costs for the software,
technical support by the software vendors, training programs offered by the software vendors,
and annual software license renewals.
Based on HMM review and discussions with City staff, it was recommended that the City of Fort
Walton Beach purchase Innovyzes InfoSWMM Executive Suite. HMM reviewed the Citys and
Countys stormwater geodatabases received to-date, and believed the 10,000-pipe version of
the software to be adequate for the Citys needs on the current project, as well as for
expanding the model to include the Countys stormwater infrastructure. HMM advised the City
to purchase the network license-based version, thereby ensuring a centralized location on the
Citys computer network for license maintenance, upgrades, etc.
The City ultimately purchased Innovyzes InfoSWMM Executive Suite 5,000-pipe version with
Okaloosa County agreeing to pay for the software upgrade to 10,000-pipes in the future to
include their stormwater data.
MODEL DEVELOPMENT
10
TABLE 3.2
License
Annual
Maintenance First Year's Cost* License
Annual
Maintenance First Year's Cost*
Bentley 5,000 $14,995 $3,600 $23,590 $14,995 $3,600 $23,590 "BentleyLEARN": $4,995 / annum (includes "on demand
SewerGEMS v8i SELECT Series 2 10,000 $19,995 $4,800 $29,790 $19,995 $4,800 $29,790 web-based training, unlimited 24/7 tech support, software
(for ArcGIS v9.3.1) Unlimited N/A N/A N/A N/A upgrades, & network licensing) SewerGEMS Course: $1,500 / person
5,000 $40,500 $6,075 $46,575 $44,550 $6,683 $51,233
10,000 $57,000 $8,550 $65,550 $62,700 $9,405 $72,105
Unlimited $60,000 $9,000 $69,000 $66,000 $9,900 $75,900
5,000 $22,000 $4,500 $26,500 $24,000 $6,750 $30,750
10,000 $29,000 $5,000 $34,000 $31,000 $7,500 $38,500
Unlimited $32,000 $5,500 $37,500 $34,000 $8,250 $42,250
First Year's Cost Annual Cost 4-yr Annual Cost Est. 5-yr Cost
Bentley SewerGEMS (10k pipes) $29,790 $9,795 $39,180 $68,970
Innozyve
InfoWorks ICM (10k junctions) $72,105 $9,405 $37,620 $109,725
RECOMMENDED SELECTION
Network Based License
InfoSWMM Exec Suite &
InfoSWMM 2D (10k pipes)$38,500 $7,500 $30,000 $68,500
Innovyze
InfoSWMM Exec Suite & 2D
(bundled)
No annual training subscipriton program; no online training /
webinars offered.
2-day workshops at Innovyze are $1,600 / person.
2-day workshops at a client's location cost $10,000 for eight (8)
persons max.
Licensing fees include all aoftware upgrades / updates.
** Includes the following InfoSWMM Suite Extensions: Calibrator, DWF Allocator, Designer, Conduit Storage Sythesizer, Subcatchment Manager, Risk Assessment Manager.
*** Includes the above InfoSWMM Suite Extensions plus these InfoSWMM Executive Suite Modules: Pond Design Manager, NetVIEW, RDII Analyst.
* SewerGEMS cost includes annual BentleyLEARN fee of $4,995.
$6,750 $38,750Innovyze
InfoSWMM Suite & 2DUnlimited (est.) $32,000
$5,250 $25,250
Innovyze
InfoSWMM 2DUnlimited (est.) $20,000 $3,000 $17,000
$18,000 $3,750 $21,750
Innovyze
InfoSWMM Exec Suite***Unlimited (est.) $20,000
Number of
Pipes / Nodes
Innovyze
InfoWorks ICM
Innovyze
InfoSWMM Suite**Unlimited (est.)
Fixed-seat License Floating Network License
Training
COMPARISON OF STORMWATER MODELING SOFTWARE
Bentley SewerGEMS, Innovyze InfoWorks ICM, Innovyze InfoSWMM
System
MODEL DEVELOPMENT
11
3.2 Data Gap Identification
Once the InfoSWMM software was selected and the most recent stormwater geodatabase
received, HMM began the process of reviewing the existing data for accuracy, missing
information, and compatibility with the selected software package. The review resulted in the
creation of the Data Gap Analysis document. The complete document is included in Appendix B
and a summary is as follows:
An identifier that is unique to each element was required prior to model creation to
allow data to be transferred between the model and GIS.
No existing drainage basins had been established.
Missing data was noted by element type and categorized as relevant or not relevant.
Object IDs were listed for relevant data necessary for model construction.
Areas with a long run of negative slopes were identified for the City to review for
accuracy.
Areas of City stormwater connection to County and FDOT systems were noted and
mapped.
Based on this document, the City completed additional fieldwork, updated the existing
geodatabase, and created the unique identifier for each element known as the Model ID. The
updated geodatabase was then used to begin the model construction process.
3.3 Model Construction
The InfoSWMM model platform is based within ArcGIS and allows for direct import of existing
GIS data using the GIS Gateway. The gateway allows the user to select the existing data to
import and map the necessary data fields in GIS to the corresponding field in InfoSWMM. The
critical element when using the gateway is having a unique identifier, in this case the Model ID,
for every element within GIS. Otherwise, InfoSWMM will create a unique model identifier and
the connectivity between GIS and the model is lost. The unique identifier allows for data to be
transferred from the model back to GIS and for model maintenance updates as additional
information becomes available.
After the data was imported from GIS, all non-essential elements were removed from the
model (i.e. pipes less than 15-inches in diameter, fittings, etc.). The drainage ditches and ponds
were added at this point based on cross-sections provided by the City and contour data. Minor
fieldwork was also completed by HMM to verify some of the pond outfall structures and ditch
cross-sections. Discharge points were then converted to outfalls with a high water tidal
MODEL DEVELOPMENT
12
elevation of 2-ft established based on conversations with City staff and National Oceanic and
Atmospheric Administration (NOAA) data.
The final step in the physical model construction process involved HMM verifying the model
connectivity. Minor connectivity errors were encountered such as pipes not connected to
nearby node, orphan nodes, and pipes connected in reverse. These errors were corrected using
the built in network review / fix toolbars within InfoSWMM.
3.4 Basin Delineation
A stormwater basin is a surface area that drains during a rainfall event to a point of interest
such as an inlet, culvert, or outfall to surface water or pond. Basin delineation is a critical step
in stormwater model development as it plays a large role in determining the amount of runoff
that enters a system. Surface runoff, in turn, is used to estimate the capacity remaining or
flooding within the conveyance system.
The stormwater basins were delineated for each inlet and drainage ditch in the model using
aerials and 1-ft contour data. InfoSWMM has the capability to create the basins; however, due
to topographic data limitations (i.e. lack of curb and gutter shots, etc) the basin boundaries had
to be created manually. The land use for each basin was then defined using existing GIS data
for use with future pollutant loading. A Curve Number (CN) was defined for each basin based
on land use category and percent impervious as shown in Table 3.3
MODEL DEVELOPMENT
13
TABLE 3.3
SCS RUNOFF CURVE NUMBERS
The basin areas were then tabulated automatically within InfoSWMM in square feet and
converted to acres. The slopes for each basin were calculated using a slope raster created using
the Spatial Analyst within ArcGIS and existing contour data. The longest length within each
basin was calculated manually based on basin boundaries, contours data, and street locations.
Based on the input data entered into each basin, the time of concentration was calculated
automatically by InfoSWMM. Finally, each basin was assigned to the corresponding inlet and
rain gages created using the Subcatchment Manager tool.
MODEL DEVELOPMENT
14
3.5 Hydrologic Model
Hydrologic models are simplified, conceptual representations of a part of the hydrologic cycle
shown in Figure 3.1 below. They are primarily used for hydrologic prediction and for
understanding hydrologic processes. This model includes precipitation, evaporation,
infiltration, and surface runoff.
FIGURE 3.1
HYDROLOGIC CYCLE
The precipitation portion of the model included rainfall intensity time series curves based on
FDOT rainfall distribution curves for the 10, 25, 50 and 100 year frequency storm events. As an
example, the 25yr-8hr rainfall distribution curve table is shown in Table 3.4. After review of the
1, 2, 4, 8, and 24 hour storm events for each frequency, in most cases the 8 hour storm was
determined to be the critical storm event based on flood duration and frequency within the
service area. A rainfall distribution curve was applied to each rain gage in the model prior to
each model simulation. The rain gages were located within each basin established within the
model.
MODEL DEVELOPMENT
15
TABLE 3.4
25YR-8HR RAINFALL DISTRIBUTION CURVE TABLE
8-HR RAINFALL (I = 0.94 IN/HR)
T (HRS) P/P TOTAL i/P TOTAL IDF 8-HR INTENSITY (IN/HR)
0.0 0.000 0.000 7.52 0.00
1.0 0.020 0.020 7.52 0.15
2.0 0.130 0.060 7.52 0.45
3.0 0.280 0.150 7.52 1.13
4.0 0.700 0.420 7.52 3.16
5.0 0.860 0.160 7.52 1.20
6.0 0.920 0.060 7.52 0.45
7.0 0.970 0.050 7.52 0.38
8.0 1.000 0.000 7.52 0.00
The evaporation was applied in the model as a constant rate based on local conditions under
the Climatology tab. This rate can also be modified for each individual storage area (pond) if
varying conditions exist.
Infiltration was included within each stormwater basin by defining a generic sand soil type
based on the USDA Soil Survey of the area. The total surface runoff from each basin was
calculated by the model based on the Curve Number assigned.
InfoSWMM offers the following ten options for modeling surface runoff from a stormwater
basin:
Nonlinear Reservoir each basin surface is treated as a nonlinear reservoir.
Colorado Urban Hydrograph Procedure uses procedures presented in the Colorado
Urban Drainage Criteria Manual of the Urban Drainage and Flood Control District.
NRCS (SCS) Dimensionless Unit Hydrograph commonly used with established Curve
Number (CN) values.
NRCS (SCS) Triangular Unit Hydrograph approximation of the dimensionless unit
hydrograph method that uses only three points.
Delmarva Unit Hydrograph used where local topography is flat and large amounts of
surface storage is available.
Snyder Unit Hydrograph relates lag time to geometric characteristics of the basin to
derive critical points for interpolating the unit hydrograph.
Clark Unit Hydrograph - derives a unit hydrograph by explicitly representing the
processes of translation and attenuation, which are the two critical phenomena in
transformation of excess rainfall to runoff hydrograph.
MODEL DEVELOPMENT
16
Espey Unit Hydrograph 10-minute unit hydrograph developed strictly for urban
watersheds.
Santa Barbara Urban Hydrograph Developed for Santa Barbara County and is suited
for urban applications.
San Diego Modified Rational Formula uses a 6-hour storm event for estimation of peak
flows from urban and rural drainage basins.
The widely used NRCS (SCS) Dimensionless Unit Hydrograph method was the one utilized for
this stormwater model as recommended by the software developer. This method utilizes curve
numbers and will also automatically calculate the time of concentration based on input data.
3.6 Hydraulic Model
Hydraulic models simulate the flow and conveyance of fluids, in this case stormwater, in order
to investigate design and operational issues. The results of a stormwater hydraulic model are
based on the amount of surface water runoff entering a system, the conveyance capacity,
conveyance slope, and pond storage capacity. The InfoSWMM model allows a system to be
analyzed over long periods of time following single or multiple storm events.
The hydraulic portion of the model begins once surface water flow from individual basins
enters the conveyance system following a storm event. The hydraulic model includes the flow
characteristics of the stormwater system such as flow, velocity, depth over diameter (d/D),
hydraulic grade line, inlet / ditch flooding, and pond storage capacity. Conveyance and storage
consisted of drainage ditches, inlets, piping, and ponds imported directly from GIS and
supplemented by additional field work.
The hydraulic model analysis was a result of the runoff generated from the hydrologic portion
of the model. The hydrologic model was based on theoretical storm events and not actual
measured rainfall. The results for various storm events were analyzed for areas of known flood
concern as provided by the City. The analysis confirmed that most of the areas of known flood
concern were also shown as flooding areas within the model. Meetings were held with City
staff to review the model output and the flood results were confirmed.
MODEL DEVELOPMENT
17
3.7 Water Quality
Stormwater runoff has both a quantity and quality component. Quantity is related to runoff
volume and duration of a storm event. Quality is related to the potential contaminants
contained within the runoff (water pollution).
This master plan deals solely with stormwater quantity in an effort to reduce or eliminate
flooding. The InfoSWMM model has been setup, to the extent possible, to include the quality
modeling component in the future by including land use characteristics within each drainage
basin. Water quality modeling will be completed in Phase 2 of the master plan and will be a
valuable tool to address the proposed rules regarding Total Maximum Daily Load (TMDL).
SYSTEM FLOOD ANALYSIS
18
4.0 SYSTEM FLOOD ANALYSIS
Following completion of the model development process, the simulations were completed and
the results reviewed to determine the extent of flooding up to and including the 100-yr storm
events. Maps and solution sets were created for the 8-hour event first since it was determined
to be the overall critical storm. The remaining rainfall events were then checked and flooding
analyzed as required. The flooding during the critical storm event occurred in several areas
within the city limits and was not isolated to any particular location. The majority of the flood
areas were located in the southeast and central sections of the city.
The model flood results from a small area of the city are shown in Figure 4.1 as an example.
Flooding is shown at inlet or ditch junction locations. The red nodes indicate inlet or ditch
flooding locations during the 25yr-8hr storm and include an identification number. The green
nodes indicate areas with no flooding. The blue lines indicate pipes and ditches. These results
were produced for each storm event and displayed automatically within the model using the
mapping tools.
FIGURE 4.1
SAMPLE FLOOD RESULTS MAP
The rainfall distribution curves were based on theoretical storm events and not actual
measured rainfall. Also, data regarding flood levels for actual rainfall events was not available
for calibrating the model. Therefore, based on meetings with the City, it was decided that the
model would be calibrated by comparing the model results for the 25-yr critical storm event to
SYSTEM FLOOD ANALYSIS
19
areas of known flooding. HGL profiles were then created for each area identified along with
flooding / storage graphs for analysis. The detailed flood analysis document is located in
Appendix C. A sample HGL profile and storage graph is shown in Figure 4.2. Based on the
model results, a summary document was then created to compare the known flood area map
provided by the City to the model results. This document confirmed flooding in most areas of
known flood concern. Some of the areas could not be checked as there were no stormwater
elements shown in GIS or the model. A few areas did not flood, but did have inlet surcharging.
The entire stormwater system was reviewed in detail using the same methodology listed above.
These profiles and graphs are included in Appendix E. The results of this analysis were used to
evaluate improvements to reduce / eliminate flooding within the system.
FIGURE 4.2
SAMPLE HGL PROFILE AND STORAGE GRAPH
SYSTEM FLOOD ANALYSIS
20
The following observations were made during the course of the stormwater system analysis:
The majority of the inlet flooding occurred for less than 2 hours.
Flooding along the coastal areas was either caused or impacted by the high tide elevation
of 2-ft.
Flooding shown in isolated roadside swale sections with no outfall was largely the result
of a lack of infiltration data available at conduits within the InfoSWMM software.
Infiltration rates needed to be adjusted at some storage (pond) locations in order to
match real world results.
The majority of the stormwater system discharges directly into the surrounding bay at
multiple locations. Due to the outfall elevation in relation to the bay and tailwater
conditions, the flood reduction options available were limited.
Flow is lost from the system once it leaves an inlet during a dynamic model simulation.
The downstream portion of each area will need to be checked carefully once
improvements are made in the model to make sure additional flooding is not created.
DESIGN ALTERNATIVE DEVELOPMENT
21
5.0 DESIGN ALTERNATIVE DEVELOPMENT
5.1 System Improvements Methodology
The most practical method to reduce flooding was determined to be increasing capacity within
the conveyance system (ditches and pipes). This method involved increasing pipe sizes,
removing negative slope pipe sections, increasing pipe slopes, and widening ditches. Each flood
area during the critical storm event was individually numbered and analyzed for potential flood
reduction. The conveyance system capacity was then increased in each identified problem area
until flooding was eliminated or reduced as much as possible. The downstream section of each
identified problem area was checked to make sure additional flooding was not created as a
result of the proposed improvements.
After the proposed system improvements to eliminate flooding during the 25-yr critical storm
event were established within the model, a flood reduction analysis for the 100-yr critical storm
was completed. The purpose of this analysis was to establish the amount of flood reduction
achieved during the critical 100-yr storm event as a result of the proposed system
improvements for the 25-yr critical storm.
An example of the flood reduction analysis is a flood area that has been modeled for the 100-yr
critical event with both the existing conditions and proposed improvements for eliminating
flooding during the 25-yr critical storm. The difference in the flood volume divided by the
volume with no improvements is identified as the flood reduction and shown as a percentage.
The percentage for the 100-yr flood reduction is identified for each flood area identified in the
model of the 25-yr storm event and is included in proposed solution in Section 4.3 for each
individual flood area.
It should be noted that the proposed improvements in upstream areas that discharge through
drainage ditches connected directly to the bay have the potential to increase downstream
flooding along these ditches during extreme storm events due to increased tailwater
conditions. Extreme storm events, such as hurricanes, that cause the tidal elevation to rise
significantly will result in reduced capacity within these drainage ditches. Most of these ditches
appear to run through open areas, such as recreation facilities, that are not heavily populated.
5.2 Proposed System Improvements
The proposed system improvements up to the 25-yr critical storm event are included in this
section for the flood areas shown in Figures 5.1 through 5.6. In areas of flooding that occurred
only during the 100-yr storm events, solutions are also included where flooding could be
eliminated by increasing the conveyance capacity. In areas where flooding occurred during the
25-yr and 100-yr storm events, only the flood reduction analysis is included for the 100-yr
storm.
DESIGN ALTERNATIVE DEVELOPMENT FIGURE 5.1
22
DESIGN ALTERNATIVE DEVELOPMENT FIGURE 5.2
23
DESIGN ALTERNATIVE DEVELOPMENT
24
Area 1
The flooding is located along Mooney Road. The area is within Okaloosa County, so no
improvements are proposed as part of this master plan. Per the County, these areas do have
minor flooding that exceeds the ditch capacity at times. These areas are not a priority for the
County because the flooding does not impact nearby homes.
Area 2
The flooding is located along Mooney Road. The area is within Okaloosa County, so no
improvements are proposed as part of this master plan. Per the County, these areas do have
minor flooding that exceeds the ditch capacity at times. These areas are not a priority for the
County because the flooding does not impact nearby homes.
Area 3
The flooding is located along Mooney Road. The area is within Okaloosa County, so no
improvements are proposed as part of this master plan. Per the County, these areas do have
minor flooding that exceeds the ditch capacity at times. These areas are not a priority for the
County because the flooding does not impact nearby homes.
Area 4
The flooding is located along Mooney Road. The area is within Okaloosa County, so no
improvements are proposed as part of this master plan. Per the County, these areas do have
minor flooding that exceeds the ditch capacity at times. These areas are not a priority for the
County because the flooding does not impact nearby homes.
Area 5
The flooding is located along Mooney Road. The area is within Okaloosa County, so no
improvements are proposed as part of this master plan. Per the County, these areas do have
minor flooding that exceeds the ditch capacity at times. These areas are not a priority for the
County because the flooding does not impact nearby homes.
Areas 6 & 7
The flooding is located along Golf Course Drive and Eagle Street NE. The proposed solution for
the 25-yr critical storm is as follows:
Increase pipe size from 18x29-inch elliptical to 22x34-inch elliptical between SWINLE00000000002042 and SWINLE00000000002044
Increase pipe size from 24-inch to 24x38-inch elliptical from SWINLE00000000002051 to SWINLE00000000002048
Increase pipe slope to existing inlet inverts and size from 27x43 elliptical to 42-inch (or elliptical equivalent) between SWINLE00000000002042 and SWINLE00000000002010
Increase pipe size from 36-inch to 48-inch and deepen inlet SWINLE00000000000421 between SWINLE00000000002010 and SWINLE00000000000421
Flooding is reduced during the 100-yr critical storm by approximately 50% after system
improvements.
DESIGN ALTERNATIVE DEVELOPMENT
25
Area 8
The flooding is located along Mooney Road. The proposed solution for the 25-yr critical storm
is as follows:
Increase pipe slope and inlet SWINLE00000000000420 depth between inlets SWINLE00000000001918 and SWNETW00000000000559
Increase pipe size from 24-inch to 30-inch at SWGRAV00000000002339 Additional flooding occurs upstream during the critical 100-yr event. The proposed solution for
the 100-yr critical storm is as follows:
Deepen inlet SWINLE00000000001940 to remove negative slope.
Increase pipe size from 18-inch to 24-inch between SWINLE00000000001939 and SWINLE00000000001948.
Area 9
The flooding is located along Mooney Road and is partially the result of the lack of data on the
upstream FDOT conveyance system. The proposed solution for the 25-yr critical storm is as
follows:
Increase pipe slope and size from 24-inch to 30-inch at SWGRAV00000000002338 Flooding is reduced during the 100-yr critical storm by approximately 60% after system
improvements.
DESIGN ALTERNATIVE DEVELOPMENT FIGURE 5.3
26
DESIGN ALTERNATIVE DEVELOPMENT
27
Area 10
The flooding is located along Highway Ave NE. The proposed solution for the 25-yr critical
storm is as follows:
Increase pipe size of SWGRAV00000000000808 from 15-inch to 24-inch
Increase upstream pipe slopes to max allowable using existing inlets Flooding is reduced during the 100-yr critical storm by approximately 20% after system
improvements.
Area 11
The flooding is located along Beachview Drive NE. The proposed solution for the 25-yr critical
storm is as follows:
Entire branch needs to be re-installed to remove negative slopes from SWINLE00000000000677 to SWINLE00000000000663
Pipe sizes need to be increased from 24-inch to 29x45-inch elliptical between SWINLE00000000000663 and SWINLE00000000000674
Pipe sizes need to be increased from 15/18-inch to 24-inch between SWINLE00000000000674 and SWINLE00000000000677
Peak flooding is reduced by approximately 30% and flood length reduced after system
improvements. Additional flooding occurs on north branch during the critical 100-yr event.
The proposed solution for the 100-yr critical storm is as follows:
Increase pipe size from 24-inch to 36-inch between SWINLE00000000000663 and SWINLE00000000000667.
Increase pipe size from 18-inch to 24-inch between SWINLE00000000000667 and SWINLE00000000000666.
Increase pipe size from 15-inch to 18-inch at SWGRAV00000000000795.
DESIGN ALTERNATIVE DEVELOPMENT FIGURE 5.4
28
DESIGN ALTERNATIVE DEVELOPMENT
29
Area 12
The flooding is located along Sudduth Circle NE and is caused by the 2-ft tidal outfall elevation. The proposed solution for the 25-yr critical storm is as follows:
Flooding can be reduced by a small amount by increasing SWGRAV00000000000729 pipe size from 15-inch to 18-inch
Flooding is reduced during the 100-yr critical storm by approximately 30% after system
improvements.
Area 13
The flooding is located along Yacht Club Drive NE. The model shows minor flooding for less
than 10 minutes that appears to be a result of the 2-ft downstream tidal elevation. There is
also a lack of infiltration along ditch sections in the model. The area is not a flood concern per
the City and has recently been cleaned out.
Area 14
The flooding is located along Hughes Street NE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 13x21-inch elliptical to 19x30-inch elliptical between SWINLE00000000000572 and SWNETW00000000000510
Flooding is reduced during the 100-yr critical storm by approximately 35% after system
improvements.
Area 15
The flooding is located along Hughes Street NE and Iowa Drive NE and is impacted by the 2-ft
tidal elevation. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size of SWGRAV00000000000567 from 30-inch to 29x45-inch elliptical
Increase pipe size of SWGRAV00000000000616 from 24-inch to 29x45-inch elliptical
Increase pipe size of SWGRAV00000000000619 from 24-inch to 24x38-inch elliptical
Increase pipe size of SWGRAV00000000000620 from 11x17-inch elliptical to 14x23-inch elliptical
Increase pipe size of SWGRAV00000000000618 from 18-inch to 24-inch
Increase pipe size of SWGRAV00000000000617 from 15-inch to 24-inch Flooding is reduced during the 100-yr critical storm by approximately 65% after system
improvements.
Area 16
The flooding is located between Hughes Street NE and Ferry Road NE. Ditch flooding cannot be prevented due to the 2-ft tidal elevation in the model.
Area 17
The flooding is located along Hughes Street NE. A surcharge depth was added to the inpoint to
remove flooding at SWINLE00000000001241. The proposed solution for the 25-yr critical storm
is as follows:
DESIGN ALTERNATIVE DEVELOPMENT
30
Increase pipe size from 24-inch to 24x38-inch elliptical between SWNETW00000000000120 and SWINLE00000000000485
Flooding is reduced during the 100-yr critical storm by approximately 15% after system
improvements.
Area 18
The flooding is located at a commercial property along Eglin Parkway NE. This area only floods
during the 100 year storm events. The proposed solution for the 100-yr critical storm is as
follows:
Increase pipe size from 18-inch to 24-inch at SWGRAV00000000001366
Area 19
The flooding is located along Buck Drive NE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 24-inch to 30-inch between SWOUTL00000000000049 and SWNETW00000000000182
Increase pipe size from 18-inch to 19x30-inch elliptical between SWNETW00000000000182 and SWINLE00000000000578
Flooding is reduced during the 100-yr critical storm by approximately 65% after system
improvements.
Area 20
The flooding is located along California Drive. The downstream pipe is undersized and at a
negative slope. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15-inch to 24-inch between SWNETW00000000000366 and SWINLE00000000002345
Increase slope by lowering invert at SWNETW00000000000366 Flooding is reduced during the 100-yr critical storm by approximately 65% after system
improvements.
Area 21
The flooding is located along Oregon Drive NE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 18-inch to 24-inch between SWINLE00000000000599 and SWNETW00000000000357
Flooding is reduced during the 100-yr critical storm by approximately 30% after system
improvements.
Areas 22 & 23
The flooding is located along Okaloosa Road NE and Laurie Drive NE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 18-inch to 24x38-inch elliptical between SWNETW00000000000172 and SWINLE00000000000610
Increase pipe size from 15-inch to 24-inch at SWGRAV00000000000731
DESIGN ALTERNATIVE DEVELOPMENT
31
Increase pipe size from 15-inch to 18-inch between SWINLE00000000000711 and SWINLE00000000000607
Increase pipe size from 18-inch to 24-inch between SWINLE00000000000610 and SWINLE00000000000714
Flooding is reduced during the 100-yr critical storm by approximately 50% and flood length
reduced after system improvements.
Area 24
The flooding is located along Kepner Drive NE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 12/15-inch to 24-inch between SWINLE00000000000616 and SWINLE00000000000706
Increase pipe size from 24-inch to 30-inch between SWINLE00000000000616 and SWOUTL00000000000079
Increase pipe slope / deepen inlets to remove negative / flat slopes between SWINLE00000000000706 and SWOUTL00000000000079.
Flooding is reduced during the 100-yr critical storm by approximately 30% and flood length
significantly reduced after system improvements.
Area 25
The flooding is located along Gardner Drive NE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe slope from SWINLE00000000000703 to SWINLE00000000000695 to establish a positive grade
Increase pipe size from 18-inch to 24-inch at SWGRAV00000000000689
Increase pipe size from 24-inch to 30-inch at SWGRAV00000000000676 Flooding is reduced during the 100-yr critical storm by approximately 65% after system
improvements.
Area 26
The flooding is located along Kepner Drive NE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 24-inch to 24x38-inch elliptical between SWINLE00000000001124 and SWINLE00000000000632
Flooding is reduced during the 100-yr critical storm by an insignificant amount after system
improvements.
Area 27
The flooding is located along Bay Drive SE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15-inch to 18-inch and increase pipe slope at SWGRAV00000000000664
DESIGN ALTERNATIVE DEVELOPMENT
32
Flooding is reduced during the 100-yr critical storm by approximately 5% after system
improvements. Additional flooding occurs on the west branch during the 100-yr critical event. The proposed solution for the 100-yr critical storm is as follows:
Increase pipe size from 15-inch to 18-inch between SWINLE00000000000627 and SWINLE00000000000694
Increase pipe size from 18-inch to 24-inch at SWGRAV00000000000666
Area 28
The flooding is located along Bay Drive SE. This area only floods during the 100 year storm
events. The proposed solution for the 100-yr critical storm is as follows:
Increase pipe size from 15-inch to 24-inch between SWOUTL00000000000364 and SWINLE00000000000839
Area 29
The flooding is located along Brooks Street SE. This area only floods during the 100 year storm
events. The proposed solution for the 100-yr critical storm is as follows:
Increase pipe size from 15-inch to 18-inch between SWNETW00000000000628 and SWINLE00000000000911
Increase pipe size from 15-inch to 24-inch at SWGRAV00000000001054
Area 30
The flooding is located along Alexandra Place SE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15-inch to 18-inch between SWINLE00000000000930 and SWNETW00000000000257
Increase pipe size from 18-inch to 24-inch between SWINLE00000000000932 and SWNETW00000000000218
Increase pipe size from 24-inch to 30-inch between SWNETW00000000000218 and SWINLE00000000000804
Increase pipe size and remove negative slope from 30-inch to 34x53-inch elliptical between SWOUTL00000000000246 and SWINLE00000000000804
Flooding is reduced during the 100-yr critical storm by approximately 50% after system
improvements.
Area 31
The flooding is located along Brooks Street SE. This area only floods during the 100 year storm
events. The proposed solution for the 100-yr critical storm is as follows:
Increase pipe size from 15-inch to 18-inch between SWINLE00000000000843 and SWINLE00000000000845
Areas 32 & 33
The flooding is located along Fourth Street SE, Third Street SE, and near Elliot Road SE. The proposed solution for the 25-yr critical storm is as follows:
DESIGN ALTERNATIVE DEVELOPMENT
33
Increase pipe size from 18-inch to 24x38-inch elliptical between SWINLE00000000000922 and SWNETW00000000000284 along with the Area 30 pipe
size increase from 30-inch to 42-inch
Deepen inlet SWINLE00000000001102
Increase pipe size from 12-inch to 18-inch at SWGRAV00000000001192
Increase pipe size from 15-inch to 18-inch at SWGRAV00000000001187
Increase pipe size from 18-inch to 24-inch between SWNETW00000000000283 and SWNETW00000000000284
Flooding is reduced during the 100-yr critical storm by an insignificant amount after system
improvements.
Area 34
The flooding is located along Oak Street SE and Elm Avenue SE. The ditch along Oak Street SE
appears to be undersized due to limited right-of-way. This ditch is not an area of flood concern
per City staff, but is a maintenance issue. The proposed solution is as follows:
Increase pipe size from 24-inch to 36-inch to prevent downstream inlet flooding between SWNETW00000000000228 and SWNETW00000000000267
Area 35
The flooding is located along Magnolia Avenue SE. The proposed solution for the 25-yr critical storm is as follows:
The pipe size appears to be adequate. The pipe slope needs to be increased from SWINLE00000000000592 to SWINLE00000000000927.
Area floods during the 100-yr critical event. The proposed solution for the 100-yr critical storm
is as follows:
Increase pipe size from 18-inch to 24-inch between SWINLE00000000000592 and SWINLE00000000000927
Area 36
The flooding is located along Buck Drive NE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15-inch to 18-inch between SWINLE00000000000580 and SWINLE00000000000582
Increase pipe size from 18-inch to 24-inch at SWGRAV00000000000624 Flooding is reduced during the 100-yr critical storm by approximately 30% after system
improvements.
Area 37
The flooding is located along Ferry Road SE. The proposed solution for the 25-yr critical storm is as follows:
Pipe slope and size to be increased from 15-inch to 18-inch between SWINLE00000000000884 and SWINLE00000000000879
Increase pipe size from 15-inch to 24-inch between SWINLE00000000000879 and SWNETW00000000000242
DESIGN ALTERNATIVE DEVELOPMENT
34
Flooding is reduced during the 100-yr critical storm by approximately 15% after system
improvements.
Area 38
The flooding is located along First Street SE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15-inch to 18-inch between SWNETW00000000000295 and SWINLE00000000000783
Flooding is reduced during the 100-yr critical storm by approximately 55% after system
improvements.
Area 39
The flooding is located along Brooks Street SE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15-inch to 18-inch between SWINLE00000000000982 and SWINLE00000000000983
Increase pipe size from 18-inch to 24-inch between SWINLE00000000000982 and SWOUTL00000000000380
Flooding is reduced during the 100-yr critical storm by approximately 85% and flood length
reduced after system improvements.
Area 40
The flooding is located along Third Street SE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15-inch to 14x23-inch elliptical between SWNETW00000000000199 and SWINLE00000000000755
Flooding is reduced during the 100-yr critical storm by approximately 10% after system
improvements.
Area 41
The flooding is located along Second Street SE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15-inch to 14x23-inch elliptical and remove negative slope at SWGRAV00000000001120
Increase pipe size from 18-inch to 24-inch between SWINLE00000000000973 and SWNETW00000000000276
Flooding is reduced during the 100-yr critical storm by approximately 50% and flood length is
reduced after system improvements.
Area 42
The flooding is located along Harbeson Avenue SE. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 18-inch to 24-inch between SWINLE00000000000971 and SWINLE00000000000964
DESIGN ALTERNATIVE DEVELOPMENT
35
Increase pipe size from 18-inch to 30-inch between SWINLE00000000000971 and SWINLE00000000000953
Increase pipe size from 18/24-inch to 36-inch between SWINLE00000000000953 and SWNETW00000000000265
Remove negative slopes through entire pipe run Flooding is reduced during the 100-yr critical storm by approximately 60% after system
improvements.
Area 43
The flooding is located along Park Circle SE. The pipes downstream of the flooding inlet are
undersized. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15/18-inch to 30-inch between SWNETW00000000000613 and SWNETW00000000000611
Deepen inlet SWINLE00000000000740 to remove negative pipe slope
Increase pipe size from 18-inch to 24-inch at SWGRAV00000000000841 Flooding is reduced during the 100-yr critical storm by approximately 40% after system
improvements.
Area 44
The flooding is located along Jackson Street NE. The proposed solution for the 25-yr critical storm is as follows:
Remove negative pipe slope between SWINLE00000000000466 and SWNETW00000000000123
Increase pipe size from 18-inch to 24-inch between SWINLE00000000000524 and SWINLE00000000000462
Increase pipe size from 30-inch to 36-inch at SWGRAV00000000000527
Increase pipe size from 30-inch to 36-inch at SWGRAV00000000000524 Flooding is reduced during the 100-yr critical storm by an insignificant amount after system
improvements.
DESIGN ALTERNATIVE DEVELOPMENT FIGURE 5.5
36
DESIGN ALTERNATIVE DEVELOPMENT
37
Areas 45 - 47
The flooding is located along Beal Parkway SW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 24-inch to 30-inch between SWNETW00000000000617 and SWNETW00000000000083
Increase pipe size from 18-inch to 24-inch between SWNETW00000000000617 and SWNETW00000000000092
Increase pipe size from 15-inch to 18-inch between SWINLE00000000000745 and SWNETW00000000000092
Increase pipe size from 15-inch to 18-inch at SWGRAV00000000001312 and SWGRAV00000000000380
Flooding is reduced during the 100-yr critical storm by approximately 70% in Area 45, 25% in
Area 46, and eliminated in Area 47 after system improvements.
Area 48
The flooding is located along Miracle Strip Parkway SW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15-inch to 18-inch at SWGRAV00000000000346 Flooding is eliminated during the 100-yr critical storm after system improvements.
Areas 49 & 50
The flooding is located along First Street SW and Robinwood Drive SW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 18/24-inch to 29x45-inch elliptical between SWFITT00000000000020 and SWINLE00000000000217
Increase pipe size from 18-inch to 24x38-inch elliptical between SWINLE00000000000278 and SWINLE00000000000217
Increase pipe size from 18-inch to 24-inch between SWINLE00000000000278 and SWNETW00000000000037
Increase pipe size from 15-inch to 18-inch at SWGRAV00000000000151 and SWGRAV00000000000157
Flooding is reduced during the 100-yr critical storm by approximately 65% in Area 49 and 85%
in Area 50 after system improvements.
Area 51
The flooding is located along a drainage ditch north of Coral Drive SW and cannot be eliminated
due to 2-ft tidal elevation.
Area 52
The flooding is located along Ranger Street SW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 18-inch to 24-inch between SWINLE00000000000247 and SWNETW00000000000061
DESIGN ALTERNATIVE DEVELOPMENT
38
Flooding is reduced during the 100-yr critical storm by approximately 75% and flood length is
reduced after system improvements.
Area 53
The flooding is located along Ed Brown Street SW and is caused by water levels in main pipe run
and cannot be eliminated. The rim of inlet SWINLE00000000000159 is lower than the crown of
the main pipe run.
Area 54
The flooding is located along a drainage ditch just north of Hollywood Boulevard NW and is
impacted by the downstream 2-ft tidal elevation and undersized outfall piping with a negative
slope. Upsizing the downstream piping and removing the negative slope reduces the ditch
flooding, but increases flooding at a downstream pond / ditch. Flooding cannot be eliminated
without potentially diverting runoff to new area. This area is of flood concern per City staff.
Area 55
The flooding is located along Industrial Street NW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15-inch to 18-inch between SWINLE00000000001288 and SWINLE00000000001286
Flooding is reduced during the 100-yr critical storm by approximately 95% and flood length is
reduced after system improvements.
Area 56
The flooding is located along Holmes Boulevard NW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 24-inch to 36-inch at SWGRAV00000000001540
Increase pipe size from 21-inch to 24-inch at SWGRAV00000000001548
Increase pipe size from 15-inch to 18-inch at SWGRAV00000000001547 Flooding is reduced during the 100-yr critical storm by approximately 80% and flood length is
reduced after system improvements.
Areas 57 - 59
The flooding is located along Highland Drive NW and Silva Drive NW. The proposed solution for the 25-yr critical storm is as follows:
Remove negative slope along entire pipe run
Increase pipe size from 30-inch to 29x45-inch elliptical between SWINLE00000000001751 and SWINLE00000000001752
Increase pipe size from 36-inch to 34x53-inch elliptical between SWINLE00000000001752 and SWNETW00000000000455
Increase pipe size from 48-inch to 48x76-inch elliptical between SWNETW00000000000455 and SWOUTL00000000000146
Flooding is reduced during the 100-yr critical storm by approximately 15% after system
improvements. It should be noted that the improvements in these areas cause increased
DESIGN ALTERNATIVE DEVELOPMENT
39
downstream flooding. The proposed improvements increase flooding along the drainage ditch
behind a recreation area within Area 54. Area 54 flooding cannot be eliminated as previously
discussed.
Area 60
The flooding is located along Rainbow Drive NW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size and steepen slope from 30-inch to 36-inch between SWINLE00000000001364 and SWINLE00000000001366
Increase pipe size from 24-inch to 30-inch between SWINLE00000000001366 and SWNETW00000000000465
Increase pipe size from 18-inch to 24-inch between SWNETW00000000000465 and SWNETW00000000000443
Increase pipe size from 15-inch to 18-inch between SWNETW00000000000443 and SWNETW00000000000457
Flooding is reduced during the 100-yr critical storm by approximately 50% after system
improvements.
Area 61
The flooding is located along Wisteria Court NW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 18-inch to 24-inch between SWNETW00000000000648 and SWINLE00000000001342 or increase pipe slope of entire branch
Flooding is reduced during the 100-yr critical storm by approximately 65% after system
improvements.
Area 62
The flooding is located along Beal Parkway NE. This area only floods during the 100 year storm
events. The proposed solution for the 100-yr critical storm is as follows:
Increase pipe size from 15-inch to 18-inch at SWGRAV00000000000594
Increase pipe size from 18-inch to 24-inch at SWGRAV00000000000039
Increase pipe size from 15-inch to 18-inch between SWINLE00000000000020 and SWINLE00000000000044
Increase pipe size from 24-inch to 30-inch between SWINLE00000000001339 and SWINLE00000000001747
Increase pipe size from 18-inch to 24-inch at SWGRAV00000000002107
Increase pipe size from 24-inch to 30-inch at SWGRAV00000000000525
Increase pipe size from 15-inch to 18-inch at SWGRAV00000000000535
Increase pipe size from 15-inch to 18-inch at SWGRAV00000000000568
Increase pipe size from 15-inch to 18-inch at SWGRAV00000000000465
Increase pipe size from 15-inch to 24-inch at SWGRAV00000000000558
DESIGN ALTERNATIVE DEVELOPMENT
40
Area 63
The flooding is located along Linstew Drive NW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15-inch to 18-inch between SWINLE00000000002396 and SWINLE00000000001386
Flooding is reduced during the 100-yr critical storm by approximately 20% after system
improvements.
Area 64
The flooding is located along Beal Parkway NW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 24-inch to 24x38-inch elliptical between SWINLE00000000001388 and SWINLE00000000001373
Additional flooding occurs during the critical 100-yr event. The proposed solution for the 100-
yr critical storm is as follows:
Increase pipe size from 24-inch to 30-inch at SWGRAV00000000002973
Increase pipe size from 18-inch to 24-inch at SWGRAV00000000000039
Increase pipe size from 15/18-inch to 24-inch between SWINLE00000000001394 and SWINLE00000000001390
Increase pipe size from 15-inch to 24-inch at SWGRAV00000000002157
Area 65
The flooding is located at a pond near Ventura Circle NW and sheet flows directly into the bay.
If the flooding is a concern, the pond volume can be increased.
Area 66
The flooding is located along Holmes Boulevard NW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15/18-inch to 24-inch between SWINLE00000000001300 and SWINLE00000000001302
Flooding is reduced during the 100-yr critical storm by approximately 30% and flood length is
reduced after system improvements.
Area 67
The flooding is located within a residential area between Bishop Avenue NW and Martisa Road
NW. This area only floods during the 100 year storm events. The proposed solution for the
100-yr critical storm is as follows:
Increase pipe size from 18-inch to 24-inch between SWNETW00000000000440 and SWINLE00000000001245
Area 68
The flooding is located along Linda Lane NW. The proposed solution for the 25-yr critical storm is as follows:
DESIGN ALTERNATIVE DEVELOPMENT
41
Remove the negative slope and / or increase pipe size from 15-inch to 18-inch between SWNETW00000000000505 and SWINLE00000000001427
Flooding is reduced during the 100-yr critical storm by approximately 15% after system
improvements.
Area 69
The flooding is located along Driftwood Avenue SW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15-inch to 18-inch at SWGRAV00000000000117 Flooding is reduced during the 100-yr critical storm by approximately 40% and flood length is
reduced after system improvements.
Area 70
The flooding is located along Deluna Road SW. This area only floods during the 100 year storm
events. The proposed solution for the 100-yr critical storm is as follows:
Increase pipe size from 18-inch to 19x30-inch elliptical between SWINLE00000000000151 and SWINLE00000000000154
Area 71
The flooding is located just north of Holmes Boulevard NW. This area only floods during the
100 year storm events. The proposed solution for the 100-yr critical storm is as follows:
Increase pipe size from 21-inch to 24x38-inch elliptical between SWNETW00000000000458 and SWINLE00000000002210
Area 72
The flooding is located at a pond along Wright Parkway NW. This area only floods during the
100 year storm events. Severe flooding occurs and the pond cannot be widened much due to
site constraints.
Area 73
The flooding is located just north of Holmes Boulevard NW. The proposed solution is as follows:
Increase pond volume by adding width / depth, adjust weir, and increase discharge pipe size to 8-inch.
Area 74
The flooding is located at a pond near Olde Cypress Circle NW. This area only floods during the
100 year storm events. Severe flooding occurs and the pond cannot be widened much due to
site constraints.
Area 75
The flooding is located at a mixed use property along Carol Avenue NW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 24-inch to 36-inch between SWINLE00000000001453 and SWINLE00000000001689
DESIGN ALTERNATIVE DEVELOPMENT
42
Flooding is reduced during the 100-yr critical storm by approximately 45% after system
improvements.
Area 76
The flooding is located at a commercial property along Carol Avenue NW and cannot be
eliminated because entire pipe run is at a negative slope and inlet SWINLE00000000002380 rim
elevation is 2-ft below the pond top elevation.
Area 77
The flooding is located along Deal Avenue NW and Poulton Drive NW. The proposed solution for the 25-yr critical storm is as follows:
Remove negative slope at SWGRAV00000000002084
Increase pipe size from 18-inch to 24-inch between SWINLE00000000001727 and SWINLE00000000001717
Increase pipe size from 30-inch to 36-inch between SWINLE00000000001717 and SWINLE00000000001713
Increase undersized downstream pipe at SWGRAV00000000001360 from 15-inch to 36-inch
Flooding is reduced during the 100-yr critical storm by approximately 40% after system
improvements.
Area 78
The flooding is located along Hollywood Boulevard NW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15-inch to 24-inch between SWINLE00000000001623 and SWINLE00000000001622
Increase pipe size from 24-inch to 30-inch between SWINLE00000000001623 and SWINLE00000000001717
Flooding is reduced during the 100-yr critical storm by approximately 60% after system
improvements.
Area 79
The flooding is located along North Audrey Circle NW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 15-inch to 18-inch between SWNETW00000000000389 and SWINLE00000000001674
Flooding is reduced during the 100-yr critical storm by an insignificant amount after system
improvements.
Area 80
The flooding is located along Jonquil Avenue NW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 18/21-inch to 24-inch between SWNETW00000000000388 and SWNETW00000000000580
DESIGN ALTERNATIVE DEVELOPMENT
43
Flooding is reduced during the 100-yr critical storm by approximately 10% after system
improvements.
Area 81
The flooding is located at a pond south of Sullivan Street NW. This area only floods during the
100 year storm events. Ditch and upstream pipe section floods during 100-yr critical event.
Ditch flooding cannot be eliminated due to backflow from downstream system. The proposed
solution for the 100-yr critical storm is as follows:
Remove negative slope through 24-inch pipe and increase pipe size to 30-inch between SWOUTL00000000000249 and SWINLE00000000001641
Increase pipe size from 18-inch to 24-inch at SWGRAV00000000001970
Increase pipe size from 15-inch to 18-inch between SWINLE00000000001640 and SWINLE00000000001639
DESIGN ALTERNATIVE DEVELOPMENT FIGURE 5.6
44
DESIGN ALTERNATIVE DEVELOPMENT
45
Area 82
The flooding is located at a pond near Mary Esther Boulevard. This area only floods during the
100 year storm events. The proposed solution for the 100-yr critical storm is as follows:
Increase pipe size from 18-inch to 24-inch between SWINLE00000000001559 and SWINLE00000000001561
Increase pipe size from 15-inch to 18-inch at SWGRAV00000000001876
Increase pipe size from 18-inch to 24-inch between SWINLE00000000001563 and SWINLE00000000001557
Increase pipe size from 15-inch to 18-inch at SWGRAV00000000001870
Area 83
The flooding is located at a pond west of Poplar Avenue NW. Moderate to heavy pond flooding
occurs. It is a County owned pond with improvements currently under design. Part of the ditch
along Lovejoy to the pond is being improved, pond capacity increased, outfall structure / pipe
upgraded, additional retention basin to be added north of outfall, and road crossing culvert to
be upgraded.
Area 84
The flooding is located along Anchors Street NW. The proposed solution for the 25-yr critical storm is as follows:
Increase pipe size from 24-inch to 29x45-inch elliptical between SWINLE00000000002158 and SWINLE00000000001890
Increase pipe size from 18-inch to 19x30-inch elliptical at SWGRAV00000000002299 Flooding is reduced during the 100-yr critical storm by approximately 25% after system
improvements.
Area 85
Inlet floods due to flood level of Gap Creek after addition of County data. 36-inch pipe
(SWGRAV000000000002530) under Burnette Avenue NW is undersized and needs to be
upgraded to three (3) 48-inch pipes.
Area 86
The flooding is located along Lovejoy Road NW and cannot be eliminated because the rim
elevation is below the downstream pipe crown.
Area 87
The flooding is located along Stokes Avenue NW. The multiple small ditch sections show very
minor flooding largely due to lack of outfall and infiltration data in the model. Area is not a
flood concern per City staff since any overflow runs to the nearby creek.
DESIGN ALTERNATIVE DEVELOPMENT
46
5.3 Conceptual Cost Estimates
Upon completion of the full model analysis, conceptual cost estimates were developed for each
flood area which included a proposed system improvement as identified in Section 5.2. A unit
price was developed per linear foot of pipe that included all items associated with pipe
installations such as select fill, asphalt, sod, silt fence, demolition, maintenance of traffic, as-
builts, mobilization and bonds, etc. The only items broken out separately were inlets and
junction boxes. A 35% construction contingency was added due to the conceptual nature of
this analysis. A 10% engineering and administration cost was added to the construction
subtotal to cover design services. The unit prices used to estimate the cost of the proposed
improvements are shown in Table 5.1.
TABLE 5.1
UNIT PRICE LIST
Material
Round RCP Pipe Select Fill Sod Silt Fence Demolition MOT As-builts
Mobilization
& Bonds
35%
Contingency Total
15-inch $45.00 $8.00 $2.50 $3.00 $10.00 $1.37 $0.34 $3.51 $25.80 $99.53
18-inch $50.00 $8.00 $2.50 $3.00 $10.00 $1.47 $0.37 $3.77 $27.69 $106.79
24-inch $60.00 $8.00 $2.50 $3.00 $10.00 $1.67 $0.42 $4.28 $31.45 $121.32
30-inch $75.00 $9.00 $3.00 $3.00 $10.00 $2.00 $0.50 $5.13 $37.67 $145.29
36-inch $95.00 $9.00 $3.00 $3.00 $15.00 $2.50 $0.63 $6.41 $47.09 $181.62
42-inch $115.00 $10.00 $3.50 $3.00 $15.00 $2.93 $0.73 $7.51 $55.18 $212.86
48-inch $140.00 $10.00 $3.50 $3.00 $15.00 $3.43 $0.86 $8.79 $64.60 $249.18
54-inch $175.00 $11.00 $4.00 $3.00 $15.00 $4.16 $1.04 $10.66 $78.35 $302.21
60-inch $210.00 $12.00 $4.00 $3.00 $15.00 $4.88 $1.22 $12.51 $91.91 $354.52
Elliptical RCP
14x23-inch $60.00 $8.00 $2.50 $3.00 $10.00 $1.67 $0.42 $4.28 $31.45 $121.32
19x30-inch $75.00 $8.00 $2.50 $3.00 $10.00 $1.97 $0.49 $5.05 $37.10 $143.11
22x34-inch $100.00 $9.00 $3.00 $3.00 $10.00 $2.50 $0.63 $6.41 $47.09 $181.62
24x38-inch $115.00 $9.00 $3.00 $3.00 $10.00 $2.80 $0.70 $7.18 $52.74 $203.41
29x45-inch $150.00 $9.00 $3.00 $3.00 $15.00 $3.60 $0.90 $9.23 $67.80 $261.53
34x53-inch $200.00 $10.00 $3.50 $3.00 $15.00 $4.63 $1.16 $11.86 $87.20 $336.36
38x60-inch $250.00 $10.00 $3.50 $3.00 $15.00 $5.63 $1.41 $14.43 $106.04 $409.00
43x68-inch $320.00 $11.00 $4.00 $3.00 $15.00 $7.06 $1.77 $18.09 $132.97 $512.89
48x76-inch $390.00 $12.00 $4.00 $3.00 $15.00 $8.48 $2.12 $21.73 $159.72 $616.05
Material
Round RCP Pipe Select Fill Asphalt Silt Fence Demolition MOT As-builts
Mobilization
& Bonds
35%
Contingency Total
15-inch $45.00 $8.00 $45.00 $3.00 $10.00 $2.22 $0.56 $5.69 $41.81 $161.28
18-inch $50.00 $8.00 $45.00 $3.00 $10.00 $2.32 $0.58 $5.95 $43.70 $168.54
21-inch $55.00 $8.00 $46.50 $3.00 $10.00 $2.45 $0.61 $6.28 $46.14 $177.98
24-inch $60.00 $8.00 $46.50 $3.00 $10.00 $2.55 $0.64 $6.53 $48.03 $185.25
27-inch $70.00 $8.00 $46.50 $3.00 $10.00 $2.75 $0.69 $7.05 $51.79 $199.78
30-inch $75.00 $9.00 $48.00 $3.00 $10.00 $2.90 $0.73 $7.43 $54.62 $210.68
36-inch $95.00 $9.00 $50.00 $3.00 $15.00 $3.44 $0.86 $8.82 $64.79 $249.91
42-inch $115.00 $10.00 $52.00 $3.00 $15.00 $3.90 $0.98 $9.99 $73.45 $283.32
48-inch $140.00 $10.00 $53.50 $3.00 $15.00 $4.43 $1.11 $11.35 $83.44 $321.83
Unit Price Per Linear Foot (Sod)
UNIT COST SUMMARY
Unit Price Per Linear Foot (Asphalt)
DESIGN ALTERNATIVE DEVELOPMENT
47
Material
Round RCP Pipe Select Fill Asphalt Silt Fence Demolition MOT As-builts
Mobilization
& Bonds
35%
Contingency Total
54-inch $175.00 $11.00 $55.00 $3.00 $15.00 $5.18 $1.30 $13.27 $97.56 $376.31
60-inch $210.00 $12.00 $57.00 $3.00 $15.00 $5.94 $1.49 $15.22 $111.88 $431.52
72-inch $270.00 $12.00 $57.00 $3.00 $15.00 $7.14 $1.79 $18.30 $134.48 $518.70
84-inch $330.00 $12.00 $57.00 $3.00 $15.00 $8.34 $2.09 $21.37 $157.08 $605.87
Elliptical RCP
14x23-inch $60.00 $8.00 $45.00 $3.00 $10.00 $2.52 $0.63 $6.46 $47.46 $183.07
17x25-inch $70.00 $8.00 $45.00 $3.00 $10.00 $2.72 $0.68 $6.97 $51.23 $197.60
19x30-inch $75.00 $8.00 $46.50 $3.00 $10.00 $2.85 $0.71 $7.30 $53.68 $207.04
22x34-inch $100.00 $9.00 $47.50 $3.00 $10.00 $3.39 $0.85 $8.69 $63.85 $246.27
24x38-inch $115.00 $9.00 $48.00 $3.00 $10.00 $3.70 $0.93 $9.48 $69.69 $268.79
29x45-inch $150.00 $9.00 $50.00 $3.00 $15.00 $4.54 $1.14 $11.63 $85.51 $329.82
34x53-inch $200.00 $10.00 $52.00 $3.00 $15.00 $5.60 $1.40 $14.35 $105.47 $406.82
38x60-inch $250.00 $10.00 $53.50 $3.00 $15.00 $6.63 $1.66 $16.99 $124.87 $481.65
43x68-inch $320.00 $11.00 $55.00 $3.00 $15.00 $8.08 $2.02 $20.71 $152.18 $586.99
48x76-inch $390.00 $12.00 $57.00 $3.00 $15.00 $9.54 $2.39 $24.45 $179.68 $693.05
Unit Price Per Linear Foot (Asphalt)
The conceptual costs were estimated using spreadsheets that included material quantities and
unit prices. A construction cost was estimated as a subtotal and then the 10 percent was
included for engineering and administration for estimating the total conceptual cost. An
example of a calculation spreadsheet is shown in Table 5.2 and the spreadsheets for all the
flood areas are included in Appendix F. The conceptual cost summary for each flood area is
included in Table 5.4, Improvement Priority List.
TABLE 5.2
SAMPLE CONCEPTUAL COST ESTIMATE
Area 41 Construction Cost
Material Quantity Unit Unit Price Total
14x23-inch Elliptical RCP (Asphalt) 35 LF $ 183.07 $ 6,407.45
24-inch RCP (Sod) 299 LF $ 121.32 $ 36,274.76
Junction Box 1 EA $ 3,500.00 $ 3,500.00
Construction Subtotal $ 46,182.22
10% Engineering & Admin $ 4,618.22
Total Project Cost $ 50,800.44
DESIGN ALTERNATIVE DEVELOPMENT
48
5.4 Evaluation Matrix
Each flood area was evaluated based on specific categories for prioritizing the proposed system
improvements. These categories were identified through meetings and conversations with City
staff as well as suggestions by HMM. The categories established were Land Use, Frequency of
City Scheduled Maintenance & Work Orders, Flood Frequency, Infrastructure Material, and
Flood Duration during the 25-yr critical storm event. Each category includes ranking criteria
that ranges from 1 to 5 points.
The land use criteria for each flood area was established using GIS data provided by City staff
and included, from low to high priority, Recreation, Low Density Residential, Medium Density
Residential, Mixed Use, and Commercial / Industrial. Maintenance criteria, from low to high
priority, included never, occasionally, and frequent. The ranking was determined by City staff
based on past scheduled maintenance frequency and volume of work orders generated. Flood
frequency criteria, from low to high priority, included 100-yr flooding, 25-yr flooding, and 10-yr
flooding. The flood frequency was determined using the InfoSWMM model and ranked based
on the storm year in which flooding occurs. Infrastructure material criteria, from low to high
priority, included plastic / concrete, clay / brick, and corrugated metal. The infrastructure
material for the flood area was determined using GIS data provided by City staff. Flood
duration criteria, from low to high priority, included < 1-hr, 2-hr, 3-hr, 4-hr, and 5-hr. The flood
duration for each flood area was determined using the InfoSWMM model and ranked based on
the length of time flooding occurs during the 25-yr critical storm event.
Each category was assigned a Weight Factor based on the importance level determined by
HMM and City staff. The category score was a product of the categorys ranking multiplied by
the Weight Factor. The total score was the sum of the category scores, which had a maximum
value of 50. A sample area evaluation matrix is shown in Table 5.3. The evaluation matrix for
each project area is located in Appendix G.
DESIGN ALTERNATIVE DEVELOPMENT
49
TABLE 5.3
DESIGN ALTERNATIVE DEVELOPMENT
50
5.5 Improvement Priority
A list of the flood areas was compiled that contained the area number, location, improvement
description, total score, and estimated project cost for each flood area as shown in Table 5.4.
For prioritizing the list, the data was sorted based on total score with the higher scores being
the higher priority. In the case of a tie, the flood area with the lowest estimated cost was given
higher priority.
TABLE 5.4
IMPROVEMENT PRIORITY LIST
Area No. Location Improvement DescriptionTotal Score
(max score 50.0)
Estimated
Project Cost
84 Anchors St NW near Forsman Dr NW Increase pipe size 45.5 $401,417.35
49&50 First Street SW and Fourth Ave SW Increase pipe size 43.5 $632,899.58
73 North of Holmes Blvd NW near Wright Pkwy NW
Increase pond volume, adjust
weir, and increase discharge
pipe size
41.0 $39,513.97
85 End of Combs Manor Ct NW Increase pipe size and quantity 41.0 $79,472.05
6&7 Golf Course Drive and Eagle Street NE Increase pipe size 41.0 $649,397.98
40 Intersection of Third St SE and Carson Dr SE Increase pipe size 40.0 $53,787.67
57-59Neighborhood between Highland Dr NW and
Silva Dr NW
Remove negative pipe slope
and increase pipe size39.5 $1,473,068.86
39 Brooks St SE near Alconese Ave SE Increase pipe size 39.0 $160,459.22
38 Intersection of Chestnut Ave SE and First St SE Increase pipe size 38.0 $16,747.87
69 Intersection of Driftwood Ave SW and Iva PL SW Increase pipe size 35.5 $26,420.36
14 Hughes St NE near Walton Dr NE Increase pipe size 35.5 $45,108.48
9 Mooney Rd near Sherwood Rd NW Increase pipe size 34.0 $22,055.59
37 Ferry Rd SE near Chicago Ave SE Increase pipe size and slope 33.0 $99,175.04
24 Kepner Dr NE north of Okaloosa Rd NERemove negative pipe slope
and increase pipe size32.0 $296,266.31
55 Industrial St NW near Robinwood Dr NW Increase pipe size 31.0 $33,991.98
22&23 Anastasia Dr SE and Okaloosa Rd NE Increase pipe size 31.0 $391,225.43
30 Alexandra PL SE near Waynel Circle SERemove negative pipe slope
and increase pipe size31.0 $717,169.51
32&33 Magnolia Ave SE near Third St SEIncrease pipe size and deepen
inlet30.5 $255,297.12
19 Intersection of Hospital Dr NE and Buck Dr NE Increase pipe size 30.0 $227,294.06
77 Poulton Dr NW near Deal Ave NWRemove negative pipe slope
and increase pipe size29.5 $252,730.70
45-47 Beal Pkwy SE near First St SE Increase pipe size 29.5 $329,840.57
15 Hughes St NE near Oregon Dr NE Increase pipe size 29.5 $366,583.90
41 Second St SE near Methodist Ave SE Increase pipe size 29.0 $50,800.44
61 Sleepy Oaks Rd NW near Wisteria Ct NW Increase pipe size and slope 29.0 $70,706.55
42 Harbeson Ave SE near Birch St SERemove negative pipe slope
and increase pipe size29.0 $808,340.09
34 Oaks St SE near Alder Ave SE Increase pipe size 28.0 $68,324.39
75Neighborhood between Carol Ave NW and
Sherry Circle NWIncrease pipe size 28.0 $120,067.12
44 Intersection of Jackson St NE and Mallard Ave NERemove negative pipe slope
and increase pipe size28.0 $140,966.46
DESIGN ALTERNATIVE DEVELOPMENT
51
Area No. Location Improvement DescriptionTotal Score
(max score 50.0)
Estimated
Project Cost
80 Jonquil Ave NW near Sullivan St NW Increase pipe size 27.0 $83,695.37
81 Commercial property north of Sullivan St NWRemove negative pipe slope
and increase pipe size27.0 $109,836.71
60 Rainbow Dr NW near Tula PL NW Increase pipe size 27.0 $503,735.84
66Intersection of Martisa Rd NW and Holmes Blvd
NWIncrease pipe size 26.5 $11,732.62
11 Beachview Dr NE near Greenbrier Dr NERemove negative pipe slope
and increase pipe size26.5 $471,756.59
10 Highway Ave NE near Beachview Dr NE Increase pipe size and slope 26.0 $28,024.98
28 Bay Dr SE near Brooks St SE Increase pipe size 26.0 $32,881.21
29 Brooks St SE near Walkedge Dr SE Increase pipe size 25.0 $26,671.28
36 Buck Dr NE near Vine Ave NE Increase pipe size 25.0 $110,887.68
68 Linda Ln NW near Lula Belle Ln NWRemove negative pipe slope
and increase pipe size24.0 $11,545.62
8 Mooney Rd near Sherwood Rd NW Increase pipe size and slope 24.0 $34,606.57
52 Intersection of Ranger St SW and Fourth Ave SW Increase pipe size 24.0 $56,984.14
79 N Audrey Circle NW north of Sullivan St NW Increase pipe size 24.0 $74,354.51
63 Linstew Dr NW north of Beal Pkwy NW Increase pipe size 24.0 $106,602.02
82 Mary Esther CTO NW south of Sullivan St NW Increase pipe size 23.0 $170,524.88
43 Park Circle SEIncrease pipe size and deepen
inlet22.0 $46,393.53
35 Magnolia Ave SE near Hollywood Blvd SE Increase pipe slope 22.0 $93,244.81
62 Beal Pkwy SE ne