Upload
isabel
View
36
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Southern Natural Gas Company 2013 Outage Review Meeting. Customer con call and Webex June 19, 2013. Welcome. Agenda. Review Unscheduled Outages (None at this time) Review of Upcoming Outages June/July & August North System South System South Louisiana - PowerPoint PPT Presentation
Citation preview
1
Southern Natural Gas Company2013 Outage Review Meeting
Customer con call and WebexJune 19, 2013
2
Welcome
Agenda
• Review Unscheduled Outages (None at this time)
• Review of Upcoming Outages– June/July & August
• North System
• South System
• South Louisiana
– Outages for the remainder of 2013• North System
• South System
• South Louisiana
• Contacts 3
Disclaimers
• Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary.
• Unless otherwise stated, all scheduled dates represent gas days as defined in the Southern Natural Gas Pipeline tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time).
• Scheduled dates are subject to change.
• Projects may be added, altered, delayed or cancelled.
• SNG will provide notice of such additions or changes via SoNet Premier postings.
• Dates as posted on SoNet should be deemed correct in the event of conflicts between SoNet posted dates and dates within this presentation.
4
Color Key for Maps
• Green– No Impact Anticipated
• Yellow– Restrictions are possible– With extended duration, restrictions could be
necessary from time to time– Meter(s) affected are denoted with (M)
• Red– Restrictions are probable
5
6
Southern Natural Gas Pipeline
LA
MS
AL
GA
FL
Enterprise
White Castle
Bear Creek
Muldon
Chattanooga
Atlanta
Thomaston
Albany
Elba
SCAiken
Elba Express
North System
South Louisiana
South System
Compressor Station
Storage FieldLNG
Pearl River
Franklinton
Gwinville
7
SNG North SystemMaintenance Review June/July & August
LA
MS
AL
GA
Logansport
Bienville
Bear Creek Storage
Onward
Pickens
Rankin
Louisville
Muldon Storage
Reform
McConnells
Providence
TarrantPell City
DeArmanville
Bell Mills
Rome
Compressor Station
Storage Field
Huntsville
Chattanooga
Atlanta
Southern will be conducting other general maintenance during this period
Bear Creek1 unit down startingJune 17 for 8 weeks
Muldon field outage starting7/15/13 to 7/19/13 and
7/22/13 to 7/26/13Storage restrictions possible
Receipt cuts on North system possible
8
SNG South SystemMaintenance Review June/July & August
MS
AL
GA
Enterprise
Gwinville
SelmaAuburn
Ellerslie
Thomaston
Ocmulgee
Hallgate
Wrens
Elmore
York
Gallion
Bay Springs
Compressor Station
Storage FieldLNG
Atlanta
Elba
Hartwell
Elba ExpressAiken
Holy Trinity
Albany
Pavo
Brookman
Riceboro
Pressure Test on the 30” South Main 2nd Loop and 24” South Main Loop
(one line at a time) 6/1/13 thru 7/31/13 Cap reduced up to 170 MMcf/d
Southern will be conducting other general maintenance during this period
Selma unit maintenance 6/3/13 thru 6/30/13
Cap reduced up to 200 MMcf/d
Elmore station outage 6/17/13 thru 6/27/13
Cap reduced up to 200 MMcf/d
Maintenance on the8” Demopolis Line
7/8/13 thru 7/25/13(M) 801400 Demopolis #1
(M) 801900 Citadel Cement
Auburn unit maintenance 6/24/13 thru 7/24/13
Enterprise Station Outage7/15/13 until sometime in
October Rose Hill (M) 504001
Cap reduced up to 400 MMcf/d
Rose Hill (504001 and 504002) Station shut-in 7/15/13 for 6
weeks.
Pipeline relocation work related to DOT highway
relocation 7-29-13 thru 8-13-13
10-25-13 thru 11-9-13Capacity reductions may occur
Anomaly digs on the 10” mainlinePavo C/S to end of line
AugustPressure reduction could impact capacity
Selma unit maintenance 7/29/13 thru 8/7/13
9
SNG South Louisiana System Maintenance Review June/July & August
Shadyside
White Castle
Franklinton
Toca
Gwinville
LAMS
Compressor Station
Storage Field
West Leg
East Leg
Pressure Test 24” WC-Franklinton LoopUnder way through the end of June
Cap reduced up to 400 MMcf/d(M) 601400 Sugar Bowl #6
White Castle, ShadysideUnit Maintenance
Scheduled During Pipeline Outage
Pearl River
Southern will be conducting other general maintenance during this period
10
SNG North System Maintenance Review remainder of 2013
LA
MS
AL
GA
Logansport
Bienville
Bear Creek Storage
Onward
Pickens
Rankin
Louisville
Muldon Storage
Reform
McConnells
ProvidenceTarrant
Pell City
DeArmanville
Bell Mills
Rome
Compressor Station
Storage Field
Huntsville
Chattanooga
Atlanta
Bear Creek Fall Shut-in Test 10/15/13 thru 10/21/13
DIQ and DWQ allocated 64%
Muldon Fall Shut-in Test 10/01/13 thru 10/07/13
DIQ and DWQ allocated 36%
Pressure Test 2nd North MainEast of Louisville
9/12/13 thru 10/8/13North system receipts may be reduced
Muldon inj & w/d may be limitedSouthern will be conducting other general
maintenance during this period
Pressure Test 2nd North MainEast of Reform
10/13 thru 11/13Capacity reduced significantly
Impact being evaluated
Pipe replacement North Main loop line West of Dearmanville
OctoberNo Capacity reductions anticipated
11
SNG South SystemMaintenance Review remainder of 2013
MS
ALGA
Enterprise
Gwinville
SelmaAuburn
Ellerslie
Thomaston
Ocmulgee
Hallgate
Wrens
Elmore
York
Gallion
Bay Springs
Compressor Station
Storage FieldLNG
Atlanta
Elba
Hartwell
Elba ExpressAiken
Holy Trinity
Albany
Pavo
Enterprise Station Outage7/15/13 until sometime in October
Rose Hill (M) 504001Cap reduced up to 400 MMcf/d
Brookman
Riceboro
Maintenance on the 16” South Main Loop 4 weeks in OctoberCap reduced up to 50 MMcf/d
Southern will be conducting other general maintenance during this period
Selma unit maintenance
In October
Auburn unit maintenance
In November
12
SNG South Louisiana SystemMaintenance Review remainder of 2013
Shadyside
White Castle
Franklinton
Toca
Gwinville
LA
MS
Compressor Station
Storage Field
West Leg
East Leg
Pearl River
White Castle, ShadysideUnit Maintenance
Mid September - mid October
Southern will be conducting other general maintenance during this period
13
Gas Control Contacts • Nancy Barton – Manager
(713) – 420 – 6191 (office) (713) – 204 – 4815 (cell) [email protected]
• Kalman (Kal) Dankovich – Outage Coordinator (713) – 420 – 7522 (office) (205) – 325 – 7305 (Gas Control) [email protected]
• Jerry Peterson – Operations Analyst (205) – 325 – 7345 (office) (205) – 325 – 7305 (Gas Control) [email protected]
• Paul Reed – Operations Analyst (205) – 325 – 7655 (office) (205) – 325 – 7305 (Gas Control) [email protected]
14
Questions?