Upload
josef-navarro
View
215
Download
0
Embed Size (px)
Citation preview
8/13/2019 Spoolbase processl
1/4
Page 1 of 4
OPERATIONS BRIEFING
For
Onshore Spoolbase Fabrication
Pipeline Technique Ltd Ref: OSSB-001
Created: December 2006
8/13/2019 Spoolbase processl
2/4
Ref: OSSB-001 Rev 1
Page 2 of 4
This document has been produced with the intention to show how the process of Spoolbase
Fabrication takes place.
The facility and equipment shown was originally mobilised to cater for Helix Energy Solutions(ESG) 2006 Reeled Pipelines 2006 Campaign.
The facility was located at the port of Hartlepool in the UK, and was initially in production during
the 3rd
and 4th
quarters of 2006.
1. On completion and acceptance of the pipe joint inspection,the pipe is relocated along the ready racks into the productionline front end for preparation and inclusion into the pipe stalk
production line.
2. Factory bevelled pipes will be cleaned using a powered wirebrush or re-bevelled to comply with the project WPS. Square
cut end supplied pipe will be bevelled in accordance with the
approved WPS. If any bevel is considered outside of the
acceptable limits after inspection it will be re-bevelled in
accordance with the approved WPS.
3. In some cases, a factory supplied bevel could be considereddamaged beyond effective repair. The pipe joint would be
removed from the ready rack and therefore not inserted into
the production line.
4. The QC Discipline Inspector shall verify the following priorto releasing the joint into the production line.
The pipe bevels are in accordance with the approved project
WPS.
Identify the joints unique identification number and record
acceptance of the joint into the PTS Mainline Welding
Inspection Report (MWSR).
5. All mainline production welding activities take place on theSpoolbase production line under the control of the Welding
Foreman in cooperation with the QC Supervisor and QCDiscipline Inspector to ensure that WPS requirements are
adhered to.
8/13/2019 Spoolbase processl
3/4
Ref: OSSB-001 Rev 1
Page 3 of 4
6. Mainline production welding verification activities include:Welding consumables type, batch/lot number and size
Pipe alignment, fit-up and clamping
Minimum preheat
All welding passes
7. During mainline production welding the QC DisciplineInspector shall carry out the inspections in accordance with
the project ITP to ensure the requirements of the approved
project WPS are adhered to. Typical inspection activities are
as follows:Alignment fit up and clamping
Preheat and inter-pass temperatures (and gas purge level
where applicable in the range of the approved WPS)
Travel speed and heat input
Verification of welder identity number, stalk/weld number,
WPS number, pipe joint number
On completion of the first (root bead) pass and the initial
check by the welder(s), visually inspect the partially
completed joint. Any remedial work identified at this point
shall be immediately re-worked by the welder(s) per pre-
approved procedures and shall be re-inspected
Following acceptance of first pass welding, prior to and
during subsequent welding monitor inter-pass temperature
On completion of the welded joint and the initial check by
the welder(s), visually inspect the completed joint
The initial check, visual inspection and any required
remedial work identified at this point must be completed
whilst the joint remains above the minimum pre-heat
temperature of the accepted WPS
QC Discipline inspector shall complete the information on
the MWSR in accordance with the ITP.
8. The PTL or QC Discipline Inspector shall carry out awelding audit on the production line. The frequency of theaudit shall be stipulated in the ITP, but as minimum it shall
be carried out at least once during each shift verifying detail
on the MWSR.
8/13/2019 Spoolbase processl
4/4
Ref: OSSB-001 Rev 1
Page 4 of 4
9. All mainline production welds shall be subjected to 100%on line NDE in accordance wit the approved project
supplied procedures.
10. All NDE reports shall be signed and approved by theevaluating NDE Technician and PTL or QC NDE
representative. At the end of each shift the original NDE
documentation for the production shift shall be submitted by
the NDE supervisor to the Spoolbase QC Supervisor for
review.
11. Field Joint Coating sub-contractor activities shall be carriedout in accordance with approved project procedures. Field
Joint Coating Supervisor shall report to the Spoolbase
Assistant Manager / Superintendent.
12. If required by the project, Pipe stalks will be marked withpaint at each weld location using 2 high stencils. The
relevant stalk number and weld number will be marked on
the pipe at 2 locations 180 degrees apart on each side of the
joint. Numbers will be marked prior to completion of field
joint coating.
Any sacrificial or non-permanent pipe strings (i.e.
straightening trial, Lead & Tail Strings) shall be uncoated.
These pipe sections will not be included as part of the
permanent pipeline.
13. The completed pipe string (stalk) will then be lifted from theoutbound rollers, to the stalk rack to await Vessel
Mobilisation.