State of Wyoming Capitol State of Wyoming Capitol Upgrades and Renovation Upgrades and Renovation projects projects Photos of the skylight and lighting project will be shown in chronological order, followed by photos of the Room 302 remodel. They will be updated throughout the 2008 interim as work progresses in Wyoming’s State Capitol.

State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Embed Size (px)

Citation preview

Page 1: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

State of Wyoming Capitol State of Wyoming Capitol Upgrades and Renovation projectsUpgrades and Renovation projects

Photos of the skylight and lighting project will be shown in chronological order, followed by photos of the Room 302 remodel. They will be updated throughout the 2008 interim as work progresses in Wyoming’s State Capitol.

Page 2: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Skylight & Lighting Project• In 1997, HDH Associates provided a condition report to the Wyoming Department of

Administration and Information (A&I) about weaknesses in the wire glass panels in the pyramidal skylights set in metal frames above the stained glass in the Senate and House of Representatives Chambers. The removal of the wire glass and installation of a new copper roof system was recommended.

• A&I implemented the HDH recommendations and chose to eliminate the skylights in the cupolas and replace that area with the new copper roof system.

• In 2002, the Wyoming Legislature’s Joint Appropriations Committee requested a cost estimate from A&I to restore natural sunlight in the House and Senate Chambers.

• In 2004, the Select Committee on Legislative Facilities was tasked to study the options for reopening the skylights in the House and Senate Chambers to sunlight and contracted with Hefferan Partnership Lighting Design to conduct a feasibility study.

• Based on this study, during the 2007 General Session, the Wyoming Legislature appropriated $1,200,000 for lighting and skylight renovation in the Senate and House Chambers.

• Edwards Construction of Cheyenne was awarded the contract by A&I, and LSO contracted with architect Glenn Garrett to design and install the skylights and update the lighting in the Chambers, which will restore natural light to the Chambers and better illuminate the stained glass.

• The project is expected to be completed by early fall of 2008.

Page 3: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The skylights are a result of many months of planning and hard work by the many parties involved in the project.

Page 4: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

(View facing West; April 2, 2008)

The copper shown here, above the Senate Chamber, will be removed and replaced with a new skylight

system.

Page 5: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

(View facing East; April 2, 2008)

Natural light will mean the difference between “night and day” in the House Chamber once the new skylight system is installed this

summer.

Page 6: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

(Senate Chamber; April 9, 2008)

The Senators’ desks have been covered with plastic in the Senate Chamber to protect them from dust and debris

that may fall during the skylight installation and lighting upgrades.

Page 7: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

(House of Representatives Chamber; April 9, 2008)

The Representatives’ desks have also been covered with plastic in the House Chamber to protect them from dust and

debris that may fall during the skylight installation and lighting upgrades.

Page 8: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

(House Chamber; June 26, 2008) Crews from Edwards Construction of Cheyenne use a

crane to hoist materials onto the roof of the House Chamber for the new catwalk system that will be installed.

Page 9: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

(House Chamber; June 26, 2008)

The catwalk is part of the Skylight Renovation and Lighting Project in the House and Senate Chambers approved by

the Wyoming Legislature in 2007.

Page 10: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

(House Chamber; June 26, 2008) This view from the Herschler Building shows crews from Edwards Construction lifting materials onto the roof of Wyoming’s State Capitol in preparation for the skylight

installation.

Page 11: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Crews from Edwards Construction, along with the skylight manufacturer, Supersky, are shown here unloading the Capitol skylights from a flatbed trailer.

(July 23, 2008)

Page 12: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The Wyoming State Capitol skylights are unloaded from the flatbed trailer

shown in this photo.

(July 23, 2008)

Page 13: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Construction crews unload the skylights, which will be installed over both the House and Senate Chambers by the Fall of 2008.

(July 23, 2008)

Page 14: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Construction crews move the skylights to a secure, staging area in this photo before the installation can begin above the House and Senate

Chambers.

(July 23, 2008)

Page 15: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The skylights sit in this secure, staging area where they will be assembled and then hoisted onto the roof of the Wyoming Capitol for installation.

(July 24, 2008)

Page 16: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Crews from Edwards Construction begin removing the copper covering from the skylights above the House Chamber.

(View facing East; July 28, 2008)

Page 17: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The copper covering from two panels above the House Chamber has been removed in preparation for the new skylights.

(View facing East; July 28, 2008)

Page 18: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Assembly of the Capitol skylights has begun in the Capitol’s north parking lot.

(July 29, 2008)

Page 19: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Once assembled, the skylights will be hoisted onto the roof of the House and Senate Chambers with a crane.

(July 29, 2008)

Page 20: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Assembly of the skylights continues to progress in the Capitol’s north parking lot as shown in this bird’s eye view.

(July 30, 2008)

Page 21: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Construction crews have assembled each section of the skylights and loaded them onto this flatbed trailer for storage until they are ready to be installed on the roof.

(July 31, 2008)

Page 22: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Here is another view of crews loading the skylight frames onto the trailer.

(July 31, 2008)

Page 23: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The copper has been completely removed from the House of Representatives Chamber.

(View facing East; July 31, 2008)

Page 24: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Crews from Edwards Construction have started taking off the copper from atop the Senate Chamber in preparation for the new skylights.

(View facing West; August 4, 2008)

Page 25: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Construction crews hoist the skylight glass onto the roof of the Capitol using a crane.

(House of Representatives Chamber; August 5, 2008)

Page 26: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The skylight glass is lowered onto the roof of the Capitol.

(House of Representatives Chamber; August 5, 2008)

Page 27: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The copper and roofing material has been completely removed from two skylight panels above the House of Representatives Chamber.

(House of Representatives Chamber; August 5, 2008)

Page 28: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The track for the new trolley system below the skylights is lowered into the attic above the House of Representatives Chamber.

(House of Representatives Chamber; August 5, 2008)

Page 29: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Edwards Construction works to fit the track into the attic through one of the skylight panels.

(House of Representatives Chamber; August 5, 2008)

Page 30: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Construction crews work to move the trolley track into its final resting place in the House of Representatives attic.

(House of Representatives Chamber; August 5, 2008)

Page 31: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

This vantage point from inside the attic shows as crews lower the rails for the catwalk and trolley system above the House of Representatives Chamber.

(House of Representatives Chamber; August 5, 2008)

Page 32: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Crews from Edwards Construction and Supersky install the skylight frames in two of the panels above the House of Representatives Chamber.

(House of Representatives Chamber; August 5, 2008)

Page 33: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Glass will be placed in the skylight frames.

(House of Representatives Chamber; August 5, 2008)

Page 34: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

This angle shows the skylight frames from the inside of the attic looking out, along with the rails for the catwalk and trolley system.

(House of Representatives Chamber; August 5, 2008)

Page 35: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The new energy-efficient LED can lights will be installed in both the House and Senate Chambers once the skylight installation is complete.

(August 5, 2008)

Page 36: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The copper has been completely removed from the Senate Chamber.

(View facing West; August 5, 2008)

Page 37: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Installation of the glass has begun on one panel of the skylights above the House Chamber.

(House of Representatives; August 7, 2008)

Page 38: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The brown copper atop the House of Representatives Chamber has been replaced with this green glass.

(House of Representatives; August 7, 2008)

Page 39: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Construction crews continue with the skylight installation on the House of

Representatives Chamber.

(House of Representatives; August 13, 2008)

Page 40: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Crews work to install another frame for the skylights above the House Chamber. Two glass panels have already been installed as shown on the right hand side.

(House of Representatives; August 13, 2008)

Page 41: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Skylight installation is complete on one side of the House of Representatives

Chamber.

(House of Representatives; August 14, 2008)

Page 42: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The new catwalk system outlines the skylights to allow for better maintenance and

cleaning in the attic above the Chambers.

(House of Representatives; August 14, 2008)

Page 43: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The last two skylight frames on the House Chamber await glass installation.

(House of Representatives; August 20, 2008)

Page 44: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

All but two frames are complete on the House Chamber.

(House of Representatives; August 20, 2008)

Page 45: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Skylight installation nears completion on the House Chamber.

(House of Representatives; August 21, 2008)

Page 46: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Skylight installation has been completed on the House Chamber.

(House of Representatives; August 26, 2008)

Page 47: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Skylight installation has begun on the Senate Chamber.

(Senate Chamber; August 26, 2008)

Page 48: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The second of eight frames is lifted onto the roof of the State Capitol with a crane.

(Senate Chamber; August 26, 2008)

Page 49: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

A skylight frame is brought into place high atop the Senate Chamber.

(Senate Chamber; August 26, 2008)

Page 50: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Installation of the skylights continues on the Senate Chamber.

(Senate Chamber; August 28, 2008)

Page 51: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Final work to the Senate skylights is completed.

(Senate Chamber; September 8, 2008)

Page 52: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The first rays of sunshine come through the House of Representatives stained glass.

(House Chamber; September 8, 2008)

Page 53: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Natural light is reintroduced into the House Chamber.

(House Chamber; September 8, 2008)

Page 54: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Plywood above the stained glass has started to be removed in the attic and polystyrene sheets have been put into place to protect the glass as work nears completion.

(House Chamber; September 8, 2008)

Page 55: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The plywood and metal decking has been removed and natural light once again shines down in the House Chamber.

(House Chamber; September 10, 2008)

Page 56: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

After nearly 10 years, natural sunlight is once again reintroduced above the stained glass in the House Chamber.

(House Chamber; September 17, 2008)

Page 57: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Sunlight has been fully restored to the Senate Chamber and the new lighting system is

also complete and fully operational.

(Senate Chamber; September 26, 2008)

Page 58: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Sunlight has been fully restored to the House and Senate Chamber’s and the new lighting system is now complete and fully operational.

Page 59: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Room 302 Remodel

• Over the course of the past three legislative sessions, the Wyoming Legislature has authorized a total of $255,000 for the remodel of Committee Room 302.

• Through an existing contract for interior design and architectural services, The Design Studio (TDSi) of Cheyenne is serving as the project manger for the remodel.

• When complete, the room will house all new furnishings, carpet, and lighting along with a new state-of-the-art audio and video conferencing system, with two 60-inch plasma television screens.

• The project is scheduled to be completed late summer of 2008.

Page 60: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

(Room 302; April 9, 2008)

The remodeling of Room 302, which is one of the main meeting rooms in the Capitol for the Wyoming Legislature, is also underway. The artwork and carpeting has been removed

in preparation for the work.

Page 61: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

(Room 302; April 9, 2008)

Mike Kopriva’s Wyoming mural has been covered with plastic to protect it from damage as renovations are being completed in Room 302. When complete, the room will have new carpet,

furniture, lighting and audio/visual systems.

Page 62: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The concrete floor has been cut in Room 302 to make way for the raceways that will

house the wires and cords for the new audio and video system.

(Room 302; July 7, 2008)

Page 63: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

This close-up shot shows the cuts in the concrete floor in Room 302.

(Room 302; July 7, 2008)

Page 64: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The floor has been cut in Room 302 and the concrete has been removed in the raceways to make way for the wires and cords for the new audio and video system.

(Room 302; July 14, 2008)

Page 65: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

This tin covering under the concrete has also been removed from the raceways.

(Room 302; July 14, 2008)

Page 66: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

This angle shows Room 302 from the southwest corner. The concrete has been removed in the raceways to make way for the wires and cords for the new audio

and video system.

(Room 302; July 14, 2008)

Page 67: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Both the concrete and tin has been removed in the raceways.

(Room 302; July 18, 2008)

Page 68: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

This close-up photograph shows how contractors have cut the floor down to the support beams in Room 302 in preparation for the electrical conduit.

(Room 302; July 18, 2008)

Page 69: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

This angle shows Room 302 from the northwest corner looking southeast where the new committee table will be placed.

(Room 302; July 18, 2008)

Page 70: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The electricians have set the electrical conduit into the troughs that will be used to power the new audio and video systems.

(July 29, 2008)

Page 71: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The electrical conduit and junction boxes have been set in the concrete troughs of Room 302.

(July 29, 2008)

Page 72: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Concrete has been poured in the raceways over the new electrical conduit and junction boxes.

(July 31, 2008)

Page 73: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The troughs in the floor have been refilled with concrete.

(July 31, 2008)

Page 74: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

With the electric conduit finished and concrete troughs filled, the carpet installation

has started to move forward.

(View facing Northwest corner; August 1, 2008)

Page 75: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Carpet installation continues in Room 302.

(View looking East; August 4, 2008)

Page 76: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Carpet installation has been completed in Room 302.

(View looking Southwest; August 5, 2008)

Page 77: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The new committee, presenter and staff tables have been moved into place in Committee Room 302.

(View looking Southwest; August 7, 2008)

Committee TablePresenters Table

Staff Table

Page 78: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The committee table will have a granite countertop and space for 16 committee members when installation is complete.

(View looking Southeast; August 7, 2008)

Committee Table

Presenters TableStaff Table

Page 79: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The buffet will house the new audio and video conferencing equipment and allow for better and increased storage for meeting materials and equipment.

(View facing West wall; August 7, 2008)

Page 80: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The new presenters table will allow for four people to present to the committee at any given time.

(View facing North wall; August 7, 2008)

Page 81: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The new staff table will allow for more working space during committee meetings.

(View facing Southwest corner; August 7, 2008)

Page 82: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Two 60-inch LG plasma screens have been hung to allow for video conferencing and electronic presentations for legislative committee meetings.

(August 13, 2008)

Page 83: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The new granite countertops have been installed on the committee table.

(August 14, 2008)

Page 84: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The new granite countertops will allow for more working space and electric plug-ins for laptops and other devices.

(August 14, 2008)

Page 85: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Installation of the audio and video systems has begun.

(August 22, 2008)

Page 86: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The microphones for the new audio system have been installed on the desks.

(August 22, 2008)

Page 87: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

New light fixtures along with the video conferencing equipment has been installed.

(September 26, 2008)

Page 88: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

The new light fixtures will provide softer and improved lighting in Room 302.

(September 26, 2008)

Page 89: State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by

Room 302 is complete.

(October 2, 2008)