22
Oak Ridge National Lab ORNL/SNS Spallation Neutron Source Safety Program Overview Samuel McKenzie ESH Coordinator Accelerator Systems Division April 13, 2005 1

Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Spallation Neutron SourceSafety Program Overview

Samuel McKenzieESH Coordinator

Accelerator Systems Division

April 13, 2005

1

Page 2: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Spallation Neutron Source

• The SNS will begin operation in 2006.• At 1.4 MW it will be ~8x ISIS, the world’s leading pulsed spallation source.• SNS will be the world’s leading facility for neutron scattering.• It will be a short drive from HFIR, a reactor source.

SNS Site – 2004

2

Page 3: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

SNS will be World-Class!

3

Page 4: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

SNS Accelerator Complex

945 ns

1 ms macropulse

mini-pulse

Cur

rent

H- stripped to protons

Front-End:Produce a 1-msec long,

chopped, low-energy H-

beam

LINAC:Accelerate

the beam to 1 GeV

Cur

rent

1ms

Accumulator Ring:Compress 1 msec long

pulse to 700 nsec

Deliver beam to Target

Chopper system makes

gaps

4

Page 5: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

SNS High Level Baseline Parameters

Proton beam energy on target 1.0 GeV

Proton beam current on target 1.4 mA

Power on target 1.4 MW

Pulse repetition rate 60 Hz

Beam macropulse duty factor 6.0 %

H- peak linac current 38 mA

Ring fill time 1.0 ms

Ring beam extraction gap 250 ns

Protons per pulse on target 1.5x1014

Proton pulse width on target 695 ns

Linac length 335 m

Total Beamline Length 903 m

5

Page 6: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Facility Parameters

Area size of construction site 86 acres

Access and service roads 5 miles

Quantity of excavation at completion 1.5 MCY

Concrete 88,000 CY

Structural Steel 4,870 T

Electrical power (connected load) 78 MVA

Electrical power (operational demand) 49 MVA

Cooling water (heat load rejection) 37.4 MW

Cooling Tower water peak flow rate 21,000 gpm

Size of buildings and structures 616,000 sq ft

Site occupancy, including users, up to 500 persons

6

Page 7: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Target Systems

• Converts up to 2 MW of 1 Gev Protons at 60 Hz into useful shortneutron pulses.

• Major Subsystems– Mercury target. – 3 Supercritical hydrogen moderators with associated cryogenic

systems and one ambient water moderator.– Beryllium reflector system.– Core vessel for target, moderator, reflectors.– 10 m diameter iron shielding with shutters for neutron beams.– Utility systems including heavy and light water.– Remote Handling systems. – Instrumentation and controls.– Linac, Ring Injection and Ring Extraction beam dumps.

7

Page 8: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Target Building and Instrument Layout

18 - Wide Angle Chopper Spectrometer –IDT DOE Funded –Commission 2007

17 - High Resolution Chopper Spectrometer –DOE Funded (SING) –Commission 2008

13 - Fundamental Physics Beamline –IDT Funding TBD –Commission TBD

11A - Powder Diffractometer –SNS Funded –Commission 2007

12 - Single Crystal Diffractometer –DOE Funded (SING) –Commission 2009

9 - Engineering Diffractometer –IDT CFI Funded –Commission 2008

6 - SANS –SNS Funded –Commission 2007

5 - Cold Neutron Chopper Spectrometer –IDT DOE Funded –Commission 2007

4A - Magnetism Reflectometer –SNS Funded –Commission 2006

3 - High Pressure Diffractometer –DOE Funded (SING) –Commission 2007

2 - Backscattering Spectrometer –SNS Funded –Commission 2006

1B - Disordered Mat’ls Diffractometer –DOE Funded (SING) –Commission 2010

PROTONS

4B - Liquids Reflectometer –SNS Funded –Commission 2006

14B - Hybrid Spectrometer –DOE Funded (SING) –Commission 2011

15 – Spin Echo

? – Chemical Spectrometer

60 m

8

Page 9: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Target Region Within Core Vessel

Core Vessel water cooled shielding

Core Vessel Multi-channel flange

Outer Reflector Plug

Target Inflatable seal

Target Module with jumpers

9

Page 10: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

History of SNS

• In 1998 DOE Broke Ground on the SNS with Critical Decision 4 (end of Project) in 2006

• In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National Lab.

• Later that Year a “New” SNS Project Director was Hired and given Equal Status with the ORNL Lab Director.

• A Stream-Lined Safety Program was Envisioned with Little if any ties to ORNL.

• In 2002 a “New” Project Director was Hired and placed SNS Back Under the Direction of ORNL.

10

Page 11: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Standards Based Management System (SBMS)

• A Proven System That Both PNNL and BNL Utilizes. Additionally INL will soon begin their Implementation Process.

• Creates “One Stop Shopping” for Work Control and the Standards that the Work Shall and/or Should Follow

• Clearly Defines ALL the Necessary Steps Needed to Perform a Certain Task.

11

Page 12: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Safety Overview

• Since 2000, SNS (Non-Construction) has had 15 Recordable Injuries and Illnesses (RIIs) Cases and 1 Day with Restrictions Case (2002).

• Additionally, ASD has 3 situations where there were violations of Internal Posting and/or Procedures (i.e. Lock Out Tag Out, Internal Parameters, etc.).

The injury rate at SNS remains exemplary (1.2 per 200,000 hours), and we must continue to strive for a continued safe work environment. In the coming months, we (SNS) will assume responsibility for the craft labor contract from Knight-Jacobs. This means we will be directly responsible for their attitude of, andcommitment to, safety.

12

Page 13: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National
Page 14: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Electrical Systems

• By far our most dangerous activity is working on de-energized electrical systems, circuits and panels.

• ASD has systems in every facet of its operation that utilizes high currents, voltages and/or capacitances!

• A rigorous Lock Out Tag Out (LOTO) program is a must. • Our LOTO program serves us well and each group has a Safety

Officer responsible for compliance with both NEC and SNS rules.

• Additionally, we have offered over 10 Electrical Safety Classes that deal with the various aspects of our electrical equipment.

14

Page 15: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Research Safety Summaries

• Research Safety Summaries (RSSs) are prepared at the Group and Lab Level. – Identify hazards a particular group is exposed to in their

work. – Assist the Group Leader in determining the appropriate

training and controls that need to be in place prior to performing work.

– Defines the complete list of SBMS requirements for that Group.

15

Page 16: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Job Hazard Analysis

• Job Hazard Analysis (JHA) - lynchpin of our Safety Program – process CLEARLY understood by all ASD employees and is

the basis of Integrated Safety Management (ISM). Work is defined in well understood steps.Associated hazards determined at each step. Action(s) established to mitigate hazards (i.e., safety glasses, erect a scaffolding, etc.). Perform work within JHA guidelines.

– JHAs are routinely reevaluated for completeness and enhancement.

– Worker driven program with constant feedback on how we can continue to make the work safer.

16

Page 17: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

ASD Example 1Hoisting and Rigging

• On Nov 5, 2001 An Employee at our old Receiving Facility was in the process of Lifting a Dipole Magnet when One of the Eye Bolts Failed.

• As a Result of this Event we (ASD) instituted a Formal Process of Developing a Lift Plan for all our Lifts. A detailed JHA is Prepared and the Documentation is reviewed by one of a Select Group of Mechanical Engineers

• The Lab’s Program is Modeled after ours and Our External Accelerator Review Committee has made several statements complimenting us on the rigor and completeness of our Hoisting and Rigging Program

17

Page 18: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

ASD Example 2Lock Out Tag Out

• On Nov 22, 2002 An Employee was inspecting a Lock and Tag applied to a Circuit Breaker in the Klystron Building when the tag came off in the employee’s hand. The incident was not properly reported.

• As a Result of this Event we (ASD) immediately provided a LOTO Practical Factors Training Program for all Affected Employee. As a result of finding additional deficiencies we provided LOTO Verification Training.

• ASD has always employed the OSHA Required Equipment Specific LOTO Process. The lab’s program now employs this process as well.

18

Page 19: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Where There’s Smoke…..There’s not ALWAYS A Fire!

• On Sept 9, 2004 An Evacuation of the Linac Tunnel, Klystron Gallery and Front End Building Occurred while we where Commissioning our Warm Accelerator (~150 MeV). This evacuation was due to Our Early Detection Smoke Alarm System.

19

Page 20: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Smoke Event Cont’

• This evacuation occurred due to a Cryogenic Gas System heater being in close Proximity to Canvas Bags containing Steel Shot that is used for shielding Purposes. The 2 kW Heater is normally used during the Initial Cryomodule fill process. For our 4 Kelvin cool down the system remained in place ~1 month. Due to Thermocouple Placement and other factors the system did not respond properly and cause the pipe to Overheat.

20

Page 21: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Smoke Event cont’

• This Overheating never caused an open flame fire but did burn several Canvas Bags that Held the Steel Shot.

21

Page 22: Spallation Neutron Source Safety Program Overview(end of Project) in 2006 • In 2000 the University of Tennessee and Battelle Teamed to win the Contract to Manage Oak Ridge National

Oak Ridge National Lab ORNL/SNS

Conclusion

• SNS has done a wonderful job of developing a concise system embracing SBMS and ISM to build a world class accelerator facility!

• We have to continue to learn from our own mistakes and from others.• We have to be open and honest about our mistakes as well as our

successes.• We must Continue to understand what we want to do before we

perform the Work (ISM).

• We have to recognize that the hazards within our divisions continue to increase as we go into operation with more and more very powerful equipment

• We have to be aware, that we share issues. Perform work in offices, storage buildings etc that carry their own risk, which usually is not as obvious as the technical ones.

22