Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Status of Polarimeter GEMs
Kondo Gnanvo
SBS Summer Collaboration Meeting
07/13/2017
Outline
▪ Status of the Production
▪ Activities in the GEM “Clean” room space
▪ Preparation for GMn Experiment
SBS Summer Coll. Meeting @ JLab
Overview of SBS GEM Trackers modules
▪ Front Tracker (FT): Track of the recoil protons
⇨ 1st tracker: 6 GEM layers, active area of 150 × 40 cm2
⇨ Layer: vertical stack of 3 GEM modules (50 × 40 cm2)
⇨ Production: 18 modules (+3 spares)
▪ Back Tracker (BT): Polarimetry of the recoil protons
⇨ 2nd & 3rd Trackers: 2 × 5 layers, active area of 200 × 60 cm2
⇨ Layer: vertical stack of 4 GEM modules (60 × 50 cm2)
⇨ Production: 40 modules (+ 8 spares)
Front Tracker layer
INFN
(Rome, Catania)
Stack of 3
GEM
mo
du
les (40
×5
0 cm
2)
Back Tracker layer
(UVa)Stack o
f 4 G
EM m
odule
s(6
0 ×
50
cm2)
Hadron arm in GEp(5)
07/13/2017 2
SBS Summer Coll. Meeting @ JLab
Production of GEM modules @ UVa
▪ 43 modules built and tested
⇨ 41 modules: 100% operational,
⇨ 2 modules: 97% OK (1 bad sector)
▪ 5 spare modules in the assembly queue
⇨ 2 almost completed, all expected by August 2017
▪ 9 modules already moved to JLab in test lab
⇨ 4 modules stored in GEM “clean” room, 5 modules on test beam stand
⇨ Next shipment of 8 modules week July 17th
▪ All 10 Al frames for Uva GEM layers in store in test lab
⇨ Frame prototype tested at UVa
⇨ One frame will be fully instrumented with 4 modules and MPD electronics
Back Tracker modules @ UVa
07/13/2017 3
Al Frame prototype with 4 UVa GEMs
X-Ray setup @ UVa
SBS Summer Coll. Meeting @ JLab
Test of GEM modules @ UVa
07/13/2017 4
Cosmic stand @ UVa
▪ Cosmic stand setup
⇨ Test that the HV sectors are all operational
⇨ Data with 4 modules fully instrumented MPD electronic
⇨ Tracking efficiency studies
▪ X-ray setup
⇨ Test the modules in high rate environment
⇨ Test DAQ in high rate and high background
⇨ Performance of x-ray background with Sr90 as source
SBS Summer Coll. Meeting @ JLab07/13/2017 5
Preliminary tracking analysis
SBS Summer Coll. Meeting @ JLab
Polarimeter GEM modules in Beam Test in Hall A (Fall 2016)
Setup in Hall A @ JLab
▪ 5 modules separated by 10 cm each: similar to a
SBS tracker configuration.
▪ Triggered by a lead-glass matrix at center
▪ Goals: Identify good tracks in a high rate,
background, effectiveness of timing and charge
correlation cuts to suppress background
▪ Placed at 70o, occupancy is ~ 1%, similar to GMn
Preliminary background suppression analysis
07/13/2017 6
SBS Summer Coll. Meeting @ JLab
▪ “Clean” room space for SBS GEM modules
⇨ Space allocated in the test lab for the storage of the GEMs modules
⇨ Migration of UVa GEM modules is ongoing
⇨ ⇨ First 4 modules arrive earlier this month
⇨ next 8 modules next week
▪ Setup of a cosmic stand for GMn GEM trackers
⇨ Goal: Have all 4 FT GEM layers (INFN) on the cosmic stand
⇨ One polarimeter UVa GEM layer on a separate setup
⇨ Cosmic data expected by 08/01/2017
▪ Goal: Full characterisation of the GEM modules
⇨ Evaluate the dead area (disabled HV sector), study efficiency, define the working HV
⇨ gas flow for each module, Full readout performance DAQ
Preparation for “Clean” Room space for SBS GEM modules
07/13/2017 7
4 UVa modules on storage shelves
Preparation for cosmic stand setupStandalone setup for UVa GEM layer frame
Bigbite Spectrometer for the GMn experiment
SBS Summer Coll. Meeting @ JLab
Preparation for GMn Experiment
GMn GEM Tracker: 4 layers
▪ Front Tracker layer: (150 cm x 40 cm) : 3 INFN modules
▪ 2 chambers already delivered @ Jlab, 2 on their way
One additional Back Tracker layer behind the GRINCH detector:
▪ Back chamber layer (200 cm x 50 cm) : 4 UVa modules
Front Tracker crate
16 MPDs (v4.0)
1 SSP
1 Trigger Supervisor
1 VME CPU or Controller
2 slots for HV PS
Back Tracker crate
7 MPDs (v.40)
1 SSP
1 Trigger Supervisor
1 VME CPU or Controller
1 slots for HV PS (or not)
2 VME crates for all 4 + 1 GEM layers
07/13/2017 8
SBS Summer Coll. Meeting @ JLab07/13/2017 9
Preparation for GMn: GEM Gas System
SBS Summer Coll. Meeting @ JLab07/13/2017 10
Preparation for GMn: GEM Gas System
SBS Summer Coll. Meeting @ JLab
Consideration on HDM cables arangment for BT layer
07/13/2017 11
Holding rails for short HDMi
cables, path panels to the
MPDI and low voltage
adapter board
Patch panels from
short to long HDMI
cables
▪ Cabling to the MPD electronics
⇨ 4 layers of BT layer read out with 4 MPD modules
⇨ Data and control signal through HDMI cables
▪ Two sets of HDMI cables:
⇨ Short cables (0.5 m to 3 m) from the back planes (GEM modules) to patch panel / connectors
⇨ Need to decide if we use same length for all cables or adapt length to minimize cross talk, noise etc …
⇨ Try out pros / cons of different length approach with the layer in “clean” room before final decision
⇨ Long cables (minimum 8 m) from the patch panel / connectors to the MPD in shielding box
⇨ Connection between long and short cables through patch panel and HDMI to HDMI connector
SBS Summer Coll. Meeting @ JLab07/13/2017 12
Preparation for GMn: HDMI cable arrangement for the BT GEM layer
Analog (data) signal ▪ Minimize number of patch panels / maximize the one to
one HDMI to HDMI connection
▪ Color coded arrangement:
▪ Magenta: direct HDMI to HDMI connection
▪ Red: 3-to-4 patch panels (analog signals)
▪ Blue: 4-to-2 patch panels (digital signals)
▪ Cyan: 12-slots backplanes
▪ Yellow and green: 5-slots backplanes
▪ Brown: BT GEM module
SBS Summer Coll. Meeting @ JLab07/13/2017 13
Preparation for GMn: HDMI cable arrangement for the BT GEM layer
Digital (control) signal ▪ Minimize number of patch panels / maximize the one to
one HDMI to HDMI connection
▪ Color coded arrangement:
▪ Magenta: direct HDMI to HDMI connection
▪ Red: 3-to-4 patch panels (analog signals)
▪ Blue: 4-to-2 patch panels (digital signals)
▪ Cyan: 12-slots backplanes
▪ Yellow and green: 5-slots backplanes
▪ Brown: BT GEM module
SBS Summer Coll. Meeting @ JLab
Production Status of Polarimeter GEM modules
⇨ 43 modules already built and fully tested
⇨ construction of the last 5 to be completed by august 2017
⇨ 9 modules already move to Jlab, remaining to be moved by set of 8 in the next few weeks
Preparation and commissioning of SBS GEMs for GMn expeiment
⇨ Acitivites in the clean room in full mode
⇨ Cosmic stand setup on going for the FT layers (4 INFN layers needed for GMn)
⇨ BT layer need for GMN in a standalone setup for test
⇨ Gas system need for the GMn GEMs has evaluated
⇨ GMn GEM electronic shielding box has been designed and scheme for optmal HDMI cabling is set
⇨ Cosmic test should be ready tp start in a few weeks
Summary
07/13/2017 14
SBS Summer Coll. Meeting @ JLab
Backup
07/13/2017 15
Triple-GEM detector
SBS Summer Coll. Meeting @ JLab
Why GEMs for Super Bigbite Spectrometer (SBS)?
2D readout strips board
GEM foil: 50 mm Kapton + few
mm copper on both sides with 70
mm holes, 140 mm pitch
Strong electrostatic field in
the GEM holes, ~ 70kV/cm
▪ SBS require high rate and good spatial resolution in trackers.
▪ Gas Electron Multiplier (GEM) detectors provide a cost effective solution for high
resolution tracking under high rates over large areas
⇨ Rate capabilities higher than many MHz/cm2, High position resolution ( < 75 μm)
⇨ Large areas (100s of m2) at modest cost, low thickness (~ 0.5% radiation length)
⇨ Used for many experiments around the world: COMPASS, Bonus, KLOE, TOTEM, STAR
FGT, ALICE TPC, pRad etc.
⇨ Future experiments with GEMs: CMS Muon Chambers upgrade, SoLID Trackers, Moller,
P2 @ Mainz, tracking at the EIC …
07/13/2017 16