State of São Paulo Metropolitan Transportation Secretariat
JURANDIR FERNANDESState Metropolitan Transportation Secretariat
November 24, 2006 8:30 am to 2:00 pm
Financing Strategy – subway-railway system
Last 12 Years Next 12 Years
New Strategy
• CapexR$ 7.2 billion
• Traditional sources: State Government and national and international agency financing
Estimated Capex: R$ 18.3 billion
New Source of Funding
Travel time reduction
Productivity to economy
Reduced Accidents
Reduced Pollution
Tax generation
Benefits
Results
330 km subway-railroad network
In 12 years: modernization of 22% of the trai network and 30% increase of subway network
Average R$ 700million/year
Demand Evolution in the last 12 years
1.6 million travels/day in metro-railway
system
129%Growth
30%Growth
53%Growth
Subway/railway (pass/ day)
(pass/ day)
(pass/ day)
SUBWAY NETWORK – SÃO PAULO METROPOLITAN AREA RAILWAY
SUBWAY4 lines- 60 kmExclusive service to SPConstituted in 19723.0 million passengers / dayR$ 1 billion revenue
METROPOLITAN TRAIN6 lines - 270KM22 Cities Constituted in 19941.6 million passengers / dayRevenue R$ 486.5 million / year
RMSP – METRO NETWORK
PRIORIT
ARY PROJE
CTS
METRÔ – Expansion
Line 2 – II StageStretch: V. Prudente - Tatuapé
Extension: 4 kmStations: 5Capex: R$ 1,000 millionIncrease:120,000 passengers/day
Line 2 – I StageStretch: Ana Rosa – V. Prudente
Extension: 8.2 kmStations: 6Capex: R$ 2,100 millionIncrease: 610,000 (from 270,000 to 880,000) passengers/day
METRÔ – Expansion
Linha 4 – YellowExtension: 13 km# Stations
Phase I - 5 stationsPhase II – more 6 stations
Capex: R$,2690 millionAnticipated demand: 860,000 passengers/day
8
Linha 5 – LilacExtension: 11.6 km# Stations: 10 Capex: R$ 3,300 millionAnticipated demand: 700,000 passengers/day
CPTM – Modernization
9
Line C Extension – StrecthJurubatuba/Grajaú
Extension: 7,3 kmNew Stations: 3 Capex: R$ 443 millionDemand Increase: 45,000 (from 120,000 to 165,000 ) passengers/day
Line FOperating revision: 32 km4 new stations and 11 modernizedCapex: R$ 242.2 millionDemand increase: 30,000 (from 120,000 to 150,000) passengers/day
CPTM – Modernization
10
Network ModernizationExtension: 270 kmInterval: 3 minutesCapex: R$ 3,800 millionDemand increase: 670,000 passengers/day
Extention of “ExpressoLeste” up to Suzano
Extension: 13 kmReformed stations: 5Capex: R$ 326 millionDemand increase: 150,000 passengers/day
Expresso SudesteExtension: 27 kmReformed stations: 7Capex: R$ 618 millionDemand: 450,000 passengers/day
New Services
Airport ExpresswayExtension: 31 kmNew stations: 2 Demand: 55 pass/day.
Guarulhos TrainExtension: 19 KmNew Stations: 3Demand: 280,000 pass/day
Capex:R$ 1.2 billion
PPP process is already authorized by the Management Council for receiving interest manifests from the private sector
BandeirantesBandeirantes Express TrainExpress Train
Railway connection between São Paulo (Barra Funda) – Jundiaí(Downtown) – Capinas(Downtown).Extension: 92 KmDemand: 55,000 pass/dayCapex: R$ 2.7 billion
Infrastructure: R$ 2.0 billionTrains: R$ 700 million
PPP process is already authorized by the Management Council for receiving interest manifests from the private sector
New Servides
2006 2012
Total
CPTM
+ 73%
+ 88%
Total
Estimated demand for the next 12 years
78 %increase
3,000
5,200
1,600
3,000
4,600
8,200
Primary projects – new 12-year cycle
Average R$ 1.57billion/year
124% increase over the previous
cycle
R$ milhõesMETRÔ - LINE 2 - Ana Rosa - Vila Prudente 2,100.0METRÔ - LINE 2 - Vila Prudente - Tatuapé 1,000.0METRÔ - LINE 4 2,960.0METRÔ - LINE 5 3,300.0CPTM - Line C – Grajau extension 443.0CPTM - Line F - modernization 242.2CPTM Line D - Expresso Sudeste 618.0CPTM Line E - Expresso Leste up to Suzano 326.0CPTM – modernization (3 minute interval) 3,800.0Guarulhos Train and Airport Expressway 1,200.0Bandeirantes Train Expressway 2,700.0
TOTAL CAPEX 18,689.2
MediumMedium CapacityCapacity CorridorsCorridorsSolutionsSolutions in Brazil in Brazil andand abroadabroad
Bus Rapid Transit – Las VegasABD Corridor - RMSP
Translohr – Clermont-FerrandGoiânia – Goiás
Lowland ExpresswayLowland Expressway
Extension: 12 Km Demand: 120,000 pass/dayCapex: R$ 260 million
Infrastructure: R$ 156 millionNPV: R$ 104 million
PPP process being prepared to be approved by the Management Council
RMC RMC –– Northwest CorridorNorthwest Corridor
Extension: 19 Km Demand: 140,000 pass/dayCapex: R$ 260 million
Infrastructure: R$ 154 millionBus: R$ 106 million
PPP process being prepared for Management Council approval.Contracted works: R$ 50 million in 2006 budget
Guarulhos Guarulhos –– TucuruviTucuruvi CorridorCorridor
Extension: 20.5 KmDemand: 178,000 pass/dayCapex: R$ 476 million
Infrastructure: R$ 381 millionNPV: R$ 95 million
PPP process being prepared for Management Council approval.
THANK YOU!