Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
SPINNING RESERVE ASSESSMENTIN
INTERCONNECTEDGENERATION SYSTEMS
A Thesis
Submitted to the College of Graduate Studies and Research
in Partial Fulfillment of the Requirements
for the Degree of
Doctor of Philosophyin the
Department of Electrical Engineering
Univ rsity of Saskatchewan
by
NURUL AMIN CHOWDHURY
Saskatoon, Saskatchewan
February 1989
The author claims copyright. Use shall not be made of the material con
tained herein without proper acknowledgement, as indicated on the copyrightpage.
COPYRIGHT
The author has agreed that the Library, University of Saskatchewan,
may make this thesis freely available for inspection. Moreover, the author
has agreed that permission for extensive copying of this thesis for scholarly
purposes may be granted by the Professor who supervised the thesis work
recorded herein or, in his absence, by the Head of the Department or the
Dean of the College in which the thesis work was done. It is understood
that due recognition will be given to the author of this thesis and to the
University of Saskatchewan in any use of the material in this thesis. Copy
ing or publication or any other use of this thesis for financial gain without
approval by the University of Saskatchewan and the author's written permis
sion is prohibited.
Requests for perrmssion to copy or to make any other use of the
material in this thesis in whole or in part should be addressed to:
Head of the Department of Electrical EngineeringUniversity of Saskatchewan
Saskatoon, Canada S7N OWO.
11
ACKNOWLEDGEMENTS
The author would like to express his heartfelt gratitude and apprecia
tion to Dr. R. Billinton for his guidance and consistent encouragement
throughout the course of this work. His advice and assistance in the
preparation of this thesis is thankfully acknowledged.
The author takes this opportunity to acknowledge the patience and un
derstanding of his wife Rina, his sons Arif and Ariq.
Financial assistance provided by the Natural Science and Engineering
Research Council of Canada and the Saskatchewan Power Corporation in the
form of a Graduate Scholarship is thankfully acknowledged.
The author thankfully acknowledges the study leave granted by the
Bangladesh University of Engineering and Technology, Dhaka.
III
UNIVERSITY OF SASKATCHEWAN
Electrical Engineering Abstract 88A3Ul
SPINNING RESERVE ASSESSMENTIN INTERCONNECTED
GENERATION SYSTEMS
Student: Nurul Amin Chowdhury Supervisor: Dr. Roy Billinton
Ph. D. Thesis Presented to the
College of Graduate Studies and Research
February 1989
ABSTRACT
Most utilities use deterministic techniques to evaluate unit commitment
and spinning reserve requirements. Deterministic approaches do not specifically take into account the stochastic behaviour of system components in the
determination of spinning reserve requirements. A probabilistic techniquedesignated as the 'Two Risks Concept' which considers the stochastic be
haviour of system components as an integral element has been developed to
assess spinning reserve requirements in interconnected systems. The tech
nique provides a rational basis for spinning reserve allocation amongst each
individual system within an interconnected configuration. The technique and
its fundamental features are illustrated in this thesis. The effect on the re
quired spinning reserve of related system parameters, generating unit failure
probabilities and tie-line capacity are also illustrated. The technique incor
porates the essential factors in interconnected systems which directly or in
directly influence system spinning reserve requirements.
The spinning reserve requirements in an interconnected configuration in
volve the recognition of contracted agreements such as export/import con
ditions between systems. The development of export/import models and a
corresponding spinning reserve assessment process are presented in this thesis.
The availability of rapid start and hot reserve units and interruptible loads
can reduce the unit commitment risk for a given set of generation and load
conditions. Rapid start and hot reserve units have been included in the
lV
time dependent risk calculation using the Area Risk Technique. The effect
of load interruption on required spinning reserve has been studied in detail.
A technique to determine the maximum allowable time delay for load inter
ruption is reported in this thesis. A generating system can carry an ad
ditional load/interruptible load on top of its firm load due to the discrete
size of the generating units without having to commit any additional units
than those required to carry the firm load. A technique to determine the
additional load/interruptible load carrying capability of isolated and intercon
nected systems is presented in this thesis.
A unit commitment technique for continually changing loads in inter
connected systems has been developed based on the 'Two Risks Concept'.The unit commitment during a specified scheduling period is constrained byrisk criteria and economic factors. The unit commitment technique in the
presence of contracted export/import and load forecast uncertainty is
described in this thesis. A risk constrained unit loading technique for inter
connected systems is also been presented in this thesis which utilises a least
costly deviation from economic load dispatch to satisfy the risk criteria.
Two reliability test systems have been utilised to conduct studies based on
the 'Two Risks Concept' and the results are presented in this thesis.
v
Table of Contents
COPYRIGHT. ACKNOWLEDGEMENTS 11
ABSTRACT ill
TABLE OF CONTENTS v
LIST OF FIGURES viiiLIST OF TABLES x
LIST OF PRINCIPAL SYMBOLS XIV
1. INTRODUCTION 1
2. BASIC MODELS AND SYSTEM CONCEPTS 8
2.1. Introduction 8
2.2. Basic Modelling Concepts 11
2.3. Markov Process 12
2.4. Generating Unit Models 13
2.4.1. Two-state model 13
2.4.2. Multi-state model 15
2.5. Matrix Multiplication Method 172.6. Capacity Outage Probability Table 21
2.7. Assessment of Spinning Reserve in a Single System 222.8. Unit Commitment in a Single System 25
2.9. Summary 27
3. SPINNING RESERVE EVALUATION IN INTERCON- 28
NECTED SYSTEMS
3.1. Introduction 28
3.2. Two Risks Concept 29
3.2.1. Equal and Unequal Single System Risk 35
3.3. Effect of Tie-line Capacity 373.4. Effect of a Load Change in One System on The Other System 40
3.5. Effect of Unit Failure Rates on Spinning Reserve 43
3.6. Rapid Start and Hot Reserve Units 46
3.6.1. Rapid start and hot reserve unit models 50
3.6.1.1. Rapid start units 50
3.6.1.2. Hot reserve units 51
3.7. Effect of Load Forecast Error 55
3.8. Summary 63
VI
4. SPINNING RESERVE WITH EXPORT/IMPORT 64
4.1. Introduction 64
4.2. Export/Import Agreements 65
4.3. Firm Purchase Backed Up by the Complete System 65
4.3.1. Tie-line constrained import model 66
4.3.2. Export/import constrained tie-line model 684.3.3. Tie-line failure neglected 70
4.4. Firm Purchase Backed Up by a Specific Unit 704.4.1. Export model 714.4.2. Tie-line constrained import model 724.4.3. Export/import constrained tie-line model 734.4.4. Remainder of the exporting generating unit 734.4.5. Tie-line failures neglected 74
4.5. Interconnected System Risk 75
4.6. Numerical Examples 76
4.6.1. Firm purchase backed up by the entire system 764.6.2. Firm purchase backed up by a specific unit 80
4.7. Effect of Export/Import on the Level of Assistance 86
4.8. Summary 88
5. INTERRUPTIBLE LOAD CONSIDERATIONS 90
5.1. Introduction 90
5.2. Interruptible Loads in a Single System 91
5.3. Additional Load/Interruptible Load Carrying Capability of a 99
System5.4. Additional Load/Interruptible Load Carrying Capability for Dif- 104
ferent System Lead Times5.5. Effect of Firm Load Variation on the Additional 107
Load/Interruptible Load Carrying Capability5.6. Daily Additional Load/Interruptible Load Carrying Capability of 108
a Generation System5.7. Interruptible Loads in an Interconnected System5.8. Interruptible Load Carrying Capability of Interconnected
tems
5.9. Summary6. UNIT COMMITMENT
6.1. Introduction6.2. Loading Order6;3. Start-Up Cost6.4. Dynamic Programming6.5. Scheduling Using the 'Two Risks Concept'6.6. Summary
7. LOCATION OF SPINNING RESERVE7 .1. Introduction7.2. Response Risk7.3. Numerical Example
118
Sys- 123
124
127
127
129130
131
133136
141
141
142144
Vll
7.4. Load Dispatch Using the 'Two Risks Concept'7.4.1. Least costly adjustments
7.5. Summary8. APPLICATION TO RELIABILITY TEST SYSTEMS
8.1. Introduction8.2. Application to the Roy Billinton Test System (RBTS)8.3. Application to the IEEE-RTS8.4. Summary
9. CONCLUSIONS
REFERENCES
147148153
161
161
162172192
193
199
Appendix A. Equivalent Capacity Model 203
A.l. A Recursive Algorithm for Capacity Model Building 203
Appendix B. Determination of Interruptible Load Carrying 205
Capability of an Interconnected Generation SystemB.l. Computational Algorithm 205
Figure 2.1:
Figure 2.2:
Figure 2.3:
Figure 2.4:
Figure 2.5:
Figure 2.6:
Figure 2. '1 :
Figure 2.8:
Figure 3.1:
Figure 3.2:
Figure 3.3:
Figure 3.4:
Figure 3.5:
Figure 3.6:
Figure 3. '1 :
Figure 5.1:
Figure 5.2:
Figure 5.3:
Figure 5.4:
Figure 5.5:
Figure 5.6:
Figure 5. 'T :
Figure 5.8:
viii
List of Figures
Subdivision of System Reliability. 8
Hierarchical Levels in Power System. 10Model for Hierarchical Level I. 10Two-state Model of a Generating Unit. 13
Three-state Model of a Generating Unit. 16
Three-state Model of a Generating Unit With No 17
Repair.Three-state Model of a Generating Unit For Spin- 18
ning Reserve Study.Three-state Model of a Power System Component. 19
Interconnected Systems. 31Area Risk Curve of a System. 46Area Risk Curves of an Interconnected System. 49
Four-state Model for Rapid Start Units. 50Five-state Model For Hot Reserve Units. 52
Seven-step Approximation of the Normal Distribu- 57tion.
Three-step Approximation of the Normal Distribu- 61tion.Area Risk Curve. 94
Equivalent Load Approach For Load Interruption. 95
Equivalent Unit Approach For Load Interruption. 95
Area Risk Curves For Two Loads. 96
Interruptible Load Carrying Capability at the Firm 104Load of 1850 MW .
Additional Load Carrying Capability at a Load 106Level of 1750MW.Additional Load Carrying Capability at a Load 107Level of 1900MWEffect of Firm Load Variation on Additional Load 109
Carrying Capability.Figure 5.9: Effect of Firm Load Variation on Additional Load 110
Carrying Capability.Figure 5.10: Hourly Peak Load Variation of One Week ill the 112
Winter of the IEEE - RTS Load Model.Figure 5.11: Daily Additional Interruptible Load Carrying 115
Capability of System A.
IX
Figure 5.12: Area Risk Curves for Isolated and Interconnected 119
System Operation.Figure 5.13: Additional Interruptible Load Carrying Capability 125
In System B.
Figure 8.1: Additional Load Carrying Capability of RBTS-2. 170
•
Table 2.1:Table 2.2:Table 2.3:Table 2.4:Table 3.1:Table 3.2:
Table 3.3:Table 3.4:Table 3.5:Table 3.6:Table 3.1:Table 3.8:Table 3.9:
Table 3.10:
Table 3.11:Table 3.12:Table 3.13:
Table 3.14:
Table 3.15:
Table 3.16:Table 3.11:
Table 4.1:Table 4.2:Table 4.3:Table 4.4:Table 4.5:Table 4.6:Table 4.1:
Table 4.8:
x
List of Tables
On-line Generating Units of System X. 24
Capacity Outage Probability Table of System X. 24Unit Commitment and Risk in System X. 25Unit Commitment and Spinning Reserve in System X. 26Assistance Equivalent Unit of System X. 28Available Generating Units in System A and System 33B.Tie Lines. 33Unit Commitment in the Interconnected System. 34Unit Commitment With Unequal Single System Risk. 36Unit Commitment With Equal Single System Risk. 38
Effect of Tie-line Capacity. 39Effect of Tie-line Capacity. 40Effect of Load Changes On Unit Commitment (Tie 42
capacity = 2x40 MW).Effect of Load Changes On Unit Commitment (Tie 44
capacity = 2x90 MW).Unit Commitment With Equal Unit Failure Rates. 45
Unit Commitment With Unequal Unit Failure Rates. 45
Transition Rate of Hot Reserve and Rapid Start 53Units.Unit Commitment With Rapid Start and Hot 55
Reserve Units.
Unit Commitment With Load Forecast Uncertainty 58
(Seven-step approximation of the load distribution).Unit Commitment With Zero Load Forecast Uncertaint)60Unit Commitment With Load Forecast Uncertainty 62
(Three-step approximation of the load distribution).Tie-Line Model. 77Tie Constrained Import Model of System A. 77
Export/Import Constrained Tie-Line Model. 78Tie-Line Model. 79Tie Constrained Import Model of System B. 79
Export/Import Constrained Tie-Line Model. 80Unit Commitments (Export is backed up by the en- 81tire exporting system).Export Model of System B. 82
Table 4.9:Table 4.10:
Table 4.11:Table 4.12:Table 4.13:Table 4.14:
Table 4.15:Table 4.16:Table 4.17:Table 4.18:
Table 4.19:
Table 4.20:
Table 5.1:
Table 5.2:Table 5.3:Table 5.4:
Table 5.5:
Table 5.6:Table 5.7:Table 5.8:
Table 6.1:
Table 6.2:Table 6.3:
Table 6.4:
Table 6.5:
Table 7.1:Table 7.2:Table 7.3:Table 7.4:Table 7.5:
Table 7.6:Table 7.7:Table 7.8:Table 7.9:Table 7.10:Table 7.11:Table 7.12:
Xl
Tie Constrained Import Model of System A. 82
Export/Import Constrained Tie-Line Model. 83
Tie Constrained Import Model of System A. 83
Export/Import Constrained Tie-Line. 84
Export Model of System A. 84
Tie Constrained Import Model of System B. 85
Export/Import Constrained Tie-Line Model. 85
Tie Constrained Import Model of System B. 85
Export/Import Constrained Tie-Line Model. 86
Unit Commitments (Export IS backed. up by a 87
specific unit).Unit Commitment With Export (Export backed up 88
by the entire exporting system).Unit Commitment With Export (Export backed up 89
by a specific unit in the exporting system).Spinning Capacity, Reserve and Unit Commitment 92
Risk.Unit Commitment and Corresponding Risk. 92
Typical Unit Commitment Situations. 98
Allowable Additional Load/Interruptible Loads and 102
Lead Times.One Week In The Winter Of The IEEE - RTS Load 114
Model.Additional Unit Requirements. 117
Additional Unit Requirements. 117Unit Commitment with Interruptible Load. 122
Cost Parameters of the Generating Units in System 135
A and B.Peak Load Variations in a 24 Hour Period. 136
Unit Commitment in System A and B. 137
Unit Commitment in System A and B With Load 138
Forecast Uncertainty.Unit Commitment in System A and B With 139
Export/Import.Failure Probability and Response Rate. 144
Load Dispatch in System X. 145
Response Risk. 145
Tie-Line Model. 145
Tie-Line Constrained Response Assistance (Assistance 146
to X provided by Y).Equivalent 5 Minute Response of System X. 146
Response Rate of Generating Units. 150
Load Dispatch During the First Hour. 151
Running Cost During the First Hour. 152
Operating Cost During the 24 Hour Period. 152
Economic Load Dispatch in System A. 154
Economic Load Dispatch in System B. 155
Table 7.13:
Table 7.14:
Table 7.15:
Table 7.16:
Table 8.1:Table 8.2:
Table 8.3:
Table 8.4:
Table 8.5:
Table 8.6:
Table 8.7:
Table 8.8:Table 8.9:
Table 8.10:
Table 8.11:
Table 8.12:
Table 8.13:Table 8.14:Table 8.15:Table 8.16:
Table 8.17:
Table 8.18:
Table 8.19:
Table 8.20:
xu
Risk Constrained Economic Load Dispatch in Sys- 156
tern A (Reloading step = 1 MW).Risk Constrained Economic Load Dispatch in Sys- 157tern B (Reloading step = 1 MW).Risk Constrained Economic Load Dispatch in Sys- 158
tem A (Reloading step = 5 MW).Risk Constrained Economic Load Dispatch in Sys- 159
tem B (Reloading step = 5 MW).RBTS Generating Units and Cost Data. 163
Unit Commitment in the RBTS. 164Unit Commitment in the RBTS With Load Forecast 165
Uncertainty (Seven-step approximation of the load
distribution) .
Unit Commitment in the RBTS With Load Forecast 166
Uncertainty (Three-step approximation of the loaddistribution) .
Unit Commitment in the RBTS With Export/Import 167
(Export is backed up by the entire exporting system).Unit Commitment in the RBTS With Export/Import 167
(Export is backed up by a Specific Unit).Unit Commitment in the RBTS With Interruptible 169
Load.Peak Load Variations of RBTS in a 24 Hour Period. 171
Unit Commitment in the RBTS (24 hours scheduling 172
period).Unit Commitment in the RBTS Without Intercon- 173nection (24 hours scheduling period).Risk Constrained Economic Load Dispatch in the 174
RBTS-l (Reloading step = 5 MW).Risk Constrained Economic Load Dispatch m the 175RBTS-2 (Reloading step = 5 MW).Generating Units in the IEEE-RTS. 176IEEE-RTS Cost Data. 177Unit Commitment in the IEEE-RTS. 179
Unit Commitment in the IEEE-RTS With Load 180
Forecast Uncertainty (Seven-step approximation ofthe load distribution).Unit Commitment in the IEEE-RTS With Load 181
Forecast Uncertainty (Three-step approximation ofthe load distribution).Unit Commitment in the IEEE-RTS With 182
Export/Import (Export IS backed up by the entire
exporting system).Unit Commitment in the IEEE-RTS With 182
Export/Import (Export IS backed up by a specificunit).Unit Commitment in the IEEE-RTS with Interrupt- 183
ible Load.
Table 8.21: Peak Load Variations of IEEE-RTS m a 24 Hour 185
Period.Unit Commitment m the IEEE-RTS (24 hour 186scheduling period) .
Unit Commitment in the IEEE-RTS Without Inter- 187
connection (24 hour scheduling period).Economic Load Dispatch in the IEEE-RTS-l. 188
Economic Load Dispatch in the IEEE-RTS-2. 189Risk Constrained Economic Load Dispatch m the 190
IEEE-RTS-l (Reloading step = 5 MW).Risk Constrained Economic Load Dispatch in the 191
IEEE-RTS-2 (Reloading step = 5 MW).Probability of Failure of Units in System X. 203
Capacity Outage Probability Table of System X. 204
Table 8.22:
Table 8.23:
Table 8.24:Table 8.25:Table 8.26:
Table 8.27:
Table A.1:Table A.2:
Xlll
xiv
LIST OF PRINCIPAL SYMBOLS
Export of System i to System j
F(R) Risk function
[ ..
tJ Import of System i from System j
Failure rate
Total load in System A
Firm load in System A
s:t Interruptible load
Interruptible load in System A
,\ ..
'JTransition rate from state i to state j
Repair rate
R, Specified single system risk
R·t Specified interconnected system risk
Actual single system risk in System A
Actual interconnected system risk in System A
s(t) Unit start-up fuel cost at time t
Unit cold start-up cost
xv
T Lead time
t:.t Discrete time step
SSR Single system risk
ISR Interconnected system risk
SSRR Single system response risk
ISRR Interconnected system response risk
Lead time for the additional thermal units
Time to start hot reserve units
Time to start rapid start units
u·l
Minimum output of unit i in MW
Maximum output of unit i in MW
x·t Output of unit i in MW
1
1. INTRODUCTION
Modern power systems have experienced a tremendous growth In the
last few decades. Almost all aspects of daily life in a modern society dependon the use of electrical energy and the performance of a power utility can be
measured in terms of the quality and reliability of the supply. Electric
power utilities supply power to customers with diverse needs. The require
ments of different customers in regard to the quality and reliability of power
supply vary widely depending on the nature of usage. Careful planning,
operation and pre-assessment of system performance are required in order to
satisfy the wide variety of customers found in a modern power system.
Operation of a power system is a vast and complex task which involves
forecasting daily load demand, utilisation of available resources under certain
constraints, understanding electro-mechanical behaviour of various system
components including generating units and most importantly the economics of
operation. The economic aspects of generation system operation deals with
the commitment and dispatch of a selected set of available generating units
under certain operating constraints in order to minimise the overall production cost. Reliability evaluation of power supply involves the recognition of
both quality and continuity of supply. The need for reliable operation of
power systems has been recognised for many years. Reliability and
economics of power system operation can not be considered as two separate
problems. The unit commitment and load dispatch in a system should be
such that economic considerations as well as predefined risk criteria are
satisfied under normal system conditions.
2
Under normal conditions, the generating capacity in operation in a
power system is greater than the actual load demand. Additional generating
capacity above that necessary to meet the load demand is required to make
the system capable of handling unforeseen load changes and possible outages
of generation or other facilities. This extra generating capacity or spinning
capacity held in reserve must be capable of responding within an allowable
margin time to ensure reliable system operation. Two types of margin time
are important; (1) time to satisfy system frequency and dynamic stabilityand (2) time to satisfy loss of generation or other facilities [1, 2]. These
margin times are normally of the order of one minute and five minutes.
The actual magnitude of these time periods can, however, vary from system
to system. In practice, all power system components have some likelihood of
failure. This likelihood can be reduced significantly by proper design and
good maintenance practices, but it can never be reduced to zero. Any sys
tem, therefore, operates with a likelihood of not fulfilling the operational re
quirements. Deterministic approaches recognise this fact but do not use it to
consistently assess system performance or spinning reserve requirements.
A number of different methods are presently used to establish the spm
ning reserve requirement in a power system. These techniques can be
generally grouped into two broad categories; namely, (1) deterministic ap
proaches and (2) probabilistic approaches. Deterministic assessment of the
spinning reserve requirement can be done using
1. percentage of system load or operating capacity,
2. fixed capacity margin,
3. largest contingency, or
4. any combination of the above methods.
Different utilities have their own rationale for selecting a particularmethod. Deterministic approaches do not specifically take into account the
3
likelihood of component failure, i.e. the probability of failure of generating
units, transmission lines, etc., in the assessment of spinning reserve. A
probabilistic approach can be used to recognise the stochastic nature of sys
tem components and to incorporate them in a consistent evaluation of the
spmnmg reserve requirement. The actual magnitude and even the type of
spmnmg reserve is therefore determined on the basis of system risk. This
risk can be defined as the probability that the system will fail to meet the
load or just be able to meet the load for a specified time period. The time
dependent risk can be expressed mathematically as
m
i=lwhere
R(t) system risk at time t
probability that the system is in state z at time t
QJt) probability that the system in state i at time t will fail to
meet the quality, continuity or other performance criteria
m total number of system states.
The selection of a suitable risk level is somewhat arbitrary as there is
no simple direct relationship between risk and corresponding worth and suf
ficient operating experience is required before arriving at a particular risk
level. The operating risk, however, can be decreased by providing more
spinning reserve, i.e. scheduling more generating units. Decreasing the risk
level will result in increased operational costs. The selection of an allowable
risk level is, therefore, a management decision.
The realisation that interconnection between two or more neighbouring
power systems can be beneficial to the utilities concerned IS well
established [3, 4, 5]. The resulting benefits apply to both system adequacy
4
and system security. The participating members of an interconnected poolcan export/import energy, exchange economic energy or assist each other
with operating reserve. The reliable operation of an interconnected power
system when considered on a 'multi-area' basis requires that each system
should have adequate capacity. to meet its own area demand [6, 7].Moreover, each individual system should have adequate capacity to meet its
export/import commitment and regulating margin. In an interconnected sys
tem considered on a 'single-area' basis, load changes are allocated for
economy dispatch to the next-in-line unit irrespective of its location [6, 7].Economy interchanges between individual members of the pool occur whenever
in achieving system economy, one system modifies its generation for a load
change in another area. Adequate operating reserve must be maintained,
however, for proper coordination and reliable operation of the interconnected
system.
Multi-area unit commitment techniques do not normally involve
probabilistic risk assessment. 'Operating reserve requirements are usuallybased on deterministic approaches in which the reserve is specified as either
a fixed margin or some combination of the capacities of the units in opera
tion and the system load.;
The emphasis when using a deterministic ap
proach to unit commitment and spinning reserve assessment is to minimise
the total operating cost [8, 9, 10, 11, 12, 13, 14, 15, 16] and in doing so a
system faces different degrees of risk throughout the day. The set of
generating units in different systems of an interconnected pool are usuallydifferent. The operating units in different systems usually differ in their size,
unavailability, response rate etc.. Deterministic approaches do not take these
factors into consideration in a consistent manner during the allocation of
spinning reserves between the pool members. There exists therefore, a pos
sibility that a system whose generating units are more likely to fail than the
units of its neighbour is neither maintaining an adequate spinning reserve
nor buying it from others. A system whose units are less likely to fail than
the units of its neighbour, however, may carry more than its share of spin-
5
rung reserve due to the same reason. The fact may not be obvious to the
pool members due to the very nature of the deterministic approach used.
The assessment of spinning reserve IS an integral part of the problem of
unit commitment. Most of the methods previously developed for unit com
mitment ignore the probabilistic aspects of system components. The units in
some of these methods are scheduled in a way that results in minimum run
ning cost [8, 9, 10, 11, 12, 13, 14, 15, 16]. Some published techniques recog
nise the random behaviour of system components but fail to use this infor
mation in a consistent manner [17, 18]. Spinning reserve assessment in an
isolated system using probabilistic methods have been published [3]. Most
power utilities today operate in interconnected configurations. There has
been relatively little published material on spinning reserve requirements in
interconnected systems which recognises the random nature of the system
components. The basic objective in using a probabilistic technique is to
maintain the unit commitment risk equal to or less than a specified value
throughout the day. A new probabilistic technique has been developed to
assess the spinnmg reserve requirements in interconnected systems. This
thesis presents this new approach and describes the related theoretical and
computational basis of the technique. / This research work concentrates on
the spinning reserves required to satisfy the system load requirement and
does not include the system dynamics associated with the initial or instan
taneous response of the system to a._�����Il :per�ll.r?���?'_!l./ The principle
strength of the technique presented in this thesis lies in its ability to include
standard operating practices and those factors which directly or indirectly in
fluence the system reliability in the assessment of spinning reserve. The
power system component models required to support the computational and
analytical work reported in this thesis have been previously published [3] and
are generally accepted by utilities in North America.
The step by step development and basis of the new probabilistic tech
nique to assess spinning reserve in interconnected systems is designated as
6
the 'Two Risks Concept' and is presented in Chapter 3. The basic ideas of
the 'Two Risks Concepts' are developed using two interconnected power sys
tems for the sake of simplicity and clarity. The technique, however, is ap
plicable to higher order interconnected systems. The effects of tie-capacityvariation on spinning reserve and corresponding risk are illustrated in
Chapter 3. Area risk curves have been used to include rapid start and hot
reserve units in the spinning reserve evaluation process in interconnected sys
tems. With interconnections, the spinning reserve requirements of one system
are affected by the load variations and unit commitments of the neighbouringsystems. This interdependence of interconnected systems with respect to
spmnmg reserve is also illustrated in Chapter 3. A technique to consider load
forecast uncertainty m the spmnmg reserve assessment usmg the
'Two Risks Concept' is presented. A simplified load probability model to
represent the load forecast uncertainty is shown in Chapter 3. New risk in
dices are defined as necessary elements of the proposed probabilistic tech
mque.
Most interconnected systems have scheduled export/import from/to their
neighbouring systems. The 'Two Risks Concept' has been used to assess
spinning reserve in interconnected systems with export/import constraints.
The development of the basic export/import models under different agree
ments are illustrated in Chapter 4.
In the absence of alternative capacity adjustments, system load can be
curtailed to reduce the system operating risk. The determination of the
magnitude of the load which should be curtailed and the corresponding max
imum allowable time delay to interrupt it to maintain the risk equal to or
less than a specified value is illustrated in Chapter 5. The basic methods
regarding the allowable load interruption and the interruptible load carrying
capability are first developed for a single system. Interruptible load con
siderations for interconnected systems are derived usmg the
'Two Risks Concept' and the basic techniques applied in a single system.
7
Daily unit commitment schedules based on the basic ideas illustrated in
Chapter 3 are presented in Chapter 6. A process of allocating spinningreserve among the operating units of an interconnected system is presentedin Chapter 7. This approach takes into consideration the responding
capabilities of the operating units and satisfies response risk criteria. The
proposed allocation process evaluates the risk associated with the responding
capability of an interconnected system and determines a loading schedule to
satisfy an acceptable risk with the least costly deviation from the economic
load dispatch. The technique is suitable for both small and large intercon
nected systems.
The techniques developed and presented in this thesis have been ap
plied to two reliability test systems. The results from studies which il
lustrate unit commitment, spinning reserve, load interruption and risk con
strained economic load dispatch etc. for the two reliability test systems are
presented in Chapter 8.
In summary, this thesis presents a new probabilistic technique for spm-.
nmg reserve assessment in interconnected generation systems. The proposed
technique incorporates the essential stochastic parameters of all the par
ticipating generation systems and the associated system interconnecting tie
lines. The introduction of the two risk indices, at the isolated system level
and at the interconnected system level, provides consistent operating criteria
in regard to unit commitment and load dispatch. The developments
presented in this thesis advance spinning reserve assessment methodologiesand provide a viable alternative to the deterministic approaches used for
unit commitment in interconnected generation systems.
8
2. BASIC MODELSAND SYSTEM CONCEPTS
2.1. Introduction
The basic objective of a power system is to generate and supply electri
cal energy to its customers as economically as possible with an acceptable
degree of reliability and quality. In general, the ability of the system to
provide an adequate supply of electrical energy is designated by the term
reliability. The concept of power system reliability covers numerous aspectsof power system performance with respect to satisfying the wide variety of
customer demands.
Due to the wide ranging implications of the term reliability, it is neces
sary to subdivide it into more specific segments. Figure 2.1 shows the basic
subdivision of power system reliability into system adequacy and system
security [19]. These designations represent two different aspects of power
system performance.
SYSTEM RELIABILITY
SYSTEM SECURITY SYSTEM ADEQUACY
Figure 2.1: Subdivision of System Reliability.
9
System adequacy relates to the existence of sufficient generation, trans
mission and distribution facilities within the system to satisfy the load
demand. Adequacy evaluation does not take system disturbances into ac
count. Security evaluation deals with the responding capability of a system
to perturbations arising within the system. The perturbations in the domain
of security analysis include system disturbances such as loss of generation
and transmission facilities. The evaluation of loss of load· expectation
(LOLE) and loss of energy expectation (LOEE) reside in the area of system
adequacy. Assessment of spinning reserve and transient stability are as
sociated with system security. The work reported in this thesis is in the
system security domain.
A power system can be divided into three functional zones; generation,
transmission and distribution [19]. System planning, operation and reliability
studies can be performed on these three functional zones individually. One
or more of these functional zones can be combined to form hierarchical levels
as shown in Figure 2.2. Hierarchical level I (HL I) represents the generation
facilities. Generation and transmission facilities together form the hierarchical
level II (HL II). The combination of all three functional zones form hierar
chical level III (HL III). The quantification of spinning reserve in HL I re
lates to the responding capability of the total spinning capacity (generation
synchronised to the bus) in the event of a perturbation and/or generation
loss. The transmission and the distribution facilities during the assessment
of spinning reserve at HL I are assumed to be fully reliable. The research,
work reported in this thesis is restricted to the assessment of spmnmg
reserve of interconnected systems at HL I. At HL I, all the generation and
load in the system can be grouped to create a hypothetical system with one
generating source supplying a single load. Figure 2.3 shows such a system
representation for spinning reserve assessment at HL I. The HL I represen
tation of an interconnected system contains an equivalent tie-line in addition
to the single generating unit feeding a solitary load.
10
r---------------,I r------------, II r-----------, I I
I I I I
I I I I
I I !IIi I HIERARCHICAL LEVEL I
I I I
I I II
L _JII II .., HIERARCHICAL LEVEL III JI II II I
L _ _ _..J I. HIERARCHICAL LEVEL III
JIIfIII
L---- .J
GENERATIONFACILITIES
----- -----
TRANSMISSIONFACILITIES
- - -- 1---- -
DISTRIBUTIONFACILITIES
Figure 2.2: Hierarchical Levels in Power System.
TOTAL SYSTEMGENERATION
TOTAL SYSTEMLOAD
Figure 2.3: Model for Hierarchical Level I.
11
2.2. Basic Modelling Concepts
Proper representation of power system components IS an important re
quirement of all power system reliability studies. A power system com
ponent can be represented in a reliability study by a model which can be
quite simple or exhaustive, or something in between. How elaborate a model
should be depends on the component itself and the type of the study in
which the model is used. In some reliability studies, the simplest model of a
particular component is quite adequate, whereas for other studies a more
elaborate model is required. A detailed component model will portray the
component behaviour more closely than a simple model of the same com
ponent. Exhaustive modelling of system components are required for greater
accuracy, but can increase the reliability computation time considerably
above that required with relatively simpler models. Simple models of system
components do not always retain the essential performance characteristics
needed in some reliability studies. A system component should be represented
by a model which is reasonably simple yet retains all the required perfor
mance features. The essential performance features that a model must
provide will vary from study to study.
Modelling of system components directly depends on the ability and
scope of the data collection system. New techniques in reliability sometimes
demand new system component models. The requirements of these new
models can place changing and sometimes increasing burdens on traditional
power utility data collection schemes. •
This chapter reviews some of the generating unit models and related
spinning reserve concepts which form the basic elements of the research work
described in this thesis on spinning reserve assessment in interconnected sys
tems.
12
2.3. Markov Process
Many power system component models used in reliability studies are
based on Markov processes. A Markov process can be defined as a stochas
tic process whose future IS independent of the past for a known
present [20, 21, 22]. The fundamental characteristic of a Markov process IS,
therefore, that the process is memoryless. The future random behaviour of
the process only depends on where it is at present. The process neither
depends on the states occupied in the past nor does it depend on how it ar
rived at its present position. A Markov process is also homogeneous. This
means that the behaviour of a system is the same at all points of time ir
respective of the point of time considered [23]. A Markov process as utilised
in reliability studies has two random variables, state and time. The state
and time may either be discrete or continuous. In the work described in
this thesis the system components are modelled by discrete states in a con
tinuous time domain.
In this thesis, a Markov process with discrete states in the continuous
time domain is called a 'continuous Markov process' and a Markov process
with discrete states in discrete time steps is called a 'discrete Markov
process'. A component modelled as a continuous Markov process will have
constant transition rates from one state to another. All power system com
ponents included in this thesis are assumed to have constant transition rates
i.e., constant failure and repair rates etc. and therefore exponentially dis
tributed residence times in the different states.
13
2.4. Generating Unit Models
2.4.1. Two-state model
Generating units should be represented by appropriate models for
probabilistic assessment of static or operating capacity requirements. A two
state representation of a generating unit is the simplest form. The generat
ing unit is considered to be either operating at full capacity or failed.
Figure 2.4 shows a two state model for a typical generating unit.
UP DOWN
p.
Figure 2.4: Two-state Model of a Generating Unit.
The unit changes its states from the operating state (up) to the failed
(down) state with a constant transition rate of A, commonly known as the
failure rate. The unit is repaired and put back into the operating state at a
rate /1, known as the repair rate. It is assumed that the residence times of
the generating unit in either of these states are exponentially distributed.
Both transition rates shown in Figure 2.4 are, therefore, time independent.The failure and repair rate of a generating unit can be determined from its
operating history.
number of failures in the given period of time
total period of time the unit was operating
/1number of repairs in the given period of time
total period of time the unit was being repaired
Sufficient operating history IS required to develop a reasonably accurate
14
model of a generating unit. The time dependent state probabilities of a
generating unit represented by the two-state model [3] are shown in Equations (2.1) and (2.2) assuming that the unit is in operating state at t = O .
.Ae-(.A+Jl)t.A+Jl
.Ae-(.A+Jl)t.A+Jl
(2.1)
(2.2)
where
probability that the generating unit is in operating state at
time t
probability that the unit IS In failed state at time t.
Steady state probabilities are used for static capacity evaluation. The
steady state probability is the limiting state probability when t -+ 00. The
limiting state probabilities Po and PI are as follows
Po Po(t=oo)Jl
--
.A+Jl
P1(t=00).A
PI .A+Jl
The fundamental difference between static and operating capacityevaluation is in the time period considered. Static capacity evaluation is
done for long term system requirements, whereas, operating capacity evalua
tion is done for short term capacity assessment to meet a load demand.
The time period used in an operating capacity evaluation IS generally rela
tively small and therefore it is possible to neglect generating unit repairs.
Using Equation (2.2) the probability of finding a two-state unit in the failed
state at a time T is grven In Equation (2.3).
P( down) (2.3)
15
If the repair process IS neglected during the time period T, then Equation
(2.3) becomes [3]
P( down) = 1 � e-AT . (2.4)
The time period T is designated in a spmnmg reserve study as the lead
time [3, 24]. This is the time period for which no additional units can be
brought into service. For short lead times of up to several hours, AT« 1
for all practical purposes. The probability that a unit fails and is not
repaired during the lead time T, therefore, IS
P( down ) � AT. (2.5)
The parameter AT is known as the outage replacement rate (ORR) which is
a time-dependent quantity.
2.4.2. Multi-state model
The operating performance of a generating unit is lumped into two
states in a two-state model. Large generating units usually have many
auxiliary equipments. These units, therefore, frequently experience deratingdue to equipment failures. A multi-state model can be used to realistically
represent such a generating unit. A generating unit model with many
derated states, however,· will increase the computational burden and com
plexity in power system .reliability studies. It is not feasible to consider a
large number of derated states. These derated states can be reduced to a
limited number by using some appropriate weighting techniques [25].
A large generating unit can be represented by a three-state model con
taining a full capacity output state, a derated capacity state and a failed
state. The derated capacity output states of a generating unit are pooledinto a single derated state in a three-state model of a generating unit.
Figure 2.5 shows such a three-state model [3]. The three-state model shown
in Figure 2.5 includes all possible transition rates. Some of these transition
rates may not exist in practice, in which case these transitions are simply
16
OPERATING
DOWNDERATED
Figure 2.5: Three-state Model of a Generating Unit.
omitted from the model. The transition rate J.t3 shown in Figure 2.5 may
not exist in practice. The repair process will probably put the unit into the
full output state after it is repaired. The time dependent state probabilitiescan be found by the matrix multiplication method [3] instead of solving the
actual differential equations. The steady state probabilities of the three-state
model can be evaluated by the frequency balance approach or by the matrix
multiplication method.
If the repair process 1S neglected in the short lead time then the three
state model in Figure 2.5 1S reduced to that shown in Figure 2.6 [3]. If the
probability of more than one transition is negligible during the short lead
time then the full three-state model of a generating unit can further be
reduced to that shown in Figure 2.7 [3]. If the unit is considered to be in
the full output state at t=O and the state residence times are assumed to be
exponentially distributed and assuming that AIT« 1 and A2T« 1, where
T is the lead time in hours, it follows from Equation (2.5) that
17
OPERATING
DERATED DOWN
Figure 2.6: Three-state Model of a Generating Unit With No
Repair.
(2.6)
P{ derated) � AIT (2.7)
P{ operating) � 1 (2.8)
The basic models and the state probabilities for other power system com
ponents can be evaluated using similar techniques.
2.5. Matrix Multiplication Method
The evaluation of time dependent or transient probabilities becomes
tedious when the number of states in which the component can reside are
more than two. The matrix multiplication method is specially useful in
determining the transient probabilities using a digital computer. The for
mulation of the problem of determining the transient probability of a certain
18
OPERATING
DERATED DOWN
Figure 2.7: Three-state Model of a Generating Unit For Spinning Reserve Study.
state of a component using the matrix multiplication method is systematicand straightforward [23]. The matrix multiplication method is equallysuitable for discrete and continuous Markov processes.
In order to apply the matrix multiplication method, it is necessary to
obtain the stochastic transitional probability matrix of the process which
fully represents the operating behaviour of the component concerned. The
elements of the stochastic transitional probability matrix are the probabilitiesof making a transition from one state to another in a single step or in a
single time interval. Figure 2.8 shows a general three-state model for the
component whose operating. behaviour can be described in the continuous
time domain with the transition rates shown. The stochastic transitional
probability matrix for the model of Figure 2.8 is
[PH P12 P13]P= P21 P22 P23P31 P32 P33
19
Figure 2.8: Three-state Model of a Power System Component.
1 2 3
1 [ 1-(A12+Au)A! ).12At AnA! 12 ).21At 1-().21+).23)At ).23At3 ).31At ).32At 1-().31+).32)At
In a discrete Markov process,
Pij = probability of making a transition to the jth state after a
single step, given that it was in state i at the beginning ofthe step.
In a continuous Markov process,
p .. =
ZJ probability of making a transition to the jth state after a
time interval of At, given that it was in state i at the
beginning of the time interval.
20
In a discrete Markov process the p·.'s are given explicitly. In the case'J
of a continuous Markov process the transitional probabilities are expressed in
terms of transition rates and the time interval. The time interval ll.t is suf
ficiently small that the probability of more than one transition in the inter
val is negligible.
The time-dependent state probabilities for a continuous Markov process
are [3J
[P(t)J [P(O)] [PJn , (2.9)
where
[P(t)Ji vector of state probabilities at time t
[P(o)Ji vector of initial probabilities
[Pj stochastic transitional probability matrix
n number of time steps used In the discretisation process.
The value of ll.t determines the number of time steps, n. A small
value of ll.t will require large value of n; and a large value of ll.t will result
in a small value of n. The term ll.t should be made sufficiently small that
the errors introduced in the values of the state probabilities become negli
gible .
•
The transient probabilities for a discrete Markov process are given
by [3]
[P(n)1 [P(O)] [p]n , (2.10)
where
[P(n)] vector of state probabilities after n time intervals.
21
2.6. Capacity Outage Probability Table
The system generation in both adequacy and security analysis at HL I
IS represented by a single equivalent generating source. The equivalent
generating source may have many different capacity output states dependingon the capacity outage states and the corresponding probabilities of the in
dividual generating units. A capacity outage probability table [3] is a sys
tematic representation of this equivalent source. In adequacy assessment,
limiting state probabilities of corresponding capacity outage states of m
dividual units are used to derive the capacity outage probability table. In
spinning reserve assessment, time dependent probabilities of the corresponding
outage states of individual generating units are used to derive the equivalentmodel. The generating units are combined using basic probability concepts.
The capacity model in the form of a capacity outage probability table can be
created using Equation (2.11).
n
(2.11)i=l
where
c·l capacity outage of state i for the unit being added
probability that the ith state of the unit exists
n number of capacity outage states of the generating unit
cumulative probability of the capacity outage state ofX MW before the unit is added
P(X) cumulative probability of the capacity outage state ofX MW after the unit is added.
The capacity outage probability table incorporates all possible genera
tion states. The table can be truncated by neglecting all capacity states in
the table whose cumulative probabilities are less than a specified value. A
22
capacity outage probability table has discrete capacity outage states with cor
responding discrete probabilities.
2.7. Assessment of Spinning Reserve in a Single System
Probabilistic techniques have been applied to evaluate the unit commit
ment and spinning reserve requirements in a power system [3}. The main
purpose of a probabilistic technique is to keep the unit commitment risk
equal to or less than a specified value throughout the day. A probabilistic
approach recognises the random behaviour of system components and incor
porates them in a consistent evaluation of the spinning reserve requirements.The unit commitment risk can be decreased by providing more spmnmg
reserve, i.e. committing more generation capacity for the same load demand.
The selection of an allowable risk level depends on the desired degree of
reliability, the corresponding cost and the optimum benefit. The unit com
mitment risk can be expressed as
N
U(t)=L Pi(t)Qi(t) , (2.12)i=l
where
U(t) system risk at time t
probability that the system is in state i at time t
probability that the system load will be equal to or greaterthan the generation in state i at time t
N total number of system states.
In the case of an operating or spinning reserve study Q i becomes either
zero or unity.
o
1
when
when
L<C·,
L>C·- l
23
where
L system load
c·,
total spinning capacity of the system at the ith state.
The capacity outage probability table of the generation system can be
arranged such that
i=1,2,3, . N-1 ,
where N is the total number of states III the generation system. Equation
(2.12) can be modified as
U(t) (2.13)t=n
where n is an integer such that (L-Cn) � ° and (L-Cn_1) < 0, i.e.
Cn-l > L � Cn. Therefore, U( t) is the cumulative probability of the genera
tion state n at time t. If Rs is the allowable unit commitment risk for a
time period of (O,t) then the unit commitment in a system should be such
that
U(t) < Rs . (2.14)
The unit commitment and the associated unit commitment risk are
based on the
certain period of time designated as the The risk
is considered to be the probability of just carrying or failing to carry the
system load [24]. The unit commitment basically depends on system load,
generating unit failure rates, system lead time and the acceptable unit com
mitment risk level. One of the most important parameters in unit commit
ment and spinning reserve evaluation is the system lead time. The basic
spinning reserve evaluation technique in a single system can be illustrated by
considering a simple example. Consider a hypothetical generation system
(System X) with the on-line units as shown in Table 2.1. The unit commit
ment order is from the top down.
24
Table 2.1: On-line Generating Units of System X.
Unit Failure Rate
3 x 40 MW3 x 20 MW4 x 10 MW
4 flyr3 flyr3 flyr
The failures and repairs of the generating units are considered to be ex
ponentially distributed. The probability of finding a two-state unit on out
age at a time equal to the system lead time can be evaluated using the
techniques explained in Section 2.4.1. A generation model in the form of a
capacity outage probability table can be constructed once the capacity state
probabilities of the individual units for a period equal to the system lead
time are known. The unit commitment risk can be found from the capacity
outage probability table given the load is known. The capacity outage prob
ability table of System X for a lead time of two hours is shown in Table 2.2
Table 2.2: Capacity Outage Probability Table of System X.
Capacity In Capacity Out Cumulative
(MW) (MW) Probability
220 0 1.00000000210 10 0.00750879200 20 0.00478778190 30 0.00274422180 40 0.00273863170 50 0.00001559160 60 0.00000812150 70 0.00000252140 80 0.00000250
If the acceptable unit commitment risk is 0.003 it can be seen from
Table 2.2 that the system can carry a load of 190 MW with a spmmng
reserve of 30 MW. In the same generating situation, the load carrying
25
capability of System X decreases to 170 MW with a spmnmg reserve of
50 MW if the acceptable unit commitment risk is selected as 0.001. In both
cases, the total spinning capacity is 220 MW. Due to the discrete nature of
the capacity outage probability table, there IS no change in risk for load
levels between two available capacity steps.
2.8. Unit Commitment in a Single System
A probabilistic approach to unit commitment in a single system re
quires that the unit commitment risk should be less than or equal to a
specified risk level for all forecast load levels. In practice, an operator would
use the probabilistic risk assessment method by adding (committing) one unit
at a time from the merit order table until the unit commitment risk given
by the generation model becomes equal to or less than the acceptable level
for the expected load. One of the most important parameters in the assess
ment of unit commi�r.r!�!lj_ risJLis_.ihe.j;im� .. ��1C3:Y.. 2!: l�a<l ,t_jill�_,,�ft�r. ,,!�!,<:�._t_��."-------�.-.-"'---�'�'-.-.. -"-'-
additional thermal generation will be aVi!-il�!>J�,
It is assumed that the additional thermal generation in System X has a
time delay of 2 hours and the specified risk level is 0.001. The unit com
mitment and corresponding risk for a load of 140 MW in System X is shown
in Table 2.3.
Table 2.3: Unit Commitment and Risk m System X.
No. of Units Total Spinning Spinning Unit CommitmentCommitted Capacity (MW) Reserve (MW) Risk
4 140 0 1.000000005 160 20 0.004102866 180 40 0.002738627 190 50 0.00000999
System X has no spinning reserve for a load of 140 MW with 4 committed
units as shown in Table 2.3. System X, therefore, is unable to meet any
generation loss or unforeseen load increase by committing only 4 units when
26
the load is 140 MW. The unit commitment risk of System X in this situa
tion is unity. As more than 4 units are committed for the same load of
140 MW, the spmnmg reserve increases and the corresponding unit commit
ment risk decreases. System X must commit 7 units to carry a load of
140 MW if the specified unit commitment risk is 0.001. If the load m
System X increases to 170 MW, System X must keep more spinnmg reserve
than that required at the 140 MW load level for the same specified unit
commitment risk. Table 2.4 shows the unit commitment and corresponding
spinning reserve in System X for a load level of 170·MW and a specifiedunit commitment risk of 0.001.
Table 2.4: Unit Commitment and Spinning Reserve m SystemX.
No. of Units Total Spinning Spinning Unit CommitmentCommitted Capacity (MW) Reserve (MW) Risk
7 190 0 1.000000008 200 20 0.002741429 210 40 0.00273863
10 220 50 0.00001559
There is no straightforward relationship between required spmnmg
reserve, specified unit commitment risk and load. The required spmnmg
reserve is a complex function of unit size, unit failure rate, lead time and
specified risk level. The spinning reserve requirement of a system, however,can be reduced by decreasing the lead time of additional generation providedother variables remain the same. This can be achieved by bringing more
rapid start units into the system. The lead time associated with a hot
reserve thermal unit is considerably less than the lead time of the same unit
in a cold reserve status. Due to unit cycling within a 24 hour scheduling
period, some of the thermal units may be in a hot reserve status at some
parts of the day. The commitment of hot reserve and rapid start units can
alleviate the spinning reserve requirement. The inclusion of hot reserve and
rapid start units in the assessment of unit commitment and spinning reserve
can be done using the area risk technique [3].
27
2.9. Summary
This chapter discusses the various functional zones of a power system
and illustrates the concept of adequacy and security. Some basic modelling
aspects including generation models in the form of capacity outage probabil
ity tables are also briefly discussed. The essential steps in the matrix mul
tiplication technique to determine state probabilities are also presented.Determination of time dependent probabilities using the matrix multiplicationmethod is a very practical technique in reliability studies. Assessment of
spinning reserve and unit commitment risk in a single system is explained in
this chapter with a simple numerical example.
28
3. SPINNING RESERVE EVALUATIONIN INTERCONNECTED SYSTEMS
3.1. Introduction
System interconnections permit the participating companies to export or
import energy for mutual benefit. In addition, the participating systems can
benefit in terms of reduced overall required spinning reserves. This can be
illustrated by an example using System X given in Section 2.7. The total
on-line spinning capacity in System X is 220 MW as shown in Table 2.2. If
the load in System X is 170 MW, System X can potentially help an inter
connected system (System Y) to reduce its spinning reserve. System Y in
its turn can also help to reduce System X's reserve requirements. The assis
tance available from System X with a load of 170 MW up to the point of
load loss in X can be modelled using the capacity outage probability table
shown in Table 2.2. The resulting equivalent assistance model is shown in
Table 3.1.
Table 3.1: Assistance Equivalent Unit of System X.
Capacity In Capacity Out Cumulative
(MW) (MW) Probability
50 0 1.0000000040 10 0.0075087930 20 0.0047877820 30 0.0027442210 40 0.002738630 50 0.00001559
If an interconnection exists between System X and System Y, the
29
equivalent assistance unit of System X can be considered as an additional
generating unit available to System Y at no extra cost as far as the spinning
reserve is concerned. If the load in System Y remains constant prior to and
after considering the assistance from System X, then the corresponding
operating risk of System Y will decrease after interconnection in comparison
to the isolated system level. The recognition of these two different risks
leads to the idea that there should be two different risk criteria; one at the
isolated system level and another at the interconnection level.
3.2. Two Risks Concept
The magnitude of the operating reserve requirement is dependent on
the selection of the basic unit commitment risk provided that the other sys-
tem variables remain fixed. For a specified unit commitment risk, the
operating reserve depends on the generating unit failure rates, load level etc ..
In a multi-area interconnected system, each individual system has to carry
its own load and should be capable of assisting its neighbour such that the
operating risks of the individual systems meet a specified risk index. The
problem is basically one of determining the set of generating units to be
committed in each individual system to meet the specified risk at the inter
connection level. One possible way to solve this problem is to commit one
generating unit at a time in one system while keeping the generation fixed in
the other systems and then to determine the interconnected system risk.
The system showing the highest interconnected system risk would then be
considered for a further unit commitment. The process would continue until
all systems meet the interconnected system risk. This method, however, does
not provide any insight into the benefits of interconnection and can require a
long computational time [26]. Since the interconnected system risk of a sys
tem depends on the assistance provided by its neighbours and on its own
commitment; a system may be able to meet the interconnected system risk
without altering its own commitment even when its load increases from one
level to another. In this method, therefore, the assistance provided by an
individual system to its neighbours is not based on any set procedure and
30
hence could lead to an unfair sharing practice with respect to spmmng
reserves.
The problem can, however, be approached by adopting a 'Two Risks
Concept' in which two risk indices are chosen; namely a Single System Risk
and an Interconnected System Risk [26]. An individual system is required to
meet its Single System Risk (SSR) without considering any assistance from
its neighbour. In addition, the individual system is also required to meet its
Interconnected System Risk (ISR) when assistance from its neighbours are
considered. In this technique, the generating units are selected in each in
dividual system such that it meets the SSR criterion and then the assistance
to each other IS considered to determine the ISR. The system more
removed from meeting its ISR is required to commit an additional unit and
the analysis continues until all the systems meet the ISR. If all participat
mg systems are equally removed from meeting the ISR, they are all asked to
commit an additional generating unit individually. Each individual system
and the pool could, however, make its own priority list for unit commitment
based on some economic and/or operational considerations. The use of a
SSR criterion prior to considering the ISR provides a consistent starting
point for interconnected system evaluation. The computational time requiredto arrive at an interconnected unit commitment schedule is approximately30% lower using the two risk approach rather than a single ISR
criterion [26].
Assume that two hypothetical power systems with no export/importagreement are interconnected radially as shown in Figure 3.1.
A is the capacity model of System A in the form of a
capacity outage probability table, which satisfies the SSR
(Rsa) of System A for the load of La'
p number of generating units which should be committed m
System A to meet its SSR
31
e'1') .. -'::
I I Tab I IA B
Figure 3.1: Interconnected Systems.
B is the capacity model of System B in the form of a
capacity outage probability table, which satisfies the SSR
(Rsb) of System B for the load of Lb'
Q number of generating units which should be committed In
System B to meet its SSR
A-La
where Ab IS the tie line constrained assistance unit from
System A available to System B.
where Ba
is the tie line constrained assistance unit from
System B available to System A.
where Ae is the equivalent capacity model - of System A
after considering the assistance.
where Be is the equivalent capacity model of System B
after considering the assistance.
The ISR in each system are
Ria risk (Ae La)Rib risk (Be Lb)
32
If both Ria and Rib' are less than or equal to the specified Intercon
nected System Risk, Ri then the number of generating units committed in
System A and System B are considered to be adequate; i.e., Ria-Ri � 0 and
Rib-Ri � o. Otherwise, if (Ria-Ri) > (Rib-Ri) then A is modified by adding
the (P+ 1) th generating unit.
A -+ A + (P+l)th unitP P+l
On the contrary, if (Ria-Ri) < (Rib-Ri) then B IS modified by adding the
(Q+l)th unit.
B -+ B + (Q+l)th unit
Q -+ Q+l
The computational process is continued to modify the capacity model of
System A or System B or both until the ISR criterion is satisfied. A com
puter program has been developed based on the 'Two Risks Concept' to
determine an individual system's share of the overall required spinning
reserve when the systems operate as a multi-area interconnected system.
Two radially interconnected hypothetical systems are used to provide numeri
cal examples. The generating units in each system and the tie lines are
described in Tables 3.2 and 3.3 using the models given in Figures 2.7 and
2.4. The available generating units in both systems are considered to be
identical so that both systems can be compared to each other with respect
to their spinning reserve requirements and the essential features of the 'Two
Risks Concept' can be established. The priority order of unit commitment is
from the top down in Table 3.2 and the lead time in both systems is con
sidered to be 4 hours. Load forecasting error at this point, is assumed to be
zero in both systems. The load in both systems is assumed to be constant
over the study period. Time varying loads can be considered by dividing
the study period into a number of subintervals during which the load is con
sidered to be constant.
33
Table 3.2: Available Generating Units m System A and SystemB.
No. of Output Capacity Transition Rate UnitUnits (MW) (Occ./hr) Type
Full Derated ).1 ).2
1 200 0.0003 hydro2 180 0.0003 hydro1 200 160 0.0005 0.0003 thermal3 150 120 0.0005 0.001 thermal3 150 120 0.0002 0.0009 thermal2 100 0.0005 thermal1 120 100 0.0001 0.0007 thermal3 100 0.0006 thermal
Table 3.3: Tie Lines.
Number ofTie Lines
Maxm. Power Transfer
Capability of Each Line
(MW)
Failure Rate
(Occ/hour)
2 100 0.000114155
Table 3.4 shows the number of generating units which must be com
mitted in System A and System B for a specified ISR of 0.0001. The SSR
is varied from 0.05 to 0.001 in discrete steps. The last two columns
(column 13 and 14) of Table 3.4 show the actual ISR of System A and
System B. The actual magnitude of the spinning reserve can be found by
subtracting load from total spmnmg capacity. Similar results can be ob
tained for other load levels.
Table 3.4: Unit Commitment in the Interconnected System.
Single System Interconnected System
SSR Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW)
A B A B A B A B A B A B A B
0.050 0.050 1800 1650 12 10 1860 1660 13 12 1980 1860 0.00007370 0.00002883
0.050 0.020 1800 1650 12 12 1860 1860 13 12 1980 1860 0.00007370 0.00002883
0.050 0.010 1800 1650 12 12 1860 1860 13 12 1980 1860 0.00007370 0.00002883
0.050 0.005 1800 1650 12 12 1860 1860 13 12 1980 1860 0.00007370 0.00002883
0.050 0.001 1800 1650 12 12 1860 1860 13 12 1980 1860 0.00007370 0.00002883
0.020 0.020 1800 1650 13 12 1980 1860 13 12 1980 1860 0.00007370 0.00002883
0.020 0.010 1800 1650 13 12 1980 1860 13 12 1980 1860 0.00007370 0.00002883
0.020 0.005 1800 1650 13 12 1980 1860 13 12 1980 1860 0.00007370 0.00002883
0.020 0.001 1800 1650 13 12 1980 1860 13 12 1980 1860 0.00007370 0.00002883
0.010 0.010 1800 1650 13 12 1980 1860 13 12 1980 1860 0.00007370 0.00002883
0.010 0.005 1800 1650 13 12 1980 1860 13 12 1980 1860 0.00007370 0.00002883
0.010 0.001 1800 1650 13 12 1980 1860 13 12 1980 1860 0.00007370 0.00002883
0.005 0.005 1800 1650 14 12 2080 1860 14 12 2080 1860 0.00000846 0.00001024
0.005 0.001 1800 1650 14 12 2080 1860 14 12 2080 1860 0.00000846 0.00001024
0.001 0.001 1800 1650 14 12 2080 1860 14 12 2080 1860 0.00000846 0.00001024
c;..:I>f.>.
35
3.2.1. Equal and Unequal Single System Risk
For each Interconnected System Risk there could be three significantlydifferent situations in terms of Single System Risk. The SSR are such that
the systems after interconnection, with the generating units committed by
each individual system to satisfy their respective SSR, (a) just satisfy the
ISR; or, (b) show the ISR lower than the specified ISR; or, (c) show the
ISR higher than the specified ISR. In situations (a) and (b) the number of
generating units to be committed is dictated by the SSR. The system witha lower SSR than that of its neighbour , therefore, will provide more assis
tance to its neighbour. This means that for two identical systems with iden
tical sets of. generating units, the system with a smaller SSR has to spin
more generating capacity than the system with higher SSR for identical load
in the two systems. Despite being identical in regard to generating units
and load, one system has to keep more spinning reserve than its neighbourbecause of its decision to select a lower SSR than its neighbour.
Table 3.5 shows the effect of unequal SSR levels. Results for equal
load of 1460 MW in System A and System B with unequal SSR are
presented. The specified ISR is 0.0001. Rows 4, 5, 8, 9, 11 and 12 of
Table 3.5 show that System B needs to commit more generating units than
System A because of the lower SSR of System B than System A for equal
load in both systems. Rows 1, 6, 10, 13 and 15 show that both systems
need an equal number [i.e., identical in this case) of on-line generating units
i.e., equal spinning reserve for equal load when the SSR of both the systems
are equal. There are other situations in Table 3.5 where equal spinning
reserve is required for unequal SSR. Due to discrete capacity outage and
probability entries in the capacity model of a system in the form of a
capacity outage probability table, the unit commitment of a system to satisfy
its single system risk criterion can remain unaltered for a limited range
(dead zone) of SSR variation. For the same reason, the unit commitment of
two identical systems with identical load can be identical at the single sys
tem level though their SSRs are different. In addition to that, if the SSR
Table 3.5: Unit Commitment With Unequal Single System Risk.
Single System Interconnected System
SSR Load No. of Capacity No. of Capacity IISR(MW) Units (MW) Units (MW)
A B A B A B A B A B A B A B
0.050 0.050 1460 1460 9 9 1510 1510 10 10 1660 1660 0.00004829 0.00004829
0.050 0.020 1460 1460 9 10 1510 1660 10 10 1660 1660 0.00004829 0.00004829
0.050 0.010 1460 1460 9 10 1510 1660 10 10 1660 1660 0.00004829 0.00004829
0.050 0.005 1460 1460 9 11 1510 1760 10 11 1660 1760 0.00001588 0.00000732
0.050 0.001 1460 1460 9 11 1510 1760 10 11 1660 1760 0.00001588 0.00000732
0.020 0.020 1460 1460 10 10 1660 1660 10 10 1660 1660 0.00004829 0.00004829
0.020 0.010 1460 1460 10 10 1660 1660 10 10 1660 1660 0.00004829 0.00004829
0.020 0.005 1460 1460 10 11 1660 1760 10 11 1660 1760 0.00001588 0.00000732
0.020 0.001 1460 1460 10 11 1660 1760 10 11 1660 1760 0.00001588 0.00000732
0.010 0.010 1460 1460 10 10 1660 1660 10 10 1660 1660 0.00004829 0.00004829
0.010 0.005 1460 1460 10 11 1660 1760 10 11 1660 1760 0.00001588 0.00000732
0.010 0.001 1460 1460 10 11 1660 1760 10 11 1660 1760 0.00001588 0.00000732
0.005 0.005 1460 1460 11 11 1760 1760 11 11 1760 1760 0.00000184 0.00000184
0.005 0.001 1460 1460 11 11 1760 1760 11 11 1760 1760 0.00000184 0.00000184
0.001 0.001 1460 1460 11 11 1760 1760 11 11 1760 1760 0.00000184 0.00000184
w0)
37
satisfies one of the two situations of (a) and (b) the unit commitment at the
interconnection level is dictated by the unit commitment at the single system
level. Moreover, if the ISR is dominant, equal spinning reserve is requiredfor equal load in two identical systems while operating at unequal SSR.
In situation (c), generating unit commitment in each individual system
is dictated by the specified ISR index. Considering all the aspects, it is
therefore, appropriate to have a single SSR for the pool members. Three
different SSR values which correspond to the situations noted as (a), (b) and
(c) are difficult to determine. They are complex functions of unit size, unit
failure rate, system load, tie capacity, ISR, etc.. Trial indices can, however
be selected for computational purposes until a desired index is found. Table
3.6 shows the units which must be committed in System A and System B
for a specified ISR of 0.0001. The SSR for both systems IS 0.01. Load in
System B is varied from 1300 MW to 2000 MW in steps of 50 MW while
the load in System A is held at 1800 MW.
3.3. Effect of Tie-line Capacity
The assistance provided by a system to its neighbour depends on the
tie-line capacity and the tie-line failure rate. If the tie-capacity is smaller
than the available assistance then the level of assistance becomes constrained
by the tie-capacity. If the tie-capacity is larger than the available assistance,
then the interconnected system can utilise all the assistance provided by its
neighbour to reduce its ISR. In both cases, however, the original assistance
model will be modified by the tie-line failure probability. Two intercon
nected systems can behave like a single system with respect to unit commit
ment and spinning reserve if the tie lines are flexible and capable of transfer
mg any amount of power as required by the systems. The actual tie
capacity in practice, is determined by economic and other operational con
siderations.
Tables 3.7 and 3.8 show the effect of tie-line capacity on the unit COID-
Table 3.6: Unit Commitment With Equal Single System Risk .
•
Single System Interconnected System
SSR Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW)
A B A B A B A B A B A B A B
O.OlD O.OlD 1800 1300 13 9 1980 1510 13 9 1980 15lD 0.00006854 0.00001896
0.010 O.OlD 1800 1350 13 9 1980 15lD 14 9 2080 1510 0.00001668 0.00003599
O.OlD 0.010 1800 1400 13 io 1980 1660 13 io 1980 1660 0.00004069 0.00001618
O.OlD 0.010 1800 1450 13 10 1980 1660 13 10 1980 1660 0.00007126 0.00002358
O.OlD 0.010 1800 1500 13 10 1980 1660 14 io 2080 1660 0.00001827 0.00004044
O.OlD 0.010 1800 1550 13 11 1980 1760 13 11 1980 1760 0.00007247 0.00002620
0.010 0.010 1800 1600 13 11 1980 1760 14 11 2080 1760 0.00001854 0.00004178
O.OlD 0.010 1800 1650 13 12 1980 1860 13 12 1980 1860 0.00007370 0.00002883
O.OlD O.OlD 1800 1700 13 12 1980 1860 14 12 2080 1860 0.00001881 0.00004315
O.OlD O.OlD 1800 1750 13 13 1980 1980 13 13 1980 1980 0.00004690 0.00002396
0.010 0.010 1800 1800 13 13 1980 1980 14 14 2080 2080 0.00000283 0.00000283
O.OlD 0.010 1800 1850 13 14 1980 2080 13 14 1980 2080 0.00004791 0.00002545
O.OlD 0.010 1800 1900 13 14 1980 2080 13 15 1980 2180 0.00003638 0.00001173
0.010 O.OlD 1800 1950 13 15 1980 2180 13 15 1980 2180 0.00004892 0.00002695
O.OlD 0.010 1800 2000 13 15 1980 2180 13 16 1980 2280 0.00003657 0.00001199
--.,
Variations (oscillations) in unit commitment in System A is due to the fact that starting from single system unit
commitments, the system with the highest ISR at any instance is responsible for committing the next unit until the
ISRcriterion is met.
w00
39
mitment and corresponding ISR in System A and System B. The specifiedSSR and ISR is 0.01 and 0.0001 respectively. Tie capacity was varied from
2 x 40 MW to 2 x 200 MW in discrete steps to observe the effect of tie
capacity on the level of assistance provided by one system to another.
Table 3.1: Effect of Tie-line Capacity.
La = 1750 MW c, = 2000 MW SSR 0.01 ISR 0.0001
Tie Capacity Units ISR
(MW) A B A B
2x40 14 16 0.00000584 0.000029692x50 14 16 0.00000505 0.000027102x60 14 16 0.00000466 0.00001421
2x70 13 16 0.00002624 0.000009082x80 13 16 0.00001326 0.000007642x90 13 15 0.00002495 0.000053462x100 13 15 0.00002494 0.000051072x125 13 15 0.00002479 0.000032272x150 13 15 0.00002479 0.000032262x175 13 15 0.00002477 0.000032112x200 13 15 0.00002477 0.00003211
The results shown in Table 3.7 have been derived for a load of 1750 MW in
System A and 2000 MW in System B. System A and System B are re
quired to commit 13 and 15 units respectively to satisfy their SSR criteria.
Both systems must commit one more unit in addition to their single system
commitment to satisfy the ISR when the tie capacity is 2x40 MW. As the
tie capacity is increased from 2x40 MW to 2x60 MW the unit commitment
of both system remain unaltered at 14 units in System A and 16 units in
System B with the ISR's decreasing with increments in tie capacity. When
the tie capacity is 2 x 90 MW, both System A and System B can satisfy their
ISR criteria without committing any additional capacity than their single sys
tem commitment. The tie capacity of 2x40 MW is, therefore, inadequate for
the potential assistance that systems A and B are capable of providing to
each other at a load level of 1750 MW in A and 2000 MW in B.
40
Table 3.8: Effect of Tie-line Capacity.
La = 1800 MW Lb = 1400 MW SSR 0.01 ISR 0.0001
Tie Capacity Units ISR
(MW) A B A B
2x40 14 11 0.00002715 0.000003422x50 14 10 0.00002554 0.000023732x60 14 10 0.00001277 0.000021882x70 14 10 0.00000681 0.000009072x80 14 10 0.00000567 0.000004422x90 13 10 0.00004283 0.000016292x100 13 10 0.00004069 0.000016182x125 13 10 0.00002198 0.000016172x150 13 10 . 0.00002172 0.000016172x175 13 10 0.00002157 0.000016172x200 13 10 0.00002157 0.00001617
Increments of tie capacity above 2x90 MW do not alter the unit com
mitment III System A and System B from the unit commitment at the tie
capacity of 2x90 MW. The ISR of System A and System B, however,
decreases as the tie capacity is increased from 2x90 MW to 2x125 MW.
The spinning reserve assistance that System A and System B can provide to
each other tends to saturate as the tie capacity IS increased beyond2 x 125 MW. Similar effects can be seen from Table 3.8 when the load III
System A is 1800 MW and in System B is 1400 MW. The tie capacity at
which the assistance benefit will tend to saturate depends on the set of
generating units and the load levels in the interconnected systems.
3.4. Effect of a Load Change in One System on The
Other System
In an interconnected system, the assistance available from one system
to its neighbour is determined by the capacity outage probability table, the
system load and the tie-line capacity. The neighbouring system sees this as-
41
sistance as an additional generating unit. The capacity model of the system
is therefore modified by the tie-line constrained equivalent assistance unit
from the other system. The ISR is thus influenced by the equivalent assis
tance unit of the neighbouring system.
If the SSR values satisfy conditions (a) and (b) as noted in Section
3.2.1 despite an increase in load in one system, then the other system will
not be affected in terms of its unit commitment plan. This is virtually the
same as considering the two interconnected member systems to be independent of each other although they are interconnected. This independence
depends on the set of generation units, unit failure rates, tie line capacity,
system load, SSR, ISR, etc. Anyone of these factors can change the equi
librium, and hence the independence IS an unstable state as far as this
aspect of operation is concerned. A near independence situation can be ach
ieved by restricting the tie line capacity, which may contradict the basic
philosophy of interconnection. Therefore, in practical power systems it is dif
ficult to maintain the state of independence with variable load. This situa
tion can, however, be achieved by lowering the SSR significantly such that
the condition (b) (the systems after interconnection show the ISR SIg
nificantly lower than the specified ISR) is satisfied for a wide range of load
changes while keeping the ISR fixed. This would, however, realise less
benefit from the interconnection than would be achieved in the state of
dependence.
Table 3.9 shows the effect of load changes in one system on another
system using the data given in Table 3.2 and a tie capacity of 2x40 MW.
The SSR and the ISR is 0.01 and 0.0001 respectively. In these studies, the
load in System A was held constant at 1800 MW and the load in System B
was varied from 1300 MW to 2000 MW in steps of 50 MW. The number
of units to be committed in System A is constant at 14 and the actual ISR
in A changes slightly with the subsequent changes in the load level in
System B.
Table 3.9: Effect of Load Changes On Unit Commitment (Tiecapacity = 2x40 MW).
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW) . Units (MW) Units (MW)
A B A B A B A B A B A B
1800 1300 13 9 1980 1510 14 10 2080 1660 0.00002715 0.00000315
1800 1350 13 9 1980 1510 14 10 2080 1660 0.00002723 0.00000823
1800 1400 13 10 1980 1660 14 11 2080 1760 0.00002715 0.00000342
1800 1450 13 10 1980 1660 14 11 2080 1760 0.00002724 0.00000902
1800 1500 13 10 1980 1660 14 12 2080 1860 0.00002715 0.00000370
1800 1550 13 11 1980 1760 14 12 2080 1860 0.00002725 0.00000983
1800 1600 13 11 1980 1760 14 13 2080 1980 0.00002710 0.00000255
1800 1650 13 12 1980 1860 14 13 2080 1980 0.00002720 0.00000534
1800 1700 13 12 1980 1860 14 13 2080 1980 0.00002731 0.00002615
1800 1750 13 13 1980 1980 14 " 14 2080 2080 0.00002721 0.00000583
1800 1800 13 13 1980 1980 14 14 2080 2080 0.00002733 0.00002733
1800 1850 13 14 1980 2080 14 15 2080 2180 0.00002721 0.00000632
1800 1900 13 14 1980 2080 14 15 2080 2180 0.00002735 0.00002856
1800 1950 13 15 1980 2180 14 16 2080 2280 0.00002721 0.00000681
1800 2000 13 15 1980 2180 14 16 2080 2280 0.00002737 0.00002983
�N
43
Table 3.10 shows the units that must be committed in System A and
System B for similar operating conditions considered in the case of Table 3.9
but with a change in the tie capacity. The tie capacity in the case of Table
3.10 is 2x90 MW. Using this tie capacity, the unit commitment in
System A changes with variation of load level in System B, although the
load in System A is held constant.
A change in load in one system also changes the level of assistance
that this system can provide to its neighbour. A system experiences the ef
fect of load change in its neighbouring system through the tie lines intercon
necting them. A system IS, therefore, less affected by load changes in its
neighbouring system if the tie capacity is far less than that which is requiredfor unconstrained power flow. This is one of the principle reasons why the
load changes in System B shown in Table 3.9 do not influence the unit com
mitment of System A when the tie capacity is 2x40 MW. On the other
hand, the unit commitment in System A for similar conditions is affected as
shown in Table 3.10 by the load changes in System B when the tie capacity
is increased to 2 x 90 MW.
3.S. Effect of Unit Failure Rates on Spinning Reserve
Generating unit failure rates are important parameters in unit commit
ment and spinning reserve assessment. The probabilities of the capacity out
age states in the capacity model of a system directly depend on the generat
mg unit failure rates. A system whose units fail more frequently than its
neighbour is likely to commit more units [i.e, more spinning reserve) than its
neighbour provided other variables are identical. The effect of unit failure
rate, however, will differ depending upon the selection of the specified SSR
and ISR as far as the spinning reserve and the unit commitment are con
cerned.
Table 3.11 shows the unit commitment in System A and System B
when all parameters including the unit failure rates in both systems are iden-
Table 3.10: Effect of Load Changes On Unit Commitment (Tiecapacity = 2x90 MW).
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW)
A B A a A B A B A B A B
1800 1300 13 9 1980 1510 13 9 1980 1510 0.00007067 0.00001909
1800 1350 13 9 1980 1510 14 10 2080 1660 0.00000290 0.00000176
1800 1400 13 10 1980 1660 13 10 1980 1660 0.00004283 0.00001629
1800 1450 13 10 1980 1660 13 10 1980 1660 0.00007338 0.00002377
1800 1500 13 10 1980 1660 14 11 2080 1760 0.00000381 0.00000467
1800 1550 13 11 1980 1760 13 11 1980 1760 0.00007459 0.00002639
1800 1600 13 11 1980 1760 14 12 2080 1860 0.00000384 0.00000497
1800 1650 13 12 1980 1860 13 12 1980 1860 0.00007581 0.00002903
1800 1700 13 12 1980 1860 14 13 2080 1980 0.00000314 0.00000307
1800 1750 13 13 1980 1980 13 13 1980 1980 0.00004903 0.00002397
1800 1800 13 13 1980 1980 14 14 2080 2080 0.00000316 0.00000316
1800 1850 13 14 1980 2080 13 14 1980 2080 0.00005003 0.00002546
1800 1900 13 14 1980 2080 13 15 1980 2180 0.00003850 0.00001173
1800 1950 13 15 1980 2180 13 15 1980 2180 0.00005103 0.00002696
1800 2000 13 15 1980 2180 13 16 1980 2280 0.00003868 0.00001199
-
Variations (oscillations) in unit commitment in System A is due to the fact that starting from single system unit
commitments, the system with the highest ISR at any instance is responsible for committing the next unit until the
ISRcriterion is met.
.c:..
.c:..
45
tical. The unit commitments are identical for equal load in both systems as
expected. In order to study the effect of unit failure rate on unit commit
ment and spinning reserve, all the transition rates of the on-line generating
Table 3.11: Unit Commitment With Equal Unit Failure Rates.
Specified SSR = 0.001 Specified ISR = 0.00001
Spinning ISR
Load (MW) Units Capacity (MW)A B A B A B A B
1650 1650 13 13 1980 1980 0.00000051 0.00000051
1750 1750 14 14 2080 2080 0.00000053 0.00000053
1850 1850 15 15 2180 2180 0.00000054 0.00000054
1950 1950 16 16 2280 2280 0.00000055 0.00000055
2050 2050 17 17 2355 2355 0.00000077 0.00000077
units of System A have been changed to 1.5 times that of the transition
rates of the on-line generating units of System B. The units that must be
committed in System A and System B are shown in Table 3.12. For all
cases, Sy�em A requires one more unit to be committed than in System BII
for equal! load in each system. The spinning reserve requirement in
System A is, therefore, higher than that in System B due to the simple
reason that the units in System A are more likely to fail than those in
System B.
Table 3.12: Unit Commitment With Unequal Unit FailureRates.
Specified SSR = 0.001 Specified ISR 0.00001
Spinning ISR
Load (MW) Units Capacity (MW)A B A B A B A B
1650 1650 13 12 1980 1860 0.00000430 0.00000641
1750 1750 14 13 2080 1980 0.00000287 0.00000566
1850 1850 15 14 2180 2080 0.00000305 0.00000621
1950 1950 16 15 2280 2180 0.00000323 0.00000678
2050 2050 17 16 2355 2280 0.00000540 0.00000873
46
3.6. Rapid Start and Hot Reserve Units
In a practical system, generating units are committed for a specified. time period during which additional generation can be made available after a
time delay. The actual time delay depends on the type of additional genera
tion and many other factors of which the type of additional generation is the
most important. The delay time associated with a thermal generating unit
can be several hours while hydro and gas turbine units can be started very
quickly. The delay times associated with starting, synchronising, and loading
of hydro and gas turbine units are relatively short. The loading characteris
tics of these rapid units are quite different from the loading characteristics of
conventional thermal units although the lead time of the thermal units can
be reduced considerably by keeping the boilers in a hot state.
The concept of area risk curves [3] can be used to include rapid start
and hot reserve units in the assessment of operating risk. This concept can
be extended to interconnected system operation. A typical area risk curve
for a system with gas turbine and thermal hot reserve units is shown in
Figure 3.2 [3].
F (R)I�- Har RESERVE UNITS IN
---- �---I� ADDITIONAL
__- __ ta L-.___:::UNITS IN
TIME
Figure 3.2: Area Risk Curve of a System.
47
In Figure 3.2, F(R) is the risk function and
t;
= the time to start rapid start gas turbine units
t h the time to start hot reserve units
ta
the lead time for the remaining thermal units.
At time tr the gas turbine units become available and the risk con
tribution decreases. The risk contribution decreases further at time th when
the hot reserve thermal units become available. At time ta' additional ther
mal units become available and the risk contribution is reduced significantly.
The ordinate of the risk curve can be considered to be zero for all practical
purposes after a lead time tao The risk level for the entire lead time for
this case IS
R (3.1)
where:
risk level calculated for the operating capacity alone for the
time interval 0 to tr,
risk level calculated for the operating capacity plus the gas
turbine units for the time interval t;
to th,
pa F(R )dtt 3h
risk level calculated for the operating capacity plus the gas•
turbine and hot reserve units for the time interval t h to ta.
The areas under the curve are calculated directly for computational purposes
and the actual integral equations are not used [3]. The total area under the
curve represents the probability that all the present on-line generating units
plus all the back up units in the system will be unable to or just able to
meet the system load demand. The SSR of the system should be equal to
or less than R.
48
In any interconnected system, participating member systems may have
different numbers and types of rapid start and hot reserve units. The lead
time associated with these units may also be quite different for different sys
tems. In an interconnected system study, the area risk curve of one system
is modified by the area risk curve(s) of its neighbour(s). The modified area
risk curves are shown in Figure 3.3.
F(RAB) is the risk function of System A with assistance from
System B
is the risk function of System B with assistance from
System A
time to start rapid start units m System A
time to start hot reserve units in System A
lead time for the remammg thermal units in System A
time to start rapid start units in System B
time to start hot reserve units in System B
lead time for the remaining thermal units in System B
The ISR of both systems for a total lead time Tare:
itra jtrb jthaRia = F(RAB )dt + F(RAB )dt + F(RAB )dt +o 1 t 2 tb 3
ra r
jthb jtaa jtabF(RAB )dt + F(RAB )dt + F(RAB )dt +t ha
4 t hb5 t
aa6
jT F(RAB )dt (3.2)tab 7
49
.....--thb��------tab
I I
F(�)
T ----.....1 TIME
Figure 3.3: Area Risk Curves of an Interconnected System.
50
where
Ria = ISR of System A
Rib = ISR of System B
3.6.1. Rapid start and hot reserve unit models
3.6.1.1. Rapid start units
The conventional two-state or three-state generating unit models
described in Sections 2.4.1 and 2.4.2 do not contain sufficient detail to ade
quately represent rapid start units. These units such as gas turbines can be
represented by the four-state model [3] shown in Figure 3.4.
FAILS TO STARr FAILED
READY FOR SERVICE IN SERVICE
Figure 3.4: Four-state Model for Rapid Start Units.
51
The time dependent state probabilities can be evaluated using matrix
multiplication techniques [3]. The stochastic transitional probability matrix P
for the four-state model shown in Figure 3.4 is as follows.
1-(A12+'\14)�t '\12�t 0 '\14�t'\21�t 1-('\21+'\23)�t '\23�t 0
p= 0 '\32�t 1-('\32+'\34)�t '\34�t'\41�t '\42�t 0 1-('\41+'\42)�t
The initial probability vector IS:
where
and
The probability of finding the unit on outage given that a demand has
occurred is given by [3]
P(down)
3.6.1.2. Hot reserve units
A thermal unit when taken out of service can be in one of two states;
hot reserve or cold reserve. In the hot reserve state, the boiler is retained
in an active or semi-active condition. In a cold reserve state, the boiler is
completely shut down. The hot reserve unit, therefore, can be brought back
into service in a shorter time than the cold reserve unit. A hot reserve
thermal unit can be represented by the five-state model [3] shown in Figure3.5.
The initial probability vector for the hot reserve unit is:
52
FAIL TO TAKE
UP LOAD FAIlED
Bar RESERVE IN SERVICE
Figure 3.5: Five-state Model For Hot Reserve Units.
[ P(0) 1 = [P10 0 0 P40 01
where
P40 = )..23/ ()..21 +)..23)PlO = I-P40 .
The time dependent state probabilities can be evaluated usmg similar
techniques to those utilised for a rapid start unit [3].
A computer program has been- written usmg the area risk concept to
53
include rapid start and hot reserve units in a spmnmg reserve study for an
interconnected system configuration. Assume that both System A and Sys
tem B has one rapid start and one hot reserve unit in addition to those
units in Table 3.2. The corresponding transition rates per hour of the rapidstart and hot reserve unit are shown in Table 3.13.
Table 3.13: Transition Rate of Hot Reserve and Rapid StartUnits.
Rapid start unit:
Capacity = 25 MW Lead time 5 minutes
All=O.OOA21 =0.0033
A31=0.0A41=0.015
A12=0.005A22=0.0A32=0.0A42=0.025
A13=0.0A23=0.0008A33=0.0A43=0.0
A14=0.03A24=O.OA34=0.025A44=0.0
Hot reserve unit:
Capacity 50 MW Lead time = 60 minutes
Al1=O.OA21=0.02A31=0.0A41=0.035A51=0.003A15=0.0A25=0.0
A12=0.024A22=0.0A32=0.0A42=0.0A52=0.0025A35=0.0A45=0.025
A13=0.0A23=0.00002A33=0.0A43=0.0A53=0.0A55=0.0
A14=0.008A24=O.OA34=0.03A44=0.0A54=0.0
Table 3.14 shows the computational results when rapid start and hot
reserve units are added to both systems. The SSR and ISR is considered to
be 0.01 and 0.0001 respectively. The load in System B is varied while the
load in System A is held constant. The actual magnitude of the operatingreserve of each system can be found by subtracting the system load from the
total committed capacity shown in columns 11 and 12 in Table 3.14.
Table 3.14: Unit Commitment With Rapid Start and Hot
Reserve Units.
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW)I
A B A B A B A B A B A B
1800 1300 13 9 1980 1510 13 9 1980 1510 0.00000581 0.00000317
1800 1350 13 9 1980 1510 13 9 1980 1510 0.00001278 0.00001219
1800 1400 . 13 10 1980 1660 13 10 1980 1660 0.00000412 0.00000076
1800 1450 13 10 1980 1660 13 10 1980 1660 0.00000599 0.00000403
1800 1500 13 10 1980 1660 13 10 1980 1660 0.00001360 0.00001478
1800 1550 13 11 1980 1760 13 11 1980 1760 0.00000603 0.00000411
1800 1600 13 11 1980 1760 13 11 1980 1760 0.00001370 0.00001530
1800 1650 13 12 1980 1860 13 12 1980 1860 0.00000607 0.00000420
1800 1700 13 12 1980 1860 13 12 1980 1860 0.00001379 0.00001583
1800 1750 13 13 1980 1980 13 13 1980 1980 0.00000484 0.00000224
1800 1800 13 13 1980 1980 13 13 1980 1980 0.00000905 0.00000905
1800 1850 13 13 1980 1980 13 13 1980 1980 0.00002350 0.00003907
1800 1900 13 14 1980 2080 13 14 1980 2080 0.00000912 0.00000936
1800 1950 13 14 1980 2080 13 14 1980 2080 0.00002375 0.00004027
1800 2000 13 15 1980 2180 13 15 1980 2180 0.00000919 0.00000967
CJl.1:0.
55
3.7. Effect of Load Forecast Error
Unit commitment and spinning reserve assessment In a power system IS
normally based on an advance estimate of hourly load variation within a
short period of time, typically 24 hrs. The prediction of future load is nor
mally done on the basis of past data and weather forecasts. A certain de
gree of error exists between the forecast and the actual load [27] due to the
random nature of system loads, the non-linear relationship between load and
weather changes and inaccuracies in weather forecasting. Load forecast un
certainty can be reasonably approximated by a normal distribution [�:]. The
mean of the distribution is the forecast load. The normal distribution can
be discretised into several class intervals for computational simplicity [3]. The
probability associated with a class interval can be assigned to the load
representing the class interval mid-point.
Assume that the load forecast uncertainty in System A and System B
can be approximated by discretizing the normal distribution of loads in
System A and System B with nand m steps respectively. For one load
step in System A there are m possible risk indices in System A due to the
m load steps in System R The ISR of System A due to the kth load step
In System A is
m
L Ra(k,j)PbU)j=1
(3.4)
where
ISR of System A due to a load of La(k) in System. A and
LbU) in System B,
ISR of System A due to the kth load step in System A and
all the load steps in System B,
kth load step of the load distribution In System A,
Jth load step of the load distribution In System B,
56
probability of the load step LbU) m System B.
The ISR of System A can be expressed as the weighted summation of
the risk contributions due to the n load steps in System A.
n
L R'ia{k)Pa(k)k=l
(3.5)
where
ISR of System A,
probability of the load step La (k) in System A.
Combining Equations (3.4) and (3.5), the ISR in System A can be expressedas
n m
Ria(k) = L {L Ra(k,i)PbU)}Pa(k)k=l j=l
(3.6)
A similar expression can be written for the corresponding ISR in System B.
Based on Equation (3.6) a computer program has been developed to assess
spmnmg reserve and unit commitment in interconnected systems in the
presence of load forecast uncertainty. Equation (3.6) indicates that rn x n in
dividual ISR computations are required to determine the unit commitment
risk in System A and System B. The computation time required to assess
spinning reserve and unit commitment with load forecast uncertainty is con-•
siderably higher than that required with zero load forecast uncertainty due to
this m x n individual risk computations. The computation time in the
presence of load forecast uncertainty, however, can be kept in reasonable
limits by approximating the load distributions with a comparatively small
number of load steps.
A normally distributed load can be approximated by seven or three
load steps depending on the degree of accuracy required. Figure 3.6 shows
57
PROBABILITY GIVEN BY INDICATED AREA
-3 -2 -1 0
NO. OF STANDARD DEVIATIONSFROM THE MEAN
+1 +2 +3
MEAN FORECAST LOAD(MW)
Figure 3.6: Seven-step Approximation of the Normal Distribution.
the seven-step approximation of a normal distribution. In the seven-step ap
proximation to normal curve, the distribution beyond ± 3.5 standard devia
tion (SD) is neglected. It IS assumed that the respective area be
tween +2.5 SD to +3.5 SD and between -2.5 SD to -3.5 SD is 0.006. As
sume that the load forecast uncertainty in System A and System B can be
approximated by the seven-step load distribution shown in Figure 3.€;. Table
3.15 shows the unit commitment and corresponding risk In System A and
System B. A standard deviation of 2% of the forecast load is assumed in
both systems. The load in System B is varied from 1300 MW to 2000 MW
in steps of 50 MW while the load in System A is held constant at
Table 3.15: Unit Commitment With Load Forecast Uncertainty(Seven-step approximation of the load distribution).
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW)
A B A B A B A B A B A B
1800 1300 14 9 2080 1510 14 9 2080 1510 0.00000931 0.00001211
1800 1350 14 10 2080 1660 14 10 2080 1660 0.00000332 0.00000139
1800 1400 14 10 2080 1660 14 10 2080 1660 0.00000508 0.00000464
1800 1450 14 10 2080 1660 14 10 2080 1660 0.00001000 0.00001519
1800 1500 14 11 2080 1760 14 11 2080 1760 0.00000521 0.00000541
1800 1550 14 11 2080 1760 14 11 2080 1760 0.00001015 0.00002664
1800 1600 14 12 2080 1860 14 12 2080 1860 0.00000529 0.00000566
1800 1650 14 12 2080 1860 14 12 2080 1860 0.00001050 0.00002760
1800 1700 14 13 2080 1980 14 13 2080 1980 0.00000448 0.00000433
1800 1750 14 13 2080 1980 14 13 2080 1980 0.00000833 0.00001457
1800 1800 14 14 2080 2080 14 14 2080 2080 0.00000453 0.00000453
1800 1850 14 14 2080 2080 14 14 2080 2080 0.00000866 0.00001589
1800 1900 14 15 2080 2180 14 15 2080 2180 0.00000480 0.00000497
1800 1950 14 15 2080 2180 14 15 2080 2180 0.00000894 0.00001714
1800 2000 14 16 2080 2280 14 16 2080 2280 0.00000490 0.00000585
CJ100
59
1800 MW. Table 3.16 shows the unit commitment and corresponding risk
for the same forecast load levels as shown in Table 3.15 but with zero load
forecast error. It can be seen by comparing the Tables 3.15 and 3.16 that
at some load levels, System A or System B must commit more generatingunits in the presence of load forecast uncertainty than that with zero forecast
uncertainty. The computation time required to determine the unit commit
ment shown in Table 3.15 is 46 mins. and 12.81 sees, CPU (VAX 8650).The computation time to determine the unit commitments for the load levels
shown in Table 3.16 with zero load forecast uncertainty is 1 min. and 37.33
sees,
A three-step approximation to the normal distribution for the loads in
System A and System B can also be used for unit commitment and spinning
reserve assessment with a small loss of accuracy compared to the seven-step
approximation. A three-step approximation will considerably reduce the com
putation time from that required with a seven-step approximation. The
saving in computation time should be judged against the potential loss of ac
curacy. Figure 3.7 shows a three-step approximation to the normal distribu
tion. In this three-step approximation the distribution beyond ± 3 SD is
neglected. It has been assumed that the respective area between + 1 SD to
+3 SD and between -1 SD to -3 SD is 0.1587 instead of 0.1574. Table 3.17
shows the unit commitments and corresponding risk in System A and
System B with the identical forecast loads shown in Table 3.15. The normal
distribution of load in the case of Table 3.17, however, is approximated by a
three-step approximation with a standard deviation of 2% of the forecast
load in both systems. The unit commitments in System A and System B
are identical with seven-step and three-step approximations to the normal
distribution except when the load is 1800 MW in System A and 1350 MW
in System B. The computation time is 8 mins. and 46.42 sees. with the
three-step approximation for an identical set of forecast load as used in the
seven-step approximation case.
Table 3.16: Unit Commitment With Zero Load Forecast Uncertainty,
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW)
A B A B A B A B A B A B
1800 1300 13 9 1980 1510 13 9 1980 1510 0.00006854 0.00001896
1800 1350 13 9 1980 1510 14 9 2080 1510 0.00001668 0.00003599
1800 1400 13 10 1980 1660 13 10 1980 1660 0.00004069 0.00001618
1800 1450 13 10 1980 1660 13 10 1980 1660 0.00007126 0.00002358
1800 1500 13 10 1980 1660 14 10 2080 1660 0.00001827 0.00004044
1800 1550 13 11 1980 1760 13 11 1980 1760 0.00007247 0.00002620
1800 1600 13 11 1980 1760 14 11 2080 1760 0.00001854 0.00004178
1800 1650 13 12 1980 1860 13 12 1980 1860 0.00007370 0.00002883
1800 1700 13 12 1980 1860 14 12 2080 1860 0.00001881 0.00004315
1800 1750 13 13 1980 1980 13 13 1980 1980 0.00004690 0.00002396
1800 1800 13 13 1980 1980 14 14 2080 2080 0.00000283 0.00000283
1800 1850 13 14 1980 2080 13 14 1980 2080 0.00004791 0.00002545
1800 1900 13 14 1980 2080 13 15 1980 2180 0.00003638 0.00001173
1800 1950 13 15 1980 2180 13 15 1980 2180 0.00004892 0.00002695
1800 2000 13 15 1980 2180 13 16 1980 2280 0.00003657 0.00001199
�
8
61
PROBABILITY GIVEN BY INDICATED AREA
0.6826
-3 -2 -1 o +1 +2 +3
NO. OF STANDARD DEVIATIONSFROM THE MEAN
MEAN = FORECAST LOAD(MW)
Figure 3.1: Three-step Approximation of the Normal Distribution.
T8ble 3.17: Unit Commitment With Load Forecast Uncertainty(Three-step approximation of the load distribution).
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW)
A B A B A B A B A B A B
1800 1300 14 9 2080 1510 14 9 2080 1510 0.00000973 0.00001242
1800 1350 14 9 2080 1510 14 9 2080 1510 0.00002264 0.00007230
1800 1400 14 10 2080 1660 14 10 2080 1660 0.00000519 0.00000454
1800 1450 14 10 2080 1660 14 10 2080 1660 0.00001049 0.00001500
1800 1500 14 11 2080 1760 14 11 2080 1760 0.00000544 0.00000606
1800 1550 14 11 2080 1760 14 11 2080 1760 0.00001066 0.00003494
1800 1600 14 12 2080 1860 14 12 2080 1860 0.00000545 0.00000629
1800 1650 14 12 2080 1860 14 12 2080 1860 0.00001074 0.00003555
1800 1700 14 13 2080 1980 14 13 2080 1980 0.00000465 0.00000451
1800 1750 14 13 2080 1980 14 13 2080 1980 0.00000855 0.00001480
1800 1800 14 14 2080 2080 14 14 2080 2080 0.00000468 0.00000468
1800 1850 14 14 2080 2080 14 14 2080 2080 0.00000866 0.00001536
1800 1900 14 15 2080 2180 14 15 2080 2180 0.00000472 0.00000487
1800 1950 14 15 2080 2180 14 15 2080 2180 0.00000885 0.00001630
1800 2000 14 16 2080 2280 14 16 2080 2280 0.00000498 0.00000679
0)t-.j
63
3.8. Summary
The theoretical and computational features of a new spinning reserve
assessment technique for interconnected systems are introduced in this chap
ter. The technique designated as the 'Two Risks Concept' uses the stochas
tic nature of the system components during the spinning reserve evaluation.
The 'Two Risks Concept' proposes that two risk levels are to be satisfied by
each individual interconnected system for a fair sharing of spinning reserve
among the pool members. The 'Two Risks Concept' has the capability to
incorporate the essential system parameters which directly or indirectly in
fluence the system reliability. The inclusion of hot reserve and rapid start
units in the unit commitment process is illustrated in this chapter. This
chapter also discusses spinning reserve assessment in interconnected systems
with load forecast uncertainty. The results of some typical spinning reserve
situations and the corresponding unit commitment risks are also presented.
64
4. SPINNING RESERVEWITH EXPORT/IMPORT
4.1. Introduction
Chapter 3 presents the basic aspects of the 'Two Risks Concept' and il
lustrates this technique for spinning reserve assessment in an interconnected
generating system assuming that there is no contracted export/import.Energy flow occurs between the interconnected systems if one system suffers
a sudden generation loss. The system with the lost generation is, however,
required to adjust its generation within an allowable time limit agreed by the
pool members. Inadvertent energy flow between systems also occurs due to
electrical disturbances and inaccuracies in the tie line control. These inter
changes are unscheduled and utilities interconnected by tie lines make pay
ments to each other for these interchanges in accordance with some
agreements [27, 28]. In a practical multi-area system, contracted
export/import between different areas IS a common operating condition. A
probabilistic assessment of the spinning reserve requirement in different areas
of a multi-area interconnected system with export/import can be performedbased on the 'Two Risks Concept'. In the following sections, a
technique [29] for spinning reserve assessment in a multi-area system with
export/import agreements is illustrated.
65
4.2. Export/Import Agreements
There could be many different agreements regarding contracted
export/import of energy between the interconnected utilities in a power pool.The export/import agreements between utilities not only control' the tie line
flow but also influence the unit commitment in the interconnected systems.
The amount of power flow through the tie lines affects the level of assistance
with respect to the spinning reserve that a system can provide to its neigh
bours. The probabilistic models for export/import will depend greatly on the
type of agreements between utilities. It is not practical to develop methods
to assess spinning reserve for all possible export/import agreements. Two
basic agreements are considered in this thesis. These agreements are (1)firm purchase by one system is backed up by the complete system of the ex
porting utility and, (2) firm purchase is tied to a specific unit in the export
ing system.
4.3. Firm Purchase Backed Up by the Complete System
In this form of agreement, the availability of a certain capacity
(import) is guaranteed by the entire exporting system. The import can be
modelled as an equivalent generating unit with an effective zero forced out
age rate as far as the importing system is concerned. The export, on the
other hand, can be modelled as an additional load as far as the exporting
system is concerned. The guarantee of the exporting system is limited by
the reliability of its generating units. An exporting system would require In
finite generation capacity to maintain a finite export capacity with 100�
reliability. If the export capacity is considerably less than the load of the
exporting system, then for all practical purposes the reliability of the export
ing capacity can be considered as 100%. If the export capacity, on the
other hand, is relatively large in comparison to the load of the exporting sys
tem, then the export commitment cannot be considered to be 100% reliable
and the actual risk associated with the export should be considered for com
putational and contractual purposes.
,66
Assume that
Li load of System i,
Iij import of System i from System j,
Eij export of System i to System j,
Tii tie capacity between System i and System j.
In the case where export is backed up by the entire exporting system
and L Eij< Li, all export can be modelled as additional load to the ex
porter. Therefore, the effective load of System i, Lei becomes
(4.1)
If all the imports �f System i are completely backed up by the respective ex
porters and the tie lines are 100% reliable, the generation model of System i
will be modified by the additional generating unit of capacity equal to the
sum of all imports of System i with forced outage rates of zero. It is as
sumed that all tie-line capacities are greater than the proposed import
through them. If a specific tie capacity, Tij is less than the proposed im
port, Iii through it, then the import of System i from System j becomes Til
In most situations, tie lines are assumed to be 100% reliable and the
development of export and import models are relatively straightforward.These models have to be modified, however, to recognise tie line constraints
if it is considered that tie-line failures cannot be neglected. Under these
conditions, the import in concern cannot be modelled as a 100% reliable
generating unit.
4.3.1. Tie-line constrained import model
The tie-line flow depends on the system states at the two ends of the
tie line. The tie-line flow IS constrained by its maximum power transfer
capability. For the sake of simplicity it is assumed that the tie-capacity is
constant during the time period equal to the system lead time. In the case
where tie-capacity varies during the study period, the study period is sub-
67
divided into several intervals and tie-capacity IS assumed to be constant
within each of these intervals.
Assume that
kth capacity state of the tie line between System i and
System j at time t ,
�/t) probability that the kth state of the tie line,· Tii exists at
time t,
total no. of capacity states in the tie-line model,
kth capacity state of the import model for the import of Iiiat time t,
�it) probability that the kth state of the import model for the
import of Iii exists at time t,
R�J-:-l(t) > Rk ( ). ii
t
and
total no. of capacity states in the import model.
If Q:j(t) > Iii the import model becomes
68
1I· .Ri/t) t)
n
1
L P:/t)S .. (t)I)
k=l
R�/t) =
Q�;:n-l(t)}S� .(t) = Pc_ .(t)
k
I) tJ
2, 3, 4, ... , (nt-n+l)
where n is an integer such that Q�.(t) > I .. > Q��l(t).tJ- lJ IJ
If Q�/t):::; Iij i.e., the tie capacity IS less than or equal to the import,
the import model is
1, 2, 3 ... , nt
The tie-line constrained import model can be considered for computa
tional purposes as an additional on-line generating unit to the importing sys
tem.
4.8.2. Export/import constrained tie-line model
The available capacity of the tie-line model with respect to the assis-1
tance of additional spinning reserve reduces to zero when Qi/t):::; Iij and the
entire tie-line model can only transfer the export/import capacity, with or
without capacity constraints on the imported power. The tie lines can,
69
however, assist the connecting systems with spinning reserve if at least
Ql iit) > Iij. The export/import constrained tie-line model can be derived
using the following relationships.
Assume that
if. .(t) =
Z)kth capacity state of the tie line between System i and
System j after fulfilling the export/import commitment at
time t,
0. .(t) =
Z)
\
Then
r.1/t)
probability that the kth capacity state of the tie line be
tween System i and System j exists after fulfilling the
export/import commitment at time t,
total number of capacity states in the tie-line model after
fulfilling export/import commitments.
kQ .. (t)t)
-
I.J.Z)
k 1, 2, 3, ... , n
0. .(t) = P'. .(t)Z) ')
where n is an integer such that Q�.(t) > I;). > Q�:l(t)f) •
-
t)
nt
L P:/t)k=n+l
and it = n + 1
The export/import constrained tie-line model is used to determine the
tie-line constrained assistance equivalent unit of each system for risk and
spinning reserve assessment.
70
4.3.3. Tie-line failure neglected
If the tie lines are assumed to be 100% reliable then the import model
also becomes 100% reliable.
1I· . T··Ri/t) I· . <
'J IJ IJ
T·· , Iij > T··'J IJ
1
Si}t) 1
and
mt - 1
The export/import constrained tie-line model with a 100% reliable tie line IS
as follows.
1T.. - I· . T··Ui/t) > I· .
t) ZJ ZJ Z)
0 , Tij < I· .
'J
�}t) 1
and
It 1
4.4. Firm Purchase Backed Up by a Specific ..
Unit
In this agreement the export is tied to a specific generating unit of the
exporting system. The export therefore cannot be modelled as a generatingunit with zero forced outage rate. The export model will have outage
parameters which are based on the unit guaranteeing the export. The ex
porting unit must be committed as long as it is available for operation. The
capacity remaining above the export commitment can, however, be used bythe exporting system to assist its neighbours with spinning reserve.
71
4.4.1. Export model
Assume that
kth capacity state of the exporting unit of System i at time
k-l kt and Ai (t) > Ai (t),
n:(t) probability that the kth capacity state of the exporting unit
of System i exists at time t,
total number of capacity states in the exporting unit,
kth capacity state of the export model for export from
System i to System j at time t, and C:; l(t) > C:/t),
D�,.(t) probability that the kth capacity state of the export model
for export from System i to System j exists at time t and
total number of capacity states in the export model.
If A�(t) > Eji i.e., unit size IS larger than the export commitment, the
export model is as follows
1E··Cji(t) J'
n
k
L B�(t)Dji(t)1.=1
k
A�+n-'(t}C .. (t)Jt
2, 3, 4, ... , (ne -n+l)k B�+n-l(t)D .. (t)Jt J
and
me = ne-n+l
n( . n+l( )where n IS an integer such that Aj t) 2: Eji > A
jt
72
If A�(t) � Eji i.e., unit size is equal to or less than export commitment,
the export model becomes
and
Other export models can be developed III a similar manner if the sys
tem has more than one export commitment.
4.4.2. Tie-line constrained import model
There can be as many as nt possible capacity states III the tie-line con
strained import model for each capacity state C��t) in the export model,
where nt is the total number of capacity states in the tie-line model. The
import model is
R�/t) = C7/t) ,C7/t) s Q�/t)
Q�/t) C�(t) > Q:/t)k
S .. (t)tJ D�.( t) J!. .(t)lJ tJ
where
m =e
total number of capacity states in the export model for the
export of System i to System j,
n 1, 2, ... , me .
73
There may be many identical capacity states and the states may not be
m order out of all the possible nt·me capacity states m the tie-line con-
strained import model. The identical capacity states can be grouped
together and the model arrangedk-l k
{ )such that R.. (t) > R. t .
tJ tJ
4.4.3. Export /import constrained tie-line model
There could be as many as nt possible states in the export/import con
strained tie-line model for each capacity state C�.(t) in the export model.'J
r1;(t) k- C:J{t)
k
C:/t)Q .. (t) Q .. (t) >tJ ZJ
k C�.(t)0 , Qdt) <ZJ
V;;(t) .I. .(t) D�.(t)ZJ ZJ
where
k nt(n-1)+1, nt(n-l)+2, ... , nt·n
n 1, 2, 3, ... , me
The states can be rearranged as discussed in the previous section. The
export/import constrained tie-line model is used to determine the tie-line con
strained assistance equivalent unit of each system for risk and spinningreserve assessment.
4.4.4. Remainder of the exporting generating unit
In many cases, the exporting unit capacity is larger than the export
commitment. This additional capacity of the exporting unit can be used bythe exporting system as committed capacity after it has fulfilled its export
commitment.
74
Assume that
kth capacity state of the remainder of the exporting unit of
System i at time t and G�-l(t) > G�(t),
probability that the kth capacity state of the remainder of
the exporting unit of System i exists at time t,
total number of states in the remainder of the exportingunit,
total number of states in the exporting unit.
The additional capacity of the exporting unit can be modelled as
1, 2, 3, ... , n
ne
L B�(t)k=n+l
n + 1
where,: is an integer such that A�(t) > Eij > A�+l(t).
4.4.5. Tie-line failures neglected
If the tie lines are assumed to be 100% reliable, then the tie-line con
strained import model can be determined as follows.
75
T·· ,��.(t) > T··tJ lJ lJ
k kT· .Ci;(t) , C .. (t) <
lJ lJ
k= D .. (t)lJ
where k = 1, 2, 3,
The export/import constrained tie-line model becomes
cI.(t) k .
, Tij >
d,P)T·· - C .. (t)IJ tJ IJ
k = 1, 2, 3, ... , n
V:/t) D�J�t)
U�:l(t) - 0
me
�/l(t) L kD .. (t)IJ
k=n+l
It n + 1·
where n IS an integer such that C�.(t) > T··> C�:\t).lJ IJ -
1J
4.5. Interconnected System Risk
Given the load and the SSR of a system, the assistance model of that
system can be developed. This assistance model depends on the set of
generating units required to be committed to satisfy the load, export/importand the SSR. The assistance of one system to the other can be realised
through the export/import constrained tie capacity. The tie-line constrained
assistance equivalent model can be developed as described earlier. The tie
line constrained assistance model of one system can be viewed as an extra
generating unit available to the neighbouring system. When this extra unit
is added to the generation capacity committed on the basis of system load,
76
export/import and SSR; the unit commitment risk is modified. This
modified unit commitment risk is the Interconnected System Risk. If the
ISR criterion IS not satisfied, generating units are added to the intercon
nected systems as described in Reference [26] until the ISR criterion is
satisfied by the participating systems.
4.6. Numerical Examples
Two systems interconnected by two tie lines are considered for numeri
cal examples. The method as described in this chapter, however, can be ap
plied to interconnected configurations with more than two systems. A com
puter program has been developed to assess the spinning reserve requirements
in interconnected systems with export/import constraints. Table 3.2 shows
the generating units in System A and System B. Table 3.3 shows the tie
lines interconnecting the two systems. The lead time for both systems is
considered to be 120 mins. The Interconnected System Risk and the Single
System Risk for both systems are 0.0001 and 0.01 respectively.
4.6.1. Firm purchase backed up by the entire system
A system must commit an adequate number of generating units to
satisfy its SSR for a particular load. In addition to the firm load, a system
may export/import some power to/from its neighbouring system. The effec
tive load seen by a system is modified by the export/import.Case 1
Assume that
La 1450 MW Eab = 0 MW , lab = 60 MW
Lb 1210 MW Eba = 60 MW , lba = 0 MW
and the export of System B is backed by the entire system.
The effective loads become
77
1390 MW
1270 MW.
The export/import of each system is considered to be 100% reliable for
the purpose of calculating SSR. This reduces the computational complexityand although the individual system must first satisfy its SSR, the same sys
tem is required to satisfy its ISR criterion as the final goal. During the ISR
assessment, therefore, the appropriate unavailability of the export/import due
to the tie-line constraints are considered. In order to satisfy the SSR
criterion, System A and System B are required to commit 10 and 9 units
respectively in the merit order shown in Table 3.2. The tie-line model for a
period of 120 minutes is shown in Table 4.1.
Table 4.1: Tie-Line Model.
Cap. Out
(MW)Cap. In
(MW)Cumulative
Probability
o100200
200
100
o
1.000000000.00045657
0.00000005
The tie-line constrained import model for the import of 60 MW by
System A from System B is shown in Table 4.2.
Table 4.2: Tie Constrained Import Model of System A.
Cap. Out
(MW)Cap. In
(MW)Cumulative
Probability
o60
60
o
1.000000000.00000005
The tie-line model as shown m Table 4.1 IS modified due to the
export/import commitment. The export/ import constrained tie-line model is
shown in Table 4.3.
78
Table 4.3: Export/Import Constrained Tie-Line Model.
Cap. Out Cap. In Cumulative
(MW) (MW) Probability
0 140 1.00000000100 40 0.00045657140 0 0.00000005
The export/import constrained tie-line model as shown in Table 4.3 is
used to assess the level of assistance, with respect to the spinning reserve,
that System A and System B can provide each other. In order to satisfy
the ISR criterion, System A is required to commit 10 and System B is re
quired to commit 9 generating units from their respective merit order tables.
The actual ISRs of System A and System B at this point are 0.00000067
and 0.00000480 respectively.
If tie-line failures are neglected, the tie-line model is equivalent to a
100% reliable tie-line with a maximum power transfer capability of 200 MW.
The unit commitment required to satisfy the SSR remains unchanged. The
tie-line constrained import model for the import of 60 MW by System A
from System B becomes 100% reliable. The export/import constrained tie
line model again becomes equivalent to a 100% reliable line with a maximum
power transfer capability of 140 MW. The· unit commitments required to
satisfy the ISR criterion for Systems A and B also remain unchanged. The
actual ISRs of System A and System B become 0.00000065 and 0.00000476
respectively.
Case 2
Consider another situation where the lead time for both systems IS 120
minutes and
79
La 1510 MW , Eab= 70 MW , lab = 0 MW
1430 MW , Eba o MW , Iba = 70 MW
and the export of System A is backed by the entire system. The specifiedSSR and ISR are 0.01 and 0.0001 respectively. The effective loads of
System A and System Bare
1580 MW
and Leb 1360 MW.
The corresponding tie-line model, tie-line constrained import model of
System B and export/import constrained tie-line model are shown in Tables
4.4, 4.5 and 4.6 respectively.
Table 4.4: Tie-Line Model.
Cap. Out Cap. In Cumulative
(MW) (MW) Probability
0 200 1.00000000
100 100 0.00045657
200 0 0.00000005
Table 4.5: Tie Constrained Import Model of System B.
Cap. Out
(MW)Cap. In
(MW)Cumulative
Probability
o70
70
o
1.000000000.00000005
System A and System B must commit 11 and 10 units respectively to satisfy
the SSR and ISR criteria. The corresponding actual ISR of System A is
0.00004874 and of System B is 0.00000135.
80
Table 4.6: Export/Import Constrained Tie-Line Model.
Cap. Out Cap. In Cumulative
(MW) (MW) Probability
0 130 1.00000000100 30 0.00045657130 0 0.00000005
The tie constrained import model of System B is equivalent to a 100%
reliable unit of 70 MW if tie-line failures are neglected. With this ap
proximation, the export/import constrained tie-line model becomes a 100%
reliable line whose maximum power transfer capability is 130 MW. The unit
commitments of both the systems required to satisfy the SSR and the ISR,
when tie-line failures are neglected, remain the same as that when tie-line
failures are considered. The actual ISR with 100% reliable tie lines,
however, becomes 0.00004870 for System A and 0.00000133 for System B.
Some typical unit commitment results with and without considering tie-line
failures are summarised in Table 4.7. It is obvious from Table 4.7 that tie
line failures do not have a significant impact on the unit commitment
schedule. Tie-line failures, therefore, can be neglected in a practical system
study.
4.6.2. Firm purchase backed up by a specific unit
'I'he availability of the export is tied to the availability of a specificunit when the export IS designated as being backed up by that unit. The
probability that the export/import commitment will be fulfilled by the
respective system is taken as unity during the unit commitment in order to
satisfy the SSR. Recognition of the appropriate failures in the export/importmodel, however, is considered during the assessment of the ISR. The
specified SSR and specified ISR are 0.01 and 0.0001 respectively in the fol
lowing numerical examples.
Table 4.7: Unit Commitments (Export is backed up by the en
tire exporting system).
Tie failures Considered Tie Failures Neglected
Load Export Import No. of ISR No. of ISR
(MW) (MW) (MW) Units Units
A B A B A B A B A B A B A B
14501210 0 0 0 0 10 9 0.00000067 0.00000036 10 9 0.00000065 0.00000036
14501210 0 60 60 0 10 9 0.00000067 0.00000480 10 9 0.00000065 0.00000476
13701530 0 0 0 0 10 11 0.00000042 0.00000069 10 11 0.00000042 0.00000067
13701530 70 0 0 70 10 10 0.00003545 0.00004918 10 10 0.00003542 0.00004915
17501770 0 0 0 0 13 13 0.00000254 0.00000263 13 13 0.00000252 0.00000261
17501770 0 80 80 0 12 14 0.00004983 0.00003659 12 14 0.00004978 0.00003653
15101540 0 0 0 0 11 11 0.00000139 0.00000142 11 11 0.00000137 0.00000139
15101540 100 0 0 100 12 10 0.00003501 0.00004826 12 10 0.00003496 0.00004823
00.....
82
Case 1
Consider that the load, export and import in System A and System B
are identical to those shown in Case 1 of Subsection 4.6.1. The effective
loads for the purpose of unit commitment in the individual systems are
1390 MW
and Leb 1270 MW.
The tie-line model for a system lead time of 120 minutes is identical to
that shown in Table 4.4. Usually the unit which backs up the export is
committed before any other unit commitment. In this example, unit #1 of
System B backs up the export of 60 MW. The export model of System B
for the export of 60 MW from System B is shown in Table 4.8.
Table 4.8: Export Model of System B.
Cap. Out
(MW)Cap. In
(MW)Cumulative
Probability
o
6060
o
1.000000000.00060005
The tie-line constrained import model of System A for the import of 60 MW
from System B to System A is shown in Table 4.9.
Table 4.9: Tie Constrained Import Model of System A.
Cap. Out
(MW)Cap. In
(MW)Cumulative
Probability
o
60
60o
1.000000000.00060005
The export/import constrained tie-line model IS shown ill Table 4.10.
83
Table 4.10: Export/Import Constrained Tie-Line Model.
Cap. Out Cap. In Cumulative
(MW) (MW) Probability
0 200 1.00000000
60 140 0.99940027
100 100 0.00045657
160 40 0.00045629
200 0 0.00000005
Unit #1 in System B has a capacity of 200 MW. This unit has ad
ditional capacity of 140 MW beyond the export commitment. This ad
ditional capacity is used for the purpose of spinning reserve and risk assess
ment. System A requires 10 units and System B requires 9 units to satisfy
the SSR of 0.01. In order to satisfy the ISR criterion, System A and
System B are again required to commit 10 and 9 units respectively from
their respective merit order tables. The actual ISR of System A is
0.00000066 and of System B is 0.00000286.
The tie lines can be represented as a 200 MW line with 100%
reliability if the tie-line failures are neglected. The tie-line constrained im
port model and the export/import constrained tie line with 100% reliable
lines are shown in Table 4.11 and 4.12 respectively.
Table 4.11: Tie Constrained Import Model of System A.
Cap. Out
(MW)Cap. In
(MW)Cumulative
Probability
o60
60
o
1.000000000.00060005
The unit commitments of both the systems with tie-line failures
84
Table 4.12: Export/Import Constrained Tie-Line.
Cap. Out
(MW)Cap. In
(MW)Cumulative
Probability
o60
200
140
1.000000000.99940000
neglected are the same as those with the tie-line failures considered. The ac
tual ISR, however, becomes 0.00000064 for System A and 0.00000283 for
System B when tie-line failures are neglected.
Case 2
Consider that the load, export and import of System A and System B
are identical to those shown in Case 2 of Subsection 4.6.1. The effective
loads for the purpose of unit commitment in the individual systems are
1580 MW
and Leb 1360 MW.
The export model, the tie-line constrained import model and the
export/import constrained tie-line model are shown in Tables 4.13, 4.14 and
4.15 respectively.
Table 4.13: Export Model of System A.
Cap. Out
(MW)Cap. In
(MW)Cumulative
Probability
o70
70o
1.000000000.00060000
System A requires 11 units and System B requires 10 units to satisfy
85
Table 4.14: Tie Constrained Import Model of System B.
Cap. Out
(MW)Cap. In
(MW)Cumulative
Probability
o70
70o
1.00000000
0.00060005
the SSR and the ISR criterion. The actual ISR of System A IS 0.00004195
and of System B is 0.00000132.
Table 4.15: Export/Import Constrained Tie-Line Model.
Cap. Out Cap. In Cumulative
(MW) (MW) Probability
0 200 1.0000000070 130 0.99940027
100 100 0.00045657
170 30 0.00045629
200 0 0.00000005
The tie-line constrained import model and the export/import con
strained tie line with tie-line failures neglected are shown in Tables 4.16 and
4.17 respectively.
Table 4.16: Tie Constrained Import Model of System B.
Cap. Out
(MW)Cap. In
(MW)Cumulative
Probability
o70
70o
1.000000000.00060000
The unit commitment in both the systems neglecting tie-line failures
remains the same as it is when tie-line failures are considered. The actual
ISRs when tie-line failures are neglected, however, become 0.00004191 for
86
Table 4.17: Export/Import Constrained Tie-Line Model.
Cap. Out
(MW)Cap. In
(MW)Cumulative
Probability
o70
200
130
1.000000000.99940000
System A and 0.00000129 for System B. Some unit commitment results
with and without considering the tie-line failures are summarised in Table
4.18. It is obvious from Table 4.18 that the tie-line failure have no sig
nificant impact on the unit commitment schedule of System A and
System B. In a practical interconnected system study, the tie-line failures
normally can be neglected. It may be necessary, however, to perform an ex
ploratory study to determine the impact of this approximation on system risk
and unit commitment schedule.
4.7. Effect of Export/Import on the Level of Assistance
The ISR of an interconnected system is influenced by the tie-line con
strained import model and the export/import constrained tie-line model. The
tie-line capacity for the purpose of unit commitment is considered to be fixed
at an average value during a particular time period. The same tie-line
capacity is shared by the export/import and the additional assistance with
respect to the spinning reserve. The tie-capacity left after fulfilling the
scheduled export/import can be used to transfer assistance in the case of a
sudden generation loss or a capacity deficiency due to a sudden load rise in
an interconnected system. The level of assistance that an interconnected sys
tem can provide to its neighbour without committing a breach of
export/import schedule depends on the tie capacity and the scheduled
export/import. Table 4.19 shows the unit commitment and correspondingrisk in System A and System B for a specified SSR of 0.01 and a specifiedISR of 0.0001 and a load level of 1750 MW in both systems. The export of
System A to System B was varied from 80 MW to 180 MW in steps of
Table 4.18: Unit Commitments (Export is backed up by a
specific unit).
Tie failures Considered Tie Failures Neglected
Load Export Import No. of ISR No. of ISR
(MW) (MW) (MW) Units Units
A B A B A B A B A B A B A B
14501210 0 0 0 0 10 9 0.00000067 0.00000036 10 9 0.00000065 0.00000036
14501210 0 60 60 0 10 9 0.00000066 0.00000286 10 9 0.00000064 0.00000283
13701530 0 0 0 0 10 11 0.00000042 0.00000069 10 11 0.00000042 0.00000067
13701530 70 0 0 70 10 10 0.00002692 0.00004921 10 10 0.00002688 0.00004918
17501770 0 0 0 0 13 13 0.00000254 0.00000263 13 13 0.00000252 0.00000261
17501770 0 80 80 0 12 14 0.00004987 0.00002805 12 14 0.00004982 0.00002799
15101540 0 0 0 0 11 11 0.00000139 0.00000142 11 11 0.00000137 0.00000139
15101540 100 0 0 100 12 10 0.00002637 0.00004825 12 10 0.00002632 0.00004822
00'1
88
Table 4.19: Unit Commitment With Export (Export hacked up
by the entire exporting system).
Export Units to Units to ISR
(MW) Satisfy SSR Satisfy ISR
Eab A B A B A B
80 14 12 14 12 0.00000726 0.00004962
100 14 12 14 12 0.00004969 0.00004918
120 14 12 15 12 0.00000234 0.00004826
140 14 12 15 12 0.00003503 0.00004826
160 14 11 15 12 0.00005228 0.00004826180 15 11 16 12 0.00000565 0.00004825
20 MW. The export was backed by the entire system of A. For an export
of 80 MW, the unit commitments in both systems required to satisfy the
ISR are identical to the respective unit commitments to satisfy the SSR. As
the export increases to 160 MW, both systems need one more unit than
their single system commitment to satisfy the ISR criterion. This is due to
the fact that as the export/import through the tie line increases, the level of
potential assistance with respect to the spinning reserve that the tie line can
carry decreases provided that the tie capacity remains constant. A system,
therefore, must commit more capacity than its previous commitment to
satisfy the ISR criterion with an assistance less than that during the pre
vious commitment. Similar results are also shown in Table 4.20. Results in
Table 4.20 were computed for similar conditions to those used in the case of
Table 4.19 other than the designation of export. The export in the case of
Table 4.20 is backed by unit # 1 of System A.
4.8. Summary
The procedure described in this chapter can be used to assess the spin
ning reserve requirements of a multi-area interconnected system configurationwith export/import constraints. The necessary steps required to evaluate the
tie constrained export/import model and the export/import constrained tie
line model are. discussed in detail. The probability of tie line failure can
89
Table 4.20: Unit Commitment With Export (Export backed up
by a specific unit in the exporting system).
Export Units to Units to ISR
(MW) Satisfy SSR Satisfy ISR
Eab A B A B A B
80 14 12 14 12 0.00000524 0.00004961100 14 12 14 12 0.00004104 0.00004921120 14 12 15 12 0.00000104 0.00004983140 14 12 15 12 0.00002636 0.00005056160 14 11 15 12 0.00004278 0.00005725180 15 11 16 12 0.00000361 0.00005725
generally be neglected in the computational process. This should be checked,
however, and may not be valid for all systems. The procedure described in
this chapter utilises a probabilistic risk assessment framework which permitsthe inclusion of those factors that influence the system reliability.
90
5. INTERRUPTIBLE LOADCONSIDERATIONS
5.1. Introduction
A probabilistic assessment of spmnmg reserve and unit commitment
normally utilises the criterion that the unit commitment risk should be less
than or equal to a specified level. In addition to other capacity adjustments,it is also possible to utilise load interruption to maintain the system fre
quency and integrity. During peak load hours it may be necessary to inter
rupt some load in order to keep the unit commitment risk within limit. A
sudden loss of generation can also cause some load to be interrupted on
short notice. The cost associated with interruption may be lower for some
loads than that of other loads, and the consumer may be willing to have
his/her load interrupted, if necessary, provided that there is some economic
benefit. Some power utilities actually consider curtailable load as part of
their spinning/operating reserve [30]. It is generally recognised that selected
load curtailment can be used to reduce system risk. The utilisation of
probabilistic risk assessment techniques can be used to quantitatively assess
the impact of such load curtailment on unit commitment risk [31]. The
magnitude of curtailable load and the corresponding maximum allowable time
delay before which the load should be curtailed to maintain the system risk
level less than or equal to a specified level, can be determined using
probabilistic techniques. Load curtailment should only be considered in the
absence of other possible capacity adjustments.
A certain number of generating units are committed at any time in the
hourly operation of a power system to satisfy the system load at a unit
91
commitment risk equal to or lower than the specified level. Because of the
discrete nature of the generating unit capacity, a system can usually carry
additional load on top of the firm load without committing any more units
than is required to carry the firm load without exceeding the specified risk
level [32]. The additional load capability provides the ability within the sys
tem to respond to unexpected load variations without materially affecting the
unit commitment and the corresponding risk.
5.2. Interruptible Loads in a Single System
The generating capacity that is spinning, synchronised to the bus and
ready to take up load is generally known as spinning reserve. The required
spinning reserve is dependent on the system load, generating unit failure
rates, lead time and allowable risk level. One of the most important
parameters in spinning reserve evaluation is lead time [3, 24], which is the
time period for which no additional capacity can be brought into service. A
generation model in the form of a Capacity Outage Probability Table [3] can
be constructed given that the probabilities associated with the different states
of the generating units for a period equal to the lead time are known. The
unit commitment risk can be found from the Capacity Outage ProbabilityTable given that the load is known [3].
In practice, an operator can use the probabilistic risk assessment
method by adding (committing) one unit at a time from a merit order table
until the unit commitment r�k given by the generation model becomes equalto or less than the acceptable value for the expected load. Consider SystemA with the available generating units shown in Table 3.2. The commitment
order is from the top down and the lead time is considered to be 2 hours.
The specified unit commitment risk in an isolated system is assumed to
be 0.001 for the studies in this section. Table 5.1 illustrates the unit commit
ment and corresponding risk in System A for a load of 1850 MW.
92
Table 5.1: Spinning Capacity, Reserve and Unit Commitment
Risk.
No. of Units Total Spinning Spinning Unit Commitment
Committed Capacity (MW) Reserve (MW) Risk
12 1860 10 0.02217724
13 1980 130 0.01511939
14 2080 230 0.00018157
With 11 committed units the system is unable to meet the load. If
the acceptable risk is 0.001 then the system requires 14 units to carry a load
of 1850 MW and the corresponding spmnmg reserve is 230 MW. Assume
that the load in System A is 2250 MW at a particular time of the day.
Table 5.2 shows the unit commitment and corresponding risk under this con
dition. The commitment of all 18 on-line units does not satisfy the risk
criterion for a load level of 2250 MW at an acceptable risk of 0.001. The
risk in this situation can be alleviated by: 1) bringing in additional generat
mg units before the lead time of ta or 2) curtailing some load if required.
Table 5.2: Unit Commitment and Corresponding Risk.
No. of Units Total Spinning Spinning Unit Commitment
Committed Capacity (MW) Reserve (MW) Risk
16 2280 30 0.0270572017 2355 105 0.01652324
18 2415 165 0.00401203
In a practical system, generating units are committed for a specifiedtime period during which additional generation can be made available after a
time delay. The actual time delay depends on many factors of which the
type of additional generation is the most important. The delay time as
sociated with a thermal generating unit may be in the order of several hours
while the delay times associated with the starting, synchronising and loading
of hydro and gas turbine units are relatively short. The loading characteris-
93
tics of these rapid start units are also quite different from those of conven
tional thermal units although the lead time of thermal units can be reduced
considerably by keeping the boilers in a hot reserve state [2]. Rapid start
and hot reserve units can be utilised to reduce the unit commitment risk.
The concept of area risk curves [3] can be used to include rapid start and
hot reserve units in the risk assessment process. The concept of area risk
curves and the models for hot reserve and rapid start units are discussed in
Chapter 3.
The availability of rapid start and hot reserve units can alleviate the
system unit commitment risk. It is also possible that the system load could
be such that the unit commitment risk criterion cannot be met even after in
cluding all available rapid start and hot reserve units. In this situation, a
suitable segment of the system load can be considered for possible interruption to reduce the unit commitment risk. Load curtailment, however, should
only be considered when other economic capacity adjustments can not be
achieved during the lead time. In this regard, interruptible loads can be
considered as part of the operating reserve. During peak load hours it may
be necessary to interrupt some load in order to keep the unit commitment
risk within limits. A sudden loss of generation may also cause some load to
be interrupted at short notice. The cost associated with interruption may be
lower for some loads than that of other loads, and a consumer may be will
ing to suffer load interruption if necessary, provided there is an economic
benefit. Risk assessment in the presence of interruptible loads can be il
lustrated using the area risk technique [3( Assume that M generating units
are operating and the system load is L MW. A typical area risk curve for
a system with interruptible load is shown in Figure 5.1. At time ti,
Ali MW of load is interrupted and the risk contribution decreases. The risk
level for the entire lead time in this case can be evaluated using similar
techniques to those utilised for rapid start and hot reserve units. In order
to simplify the problem, all M units are considered to be on-line units. In
terruptible load can be considered for computational purposes as a load
94
F(R)
......LOAD INTERRUPTION
(�li MW)
ADDITIONAL___.
UNITS IN
o t·1 TIME
Figure 5.1: Area Risk Curve.
variation or as an equivalent generating unit with a failure rate equal to
zero. Figure 5.2 shows the system load and total spinning capacity when
the interruptible load is considered in the computational technique as a load
variation. Figure 5.3 shows the system load and total spinning capacity
when the same interruptible load is considered as an equivalent generatingunit. Both approaches provide identical results.
A generation system may interrupt some of the designated load if the
unit commitment risk for the period of the lead time is greater than the
specified risk, Rs' Figure 5.4 shows two risk functions for two different loads.
The shaded area in Figure 5.4 represents the reduction of unit commitment
risk due to a load interruption at time ti.Assume that
L is the system load,�li is the interruptible load,F(R1) IS the risk function for a load of (L-�li) MW with M units,
F(R2) is the risk function for a load of L MW with M units.
95
LI--------
SPINNING CAPACITY
MWJl
C�--------------------------------
LOAD .L-.6ol· - -- - - -'------------11
I
I
o-
t TIMEa
Figure 5.2: Equivalent Load Approach For Load Interruption.
I
I. �
-
0 t. t TIME]. a
MWJ•SPINNING CAPACITYC+.6oI· -----------------
1
C ......------
LOADL �----------------------------��
Figure 5.3: Equivalent Unit Approach For Load Interruption.
F(R)
96
t·1
o TIME
Figure 5.4: Area Risk Curves For Two Loads.
Unit commitment risk can be expressed as
when load L .MW and
when load L-Al· .MWt
If Rf > R8' load curtailment is necessary in the absence of other
capacity adjustments. Once it has been decided to interrupt some load, it is•
important to determine the magnitude of the interruptible load and the time
of interruption. In practice, a utility has prior knowledge regarding the
various loads that can be interrupted with minimum penalty. The load with
the least penalty for interruption should be considered first. The time of in
terruption, ti can be determined by solving Equation (5.1) where ti is the
maximum allowable time delay for curtailment of Ali MW. Curtailment of
Ali MW load after time ti will not reduce the unit commitment risk to a
value equal to or lower than the specified risk.
97
(5.1)
or
(5.2)
For computational purposes, Equation (5.1) is solved by an iterative
method with the help of the following sequence.
t . = t·n-1 - nf:l.tt t
where
and
Dot discrete time step.
A course time step can be used as a starting point to roughly identify
the zone where f(t) crosses the time axis in Equation (5.2). A smaller time
step can then be used to finally solve for t i: Solutions for other interrupt
ible loads can be achieved in the same manner. In order to reduce the unit
commitment risk, however, a system must interrupt a minimum amount of
load. This minimum interruptible load at any point varies with the operat
ing variables prevailing at that point of time. An interruptible load which is
at least equal to or greater than the minimum bound at an operating situa
tion, should satisfy the following relationship.
where
98
Dolm - mmimum load that has to be interrupted.
Consider a load of 2090 MW and a lead time of 120 mins. The com
mitment of all 16 units in System A will result in a unit commitment risk
of 0.00279073, which is higher than the allowable risk of 0.001. The min
imum load Dolm, that must be interrupted almost instantaneously to bring
the unit commitment risk below the allowable risk is approximately 11 MW.
A load of 50 MW should be interrupted within 36 minutes in order to keepthe unit commitment risk equal to the allowable risk of 0.001.
Table 5.3 shows some typical unit commitment situations in System A
when interruptible loads are considered as part of the operating reserve.
The system load is again 2090 MW and the allowable risk is 0.001 with a
lead time of 120 mins.
Table 5.3: Typical Unit Commitment Situations.
No. of Spinning Operating Interruption UnitUnits Reserve Reserve Load Time Commitment
Committed (MW) (MW) (MW) (Minutes) Risk
16 190 190 0.0027907316 190 240 50 36 0.00098528
16 190 270 80 39 0.0009937816 190 300 110 40 0.00099580
In Table 5.3, the operating reserve includes spinning reserve and interruptible
load. The 4th row of Table 5.3 shows that System A can carry a load of
2090 MW with a unit commitment risk of 0.00099580 provided that the sys
tem has the option to interrupt 110 MW load within 40 minutes, if neces-
sary.
99
5.3. Additional Load/Interruptible Load CarryingCapability of a System
A generation system can carry additional load on top of the firm load
without committing any additional units than is required to carry the firm
load, if the actual unit commitment risk at the firm load condition is less
than the specified risk, Rs' The shaded area in Figure 5.4 represents the
reduction in risk due to a load interruption at time ti"Assume that
L f is the firm load,6.1
ais the additional load,
F(R1) IS the risk function for a load of Lf MW withM units,
F(R2) is the risk function for a load of L f+6.1a MW with M units.
Based on these assumptions, unit commitment risk can be expressed as
when L=L f and
Rf< Rs' additional load is added in suitable steps. The additional load
can be increased up to the point at which Ra=Rs' If the additional load IS
increased further then Ra > Rs' i.e., the unit commitment risk criterion IS
violated. The unit commitment risk can be reduced even with this increased
additional load if the additional load is capable of being interrupted prior to
tao The time of interruption, ti can be determined by solving Equation
(5.3).
{tiF(R2)dt + {ta F(Rl)dt s n,io itiLoad interruption should only be considered as an operating strategy if other
(5.3)
economic adjustments cannot be done within the system lead time and if
load interruption is permissible.
100
A power system commits a designated number of generating units using
a specified system lead time to satisfy a forecast load at a unit commitment
risk less than or equal to a specified risk. Due to the discrete size of the
generating units, the capacity outage probability table may have some room
for additional load on top of the firm load of the system; without requiring
any additional units to be committed other than those required to satisfy the
firm load. This additional load must not cause the actual unit commitment
risk to exceed the specified risk. The allowable additional load depends on
the firm load of the system, the set of generating units and the specifiedunit commitment risk of the system. The window between the capacity out
age probability table and the firm load of the system may be wide enoughto carry a certain additional load for a period equal to the system lead time,
or the window could be just enough to carry the additional load for a periodless than the system lead time without violating the risk criterion. The ad
ditional load which the system can carryon top of its firm load for a periodless than the system lead time is designated as the allowable interruptibleload. Interruptible load can be added to the system on top of the firm load
without committing any additional generation other than that required to
meet the firm load until the actual unit commitment risk becomes equal to
the specified unit commitment risk. It is of interest to determine the mag
nitude of additional load/interruptible load carrying capability of a system.
This is not a constant value and will vary with the system firm load and
the generating units in operation. The additional load/interruptible load
does not involve any additional unit commitment costs and is serviced at the
production cost. The generating system shown in Table 3.2 is used to il
lustrate this concept. The unit commitment order is from the top down.
In order to determine the additional load carrying capability of the sys
tem, a sufficient number of generating units are first committed to carry the
firm load at an unit commitment risk lower or equal to the specified risk.
If the actual unit commitment risk is equal to the specified risk no further
evaluation is done. In this case, the system will not be able to carry any
101
additional load/interruptible load on top of its firm load at that time. If
the actual risk is less than the specified risk, certain additional load is added
to the firm load and the unit commitment risk is re-evaluated. If the newly
calculated unit commitment risk is less than the specified risk then the sys
tem is able to carry the corresponding additional load on top of the firm
load without adding any additional units. The additional load is increased
gradually until a point is reached where the actual risk becomes equal to the
specified risk. The magnitude of the additional load could be increased fur
ther but the system would not be able to carry that additional load without
committing additional unit(s). The system may be able to carry the same
additional load without requiring additional generation if the time required to
remove the additional load is less than the system lead time. In order to
consider this variable, the magnitude of the additional load IS gradually in
creased and the time period, before which the additional load should be
removed in order to keep the actual risk from exceeding its limit is deter
mined from Equation (5.3). This procedure results in a set of additional
load/interruptible loads and corresponding times which are dependent on the
set of generating units, firm load of the system and the specified risk. The
time period for which the additional load/interruptible load can be carried
by the system, before the system unit commitment risk exceeds its limit, is
called the lead time of the additional load/interruptible load. A set of ad
ditional load/interruptible loads for the generation system shown in Table 3.2
is given in Table 5.4.
Table 5.4 was derived for a firm load of 1850 MW with a system lead
time of 120 minutes and a unit commitment risk of 0.001. The system re
quires 14 committed generating units to carry the firm load of 1850 MW.
The actual unit commitment risk at this point is 0.00018157 and the spin
ning capacity is 2080 MW. The first column of Table 5.4 shows the ad
ditional load/interruptible load that the system is able to carryon top of the
firm load of 1850 MW. The second column shows the lead time of the ad
ditional load/interruptible load in minutes for which the corresponding ad-
102
Table 5.4: Allowable Additional Load/Interruptible Loads andLead Times.
Total spinning capacity = 2080 MW
Int.load(MW) Lead time(mins) Risk
5 120 0.00018157
10 120 0.0001876715 120 0.00018767
20 120 0.00019266
25 120 0.0001926630 37 0.00097904
35 37 0.00097904
40 37 0.0009801145 37 0.00098011
50 25 0.0009722555 25 0.00097225
60 25 0.0009723565 25 0.00097235
70 25 0.0009724175 25 0.0009724180 6 0.00094090
85 6 0.00094090
90 6 0.0009409095 6 0.00094090
100 6 0.00094094105 6 0.00094094
110 5 0.00087274
115 5 0.00087274
120 5 0.00087274125 5 0.00087274130 4 0.00084117135 4 0.00084117
140 4 0.00084117
145 4 0.00084117
150 4 0.00084117
155 4 0.00084117160 4 0.00084118
165 4 0.00084118
170 4 0.00084118
175 4 0.00084118
180 4 0.00084118
185 4 0.00084118
190 4 0.00087449
103
Table 6.4: (continued)
Int.load(MW) Lead time(mins) Risk
195 4 0.00087449
200 3 0.00080628
205 3 0.00080628
210 3 0.00081128
215 3 0.00081128
220 3 0.00081128225 3 0.00081128
ditional load or interruptible load in the first column or an additional
load/interruptible load of magnitude less than that shown in the first column
can be carried by the system, without committing any additional generation
than that committed to carry the firm load of 1850 MW and without violat
ing the unit commitment risk. The third column shows the actual unit com
mitment risk for the system. When the lead time associated with the inter
ruptible load becomes equal to the system lead time, the load (interruptible)becomes the additional load which the system should be able to carry with
out being required to interrupt it. Table 5.4 shows that the generation sys
tem given in Table 3.2 can carry an additional load of 25 MW on top of
the firm load of 1850 MW with an actual unit commitment risk of
0.00019266. Figure 5.5 is a pictorial representation of Table 5.4. The sys
tem can carry the additional load/interruptible load shown by the symbols in
Figure 5.5 and all other. additional load/interruptible loads vertically below
the individual symbols. In Figure 5.5, all symbols are connected to show
the trend in the variation of the lead time associated with different ad
ditional load/interruptible loads. A point on the curve other than the sym
bols is not a valid point unless it lies vertically below a symbol. If the
coordinate of a symbol is (ti ' �li) then the rectangle formed by the points
(0 , 0), (0 , �li)' (ti ' 0) and «. ' �li) represents a valid operating zone as
far as the unit commitment risk is concerned. This condition applies to all
similar figures in this thesis.
Different sets of additional load/interruptible loads exist for different
104
300�-----------------------------------.
3t:E 200.5"'Ca
_gs..: 100-
.s
fIRM LOAD - 1850 MWSPECIfIED RISK - 0.001TOTAL NO. Of UNITS SPINNING - 14TOTAL SPIN. CAPACITY - 2080 MW
O�----..------�----..----�----�----...
o 20 40 60 80
Lead Time in mins.100 120
Figure 5.5: Interruptible Load Carrying Capability at the FirmLoad of 1850 MW.
firm loads. It is difficult to determine a general relationship between the ad
ditional load that a system is able to carry without crossing the risk line
and the different parameters of the generation system. It can be seen from
Figure 5.5 that as the interruptible load magnitude is increased, its lead time
is decreased, i.e. the higher the interruptible load is, the shorter the allow
able time period would be before which the load has to be curtailed in order
to keep the unit commitment risk from growing larger than the specified unit
commitment risk.
5.4. Additional Load/Interruptible Load CarryingCapability for Different System Lead Times
The required spinning reserve is a function of generation, system load,
system lead time and operating risk. A part of this spinning reserve can be
used to carry additional load or additional interruptible load on top of the
firm load without adding any additional units and without violating the risk
criterion. In general the magnitude of the required spinning reserve mcreases
with an increase in system lead time. A generation system with a longer
105
lead time than that of another generation system, therefore, 1S likely to carry
more spinning reserve than the other system, provided the system load and
other parameters are identical in both systems. Theoretically, a generation
system in which the standby capacity can respond without any delay ir
respective of any contingency, does not require spinning reserve. A practical
system can not achieve this responding capability. A system can, however,
have many rapid start units which can be synchronised in a relatively short
time compared to conventional thermal units. A system whose standby
response capability is much faster than that of another system will have
smaller room for additional load or additional interruptible load than its
counterpart provided that they have equal risk criteria.
As the system lead time decreases from 240 minutes to 15 minutes, the
unit commitment mayor may not change for a given system load. Figure5.6 shows the additional load/interruptible load carrying capability of genera
tion System A when the load is 1750 MW and the specified risk is 0.001.
The unit commitment of System A at this load level remained unchanged at
13 units for all values of lead time of 240, 120, 60, 30 and 15 minutes. The
additional load carrying capability of A at a load of 1750 MW with 13 com
mitted units is 25 MW for lead time of 240, 120 and 60 minutes. The ad
ditional load carrying capability increases to 75 MW for lead times of 30 and
15 minutes. If the unit commitment required to carry the load of 1750 MW
remains unchanged at 13 units the unit commitment risk decreases from
0.00064776 to 0.00000258 as the lead time decreases from 240 minutes to 15"
minutes. This reduction in risk level is reflected as increased additional load
carrying capability for lead times of 30 and 15 minutes. The system at the
same generation and loading condition can, however, carry additional inter
ruptible load of 80 MW for 2 minutes when the system lead time is 240
minutes. The interruption of the 80 MW load can be delayed up to 6
minutes for a system lead time of 120 minutes and 7 minutes for system
lead times of 30 and 15 minutes.
106
250�------------------------------------�----------.,
c-
e
4
100 - I �
fIRM LOAD - 1750 MWSPECIfIED RISK - 0.001
.E
200- ,�
150 -
II'
I
LEAD TIME(mi.ns)240120603015
NO. Of UNITS
1313131313
Legend• �_1q_!!,j._'1�.:__
C 120 mLns.
• 60 mi.ns.
o 30 ,!i.ns ':._
A � �ns-=-
·�ifl!50 -
ilt 1:n,-------1---------------------------"-------.�O�--A---&----��.--------._--.U------P_--------�------�-�I , , I
o 50 100 150 200
Lead TIme in mins.250
Figure 5.6: Additional Load Carrying CapabilityLevel of 1750 MW.
at a Load
Figure 5.7 shows the additional load/interruptible load carrying
capability of System A when the firm load is 1900 MW. System A must
commit 15 units for lead times of 240, 120 and 60 minutes and 14 units for
lead times of 30 and 15 minutes to satisfy the specified unit commitment
risk of 0.001. The additional load carrying capability is 75 MW for lead
times of 240, 120 and 60 minutes but reduces to 25 MW for lead times of
30 and 15 minutes. System A can carry an additional interruptible load of
80 MW for 23, 40 and 44 minutes for system lead times of 240, 120 and 60
minutes respectively. The system can not carry any additional load or inter
ruptible load beyond 25 MW when the system lead time is 30 minutes. If
the system lead time is reduced to 15 minutes for the same unit commit
ment and firm load then the actual risk is much less. In this case the sys
tem can carry additional interruptible load of 80 MW with a delay time of 3
minutes.
107
300�----------------------------------------�----------�
.5"0o
..9150
LEAD TIME(m�ns)240120603015
NO. OF' UN ITS
15151514H
Legend• .?.1.q_!'.!-_I!!.:__
[J 120 m�ns.
• 60 m�ns.
o 30 m�ns'!._t:. � �ns�
�-
.5 100
.".-,:;::ItI ! 11I • :�----�".r--�".....�--�--�--�-�-----------------------------------T� I I !
50 I .1 9 io� ! a i i
:o 50 100 150 200 250
Lead Time in mins.
F'IRM LOAD - 1900 MWSPECIF'IED RISK - 0.001
250
� 200:2
Figure 5.7: Additional Load Carrying CapabilityLevel of 1900 MW.
at a Load
5.5. Effect of Firm Load Variation on the Additional
Load/Interruptible Load Carrying Capability
A system will commit a designated number of generating units to carry
a forecast firm load at an actual unit commitment risk equal to or lower
than the specified unit commitment risk. The same system capacity may
also be able to carry some additional load on top of the firm load without
the actual risk exceeding the specified risk. As the additional load increases,
the difference between the actual and specified unit commitment risk
decreases. In the same manner, the system firm load can be increased such
that no further unit addition is required but the actual unit commitment
risk increases to the specified unit commitment risk. As the difference be
tween the actual and specified unit commitment risk decreases, the additional
•
108
load or the interruptible load carrying capability of the system decreases for
the given set of generating units. Figure 5.8 shows the additional
load/interruptible load carrying capability of System A for a system lead
time of 120 minutes. As the firm load increases from 1850 MW to
1870 MW in steps of 10 MW, the additional load or interruptible load mag
nitude decreases. When the firm load becomes 1880 MW , the system needs
an additional generating unit above that required for a firm load of 1850 -
1870 MW. The additional load and the interruptible load carrying capability
of System A is increased compared to that which existed at the firm load of
1870 MW. Once the system commences to operate 15 generating units, one
more than that required for a firm load of 1870 MW, the additional load
and interruptible load carrying capability again starts to decrease from its
new value as the firm load increases. This is shown in Figure 5.9, where
the firm load increases from 1870 MW to 1910 MW III steps of 10 MW.
Similar characteristics occur for other system lead times.
5.6. Daily Additional Load/Interruptible Load CarryingCapability of a Generation System
The magnitude of interruptible load and corresponding lead time
depends on the number of operating units, system unit commitment risk,
firm load and system lead time. It IS not possible, therefore, to determine a
unique additional load/interruptible load which the system will be able to
carry at all times. Different results have been obtained using system lead
times of 240, 120 and 60 mins. If the firm load and the on-line units are
such that the actual unit commitment risk is close to the specified unit com
mitment risk, there is not enough room for additional load/interruptible load.
When the actual unit commitment risk is significantly less than the specified
unit commitment risk, the system may be able to carry some additional
load/interruptible load with different combinations of magnitude and lead
time. The hourly load in a day varies from the low load to the peak load.
The additional load/interruptible load carrying capability of the system with
out committing any additional generation will change in different portions of
300
I � I Legend I
250-
�200-
::Ec.-
"'00 150-
.9c-
.£100-
50-
I-'o<0
I
,.?�·�1��?•
to- --...PJ:
Ii.--------------- .¢--------m.-- ..-�---.
.---------. 0
Q----A.r.tt .------------------------------------------------- •
�----------------------------�tt----------•
o0 20 40 60 80 100 120
Lead Time in mins.
• JJ!�Q_!!.lLl'_J�t!l1.�o 18§!Lll!L 14J!N ITS
tt 187'1 MW_14 �NIT�o �8CLMW_!5 �ITI
TOTAL SPIN. CAP. - 2080 MW (14 UNITS)TOTAL SPIN. CAP. - 2180 MW (15 UNITS)
16-
-1----- __- �------
I
J
Figure 5.8: Effect of Firm Load Variation on Additional Load
Carrying Capability.
�200
�e.-
"'013 150
.3..:-
.E100
300��----------------------------------------------P-------------�
250
......
......o
TOTAL SPIN. CAP. - 2080 MW (14 UNITS)TOTAL SPIN. CAP. - 2180 MW (15 UNITS)
Legend• J_8.zQ_nli_H__lJ�11.�[J 18!!QJ:!!L15_!!NITS• 189Q MW)5 lJNIT�o 190Q_MW_l5 _!!N ITS
A 1910 MW 15 UNITS
III
·...,--------i:.__
...-----
.cr - - -
IA . -_
--1-Ii .-__ .
� c?-- -
.
-------------------,----------
• A .----------_
T.
�---------------•
.--------------- .IIII
.---------.•.
.------------------------------------------------------------------------.o
0 20 40 60 80 100 120
Lead Time in mins.
50
Figure 5.9: Effect of Firm Load Variation on Additional Load
Carrying Capability.
111
the day. The IEEE - RTS [33] load model has been used to illustrate the
variability of the additional load/interruptible load carrying capability in a
day. One week in the winter was taken from the IEEE - RTS load model.
The hourly peak load variations for the week are shown in Figures 5.10.
The number of generating units, spinning capacity and the set of additional
load/interruptible loads was determined in each day for three distinct load
zones for the generating System A.
The weakly peak load is assumed to be 1920 MW. The hourly peak
load variation for the 7 day period shows a common characteristic of two
peaks and one valley in each day. The peaks and valley for the 7 day
period are shown in Table 5.5. The additional load/interruptible load car
rying capabilities were determined for a system lead time of 120 minutes.
•
The two peaks and one valley from the load model in a day were con
sidered for unit commitment. During the intervals when load varies from
one peak to another peak or peak to valley, generating units are either
gradually committed to service or taken out of service. Within these inter
vals, a system can handle the additional load simply by committing some
units earlier than the planned schedule when the firm load is increasing, or
by keeping some units on line for a greater period than they were planned
for as long as the unit commitment risk criterion is met. During these in
tervals, additional load can be handled by adjusting the- unit commitments,
and therefore do not jeopardise the system's ability to carry additional load .
Unit commitments during the peaks and valleys can therefore be considered
in order to evaluate the additional load/interruptible load carrying capability
of the system. It is assumed that other capacity adjustments cannot be
done before the time period equal to the system lead time. The additional
load/interruptible load carrying capability of the system varies from peak to
peak and from peak to valley in a given day. The minimum additional
load/interruptible load carrying capability for the two peaks and one valley
situation is considered to be the additional load/interruptible load carrying
'XCJ
l"'"::siu
-I
100 I. . . .
I· . . .
· . . .
· . . .
· . . .
· . . .
i-' ! i •••,!90 -f•••••••••••••••, ···········'···7·.. ···•·• ••..••.....••..
i /. 1•• ••• l\
· . . ..: : : :
�· . . .
· . . .
10 -f•••••••••••••••,•••••••.•.•••••••••.•••••••••••••••••••••••••••••••••••••••••
! I �ONOA� j.70 -f••.••.•••••••••,.... • ••.•••4••••••••••••••••••••••••••••••4••••••\••••••
I;..· I I 1·\• i i j !&0 .;.t...,.···· ..···i.. ·· ...········.. ·i·······....······i······· .. ·······i····· .. ·····
•.•• j. ! ! i
. . .
50: ! : :
o
100 : : : •• :
�::: . '\:
oX 1 •••••• l I •CJ :: .:\e 90 .••.•........••, .•.•.•••.t , I!' ,••.•••••...••
Cl. ! iii� .•... \....
.....
::si 1 Ii: i.e 80 , .•.•.••+
\.
-I � WEDNESDAY !l; 70 i··Z·-:········i
i i �\.
· ." . '.
� . : : : :'-' " ! ! ! !" ..: : : : .
.sDI.
r······.·i! ···_··-:--········T-·······..
r···.. ·····
.' . . .
· . . .
· . . .
· . . .
50 iii io 5 ro � �
TIme in hrs.
-o
�.........
"CJ
.s
5 10 �
TIme in hrs.
2520 25
roo • • ••••.· . . ,.
� i •••••• i I •oX ::..:\CJ : I: . :.u 90 , ····,···············:············.. ·t· •••••••••••
0.. ; i 1 ! \>-. i·! i !::si i! iii·i 10 ·····....
·····T···: ····TU·ESO·Ay···..
······r····'··....
-
it··!·o 70 .••• ·.·1· .. • 1 4 ,••
: : : :
� . : : : :
'-' ,,: : : :
" .., i : ! : •
CJ 60 Ii •...........! ! ! .
a.:::
..J:::::. : : :· . . .
50: : : :
o
loai ! ! !
�.. .....
..x ::: ,:
CJ ! •••••• ! I •
e 90 ·····•· ..
······,··········7··t···· • • ···········t�·············
0.. !!: i."'" !!! t ! \- .•..
, .
�. '" . .
., 10 · .......•······i··.·····,······j············..·i··.. · .. ··.·····i···· •........
! ! / T�URSD�Y I \o 70 •.••••.••••••••1••
1.. · 4 ,••••••••••••·.·,·•••• ••• .
: : : :
\. ::::!S, • : : : :
· . . .
-0' , : : : :
CJ 60· ...•: ..•.... !.. . ! ! ! .
.9 I· -r iii I50 iii io 5 ro � �
TIme in hrs.
.....
.....�
255 10 �
TIme in hrs.20 25
Figure 5.10: Hourly Peak Load Variation of One Week in the
Winter of the IEEE - RTS Load Model.
�D
�>..
::xI)
�'0�.....,
"CJD
..9
100 . • •
�i • • ••• !· . .. ,.
904···············1···········••••••.i .. ·/.···.····· •..·.··.·······
: /:.. :\
: : : :.· . . .
\: : ! :10 4 · ······,········.·.. ··, ·· ·,·.. ····.. · .. · .. ,···· .
j I �RIDA� I·70 4 · ···,· .. · � " 1 � "
i / iii .\. : : : :· . . .
60 .-:..'.........1··· ····.. ··· ..�··.. ·······....�........·······i···.. · .... ·
•.: : : :
•••• l 1 !· . . .
· .. . .
50: : : :
o
10 : : : :
'i j SATURDAY r-;II :.. , : ••Q.. 70 ! ! ! ·· .. ·· .. l·.. ·
\..
� i· •••' ! •� . /! . .
\... ....· . . .
!. 1 ! ! ! •W'
• • • • • •
3t 60 -I.• • .. ·•.. ·· .. :.. · ......
7····l .. · ...... · .. ···!· .. ·· ..··....·-!·.. • .. · .. · ....
\.. . .
.. . . .
: : : :.. . . .
· . . .
'.. ! /. i i· i••••
• •
504···· .. · .. ·· .' •........! : ! ..
. . .
· . . .· . . .
! � i j40
: : : :
o 5 W � �
TIme in hrs.
'0�.._.,
'8...9
5 20 Z52510 �
TIme in hrs.
10
j i j !: 1 : •• :
1 : 1 /. •
701: : .: 1:. .. ..
: :.:.:.>- ::. - :, : \
::x !.. Ii. ! •I) : I: . : \.,. ::::.... . . . .
.� 10 I ' : : :•••••••••••••••:............ •
'. ! / SUNDAY !'. ! ,.: : i
"CJ 50 • ':"i •·.. ·· .. ·l ' r
· .. · l·
a -:::
..9::::· .. . .
· . . .
: i : :40
.
: : : :
o
�D
�I-'......w
'0�.......
·
5I
20 25
Figure 5.10:
I I
10 �
TIme in hrs.
(continued) Hourly Peak Load Variation of One Week m
the Winter of the IEEE - RTS Load Model.
114
Table 5.5: One Week In The Winter Of The IEEE - RTS LoadModel.
MondayTuesdayWednesdayThursdayFridaySaturdaySunday
Valley (MW) Peak 1 (MW) Peak 2 (MW)
1056 1728 1786
1152 1862 1920
1131 1824 1882
1114 1786 1843
1075 1728 1824
960 1344 1496
960 1306 1440
capability of the day. Figure 5.11 shows the additional load/interruptibleload that System A is able to carry on a day without having to commit any
additional unit(s) than those required to satisfy the firm load and without
violating the system unit commitment Tisk criterion. It should be noted that
the actual unit commitment 'risk, corresponding to the points denoted by the
symbols shown in Figure 5.11 and all points vertically below the symbols, is
either equal to or less than the specified unit commitment risk.
The mmimum additional load/interruptible load carrying capability
resulting from 14 peaks and 7 valleys in the 7 day period can be considered
as the additional load/interruptible load carrying capability of the system on
a weekly basis. It is important for the system manager to know what an
additional load/interruptible load will cost the system in terms of capacity
cost, or more simply whether such load should be supported by an ad
ditional operating unit. Table S.6 and Table 5.7 show whether additional
generation is required to carry a given interruptible load on top of the firm
load for a specified lead time.
Table 5.6 shows that if the interruptible load is 60 MW with 30
minutes lead time then additional units would have to be committed 6 times
for the 21 load zones. Table 5.7 shows this requirement would drop to 4
times if the interruptible load is 40 MW. If the additional interruptible load
�:2 200.5
s..9� 100
£
�:2 200.5
-g..9c 100...
..5
300------�----�----�----�----�----�
•I
•
� i . . . ... , � + : � + .
• l l l l :
� I 'I MONDAY I I,! ! ! i i
.. •=.......;.... ·······�·········· .. i····· .. ·····f·············�···· .. ··· ...
: I: : : :: .__. : : :
� . : : :
: ::: �: : i i •• f'"
0: :::,o 20 40 60 80 100 120
TIme in mins.
3..
!.: : :
· . .
I: : : I •..., ······i············t············t·· .. ·········i············t······ .. ·····
-' . . . .
: l WEDNESDAY I. . .
.. . . . .• • • • f
I• • • • •• • • • I
....• ·····i···· .. ··· .. ··�···· .. ······j·· .. · .. ·····i· .. ·· .. ··· ..-t··· .
• I • • • •
---1--. i ! i i: I: : : :
� .-;. iiil l. ::.•• •• I
o:: ::
'"o 20 40 60 80 100 120
TIme in mins.
3••
I"
"I... ..... .,... "
,. ... .... ..., '".... ..... • I., ...., ..... "... "... ..
•••........ J � : -!. ..
I ., ••.. "
....:: ::_... ....
: I:
TUESDAY: II. . . . •.... •• • f· .. ••••• .. · .. ··-:-···· • .. •·• .. t .. •• .. ••••• ·f •• ? .
I' . . . .
.: : : : :· . . .. .• • • • I
.�.: : : :
l Iii i 1: .---+. : : :
I: :.
. : :•o iii I I I
o 20 40 60 80 100 120
TIme in mins.
:=� 200.�"tJ"
..9c 100...
..5
3.. .
.
.
. I. . . , . .
I : : : : :
.: : : : :· . . . .
.- : .:. � : � .
T : : : : :. : . . . :
• l THURSDAY 1I • • • I •
• • • I • •· , . . .
_. • I • •
.. ··J········i .. ···········,.;.·········· .. ·.············i·· -t •..•••.•••••.---i-.: : : :
: I : : : :
i •__ .' i i !: . . . .
.! •
o:
'"o 20 40 60 80 100 120
TIme in mins.
I-'I-'�
:=:2 200.5
-g..9� 100-
..5
Figure 5.11: Daily Additional Interruptible Load CarryingCapability of System A.
300, .
� I• i ii i :.
I: : : :
�
1.iii i i;;> _ I 0 • • ,
. . . . . .::::::Ii! 200 ' •........ � .:. 01 •••••••••••• :•••••••••••• .:. .
C.: : : : :
.- .: : : : :
�! ! PRIDAY ! I•: : 0 : :
· . . . .
•• • • I •· . . . .
100-4".�•.......j. •••••••••••• j •••••••••••• .j .j. ••••••••••••: I: : : :: .__. : : :
i • : : :
: :: : �: :! :.· .. ..
o: :: :,
o 20 .0 60 eo 100 120
TIme in mins.
�
1i • • •
::::::IE 200 ......•...... ; : ; : .
C I: : : :
.- •• l : : l
-� 1 SUNDAY 1.' : : : :
. . . .
100 -4 ...........•. j i ; i .
.' : : : :. . . .
I : : : :
.: : : :••
•
: : I : :i i .: :.: : : :.---1
10 20 30 .0 50
."a
.9cC
."a
.s..:+-
J:
300,_----��----�------�----�------,
o_o
TIme in mins.
300 , ,
•� I, • i>- ... : : : • i
:2 200 ·····':.····i············+············f············�···· + ..
C I' , , . ,. . , . .
.- .:. . . :
� +! SATURDAY !.9 •: . . . :
. . . . ,
,: :.: : :
100 .....•� + i · ·� + ..
: I: : : :
i --+. i � i: :. :
. .
.iii Ii: :: .
o' "
IIIo 20 .0 60 eo 100 120
TIme in mins.
�
....
....0)
Figure 5,11: (continued) Daily Additional Interruptible Load CarryingCapability of System A.
117
Table 5.6: Additional Unit Requirements.
System lead time = 120 mins.Intr. load = 60 MW, lead time = 30 mins.
Valley Peak 1 Peak 2
Monday No No No
Tuesday Yes Yes No
Wednesday Yes No No
Thursday No No Yes
Friday No No No
Saturday No No No
Sunday No Yes Yes
Table 5.7: Additional Unit Requirements.
System lead time = 120 mins.Intr. load = 40 MW, lead time = 30 mins.
Valley Peak 1 Peak 2
Monday No No No
Tuesday Yes Yes No
Wednesday No No No
Thursday No No No
Friday No No No
Saturday No No No
Sunday No Yes Yes
IS 20 MW with a lead time of 42 minutes then no additional units are re
quired to be committed during the weekly period. In this example the ad
ditional load/interruptible load carrying capability on Sunday is the lowest
during the week and, therefore, determines the maximum additional
load/interruptible load carrying capability of the period.
118
5.7. Interruptible Loads in an Interconnected System
Unit commitment and spinning reserve assessment in interconnected sys
tems using the 'Two Risks Concept' is discussed in detail in Chapter 3 and
in Reference [26]. Unit commitment risk of a system can be reduced if part
of the system load is interruptible. Risk evaluation in an interconnected sys
tem with load interruption capability can be illustrated using the area risk
curve technique [3]. Consider Systems A and B as interconnected throughtwo tie lines and that each tie line has 100 MW of power transfer capabilityand a failure rate of one failure per year. The system lead time of both the
systems is assumed to be 120 minutes. Typical area risk curves for isolated
and interconnected system operation are shown in Figure 5.12
Hot reserve and rapid starting units are not included for the sake of
simplicity in the example shown in Figure 5.12. The area risk curve of the
interconnected system shows that the risk function is subdivided into several
time intervals based on the instant of load interruption in System A and
System B and the system lead time of System A and System B. In situa-"
tions where rapid starting and hot reserve units are available, the number of
subinterval will increase. The risk can be calculated using a similar tech
nique to that used in the isolated system. The risk calculated from the risk
function as shown in Figure 5.12 will depend on the magnitude and instant
of load interruption. The ISR of System A and System B with load inter
ruption can be expressed as following:
(5.4)
F(A)
F(B)r---_
119
(Alia MW)
ADDITIONAL _.UNITS IN
o taa TIME
�- LOAD INTERRUPTION (Alib MW)
o TIME
o
Figure 5.12: Area Risk Curves for Isolated and Interconnected
System Operation.
120
Similarly
(5.5)
In order to satisfy the ISR criterion, both Ria and Rib should be equalto or less than the specified ISR, Ri. Equations (5.4) and (5.5) can be
satisfied by adjusting the four variables Lia, Lib' tia and tib. This will
produce an infinite number of solutions. The magnitude and maximum al
lowable time delay of load interruption in one system can be derived if the
magnitude and maximum allowable time delay of load interruption in
another system is known. This will give a suitable starting point for a trial
solution leading to a desirable solution.
The levels of SSR and ISR largely influence the unit commitment in an
interconnected system. The levels of SSR and ISR could be such that the
unit commitment which just satisfies the SSR is also capable of satisfyingthe ISR for a range of loads as discussed in Section 3.2.1 of Chapter 3. In
this situation, the SSR is dominant over the ISR as far as spinning reserve
and unit commitment is concerned. Depending upon the level of SSR and
ISR, ISR can be dominant over SSR for a range of system loads. With
dominant SSR the objective of load interruption is to satisfy the specifiedSSR i.e., to satisfy the risk criterion in an isolated system. Once the SSR
criterion is satisfied, the corresponding ISR criterion will also be satisfied in
the case of a dominant SSR. Load interruption in an isolated system is al
ready explained in the previous sections of this chapter. With dominant
ISR, however, the objective of load interruption is to satisfy the ISR
criterion provided the SSR criterion is already satisfied.
121
Consider System A and System B each with identical generating units
as shown in Table 3.2 in Chapter 3. The SSR for both systems is 0.01 and
the specified ISR is 0.00001. System A must commit 16 units and System B
15 units for a load of 2100 MW in A and 1950 MW in B. The intercon
nected unit commitment risks in A and B for this operating condition are
0.00000915 and 0.00000360 respectively. The interconnected unit commitment
risk of System A becomes 0.00002320 with 16 committed units and the cor
responding unit commitment risk of System B becomes 0.00001958 with 15
committed units if the load in System B increases to 1980 MW with the
load in System A remaining at 2100 MW. System A is unable to satisfy its
ISR criterion and it has a higher ISR than System B even after committing
all the available 16 units. System A is therefore responsible for committing
additional unit(s). In the absence of any additional unit(s) System A can
consider curtailment of its interruptible load in order to satisfy the ISR
criterion. The magnitude and the corresponding maximum allowable time
delay of load interruption in System A can be determined using a similar
approach to that used in the case of an isolated system. In the case of in
terconnected systems, however, the assistance from neighbours is included In
the risk assessment process. A computer program has been developed to
compute the magnitude and the corresponding maximum allowable time delay
for load interruption in interconnected systems, if such interruption is neces
sary. System A can satisfy the ISR criterion for a load of 2100 MW by
committing all 16 available units provided it can interrupt 25 MW of load
within 67 minutes. System B IS required to commit 15 generating units to
satisfy its load of 1980 MW. The corresponding ISR of System A and B
are 0.00000955 and 0.00000987 respectively.
Interruptible loads can be included in the unit commitment process in
interconnected systems using the area risk technique. Table 5.8 shows the
units that must be committed in System A and System B when both sys
tems are capable of interrupting 30 MW load within 20 minutes. The
specified SSR is 0.01 and the ISR is 0.00001.
..-----------------------------------------------�-------- __ -
Tsble 5.8: Unit Commitment with Interruptible Load.
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW)
A B A B A B A B A B A B
1800 1300 13 9 1980 1510 13 9 1980 1510 0.00000260 0.00000158
1800 1350 13 9 1980 1510 13 10 1980 1660 0.00000093 0.00000012
1800 1400 13 10 1980 1660 13 10 1980 1660 0.00000156 0.00000093
1800 1450 13 10 1980 1660 13 10 1980 1660 0.00000280 0.00000210
1800 1500 13 10 1980 1660 13 11 1980 1760 0.00000156 0.00000094
1800 1550 13 11 1980 1760 13 11 1980 1760 0.00000284 0.00000221
1760 13 0.00000157I-'
1800 1600 13 11 1980 12 1980 1860 0.00000095 �l�
1800 1650 13 12 1980 1860 13 12 1980 1860 0.00000287 0.00000232
1800 1700 13 12 1980 1860 13 13 1980 1980 0.00000106 0.00000031
1800 1750 13 13 1980 1980 13 13 1980 1980 0.00000193 0.00000145
1800 1800 13 13 1980 1980 13 13 1980 1980 0.00000357 0.00000357
1800 1850 13 13 1980 1980 13 14 1980 2080 0.00000194 0.00000147
1800 1900 13 14 1980 2080 13 14 1980 2080 0.00000363 0.00000376
1800 1950 13 14 1980 2080 13 15 1980 2180 0.00000195 0.00000150
1800 2000 13 15 1980 2180 13 15 1980 2180 0.00000369 0.00000396
123
5.8. Interruptible Load Carrying Capability of
Interconnected Systems
If the actual ISR of an interconnected power system is less than the
specified ISR, the system can carry some additional load/interruptible load
on top of the firm load without committing any additional unit(s) other than
those required to carry the firm load. The factors which affect the ad
ditional load/ interruptible load carrying capability of an isolated system also
affect the additional load/interruptible load carrying capability of an intercon
nected system. In addition, the additional load/interruptible load carrying
capability of an interconnected system also depends on the assistance from
neighbouring systems. In the determination of the additional
load/interruptible load carrying capability of an interconnected system, the
unit commitments required to carry the firm loads of all the systems inter
connected together are not modified until the firm loads change. A set of
additional load/interruptible load and the corresponding lead time of an in
terconnected system can be derived using a similar method to that employed
for isolated systems given that the firm load and additional load/interruptibleload of the neighbouring systems are known. Any change in the additional
load/ interruptible load of the neighbouring systems will change the ad
ditional load/interruptible load carrying capability of an interconnected sys
tem. There could therefore be many solution sets depending upon the ad
ditional load/ interruptible load conditions within the neighbouring systems.
The solution technique is discussed in detail in Appendix A.
A computer program has been developed to evaluate the additional
load/interruptible load carrying capability of an interconnected system. The
interconnected systems A and B noted earlier have been used to illustrate
the application. Figure 5.13 shows the additional load/interruptible load car
rying capability of System B when the firm load of System B is 1640 MW
and the firm load of System A is 1870 MW. The SSR and ISR are con
sidered to be 0.01 and 0.00001 respectively. Additional load/interruptibleloads of System B are plotted for additional load/interruptible loads of 15,
124
35 and 65 MW with interruption times of 50, 30 and 15 minutes respectively
in System A. Figure 5.13 also showi a base curve with no additional
load/interruptible load in System A. The system lead time for both systems
is 120 minutes. The additional load/interruptible load that an interconnected
system can carry does not require any additional committed capacity other
than that required to satisfy the firm load. This additional
load/interruptible load, however, affects the actual ISR of the interconnected
system and the ISR of its neighbours. The ability of an interconnected sys
tem to carry an additional load/interruptible load can extend up to the
point where its actual ISR becomes equal to the ISR of anyone of its neigh
bours. The overall additional load/interruptible load carrying capability of
all the member systems of an interconnected pool can give the system
planner/operator an appreciation of the additional interruptible load that the
pool can carry at all time or at a specific operating point without having to
commit any additional capacity.
5.9. Summary
Probabilistic techniques to include load curtailment ill the operating
reserve assessment of isolated and interconnected systems are discussed in
this chapter. Interruptible loads can be included in a system probabilisticrisk assessment using the area risk technique. Probabilistic methods can be
used to provide a consistent approach to evaluating load interruptibility and
its effects on the unit commitment risk of both isolated and interconnected
system. These techniques are used in this chapter to evaluate the magnitude
and corresponding maximum allowable time delay for load interruption re
quired to reduce the unit commitment risk in the absence of other capacity
adjustments. Load interruptions, however, should be considered in conjunc
tion with other economic adjustments.
A generation system can carry an additional load or an additional in
terruptible load on top of its firm load without committing any additional
generation above that required to carry its firm load. This capability
250,-------------------------------------�---------------
. -----------... ----------------.
.-------.
Io
•
o 20 40 60 80 100 120
Lead Time in mins.
·200-
�� 150-c
......
"'C0
.s. 100-L.
-+-C
50-
•
i. _-
..
11._.
L�._-
..
�r.-=-0__••I
�= _..
.
o.; th.::.:-::.:'0-------.
-.-
fIRM LOAD IN SYSTEM A - 1870 MWfIRM LOAD IN SYSTEM B - 1640 MW
Legend• 9__���__q_T�_�!: __L_�_� _
o 15___!j!iz._§Q_mL�:....Ln J!• 35 _1'!!iz..._;!��_'2!.:..__
Ln J:t•o § � !.§ �ns.!.-LI}_A
Figure 5.13: Additional Interruptible Load Carrying Capabilityin System B .
..
i-'t>.:)�l
126
depends on the operating set of generating units, the firm load and the
specified unit commitment risk. In addition to these factors, the additional
load/additional interruptible load carrying capability of an interconnected sys
tem also depends upon related conditions within the neighbouring systems.
A probabilistic technique which can be used to evaluate the inherent inter
ruptible load carrying capability of isolated and interconnected generating
systems without having to commit any extra unit(s) other than those re
quired to carry the firm load is also presented in this chapter.
The additional load/interruptible load that an isolated or an intercon
nected system can carry in addition to a given firm load, without violating
the specified risk, is not a unique quantity. There IS at any moment,
however, a unique set of additional load/interruptible loads and associated
lead times. This set will change for different generating unit combinations
even if the firm load and specified unit commitment risk remain unchanged.
127
6. UNIT COMMITMENT
6.1. Introduction
The load in a practical power system changes continuously and it is
not economical to run all the units required to satisfy the peak load during
the low loads. Depending upon the load levels, some units are put into ser
vice at one time and may be removed. from service at another time of the
day. The units in the various segments of a scheduling period should be
committed in such a way that the operating cost is minimised with a satis
factory level of reliability. There are many generating unit factors which af
fect the unit commitment. They are in general, fuel price, heat rate curve,
start up cost, unit failure rate and the time delay associated with starting,
synchronising and loading.
Assessment of spinning reserve is an integral part of unit commitment.
The unit commitment should be such that the unit commitment risk is less
than or equal to a specified level. In an interconnected system, the unit
commitment should satisfy two risk levels, namely single system risk (SSR)and interconnected system risk (ISR) as discussed in the previous chapters.
Once the unit commitment risk levels are satisfied, the spinning capacity in
excess of the system load is the spinning reserve available at that point of
time. The unit commitment technique in interconnected systems at a con
stant load level has been explained in Chapter 3. The inclusion of hot
reserve units, rapid start units and interruptible load to reduce unit commit
ment risk has also been discussed in Chapters 3 and 5. The application of
the 'Two Risks Concept' to unit commitment for a continually changing load
is considered in this chapter.
128
A number of methods for unit commitment have been published. The
majority of these methods deal with economic optimisation of unit
scheduling [6, 8, 9, 10, 11, 15, 16]. Economic starting and stopping of
generating units has been considered in Reference [91. Some of the published
material utilises mathematical programming in order to minimise running
cost [8, 12, 14, 34]. The use of a unit priority list has also been
suggested [9]. Relatively little work has been done on the application of
quantitative reliability concepts to unit commitment [4, 17, 24, 26, 35]. The
reliability methods presented are basically for isolated systems and become
impractical with a large number of operating units with back up units
having variable start-up times [17, 35].
This chapter presents a probabilistic technique which applies quantitative reliability assessment to unit commitment and spinning reserve evalua
tion. The proposed method suggests that the unit commitment of an inter
connected system in each scheduling period should be such that two different
risk levels; SSR at the isolated system level and ISR at the interconnected
system level are satisfied. If an interconnected system is unable to satisfy its
SSR or ISR during a scheduling period, it should bring more generation into
service or it should buy energy from its neighbours.
Generating units used in a previous scheduling period can still be in a
hot reserve state and can be brought into service in a relatively short period
of time depending upon the length of time these units are out of service.
Hydro and rapid start gas turbine units can be started and put into service
in the order of 5 to 10 minutes. In the absence of other potential capacity
adjustments, the presence of interruptible loads can reduce the unit commit
ment risk. These aspects can be included in the assessment of unit commit
ment risk and are discussed in Chapters 3 and 5. It has been assumed in
the following sections for the sake of simplicity that the thermal units once
taken out of service are not maintained in a hot reserve state.
129
6.2. Loading Order
A priority unit loading order can be prepared based on economic and
system operating factors. The priority list approach to unit commitment is
used by many utilities. The principle advantages of this technique are that
it is simple, straightforward and can be applied to systems with a large
number of units. As the load increases, individual units are committed ac
cording to a pre-determined priority order. Units are removed from service
as the load decreases using the reverse priority order. Different utilities use
different approaches to prepare their priority order of unit commitment. The
approach used by the Texas Electric Service Company to prepare the unit
commitment priority list is presented in Reference [6] and utilises Equation
(6.1).
c·• (6.1)
where
Ci relative operating cost of unit I at the point of maximum
efficiency - $ /MWH
Hi most efficient heat rate of unit t - BTU /MWH
Fi = fuel cost of unit i - $/BTU
PG i= generation of unit i at the point of maximum efficiency
- MW
• minimum expected run time of unit l before cycling - hours
Si start up cost of unit z - $
A priority unit order list should in general reflect the long term
economic objectives of the utility in question.
The operating cost of hydro units are usually far lower than the
operating cost of thermal units and hydro units are generally considered first
130
for commitment where there is sufficient water. Limited storage hydro units,
however, are often used for peak shaving purposes. The time delays as
sociated with starting, synchronising and loading hydro units are in the order
of 5 to 10 minutes and therefore some hydro units are retained as standby
units. Run of the river hydro units which can not be operated due to low
water conditions do not serve any standby generation purpose.
The area frequency and tie line regulation requirements of a system
must be satisfied. Hydro, gas turbine and gas engines can respond to load
changes at a faster rate than conventional thermal units. Some of these fast
acting units should be committed to satisfy local area constraints if the
responding capability of the operating thermal and/or nuclear units are not
satisfactory. The available hydro, gas turbine and gas engines not com
mitted during a particular period act as ready reserve for that period.
6.3. Start-Up Cost
There is a cost associated with starting a thermal unit. The cost
depends on the duration of time since the unit last operated. The start-up
cost of a thermal unit can be expressed as 19]
where
s(t) = unit start-up fuel cost at time t,"
So = unit cold start-up cost,
a cooling rate of the unit,
T shut down hour of the unit.
The shut down time of all units are usually recorded. The unit start
up cost over a scheduling period can be calculated knowing the cold start-up
cost and the cooling rate of the units. The start-up costs of hydro units are
131
negligible compared to those of thermal units and can be considered to be
zero for all practical purposes.
6.4. Dynamic Programming
Optimisation of non-linear functions with n decision variables can be
achieved using dynamic programming [36, 37, 38]. A dynamic programmmg
method applied to unit commitment was presented in 1966 [8]. The method
replaces the problem of finding optimum outputs of the various units for a
given load with the problem of finding optimum outputs of the various units
for all load levels between minimum and maximum output of the units. The
optimum way of operating N units can be found once the optimum way of
operating N-l units is known.
The dynamic programmmg starts with a single unit. The input-output
curves of all the units must be known. With only one unit available, the
input in dollars per hour as a function of output in megawatts can be deter
mined from the input-output curve of the unit. The curve is defined from
the minimum to the maximum output of the unit. With two units avail
able, a curve of input in dollars per hour as a function of output in
megawatts can be obtained from the input-output curves of these units. The
combined input-output curve will be defined from the minimum to the max
imum output of the two units. At each load level between the mmunum
and maximum output of the two units, the load will be shared by each unit
in such a way that the input in dollars per hour becomes minimum. Based
on the combined input-output curve of two units a combined input-output
curve of three units can be obtained. Similarly the procedure is extended to
obtain the combined cost curve for all the available units.
Assume that
minimum running cost of carrying z MW load on N
generating units,
132
cost of carrying xi MW load on the ith unit.
The output of an individual unit is constrained by its mmimum and
maximum output as follows:
U· < z . < v·t t - t
where
Ui = minimum output of unit i in MW,
Vi = maximum output of unit i in MW.
The total output z is constrained as
where
gN = Min{u1 ,u2 ' ... ,uN}N
hN = LVii=1
The mmimum runmng cost for a total output of z MW IS:
subject to the following conditions .
•
gN < z-/ < hN-1-1 -
where
N-l
i=l
The maximum output of a unit can be the rated capacity of that
133
unit. The minimum output of a unit can be considered to be some value
or zero whichever is applicable.
6.5. Scheduling Using the 'Two Risks Concept'
The reliability constraints are first satisfied in this approach. The
number of units required to be committed in an interconnected system are
determined first from a table of loading order priorities for the respective
systems. The unit commitment should be such that it satisfies the SSR and
ISR criteria. Hot reserve and rapid start units are included in the unit
commitment process using the area risk technique. The number of units re
quired in each interconnected system is determined in this manner for each
commitment period.
After the reliability constraints are satisfied, a tentative unit loading
schedule in each commitment period is prepared using dynamic programming
to assess the hourly running cost. The cost curve Yi In dollars per hour as
a function of the output xi in' MW for thermal units is approximated by a
second order function as shown below.
Yo = a 0 + b .z 0 + c ox2 0
t Z 1 t Z 1
where ai' bi and c/s are cost coefficients, which can be estimated from ac
tual input-output unit data.
For the sake of simplicity all hydro units in this thesis are considered
to be run of the river generating units without any energy constraints and
whose input-output is given by
The last step of this commitment method is to check whether delaying
or advancing the starting and stopping of a certain unit results in a saving
In the running cost [9]. If a saving is possible, the commitment schedule is
134
altered and another tentative loading schedule IS prepared usmg the
previously established input-output curves obtained by dynamic programming.The checking for readjustments of starting and stopping times of units con
tinues until no further savings are achieved. A normalised cooling rate of
0.25 is considered for all thermal units in this thesis.
Identical generation systems A and B with generating units shown in
Table 3.2 are considered for unit commitment over a period of 24 hours.
System A and. System B are interconnected with the 2x100 MW tie lines
described in Table 3.3. Assume that both System A and B have one
25 MW rapid start hydro unit and one 25 MW rapid start gas turbine unit
available in addition to the units in Table 3.2. These rapid start units have
a lead time of 5 minutes. The rapid start hydro unit has a failure rate of
0.0002 per hour with a negligible starting failure rate. The transition rates
of the rapid start gas turbine unit are given in Table 3.13. The commence
ment of the scheduling period is arbitrary. In this chapter the scheduling
period commences from the moment of the daily peak and it is assumed that
the peak loads in both systems occur at the same time. These assumptionshave no influence on the basic method of unit commitment.
The coefficients of the running cost vs. output in MW curves and the
cold start-up cost of the generating units in both System A and B are given
in Table 6.1. Table 6.2 shows the hourly peak load variation in System A
and System B in a 24 hour commitment period. Table 6.3 shows the unit
commitment in System A and System B for the hourly peak load variation
shown in Table 6.2 with zero load forecast uncertainty. The specified SSR
of 0.01 and ISR of 0.0001 are used in obtaining the unit commitment
schedule for System A and System B. The lead times of additional thermal
generation in both systems are considered to be 2 hours.
The unit commitment in System A and System B with 4 % load
forecast uncertainty is shown in Table 6.4. The mean values of the daily
135
Table 6.1: Cost Parameters of the Generating Units In SystemA and B.
Unit # a· b· c· Cold Start-Up Typet t t
z Cost($)
1 0 0.2643 0.0 0 hydro2 0 0.2750 0.0 0 hydro3 0 0.2750 0.0 0 hydro4 60 1.1954 0.00127 70 thermal5 52 1.2136 0.00148 92 thermal6 52 1.2136 0.00148 95 thermal7 52 1.2241 0.00148 97 thermal8 45 1.2458 0.00212 100 thermal9 45 1.2458 0.00234 100 thermal
10 46 1.2532 0.00212 100 thermal-11 40 1.6966 0.00382 65 thermal
12 40 1.6966 0.00382 65 thermal13 29 1.8015 0.00212 110 thermal14 32 1.7522 0.00401 70 thermal15 32 1.8518 0.00393 70 thermal16 32 1.8518 0.00393 70 thermal17 0 0.25 0.0 0 hydro18 65 2.2271 0.00415 150 rapid start
peak load variation are shown in Table 6.2. The load forecast uncertainty
in this case has been modelled using the three-step approximation to the
normal distribution discussed in Section 3.7. The magnitude of overall spin
ning reserve requirement with load forecast uncertainty is higher than that
without load forecast uncertainty as seen from Tables 6.3 and 6.4
Unit commitment in System A and B with export/import is shown in
Table 6.5 for the hourly peak load variations shown in Table 6.2. System A
exports 60 MW to System B and the export is backed by the entire system
of A. The total spinning capacity in System A includes the load in A, ex
port commitment to B and the spinning reserve. The spinning reserve In
System A with a contracted export to System B is
Spinning Reserve = Total spinning capacity - Load - Export
136
Table 6.2: Peak Load Variations in a 24 Hour Period.
Hour
1
2
34
5
678
910111213
141516
1718192021222324
The spinning reserve m
IS
Spinning Reserve
6.6. Summary
A new reliability
La(MW) Lb(MW)
1900 1920
1880 19001840 18501820 18201800 1800
1750 17001770 16501740 16001700 15501600 15001500 14801400 14201310 1320
1200 12101150 11501100 11001150 10601250 1100
1400 13001550 14001650 16501730 17501820 18501900 1920
System B with a contracted import from System A
Total spinning capacity - Load + Import
constrained unit commitment method for intercon
nected systems is discussed in this chapter. The unit commitment must
satisfy two risk levels; one at the isolated system level and another in the
interconnection level. The method uses a priority loading order for the units
to be committed during the period of increasing generation requirements.
137
Table 6.3: Unit Commitment in System A and B.
Hour System A System B
La No. of . Spinning Lb No.of Spinning(MW) Units Reserve{MW) (MW) Units Reserve{MW)
1 1900 14 180 1920 14 1602 1880 14 200 1900 14 180
3 1840 13 140 1850 13 130
4 1820 13 160 1820 13 160
5 1800 13 180 1800 13 180
6 1750 12 110 1700 12 1607 1770 13 210 1650 11 no
8 1740 12 120 1600 11 1609 1700 12 160 1550 10 no
10 1600 11 160 1500 10 160
11 1500 10 160 1480 10 18012 1400 9 110 1420 10 240
13 1310 9 200 1320 9 190
14 1200 8 160 1210 8 150
15 1150 8 210 1150 8 210
16 1100 7 110 1100 7 110
17 1150 8 210 1060 7 15018 1250 8 110 1100 7 110
19 1400 9 110 1300 9 21020 1550 11 210 1400 9 11021 1650 12 210 1650 12 21022 1730 12 130 1750 13 23023 1820 13 160 1850 13 130
24 1900 14 180 1920 14 160
138
Table 6.4: Unit Commitment in System A and B With LoadForecast Uncertainty.
Hour System A System B
La No. of Spinning Lb No.of Spinning(MW) Units Reserve{MW) (MW) Units Reserve{MW)
1 1900 14 180 1920 15 260
2 1880 14 200 1900 15 280
3 1840 14 240 1850 14 230
4 1820 14 260 1820 14 260
5 1800 14 280 1800 14 280
6 1750 13 230 1700 12 160
7 1770 13 210 1650 12 210
8 1740 13 240 1600 11 160
9 1700 12 160 1550 11 210
10 1600 12 260 1500 10 160
11 1500 11 260 1480 10 180
12 1400 10 260 1420 10 240
13 1310 9 200 1320 9 190
14 1200 8 160 1210 8 150
15 1150 8 210 1150 8 210
16 1100 8 260 1100 8 260
17 1150 8 210 1050 7 160
18 1250 9 260 1100 7 110
19 1400 10 260 1300 9 210
20 1550 11 210 1400 10 260
21 1650 12 210 1650 12 210
22 1730 13 250 1750 13 230
23 1820 14 260 1850 14 230
24 1900 14 180 1920 15 260
139
Table 6.5: Unit Commitment In System A and B With
Export/Import.
Hour System A System B
La No. of Spinning Lb No.of Spinning(MW) Units Reserve(MW) (MW) Units Reserve(MW)
1 1900 15 220 1920 13 120
2 1880 14 140 1900 13 1403 1840 14 180 1850 13 1904 1820 14 200 1820 13 2205 1800 14 220 1800 12 120
6 1750 13 170 1700 11 1207 1770 13 150 1650 11 1708 1740 13 180 1600 10 120
9 1700 13 220 1550 10 17010 1600 12 200 1500 10 220
11 1500 11 200 1480 10 24012 1400 10 200 1420 9 15013 1310 9 140 1320 9 25014 1200 9 250 1210 8 210
15 1150 8 150 1150 7 12016 1100 8 200 1100 7 17017 1150 8 150 1060 7 21018 1250 9 200 1100 7 17019 1400 10 200 1300 8 120
20 1550 11 150 1400 9 17021 1650 12 150 1650 11 17022 1730 13 190 1750 12 17023 1820 14 200 1850 13 19024 1900 15 220 1920 13 120
140
The starting and stopping times of different units are adjusted to achieve
savings in the running cost.
141
7. LOCATION OF SPINNING RESERVE
7.1. Introduction
Reliable power system operation requires that the system generation
must respond to sudden changes in generation due to generation outages or
to unforeseen changes in system load or to any other contingency which
results in a generation loss. Hydro units can pick up load in the order of 1
to 5 minutes and, therefore, can respond to the generation or load changes
very quickly. Hydro units held as spinning reserve can be utilised to satisfythe system frequency and dynamic stability. The running costs of hydro
units are far lower than those of thermal units. Substantial economic
savings can be achieved by loading hydro units to their maximum output
level. Some sort of compromise between response requirements and economic
savings must be made when loading the hydro units.
Economic load dispatch methods consider allocation of load into dif
ferent operating units III order to achieve mmimum running
cost [13, 14, 39, 40]. Part of the spinning reserve must be available within
a certain margin time [41] to protect system frequency and tie line regula-_.
tion. Two types of margin time are important; (1) time to satisfy system
frequency and dynamic stability and (2) time to satisfy loss of generation or
other facilities. These margin times are normally of the order of one minute
and five minutes. The actual magnitude of these time periods can, however,
vary from system to system. A system may have a large amount of spin
ning reserve with a particular generation/load condition but the actual
responding capability can be quite inadequate for reliable system operation.
142
A method for spinning reserve allocation m interconnected systems
which satisfies specified risk criteria is presented in this chapter. Algorithms
are developed for two interconnected systems. Spinning reserve location in
multi-interconnected power systems can be considered using the multi-area
techniques given in references [5] and [42J.
7.2. Response Risk
Assessment of spinning reserve and unit commitment as developed in
the preVIOUS chapter do not suggest the manner in which the individual com
mitted units should be loaded. The units held as spinning reserve should be
capable of picking up load within the specified margin time in the case of a
sudden generation loss or an increase in the load. The ability of a unit to
respond to sudden changes and pick up load, if required, depends on the
unit type. Hydro units can pick up load of up to 30% of their full output
capacity in one minute. These units therefore play a dominant role in satis
fying system frequency and tie-line regulation. Typical thermal units can
pick up 1-3% of their full output capacity in one minute. The response rate
of thermal units depends on the loading point. Gas turbine and some gas
engines can pick up load in a relatively short period of time. The time
delay associated with starting, synchronising and loading these gas turbine
and gas engines could be in the order of three to five minutes.
The allocation of spmmng reserve amongst the committed units can be
done by selecting a suitable risk level. The load dispatch should be such
that the system should. have adequate responding capability. The probability
of meeting the regulating margin within the specified margin time, known as
response risk, ��?1l1� l:>�._�q'!�LtQ ... <?l" .1E!s§ . th�Jt, <L �P�c!t1�<lleyel. The assess
ment of response risk can be done using the I1:!(il"gi�.. E�e and failure andt::--_ _�_._.. �_�__
w--·----'''''··-· ""- ,.,� .. ,'"_ �.�=.,-,.."",�"�." .. �._...•. �." ,,.,,�.,,,, "" .. �",- .. _.,,,...,_,-�.. '-.�-'.. ""'.'
response rate of the units held in reserve. The response risk evaluation tech-'---_ _--- ,.",
"."." " __._-----,_,,, .. __ _,, ,. ,' "
- .. ,..'
, .. , .. , _"
"'
.
nique is similar to the technique for unit commitment risk evaluation., The
\,-�I!it c�P�<:Jt.y�J!l- �i�§p.Q!l.se··risk ey�_l_'!<Lti()..I! ... i� .. !�e t()t(iLE��P()_n_� output of the- .. --.'� -.". -""---�-��,,"'. ,,- .. _-,,' '''-'''�'-' ._"-_'-" •..... , .�.�.,-.
unit at the end ()Lth.�,_IIta,l"giI]. tip:l,e. The O!1ta,_geJ�I>J<L�ement rate (ORRLip.-
. -
,- -----. ---�----.-...• - ... __ .---- --
.. '. � -.- ....•
--�.-.��-�-�.--.".� .. -,,- ...•. - ....... ��-----�.-- .....•.--
143
the case of response risk evaluation is the probability that th�__ll.I!!t.JClU§ and�
. __ • __�'�__ .'.�....__ " .. .• �._ ,_�.' ' � -.,_"._",� ··_.r = __ .� ••. __ �_ ,,""._�� •• ,,�,� ........_._ ,�.'/"'''''' '__ -_.--._. ----.----�--."' -�-
is not replaced within the margin time. The response risk evaluation tech-
nique for a single system is discussed in detail in Reference [3].
In the case of an interconnected system, the response capacity IS
modified by assistance from neighbouring systems. All tie line constrained
response assistance can be considered as responding units available to the
system of concern. The technique of developing an equivalent response
capacity model is similar to that of developing an equivalent transient
capacity model as explained in Chapter 3.
The time delays associated with hot reserve units are such that the
units can not be included in the response capacity model. Hydro, rapid
start gas turbine and gas engines can be included in the risk assessment
using the area risk technique explained in Chapter 3. Interruptible loads
with the maximum allowable time delay of up to 5 minutes can be included
in the response risk assessment using the area risk technique. Chapter 5 ex
plains in detail the inclusion of interruptible load in the risk assessment
process. In the case of response risk assessment, the lead time of additional
response capacity is equal to the margin time. It is assumed that after the
margin time there will be enough responding capacity available to the system
that the risk will become zero for all practical purposes.
An interconnected system must meet two risk levels for both the
regulating margin requirements. The committed units in a system should be
dispatched in a way that the response risk designated as single system
response risk (SSRR) should be less than or equal to a specified level. Once
the response risk criteria at the single system level are satisfied in each sys
tem, all response assistances are considered at the interconnection level. All
response assistances to a given system in the interconnected configuration are
added to form an equivalent response model and the response risk designated
as the interconnected system response risk (ISRR) must satisfy a specified
144
risk level. The system most removed from meeting its ISRR criterion is re
quired to modify its dispatch in order to achieve greater response. The ac
tual ISRR of an interconnected system can be improved by having more
rapid start units available to the system.
7.3. Numerical Example
A numerical example to illustrate the assessment of response risk in an
interconnected system is shown in this section. Consider the generation
System X in Table 2.1 in Chapter 2. Assume that the specified unit com
mitment risk of System X at the single system level is 0.001. System X
must commit all 10 of its available units in order to carry a load of
170 MW if the lead time of additional thermal generation is two hours. The
equivalent generation model for 10 committed units with a lead time of two
hours in the form of a capacity outage probability table is shown in Table
2.2 of Chapter 2. The probability of unit failure assuming a 5 minute mar-
gm time is shown in Table 7.1.
Table '1.1: Failure Probability and Response Rate.
Unit Failure Probability ResponseSize Rate of Failure Rate
(MW) (fjyr) in 5 mins. (MWjmin)
40 4 0.00003805 1
20 3 0.00002854 1
10 3 0.00002854 1
Table 7.2 shows a possible load dispatch (not necessarily economic) of 10
operating units in system X when the load is 170 MW. The 5 minute
response risk is shown in Table 7.3 for the load dispatch in Table 7.2. If
the 5 minute regulating margin requirement of System X is assumed to be
25 MW, then the SSRR of X is 0.00017123 for the dispatch shown in Table
7.2.
145
Table 7.2: Load Dispatch ill System X.
Unit 1 2 3 4 5 6 7 8 9 10
G 40 40 40 20 20 20 10 10 10 10
L 40 40 40 10 10 10 10 5 5 0
R 0 0 0 5 5 5 0 5 5 5'
G is available generating capacity in MWL is individual unit loading in MWR is the 5 minute response in MW
Table 7.3: Response Risk.
Response(MW)
Individual
ProbabilityCumulative
Probability(risk)
3025
0.999828770.00017123
1.000000000.00017123
Assume that System X is interconnected to a neighbouring system
(System Y) through a tie line which has a maximum power transfer
capability of 27 MW and a failure rate of 1 failure/year. Table 7.4 shows
the tie-line model for the 5 minute margin time.
Table 7.4: Tie-Line Model.
Cap. In Cap. out Individual Cumulative
(MW) (MW) Probability Probability
27 0 0.99999049 1.00000000
0 27 0.00000951 0.00000951
The available generation, load and load dispatch in System Y is assumed to
146
be identical to that in System X and therefore the response reserve of
System Y will be identical to that shown in Table 7.3. The tie-line con
strained response assistance to System X provided by System Y is shown in
Table 7.5.
Table 1.5: Tie-Line Constrained Response(Assistance to X provided by Y).
Assistance
Response Individual Cumulative
(MW) Probability Probability
27 0.99981926 1.00000000
25 0.00017123 0.00018074
0 0.00000951 0.00000951
The 5 minute response of System X will be modified by the tie-line
constrained response assistance it can receive from System Y. The equiv
alent 5 minute response of System X is shown in Table 7.6.
Table 1.6: Equivalent 5 Minute Response of System X.
Response Individual Cumulative
(MW) Probability Probability( risk)
57 0.99964806 1.00000000
55 0.00017120 0.00035194
52 0.00017120 0.00018074
50 0.00000003 0.00000954
30 0.00000951 0.00000951
The 5 minute response risk of System X at the interconnection level can be
found from Table 7.6 given the 5 minute regulating margin of System X. If
the 5 minute regulating margin of System X is 30 MW then the ISRR of X
is 0.00000951. The equivalent 5 minute response model of System Y can be
developed in a similar manner. The equivalent 5 minute response model of
147
System X will change if the load dispatch in System X or in System Y or
both are changed. The one minute response risk can be evaluated using a
similar approach.
7.4. Load Dispatch Using the 'Two Risks Concept'
The load dispatch in an interconnected system should be such that the
one minute and 5 minute response requirements meet two risk levels; one at
the single system level and another at the interconnected system level.
Response risk changes with load dispatch. A particular economic load dis
patch may not meet the reliability criteria. There must be adequate
responding generation to satisfy the one minute and five minute response
reserve requirements. The one minute response reserve requirement can be
assessed by off-line transient and dynamic stability studies of the intercon
nected systems. The factors which affect the response risk are the loading of
units, unit failure rate, response rate of units, availability of rapid start
standby units etc.. The distribution of responding generation on many units
rather than on a few units for the same amount of responding generation
reduces the response risk. The system operating cost, however, will increase
if the response requirement is increased.
•
The first step of the load dispatch approach usmg the 'Two Risks
Concept' is to prepare an economic loading schedule. The second and final
step of this approach is to make the least costly adjustments of the economic
schedule to meet the risk criteria. The economic loading schedule in each
interconnected system can be prepared using any suitable economic load dis
patch technique. Once the economic loading schedules for each system are
prepared, the SSRR and ISRR of each system are evaluated. If the SSRR
and ISRR criteria are satisfied m each interconnected system, the economic
loading schedule in each system stands as a reliable loading schedule. In the
event that the risk criteria are not satisfied, the system farthest removed
from meeting the ISRR become responsible for making the necessary change
in its load dispatch provided all the systems satisfy the SSRR criterion.
148
Dynamic programming was used to obtain the economie loading
schedules for System A and System B. Several assumptions have been made
in the application of dynamic programming to obtain economic loading
schedules. Transmission losses in both areas and in the tie-lines have been
neglected. AU hydro generation is considered to be run of the river type
without any energy constraints. Ril?;_orous economic load dispatch
techniques [13, 14, 39, 43] can be applied if necessary to consider the trans
mission losses and pumped storage hydro if necessary.
7.4.1. Least costly adjustments
The response output of a generating unit depends on response rate,
margin time and the spmnmg reserve held on the unit. The response
capability of a unit is the product of response rate and the margin time as
suming a constant response rate over the output range of the unit, { In the
case where the spinning reserve held on the unit is less than the response
capability of that unit, the response output IS constrained by the spinning
reserve held on the unit. The first step of the least costly adjustment is to
classify the operating units into three groups according to whether an in
dividual unit's spinning reserve is higher (Group I) or lower (Group II) than
or equal (Group III) to its response capability. The next step is to identify
the unit in Group II whose incremental running cost at the respective load
point is the highest and the unit in Group I whose incremental running cost
at the respective load point is the lowest. The unit identified this way in
Group I is the acceptor unit and the unit identified in Group II is the donor
unit. If transmission losses are considered when obtaining the economic
loading schedule in the first step, the incremental running cost during the
identification process should include the incremental transmission cost. Once
the donor and acceptor in a system is identified, an incremental load is
taken away from the donor and put into the acceptor unit. The ISRR of all
interconnected systems are re-assessed and the whole process is repeated until
the system in concern satisfies its ISRR criterion. Any constraints regarding
the reloading of the units can be considered during the adjustments.
149
The incremental running cost of the units In Group I and Group II can
be obtained in the following way.'
Assume
(7.1)
where
Y i running cost of unit i in $ /hr,xi = output of unit i in MW.
The running cost of unit i for a load of (x+�x) MW IS
c. + b.(x+�x.) + c.(x+�x.)2I' 1 I t I I t (7.2)
where
� Y i= change in running cost in unit i in $ /hr,
�xi = change in output of unit i in MW.
From Equations (7.1) and (7.2) the change in running cost of unit t
can be expressed as
�Y' = {b. + c.(2x+�x.)}�x.I 1 'I & t(7.3)
In the limiting case, Equation (7.3) can be rearranged as the derivative of
the running cost of unit i at a load point of xi MW.
b. + 2c·x·tIt
A discrete change of �X In output of the donor and the acceptor unit has
been used for computational purposes. A smaller value of �x will require a
longer computation time than that of a larger value of �x for the same
starting loading schedule. �x is positive for the acceptor unit and negative
for the donor unit. Once the discrete reloading between the donor and the
acceptor is done a new pair of donor and acceptor is selected. A discrete
load change of 1 MW and 5 MW was used to obtain the loading schedules
for System A and System B.
150
Table 7.7 shows the response rate of the available generating units in
System A and System B. Response rate of all generating units are assumed
constant over the entire output range of the respective units.
Table 7.7: Response Rate of Generating Units.
Unit #z
Maximum
Output(MW)
ResponseRate
(MWjmin)
Minimum
Output(MW)
Type
1234
5
67
89
101112131415
161718
200180180200
150200150200150150100100120100100
1002525
ooo
70507050705050
303030303030
oo
40.0
30.030.0
3.02.03.0
2.03.02.02.01.51.52.02.0
2.02.05.05.0
hydrohydrohydrothermalthermalthermalthermalthermalthermalthermalthermalthermalthermalthermalthermalthermal
hydrorapid start
The hourly peak load variation and the corresponding unit commitment in
System A and System B as shown in respective Tables 6.2 and 6.3 of Sec
tion 6.5 are considered for the purpose of load dispatch. The load duringthe first hour of the 24 hour scheduling period is 1900 MW in System A
and 1920 MW in System B. The load dispatch during this hour is shown
in Table 7.8. The running cost during this first hour is $2757.10 in
System A and $2800.08 in System B according to the economic load dis
patch. The specified SSRR and ISRR is 0.01 and 0.0001 respectively. The
economic load dispatch in both systems during the first hour have been
modified to meet the reliability criteria. The resultant load dispatch requires
151
Table 7.8: Load Dispatch During the First Hour.
Unit # Economic Load Risk Constrained Economic Load Dispatchz Dispatch ..6. x 1 MW ..6. x 5 MW
A B A B A B
1 200 200 200 200 200 2002 180 180 134 154 130 1503 180 180 180 180 180 1804 200 200 185 185 185 1855 150 150 140 140 140 1406 150 150 140 140 140 1407 150 150 140 140 140 1408 150 150 140 140 140 1409 150 150 140 140 140 140
10 150 150 140 140 140 14011 57 61 77 77 87 91
12 57 61 93 93 92 91
13 78 86 110 110 108 10614 48 52 81 81 78 77
The output of all units are in MW
an increased running cost in both the systems. The running cost during the
first hour is $2884.44 in System A and $2889.94 in System B when a reload
ing stepsize of 1 MW has been used. The computation time required to res
chedule the economic load dispatch during the first hour to meet the
reliability criteria is 10.68 CPU seconds with a reloading step of 1 MW and
1.89 CPU seconds with a reloading step of 5 MW. The running cost during
the first hour is $2892.47 in System A and $2898.19 in System B when a
reloading stepsize of 5 MW has been used. The running costs for reliabilityconstrained economic load dispatch is summarised in Table 7.9.
The operating cost during the 24 hour period is shown in Table 7.10.
The operating cost in .each system includes the starting cost of generatingunits during the 24 hour scheduling period. The total starting cost during
152
Table '1.9: Running Cost During the First Hour.
EconomicLoad Dispatch
Risk ConstrainedEconomic Load Dispatch
System .6.x = 1 MW .6.x = 5 MW
AB
$2757.10$2800.08
$2884.44$2889.94
$2892.47$2898.19
.6.x = reloading step size in MW
Table '1.10: Operating Cost During the 24 Hour Period.
EconomicLoad Dispatch
Risk ConstrainedEconomic Load Dispatch
System .6.x = 1 MW .6.x = 5 MW
AB
$50,239.93$48,377.10
$52,846.59$50,956.67
$53,031.99$51,119.12
.6.x = reloading step size in MW
this 24 hour period is $525.00 in System A and $513.00 in System B. The
operating cost in both System A and System B has increased with the im
position of the response risk criteria compared to that with economic load
dispatch. The additional operating cost due to the imposition of response
risk criteria can be considered as the cost of reliability and should be judged
against the worth of reliability. The question of reliability worth is beyondthe scope of this thesis. The computation time required td reschedule the
unit loadings starting from the economic load dispatch to satisfying the risk
criteria depends on the number of units committed during a particular
period, economic load dispatch, SSRR, ISRR, reloading step size etc.. The
computation times required to reload the units in the first hour in order to
153
satisfy the risk criteria starting from the economic schedule, therefore, are
not representative. The computation time to reschedule the unit loadings
during the 24 hour period to obtain a risk constrained economic dispatch
starting from the basic economic dispatch is 3 minutes 22.29 seconds and
56.55 seconds CPU for a reloading step size of 1 MW and 5 MW respec
tively. The economic and the risk constrained economic load dispatches for
the 24 hour period assuming constant hourly loads as shown in Table 6.2
are presented in Tables 7.11 to 7.16.
The first three units in both Systems A and B are hydro generatingunits. The running cost of these hydro units are much lower than the ther
mal units in either system. In the economic load dispatch for System A
and System B shown in Tables 7.11 and 7.12, these three hydro units are
dispatched to their maximum output level. The response rates of the first
three hydro units as shown in Table 7.7 are considerably higher than those
of the thermal units in the system. Part of the spinning capacity of some of
these hydro units are held as reserve capacity when the risk constraints are
imposed on the economic load dispatch. This is evident in Tables 7.13 to
7.16. After fulfilling the 5 minute response criterion the one minute response
requirements are considered in a similar manner. Only the on-line generat
ing units contribute to the one minute response capability of a system. The
loading of the units are further modified if necessary, to meet the one
minute response risk criteria if necessary.
7.S. Summary
A risk constrained spmnmg reserve allocation technique IS presented in
this chapter. Spinning reserve should be allocated among the operationalunits in such a way that the response requirements are satisfied. Each in
terconnected system must satisfy SSRR and ISRR for 5 minute and one
minute regulating margins. An interconnected system can receive assistance
from its neighbour to meet its response requirements. This assistance is
taken into consideration when meeting the ISRR. Risk constrained economic
154
Table 1.11: Economic Load Dispatch in System A.
Individual Unit Outputs
Hour La . Xl X2 X3 X4 X5 X6 x7 Xs Xg XlO Xu X12 X13 x14
1 1900 200 180 180 200 150 150 150 150 150 150 57 57 78 48
2 1880 200 180 180 200 150 150 150 150 150 150 53 53 71 43
3 1840 200 180 180 200 150 150 150 150 150 150 54 54 72
4 1820 200 180 180 200 150 150 150 150 150 150 49 48 63
5 1800 200 180 180 200 150 150 150 150 150 150 43 43 54
6 1750 200 180 180 200 150 150 150 150 150 150 45 45
7 1770 200 180 180 200 150 150 150 150 150 150 36 35 39
8 1740 200 180 180 200 150 150 150 150 150 150 40 409 1700 200 180 180 200 150 150 150 148 135 147 30 30
10 1600 200 180 180 200 150 150 150 124 113 123 30
11 1500 200 180 180 192 150 150 150 103 94 101
12 1400 200 180 180 193 150 150 150 103 94
13 1310 200 180 180 169 138 138 135 89 81
14 1200 200 180 180 162 132 132 129 85
15 1150 200 180 180 149 122 122 119 7816 1100 200 180 180 157 129 129 12517 1150 200 180 180 149 122 122 119 7818 1250 200 180 180 173 143 143 139 9219 1400 200 180 180 193 150 150 150 103 94
20 1550 200 180 180 199 150 150 150 108 97 106 30
21 1650 200 180 180 200 150 150 150 131 119 130 30 30
22 1730 200 180 180 200 150 150 150 150 150 150 35 35
23 1820 200 180 180 200 150 150 150 150 150 150 49 48 63
24 1900 200 180 180 200 150 150 150 150 150 150 57 57 78 48
La and x/s are in MW
155
Table 7.12: Economic Load Dispatch in System B.
Individual Unit Outputs
Hour t., xl x2 X3 X4 x5 x6 X7 Xs X9 XlO Xu Xl2 X13 xl4
1 1920 200 180 180 200 150 150 150 150 150 150 61 61 86 52
2 1900 200 180 180 200 150 150 150 150 150 150 57 57 78 48
3 1850 200 180 180 200 150 150 150 150 150 150 57 56 77
4 1820 200 180 180 200 150 150 150 150 150 150 49 48 63
5 1800 200 180 180 200 150 150 150 150 150 150 43 43 54
6 1700 200 180 180 200 150 150 150 148 135 147 30 30
7 1650 200 180 180 200 150 150 150 142 128 140 308 1600 200 180 180 200 150 150 150 124 113 123 309 1550 200 180 180 200 150 150 150 118 106 116
10 1500 200 180 180 192 150 150 150 103 94 10111 1480 200 180 180 185 150 150 149 99 90 97
12 1420 200 180 180 173 142 142 138 92 83 9013 1320 200 180 180 171 140 140 137 90 8214 1210 200 180 180 164 135 134 131 8615 1150 200 180 180 149 122 122 119 7816 1100 200 180 180 157 129 129 12517 1060 200 180 180 146 119 119 11618 1100 200 180 180 157 129 129 12519 1300 200 180 180 166 137 137 133 88 7920 1400 200 180 180 193 150 150 150 103 9421 1650 200 180 180 200 150 150 150 131 119 130 30 30
22 1750 200 180 180 200 150 150 150 150 147 150 31 31 31
23 1850 200 180 180 200 150 150 150 150 150 150 57 56 7724 1920 200 180 180 200 150 150 150 150 150 150 61 61 86 52
-
Lb and x/s are in MW
156
Table 7.13: Risk Constrained Economic Load Dispatch ill Sys-tem A (Reloading step = 1 MW).
Individual Unit Outputs
Hour La xl X2 X3 X4 x5 X6 X7 X8 X9 XlO x11 X12 X13 x14
1 1900 200 134 180 185 140 140 140 140 140 140 77 93 110 81
2 1880 200 114 180 185 140 140 140 140 140 140 77 93 110 81
3 1840 200 164 180 185 140 140 140 140 140 140 81 80 110
4 1820 200 144 180 185 140 140 140 140 140 140 81 80 110
5 1800 200 124 180 185 140 140 140 140 140 140 81 80 110
6 1750 200 180 180 188 140 141 140 140 140 140 81 80
7 1770 200 94 180 185 140 140 140 140 140 140 81 80 110
8 1740 200 174 180 185 140 140 140 140 140 140 81 80
9 1700 200 134 180 185 140 140 140 140 135 140 83 83
10 1600 200 127 180 185 140 140 140 140 140 140 68
11 1500 200 119 180 185 140 140 140 128 128 140
12 1400 200 159 180 185 140 140 140 134 122
13 1310 200 69 180 175 140 140 140 140 126
14 1200 200 99 180 185 140 140 140 116
15 1150 200 49 180 185 140 140 140 116
16 1100 200 139 180 165 140 140 13617 1150 200 49 180 185 140 140 140 116
18 1250 200 149 180 185 140 140 140 116
19 1400 200 159 180 185 140 140 140 134 12220 1550 200 77 180 185 140 140 140 140 140 140 68
21 1650 200 84 180 185 140 140 140 131 125 140 93 92
22 1730 200 164 180 185 140 140 140 140 140 140 81 80
23 1820 200 144 180 185 140 140 140 140 140 140 81 80 110
24 1900 200 134 180 185 140 140 140 140 140 140 77 93 110 81
La and Xi's are in MW
157
Table 7.14: Risk Constrained Economic Load Dispatch in Sys-tem B (Reloading step = 1 MW).
Individual Unit Outputs
Hour Lb xl x2 x3 x4 x5 x6 x7 Xg Xg XlO Xu x12 x13 x14
1 1920 200 154 180 185 140 140 140 140 140 140 77 93 110 81
2 1900 200 134 180 185 140 140 140 140 140 140 77 93 110 81
3 1850 200 174 180 185 140 140 140 140 140 140 81 80 110
4 1820 200 144 180 185 140 140 140 140 140 140 81 80 1105 1800 200 124 180 185 140 140 140 140 140 140 81 80 110
6 1700 200 134 180 185 140 140 140 140 135 140 83 83
7 1650 200 177 180 185 140 140 140 140 140 140 688 1600 200 127 180 185 140 140 140 140 140 140 68
9 1550 200 169 180 185 140 140 140 128 128 14010 1500 200 119 180 185 140 140 140 128 128 14011 1480 200 99 180 185 140 140 140 128 128 14012 1420 200 39 180 173 140 140 140 140 128 14013 1320 200 79 180 175 140 140 140 140 12614 1210 200 109 180 185 140 140 140 11615 1150 200 49 180 185 140 140 140 11616 1100 200 139 180 165 140 140 13617 1060 200 99 180 165 140 140 13618 1100 200 139 180 165 140 140 13619 1300 200 59 180 175 140 140 140 140 12620 1400 200 159 180 185 140 140 140 134 12221 1650 200 84 180 185 140 140 140 131 125 140 93 92
22 1750 200 74 180 185 140 140 140 140 140 140 81 80 11023 1850 200 174 180 185 140 140 140 140 140 140 81 80 11024 1920 200 154 180 185 140 140 140 140 140 140 77 93 110 81
Lb and x/s are in MW
158
Table 7.15: Risk Constrained Economic Load Dispatch in Sys-tem A (Reloading step = 5 MW).
Individual Unit Outputs
Hour La xl x2 x3 X4 x5 x6 x7 Xs Xg xlO xll X12 xIS xl4
1 1900 200 130 180 185 140 140 140 140 140 140 87 92 108 78
2 1880 200 110 180 185 140 140 140 140 140 140 88 93 106 78
3 1840 200 160 180 185 140 140 140 140 140 140 84 84 107
4 1820 200 140 180 185 140 140 140 140 140 140 84 83 108
5 1800 200 120 180 185 140 140 140 140 140 140 83 83 109
r,6 1750 200 180 180 185 140 140 140 140 140 140 85 80
7 1770 200 90 180 185 140 140 140 140 140 140 81 85 109
8 1740 200 170 180 185 140 140 140 140 140 140 85 80
9 1700 200 125 180 185 140 140 140 143 135 142 85 85
10 1600 200 125 180 185 140 140 140 139 138 138 75
11 1500 200 115 180 187 140 140 140 138 124 136
12 1400 200 155 180 188 140 140 140 133 12413 1310 200 65 180 184 138 138 140 139 12614 1200 200 95 180 182 137 137 139 130
15 1150 200 45 180 184 137 137 139 128
16 1100 200 135 180 172 139 139 13517 1150 200 45 180 184 137 137 139 128
18 1250 200 140 180 183 143 143 139 122
19 1400 200 155 180 188 140 140 140 133 12420 1550 200 70 180 189 140 140 140 138 137 136 80
21 1650 200 80 180 185 140 140 140 131 139 140 90 85
22 1730 200 160 180 185 140 140 140 140 140 140 85 80
23 1820 200 140 180 185 140 140 140 140 140 140 84 83 108
24 1900 200 130 180 185 140 140 140 140 140 140 87 92 108 78
La and =» are in MW
159
Table 7.16: Risk Constrained Economic Load Dispatch in Sys-tem B (Reloading step = 5 MW).
Individual Unit Outputs
Hour Lb xl X2 X3 X4 x5 X6 X7 Xs Xg XIO Xll Xl2 Xl3 x14
1 1920 200 150 180 185 140 140 140 140 140 140 91 91 106 77
2 1900 200 130 180 185 140 140 140 140 140 140 87 92 108 78
3 1850 200 170 180 185 140 140 140 140 140 140 82 86 1074 1820 200 140 180 185 140 140 140 140 140 140 84 83 108
5 1800 200 120 180 185 140 140 140 140 140 140 83 83 109
6 1700 200 125 180 185 140 140 140 143 135 142 85 85
7 1650 200 175 180 185 140 140 140 142 138 140 70
8 1600 200 125 180 185 140 140 140 139 138 138 75
9 1550 200 165 180 185 140 140 140 138 126 13610 1500 200 115 180 187 140 140 140 138 124 136
11 1480 200 95 180 185 140 140 144 134 125 13712 1420 200 35 180 178 142 142 138 137 128 14013 1320 200 75 180 181 140 140 137 140 12714 1210 200 lOS 180 184 140 139 136 12615 1150 200 45 180 184 137 137 139 12816 1100 200 135 180 172 139 139 135
17 1060 200 9S 180 171 139 139 136
18 1100 200 135 180 172 139 139 13519 1300 200 55 180 181 137 137 138 138 13420 1400 200 155 180 188 140 140 140 133 12421 1650 200 80 180 185 140 140 140 131 139 140 90 85
22 1750 200 70 180 185 140 140 140 140 142 140 86 81 106
23 1850 200 170 180 185 140 140 140 140 140 140 82 86 10724 1920 200 150 180 185 140 140 140 140 140 140 91 91 106 77
Lb and x/s are in MW
160
loading schedules have been developed using reloading steps of 1 MW and 5
MW. In an actual system, other reloading steps should be tried to meet the
specific needs of the system in terms of operating economy and computation
time.
161
8. APPLICATION TO RELIABILITYTEST SYSTEMS
8.1. Introduction
The application of the 'Two Risks Concept' and the related computer
programs developed to assess the spinning reserve and unit commitment in
interconnected systems have been tested using selected reliability test sys
tems. The IEEE - Reliability Test System has been used extensively to
compare the capabilities of computer programs used in reliability studies.
The IEEE-RTS represents a reasonably large power system. The size of the"
IEEE-RTS makes it difficult to obtain a direct appreciation of the various
steps involved in the computational process and the effectiveness of various
assumptions. A small test system designated as the Roy Billinton Test Sys
tem (RBTS) [44] has also been used for many years by the Power Systems
Research Group at the University of Saskatchewan to test a wide variety of
computer programs for reliability studies. The IEEE-RTS and RBTS have
been used to assess the spinning reserve and unit commitment requirements
in interconnected systems and the results are presented in this chapter. Nei
ther reliability test systems contains complete data for conducting spinning
reserve studies in an interconnection mode. The missing data have been as
sumed wherever required.
..
The specified SSR and ISR have been taken as 0.01 and 0.0001 respec
tively in all cases. The lead time in each interconnected system is assumed
to be 120 minutes. The results presented in this chapter utilise the main
concepts developed and illustrated in the previous chapters.
162
8.2. Applieation to the Roy Billinton Test System
(RBTS)
The RBTS has 11 generating units of which 7 are hydro units ranging
from 5 MW to 40 MW. The hydro units can be started, synchronised and
loaded up to the full output capacity in 5 minutes. The annual peak load
of the RBTS is 185 MW. The generating units in the RBTS and the cor
responding running cost data are shown in Table 8.1. It is assumed that
two identical RBTS are interconnected radially through a tie line with a
maximum power transfer capability of 30 MW. The tie line failure is con
sidered to be one per year. The two RBTS have been designated as
RBTS-1 and RBTS-2-. Table 8.2 shows the units that the two RBTS must
commit to satisfy a SSR of 0.01 and an ISR of 0.0001. The corresponding
spinning reserve can be found by subtracting load in columns 1 and 2 from
the respective total spinning capacity in columns 9 and 10. The load in
RBTS-1 is varied from 110 MW to 185 MW in steps of 5 MW while the
load in RBTS-2 is kept constant at 100 MW. Columns 11 and 12 show the
unit commitment risk at the interconnected level.
Table 8.3 shows the units that must be committed in RBTS-1 and
RBTS-2 when the forecast load has an uncertainty of 4% of the forecast
mean. The load in each system has been assumed to be normally dis
tributed and the distribution has been approximated by seven discrete steps
as noted in Section 3.7 of Chapter 3. Table 8.4 shows the units that must
be committed in each RBTS when the load forecast uncertainty is 4% of the
forecast mean but the load distribution has been approximated by three dis
crete steps as noted in Section 3.7 of Chapter 3.
The level of potential assistance with respect to spinning reserve
decreases when part of the tie-capacity is set aside for export/import. Table
8.5 shows the unit commitment in RBTS-1 and RBTS-2 with export/importwhen the export IS backed up by the entire system of the exporting utility.
Table 8.5 shows that the RBTS-1 and RBTS-2 must commit 6 and 7 units
Table 8.1: RBTS Generating Units and Cost Data.
Unit Unit Priority Failure Running Cost Cold Maximum Minimum ResponseSize Type Loading Rate Parameter Start-up Output Output Rate
(MW) Order (f/yr) a· b. c· Cost($) (MW) (MW) (MW/min)1 1 1
40 hydro 1 3.0 0 0.50 0.0 0 40 0 8
20 hydro 2 2.4 0 0.50 0.0 0 20 0 4
20 hydro 3 2.4 0 0.50 0.0 0 20 0 4
40 thermal 4 6.0 26 12.00 0.01 70 40 10 2
40 thermal 5 6.0 28 12.00 0.01 75 40 10 2
20 thermal 6 5.0 16 12.25 0.02 36 20 5 1
10 thermal 7 4.0 14 12.50 0.02 30 10 3 1
20 hydro 8 2.4 0 0.50 0.0 0 20 0 4
20 hydro 9 2.4 0 0.50 0.0 0 20 0 4t-'0)w
5 hydro 10 2.0 0 0.50 0.0 0 5 0 1
5 hydro 11 2.0 0 0.50 0.0 ·0 5 0 1
.J"�
--.- ..... _.
Table 8.2: Unit Commitment in the RBTS.
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW)
1 2 1 2 1 2 1 2 1 2 1 2
110 100 4 4 120 120 5 4 160 120 0.00000010 0.00000042
115 100 4 4 120 120 5 4 160 120 0.00000010 0.00000042
120 100 5 4 160 120 5 4 160 120 0.00000060 0.00000059
125 100 5 4 160 120 5 4 160 120 0.00000060 0.00000059
130 100 5 4 160 120 5 4 160 120 0.00000061 0.00000059
135 100 5 4 160 120 5 4 160 120 0.00000061 0.00000059
140 100 5 4 160 120 6, 4 180 120 0.00000071 0.00000065 I-'0)
145 100 5 4 160 120 6 4 180 120 0.00000071 0.00000065�
150 100 5 '4 160 120 6 4 180 120 0.00000072 0.00000065
155 100 5 4 160 120 6 4 180 120 0.00000073 0.00000065
160 100 6 4 180 120 7 4 190 120 0.00000081 0.00000071
165 100 6 4 180 120 7 4 190 120 0.00000082 0.00000071
170 100 6 4 180 120 8 4 210 120 0.00000157 0.00000069
175 100 6 4 180 120 8 4 210 120 0.00000157 0.00000069
180 100 7 4 190 120 8 4 210 120 0.00000191 0.00000074
185 100 7 4 190 120 8 4 210 120 0.00000212 0.00000074
•
Table 8.3: Unit Commitment in the RBTS With Load Forecast
Uncertainty (Seven-step approximation of the load
distribution) .
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW)
1 2 1 2 1 2 1 2 1 2 1 2
110 100 4 4 120 120 5 4 160 120 0.00000011 0.00000243
115 100 5 4 160 120 5 4 160 120 0.00000017 0.00000246
120 100 5 4 160 120 5 4 160 120 0.00000086 0.00000264
125 100 5 4 160 120 5 4 160 120 0.00000607 0.00000523
130 100 5 4 160 120 5 4 160 120 0.00003839 0.00002381
135 100 5 4 160 120 6 4 180 120 0.00000029 0.00000249
140 100 5 4 160 120 6 4 180 120 0.00000175 0.00000318
145 100 5 4 160 120 6 4 180 120 0.00001448 0.00001031
150 100 6 4 180 120 6 4 180 120 0.00007212 0.00004404
155 100 6 4 180 120 7 4 190 120 0.00001450 0.00001033
160 100 6 4 180 120 7 4 190 120 0.00007215 0.00004405
165 100 6 4 180 120 8 4 210 120 0.00000104 0.00000262
170 100 7 4 190 120 8 4 210 120 0.00000618 0.00000526
175 100 7 4 190 120 8 4 210 120 0.00002483 0.00001591
180 100 8 4 210 120 8 4 210 120 0.00008561 0.00004915
185 100 8 4 210 120 9 4 230 120 0.00002116 0.00000318
I-'
O'lCon
Table 8.4: Unit Commitment in the RBTS With Load Forecast
Uncertainty (Three-step approximation of the load
distribution) .
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW),
1 2 1 2 1 2 1 2 1 2 1 2
110 100 4 4 120 120 5 4 160 120 0.00000010 0.00000040
115 100 5 4 160 120 5 4 160 120 0.00000019 0.00000044
120 100 5 4 160 120 5 4 160 120 0.00000050 0.00000052
125 100 5 4 160 120 5 4 160 120 0.00001486 0.00000914
130 100 5 4 160 120 5 4 160 120 0.00007676 0.00004621
135 100 5 4 160 120 6 4 180 120 0.00000021 0.00000045
140 100 5 4 160 120 6 4 180 120 0.00000058 0.00000057
145 100 5 4 160 120 6 4 180 120 0.00001494 0.00000919
150 100 6 4 180 120 6 4 180 120 0.00007690 0.00004626
155 100 6 4 180 120 7 4 190 120 0.00001496 0.00000920
160 100 6 4 180 120 7 4 190 120 0.00007696 0.00004630
165 100 6 4 180 120 8 4 210 120 0.00000045 0.00000047
170 100 7 4 190 120 8 4 210 120 0.00001573 0.00000921
175 100 7 4 190 120 8 4 210 120 0.00001578 0.00000923
180 100 8 4 210 120 8 4 210 120 0.00008724 0.00004635
.......0)0)
167
Table 8.5: Unit Commitment in the RBTS With Export/Import(Export is backed up by the entire exportingsystem).
Load Export Import No. of ISR
(MW) (MW) (MW) Units1 2 1 2 1 2 1 2 1 2
150 160 0 0 0 0 6 7 0.00000096 0.00000097150 160 10 0 0 10 7 6 0.00000183 0.00000175160 160 0 0 0 0 7 7 0.00000097 0.00000097160 160 15 0 0 15 8 6 0.00006148 0.00000152170 160 0 0 0 0 8 7 0.00000133 0.00000075170 160 0 10 10 0 7 8 0.00000162 0.00000181180 160 0 0 0 0 8 6 0.00000217 0.00000217180 160 0 15 15 0 8 8 0.00000150 0.00006148
respectively to carry a load of 150 MW in RBTS-l and 160 MW in RBTS-2
with zero export/import. The units that must be committed in each RBTS
changes to 7 units for RBTS-l and 6 units for RBTS-2 for an export of
10 MW by RBTS-l to RBTS-2. Table 8.6 shows the unit commitment when
the export is backed up by the first unit in the exporting system. The unit
backing up the export is a 40 MW thermal unit. This unit has a must run
status as long as it is available for service.
Table 8.6: Unit Commitment in the RBTS With Export/Import(Export is backed up by a Specific Unit).
Load Export Import No. of ISR
(MW) (MW) (MW) Units1 2 1 2 1 2 1 2 1 2
150 160 0 0 0 0 6 7 0.00000096 0.00000097150 160 10 0 0 10 7 6 0.00000137 0.00000181160 160 0 0 0 0 7 7 0.00000097 0.00000097160 160 15 0 0 15 8 6 0.00003167 0.00000152170 160 0 0 0 0 8 7 0.00000133 0.00000075170 160 0 10 10 0 7 8 0.00000169 0.00000158180 160 0 0 0 0 8 6 0.00000217 0.00000211180 160 0 15 15 0 8 8 0.00000166 0.00003168
168
The presence of interruptible loads can reduce the unit commitment
risk for a particular system load level and a given set of generation. The
ability of a system to interrupt load can be considered as the ability to
bring in ready reserve into the system depending upon the allowable time
delay of such load interruption. Table 8.7 shows the units that must be
committed in RBTS-1 and RBTS-2 when both systems have the ability to
interrupt 10 MW of their load within a time delay of 10 minutes. An inter
connected generation system can carry some additional load/interruptible load
on top of its firm load without having to modify its unit commitment or
that of its neighbours from the commitments required to carry the respectivefirm loads. This capability, however, depends on the firm load and unit
commitment in all the member systems and the available assistance from the
neighbouring systems. In order to carry a load of 150 MW in RBTS-l and
180 MW in RBTS-2, RBTS-l and RBTS-2 must commit 6 and 9 generatingunits respectively from their priority loading order list. The additional
load/interruptible load carrying capability of RBTS-2 on top of its firm load
of 180 MW is shown in Figure 8.1. The corresponding additional load in
RBTS-l is assumed to be zero. The additional load carrying capability of
RBTS-2 will change for a corresponding change In the additional
load/interruptible load in RBTS-l.
Generating units in a system are usually committed on a continuous
basis during a scheduling period depending upon the forecast load and
economic factors. In order to have two different load profiles in the two in-•
terconnected systems, the percentiles of the hourly peak load on Tuesday and
Monday during the week #51 of the IEEE-RTS load model have been used
to provide the load profiles over a 24 hour period in RBTS-l and RBTS-2
respectively. The annual peak load for the RBTS is 185 MW. The hourly
peak load variations in a 24 hour period in both RBTS-l and RBTS-2 are
given in Table 8.8. The unit commitment and spinning reserve in both
RBTS-l and RBTS-2 during this 24 hour scheduling period are shown in
Table 8.9. Table 8.10 shows for comparison purposes, the unit commitment
Table 8.7: Unit Commitment in the RBTS With InterruptibleLoad.
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW)
1 2 1 2 1 2 1 2 1 2 1 2
110 100 4 4 120 120 5 4 160 120 0.00000010 0.00000029
115 100 4 4 120 120 5 4 160 120 0.00000010 0.00000029
120 100 5 4 160 120 5 4 160 120 0.00000051 0.00000046
125 100 5 4 160 120 5 4 160 120 0.00000051 0.00000046
130 100 5 4 160 120 5 4 160 120 0.00000060 0.00000046
135 100 5 4 160 120 5 4 160 120 0.00000060 0.00000046
140 100 5 4 160 120 6 4 180 120 0.00000062 0.00000052
145 100 5 4 160 120 6 4 180 120 0.00000062 0.00000052
150 100 5 4 160 120 6 4 180 120 0.00000071 0.00000052
155 100 5 4 160 120 6 4 180 120 0.00000071 0.00000052
160 100 6 4 180 120 7 4 190 120 0.00000080 0.00000057
165 100 6 4 180 120 7 4 190 120 0.00000080 0.00000057
170 100 6 4 180 120 8 4 210 120 0.00000078 0.00000055
175 100 6 4 180 120 8 4 210 120 0.00000078 0.00000055
180 100 7 4 190 120 8 4 210 120 0.00000165 0.00000060
185 100 7 4 190 120 8 4 210 120 0.00000165 0.00000060
-
(;r)�
170
40,_------------------------------------------�
r.""
20
fIRM LOAD IN RBTS-] - 150 M�fIRM LOAD IN RBTS-2 - 180 MW
.......................................... -
-_
............................................
ii•
30
10
04---------�--------------------------------�
70 80 90 100 110 120
Lead TIme in mins
Figure 8.1: Additional Load Carrying Capability of RBTS-2.
schedule for both RBTS-1 and RBTS-2 with no interconnection between
them. Both systems are required to satisfy a unit commitment risk of
0.0001 which is equal to the specified ISR. RBTS-1 is unable to satisfy its
unit commitment risk in absence of interconnection during the hours of 17,
18 and 19 after committing all 11 available units. The overall spinning
reserve requirements in both RBTS-1 and RBTS-2 are higher in the case of
no interconnection than those with interconnection.
The conventional economic load dispatch may not provide sufficient
response reserve on the generating units. A reliable load dispatch should be
such that an adequate 1 minute and 5 minute regulating margin exists. The
1 minute regulating reserve requirement can be determined by dynamic and
171
Table 8.8: Peak Load Variations of RBTS in a 24 Hour Period.
Hour Lt(MW) L2(MW)
1 124 1152 117 1093 111 1034 110 1015 110 1016 111 1037 137 1278 159 1489 176 164
10 178 16611 178 16612 176 16413 176 16414 176 16415 172 16016 174 16217 183 17018 185 17219 185 17220 178 16621 168 15622 154 143
23 135 12624 117 109
. transient stability studies. Hydro and rapid start gas turbine and gas en
gines can be considered as part of the 5 minute response reserve because of
their relatively short lead time (in the order of 5 minutes). Tables 8.11 and
8.12 show the modified economic load dispatch in RBTS-l and RBTS-2. It is
interesting to note that the load dispatch shown in Tables 8.11 and 8.12
satisfy the 5 minute response criterion without any load adjustments. The
SSRR and ISRR are chosen as 0.01 and 0.0001 respectively. Both RBTS
have a significant number of hydro units compared to their thermal units.
Some of these hydro units are left as ready reserve which provides additional
5 minute response reserve on top of the on-line response reserve. The trans
mission and tie-line losses have been neglected and all hydro units have been
considered as run of the river units without any energy constraints.
172
Table 8.9: Unit Commitment in the RBTS (24 hours schedulingperiod).
Hour RBTS-1 RBTS-2
Ll No. of Spinning L2 No.of Spinning(MW) Units Reserve(MW) (MW) Units Reserve(MW)
1 124 5 36 115 5 45
2 117 5 43 109 4 11
3 111 5 49 103 4 17
4 110 5 50 101 4 19
5 110 5 50 101 4 19
6 111 5 49 103 4 17
7 137 5 23 127 5 33
8 159 6 21 148 6 32
9 176 8 34 164 7 26
10 178 8 32 166 7 24
11 178 8 32 166 7 24
12 176 8 34 164 7 26
13 176 8 34 164 7 26
14 176 8 34 164 7 26
15 172 8 38 160 7 30
16 174 8 36 162 7 28
17 183 8 27 170 7 20
18 185 9 45 172 7 18
19 185 9 45 172 7 18
20 178 8 32 166 7 24
21 168 7 22 156 6 24
22 154 6 26 143 5 17
23 135 5 25 126 5 34
24 117 5 43 109 4 11
8.3. Application to the IEEE-RTS
The IEEE-RTS has 32 generating units rangmg from sizes of 12 MW
to 400 MW. Among the units there are 6 x 50 MW hydro units and
2x400 MW nuclear units. Nuclear units are considered to operate as base
load units and load fluctuations are not taken up by the nuclear units. The
response rate of the nuclear units of the IEEE-RTS within the margin time
of 5 minutes is considered to be zero for all practical purposes. Two iden-
173
Table 8.10: Unit Commitment in the RBTS Without Interconnection (24 hours scheduling period).
Hour RBTS-2RBTS-1
No. of SpinningUnits Reserve(MW)
No.of
UnitsSpinning
Reserve(MW)
1
23
4
5
67
89
10
11
121314
1516
1718
19
2021222324
124117111
110
110111137159176178178176176176
172174183185
185178168154
135117
6
5555
5
689
9
9
99999*
*
*
56
434950
50494351
54
52525454
545856**
**
**
115109
103101101103
127148
164166166164164164
160162170172172166156143126109
5
55
5
55
67
8
88
8888
89
9988
7
65
455157
59595753424644
44
46464650
48605858
44
544754
51
9
8865
524256
4543
tical IEEE-RTS have been considered to be interconnected through three tie
lines. Each of the three tie lines can transfer up to 100 MW on average.
The failure rate of each tie line is one failure per year. Two of 6x50 MW
hydro units are placed at the end of the loading order priority list in each
IEEE-RTS. The lead times of all hydro units are considered to be 5
minutes.
Studies similar to those conducted for the RBTS have been done for
the IEEE-RTS. The generating unit data of each IEEE-RTS are shown in
174
Table 8.11: Risk Constrained Economic Load Dispatch in the
RBTS-1 (Reloading step = 5 MW).
Load
(MW)Individual Unit Outputs
(MW)
Hour L1
67
89
10
11
12
13
14
15
1617
18
1920
2122
23
24
1234
124117
2020
20
2020202020
2020
20202020202020
202020202020202020
2219
16
15
1516
29
34
3232
3232
32
3230
313428
2832
3632
28
19
22181515
15152834
32323232323230
313427273236322718
119
10
10999
9
911
77
101110
34
4
3333
343345
202020
2020
20202020202020
20
20
4040
5
111 40 20
110 40 20
110 40 20111 40 20137 40 20159 40 20
176 40 20178 40 20178 40 20
176 40 20
176 40 20
176 40 20172 40 20174 40 20183 40 20
185 40 20
185 40 20178 40 20168 40 20154 40 20135 40 20
117 40 20
Table 8.13. The runnmg cost of each generating unit is estimated by a
second degree polynomial using the heat rates provided [33] at different out
put levels of the unit. Table 8.14 shows the running cost and the cold
start-up cost of each unit. The two IEEE-RTS have been designated as
IEEE-RTS-1 and IEEE-RTS-2 for the sake of clarity.
Table 8.15 shows the units that must be committed in each IEEE-RTS
for the corresponding loads in columns 1 and 2. The load in IEEE-RTS-2 is
varied from 2100 MW to 2850 MW while the load in IEEE-RTS-l is held
175
Table 8.12: Risk Constrained Economic Load Dispatch ill theRBTS-2 (Reloading step = 5 MW).
Load Individual Unit Outputs(MW) (MW)
Hour 12 xl X2 X3 X4 X5 x6 x1 x8 Xg xlO
1 115 40 20 20 18 172 109 40 20 20 29
3 103· 40 20 20 23
4 101 40 20 20 21
5 101 40 20 20 216 103 40 20 20 237 127 40 20 20 24 238 148 40 20 20 30 30 89 164 40 20 20 34 34 11 5
10 166 40 20 20 35 35 11 5
11 166 40 20 20 35 35 11 512 164 40 20 20 34 34 11 513 164 40 20 20 34 34 11 514 164 40 20 20 34 34 11 515 160 40 20 20 33 33 10 4
16 162 40 20 20 34 34 10 4
17 170 40 20 20 36 36 12 6
18 172 40 20 20 37 37 12 6
19 172 40 20 20 37 37 12 6
20 166 40 20 20 35 35 11 5
21 156 40 20 20 33 33 1022 143 40 20 20 32 3123 126 40 20 20 23 2324 109 40 20 20 29
Table 8.13: Generating Units in the IEEE-RTS.
Unit Unit No. of Priority Failure Maximum Minimum ResponseSize Type Units Loading Rate Output Output Rate
(MW) Order (f/yr) (MW) (MW) (MW/min)
50 hydro 6 1-4,31-32 4.42 50 0 10
400 nuclear 2 5-6 7.96 400 200 �O
350 thermal 1 7 7.62 350 150 9
197 thermal 3 8-10 9.22 197 80 6
155 thermal 4 11-14 9.13 155 60 5
100 thermal 3 15-17 7.30 100 40 3
76 thermal 4 18-21 4.47 76 25 2
12 thermal 5 22-26 2.98 12 5 1
20 thermal 4 27-30 19.47 20 6I-'
4 -1Q)
Table 8.14: IEEE-RTS Cost Data.
Unit Unit No. of Priority Running Cost Cold
Size Type Units Loading Parameter Start-up(MW) Order a· b· c· Cost($)I I I
50 hydro 6 1-4,31-32 0.0 0.5 0.0 0
400 nuclear 2 5-6 216.57585 5.34515 0.00028 800
350 thermal 1 7 388.25027 8.91965 0.00392 300
197 thermal 3 8-10 301.22318 20.02271 0.003 150
155 thermal 4 11-14 206.70340 9.27063 0.00667 100
100 thermal 3 15-17 286.24109 17.92387 0.02203 80
76 thermal 4 18-21 100.43962 12.14489 0.01131 60
12 thermal 5 22-26 30.39611 23.27773 0.13733 15
20 thermal 4 27-30 40.0 37.55452 0.18256 30......-...:t-...:t
178
constant at 2100 MW. The number of units that must be committed in
IEEE-RTS-1 varies between 12 and 13 although its load is at a constant
level. This is due to the reason that the independence of a system from the
operating variations of another system is lost when these systems are inter
connected with the objective of assisting each other with respect to spinning
reserves. This phenomenon is explained in detail in Section 3.4 of Chapter
3. The unit commitment with load forecast error is shown in Tables 8.16
and 8.17. All the load levels in Table 8.16 have a load forecast uncertainty
of 4% of the forecast mean and the load distribution is approximated by
seven discrete steps. The unit commitment and corresponding risk using the
three-step approximation to the load distribution is shown in Table 8.17.
The unit commitment risks have also been assessed with export/importbetween two interconnected IEEE-RTS. Table 8.18 shows the units that
must be committed in each IEEE-RTS and the corresponding unit commit
ment risk if the export is backed up by the entire exporting system. The
unit commitment and the corresponding risk with export backed up by a
specific unit in the exporting system is shown in Table 8.19. The unit that
is backing up the export in the IEEE-RTS is a hydro unit of 50 MW size.
This is a must run unit. Any unit can be used to back up the export.
The unit which backs up the export will have a must run status.
The presence of interruptible load can reduce the unit commitment risk
of a system. Load curtailment, however, should only be considered in the
absence of other economic capacity adjustments. Table 8.20 shows the unit
commitment in IEEE-RTS-1 and IEEE-RTS-2 when both IEEE-RTS have an
interruptible load of 70 MW with a lead time of 10 minutes. It can be seen
from Tables 8.15 and 8.20 that the unit commitments in both IEEE-RTS
with the 70 MW interruptible load are identical to those without the inter
ruptible load except when the load in IEEE-RTS-2 is 2250 and 2750 MW.
The ISR in both IEEE-RTS is reduced in the presence of the 70 MW inter
ruptible load in both systems for the same load and unit commitment situa-
Table 8.15: Unit Commitment in the. IEEE-RTS.
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW).
Units (MW) Units (MW)
1 2 1 2 1 2 1 2 1 2 1 2
2100 2100 12 12 2251 2251 13 13 2406 2406 0.00001039 0.00001039
2100 2150 12 12 2251 2251 12 13 2251 2406 0.00007758 0.00003139
2100 2200 12 13 2251 2406 13 13 2406 2406 0.00001111 0.00003717
2100 2250 12 13 2251 2406 12 14 2251 2561 0.00007735 0.00001165
2100 2300 12 13 2251 2406 12 14 2251 2561 0.00007778 0.00003168
2100 2350 12 14 2251 2561 13 14 2406 2561 0.00001117 0.00003742
2100 2400 12 14 2251 2561 12 15 2251 2661 0.00007791 0.00003189
2100 2450 12 14 2251 2561 13 15 2406 2661 0.00001118 0.00003753
2100 2500 12 15 2251 2661 12 16 2251 2761 0.00007805 0.00003211
2100 2550 12 15 2251 2661 13 16 2406 2761 0.00001118 0.00003764
2100 2600 12 16 2251 2761 12 17 2251 2861 0.00007819 0.00003232
2100 2650 12 16 2251 2761 13 17 2406 2861 0.00001118 0.00003775
2100 2700 12 17 2251 2861 13 18 2406 2937 0.00001118 0.00003778
2100 2750 12 17 2251 2861 12 19 2251 3013 0.00007835 0.00003258
2100 2800 12 18 2251 2937 13 19 2406 3013 0.00001118 0.00003789
2100 2850 12 19 2251 3013 13 20 2406 3089 0.00001112 0.00003773
•
....-1<0
Table 8.16: Unit Commitment in the IEEE-RTS With LoadForecast Uncertainty (Seven-step approximation ofthe load distribution).
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW)
1 2 i 2 1 2 1 2 1 2 1 2
2100 2100 13 13 2406 2406 13 13 2406 2406 0.00003071 0.00003071
2100 2150 13 13 2406 2406 13 13 2406 2406 0.00005779 0.00009311
2100 2200 13 13 2406 2406 13 14 2406 2561 0.00002031 0.00001470
2100 2250 13 14 2406 2561 13 14 2406 2561 0.00003181 0.00003156
2100 2300 13 14 2406 2561 13 14 2406 2561 0.00005796 0.00009179
2100 2350 13 14 2406 2561 13 15 2406 2661 0.00003370 0.00003374
2100 2400 13 15 2406 2661 13 15 2406 2661 0.00006336 0.00009349
2100 2450 13 15 2406 2661 13 16 2406 2761 0.00003393 0.00003404
2100 2500 13 16 2406. 2761 13 17 2406 2861 0.00002740 0.00002130
2100 2550 13 16 2406 2761 13 17 2406 2861 0.00003609 0.00003719
2100 2600 13 17 2406 2861 13 18 2406 2937 0.00003065 0.00003190
2100 2650 13 18 2406 2937 13 18 2406 2937 0.00004721 0.00008073
2100 2700 13 18 2406 2937 13 19 2406 3013 0.00003635 0.00006677
2100 2750 13 19 2406 3013 13 20 2406 3089 0.00003300 0.00003408
2100 2800 13 20 2406 3089 13 20 2406 3089 0.00005616 0.00008965
2100 2850 13 20 2406 3089 13 21 2406 3165 0.00004588 0.00006940
�00o
Table 8.17: Unit Commitment in the IEEE-RTS With Load
Forecast Uncertainty (Three-step approximation ofthe load distribution).
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW)
1 2 1 2 1 2 1 2 1 2 1 2
2100 2100 13 13 2406 2406 13 13 2406 2406 0.00002935 0.00002935
2100 2150 13 13 2406 2406 13 13 2406 2406 0.00006866 0.00008837
2100 2200 13 13 2406 2406 13 14 2406 2561 0.00002883 0.00002090
2100 2250 13 14 2406 2561 13 14 2406 2561 0.00002962 0.00003069
2100 2300 13 14 2406 2561 13 14 2406 2561 0.00006658 0.00008550
2100 2350 13 14 2406 2561 13 15 2406 2661 0.00002987 0.00003123
2100 2400 13 15 2406 2661 13 15 2406 2661 0.00006696 0.00008689
2100 2450 13 15 2406 2661 13 16 2406 2761 0.00003004 0.00003146
2100 2500 13 16 2406 2761 13 17 2406 2861 0.00002993 0.00002211
2100 2550 13 16 2406 2761 13 17 2406 2861 0.00003148 0.00003299
2100 2600 13 17 2406 2861 13 18 2406 2937 0.00003017 0.00003142
2100 2650 13 18 2406 2937 13 18 2406 2937 0.00005079 0.00007310
2100 2700 13 18 2406 2937 13 19 2406 3013 0.00003174 0.00005902
2100 2750 13 19 2406 3013 13 20 2406 3089 0.00003045 0.00003200
2100 2800 13 20 2406 3089 13 20 2406 3089 0.00005102 0.00007431
2100 2850 13 20 2406 3089 13 21 2406 3165 0.00005087 0.00006421
.....00.....
182
Table 8.18: Unit Commitment III the IEEE-RTS With
Export / Import (Export is backed up by the entire
exporting system).
Load Export Import No. of ISR
(MW) (MW) (MW) Units1 2 1 2 1 2 1 2 1 2
2400 2100 0 0 0 0 15 12 0.00003189 0.000077912400 2100 30 0 0 30 15 12 0.00004157 0.000077872450 2100 0 0 0 0 15 13 0.00003753 0.000011182450 2100 40 0 0 40 16 12 0.00003153 0.000077402500 2100 0 0 0 0 16 12 0.00003211 0.000078052500 2100 0 30 30 0 15 13 0.00006346 0.00003144
2550 2100 0 0 0 0 16 13 0.00003764 0.000011182550 2100 0 40 40 0 16 13 0.00003142 0.00003088
Table 8.19: Unit Commitment in the IEEE-RTS With
Export /Import (Export is backed up by a specificunit).
Load Export Import No. of ISR
(MW) (MW) (MW) Units1 2 1 2 1 2 1 2 1 2
2400 2100 0 0 0 0 15 12 0.00003189 0.000077912400 2100 30 0 0 30 15 12 0.00004159 0.000077902450 2100 0 0 0 0 15 13 0.00003753 0.000011182450 2100 40 0 0 40 16 12 0.00003150 0.000077402500 2100 0 0 0 0 16 12 0.00003211 0.000078052500 2100 0 30 30 0 15 13 0.00006350 0.000031402550 2100 0 0 0 0 16 13 0.00003764 0.000011182550 2100 0 40 40 0 16 13 0.00003145 0.00003085
•
Table 8.20: Unit Commitment in the IEEE-RTS with Interruptible Load.
Single System Interconnected System
Load No. of Capacity No. of Capacity ISR
(MW) Units (MW) Units (MW)
1 2 1 2 1 2 1 2 1 2 1 2
2100 2100 12 12 2251 2251 13 13 2406 2406 0.00000378 0.00000378
2100 2150 12 12 2251 2251 12 13 2251 2406 0.00003722 0.00001112
2100 2200 12 12 2251 2251 13 13 2406 2406 0.00000425 0.00001100
2100 2250 12 13 2251 2406 13 13 2406 2406 0.00000430 0.00001171
2100 2300 12 13 2251 2406 12 14 2251 2561 0.00002528 0.00001130
2100 2350 12 13 2251 2406 13 14 2406 2561 0.00000426 0.00001116
2100 2400 12 14 2251 2561 12 15 2251 2661 0.00002532 0.00001136
2100 2450 12 14 2251 2561 13 15 2406 2661 0.00000426 0.00001122
2100 2500 12 14 2251 2561 12 16 2251 2761 0.00002536 0.00001143
2100 2550 12 15 2251 2661 13 16 2406 2761 0.00000426 0.00001128
2100 2600 12 15 2251 2661 12 17 2251 2861 0.00002540 0.00001149
2100 2650 12 16 2251 2761 13 17 2406 2861 0.00000426 0.00001134
2100 2700 12 16 2251 2761 13 18 2406 2937 0.00000426 0.00001086
2100 2750 12 17 2251 2861 13 18 2406 2937 0.00000439 0.00001194
2100 2800 12 17 2251 2861 13 19 2406 3013 0.00000426 0.00001137
2100 2850 12 18 2251 2937 13 20 2406 3089 0.00000426 0.00001086
�00w
184
tion. It is noted in Chapter 5, that an interconnected system can carry an
additional load/interruptible load on top of its firm load without having to
commit any additional capacity than that required to carry the firm load
and still maintaining the risk criteria. This can de illustrated by an ex
ample. Consider a firm load of 2040 MW in IEEE-RTS-1 and 2520 MW in
IEEE-RTS-2. IEEE-RTS-1 and IEEE-RTS-2 must commit 12 and 16 units
respectively from their loading order priority" list. If the firm load and unit
commitment in each system is unchanged then IEEE-RTS-2 can carry an ad
ditional load of up to 50 MW given that the additional load in IEEE-RTS-1
is zero. The additional load carrying capability of IEEE-RTS-2 reduces to a
maximum of 40 MW if IEEE-RTS-1 carries an additional load of 10 MW.
This capability will change with any change in firm load or unit commit
ment in anyone of the interconnected utilities.
The percentiles of hourly peak load variations in a 24 hour scheduling
period in each IEEE-RTS are identical to those considered for the RBTS.
The annual peak load of the IEEE-RTS is 2850 MW. The hourly peak load
variations in each IEEE-RTS during the specified 24 hour scheduling periodare shown in Table 8.2l. The unit commitment during the same 24 hour
scheduling period is shown in Table 8.22. This table also shows the number
of units that should be committed in each IEEE-RTS and the corresponding
hourly spinning reserve during the 24 hour scheduling period.reserve in IEEE-RTS-1 varies from 145 MW to 455 MW.
reserve in IEEE-RTS-1 during the peak load of 2850 MW IS
The spinningThe spinning
239 MW. The..
spinning reserve in IEEE-RTS-2 varies from 135 MW to 282 MW. Table
8.23 shows for comparison purposes, the unit commitment schedule for both
IEEE-RTS-1 and IEEE-RTS-2 with no interconnection between them. Both
systems are required to satisfy a unit commitment risk of 0.0001 which 1S
equal to the specified ISR. The overall spinning reserve requirements In
both IEEE-RTS-1 and IEEE-RTS-2 are higher in the case of no interconnec
tion than those of with interconnection.
185
Table 8.21: Peak Load Variations of IEEE-RTS III a 24 HourPeriod.
Hour L1(MW) L2(MW)
1 1910 17762 1796 16703 1710 15904 1682 15645 1682 15646 1710 15907 2109 19618 2451 22799 2708 2518
10 2736 254411 2736 254412 2708 251813 2708 251814 2708 251815 2651 246516 2679 249117 2822 262418 2850 265119 2850 265120 2736 254421 2594 241222 2366 220023 2081 193524 1796 1670
Tables 8.24 and 8.25 show the economic load dispatch in IEEE-RTS-l
and IEEE-RTS-2 respectively for the 24 hour unit commitment shown in
Table 8.22. These economic load dispatches, however, do not satisfy the 5
minute response criterion. Risk constrained economic load dispatch has
been obtained for both IEEE-RTS assuming that all hydro units are run of
the river generating units without any energy constraints. The transmission
and tie-line losses have been neglected III determining the load dispatch. A
reloading step of 5 MW has been used to modify the economic load dispatchinto the risk constrained economic load dispatch. The risk constrained load
dispatch in IEEE-RTS-l is shown in Table 8.26. The corresponding dispatch
186
Table 8.22: Unit Commitment In the IEEE-RTS (24 hour
scheduling period) .
Hour IEEE-RTS-l IEEE-RTS-2
No. of SpinningUnits Reserve(MW)
No.of
UnitsSpinning
Reserve(MW)
1
23
45
678
9
10
11121314
15161718192021
222324
1910
179617101682
16821710210924512708273627362708270827082651267928222850
285027362594
236620811796
1212
1111
11
1113151818
1818181818
18192020
1816141310
1776167015901564
15641590196122792518
25442544251825182518
2465249126242651
265125442412220019351670
10109
999
11141616
1616161615
15171717
16151311
10
165271154
180180154
135282243
217217243
243243196170237
210210217249
206161271
341
455386414
414386297210229
201
201229229229286258
191239239201167195325145
In IEEE-RTS-2 IS shown In Table �.27. Generating units In each of the
IEEE-RTS have been dispatched such that the total spinning capacity In
each system has enough response reserve to satisfy the 5 minute regulating
margin. The running cost of each 50 MW hydro unit in the IEEE-RTS is
the lowest of all units. These hydro units are dispatched to their full out
put level to obtain greater savings as shown in the economic load dispatchIn Tables 8.24 and 8.25. The response rate of these hydro units IS the
highest among units of the IEEE-RTS. In the risk constrained load dis
patches shown in Tables 8.26 and 8.27 some of these hydro units are used
187
Table 8.23: Unit Commitment in the IEEE-RTS Without Inter-connection (24 hour scheduling period).
Hour IEEE-RTS-l IEEE-RTS-2
L1 No. of Spinning L2 No.of Spinning(MW) Units Reserve(MW) (MW) Units Reserve(MW)
1 1910 13 496 1776 12 4752 1796 12 455 1670 11 4263 1710 12 541 1590 11 5064 1682 11 414 1564 11 5325 1682 11 414 1564 11 5326 1710 12 541 1590 11 5067 2109 14 452 1961 13 4458 2451 17 410 2279 16 4829 2708 21 457 2518 18 419
10 2736 21 429 2544 19 46911 2736 21 429 2544 19 46912 2708 21 457 2518 18 41913 2708 21 457 2518 18 419
14 2708 21 457 2518 18 41915 2651 21 514 2465 18 47216 2679 21 486 2491 18 44617 2822 26 403 2624 20 46518 2850 28 415 2651 20 43819 2850 28 415 2651 20 43820 2736 21 429 2544 19 46921 2594 19 419 2412 17 44922 2366 17 495 2200 15 46123 2081 14 480 1935 13 47124 1796 12 455 1670 11 426
Table 8.24: Economic Load Dispatch in the IEEE-RTS-i.
Load
(MW)Individual Unit Outputs
(MW)
HourLl xl X2 X3 X4 X5 X6 X7 Xs X9 XlO Xu Xl2 X13 X14 X15 X16 Xl7 XIS X19 X20 X2l
11910 50
21796 50
31710 50
41682 50
51682 50
61710 50
72109 50
82451 50
92708 50
102736 50
112736 50122708 50
132708 50
142708 50
152651 50
162679 50
172822 50
182850 50
192850 50
202736 50212594 50
222366 50
232081 50
50 50
50 50
50 50
50 50
50 50
50 50
50 50
50 50
50 50
50 50
50 50
50 50
50 50
50 50
50 50
50 50
50 5050 50
50 50
50 50
50 50
50 50
50 50
50 400 400 350 84 83 83 155 155
50 400 400 280 80 80 80 138 138
50 400 400. 315 80 80 80 155
50 400 400 295 80 80 80 14750 400 400 295 80 80 80 14750 400 400 315 80 80 80 155
50 400 400 350 98 98 98 155 155 155
50 400 400 350 139 138 138 155 155 155 155 66
50 400 400 350 153 153 152 155 155 155 155 68
50 400 400 350 161 161 161 155 155 155 155 69
50 400 400 350 161 161 161 155 155 155 155 69
50 400 400 350 153 153 152 155 155 155 155 68
50 400 400 350 153 153 152 155 155 155 155 68
50 400 400 350 153 153 152 155 155 155 155 68
50 400 400 350 136 136 135 155 155 155 155 66
50 400 400 350 144 144 144 155 155 155 155. 67
50 400 400 350 164 163 163 155 155 155 155 70
50 400 400 350 150 149 149 155 155 155 155 68
50 400 400 350 150 149 149 155 155 155 155 68
50 400 400 350 161 161 161 155 155 155 155 69
50 400 400 350 161 161 162 155 155 155 155 70
50 400 400 350 132 132 132 155 155 155 155
50 400 400 350 89 89 88 155 155 155
241796 50 50 50 50 400 400 350 149 149 148
6869696868
6866677068
68
6970
68
69696868
6866
677068
68
69
767676767676767676767676
.....0000
767676
7676
Table 8.25: Economic Load Dispatch in the IEEE-RTS-2.
Load
(MW)Individual Unit Outputs
(MW)
HourL2 xl x2 X3 X4 X5 x6 X7 X8 X9 XlO Xu Xu Xl3 x14 Xl5 Xl6 Xl7 xl8 xl9 X20 X21
11776 50 50 50 50 400 400 350 142 142 14221670 50 50 50 50 400 400 350 107 107 10631590 50 50 50
41564 50 50 50
51564 50 50 5061590 50 50 5071961 50 50 50
82279 50 50 50
92518 50 50 50102544 50 50 50112544 50 50 50122518 50 50 50132518 50 50 50
142518 50 50 50152465 50 50 50162491 50 50 50172624 50 50 50182651 50 50 50192651 50 50 50
202544 50 50 50212412 50 50 50222200 50 50 50
231935 50 50 50241670 50 50 50
50 400 400 350 120 12050 400 400 350 107 10750 400 400 350 107 10750 400 400 350 120 12050 400 400 350 152 152 152 15550 400 400 350 103 103 103 155 155 155 15550 400 400 350 139 139 138 155 155 155 155 66 6650 400 400 350 146 146 146 155 155 155 155 68 6850 400 400 350 146 146 146 155 155 155 155 68 6850 400 400 .350 139 139 138 155 155 155 155 66 6650 400 400 350 139 139 138 155 155 155 155 66 6650 400 400 350 139 139 138 155 155 155 155 66 6650 400 400 350 143 143 142 155 155 155 155 6750 400 400 350 151 151 151 155 155 155 155 6850 400 400 350 150 150 150 155 155 155 155 68 68 6850 400 400 350 158 158 158 155 155 155 155 69 69 6950 400 400 350 158 158 158 155 155 155 155 69 69 6950 400 400 350 146 146 146 155 155 155 155 68 6850 400 400 350 126 126 125 155 155 155 155 6550 400 400 350 128 128 129 155 155 15550 400 400 350 144 143 143 15550 400 400 350 107 107 106
I-'00to
Table 8.26: Risk Constrained Economic Load Dispatch in theIEEE-RTS-1 (Reloading step = 5 MW).
Load
(MW)Individual Unit Outputs
(MW)
HourLl xl x2 x3 x4 Xs x6 x7 Xg Xg XIO xll x12 Xu Xu xIS x16 x17 xIS x19 x20 X21
11910 50 40
21796 0 0
31710 20 0
41682 0
51682 0
61710 20
72109 50
82451 50
92708 50
102736 50
112736 50
122708 50
132708 50
142708 50
152651 50
162679 50
172822 50
182850 50
192850 50
202736 50
212594 50
222366 50
o 0
o 0o 0
50 50
50 50
50 50
50 50
50 50
50 50
50 50
50 50
50 50
50 5050 50
50 50
50 50
50 50
50 50
50 50
o 50 400 400 305 84 163 158 130 130
o 20 400 400 280 105 165 160 133 133
o 50 400 400 305 80 165 160 130
40 400 400 295 90 165 160 132
40 400 400 295 90 165 160 132
50 400 400 305 80 165 160 130
50 400 400 310 98 153 153 130 130 135
50 400 400 350 139 138 148 155 155 150 150
50 400 400 350 153 153 152 155 155 155 155
50 400 400 350 161 161 161 155 155 155 155
50 400 400 350 161 161 161 155 155 155 155
50 400 400 350 153 153 152 155 155 155 155
50 400 400 350 153 153 152 155 155 155 155
50 400 400 350 153 153 152 155 155 155 155
50 400 400 350 136 136 150 155 155 130 135
50 400 400 350 144 144 144 155 155 145 15050 400 400 350 164 163 163 155 155 155 155
50 400 400 350 150 149 149 155 155 155 155
50 400 400 350 150 149 149 155 155 155 155
50 400 400 350 161 161 161 155 155 155 155
50 400 400 350 161 161 162 155 155 155 155
50 400 400 350 132 137 137 155 155 150 150
232081 50 50 30 50 400 400 305 89 159 158 130 130 130
241796 50 50 50 50 400 400 350 149 149 148
6668696968
6868
81
6770
6868
6970
686969
68
6868
81827073736970
6869
69686868767770686869
76767676767666
6676767676
I-'
8
76
7171
7676
Table 8.27: Risk Constrained Economic Load Dispatch in the
IEEE-RTS-2 (Reloading step = 5 MW).
Load
(MW)Individual Unit Outputs
(MW)
HourL2 xl X2 x3 X4 x5 x6 x7 Xs X9 xlO Xu X12 Xl3 X14 Xl5 Xl6 Xl7 XIS Xl9 X20 X21
11776 50 50 50
21670 50 50 10
31590 50 50 50
41564 50 50 50
51564 50 50 50
61590 50 50 50
71961 50 50 50
82279 50 50 50
92518 50 50 50
102544 50 50 50
112544 50 50 50
122518 50 50 50
132518 50 50 50
142518 50 50 50
152465 50 50 50
162491 50 50 50
172624 50 50 50
182651 50 50 50
50 400 400 350 142 142 142
50 400 400 305 107 147 151
50 400 400 350 120 120
50 400 400 325 122 11750 400 400 325 122 11750 400 400 350 120 120
50 400 400 350 152 152 152 15550 400 400 350 103 153 148 130 130 130 135
50 400 400 350 139 139 138 155 155 140 145
50 400 400 350 146 146 146 155 155 155 155
50 400 400 350 146 146 146 155 155 155 155
50 400 400 350 139 139 138 155 155 140 145
50 400 400 350 139 139 138 155 155 140 145
50 400 400 350 139 139 138 155 155 140 145
50 400 400 350 143 143 142 155 155 155 155
50 400 400 350 151 151 151 155 155 155 155
50 400 400 350 150 150 150 155 155 150 155
50 400 400 350 158 158 158 155 155 155 155
192651 50 50 50 50 400 400 350 158 158 158 155 155 155 155
202544 50 50 50 50 400 400 350 146 146 146 155 155 155 155
212412 50 50 50 50 400 400 350 126 126 165 155 155 130 135
222200 50 50 50 50 400 400 350 128 138 139 155 145 145
231935 50 50 50 50 400 400 350 144 143 143 155
241670 50 50 10 50 400 400 305 107 147 151
8168
688181816768
686969 6968 6870
7668
68767676
.....
!O.....
7369
68
6969
192
as response reserve unit whenever necessary. The running cost during the 24
hour period is $635,592.69 in IEEE-RTS-1 and $573,102.13 in IEEE-RTS-2
when the units are dispatched economically. The starting cost is $623.21 in
IEEE-RTS-1 and $766.29 in IEEE-RTS-2. During the 24 hour period the
reliability constrained economic dispatch require an addiitonal running cost of
$22,132.69 in IEEE-RTS-1 and $5,492.75 in IEEE-RTS-2 compared to the
respective economic load dispatch. The computation time required to modifythe economic load dispatch into the risk constrained economic load dispatchas shown in Tables 8.26 and 8.27 is 11.44 CPU seconds.
8.4. Summary
The unit commitment and spmnmg reserve assessment techniques based
on the 'Two Risks Concept' have been applied to two different reliability
test systems. The unit commitment and spinning reserves which satisfy the
two risk levels are presented in this chapter. The results of risk constrained
economic load dispatch in interconnected RBTS and IEEE-RTS are also dis
cussed. The computer programs developed can also assess spinning reserve
and unit commitment risk in interconnected systems using other assumptionsthan those utilised in this chapter.
193
9. CONCLUSIONS
This thesis presents a new probabilistic technique to assess spmnmg
reserve requirements in interconnected systems. The technique is based on
the fulfilment of two specified risk levels in each interconnected system. An
interconnected system must satisfy the single system risk (SSR) at the ISO
lated level and also the interconnected system risk (ISR) at the intercon
nected level. The philosophy behind the new technique is designated as the
'Two Risks Concept'. The basic principles of the 'Two Risks Concept' are
developed and discussed in detail in Chapter 3. Spinning reserve assessment
involving the 'Two Risks Concept' utilises the essential stochastic parameters
of the generating units and tie lines which influence the system reliability.
The proposed technique uses conventional generating unit models. Improvedmodels for generating units and tie lines can, however, be readily incor
porated into the computational process of the new technique. Rapid start
and hot reserve units can be included in the assessment of unit commitment
risk. The area risk curve technique has been extended to include rapid start
and hot reserve units into the spinning reserve and unit commitment risk as
sessment process. The matrix multiplication technique has been used to
determine the transient probabilities of rapid start and hot reserve units.
In the 'Two Risks Concept', the unit commitment and spinning reserve
In one system is affected by the unit commitment and spinning reserve of
neighbouring system(s). System independence is lost when this system is in
terconnected with another system where the objective is to provide and/orreceive assistance in regard to spinning reserve. In the case of a dominant
SSR, the unit commitment of an interconnected system is primarily dictated
by the SSR. The system with a smaller SSR, therefore, has to spin more
194
generating capacity than the system with a higher SSR for identical load and
generating sets. Despite being identical in regard to load and generation
sets, a system will have to maintain more spinning reserve than its neighbour because of its decision to select a lower SSR. It is, therefore, desirable
to have a single SSR for all participating systems. In the case of a
dominant ISR, the unit commitment and spinning reserve is dictated by the
ISR itself. It is, however, difficult to obtain a dominant ISR level. The
dominance can be shifted from the ISR to the SSR or vice versa with
changes in load level, generation etc.. The level of assistance that an inter
connected system can provide to its neighbour is dependent on the tie line
capacity. The level of assistance generally increases with an increase in tie
capacity provided other factors remain the same. The assistance , however,saturates when the tie capacity is increased beyond a certain level. The tie
capacity beyond which the available assistance saturates depends on generat
ing units, unit commitment risk, spinning reserve etc.. The effect of one
single parameter on this level will vary from one set of interconnected sys
tems to another. These effects should be examined in each case.
Load forecasting in any system involves some degree of uncertainty.The proposed probabilistic technique can include load forecast uncertainty in
the assessment of spinning reserve and unit commitment risk. The probabil
ity distribution of the forecast load can be represented by a discrete distribu
tion. The computation time required to determine the spinning reserve re
quirements in an interconnected system increases with an increase in the
number of steps used in the load distribution. Examples with seven-step
and three-step approximations to a normally distributed load are shown in
Chapter 3.
Interconnected systems export/import energy to/from neighbouring sys
tems. Usually the export/import between two or more interconnected sys
tems is governed by agreements between the utilities concerned. The nature
of these agreements vary widely. Two basic export/import agreements have
195
been considered in this thesis. The agreements are: 1) firm purchase by one
system backed up by the complete system of the exporting utility and 2)firm purchase tied to a specific unit in the exporting utility. Methods have
been illustrated in this thesis to assess spinning reserve in interconnected sys
tems with export/import using risk constraints based on the 'Two Risks
Concept' . The method can easily be extended to accommodate other
export / import agreements.
Interruptible loads can be included in the unit commitment risk assess
ment of interconnected systems using the area risk technique. Interruptibleloads can be considered to be equivalent to ready reserve depending upon
the allowable time delay associated with the interruptible loads. It is
generally appreciated that interruptible loads can reduce the system risk.
There has been relatively little work done on the development of systematic
quantitative approach to determine the effects of interruptible loads in singleor in interconnected systems. A probabilistic method has been developed to
assess the magnitude of curtailable load and the corresponding maximum al
lowable time delay before which the load must be interrupted to maintain
the system risk level equal to or less than a specified value. The same
method, with little modification, has also been used to determine the ad
ditional load/interruptible load carrying capability of a power system. Inter
ruptible loads can be included in the risk assessment process either by an
equivalent load approach or by an equivalent generating unit approach.Both approaches to incorporating interruptible loads provide identical results.
,
Important probabilistic features of interruptible loads and additional load car-
rying capability have been developed. Based on the principles created for
isolated system applications, techniques have been developed to study the ef
fects of having interruptible loads in an interconnected system. These
developments are reported in this thesis.
A generation system can carry additional load or additional interruptible load on top of its firm load without committing additional generation
196
above that required to carry the firm load. This capability depends on the
operating set of generating units, the firm load and the specified unit com
mitment risk. In addition to these factors, the additional load/interruptibleload carrying capability of an interconnected system also depends upon the
operating conditions and unit commitment within the neighbouring system.
The additional load/interruptible load that an isolated or an interconnected
system can carry in addition to the firm load without violating the unit
commitment risk is not a unique quantity. There is at any moment,
however, a unique set of additional loads/interruptible loads and correspond
ing lead times. This set will change with a change in the operating units
even if the firm load and the specified unit commitment risk remain un
changed. The minimum additional load/interruptible load carrying capabilityof a system can be determined for a specific scheduling period. These con
cepts can be used in short and medium term operational planning.
The 'Two Risks Concept' has been used to develop unit commitment
schedules on a continuous basis for a specified period. Units have been com
mitted according to a predetermined loading order such that a specified SSR
level is satisfied at the isolated system level and a specified ISR level is also
satisfied at the interconnection level. The determination of a priority loadingorder for the generating units in a system is not discussed in detail in this
thesis as this activity IS outside the scope of this research work. Different
utilities use different approaches to determine their priority loading order
based on accepted economic and operating goals. Once the units are
scheduled in each hour of the scheduling period, the stopping and restartingtime of each unit is delayed or advanced if such modification results in ac
ceptable savings. This advancing or delaying of the stopping and restartingtimes are based on a tentative economic load dispatch and forecast load
during the scheduling period. A method of determining risk constrained unit
commitment on a continuous basis is presented in this thesis. This proce
dure can easily be implemented in interconnected systems.
197
Economic load dispatch does not normally consider probabilistic aspects
of the response capability of a system. A reliable load dispatch should be
such that an interconnected system must be able to respond with enoughreserve capacity to maintain dynamic stability, loss of generation or un
foreseen load changes within an allowable margin time. In the terms of the
'Two Risks Concept', each interconnected system must maintain enough
responding reserve for the specified margin times such that a specified SSRR
is satisfied at the isolated system level and a specified ISRR is satisfied at
interconnected level. Chapter 7 presents a technique for obtaining a risk
constrained economic load dispatch starting from an economic load dispatch.The computation time required to modify an economic load dispatch into a
risk constrained economic dispatch is insignificant. The computation time in
creases with a decrease in the reloading step used to modify the economic
load dispatch. An increase in the reloading step size, however, moves the
risk constrained economic load dispatch further away from the initial
economic point. Each individual pool must use its own judgement in
selecting an appropriate reloading step. Several assumptions have been made
in the development of the risk constrained economic load dispatch technique.The most important assumptions are that the transmission and tie line losses
are negligible and that all hydro units are run of the river type. Transmis
sion and tie line losses can be included in the reloading process by includingthe change in losses due to the change in reloading a unit. Any appropriatetransmission loss formula can be used for this purpose with a sacrifice in
computation time. The algorithm that modifies the economic load dispatchinto a risk constrained economic load dispatch is simple in concept and can
.
be implemented in interconnected systems with little difficulty.
•
Two reliability test systems are utilised in order to illustrate the tech
niques presented in this thesis. The results of studies on spmnmg reserve
requirement, unit commitment and reliability constrained load dispatch in in
terconnected RBTS and interconnected IEEE-RTS are presented in this
thesis. The methods presented can easily be implemented in small or large
power systems.
198
I
The spinning reserve assessment technique presented in this thesis is
based on the stochastic behaviour of the system components. The proposed
technique advances the method of spinning reserve assessment III intercon
nected systems and provides a framework within which a fair allocation of
spinning reserve among the interconnected utilities can be achieved. The
techniques presented in this thesis are very practical and incorporate important operating practices.
199
REFERENCES
1. A. V. Jain, R. Billinton, "SpinningPower System", IEEE Paper No.
IEEE/PES Winter Meeting, NewFebruary 2 1973.
Reserve Allocation in a ComplexC 73 097-3 , Presented at the
York, New York, January 28 -I2. Adarsh V. Jain, Operating Reserve Assessment in Multi-Interconnected
Systems, PhD dissertation, University Of Saskatchewan; Saskatoon,Canada, 1972.
3. R. Billinton and R. N. Allan, Reliability Evaluation of Power Systems,Longmans (England) I Plenum Press, New York, 1984.
4. R. Billinton, A. V. Jain, "Interconnected System Spinning ReserveRequirements", IEEE Transactions on Power Apparatus and Systems,Vol. PAS-91, March/April 1972, pp. 517-526.
5. R. Billinton, A. V. Jain, "Power System Spinning Reserve Determination in a Multi System Configuration", IEEE Paper No. T72 �02-6,Presented at the IEEE Summer Power Meeting, San
Francisco,California, July 9-14 1972.
6. . Raymond R. Shoults, Show Kang Chang, Steve Helmick, W. MackGrady, "A Practical Approach to Unit Commitment, Economic Dispatch and Savings Allocation For Multiple-area Pool Operation WithImport Iexport Constraints", IEEE Transactions on Power Apparatusand Systems, Vol. PAS-99, No.2, MarchiApril 1980, pp. 625-633.
7. Nathan Cohn, "Methods of Controlling Generation on InterconnectedPower System", AlEE Paper 60-846, Presented at AlEE SummerGeneral Meeting, Atlantic City, N. J., June 19-24 1960.
8. P. G. Lowery, "Generating Unit Commitment by DynamicProgramming", IEEE Transactions on Power Apparatus and Systems,Vol. PAS-85, No.5, May 1966, pp. 422-426.
9. R. H. Kerr, J. L. Scheidt, A. J. Fontana, J. K. Wiley, "UnitCommitment", IEEE Transactions on Power Apparatus and Systems,Vol. PAS-85, No.5, May 1966, pp. 417-421.
10. H. H. Happ, R. C. Johnson, ·W. J. Wright, "Large Scale Hydro-
200
Thermal Unit Commitment-Method and Results", IEEE Transactionson Power Apparatus and Systems, Vol. PAS-90, May/June 1971, pp.1373-1382.
11. K. Hara, M. Kimura and N. Honda, "A Method for PlanningEconomic Unit Commitment and Maintenance of Thermal Power
Systems", IEEE Transactions on Power Apparatus and Systems, Vol.
PAS-85, No.5, May 1966, pp. 427-436.
12. John A. Muckstadt and Richard C. Wilson, "An Application of
Mixed-Integer Programming Duality to Scheduling Thermal GeneratingSystems", IEEE Transaction on Power Apparatus and Systems, Vol.
PAS-87, No. 12, Dec. 1968.
13. E. B. Dahlin and D. W. C. Shen, "Optimal Solution to the HydroSteam Dispatch Problem for Certain Practical Systems", IEEE Transaction on Power Apparatus and Systems, Vol. PAS-85, No.5, May1966, pp. 437-458.
14. 1. Hano, Y. Tamura and S. Narita, "An Application of the Maximum
Principle to the Most Economical Operation of Power Systems", IEEETransactions on Power Apparatus and Systems, Vol. PAS-85, No.5,May 1966, pp. 486-494.
15. John J. Shaw, Dimitri P. Bertsekas, "Optimal Scheduling of LargeHydrothermal Power Systems", IEEE Transactions on Power Apparatus and Systems, Vol. PAS-_104, No.2, February 1985, pp.286-294.
16. T. N. Saha, S. A. Khaparde, "An Application of a Direct Method to
the Optimal Scheduling of Hydrothermal System", IEEE Transactionson Power Apparatus and Systems, Vol. PAS-97, No.3, May/June1978, pp. 977-983.
17. J. D. Guy, "Security- Constrained Unit Commitment", IEEE Transactions on Power Apparatus and Systems, Vol. PAS-90, May/Jun
1971, pp. 1385-1389.
18. Bruce F. Wollenberg, Kenneth A. Fegley, "A Cost Effective SecurityDispatch Methodology", IEEE Transactions on Power Apparatus and
Systems, Vol. PAS-95, No.1, January/February 1976, pp. 401-409.
19. R. Billinton and R. N. Allan, "Power System Reliability m
Perspective", lEE Electronics and Power, Mar 1984, pp. 231-236.
20. M. S. Bartlett, An Introduction to Stochastic Processes With SpecialReference to Methods and Applications, The Syndics of the CambridgeUniversity Press, London, 1966.
21. E. B. Dynkin, translated from the Russian by D. E. Brown, edited byT. Kovary, Theory of Markov Processes, Prentice-Hall Inc., EnglewoodCliffs, N.J./Pergamon Press, London, 1961.
I22.
23.
24.
25.
26.
27.
28.
29.
•
201
E. B. Dynkin, translated from the Russian by J. Fabius,V. Greenberg, A. Maitra, G. Majone, Markov Processes, AcademicPress Inc., Publishers New York, N. Y., Vol. I, 1965.
R. Billinton and R. N. Allan, Reliability Evaluation of EngineeringSystems: Concepts and Techniques, Longmans (England)/ Plenum
Press, New York, 1983.
L .. T. Anstine, R. E. Burke, J. E. Casey, R. Holgate, R. S. John andH. G. Stewart, "Application of Probability Methods to the Determination of Spinning Reserve Requirements for the Pennsylvania-NewJersey-Maryland Interconnection", IEEE Transactions on Power Apparatus and Systems, Vol. PAS-821963, pp. 726-735.
Kamal Debnath, Reliability Modelling of Power System ComponentsUsing the CEA-ERIS Data Base, PhD dissertation, University Of Sas
katchewan, Saskatoon, Canada, June 1988.
R. Billinton, Nurul A. Chowdhury, "Operating Reserve Assessment InInterconnected Generating Systems", IEEE Transactions on Power Apparatus and Systems, Vol. PAS-3, No.4, November 1988, pp.1479-1487.
Robert H. Miller, Power System Operation, McGraw-Hill Book Com
pany, New York, New York, 1970.
Leon K. Kirchmayer, Economic Control of interconnected Systems,John Wiley & Sons, Inc., New York/Chapman & Hall, Ltd., London,1959.
N. Chowdhury, R. Billinton, "Assessment of Spinning Reserve in Interconnected Generation Systems With Export/Import Constraints", IEEE
Paper No. WP 89-65, Accepted for Presentation at the IEEE/PES1989 Winter Meeting, New York, New York, January 29 - February 31989.
J. 1. Nish, N. A. Millar, "Generating System Operating Reserve As
sessment Practices Used by Canadian Utilities", Canadian Electrical
Association, Power system Planning and Operation Section, SpringMeeting1984.
31. R. Billinton, N. A. Chowdhury, "Operating Benefits of InterruptibleLoads", Presented at the 1988 Spring Meeting of Canadian Electrical
Association/Power System Planning and Operating Section, Montreal,Quebec, March 16-21 1988.
30.
32. N. Chowdhury, R. Billinton, "Interruptible Load Carrying Capabilityof a Generation System", IEEE Paper No. 88 SM 652-0 , Presentedat the IEEE/PES Summer Meeting, Portland, Oregon, July 24 - 291988.
202
34. James G. Waight, Farrokh Albuyeh, Anjan Bose, "Scheduling of
Generation and Reserve Margin Using Dynamic and Linear
Programming", IEEE Transactions on Power Apparatus and Systems,vei. PAS-100, No.5, May 1981, pp. 2226-2230.
35. A. K. Ayoub, A. D. Patton, "Optimal Thermal Generating Unit
Commitment", IEEE Transactions on Power Apparatus and Systems,Vol. PAS-90, No.4, July/August 1971, pp. 1752-1756.
36. Richard Bellman, Dynamic Programming, Princeton University Press,Princeton, N.J., 1957.
37. Richard E. Bellman, Stuart E. Dreyfus, Applied DynamicProgramming, Princeton University Press, Princeton, N.J., 1962.
38. George L. Nemhauser, Introduction to Dynamic Programming, John
Wiley and Sons Inc., New York, New York, 1966.
39. 1. Megahad, N. Abou-Taleb, M. Iskandrani, A. Moussa, "A ModifiedMethod for Solving the Economic Dispatching Problem", IEEE Transactions on Power Apparatus and Systems, Vol. PAS-96, No.1,January/February 1977, pp. 124-132.
40. T. H. Lee, D. H. Thorne, E. F. Hill, "Modified Minimum Cost Flow
Dispatching Method for Power System Application", IEEE Trans
actions on Power Apparatus and Systems, Vol. PAS-100, No.2,February 1981, pp. 737-744.
41. W. O. Stadlin, "Economic Allocation of Regulating Margin", IEEE
Transactions on Power Apparatus and Systems, Vol. PAS-90, JulyAugust 1971, pp. 1776-1781.
42. Chaw Lam Wee, A Frequency and Duration Approach for GeneratingCapacity Reliability Evaluation, PhD dissertation, University Of Sas
katchewan, Saskatoon, Canada, 1985.
43. H. H. Happ, "Optimal Power Dispatch", IEEE Transaction on Power
Apparatus and Sy.stems, Vol. PAS-93, No.3, 1974, pp. 820-830.
44. R. Billinton, S. Kumar, N. Chowdhury, K. Chu, K. Debnath, L. Goel,E. Khan, P. Kos, G. Nourbakhsh, J. Oteng-Adjei, "A Reliability Test
System for Educational Purposes - Basic Data", IEEE Paper No. 89
WM 035-7-PWRS, Presented at the IEEE/PES 1989 Winter Meeting,New York, New York, January 29 - February 3 1989.
203
Appendix A
Equivalent Capacity Model
A.I. A Recursive Algorithm for Capacity Model Building
A simple recursive algorithm can be used to create a capacity model of
a generation system [3}. The technique is applicable for multi-state units as
well as for two-state units. Consider System X in Chapter 2 with a lead
time of two hours. Table A.l shows the probability of failure of the units
in System X in 2 hours.
Table A.l: Probability of Failure of Units in System X.
Unit Probability of Failure
3 x 40 MW3 x 20 MW4 x 10 MW
0.000913240.000684930.00068493
The capacity outage probability table IS created sequentially usmg
Equation (2.11) as follows:
Add the first unit
P(O) = (0.99908676)(1.0) + (0.00091324)(1.0) = 1.0
P(40) = (0.99908676)(0) + (0.00091324)(1.0) = 0.00091324
Add the second unit
P(O) = (0.99908676)(1.0) + (0.00091324)(1.0) = 1.0
P(40) = (0.99908676)(0.00091324) + (0.00091324)(1.0) = 0.00182565
P(80) = (0.99908676)(0) + (0.00091324)(0.00091324) = 0.00000083
Add the third unit
P(O) = (0.99908676)(1.0) + (0.00091324)(1.0) 1.0
204
P(40) = (0.99908676)(0.00182565) + (0.00091324)(1.0) = 0.00273722
P(80) = (0.99908676)(0.00000083) + (0.00091324)(0.00182565) = 0.00000250
P(120) = (0.99908676)(0) + (0.00091324)(0.00000083) = 0.00000000
The remaining units -in System X can be added in a similar manner.
The resulting capacity model in the form of a capacity outage probabilitytable after adding all 10 units in System X is shown in Table A.2.
Table A.2: Capacity Outage Probability Table of System X.
Capacity In Capacity Out Cumulative
(MW) (MW) Probability
220 0 1.00000000
210 10 0.00750879
200 20 0.00478778190 30 0.00274422
180 40 0.00273863
170 50 0.00001559
160 60 0.00000812
150 70 0.00000252
140 80 0.00000250
A similar approach is followed in adding an equivalent assistance unit
to the on-line capacity model of a system .
•
Ji
,205
Appendix B
Determination of Interruptible Load
Carrying Capability of an InterconnectedGeneration System
B.I. Computational Algorithm
If the actual ISR of an interconnected power system is less than the
specified ISR, the system may be able to carry some additional load or ad
ditional interruptible load on top of its firm load without having to modify
its unit commitment from what is required to satisfy the firm load. The ad
ditional load/interruptible load carrying capability of an interconnected sys
tem among many things also depends on the firm load and unit commitment
of the neighbouring systems. A set of additional load/interruptible load and
the corresponding lead time of a system can be derived provided the firm
load and additional load/interruptible load of the neighbours are known.
There could be as many sets of solution as the assumptions regarding the
additional load/interruptible load of the neighbouring systems.
Assume that
T = total study period,Rs = specified SSR,
Ri = specified ISR,. Rsa = actual SSR of System A,
Rsb actual SSR of System B,
Ria = actual ISR of System A,
Rib = actual ISR of System B,L fa
= firm load of System A,L fb
= firm load of System B,tmin = minimum allowable time delay for load interruption,
206
additional load of °a
In System A with a lead time of Ta'
additional load of 0b in System B with a lead time of Tb'
set of additional loads in System A for additonal load of
(Ob,Tb) in System B,
set of additional loads III System B for additonal load of
(Oa,Ta) in System A.
For each (Oa,Ta) in System A there will be a corresponding set of ad
ditional load/interruptible load, Sb(8 ,T) in System B. To start the com-, a a
putation it is assumed that the additional loads can be tolerated for' the en
tire period of T. To derive all possible sets of additional loads in System A
and B, °a
and 0b can be assumed zero to start with. A set of additional
loads and corresponding lead times in System B can be derived for each ad
ditional load (0a,Ta) in System A provided the additional load in A satisfies
the SSR criterion. If the additional load in A does not satisfy the SSR
criterion Ta
is modified as
T ...... T -Ata a
where
At is the discrete time step in minutes,
before the computation proceeds any further. After the SSR criterion of
System A is satisfied ()b is updated to ()b+A1, where Al is the discrete incre
ment in additiotnal load. If all the risk criteria are met, (()b+A/,Tb) becomes
an element of the set Sb(Oa,Ta). In the case where any of the risk criterion
is not met the lead time of the addiitonal load is modified acording to the
following conditions.
If Rsb> R" the lead time Tb IS modified as
207
If R < R R > Rand R > R Tb is modified assb - 8' ia i ib i
T -+ T -Cita a
and the computations for a new set of additional load/interruptible load In
System B begins.
When Tb reches to a value such that Tb � tmin, the additional load
(Oa,Ta) of A is updated to (Oa+Ci1,Ta) and a new set of calculations start to
determine the additional load/interuptible load of B with a starting value of
(O,T). The computation stops when Ta � tmin0
The computation time depends on the selection of Cil,Cit and tmin0 In
this thesis Cil,Cit and t min is taken as 5 MW, 5 minutes and 2 minutes
respectively.