14
STEREO - Solar Terrestrial Relations Observatory Mission STEREO STEREO Science Team Meeting May 2, 2005 Presented by Edward Reynolds APL STEREO Project Manager

STEREO - Solar Terrestrial Relations Observatory Mission STEREO STEREO Science Team Meeting May 2, 2005 Presented by Edward Reynolds APL STEREO Project

Embed Size (px)

Citation preview

STEREO - Solar Terrestrial Relations Observatory Mission

STEREO

STEREO Science Team Meeting

May 2, 2005Presented by

Edward ReynoldsAPL STEREO Project Manager

(ELR 4/29/05) - 2STEREO - Solar Terrestrial Relations Observatory Mission

STEREO

General Status

• Observatory Integration status– Core spacecraft integration is nearly complete– Both spacecraft are ready for instrument integration

• Mission Operations Center– Facility complete and equipment operational– MOC facility used for Mission Simulations and DSN tests– POC facility ready for instrument teams

• Four Mission Simulations performed on each spacecraft• Five Dress rehearsals performed using equipment and

personnel being planned.

(ELR 4/29/05) - 3STEREO - Solar Terrestrial Relations Observatory Mission

STEREO

Spacecraft Stacking Operations

(ELR 4/29/05) - 4STEREO - Solar Terrestrial Relations Observatory Mission

STEREO

Spacecraft Stack – Dynamics Load Testing

(ELR 4/29/05) - 5STEREO - Solar Terrestrial Relations Observatory Mission

STEREO

Integration Status

• Spacecraft integration at APL – Both spacecraft integrated within the same room– Facility controlled for contamination, ESD, and security– Spacecraft to remain at APL until after stacked vibration testing

• Most environmental testing to occur at GSFC– Acoustics, thermal vacuum, shock, ESD, mass properties

• Launch activities will occur over a 11-week period– While at GSFC and Launch site, spacecraft will be controlled from

MOC at APL– Project will follow security procedures of KSC/CCAFS– Background checks need to be submitted in a timely manner– Visitors and guests will be escorted when required– Once spacecraft is fueled, access around it will be limited to

essential personnel

(ELR 4/29/05) - 6STEREO - Solar Terrestrial Relations Observatory Mission

STEREO

STEREO I&T Flow

12/1/2004 1/1/2005 2/1/2005 3/1/2005 4/1/2005 5/1/2005 6/1/2005 7/1/2005

CTTHarness insp.

PDU Int.IEM, Power System,

RF System, AutonomyIEM, G&C,IDPU, SIM1

HGA, battery, CPT,blankets, Sim2, align

1/1/2005 2/1/2005 3/1/2005 4/1/2005 5/1/2005 6/1/2005 7/1/2005 8/1/2005

CTTInstrument integration, thermal closeout,

phasing, alignments, SIM2Harness install,

Hi-PotPDU, EM IEM,

Power Sys, RF SysG&C, Autonomy, SIM1

Buses CompleteSpacecraft A Integration - APL

Spacecraft B Integration - APL

9/1/2005 10/1/2005 11/1/2005 12/1/2005

Vib, Shock,Align

Spin, Mass Props

EMC Testing

Thermal Vacuum Balance& Cycling (SIM3, CPT)

APL GSFC GSFC: SES ChamberCPT,Align.

Pack & Ship

1/1/2006 2/1/2006

Unpack& Setup

Alignment, CPT,& DSN

SIM4, Pyro,Lens C/O

Leak, Load Prop, Spin& Battery Condition

Canning, Transport,& Pad Operations

Astrotech or AE

Transport

CCAFS: Pad 17

Launch Site Ops: KSC

Environmental Testing

Instrument integration, thermal closeout,phasing, alignments, SIM2

BOOM

Note: The instrument dates denote their arrival at Receiving at APL and not the date of their installation onto a spacecraft

Rev: April 27, 2005

CPT

CPT

CTT

IDPU

Env.Prep

Env.Prep

Acoustic, ShockFunctional

Ship to GSFC

SWAV

SEP

SEP

PLAS

PLAS

HI

HI-B

SEB, SCIP

SCIP, SEBBOOM, IDPU

SWAV

(ELR 4/29/05) - 7STEREO - Solar Terrestrial Relations Observatory Mission

STEREO

STEREORecent Accomplishments

- Hi-Shear under contract for Pyro Sep-Nuts (replaces STARSYS QwkNuts)- DSN/CTT Testing Completed on Spacecraft A & B

- Performance and Operations

- Power, RF, G&C subsystems integrated on Spacecraft A & B- Propulsion system integrated and leak tested on Spacecraft A & B- IEM B cold lock-up root cause identified and mitigated,

- IEM B integrated on Spacecraft

- Mission Sim #1 on both Spacecraft A & B- Launch, Separation, Detumble, 1st contact, delta-V and momentum dumps, EA mode

- IMPACT IDPU & Boom Integrated on Spacecraft A- Command Loss Timer Test (72-hour) Spacecraft A- 85% of thermal blanketing complete- Flight batteries ready for integration- Solar arrays delivered and undergoing flash illumination testing- HGA assemblies completing TV chamber testing (deployments, actuations)

(ELR 4/29/05) - 8STEREO - Solar Terrestrial Relations Observatory Mission

STEREO

Photo Gallery

(ELR 4/29/05) - 9STEREO - Solar Terrestrial Relations Observatory Mission

STEREO

Educational Video Production

(ELR 4/29/05) - 10STEREO - Solar Terrestrial Relations Observatory Mission

STEREO

Mission Orbit

SunSun

Earth

Ahead @ +22/year

Behind @ -22/year

Heliocentric Inertial Coordinates(Ecliptic Plane Projection)

Ahead

Behind

Earth

1 yr.

2 yr.

3 yr.

4 yr.

1yr.

2yr.

3 yr.4 yr.

5 yr.

5 yr.

(ELR 4/29/05) - 11STEREO - Solar Terrestrial Relations Observatory Mission

STEREO

Phasing Orbit

Mission TimelineLaunch: Feb. 11 – 24, 2006 ~4:00 am EST

S1: April 8, 2006S2: May 16, 2006

Lunar Orbit

+22°/yr Ahead

-22°/yr Behind

• 4.5 Revolutions in Phasing Orbit• First lunar swingby, S1

– Behind escapes– Ahead spacecraft enters 1 month ‘outer loop’

• Second lunar swingby, S2– Ahead escapes

To Sun A1

A2A3

A4 A5S1

S2

(ELR 4/29/05) - 12STEREO - Solar Terrestrial Relations Observatory Mission

STEREO

Day 1 (11-Feb) Phasing Orbit Schematic

A17.2 / 77

A574.3 / 137

TIP42 min / h=178 km

C3 = -1.6 km2/s2 P114.5 / 1.32

P229.1 / 1.58

P340.4 / 1.80

P452.0 / 2.21

S294.5

S155.8

Behind

Ahead

KeyEvent ID

Elapsed Time (days)/Distance (Re)

A221.8 / 77

A334.7 / 65

A446.7 / 65

= Planned V

= TCM V

SummaryMin. Perigee Altitude = 2,036 km @ P1Lunar Flyby Radius: S1: Ahead = 12,361 km, Behind = 8,105 kmS2: Ahead = 16,214 km

(ELR 4/29/05) - 13STEREO - Solar Terrestrial Relations Observatory Mission

STEREO

Spacecraft Mission Operations Mission Operations Center Facility

MOC Space

CommandPit

HIL AHIL B

BPrimaryBackup

APrimaryBackup

AssessmentWorkstations

EngineeringDisplay

Workstations

(ELR 4/29/05) - 14STEREO - Solar Terrestrial Relations Observatory Mission

STEREO

Spacecraft Mission Operations Mission Operations Center Facility – At APL

POC Space