STORAGE TANK RULES AND REGULATIONS. IF YOU DON”T KNOW THE ANSWER YOU SHOULD BE ABLE TO LOOK IT UP USING THE TABLE OF CONTENTS

Embed Size (px)

Citation preview

  • Slide 1
  • STORAGE TANK RULES AND REGULATIONS
  • Slide 2
  • IF YOU DONT KNOW THE ANSWER YOU SHOULD BE ABLE TO LOOK IT UP USING THE TABLE OF CONTENTS
  • Slide 3
  • 18 23 25 30
  • Slide 4
  • WWQRR CHAPTER 17, SECTIONS 1-5 PAGES 17-1 Through 17-8 Section 1 = Authority Section 2 = Codes & Standards referenced in this Chapter Section 3 = Purpose Section 4 = Applicability Section 5 = Definitions
  • Slide 5
  • Cathodic Anode Protection Corrective Action Plan Connected Ancilary Parts Continuous Amperage Protocol WWQRR, Chapter 17, Section 5 (k)
  • Slide 6
  • SECTION 6 = DESIGN & CONSTRUCTION STANDARDS FOR UST SYSTEMS SECTION 7 = SUBSTANDARD USTS SECTION 8 = REPAIRS ALLOWED WWQRR CHAPTER 17, SECTIONS 6 8 PAGES 17-9 Through 17-17
  • Slide 7
  • Slide 8
  • CHAPTER 17, SECTION 6 PAGE 17-9 In order to prevent releases due to structural failure, corrosion, or spills and overfills for as long as the UST system is used to store regulated substances, all owners and/or operators of UST systems shall meet the following requirements.. This section is for Tanks, Piping, Spill and Overfill prevention Equipment, Installation and Certification of Installation
  • Slide 9
  • ALL NEW AND REPLACEMENT TANKS HAVE TO BE DOUBLE WALL AND ALL NEW AND REPLACEMENT PIPING HAS TO BE DOUBLE WALL AS WELL (WS 35-11-1429)
  • Slide 10
  • Chapter 17, Section 6(c) found on page 17-12 EVERY UST THAT RECEIVES DELIVERIES OF GREATER THAN 25 GALLONS, MUST HAVE OVERFILL AND SPILL PREVENTION EQUIPMENT.
  • Slide 11
  • Butterfly valve in the drop tube Ball check valve in the vent tube Top of the tank must be vapor tight (not allowed on ASTs) Both of the above devices restrict the flow when the tank is 95% full. Chapter 17, Section 6(c)(i)(B)(I) page 17-11 Overfill alarm must function at 90% full Chapter 17, Section 6(c)(i)(B)(II) page 17-13
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Slide 17
  • Slide 18
  • Slide 19
  • Slide 20
  • Install an overfill alarm. Report a suspected release. Report the violation to the DEQ and pay a pre-set penalty. Remove the stick and check the butterfly valve for proper operation. Chapter 17, Section 6(c) on page 17-11
  • Slide 21
  • 5 10 20 25 Chapter 17, Section 6(c)(ii)on page17-13
  • Slide 22
  • A 3 gallon spill bucket. A butterfly valve in the drop tube. A ball check valve in the vent lines. An overfill alarm that is visible or audible to the delivery driver. Chapter 17, Section 6(c) on page 17-13 this is a spill prevention device
  • Slide 23
  • Have an alarm of at least 95 decibels. Be audible to the operator of the station. Have a flashing light at least 12 feet above ground. Be able to alert the transfer operator when the tank is no more than 90% full Chapter 17, Section 6(c) on page17-13
  • Slide 24
  • Put the other 500 gallons of unleaded gasoline in the Premium tank. Send the 500 gallons back to the supplier Ignore the overfill alarm and put the 500 gallons in the unleaded tank Fill vehicles directly from the delivery truck until the unleaded gasoline is gone.
  • Slide 25
  • Remove the device. Replace the device. Install an overfill alarm. Place a stick in the drop tube to hold the device open and allow deliveries to continue. Chapter 17, Section 6(c) on page17-11
  • Slide 26
  • CHAPTER 17, SECTION 7 PAGE 17-15 Substandard USTs. UST systems which do not meet the standards of Section 6 shall not be placed back into service if they have been out of use for more than one year. Substandard USTs shall be permanently closed or removed from the ground in accordance with Part G of this chapter. CHAPTER 17, SECTION 8 PAGE 17-15 Repairs Allowed. Owners and/or operators of storage tank systems shall ensure that repairs will prevent releases due to structural failure or corrosion as long as the storage tank system is used to store regulated substances. The repairs shall meet the following ..
  • Slide 27
  • Section 9 = Notification Requirements Section 10 = Spill and Overfill Control Section 11 = Operation & Maintenance of Corrosion Protection (CP) Section 12 = Compatibility Section 13 = Inspection and Right of Entry, Reporting, and Record Keeping. WWQRR CHAPTER 17, SECTIONS 9 13 PAGE 17-18
  • Slide 28
  • CHAPTER 17, SECTION 9 New UST Systems. Any owner and/or operator who brings an underground storage tank system into use after May 8, 1986,shall, within thirty (30) days of bringing such tank into use, submit, on the form prescribed by the department, a notice of the existence of such tank system to the department. Fees. Owners and/or operators of storage tank systems shall pay the annual fees specified by W.S. 35-11-1425 no later than January 1 of each year or thirty (30) days after the first invoice, whichever is the later date. Fees are not prorated, the fee is assessed based on a calendar year. Fees begin on the date when the tank is first filled with a regulated substance and end on the date when the tank is placed permanently out of service or converted to a non-regulated use under these regulations. Certification. All owners and/or operators of new UST systems shall certify on the notification form conformance with the following requirements of Section 6(a),6(b), 6(c), 6(d), as well as Release Detection Requirements in Sections 14-17 and Financial responsibility requirements in Chapter 19 !
  • Slide 29
  • CHAPTER 17, SECTION 9 Installer Certification. All owners and/or operators of new UST systems shall ensure that the installer certifies on the notification form that the methods used to install the tanks and piping complies with the requirements in Section 6(d). Requirements for sellers. After the effective date of these regulations, any person who sells a tank intended to be used as a regulated storage tank, and any person who transfers an existing storage tank system shall notify the purchaser of such tank of the owner's notification obligations in accordance with this section. After the effective date of these regulations, any person who sells a contaminated site shall notify the purchaser that the site is a contaminated site subject to requirements of this chapter. Transfer of Control. Prior to the transfer of control of a storage tank system to a different owner and/or operator, notification of the transfer shall be provided to the department pursuant to W.S. 35-11-1420(a). Such notifications shall be provided on a form developed and provided by the department.
  • Slide 30
  • Notify the Secretary of State that a change of ownership has taken place. Provide copies of leak detection records for the past three years to the new owner. Notify the new owner that that there are requirements under the storage tank program. File a state form, signed by the current owner and the new owner showing that the transfer has taken place Chapter 17, Section 9(f)
  • Slide 31
  • CHAPTER 17, SECTION 10 PAGE 17-19 Owners and/or operators of storage tank systems shall ensure that releases due to spilling or overfilling do not occur. The owner and/or operator shall ensure that the volume available in the tank is greater than the volume of regulated substance to be transferred to the tank before the transfer is made. The owner and/or operator shall also insure that the transfer operation is monitored constantly to prevent overfilling and spilling. Owners and/or operators shall report, investigate, and clean up any spills and overfills in accordance with Section 22. Surface spills that occur at a storage tank facility during the transfer of a regulated substance to the tank are required to be reported and cleaned up by any person owning or having controlled the regulated substance pursuant to Section 22(a) of this Chapter, and Chapter 4, Water Quality Rules and Regulations.
  • Slide 32
  • CHAPTER 17, SECTION 11 PAGE 17-20 All owners and/or operators of steel storage tank systems with CP shall comply with the following requirements to ensure that releases due to corrosion are prevented for as long as the storage tank system is used to store regulated substances: Continuous Operation. All CP systems shall be operate and maintained to continuously provide corrosion protection to the metal components of that portion of the tank and piping that routinely contain regulated substances and are in contact with the ground. Once installed, CP systems shall not be removed, even if the tank has also been internally lined, as long as steel tanks or connected piping exist on that site. This does not preclude replacement of parts of the CP system which have become defective.
  • Slide 33
  • CHAPTER 17, SECTION 11 Periodic Inspections. All storage tank systems equipped with CP systems shall be inspected for proper operation by a qualified CP tester in accordance with the following requirements: (i) All CP systems shall be tested within six (6) months of installation and at least once every three (3) years thereafter. (ii) The criteria that are used to determine that CP is adequate shall be in accordance with the NACE Standard RP0285-2002, "Control of External Corrosion on Metallic that is Buried, Partially Buried, or Submerged Liquid Storage Systems. (iii) All CP systems shall be tested within six months of any repair or substantial modification to the storage tank system, or any other installation on the facility requiring excavation, in accordance with NACE Standard RP0285-2002.
  • Slide 34
  • Slide 35
  • December 1, 2010 June 1, 2011 December 1, 2011 June 1, 2013 Chapter 17, Section 11(b)(i) on page 17-20 STI-P3 is a registered trademark of the Steel Tank Institute. STI-P3 tanks have 3 corrosion prevention features: A sacrificial anode, a dielectric coating on the tank and dielectric bushings in all of the tank bungs.
  • Slide 36
  • August 17, 2011 February 17, 2011 August 17, 2013 February 17, 2013 Chapter 17, Section 11(b)(i) on page17-20
  • Slide 37
  • File the report and do nothing else. Have the cathodic protection tester install additional anodes. Wet the ground around the sacrificial anodes and retest the system. Investigate the failing result retest the system and if it fails again hire a licensed corrosion expert to design the repairs or replacement system. Chapter 17, Section 11(a) on page17-20 & Section 47(b) page 17-103.
  • Slide 38
  • The last two tests The last three tests The last three years worth Every test since the tank was first installed. Chapter 17, Section 11(d)(i) on page17-21
  • Slide 39
  • Slide 40
  • CHAPTER 17, SECTION 11 Impressed Current Systems. Storage tank systems with impressed current CP systems shall also be inspected by the owner and/or operator every sixty (60) days to ensure the equipment is running properly. The owner and/or operator shall make a record of these inspections, including the date of the inspection, the voltage reading on the rectifier, the amperage reading on the rectifier, and the hour reading on a properly connected hour meter showing how long the system has operated since the last inspection. The owner and/or operator shall compare those readings to the readings determined to be correct during the last inspection required under paragraph (b) of this section. Large changes in the voltage or amperage readings, or zero readings, shall be investigated by the owner and/or operator. Records. For storage tank systems using CP, records of the operation of the CP system shall be maintained in accordance with Section 13(c), to demonstrate compliance with the performance standards in this section.
  • Slide 41
  • Slide 42
  • All tanks and pressurized lines. All automatic tank gauging systems. All corrosion protection systems, regardless of the type. All automatic line leak detectors, regardless of the type. Chapter 17, Section 11(b)(iii) on page 17-20
  • Slide 43
  • October 1, 2010 April 1, 2011 April 1, 2013 Never, this is an impressed current system. Chapter 17, Section 11(b)(i) on page 17-20
  • Slide 44
  • The last two The last three The last three years worth. Six months worth, regardless of how often it is checked. Chapter 17, Section 11(d)(ii) on page 17-21
  • Slide 45
  • CHAPTER 17, SECTION 12 PAGE 17-21 Storage tank system(s) shall be made of, or lined with, materials that are compatible with the regulated substance stored. Owners and/or operators storing alcohol blended gasoline shall use the following industry standards or practices to comply with this section: (i) API Publication 1626, "Storing and Handling Ethanol and Gasoline-Ethanol Blends at Distribution Terminals and Service Stations"; and (ii) API Publication 1627, "Storage and Handling of Gasoline-Methanol Blends at Distribution Terminals and Service Stations".
  • Slide 46
  • Institute groundwater monitoring for dissolved alcohol. Replace all tanks and lines before the change is made, new tanks and lines must be double walled. Insure that the there are no plastic parts that contact the E-85. All plastic dissolves in E-85. Insure that all of the tanks, dispensers, lines, leak detection equipment, pipe dope, glue, and gasket materials are compatible with E-85. Chapter 17, Section 12 on page 17-21
  • Slide 47
  • CHAPTER 17, SECTION 13 PAGE 17-22 Inspection and Right of Entry. Any authorized agent of the State of Wyoming has the right of entry for inspection, assessments and corrective actions in accordance with the provisions of W.S. 35-11-1422. Owners and/or operators shall cooperate fully with inspections, including providing access to all manholes, dispenser cabinets, CP rectifiers, and tank monitoring equipment. Compliance with this section will require that owners and/or operators open manholes and other access points so that DEQ inspectors may see the condition of all equipment. Recordkeeping. Owners and/or operators shall submit the following information to the department: (i) Documentation of operation of CP Systems (Section 11); (ii) Documentation of storage tank system repairs (Section 8); (iii) Compliance with release detection requirements (Section 14 through 18 for USTs and Sections 36 and 37 for ASTs); and (iv) Results of the site investigation conducted at permanent closure and changes in service (Section 31).
  • Slide 48
  • CHAPTER 17, SECTION 13 Availability and maintenance of records. Owners and/or operators of UST systems shall keep the records required either: (i) At the storage tank site and immediately available for inspection by the department; or (ii) At a readily available alternate site and be provided for inspection to the department, upon request. The readily available alternative site shall be within the boundaries of the State of Wyoming. If records are to be kept at an alternate site, the department shall be notified in writing of the name, address and telephone number for that alternate facility. Operators Annual Inspection. Storage tank system owners and/or operators shall provide an annual report of inspection for the entire facility. An annual inspection is to be conducted either by the owner, the operator, or a qualified consultant. The inspector shall meet all of the qualifications as a CP tester if he or she inspects a CP system. Reference CHAPTER 17, SECTION 13(e) for additional Requirements
  • Slide 49
  • Slide 50
  • Slide 51
  • Slide 52
  • Results of site investigations Documentation of storage tank system repairs Documentation of the operation of CP systems Records showing how often the fuel filters were changed Chapter 17, Section 13(c) on page 17-22
  • Slide 53
  • The facility itself. An area office located in Casper, Wyoming. At the corporate office in Saint Louis, Missouri. At the registered agents office in Cheyenne, Wyoming. Chapter 17, Section 13(d) on page 17-23
  • Slide 54
  • Clean up all operating equipment before the inspection. Check all of your spill buckets for leakage before the inspection. Close down the station to prevent injury to the inspectors during the inspection. Open all manholes, dispenser cabinets, rectifier boxes, and tank monitoring equipment. Chapter 17, Section 13(b)(vi) on page17-22
  • Slide 55
  • Documentation of every fuel delivery for the preceding year. Records of leak detection for the preceding year. The name, address, and Fuel Tax license number for every fuel supplier used for the preceding year. The manufacturers name, model number, and serial number for all leak detection equipment used to comply with any requirement of the storage tank program. Chapter 17, Section 13(e)(v) on page 17-24
  • Slide 56
  • Section 14 = Requirements for all UST Systems Section 15 = Petroleum USTs with a capacity of 2,000 gallons or less. Section 16 = Petroleum USTs with a capacity of more than 2,000 gallons. Section 17 = Hazardous Substance UST Systems Section 18 = Release Detection Recordkeeping for UST Owners/Operators WWQRR CHAPTER 17, SECTIONS 14 18 PAGE 17-25
  • Slide 57
  • WWQRR CHAPTER 17, SECTIONS 14 18 Release Detection. Owners and/or operators of UST systems shall provide a method, or combination of methods, of release detection that: (i) Can detect a release from any portion of the tank and the connected piping that routinely contains a regulated substance; (ii) Is installed, calibrated, operated, and maintained in accordance with the manufacturer's instructions, including routine maintenance and service checks showing that the leak detection equipment is fully operational and in proper calibration; and (iii) Meets the performance requirements in Sections 15, 16, or 17. Reference CHAPTER 17, SECTION 14(b) 14(f) for additional Requirements
  • Slide 58
  • WWQRR CHAPTER 17, SECTIONS 14 18 Release Reporting. When a release detection method operated in accordance with the performance standards in Sections 15, 16, or 17 indicates a release may have occurred, owners and/or operators shall notify the department in accordance with Part E. Timing. Owners and/or operators of new or existing UST systems shall comply with the release detection requirements of this part immediately upon installation. USTs without leak detection. Any owner and/or operator of an UST system that cannot apply a method of release detection that complies with the requirements of this part shall complete the closure procedures in Part G. Petroleum USTs less than 1000 gallons. Owners and/or operators of USTs with a capacity of one thousand (1,000) gallons or less may use manual tank gauging as the sole leak detection method for the tank. Manual tank gauging shall be conducted weekly in accordance with Section 15 (a).
  • Slide 59
  • WWQRR CHAPTER 17, SECTIONS 14 18 Petroleum USTs with a throughput of less than 15,000 gallons per month. (No longer required to perform tracer survey) Not withstanding any other provision of this chapter, owners and/or operators of USTs with a throughput of less than 15,000 gallons per month may use inventory control as a monthly monitoring technique provided that: (i) the inventory control balances within 150 gallons per month. In the event that a single month fails to balance within 150 gallons, the operator shall immediately submit that month to an outside vendor for Statistical Inventory Reconciliation; (ii) the USTs are secured against theft in such a way that any theft is readily obvious; and (iii) all of the requirements listed under Section 16(a) are met.
  • Slide 60
  • Leak detection is required for all pressurized piping. There are three types of line leak detectors Mechanical line leak detectors Electronic line leak detectors Sump sensors U.S. Suction lines must be pressure tested
  • Slide 61
  • Slide 62
  • Slide 63
  • CHAPTER 17, SEC. 14 (g) CHAPTER 17, SEC. 13 (e)(ii)
  • Slide 64
  • Slide 65
  • CHAPTER 17, SEC. 14 (g) CHAPTER 17, SEC. 13 (e)(iii)(B)
  • Slide 66
  • September 17, 2010 March 17, 2011 March 17, 2012 March 17, 2013 Chapter 17, Section 14(g)(i)(B) on page17-26
  • Slide 67
  • Visually inspect the dispenser hoses for cracks. Pressure test the lines at 1.5 times operating pressure. Remove the line leak detector and clean the operating part of the valve. Purge the line, place the line on a vacuum and see if the line will hold a vacuum. Chapter 17, Section 14(g)(i)(B)(1) on page17-27
  • Slide 68
  • Nothing. Pressure test the lines at 1.5 times of the operating pressure. Pressure test the lines at standard temperature and pressure. Remove the impact valves beneath each dispenser and check the rubber seals for wear. Chapter 17, Section 14(g)(i)(B)(2) on page17-26
  • Slide 69
  • April 30, 2010 September 30, 2010 March 1, 2013 Never, these are double wall lines Chapter 17, Section 14(g)(i)(B) on page17-26
  • Slide 70
  • Once every month. Once every six months. Once every three years. Annually, within one year of the previous test. Chapter 17, Section 14(g)(i)(B) on page 17-26
  • Slide 71
  • CHAPTER 17, SEC. 14 (g)(i)(B)(2) CHAPTER 17, SEC. 13 (e) CHAPTER 17,SEC. 19(c)
  • Slide 72
  • Slide 73
  • Slide 74
  • Slide 75
  • Slide 76
  • Slide 77
  • Slide 78
  • Slide 79
  • Find some way to silence the alarm, and note this for the next operators annual inspection. Open the sumps and determine if the sump sensors alarmed because of water or product in the sumps. Remove all of the water, if any, from the sumps and have the sump sensors re-set on the bottom of the sump. If there is product in the sump, report a suspected release, have tests run to locate the leak, have the equipment repaired, and dispose of spilled product properly. Chapter 17, Section 19(c) on page17-42
  • Slide 80
  • January 1, 2011 April 21, 2011 October 21, 2010 April 21, 2013 Chapter 17, Section 13(e)(iii)(c) on page 17-24
  • Slide 81
  • Chapter 17, Sec. 14 (g) (ii and iii) Page 17-27 There are two types of suction systems, U.S. Suction and Exempt Suction
  • Slide 82
  • Slide 83
  • Slide 84
  • Monthly. Once every three years. Annually within one year of the last test. Never, this is an exempt suction system. Chapter 17, Section 14(g)(i)(iii) on page17-27
  • Slide 85
  • The system must be constructed with double wall lines. The lines must be pressure tested once every three years. The system must be equipped with electronic line leak detectors. The system must be equipped with mechanical line leak detectors. Chapter 17, Section 14(g)(ii) on page17-27
  • Slide 86
  • WWQRR CHAPTER 17, SECTIONS 14 (h) New UST installations and repairs. Regardless of any other section in this chapter, after the effective date of this chapter, all new and replacement installations and repairs of existing piping shall meet the following secondary containment criteria: (i) New or replacement tanks shall be provided with full secondary containment in the form of: (a) Double Walled tanks; or (b) Single wall tanks with a polyethylene tank jacket. (ii) New or replacement connected piping shall be provided with full secondary containment in the form of: (a) Double wall lines; or (b) Single wall lines with secondary containment piping. And (iii) All dispensers must be equipped with full secondary containment in the form of dispenser pans. (iv) All secondary containment systems shall be monitored in accordance with Section 16(f).
  • Slide 87
  • WWQRR CHAPTER 17, SECTION 15 PAGE 17- 28 Manual tank gauging. Manual tank gauging shall meet the following requirements: (i) Tank liquid level measurements shall be taken at the beginning and ending of a period of at least thirty-six (36) hours during which no liquid is added to or removed from the tank; (ii) Level measurements shall be based on an average of two (2) consecutive stick readings at both the beginning and end of the period; (iii) The equipment used shall be capable of measuring the depth of the regulated substance over the full range of the USTs height to the nearest one- eighth (1/8) of an inch;
  • Slide 88
  • CHAPTER 17, SEC. 15 PAGE 17-29
  • Slide 89
  • 24 Hrs 36 Hrs 44 Hrs 58 Hrs Chapter 17, Section 15(a)(iv) on page 17-29
  • Slide 90
  • CHAPTER 17, SEC. 16 (a) Page 17-30 Petroleum USTs with a capacity of More than 2,000 gallons
  • Slide 91
  • Report and investigate a suspected release Conduct an API 653 inspection of the tank. Remove all the product from the tank until it can be verified that the tank is not leaking. Check the inventory control records carefully and wait until the next month to report a release Chapter 17, Section 16(a)(viii) on page 17-31
  • Slide 92
  • Within 1% Within 6 cubic inches in 5 gallons Within 2.5 ounces in 10 gallons 25 milliliters in 10 liters Chapter 17, Section 16(a) (v) on page 17-30
  • Slide 93
  • Nothing, the automatic tank gauge passed both months. Report and investigate a suspected release. Nothing, both months the IC records were over. Immediately empty the tank until it can be determined if it leaked. Chapter 17, Section 16(a)(viii)(A) on page 17-31 Allowable limit was 230 gallons!!!
  • Slide 94
  • Recheck the figures, this is too far off to ignore. Nothing, inventory control passes for that month. Submit the records to a statistical inventory reconciliation provider Report a suspected release and conduct a tank tightness test and line pressure test. Chapter 17, Section 16(a)(viii)(A) on page 17-31 Allowable amount was 785 gallons
  • Slide 95
  • Report a suspected release and investigate. Check the calibration of the automatic tank gauge. Check the calibration of the meters in the dispensers. Make sure that the inventory control records are closed at the same time each day and that there are no mathematical mistakes. Chapter 17, Section 16(a)(viii)(C) on page 17-31
  • Slide 96
  • Tracer Surveys. Tank Tightness Testing. Groundwater Monitoring. Statistical Inventory Reconciliation Chapter 17, Section 16(a)(ix) on Page17-31
  • Slide 97
  • CHAPTER 17, SEC. 16 (b) PAGE 17-32
  • Slide 98
  • Only the tank and the connected piping. The tank, the connected piping and all vent lines. That portion of the tank that routinely contains regulated substances. The tank, connected piping and all of the product lines inside the dispenser cabinet. Chapter 17, Section 16(b) Page 17-32
  • Slide 99
  • CHAPTER 17, SEC. 16 (c) PAGE 17-32
  • Slide 100
  • ANYTHING OTHER THAN A PASSING RESULT REQUIRES INVESTIGATION. ONE PASSING RESULT FOR EACH TANK IS REQUIRED FOR EACH CALENDAR MONTH THAT YOU OPERATE.
  • Slide 101
  • Slide 102
  • Tank tightness testing annually. Statistical inventory reconciliation. Inventory control or another method of equivalent performance. Nothing, automatic tank gauging does not require anything further. Chapter 17, Section 16(c)(i) on page 17-32
  • Slide 103
  • .1 .2 3 1.5 Times Operating Pressure Chapter 17, Section 16(c)(i) on page 17-32
  • Slide 104
  • 5 gallons per day. .1 gallons per hour. .2 gallons per hour. 50 gallons per month. Chapter 17, Section 16(c) on page 17-32
  • Slide 105
  • Report a suspected release and investigate. Have the tank gauge re-calibrated and all of the probes cleaned and checked. Re-check the inventory control records to make sure that the tank is not leaking. Wait until the second consecutive month and then report a suspected release if a passing result is not obtained. Chapter 17, Section 16(c)(ii)(C) page 17-32
  • Slide 106
  • CHAPTER 17, SEC. 16 (d) PAGE 17-33
  • Slide 107
  • All acids, strong caustics, and aqueous solutions. Only those substances that are not liquids at standard temperature and pressure. Those that have a specific gravity that is greater than the specific gravity of diesel. Only those substances that are sufficiently volatile to be detected by the monitoring devices. Chapter 17, Section 16(d)(ii) on page17-33
  • Slide 108
  • CHAPTER 17, SEC. 16 (e) PAGE 17-34
  • Slide 109
  • Any trace of product on the groundwater, even a sheen on the surface. Dissolved products in groundwater down to the drinking water equivalent level. Floating products at least 1/8 thick on the groundwater. Sinking products that accumulate at the bottom of the well. Chapter 17. Section 16(e)(vi) on page 17-34
  • Slide 110
  • 5 feet. 10 feet. 20 feet. 100 feet. Chapter 17, Section 16(e)(ii) on page 17-34
  • Slide 111
  • CHAPTER 17, SEC. 16 (f) PAGE 17-35 You cannot use interstitial monitoring unless you have a double wall tank. Interstitial monitoring looks for product between the two walls of a double wall tank. All new or replacement tanks have to be double wall with interstitial monitoring.
  • Slide 112
  • Once a week. Twice a month. Once every thirty (30) days. You never have to look at this system as long as the alarm does not go off. Chapter 17, Section 16 Opening Statement on page17-30 Note that this section applies to all leak detection methods.
  • Slide 113
  • He has to report a suspected release and investigate. He has to take the tank out of service and repair or replace the tank. He has to have any replacement tank inspected by the department during installation. If the operator cannot repair the tank he can now consider this tank to be a single wall tank. He will have to change monitoring methods. Chapter 17, Section 16(f) on page17-35 W.S. 35-11-1429 on page 12
  • Slide 114
  • Report a suspected release and investigate. Reset the system and see if it alarms again. Have a service company raise the level of the interstitial alarm. Ignore the alarm, it is probably just rainwater or a short circuit. Chapter 17, Section (f)(iv) on page 17-36
  • Slide 115
  • CHAPTER 17, SEC. 16 (g) PAGE 17-37
  • Slide 116
  • This is not a passing result
  • Slide 117
  • Report a confirmed release to the National Response Center. Nothing unless he receives two inconclusive results in a row. Before doing anything else, run a Tracer Survey on the tank system that had the inconclusive result. Investigate the inconclusive result by auditing the information submitted to the SIR company and re-submitting the audited information. Chapter 17, Section 16 (g)(iv) on page17-37
  • Slide 118
  • Investigate a suspected release. Report a suspected release. Place the failing tank in Temporarily Out of Use condition within 5 days. Audit the input records to the SIR company to insure that the failing result was not due to an error in data entry. Chapter 17, Section 16(g)(v)(A) on page17-37
  • Slide 119
  • correct for tank tilt. automatically exclude bad data. detect a leak of 150 gallons per month. allow for electronic submission of the data through the internet. Chapter 17, Section 16(g)(ii) on page 17-37 Note that all Tank leak detection methods must be able to detect 150 gallons per month
  • Slide 120
  • CHAPTER 17, SEC. 16 (h) PAGE 17-37
  • Slide 121
  • Anytime during the month. Before the 1 st of every month. Before the 25 th of each month. After the last day of the month. Chapter 17, Section 16(h)(iv) on page 17-38
  • Slide 122
  • .10 gallons per hour. 150 gallons per month 1.0 gallons per minute 300 gallons per month. Chapter 17, Section 16(h)(i) on page 17-38
  • Slide 123
  • 75% 95% 89.5% 99.9% Chapter 17, Section 16(h)(i) on page 17-38 Note that all leak detection methods must have the same probability of detecting a release.
  • Slide 124
  • Other methods can be found in Chapter 17, Sec. 16 (j) on page 17-38
  • Slide 125
  • CHAPTER 17, SECTION. 17 Page 17-39 Hazardous substance UST systems shall have a secondary containment system, be constructed with double walled tanks, or be constructed with an external liner or vault surrounding the entire tank system. Hazard Substance UST Systems
  • Slide 126
  • CHAPTER 17, SECTION. 18 Page17-41 All UST system owners and/or operators shall maintain records in accordance with Section 13 demonstrating compliance with all applicable requirements of this part. Release Detection Recordkeeping for UST Owners and/or Operators
  • Slide 127
  • WWQRR CHAPTER 17, SECTIONS 19 28 PAGE 17-42 Section 19 = Reporting of Suspected Releases Section 20 = Release Investigation & Confirmation for Eligible Owners and/or Operators Section 21 = Release Investigation and Confirmation for Owners and/or Operators Not Eligible for the Corrective Action Account Section 22 = Reporting and Cleanup of Spills and Overfills Section 23 = General Section 24 = Owners and/or operators Not Eligible for the State Corrective Action Program Section 25 = Owners and/or operators Eligible for the State Corrective Action Program Section 26 = Public Participation Section 27 = Corrective Action Prioritization Ranking System Section 28 = Termination of Corrective Actions
  • Slide 128
  • Release Is the release of product that is eligible for cleanup under the corrective action account and must have originated from a regulated portion of the tank. Spill Is a spill that is not eligible for cleanup by the corrective action account, such as overfilling the tank or a customer overfills their vehicle.
  • Slide 129
  • Report a spill and clean up the spill as quickly as possible. Call the delivery company to get them to clean up the spill. Call the fire department and have them flush the oil into the storm drain. File a claim with your insurance company to get them to clean up the spill. WWQRR, Chapter 17, Section 22 Page 17-45
  • Slide 130
  • Report and clean up the spill. Clean up the spill with detergent. Wait until the gasoline evaporates before allowing any more sales. Call the fire department and have them wash down the spilled gasoline. WWQRR, Chapter 17, Section 22 Page 17-45
  • Slide 131
  • Within 24 hours Within 48 hours Within 7 days Within 30 days WWQRR, Chapter 17, Section 19 Page 17-42
  • Slide 132
  • Within 24 hours Within 48 hours Within 7 days Within 30 days WWQRR, Chapter 17, Section 20 Page 17-43
  • Slide 133
  • WWQRR CHAPTER 17, SECTION 29 PAGE 17-57 Section 29 = MSA Requirements
  • Slide 134
  • WWQRR CHAPTER 17, SECTIONS 30 - 32 PAGE 17-64 Section 30 = Temporary Closure Section 31 = Permanent Closure and Changes in Service Section 32 = Applicability to Previously Closed or Abandoned Storage Tank Systems
  • Slide 135
  • All sump sensors must be tested annually. The automatic tank gauge must be checked monthly. The automatic line leak detectors must be tested annually. The cathodic protection system, of either type, must be tested on the same schedule as an operating tank. Chapter 17, Section 30(a) on page 17-64
  • Slide 136
  • WWQRR CHAPTER 17, SECTIONS 33 PAGE 17-67 Section 33 = General
  • Slide 137
  • WWQRR CHAPTER 17, SECTIONS 34 - 37 PAGE 68 Section 34 = Tanks Covered Section 35 = Construction Requirements for AST Systems Section 36 = AST Leak Detection Requirements Section 37 = Leak Detection Requirements for Underground Lines Connected ASTS.
  • Slide 138
  • the storage capacity of the largest tank twice the storage capacity of the largest tank the total storage capacity of both of his tanks 110% of the storage capacity of the largest tank Chapter 17, Section 35(b) 17-68
  • Slide 139
  • A foam fire suppression system. A chain link fence no less than six (6) feet high. A permanently mounted ladder and catwalk to the top of the tanks. An emergency switch not less than 20 feet or more than 100 feet from the dispensers. Chapter 17, Section 35 (r), (t) and (x) on pages 17-75 and 76
  • Slide 140
  • All aboveground lines must be made of steel. All underground lines must be double walled. All underground lines must be non-corrodible. All underground lines must be encased in concrete. Chapter 17, Section 35(h) on page 17-71
  • Slide 141
  • A concrete block wall. Boulders around the tank. A corrugated steel secondary containment structure 4 inch steel pipe guard posts not more than 4 feet apart, filled with concrete. Chapter 17, Section 35(c) on page 17-68
  • Slide 142
  • Painting the tank annually. An impressed current system. A horizontal cylinder tank on saddles. A tank constructed to UL 2085 standards. Chapter 17, Section 35(d) on page 17-69