Steam Net Simulation at Borealis' Cracker Site in

Stenungsund

Presentation at Nordic Process Control Workshop 15, Porsgrunn

29 January 2009Veronica Olesen

Page 2: Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

Solvina

Göteborg

Västerås

Page 3: Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

•Power Engineering •Process Engineering•Automatic Control •Chemical Engineering •Computer Technology •Mathematics •Nuclear Power Safety

•Power Engineering •Process Engineering•Automatic Control •Chemical Engineering •Computer Technology •Mathematics •Nuclear Power Safety

Solvina

Page 4: Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

Borealis Stenungsund

Page 5: Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

Borealis Stenungsund

Ethylene

HP steam

LP steam from LD5

New

Page 6: Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

Cracker Steam NetFrom production

Boilers

To PE

To processesDump

HP

MP

LP

From LD5

NewNew

Page 7: Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

Trip of LD5From production

Boilers

To PE

To processesDump

From LD5

Page 8: Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

Trip of LD5From production

Boilers

To PE

To processesDump

From LD5

Page 9: Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

Trip of LD5From production

Boilers

To PE

To processesDump

From LD5

?

?

?

Major pressure drops

Page 10: Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

Pressure ControlFrom production

Boilers

To PE

To processesDump

From LD5

Page 11: Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

Findings• Restrictions necessary on the PE site to

slow down the course of events.

Page 12: Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

Findings• Restrictions necessary on the PE site to

slow down the course of events.• Use the same measuring point for all

control loops in the LP net.

PI PIPI

Page 13: Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

Findings• Restrictions necessary on the PE site to

slow down the course of events.• Use the same measuring point for all

control loops in the LP net.• Feed forward needed in boiler control

Accep

tab

le p

ressu

re

ran

ge

t0

Page 14: Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

Findings• Restrictions necessary on the PE site to

slow down the course of events.• Use the same measuring point for all

control loops in the LP net.• Feed forward needed in boiler control• Dynamic simulations necessary prior to

mayor changes.

Page 15: Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

Thank you for listening

Questions?