775
STATE OF DELAWARE CAESAR RODNEY SCHOOL DISTRICT CONTRACT # SRS-18-012-NEWELEM SPECIFICATIONS VOLUME 2 FOR NEW CAESAR RODNEY ELEMENTARY SCHOOL IN Magnolia, Delaware PREPARED BY Becker Morgan Group, Inc. BIDDING DOCUMENTS May 14, 2018

STATE OF DELAWARE CAESAR RODNEY SCHOOL DISTRICT …bidcondocs.delaware.gov/SRS/SRS18012-NewElem_specs_vol2.pdfTABLE OF CONTENTS 000110 - 1 SECTION 000110 TABLE OF CONTENTS VOLUME I

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • STATE OF DELAWARE

    CAESAR RODNEY SCHOOL DISTRICT

    CONTRACT # SRS-18-012-NEWELEM

    SPECIFICATIONS

    VOLUME 2

    FOR

    NEW CAESAR RODNEY ELEMENTARY SCHOOL

    IN

    Magnolia, Delaware

    PREPARED

    BY

    Becker Morgan Group, Inc.

    BIDDING DOCUMENTS

    May 14, 2018

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    PROJECT TITLE PAGE 000101 - 1

    DOCUMENT 000101 - PROJECT TITLE PAGE

    1.1 PROJECT MANUAL VOLUME 2

    A. New Caesar Rodney Elementary School.

    B. Magnolia, Delaware.

    C. Owner Project No. SRS-18-012-NEWELEM.

    D. Architect Project No. 2017073.00.

    E. Owner: Caesar Rodney School District. Ken Starke 7 Front Street

    Wyoming, Delaware 19934

    Phone: 302.698.4800 Fax: 302.697.3406

    F. Architect: Becker Morgan Group, Inc. Bryan Hutchison, AIA 312 West Main Street, Suite 300

    Salisbury, Maryland 21801

    Phone: 410.546.9100 Fax: 410.546.5824

    G. Civil Engineer: Becker Morgan Group, Inc. Jonathan Falkowski, P.E. 309 South Governors Avenue

    Dover, Delaware 19904

    Phone: 302.734.7950 Fax: 302.734.7965

    H. Structural Engineer: Baker Ingram Associates, Inc. Cherie Moore, P.E. 1050 South State Street

    Dover, Delaware 19901

    Phone: 302.734.7400 Fax: 302.734.7592

    I. Mechanical and Electrical Engineer: Studio JAED Brian Zigmond, P.E. 2500 Wrangle Hill Road

    Fox Run Office Plaza, Suite 110

    Bear, Delaware 19701

    Phone: 302.832.1652 Fax: 302.832.1423

    J. Food Service Consultant: Nyikos Associates, Inc. Jay Garcia, FCSI 18205-A Flower Hill Way

    Gaithersburg, Maryland 20879

    Phone: 240.683.9530 Fax: 240.683.9532

    K. Issued: May 14, 2018.

    L. Copyright 2018 Becker Morgan Group, Inc. All rights reserved.

    END OF DOCUMENT 000101

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    TABLE OF CONTENTS 000110 - 1

    SECTION 000110 TABLE OF CONTENTS

    VOLUME I

    DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

    000101 PROJECT TITLE PAGE

    000110 TABLE OF CONTENTS

    000115 LIST OF DRAWING SHEETS

    001116 INVITATION TO BID

    002113 INSTRUCTIONS TO BIDDERS

    002600 PROCUREMENT SUBSTITUTION PROCEDURES

    002600A SUBSTITUTION REQUEST – BIDDING AND NEGOTIATING PHASE

    003132 GEOTECHNICAL DATA

    003132A HILLIS-CARNES GEOTECHNICAL ENGINEERING REPORT

    004113 BID FORM

    004313 BID BOND

    004393 BID SUBMITTAL CHECKLIST

    005213 AGREEMENT FORM – STIPULATED SUM

    005213A AIA DOCUMENT A101-2007 STANDARD FORM OF AGREEMENT BETWEEN OWNER

    AND CONTRACTOR

    005400 SUPPLEMENT TO AGREEMENT BETWEEN OWNER AND CONTRACTOR A101-2007

    006000 PROJECT FORMS

    006100A PERFORMANCE BOND

    006100B PAYMENT BOND

    006216 CERTIFICATES OF INSURANCE

    007200 GENERAL CONDITIONS

    007200A AIA DOCUMENT A201-2007 GENERAL CONDITIONS OF THE CONTRACT FOR

    CONSTRUCTION

    007300 SUPPLEMENTARY GENERAL CONDITIONS

    007346 WAGE DETERMINATION SCHEDULE

    007346A PREVAILING WAGE RATES

    008113 GENERAL REQUIREMENTS

    008114 DRUG TESTING REPORT FORMS

    DIVISION 01 – GENERAL REQUIREMENTS

    011000 SUMMARY

    012100 ALLOWANCES

    012200 UNIT PRICES

    012300 ALTERNATES

    012500 SUBSTITUTION PROCEDURES

    012500A SUBSTITUTION REQUEST – CONSTRUCTION PHASE

    012600 CONTRACT MODIFICATION PROCEDURES

    012600A EXHIBIT – FIELD BULLETIN

    012900 PAYMENT PROCEDURES

    013100 PROJECT MANAGEMENT AND COORDINATION

    013100A RELEASE OF ELECTRONIC MEDIA

    013100B CADD RELEASE FORM

    013200 CONSTRUCTION PROGRESS DOCUMENTATION

    013300 SUBMITTAL PROCEDURES

    014000 QUALITY REQUIREMENTS

    014200 REFERENCES

    015000 TEMPORARY FACILITIES AND CONTROLS

    016000 PRODUCT REQUIREMENTS

    017300 EXECUTION

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    TABLE OF CONTENTS 000110 - 2

    017700 CLOSEOUT PROCEDURES

    017823 OPERATION AND MAINTENANCE DATA

    017839 PROJECT RECORD DOCUMENTS

    017900 DEMONSTRATION AND TRAINING

    019113 GENERAL COMMISSIONING REQUIREMENTS

    VOLUME II

    DIVISION 02 – EXISTING CONDITIONS

    NOT USED

    DIVISION 03 – CONCRETE

    033000 CAST-IN-PLACE CONCRETE

    034900 GLASS-FIBER-REINFORCED CONCRETE (GFRC)

    DIVISION 04 – MASONRY

    042000 UNIT MASONRY

    047200 CAST STONE MASONRY

    047300 MANUFACTURED STONE MASONRY

    DIVISION 05 – METALS

    051200 STRUCTURAL STEEL

    052100 STEEL JOIST FRAMING

    053100 STEEL DECKING

    054000 COLD-FORMED METAL FRAMING

    054400 COLD-FORMED METAL TRUSSES

    055000 METAL FABRICATIONS

    055113 METAL PAN STAIRS

    055133 METAL LADDERS

    055213 PIPE AND TUBE RAILINGS

    057000 DECORATIVE METAL

    DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

    061053 MISCELLANEOUS ROUGH CARPENTRY

    061600 SHEATHING

    062013 EXTERIOR FINISH CARPENTRY

    064023 INTERIOR ARCHITECTURAL WOODWORK

    068200 COMPOSITE TRIM

    DIVISION 07 – THERMAL AND MOISTURE PROTECTION

    071113 BITUMINOUS DAMP PROOFING

    071326 SELF-ADHERING SHEET WATERPROOFING

    072100 THERMAL INSULATION

    072500 WEATHER BARRIERS

    072736 SPRAYED FOAM AIR BARRIER

    074113.16 STANDING-SEAM METAL ROOF PANELS

    074213.13 FORMED METAL WALL PANELS

    074293 SOFFIT PANELS

    075416 KETONE ETHYLENE ESTER (KEE) ROOFING

    076200 SHEET METAL FLASHING AND TRIM

    077100 ROOF SPECIALTIES

    077200 ROOF ACCESSORIES

    077253 SNOW GUARDS

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    TABLE OF CONTENTS 000110 - 3

    078413 PENETRATION FIRESTOPPING

    078443 JOINT FIRESTOPPING

    079100 PREFORMED JOINT SEALS

    079200 JOINT SEALANTS

    079219 ACOUSTICAL JOINT SEALANTS

    079513.13 INTERIOR EXPANSION JOINT COVER ASSEMBLIES

    DIVISION 08 – OPENINGS

    080671 DOOR HARDWARE SCHEDULE

    081113 HOLLOW METAL DOORS AND FRAMES

    081416 FLUSH WOOD DOORS

    083113 ACCESS DOORS AND FRAMES

    083313 COILING COUNTER DOORS

    083323 OVERHEAD COILING DOORS

    084113 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

    085113 ALUMINUM WINDOWS

    087100 DOOR HARDWARE

    088000 GLAZING

    088813 FIRE-RESISTANT GLAZING

    089119 FIXED LOUVERS

    DIVISION 09 – FINISHES

    092116.23 GYPSUM BOARD SHAFT WALL ASSEMBLIES

    092216 NON-STRUCTURAL METAL FRAMING

    092900 GYPSUM BOARD

    093013 CERAMIC TILING

    095113 ACOUSTICAL PANEL CEILINGS

    095443 STRETCHED-FABRIC CEILING SYSTEMS

    096513 RESILIENT BASE AND ACCESSORIES

    096516 RESILIENT SHEET FLOORING

    096519 RESILIENT TILE FLOORING

    096566 RESILIENT ATHLETIC FLOORING

    096723 RESINOUS FLOORING

    096813 TILE CARPETING

    097200 WALL COVERINGS

    098433 SOUND-ABSORBING WALL UNITS

    099113 EXTERIOR PAINTING

    099123 INTERIOR PAINTING

    099600 HIGH PERFORMANCE COATINGS

    DIVISION 10 – SPECIALTIES

    101100 VISUAL DISPLAY UNITS

    101200 DISPLAY CASES

    101416 PLAQUES

    101416A PLAQUE

    101419 DIMENSIONAL LETTER SIGNAGE

    101423 PANEL SIGNAGE

    101463 ELECTRONIC MESSAGE SIGNAGE

    102113.19 PLASTIC TOILET COMPARTMENTS

    102123 CUBICLE CURTAINS AND TRACK

    102239 FOLDING PANEL PARTITIONS

    102800 TOILET, BATH, AND LAUNDRY ACCESSORIES

    104413 FIRE PROTECTION CABINETS

    104416 FIRE EXTINGUISHERS

    105113 METAL LOCKERS

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    TABLE OF CONTENTS 000110 - 4

    105613 METAL STORAGE SHELVING

    107316.13 METAL CANOPIES

    107326.13 METAL WALKWAY COVERINGS

    107516 GROUND-SET FLAGPOLES

    DIVISION 11 – EQUIPMENT

    112800 OFFICE EQUIPMENT

    113013 RESIDENTIAL APPLIANCES

    114000 FOOD SERVICE EQUIPMENT

    115213 PROJECTION SCREENS

    116143 STAGE CURTAINS

    116623 GYMNASIUM EQUIPMENT

    DIVISION 12 – FURNISHINGS

    122113 HORIZONTAL LOUVER BLINDS

    122413 ROLLER WINDOW SHADES

    123216 MANUFACTURED PLASTIC-LAMINATE-CLAD CASEWORK

    123623.13 PLASTIC-LAMINATE-CLAD COUNTERTOPS

    123661.16 SOLID SURFACING COUNTERTOPS

    DIVISION 13 – SPECIAL CONSTRUCTION

    N/A

    DIVISION 14 – CONVEYING EQUIPMENT

    142400 HYDRAULIC ELEVATORS

    VOLUME III

    DIVISION 21 – FIRE SUPPRESSION

    210500 COMMON WORK RESULTS FOR FIRE SUPPRESSION

    210513 COMMON MOTOR REQUIREMENTS FOR FIRE SUPPRESSION EQUIPMENT

    210548 VIBRATION & SEISMIC CONTROLS FOR FIRE SUPPRESSION PIPING AND EQUIPMENT

    210553 IDENTIFICATION FOR FIRE SUPPRESSION PIPING AND EQUIPMENT

    210719 FIRE SUPPRESSION PIPING INSULATION

    211200 FIRE-SUPPRESSION STANDPIPES

    211300 FIRE-SUPPRESSION SPRINKLER SYSTEMS

    213000 FIRE PUMPS

    DIVISION 22 – PLUMBING

    220516 EXPANSION FITTINGS AND LOOPS FOR PLUMBING PIPING

    220519 METERS AND GAGES FOR PLUMBING PIPING

    220548 VIBRATION AND SEISMIC CONTROLS FOR PLUMBING PIPING AND EQUIPMENT

    220553 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

    220716 PLUMBING EQUIPMENT INSULATION

    220719 PLUMBING PIPING INSULATION

    221005 PLUMBING PIPING

    221006 PLUMBING PIPING SPECIALTIES

    221113 FACILITY WATER DISTRIBUTION PIPING

    221313 FACILITY SANITARY SEWERAGE

    221343 FACILITY PACKAGED SEWAGE PUMPING STATION

    223000 PLUMBING EQUIPMENT

    224000 PLUMBING FIXTURES

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    TABLE OF CONTENTS 000110 - 5

    DIVISION 23 – HVAC

    230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT

    230516 EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING

    230519 METERS AND GAGES FOR HVAC PIPING

    230548 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT

    230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

    230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC

    230713 DUCT INSULATION

    230719 HVAC PIPING INSULATION

    230800 COMMISSIONING OF HVAC

    230913 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

    230923 DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC

    230993 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

    232113 HYDRONIC PIPING

    232300 REFRIGERANT PIPING

    233100 HVAC DUCTS AND CASINGS

    233300 AIR DUCT ACCESSORIES

    233423 HVAC POWER VENTILATORS

    233700 AIR OUTLETS AND INLETS

    233813 COMMERCIAL-KITCHEN HOODS

    237223 PACKAGED AIR-TO-AIR ENERGY RECOVERY UNITS

    237413 PACKAGED OUTDOOR CENTRAL-STATION AIR-HANDLING UNITS

    238101 TERMINAL HEAT TRANSFER UNITS

    238127 SMALL SPLIT-SYSTEM HEATING AND COOLING

    238129 VARIABLE REFRIGERANT VOLUME (VRV) HVAC SYSTEM

    VOLUME IV

    DIVISION 26 – ELECTRICAL

    260519 LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

    260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

    260529 HANGARS AND SUPPORTS FOR ELECTRICAL SYSTEMS

    260534 CONDUIT

    260537 BOXES

    260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

    260573 POWER SYSTEM STUDIES

    260919 ENCLOSED CONTACTORS

    260923 LIGHTING CONTROL DEVICES

    262200 LOW-VOLTAGE TRANSFORMERS

    262413 SWITCHBOARDS

    262416 PANELBOARDS

    262701 ELECTRICAL SERVICE ENTRANCE

    262717 EQUIPMENT WIRING

    262726 WIRING DEVICES

    262813 FUSES

    262817 ENCLOSED CIRCUIT BREAKERS

    262818 ENCLOSED SWITCHES

    262913 ENCLOSED CONTROLLERS

    262923 VARIABLE FREQUENCY MOTOR CONTROLLERS

    263213 ENGINE GENERATORS

    263600 TRANSFER SWITCHES

    264300 SURGE PROTECTIVE DEVICES

    265100 INTERIOR LIGHTING

    265600 EXTERIOR LIGHTING

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    TABLE OF CONTENTS 000110 - 6

    DIVISION 27 – COMMUNICATIONS

    271005 STRUCTURED CABLING FOR VOICE AND DATA – INSIDE PLANT

    275117 PUBLIC ADDRESS SYSTEMS

    275120 GYM & CAFETERIA AUDIOVISUAL REINFORCEMENT SYSTEM

    275313 WIRELESS CLOCK SYSTEMS

    DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

    281000 ACCESS CONTROL SYSTEMS

    281601 INTRUSION DETECTION SYSTEMS

    282319 NETWORK VIDEO RECORDING SYSTEM

    283100 FIRE DETECTION AND ALARM

    DIVISION 31 – EARTHWORK

    311000 SITE CLEARING

    312000 EARTH MOVING

    312319 DEWATERING

    313116 TERMITE CONTROL

    315000 EXCAVATION SUPPORT AND PROTECTION

    DIVISION 32 – EXTERIOR IMPROVEMENTS

    321216 ASPHALT PAVING

    321313 CONCRETE PAVING

    321373 CONCRETE JOINT SEALANT

    323113 CHAIN LINK FENCES AND GATES

    323300 SITE FURNISHINGS

    329200 TURF AND GRASSES

    329300 LANDSCAPE ARCHITECTURE

    DIVISION 33 – UTILITIES

    330500 COMMON WORK RESULTS FOR UTILITIES

    334100 STORM DRAINAGE UTILITY PIPING

    337119 ELECTRICAL UNDERGROUND DUCTS AND MANHOLES

    337900 SITE GROUNDING

    END OF TABLE OF CONTENTS

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 1

    SECTION 033000 - CAST-IN-PLACE CONCRETE

    PART 1 - GENERAL

    1.1 RELATED DOCUMENTS

    A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

    1.2 SUMMARY

    A. Section includes cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes.

    B. Related Requirements:

    1. Section 312000 "Earth Moving" for drainage fill under slabs-on-grade.2. Section 321313 "Concrete Paving" for concrete pavement and walks.3. Section 321316 "Decorative Concrete Paving" for decorative concrete pavement and

    walks.

    1.3 DEFINITIONS

    A. Cementitious Materials: Portland cement alone or in combination with one or more of the following: blended hydraulic cement, fly ash, slag cement, other pozzolans, and silica fume; materials subject to compliance with requirements.

    B. W/C Ratio: The ratio by weight of water to cementitious materials.

    1.4 PREINSTALLATION MEETINGS

    A. Preinstallation Conference: Conduct conference at Project site.

    1. Before submitting design mixtures, review concrete design mixture and examineprocedures for ensuring quality of concrete materials. Require representatives of eachentity directly concerned with cast-in-place concrete to attend, including the following:

    a. Contractor's superintendent.b. Independent testing agency responsible for concrete design mixtures.c. Ready-mix concrete manufacturer.d. Concrete Subcontractor.e. Special concrete finish Subcontractor.

    2. Review special inspection and testing and inspecting agency procedures for field qualitycontrol, concrete finishes and finishing, cold- and hot-weather concreting procedures,curing procedures, construction contraction and isolation joints, and joint-filler strips,

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 2

    semirigid joint fillers, vapor-retarder installation, anchor rod and anchorage device installation tolerances, steel reinforcement installation, [methods for achieving specified floor and slab flatness and levelness and concrete protection.

    1.5 ACTION SUBMITTALS

    A. Product Data: For each type of product.

    B. Design Mixtures: For each concrete mixture. Submit alternate design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments.

    1. Indicate amounts of mixing water to be withheld for later addition at Project site.

    C. Steel Reinforcement Shop Drawings: Placing Drawings that detail fabrication, bending, and placement. Include bar sizes, lengths, material, grade, bar schedules, stirrup spacing, bent bar diagrams, bar arrangement, splices and laps, mechanical connections, tie spacing, hoop spacing, and supports for concrete reinforcement.

    D. Construction Joint Layout: Indicate proposed construction joints required to construct the structure.

    1. Location of construction joints is subject to approval of the Architect.

    E. Samples: For waterstops & vapor retarder.

    1.6 INFORMATIONAL SUBMITTALS

    A. Qualification Data: For Installer, manufacturer & testing agency.

    B. Welding certificates.

    C. Material Certificates: For each of the following, signed by manufacturers:

    1. Cementitious materials. 2. Admixtures. 3. Form materials and form-release agents. 4. Steel reinforcement and accessories. 5. Fiber reinforcement. 6. Waterstops. 7. Curing compounds. 8. Floor and slab treatments. 9. Bonding agents. 10. Adhesives. 11. Vapor retarders. 12. Semirigid joint filler. 13. Joint-filler strips. 14. Repair materials.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 3

    D. Material Test Reports: For the following, from a qualified testing agency:

    1. Aggregates: Include service record data indicating absence of deleterious expansion of concrete due to alkali aggregate reactivity.

    E. Formwork Shop Drawings: Prepared by or under the supervision of a qualified professional engineer, detailing fabrication, assembly, and support of formwork.

    1. Shoring and Reshoring: Indicate proposed schedule and sequence of stripping formwork, shoring removal, and reshoring installation and removal.

    F. Floor surface flatness and levelness measurements indicating compliance with specified tolerances.

    G. Field quality-control reports.

    H. Minutes of preinstallation conference.

    1.7 QUALITY ASSURANCE

    A. Installer Qualifications: A qualified installer who employs on Project personnel qualified as ACI-certified Flatwork Technician and Finisher and a supervisor who is an ACI-certified Concrete Flatwork Technician.

    B. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment.

    1. Manufacturer certified according to NRMCA's "Certification of Ready Mixed Concrete Production Facilities."

    C. Welding Qualifications: Qualify procedures and personnel according to AWS D1.4/D 1.4M.

    1.8 PRECONSTRUCTION TESTING

    A. Preconstruction Testing Service: Engage a qualified testing agency to perform preconstruction testing on concrete mixtures.

    1.9 DELIVERY, STORAGE, AND HANDLING

    A. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending and damage. Avoid damaging coatings on steel reinforcement.

    B. Waterstops: Store waterstops under cover to protect from moisture, sunlight, dirt, oil, and other contaminants.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 4

    1.10 FIELD CONDITIONS

    A. Cold-Weather Placement: Comply with ACI 306.1 and as follows. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures.

    1. When average high and low temperature is expected to fall below 40 deg F (4.4 deg C) for three successive days, maintain delivered concrete mixture temperature within the temperature range required by ACI 301 (ACI 301M).

    2. Do not use frozen materials or materials containing ice or snow. Do not place concrete on frozen subgrade or on subgrade containing frozen materials.

    3. Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in mixture designs.

    B. Hot-Weather Placement: Comply with ACI 301 (ACI 301M) and ACI 305.1 (ACI 305.1M), and as follows:

    1. Maintain concrete temperature below 90 deg F (32 deg C) at time of placement. Chilled mixing water or chopped ice may be used to control temperature, provided water equivalent of ice is calculated to total amount of mixing water. Using liquid nitrogen to cool concrete is Contractor's option.

    2. Fog-spray forms, steel reinforcement, and subgrade just before placing concrete. Keep subgrade uniformly moist without standing water, soft spots, or dry areas.

    PART 2 - PRODUCTS

    2.1 CONCRETE, GENERAL

    A. ACI Publications: Comply with the following unless modified by requirements in the Contract Documents:

    1. ACI 301 (ACI 301M). 2. ACI 117 (ACI 117M).

    2.2 FORM-FACING MATERIALS

    A. Smooth-Formed Finished Concrete: Form-facing panels that provide continuous, true, and smooth concrete surfaces. Furnish in largest practicable sizes to minimize number of joints.

    1. Plywood, metal, or other approved panel materials.

    B. Rough-Formed Finished Concrete: Plywood, lumber, metal, or another approved material. Provide lumber dressed on at least two edges and one side for tight fit.

    C. Chamfer Strips: Wood, metal, PVC, or rubber strips, 3/4 by 3/4 inch (19 by 19 mm), minimum.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 5

    D. Form-Release Agent: Commercially formulated form-release agent that does not bond with, stain, or adversely affect concrete surfaces and does not impair subsequent treatments of concrete surfaces.

    1. Formulate form-release agent with rust inhibitor for steel form-facing materials.

    2.3 STEEL REINFORCEMENT

    A. Reinforcing Bars: ASTM A 615/A 615M, Grade 60 (Grade 420), deformed.

    B. Steel Bar Mats: ASTM A 184/A 184M, fabricated from ASTM A 615/A 615M, Grade 60 (Grade 420), deformed bars, assembled with clips.

    C. Plain-Steel Wire: ASTM A 1064/A 1064M, as drawn.

    D. Plain-Steel Welded-Wire Reinforcement: ASTM A 1064/A 1064M, plain, fabricated from as-drawn steel wire into flat sheets.

    2.4 REINFORCEMENT ACCESSORIES

    A. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded-wire reinforcement in place. Manufacture bar supports from steel wire, plastic, or precast concrete according to CRSI's "Manual of Standard Practice," of greater compressive strength than concrete and as follows:

    1. For concrete surfaces exposed to view, where legs of wire bar supports contact forms, use CRSI Class 1 plastic-protected steel wire or CRSI Class 2 stainless-steel bar supports.

    2.5 CONCRETE MATERIALS

    A. Cementitious Materials:

    1. Portland Cement: ASTM C 150/C 150M, Type I or Type II. 2. Fly Ash: ASTM C 618, Class F. 3. Blended Hydraulic Cement: ASTM C 595/C 595M, Type IS, portland blast-furnace slag

    cement.

    B. Normal-Weight Aggregates: ASTM C 33/C 33M, coarse aggregate or better, graded. Provide aggregates from a single source.

    1. Maximum Coarse-Aggregate Size: 1-1/2 inches (38 mm) nominal. 2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.

    C. Air-Entraining Admixture: ASTM C 260/C 260M.

    D. Chemical Admixtures: Certified by manufacturer to be compatible with other admixtures and that do not contribute water-soluble chloride ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 6

    1. Water-Reducing Admixture: ASTM C 494/C 494M, Type A. 2. Retarding Admixture: ASTM C 494/C 494M, Type B. 3. Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type D. 4. High-Range, Water-Reducing Admixture: ASTM C 494/C 494M, Type F. 5. High-Range, Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type G. 6. Plasticizing and Retarding Admixture: ASTM C 1017/C 1017M, Type II.

    E. Set-Accelerating Corrosion-Inhibiting Admixture: Commercially formulated, anodic inhibitor or mixed cathodic and anodic inhibitor; capable of forming a protective barrier and minimizing chloride reactions with steel reinforcement in concrete and complying with ASTM C 494/C 494M, Type C.

    F. Water: ASTM C 94/C 94M and potable.

    2.6 WATERSTOPS

    A. Flexible PVC Waterstops: CE CRD-C 572, for embedding in concrete to prevent passage of fluids through joints. Factory fabricate corners, intersections, and directional changes.

    1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

    a. BoMetals, Inc. b. Greenstreak. c. Paul Murphy Plastics Company. d. Vinylex Corp.

    2. Profile: [Flat dumbbell with center bulb] [Flat dumbbell without center bulb]

    [Ribbed with center bulb] [Ribbed without center bulb] [As indicated] .

    3. Dimensions: 9 inches by 3/8 inch thick (225 mm by 10 mm thick); nontapered.

    2.7 VAPOR RETARDERS

    A. Sheet Vapor Retarder: ASTM E 1745, Class A. Include manufacturer's recommended adhesive or pressure-sensitive tape.

    1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

    a. Fortifiber Building Systems Group; Moistop Ultra 15. b. Grace Construction Products, W. R. Grace & Co.; Florprufe 120. c. Meadows, W. R., Inc.; Perminator 15 mil. d. Raven Industries Inc.; Vapor Block 15. e. Stego Industries, LLC; Stego Wrap 15 mil Class A.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 7

    2.8 LIQUID FLOOR TREATMENTS

    A. Penetrating Liquid Floor Treatment: Clear, chemically reactive, waterborne solution of inorganic silicate or siliconate materials and proprietary components; odorless; that penetrates, hardens, and densifies concrete surfaces.

    1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

    a. ChemTec Int'l; ChemTec One. b. Euclid Chemical Company (The), an RPM company; Euco Diamond Hard. c. L&M Construction Chemicals, Inc.; Seal Hard. d. Meadows, W. R., Inc.; LIQUI-HARD.

    2.9 CURING MATERIALS

    A. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for application to fresh concrete.

    1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

    a. Axim Italcementi Group, Inc.; CATEXOL CimFilm. b. ChemMasters; SprayFilm. c. Euclid Chemical Company (The), an RPM company; Eucobar. d. L&M Construction Chemicals, Inc.; E-CON. e. Meadows, W. R., Inc.; EVAPRE.

    B. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. (305 g/sq. m) when dry.

    C. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.

    D. Water: Potable.

    E. Clear, Waterborne, Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B, dissipating.

    1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

    a. Anti-Hydro International, Inc.; AH Curing Compound #2 DR WB. b. ChemMasters; Safe-Cure Clear. c. Euclid Chemical Company (The), an RPM company; Kurez W VOX;

    TAMMSCURE WB 30C. d. L&M Construction Chemicals, Inc.; L&M Cure R. e. Meadows, W. R., Inc.; 1100-CLEAR.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 8

    F. Clear, Waterborne, Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B, nondissipating, certified by curing compound manufacturer to not interfere with bonding of floor covering.

    1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

    a. Anti-Hydro International, Inc.; AH Clear Cure WB. b. ChemMasters; Safe-Cure & Seal 20. c. Euclid Chemical Company (The), an RPM company; Aqua Cure VOX;

    Clearseal WB 150. d. L&M Construction Chemicals, Inc.; Dress & Seal WB. e. Meadows, W. R., Inc.; Vocomp-20.

    2.10 RELATED MATERIALS

    A. Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic fiber or ASTM D 1752, cork or self-expanding cork.

    B. Semirigid Joint Filler: Two-component, semirigid, 100 percent solids, epoxy resin with a Type A shore durometer hardness of 80 or aromatic polyurea with a Type A shore durometer hardness range of 90 to 95 according to ASTM D 2240.

    C. Bonding Agent: ASTM C 1059/C 1059M, Type II, nonredispersible, acrylic emulsion or styrene butadiene.

    D. Epoxy Bonding Adhesive: ASTM C 881, two-component epoxy resin, capable of humid curing and bonding to damp surfaces, of class suitable for application temperature and of grade to suit requirements, and as follows:

    1. Types IV and V, load bearing, for bonding hardened or freshly mixed concrete to hardened concrete.

    E. Reglets: Fabricate reglets of not less than 0.022-inch- (0.55-mm-) thick, galvanized-steel sheet. Temporarily fill or cover face opening of reglet to prevent intrusion of concrete or debris.

    F. Dovetail Anchor Slots: Hot-dip galvanized-steel sheet, not less than 0.034 inch (0.85 mm) thick, with bent tab anchors. Temporarily fill or cover face opening of slots to prevent intrusion of concrete or debris.

    2.11 REPAIR MATERIALS

    A. Repair Underlayment: Cement-based, polymer-modified, self-leveling product that can be applied in thicknesses from 1/8 inch (3.2 mm) and that can be feathered at edges to match adjacent floor elevations.

    1. Cement Binder: ASTM C 150/C 150M, portland cement or hydraulic or blended hydraulic cement as defined in ASTM C 219.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 9

    2. Primer: Product of underlayment manufacturer recommended for substrate, conditions, and application.

    3. Aggregate: Well-graded, washed gravel, 1/8 to 1/4 inch (3.2 to 6 mm) or coarse sand as recommended by underlayment manufacturer.

    4. Compressive Strength: Not less than 4100 psi (29 MPa) at 28 days when tested according to ASTM C 109/C 109M.

    B. Repair Overlayment: Cement-based, polymer-modified, self-leveling product that can be applied in thicknesses from 1/4 inch (6.4 mm) and that can be filled in over a scarified surface to match adjacent floor elevations.

    1. Cement Binder: ASTM C 150/C 150M, portland cement or hydraulic or blended hydraulic cement as defined in ASTM C 219.

    2. Primer: Product of topping manufacturer recommended for substrate, conditions, and application.

    3. Aggregate: Well-graded, washed gravel, 1/8 to 1/4 inch (3.2 to 6 mm) or coarse sand as recommended by topping manufacturer.

    4. Compressive Strength: Not less than 5000 psi (34.5 MPa) at 28 days when tested according to ASTM C 109/C 109M.

    2.12 CONCRETE MIXTURES, GENERAL

    A. Prepare design mixtures for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, according to ACI 301 (ACI 301M).

    1. Use a qualified independent testing agency for preparing and reporting proposed mixture designs based on laboratory trial mixtures.

    B. Cementitious Materials:[ Use fly ash, pozzolan, slag cement, and silica fume as needed to reduce the total amount of portland cement, which would otherwise be used, by not less than 40 percent.] [ Limit percentage, by weight, of cementitious materials other than portland cement in concrete as follows:]

    1. Fly Ash: 25 percent. 2. Combined Fly Ash and Pozzolan: 25 percent. 3. Slag Cement: 50 percent. 4. Combined Fly Ash or Pozzolan and Slag Cement: 50 percent portland cement minimum,

    with fly ash or pozzolan not exceeding 25 percent. 5. Silica Fume: 10 percent. 6. Combined Fly Ash, Pozzolans, and Silica Fume: 35 percent with fly ash or pozzolans not

    exceeding 25 percent and silica fume not exceeding 10 percent. 7. Combined Fly Ash or Pozzolans, Slag Cement, and Silica Fume: 50 percent with fly ash

    or pozzolans not exceeding 25 percent and silica fume not exceeding 10 percent.

    C. Limit water-soluble, chloride-ion content in hardened concrete to [0.06] [0.15] [0.30] [1.00] percent by weight of cement.

    D. Admixtures: Use admixtures according to manufacturer's written instructions.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 10

    1. Use [water-reducing] [high-range water-reducing] [or] [plasticizing] admixture in concrete, as required, for placement and workability.

    2. Use water-reducing and -retarding admixture when required by high temperatures, low humidity, or other adverse placement conditions.

    3. Use water-reducing admixture in pumped concrete, concrete for heavy-use industrial slabs and parking structure slabs, concrete required to be watertight, and concrete with a w/c ratio below 0.50.

    4. Use corrosion-inhibiting admixture in concrete mixtures where indicated.

    E. Color Pigment: Add color pigment to concrete mixture according to manufacturer's written instructions and to result in hardened concrete color consistent with approved mockup.

    2.13 CONCRETE MIXTURES FOR BUILDING ELEMENTS

    A. Footings: Normal-weight concrete.

    1. Minimum Compressive Strength: 3000 psi (20.7 MPa) at 28 days. 2. Maximum W/C Ratio: 0.50. 3. Slump Limit: 4 inches (100 mm) for concrete with verified slump of 2 to 4 inches (50 to

    100 mm) plus or minus 1 inch (25 mm). 4. Air Content: 5.5 percent, plus or minus 1.5 percent at point of delivery for 1-1/2-inch (38-

    mm) nominal maximum aggregate size.

    B. Foundation Walls and Piers: Normal-weight concrete.

    1. Minimum Compressive Strength: 4000 psi (27.6 MPa) at 28 days. 2. Maximum W/C Ratio: 0.45. 3. Slump Limit: 4 inches (100 mm) , plus or minus 1 inch (25 mm). 4. Air Content: 5.5 percent, plus or minus 1.5 percent at point of delivery for 1-1/2-inch (38-

    mm) nominal maximum aggregate size.

    C. Slabs-on-Grade: Normal-weight concrete.

    1. Minimum Compressive Strength: 5000 psi (34.5 MPa) exterior and 4000 psi (27.6 MPa) interior at 28 days.

    2. Maximum W/C Ratio: 0.45. 3. Slump Limit: 4 inches (100 mm), plus or minus 1 inch (25 mm). 4. Air Content: 5.5 percent, plus or minus 1.5 percent at point of delivery for 1-1/2-inch (38-

    mm) nominal maximum aggregate size. 5. Air Content: Do not allow air content of trowel-finished floors to exceed 3 percent.

    D. Suspended Slabs: Normal-weight concrete.

    1. Minimum Compressive Strength: 4000 psi (27.6 MPa) at 28 days. 2. Maximum W/C Ratio: 0.45. 3. Minimum Cementitious Materials Content: 520 lb/cu. yd. (309 kg/cu. m). 4. Slump Limit: 4 inches (100 mm), plus or minus 1 inch (25 mm). 5. Air Content: 5.5 percent, plus or minus 1.5 percent at point of delivery for 1-1/2-inch (38-

    mm) nominal maximum aggregate size. 6. Air Content: Do not allow air content of trowel-finished floors to exceed 3 percent.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 11

    2.14 FABRICATING REINFORCEMENT

    A. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice."

    2.15 CONCRETE MIXING

    A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94/C 94M and ASTM C 1116/C 1116M, and furnish batch ticket information.

    1. When air temperature is between 85 and 90 deg F (30 and 32 deg C), reduce mixing and delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F (32 deg C), reduce mixing and delivery time to 60 minutes.

    B. Project-Site Mixing: Measure, batch, and mix concrete materials and concrete according to ASTM C 94/C 94M. Mix concrete materials in appropriate drum-type batch machine mixer.

    1. For mixer capacity of 1 cu. yd. (0.76 cu. m) or smaller, continue mixing at least 1-1/2 minutes, but not more than 5 minutes after ingredients are in mixer, before any part of batch is released.

    2. For mixer capacity larger than 1 cu. yd. (0.76 cu. m), increase mixing time by 15 seconds for each additional 1 cu. yd. (0.76 cu. m).

    3. Provide batch ticket for each batch discharged and used in the Work, indicating Project identification name and number, date, mixture type, mixture time, quantity, and amount of water added. Record approximate location of final deposit in structure.

    PART 3 - EXECUTION

    3.1 FORMWORK INSTALLATION

    A. Design, erect, shore, brace, and maintain formwork, according to ACI 301 (ACI 301M), to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads.

    B. Construct formwork so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117 (ACI 117M).

    C. Construct forms tight enough to prevent loss of concrete mortar.

    D. Construct forms for easy removal without hammering or prying against concrete surfaces. Provide crush or wrecking plates where stripping may damage cast-concrete surfaces. Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical.

    1. Install keyways, reglets, recesses, and the like, for easy removal. 2. Do not use rust-stained steel form-facing material.

    E. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required elevations and slopes in finished concrete surfaces. Provide and secure units to support screed strips; use strike-off templates or compacting-type screeds.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 12

    F. Provide temporary openings for cleanouts and inspection ports where interior area of formwork is inaccessible. Close openings with panels tightly fitted to forms and securely braced to prevent loss of concrete mortar. Locate temporary openings in forms at inconspicuous locations.

    G. Chamfer exterior corners and edges of permanently exposed concrete.

    H. Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and bulkheads required in the Work. Determine sizes and locations from trades providing such items.

    I. Clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, dirt, and other debris just before placing concrete.

    J. Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks and maintain proper alignment.

    K. Coat contact surfaces of forms with form-release agent, according to manufacturer's written instructions, before placing reinforcement.

    3.2 EMBEDDED ITEM INSTALLATION

    A. Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

    1. Install anchor rods, accurately located, to elevations required and complying with tolerances in Section 7.5 of AISC 303.

    2. Install reglets to receive waterproofing and to receive through-wall flashings in outer face of concrete frame at exterior walls, where flashing is shown at lintels, shelf angles, and other conditions.

    3. Install dovetail anchor slots in concrete structures as indicated.

    3.3 REMOVING AND REUSING FORMS

    A. General: Formwork for sides of beams, walls, columns, and similar parts of the Work that does not support weight of concrete may be removed after cumulatively curing at not less than 50 deg F (10 deg C) for 24 hours after placing concrete. Concrete has to be hard enough to not be damaged by form-removal operations, and curing and protection operations need to be maintained.

    1. Leave formwork for beam soffits, joists, slabs, and other structural elements that support weight of concrete in place until concrete has achieved at least 70 percent of its 28-day design compressive strength.

    2. Remove forms only if shores have been arranged to permit removal of forms without loosening or disturbing shores.

    B. Clean and repair surfaces of forms to be reused in the Work. Split, frayed, delaminated, or otherwise damaged form-facing material are not acceptable for exposed surfaces. Apply new form-release agent.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 13

    C. When forms are reused, clean surfaces, remove fins and laitance, and tighten to close joints. Align and secure joints to avoid offsets. Do not use patched forms for exposed concrete surfaces unless approved by Architect.

    3.4 VAPOR-RETARDER INSTALLATION

    A. Sheet Vapor Retarders: Place, protect, and repair sheet vapor retarder according to ASTM E 1643 and manufacturer's written instructions.

    1. Lap joints 6 inches (150 mm) and seal with manufacturer's recommended tape.

    B. Bituminous Vapor Retarders: Place, protect, and repair bituminous vapor retarder according to manufacturer's written instructions.

    3.5 STEEL REINFORCEMENT INSTALLATION

    A. General: Comply with CRSI's "Manual of Standard Practice" for fabricating, placing, and supporting reinforcement.

    1. Do not cut or puncture vapor retarder. Repair damage and reseal vapor retarder before placing concrete.

    B. Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign materials that reduce bond to concrete.

    C. Accurately position, support, and secure reinforcement against displacement. Locate and support reinforcement with bar supports to maintain minimum concrete cover. Do not tack weld crossing reinforcing bars.

    1. Weld reinforcing bars according to AWS D1.4/D 1.4M, where indicated.

    D. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.

    E. Install welded-wire reinforcement in longest practicable lengths on bar supports spaced to minimize sagging. Lap edges and ends of adjoining sheets at least one mesh spacing. Offset laps of adjoining sheet widths to prevent continuous laps in either direction. Lace overlaps with wire.

    3.6 JOINTS

    A. General: Construct joints true to line with faces perpendicular to surface plane of concrete.

    B. Construction Joints: Install so strength and appearance of concrete are not impaired, at locations indicated or as approved by Architect.

    1. Place joints perpendicular to main reinforcement. Continue reinforcement across construction joints unless otherwise indicated. Do not continue reinforcement through sides of strip placements of floors and slabs.

    2. Form keyed joints as indicated. Embed keys at least 1-1/2 inches (38 mm) into concrete.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 14

    3. Locate joints for beams, slabs, joists, and girders in the middle third of spans. Offset joints in girders a minimum distance of twice the beam width from a beam-girder intersection.

    4. Use a bonding agent at locations where fresh concrete is placed against hardened or partially hardened concrete surfaces.

    5. Use epoxy-bonding adhesive at locations where fresh concrete is placed against hardened or partially hardened concrete surfaces.

    C. Contraction Joints in Slabs-on-Grade: Form weakened-plane contraction joints, sectioning concrete into areas as indicated. Construct contraction joints for a depth equal to at least one-fourth of concrete thickness as follows: 1. Sawed Joints: Form contraction joints with power saws equipped with shatterproof

    abrasive or diamond-rimmed blades. Cut 1/8-inch- (3.2-mm-) wide joints into concrete when cutting action does not tear, abrade, or otherwise damage surface and before concrete develops random contraction cracks.

    D. Isolation Joints in Slabs-on-Grade: After removing formwork, install joint-filler strips at slab junctions with vertical surfaces, such as column pedestals, foundation walls, grade beams, and other locations, as indicated.

    1. Extend joint-filler strips full width and depth of joint, terminating flush with finished concrete surface unless otherwise indicated.

    2. Terminate full-width joint-filler strips not less than 1/2 inch (13 mm) or more than 1 inch (25 mm) below finished concrete surface where joint sealants, specified in Section 079200 "Joint Sealants," are indicated.

    3. Install joint-filler strips in lengths as long as practicable. Where more than one length is required, lace or clip sections together.

    3.7 WATERSTOP INSTALLATION

    A. Flexible Waterstops: Install in construction joints and at other joints indicated to form a continuous diaphragm. Install in longest lengths practicable. Support and protect exposed waterstops during progress of the Work. Field fabricate joints in waterstops according to manufacturer's written instructions.

    B. Self-Expanding Strip Waterstops: Install in construction joints and at other locations indicated, according to manufacturer's written instructions, adhesive bonding, mechanically fastening, and firmly pressing into place. Install in longest lengths practicable.

    3.8 CONCRETE PLACEMENT

    A. Before placing concrete, verify that installation of formwork, reinforcement, and embedded items is complete and that required inspections are completed.

    B. Do not add water to concrete during delivery, at Project site, or during placement unless approved by Architect.

    C. Before test sampling and placing concrete, water may be added at Project site, subject to limitations of ACI 301 (ACI 301M).

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 15

    1. Do not add water to concrete after adding high-range water-reducing admixtures to mixture.

    D. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete is placed on concrete that has hardened enough to cause seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as indicated. Deposit concrete to avoid segregation.

    1. Deposit concrete in horizontal layers of depth not to exceed formwork design pressures and in a manner to avoid inclined construction joints.

    2. Consolidate placed concrete with mechanical vibrating equipment according to ACI 301 (ACI 301M).

    3. Do not use vibrators to transport concrete inside forms. Insert and withdraw vibrators vertically at uniformly spaced locations to rapidly penetrate placed layer and at least 6 inches (150 mm) into preceding layer. Do not insert vibrators into lower layers of concrete that have begun to lose plasticity. At each insertion, limit duration of vibration to time necessary to consolidate concrete and complete embedment of reinforcement and other embedded items without causing mixture constituents to segregate.

    E. Deposit and consolidate concrete for floors and slabs in a continuous operation, within limits of construction joints, until placement of a panel or section is complete.

    1. Consolidate concrete during placement operations, so concrete is thoroughly worked around reinforcement and other embedded items and into corners.

    2. Maintain reinforcement in position on chairs during concrete placement. 3. Screed slab surfaces with a straightedge and strike off to correct elevations. 4. Slope surfaces uniformly to drains where required. 5. Begin initial floating using bull floats or darbies to form a uniform and open-textured

    surface plane, before excess bleedwater appears on the surface. Do not further disturb slab surfaces before starting finishing operations.

    3.9 FINISHING FORMED SURFACES

    A. Rough-Formed Finish: As-cast concrete texture imparted by form-facing material with tie holes and defects repaired and patched. Remove fins and other projections that exceed specified limits on formed-surface irregularities.

    1. Apply to concrete surfaces not exposed to public view.

    B. Related Unformed Surfaces: At tops of walls, horizontal offsets, and similar unformed surfaces adjacent to formed surfaces, strike off smooth and finish with a texture matching adjacent formed surfaces. Continue final surface treatment of formed surfaces uniformly across adjacent unformed surfaces unless otherwise indicated.

    3.10 FINISHING FLOORS AND SLABS

    A. General: Comply with ACI 302.1R recommendations for screeding, restraightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 16

    B. Scratch Finish: While still plastic, texture concrete surface that has been screeded and bull-floated or darbied. Use stiff brushes, brooms, or rakes to produce a profile amplitude of 1/4 inch (6 mm) in one direction.

    1. Apply scratch finish to surfaces indicated and to receive mortar setting beds for bonded cementitious floor finishes.

    C. Float Finish: Consolidate surface with power-driven floats or by hand floating if area is small or inaccessible to power-driven floats. Restraighten, cut down high spots, and fill low spots. Repeat float passes and restraightening until surface is left with a uniform, smooth, granular texture.

    1. Apply float finish to surfaces indicated, to receive trowel finish and to be covered with fluid-applied or sheet waterproofing, built-up or membrane roofing, or sand-bed terrazzo.

    D. Trowel Finish: After applying float finish, apply first troweling and consolidate concrete by hand or power-driven trowel. Continue troweling passes and restraighten until surface is free of trowel marks and uniform in texture and appearance. Grind smooth any surface defects that would telegraph through applied coatings or floor coverings.

    1. Apply a trowel finish to surfaces exposed to view or to be covered with resilient flooring, carpet, ceramic or quarry tile set over a cleavage membrane, paint, or another thin-film-finish coating system.

    2. Finish surfaces to the following tolerances, according to ASTM E 1155 (ASTM E 1155M), for a randomly trafficked floor surface:

    a. Specified overall values of flatness, F(F) 25; and of levelness, F(L) 20; with minimum local values of flatness, F(F) 17; and of levelness, F(L) 15.

    E. Trowel and Fine-Broom Finish: Apply a first trowel finish to surfaces where ceramic or quarry tile is to be installed by either thickset or thinset method. While concrete is still plastic, slightly scarify surface with a fine broom.

    1. Comply with flatness and levelness tolerances for trowel-finished floor surfaces.

    F. Broom Finish: Apply a broom finish to exterior concrete platforms, steps, ramps, and elsewhere as indicated.

    1. Immediately after float finishing, slightly roughen trafficked surface by brooming with fiber-bristle broom perpendicular to main traffic route. Coordinate required final finish with Architect before application.

    3.11 MISCELLANEOUS CONCRETE ITEM INSTALLATION

    A. Filling In: Fill in holes and openings left in concrete structures after work of other trades is in place unless otherwise indicated. Mix, place, and cure concrete, as specified, to blend with in-place construction. Provide other miscellaneous concrete filling indicated or required to complete the Work.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 17

    B. Curbs: Provide monolithic finish to interior curbs by stripping forms while concrete is still green and by steel-troweling surfaces to a hard, dense finish with corners, intersections, and terminations slightly rounded.

    C. Equipment Bases and Foundations:

    1. Coordinate sizes and locations of concrete bases with actual equipment provided. 2. Construct concrete bases [4 inches (100 mm)] [6 inches (150 mm)] [8 inches (200 mm)]

    high unless otherwise indicated, and extend base not less than 6 inches (150 mm) in each direction beyond the maximum dimensions of supported equipment unless otherwise indicated or unless required for seismic anchor support.

    3. Minimum Compressive Strength: [5000 psi (34.5 MPa)] [4500 psi (31 MPa)] [4000 psi (27.6 MPa)] [3500 psi (24.1 MPa)] [3000 psi (20.7 MPa)] at 28 days.

    4. Install dowel rods to connect concrete base to concrete floor. Unless otherwise indicated, install dowel rods on 18-inch (450-mm) centers around the full perimeter of concrete base.

    5. For supported equipment, install epoxy-coated anchor bolts that extend through concrete base and anchor into structural concrete substrate.

    6. Prior to pouring concrete, place and secure anchorage devices. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

    7. Cast anchor-bolt insert into bases. Install anchor bolts to elevations required for proper attachment to supported equipment.

    D. Steel Pan Stairs: Provide concrete fill for steel pan stair treads, landings, and associated items. Cast-in inserts and accessories as shown on Drawings. Screed, tamp, and trowel finish concrete surfaces.

    3.12 CONCRETE PROTECTING AND CURING

    A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection and ACI 305.1 (ACI 305.1M) for hot-weather protection during curing.

    B. Evaporation Retarder: Apply evaporation retarder to unformed concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h (1 kg/sq. m x h) before and during finishing operations. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing.

    C. Formed Surfaces: Cure formed concrete surfaces, including underside of beams, supported slabs, and other similar surfaces. If forms remain during curing period, moist cure after loosening forms. If removing forms before end of curing period, continue curing for remainder of curing period.

    D. Unformed Surfaces: Begin curing immediately after finishing concrete. Cure unformed surfaces, including floors and slabs, concrete floor toppings, and other surfaces.

    E. Cure concrete according to ACI 308.1, by one or a combination of the following methods:

    1. Moisture Curing: Keep surfaces continuously moist for not less than seven days with the following materials:

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 18

    a. Water. b. Continuous water-fog spray. c. Absorptive cover, water saturated, and kept continuously wet. Cover concrete

    surfaces and edges with 12-inch (300-mm) lap over adjacent absorptive covers.

    2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 12 inches (300 mm), and sealed by waterproof tape or adhesive. Cure for not less than seven days. Immediately repair any holes or tears during curing period, using cover material and waterproof tape.

    a. Moisture cure or use moisture-retaining covers to cure concrete surfaces to receive floor coverings.

    b. Moisture cure or use moisture-retaining covers to cure concrete surfaces to receive penetrating liquid floor treatments.

    c. Cure concrete surfaces to receive floor coverings with either a moisture-retaining cover or a curing compound that the manufacturer certifies does not interfere with bonding of floor covering used on Project.

    3. Curing Compound: Apply uniformly in continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Maintain continuity of coating and repair damage during curing period.

    a. Removal: After curing period has elapsed, remove curing compound without damaging concrete surfaces by method recommended by curing compound manufacturer unless manufacturer certifies curing compound does not interfere with bonding of floor covering used on Project.

    4. Curing and Sealing Compound: Apply uniformly to floors and slabs indicated in a continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Repeat process 24 hours later and apply a second coat. Maintain continuity of coating and repair damage during curing period.

    3.13 LIQUID FLOOR TREATMENT APPLICATION

    A. Penetrating Liquid Floor Treatment: Prepare, apply, and finish penetrating liquid floor treatment according to manufacturer's written instructions.

    1. Remove curing compounds, sealers, oil, dirt, laitance, and other contaminants and complete surface repairs.

    2. Do not apply to concrete that is less than 28 days old. 3. Apply liquid until surface is saturated, scrubbing into surface until a gel forms; rewet;

    and repeat brooming or scrubbing. Rinse with water; remove excess material until surface is dry. Apply a second coat in a similar manner if surface is rough or porous.

    B. Sealing Coat: Uniformly apply a continuous sealing coat of curing and sealing compound to hardened concrete by power spray or roller according to manufacturer's written instructions.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 19

    3.14 JOINT FILLING

    A. Prepare, clean, and install joint filler according to manufacturer's written instructions.

    1. Defer joint filling until concrete has aged at least one month(s). Do not fill joints until construction traffic has permanently ceased.

    B. Remove dirt, debris, saw cuttings, curing compounds, and sealers from joints; leave contact faces of joints clean and dry.

    C. Install semirigid joint filler full depth in saw-cut joints and at least 2 inches (50 mm) deep in formed joints. Overfill joint and trim joint filler flush with top of joint after hardening.

    3.15 CONCRETE SURFACE REPAIRS

    A. Defective Concrete: Repair and patch defective areas when approved by Architect. Remove and replace concrete that cannot be repaired and patched to Architect's approval.

    B. Patching Mortar: Mix dry-pack patching mortar, consisting of 1 part portland cement to 2-1/2 parts fine aggregate passing a No. 16 (1.18-mm) sieve, using only enough water for handling and placing.

    C. Repairing Unformed Surfaces: Test unformed surfaces, such as floors and slabs, for finish and verify surface tolerances specified for each surface. Correct low and high areas. Test surfaces sloped to drain for trueness of slope and smoothness; use a sloped template.

    1. Repair finished surfaces containing defects. Surface defects include spalls, popouts, honeycombs, rock pockets, crazing and cracks in excess of 0.01 inch (0.25 mm) wide or that penetrate to reinforcement or completely through unreinforced sections regardless of width, and other objectionable conditions.

    2. After concrete has cured at least 14 days, correct high areas by grinding. 3. Correct localized low areas during or immediately after completing surface finishing

    operations by cutting out low areas and replacing with patching mortar. Finish repaired areas to blend into adjacent concrete.

    4. Correct other low areas scheduled to receive floor coverings with a repair underlayment. Prepare, mix, and apply repair underlayment and primer according to manufacturer's written instructions to produce a smooth, uniform, plane, and level surface. Feather edges to match adjacent floor elevations.

    5. Correct other low areas scheduled to remain exposed with a repair topping. Cut out low areas to ensure a minimum repair topping depth of 1/4 inch (6 mm) to match adjacent floor elevations. Prepare, mix, and apply repair topping and primer according to manufacturer's written instructions to produce a smooth, uniform, plane, and level surface.

    6. Repair defective areas, except random cracks and single holes 1 inch (25 mm) or less in diameter, by cutting out and replacing with fresh concrete. Remove defective areas with clean, square cuts and expose steel reinforcement with at least a 3/4-inch (19-mm) clearance all around. Dampen concrete surfaces in contact with patching concrete and apply bonding agent. Mix patching concrete of same materials and mixture as original concrete, except without coarse aggregate. Place, compact, and finish to blend with adjacent finished concrete. Cure in same manner as adjacent concrete.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 20

    7. Repair random cracks and single holes 1 inch (25 mm) or less in diameter with patching mortar. Groove top of cracks and cut out holes to sound concrete and clean off dust, dirt, and loose particles. Dampen cleaned concrete surfaces and apply bonding agent. Place patching mortar before bonding agent has dried. Compact patching mortar and finish to match adjacent concrete. Keep patched area continuously moist for at least 72 hours.

    D. Perform structural repairs of concrete, subject to Architect's approval, using epoxy adhesive and patching mortar.

    E. Repair materials and installation not specified above may be used, subject to Architect's approval.

    3.16 FIELD QUALITY CONTROL

    A. Special Inspections: Owner will engage a special inspector and qualified testing and inspecting agency to perform field tests and inspections and prepare test reports.

    B. Inspections:

    1. Steel reinforcement placement. 2. Steel reinforcement welding. 3. Headed bolts and studs. 4. Verification of use of required design mixture. 5. Concrete placement, including conveying and depositing. 6. Curing procedures and maintenance of curing temperature. 7. Verification of concrete strength before removal of shores and forms from beams and

    slabs.

    C. Concrete Tests: Testing of composite samples of fresh concrete obtained according to ASTM C 172/C 172M shall be performed according to the following requirements:

    1. Testing Frequency: Obtain one composite sample for each day's pour of each concrete mixture exceeding 5 cu. yd. (4 cu. m), but less than 25 cu. yd. (19 cu. m), plus one set for each additional 50 cu. yd. (38 cu. m) or fraction thereof.

    2. Testing Frequency: Obtain at least one composite sample for each 100 cu. yd. (76 cu. m) or fraction thereof of each concrete mixture placed each day.

    a. When frequency of testing provides fewer than five compressive-strength tests for each concrete mixture, testing shall be conducted from at least five randomly selected batches or from each batch if fewer than five are used.

    3. Slump: ASTM C 143/C 143M; one test at point of placement for each composite sample, but not less than one test for each day's pour of each concrete mixture. Perform additional tests when concrete consistency appears to change.

    4. Air Content: ASTM C 231/C 231M, pressure method, for normal-weight concrete; one test for each composite sample, but not less than one test for each day's pour of each concrete mixture.

    5. Concrete Temperature: ASTM C 1064/C 1064M; one test hourly when air temperature is 40 deg F (4.4 deg C) and below or 80 deg F (27 deg C) and above, and one test for each composite sample.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    CAST-IN-PLACE CONCRETE 033000 - 21

    6. Unit Weight: ASTM C 567/C 567M, fresh unit weight of structural lightweight concrete; one test for each composite sample, but not less than one test for each day's pour of each concrete mixture.

    7. Compression Test Specimens: ASTM C 31/C 31M.

    a. Cast and laboratory cure two sets of two standard cylinder specimens for each composite sample.

    b. Cast and field cure two sets of two standard cylinder specimens for each composite sample.

    8. Compressive-Strength Tests: ASTM C 39/C 39M; test one set of two laboratory-cured specimens at 7 days and one set of two specimens at 28 days.

    a. Test one set of two field-cured specimens at 7 days and one set of two specimens at 28 days.

    b. A compressive-strength test shall be the average compressive strength from a set of two specimens obtained from same composite sample and tested at age indicated.

    9. When strength of field-cured cylinders is less than 85 percent of companion laboratory-cured cylinders, Contractor shall evaluate operations and provide corrective procedures for protecting and curing in-place concrete.

    10. Strength of each concrete mixture will be satisfactory if every average of any three consecutive compressive-strength tests equals or exceeds specified compressive strength and no compressive-strength test value falls below specified compressive strength by more than 500 psi (3.4 MPa).

    11. Test results shall be reported in writing to Architect, concrete manufacturer, and Contractor within 48 hours of testing. Reports of compressive-strength tests shall contain Project identification name and number, date of concrete placement, name of concrete testing and inspecting agency, location of concrete batch in Work, design compressive strength at 28 days, concrete mixture proportions and materials, compressive breaking strength, and type of break for both 7- and 28-day tests.

    12. Nondestructive Testing: Impact hammer, sonoscope, or other nondestructive device may be permitted by Architect but will not be used as sole basis for approval or rejection of concrete.

    13. Additional Tests: Testing and inspecting agency shall make additional tests of concrete when test results indicate that slump, air entrainment, compressive strengths, or other requirements have not been met, as directed by Architect. Testing and inspecting agency may conduct tests to determine adequacy of concrete by cored cylinders complying with ASTM C 42/C 42M or by other methods as directed by Architect.

    14. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements.

    15. Correct deficiencies in the Work that test reports and inspections indicate do not comply with the Contract Documents.

    END OF SECTION 033000

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    GLASS-FIBER-REINFORCED CONCRETE (GFRC) 034900 - 1

    SECTION 034900 - GLASS-FIBER-REINFORCED CONCRETE (GFRC)

    PART 1 - GENERAL

    1.1 RELATED DOCUMENTS

    A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

    1.2 SUMMARY

    A. Section includes glass-fiber-reinforced concrete (GFRC) panels consisting of GFRC, panel frames, anchors, and connection hardware.

    1. GFRC panels include wall units and column covers.

    B. Related Requirements:

    1. Section 051200 "Structural Steel Framing" for attaching connection devices to steel framing. 2. Section 079200 "Joint Sealants" for elastomeric joint sealants and sealant backings.

    1.3 DEFINITIONS

    A. Design Reference Sample: Sample of GFRC color, finish, and texture that has been preapproved by Architect before execution of the Contract.

    1. Design Reference Sample: Matching approved cast stone.

    1.4 PREINSTALLATION MEETINGS

    A. Preinstallation Conference: Conduct conference at Project site.

    1.5 ACTION SUBMITTALS

    A. Product Data: For each type of product. Include GFRC design mixes.

    B. Shop Drawings: Show fabrication and installation details for GFRC panels including the following:

    1. Panel elevations, sections, and dimensions. 2. Thickness of facing mix, GFRC backing, and bonding pads for typical panels. 3. Finishes. 4. Joint and connection details. 5. Erection details. 6. Panel frame details for typical panels including sizes, spacings, thicknesses, and yield strengths of

    various members.

    7. Locations and details of connection hardware attached to structure. 8. Sizes, locations, and details of flex, gravity, and seismic anchors for typical panels. 9. Other items sprayed into panels.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    GLASS-FIBER-REINFORCED CONCRETE (GFRC) 034900 - 2

    10. Erection sequence for special conditions. 11. Relationship to adjacent materials. 12. Description of loose, cast-in, and field hardware.

    C. Samples for Verification: For each type of finish indicated on exposed GFRC surfaces, representative of finish, color, and texture variations expected, approximately 12 by 12 inches (305 by 305 mm) by actual

    thickness.

    D. Delegated-Design Submittal: For GFRC panels, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.

    1.6 INFORMATIONAL SUBMITTALS

    A. Qualification Data: For manufacturer.

    B. Welding certificates.

    C. Steel Sheet Certificates: For steel sheet used in cold-formed steel panel framing, mill certificates signed by manufacturers of steel sheet, or test reports from a qualified testing agency, indicating that steel sheet

    used in cold-formed metal panel framing complies with requirements including uncoated steel thickness,

    yield strength, tensile strength, total elongation, chemical requirements, and galvanized-coating thickness.

    D. Mill Certificates: For structural-steel shapes and hollow structural sections used in panel framing.

    E. Source Quality-Control Program: For GFRC manufacturer.

    F. Source Quality-Control Test Reports: For GFRC, inserts, and anchors.

    1.7 QUALITY ASSURANCE

    A. Manufacturer Qualifications: Designated a PCI-certified plant for Group G - Glass Fiber Reinforced Concrete or designated an APA-certified plant for GFRC production.

    B. Installer Qualifications: Manufacturer of GFRC panels.

    C. Welding Qualifications: Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural Welding Code - Steel," and AWS D1.3/D1.3M, "Structural Welding Code - Sheet Steel."

    D. Mockups: Build mockups to demonstrate aesthetic effects and to set quality standards for fabrication and installation.

    1. Build mockup of typical wall area as shown on Drawings.

    a. Include typical components, attachments to building structure, and methods of installation. b. Include window opening with GFRC returns. c. Include sealant-filled joint complying with requirements in Section 079200 "Joint

    Sealants."

    2. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    GLASS-FIBER-REINFORCED CONCRETE (GFRC) 034900 - 3

    1.8 DELIVERY, STORAGE, AND HANDLING

    A. Handle and transport GFRC panels supported on nonstaining material and with nonstaining resilient spacers between panels.

    B. Store GFRC panels off of ground on firm, level, and smooth surfaces supported on nonstaining material and with nonstaining resilient spacers between panels. Place stored panels so identification marks are

    clearly visible.

    PART 2 - PRODUCTS

    2.1 MANUFACTURERS

    A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

    1. Advanced Architectural Stone, Fort Worth, Texas. 2. Cary Concrete Products, Inc., Woodstock, Illinois. 3. Coastal Precast Systems, Inc., Chesapeake, Virginia. 4. Conewago Precast Building System, Hanover, Pennsylvania. 5. Custom Castings Northeast, Inc., Lemont, Pennsylvania. 6. Pioneer Concrete, Inc., Wilmington, Delaware. 7. Towne House Restorations, Brooklyn, New York.

    B. Source Limitations: Obtain GFRC panels from single source from single manufacturer.

    2.2 PERFORMANCE REQUIREMENTS

    A. Delegated Design: Engage a qualified professional engineer, as defined in Section 014000 "Quality Requirements," to design GFRC panels, including panel frames, anchors, and connections.

    B. Structural Performance: GFRC panels, including panel frames, anchors, and connections, shall withstand the following design loads as well as the effects of thermal- and moisture-induced dimensional changes

    within limits and under conditions indicated:

    1. Loads: As indicated. 2. Deflection Limits: Design panel frames to withstand design loads without lateral deflections

    greater than 1/240 of wall span.

    3. Thermal Movements: Provide for thermal movements resulting from annual ambient temperature changes of 120 deg F (67 deg C).

    4. Design panel frames and connections to accommodate deflections and other building movements. 5. Design panel frames to transfer window loads to building structure.

    C. PCI Manuals: Comply with requirements and recommendations in the following PCI manuals unless more stringent requirements are indicated:

    1. PCI MNL 128, "Recommended Practice for Glass Fiber Reinforced Concrete Panels." 2. PCI MNL 130, "Manual for Quality Control for Plants and Production of Glass Fiber Reinforced

    Concrete Products."

    D. AISI Specifications: Comply with AISI's "North American Specification for the Design of Cold-Formed Steel Structural Members."

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    GLASS-FIBER-REINFORCED CONCRETE (GFRC) 034900 - 4

    E. AISC Specifications: Comply with AISC 360, "Specification for Structural Steel Buildings."

    2.3 MOLD MATERIALS

    A. Molds: Rigid, dimensionally stable, non-absorptive material, warp and buckle free, that provides continuous GFRC surfaces within tolerances; nonreactive with GFRC and capable of producing required

    finish surfaces.

    1. Mold-Release Agent: Commercially produced liquid-release agent that does not bond with, stain, or adversely affect GFRC surfaces and does not impair subsequent surface or joint treatments of

    GFRC.

    B. Form Liners: Units of face design, texture, arrangement, and configuration to match GFRC design reference sample. Provide solid backing and form supports to ensure that form liners remain in place

    during GFRC application. Use with manufacturer's recommended liquid-release agent that does not bond

    with, stain, or adversely affect GFRC surfaces and does not impair subsequent surface or joint treatments

    of GFRC.

    C. Surface Retarder: Chemical liquid-set retarder capable of temporarily delaying hardening of newly placed GFRC face mix to depth of reveal specified.

    2.4 GFRC MATERIALS

    A. Portland Cement: ASTM C 150/C 150M; Type I, II, or III.

    1. For surfaces exposed to view in finished structure, use white of same type, brand, and source throughout GFRC production.

    B. Metakaolin: ASTM C 618, Class N.

    C. Glass Fibers: Alkali resistant, with a minimum zirconia content of 16 percent, 1 to 2 inches (25 to 50 mm) long, specifically produced for use in GFRC, and complying with ASTM C 1666/C 1666M.

    D. Sand: Washed and dried silica, complying with composition requirements in ASTM C 144; passing a No. 20 (0.85-mm) sieve with a maximum of 2 percent passing a No. 100 (0.15-mm) sieve.

    E. Facing Aggregate: ASTM C 33/C 33M, except for gradation, and PCI MNL 130, 1/4-inch (6-mm) maximum size.

    1. Aggregates: Selected, hard, and durable; free of material that reacts with cement or causes staining; to match sample.

    2. Fine Aggregate: Natural or manufactured sand with a maximum of 5 percent passing a No. 100 (0.15-mm) sieve and a maximum of 3 percent passing a No. 200 (0.075-mm) sieve.

    F. Coloring Admixture: ASTM C 979/C 979M, synthetic mineral-oxide pigments or colored water-reducing admixtures, temperature stable, nonfading, and alkali resistant.

    G. Water: Potable; free from deleterious material that may affect color stability, setting, or strength of GFRC and complying with chemical limits in PCI MNL 130.

    H. Polymer-Curing Admixture: Acrylic thermoplastic copolymer dispersion complying with PCI MNL 130.

    I. Air-Entraining Admixture: ASTM C 260/C 260M, containing not more than 0.1 percent chloride ions.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    GLASS-FIBER-REINFORCED CONCRETE (GFRC) 034900 - 5

    J. Chemical Admixtures: ASTM C 494/C 494M, containing not more than 0.1 percent chloride ions.

    2.5 ANCHORS, CONNECTORS, AND MISCELLANEOUS MATERIALS

    A. Stainless-Steel Plates: ASTM A 240/A 240M or ASTM A 666, Type 304.

    B. Carbon-Steel Shapes and Plates: ASTM A 36/A 36M, finished as follows:

    1. Finish: Zinc coated by hot-dip process according to ASTM A 123/A 123M, after fabrication, or ASTM A 153/A 153M, as applicable.

    2. Finish: Shop primed with paint complying with MPI#79 on surfaces prepared to comply with SSPC-SP 2, "Hand Tool Cleaning," or better.

    C. Stainless-Steel Bars and Shapes: ASTM A 276, Type 304.

    D. Carbon-Steel Bars: ASTM A 108, Grade 1018, not less than 1/4 inch (6 mm) in diameter, finished as follows:

    1. Finish: Zinc coated by hot-dip process according to ASTM A 123/A 123M, after fabrication, or ASTM A 153/A 153M, as applicable.

    2. Finish: Shop primed with paint complying with MPI#79 on surfaces prepared to comply with SSPC-SP 2, "Hand Tool Cleaning," or better.

    E. Malleable-Iron Castings: ASTM A 47/ A 47M, Grade 32510 (Grade 22010).

    F. Carbon-Steel Castings: ASTM A 27/A 27M, Grade 60-30 (Grade 415-205).

    G. Bolts: ASTM A 307 or ASTM A 325 (ASTM F 568M or ASTM A 325M), finished as follows:

    1. Finish: Zinc coated by hot-dip process according to ASTM A 123/A 123M, after fabrication, and ASTM A 153/A 153M, as applicable.

    H. Reglets: Stainless steel, ASTM A 240/A 240M, Type 304, 0.016 inch (0.40 mm) thick.

    2.6 PANEL FRAME MATERIALS

    A. Cold-Formed Steel Framing: Manufacturer's standard C-shaped steel studs, complying with AISI's "North American Specification for the Design of Cold-Formed Steel Structural Members," with minimum

    uncoated steel thickness of 0.053 inch (1.35 mm); with stiffened flanges, U-shaped steel track; and of the

    following steel sheet:

    1. Metallic-Coated Steel Sheet: ASTM A 653/A 653M, structural-steel sheet, G90 (Z275) zinc coating, of grade required by structural performance of framing.

    B. Hollow Structural Sections: Steel tubing, ASTM A 500/A 500M, Grade B, or ASTM A 513, finished as follows:

    1. Finish: Shop primed with organic zinc-rich primer complying with SSPC-Paint 20 on surfaces prepared to comply with SSPC-SP 6/NACE No. 3, "Commercial Blast Cleaning."

    C. Steel Channels and Angles: ASTM A 36/A 36M, finished as follows:

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    GLASS-FIBER-REINFORCED CONCRETE (GFRC) 034900 - 6

    1. Finish: Shop primed with organic zinc-rich primer complying with SSPC-Paint 20 on surfaces prepared to comply with SSPC-SP 6/NACE No. 3, "Commercial Blast Cleaning."

    2.7 GFRC MIXES

    A. Mist Coat: Portland cement, sand slurry, and admixtures; of same proportions as backing mix without glass fibers.

    B. Face Mix: Proportion face mix of portland cement, sand, facing aggregates, and admixtures to comply with design requirements.

    C. Backing Mix: Proportion backing mix of portland cement, glass fibers, sand, and admixtures to comply with design requirements. Provide nominal glass-fiber content of not less than 5 percent by weight of

    total mix.

    D. Polymer-Curing Admixture: 6 to 7 percent by weight of polymer-curing admixture solids to dry portland cement.

    E. Air Content: 8 to 10 percent; ASTM C 185.

    F. Coloring Admixture: Not to exceed 10 percent of cement weight.

    2.8 PANEL FRAME FABRICATION

    A. Fabricate panel frames and accessories plumb, square, true to line, and with components securely fastened.

    1. Fabricate panel frames using jigs or templates. 2. Cut cold-formed metal framing members by sawing or shearing; do not torch cut. 3. Fasten cold-formed metal framing members by welding. Comply with AWS D1.3/D1.3M. 4. Fasten framing members of hollow structural sections, steel channels, or steel angles by welding.

    Comply with AWS D1.1/D1.1M.

    5. Weld anchors to panel frames.

    B. Reinforce framing assemblies, as necessary, to withstand erection stresses.

    C. Galvanizing Repair: Touch up damaged galvanized surfaces according to ASTM A 780/A 780M.

    D. Painting Repair: Touch up damaged painted surfaces using same primer.

    2.9 MOLD FABRICATION

    A. Construct molds that result in finished GFRC complying with profiles, dimensions, and tolerances indicated, without damaging GFRC during stripping. Construct molds to prevent water leakage and loss

    of cement paste.

    1. Coat contact surfaces of molds with form-release agent. 2. Coat contact surfaces of molds with surface retarder.

    B. Place form liners accurately to provide finished surface texture indicated. Provide solid backing and supports to maintain stability of liners during GFRC application. Coat form liner with form-release agent.

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    GLASS-FIBER-REINFORCED CONCRETE (GFRC) 034900 - 7

    C. Locate, place, and secure flashing reglets accurately.

    2.10 GFRC FABRICATION

    A. Proportioning and Mixing: For backing mix, meter sand/cement slurry and glass fibers to spray head at rates to achieve design mix proportions and glass-fiber content according to PCI MNL 130 procedures.

    B. Spray Application: Comply with general procedures as follows:

    1. Spray or place face mix in thickness indicated on Shop Drawings. 2. Proceed with spraying backing mix before face mix has set, using procedures that produce a

    uniform thickness and even distribution of glass fibers and matrix.

    3. Consolidate backing mix by rolling or other technique to achieve complete encapsulation of glass fibers and compaction.

    4. Measure thickness with a pin gage or other acceptable method at least once for every 5 sq. ft. (0.5 sq. m) of panel surface. Take no fewer than six measurements per panel.

    C. Hand form and consolidate intricate details, incorporate formers or infill materials, and overspray before material reaches initial set to ensure complete bonding.

    D. Attach panel frame to GFRC before initial set of GFRC backing, maintaining a minimum clearance of 1/2 inch (13 mm) from GFRC backing, and without anchors protruding into GFRC backing.

    E. Build up homogeneous GFRC bonding pads over anchor feet, maintaining a minimum thickness of 1/2 inch (13 mm) over tops of anchor feet, before initial set of GFRC backing. Measure bonding pad

    thickness at 25 percent of anchor locations.

    F. Inserts and Embedments: Build up homogeneous GFRC bosses or bonding pads over inserts and embedments to provide enough anchorage and embedment to comply with design requirements.

    G. Curing: Employ initial curing method that ensures sufficient strength for removing units from mold. Comply with PCI MNL 130 procedures.

    1. Keep moisture off of the surfaces of mixes with polymer curing admixtures during the first three hours of curing. Maintain temperature between 60 and 120 deg F (16 and 49 deg C) during the

    first 16 hours.

    2. Prevent drying of moist curing mixes during the first 24 hours. Maintain units in surface-damp condition at a temperature above 60 deg F (16 deg C) and 95 percent relative humidity for seven

    days.

    H. Panel Identification: Mark each GFRC panel to correspond with identification mark on Shop Drawings. Mark each panel with its casting date.

    2.11 FABRICATION TOLERANCES

    A. Manufacturing Tolerances: Manufacture GFRC panels so each finished unit complies with PCI MNL 130 for dimension, position, and tolerances.

    B. Manufacturing Tolerances: Manufacture GFRC panels so each finished unit complies with the following dimensional tolerances. For dimensional tolerances not listed below, comply with PCI MNL 130.

    1. Overall Height and Width of Units, Measured at the Face Adjacent to Mold: As follows:

  • NEW CAESAR RODNEY ELEMENTARY SCHOOL 2017073.00

    GLASS-FIBER-REINFORCED CONCRETE (GFRC) 034900 - 8

    a. 10 feet (3 m) or less, plus or minus 1/8 inch (3 mm). b. More than 10 feet (3 m), plus or minus 1/8 inch per 10 feet (3 mm per 3 m); 1/4 inch (6

    mm) maximum.

    2. Edge Return Thickness: Plus 1/2 inch (13 mm), minus zero inch (zero mm). 3. Architectural Facing Thickness: Plus 1/8 inch (3 mm), minus zero inch (zero mm). 4. Backing Thickness: Plus 1/4 inch (6 mm), minus zero inch (zero mm). 5. Panel Depth from Face of Skin to Back of Panel Frame or Integral Rib: Plus 3/8 inch (10 mm),

    minus 1/4 inch (6 mm).

    6. Angular Variation of Plane of Side Mold: Plus or minus 1/32 inch per 3 inches (0.8 mm per 75 mm) of depth, or plus or minus 1/16 inch (1.5 mm) total, whichever is greater.

    7. Variation from Square or Designated Skew (Difference in Length of Two Diagonal Measurements): Plus or minus 1/8 inch per 72 inches (3 mm per 1800 mm) or plus or minus 1/4

    inch (6 mm) total, whichever is greater.

    8. Local Smoothness: 1/4 inch per 10 feet (6 mm per 3 m). 9. Bowing: Not to exceed L/240 unless unit complies with erection tolerances using connection

    adjustments.

    10. Length and Width of Block Outs and Openings within One Unit: Plus or minus 1/4 inch (6 mm). 11. Location of Window Opening within Panel: Plus or minus 1/4 inch (6 mm). 12. Maximum Permissible Warpage of One Corner out of the Plane of the Other Three: 1/16 inch per

    12 inches (1.5 mm per 305 mm) of distance from nearest adjacent corner.

    C. Position Tolerances: Measured from datum line locations, as indicated on Shop Drawings.

    1. Panel Frame and Track: Plus or minus 1/4 inch (6 mm). 2. Flashing Reglets at Edge of Panel: Plus or minus 1/4 inch (6 mm). 3. Inserts: Plus or minus 1/2 inch (13 mm). 4. Special Handling Devices: Plus or minus 3 inches (75 mm). 5. Location of Bearing Devices: Plus or minus 1/4 inch (6 mm). 6. Blockouts: Plus or minus 3/8 inch (10 mm).

    D. Panel Frame Tolerances: As follows:

    1. Vertical and Horizontal Alignment: 1/4 inch per 10 feet (6 mm per 3 m). 2. Spacing of Framing Member: Plus or minus 3/8 inch (10 mm). 3. Squareness of Frame: Difference in length of diagonals of 3/8 inch (10 mm). 4. Overall Size of Frame: Plus or minus 3/8 inch (10 mm).

    2.12 FINISHES

    A. Exposed faces shall be free of joint marks, grain, and other obvious defects. Corners, including false joints, shall be uniform, straight, and sharp. Finish exposed-face surfaces of GFRC to match approved

    design reference sample, mockups, and as follows:

    1. Acid-Etched Finish: Use acid and hot-water solution equipment, application techniques, and cleaning procedures to expose aggregate and surrounding matrix surfaces.

    2.13 SOURCE QUALITY CONTROL

    A. Quality-Control Testing: Establish and maintain a quality-control program for manufacturing GFRC panels according to PCI MNL 130.

    1. Test materials and inspect production techniques.

  • NEW CAESAR RODNEY ELEMENT