South Massachusetts Avenue Corridor Safety Improvements Public Meeting #2| June 19, 2018

South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

South Massachusetts Avenue Corridor Safety Improvements

Public Meeting #2| June 19, 2018

Page 2: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

• Welcome

• Project Background

and Process

• Analysis and

Conceptual Design

• Discussion/Plan ReviewBreak-Out Session

AgendaMassachusetts Avenue – Sidney Street to Memorial Drive

Page 3: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

PROJECT BACKGROUND

Municipal Policies

Complete Streets are designed and operated to enable safe access for all users –regardless of age, ability, or mode of transportation (2016).

Vision Zero calls for the elimination of fatalities and serious injuries resulting from traffic crashes, and emphasizes that they can, and should be prevented (2016).

Vehicle Trip Reduction Ordinance established programs to encourage alternatives to single-occupancy vehicle travel (1992).

Cambridge Growth Policy emphasizes sustainable modes of transportation such as walking, biking and using transit and low-emission vehicles, which promote livability and help to improve air quality and reduce greenhouse gas emissions (1993/2007).

Page 4: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

PROJECT BACKGROUND

From Plans to Actions

Page 5: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

Existing ConditionsLafayette Square to the Charles River

from Sidney Street to Memorial Drive

5

CORRIDOR INFORMATION

Page 6: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

Existing Conditions Mass. Ave. Cross-Section (at Amherst Street)

✓ 88’ wide

✓ On-street bike lane

✓ On-street vehicle

parking

✓ Mix of meters and

other parking

✓ Bus stops

✓ Curb extensions at

multiple locations

14’Sidewalk

9’Parking

12’Travel

11’Travel

8’Parking

13’Sidewalk

5’Bike

Lane

11’Travel

5’Bike

Lane

CORRIDOR INFORMATION

Page 7: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

PROJECT BACKGROUND

Flexible Implementation

Based on Policies and Plans and

direction of City leadership:

• Evaluate and implement “quick

build” solutions to enhance the

comfort and promote sustainable

transportation for people walking,

biking, driving and using transit

✓ Designs that are flexible after

implementation

✓ Modifications possible based on

evaluation (including feedback)

Page 8: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

CORRIDOR INFORMATION

Corridor Safety HistoryReported Crashes Requiring EMS Transport, 2015-2016

8

Page 9: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

CORRIDOR INFORMATION

Safety History Reported Bicycle Crashes, 2015-2016

9

Project Limits

Page 10: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

10

CORRIDOR INFORMATION

People Bicycling

Throughout the entire

corridor length, users experience the second

lowest level of comfort.

Page 11: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

People Walking

11

CORRIDOR INFORMATION

✓ Local and regional

destinations and

connections

✓ Evaluating ease

and comfort of

crossing at and

between

intersections

Walking in this

corridor:

Page 12: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

Transit ServiceMBTA Bus Route 1: PM Peak

Method: Automatic Passenger Counter (APC) Data (MBTA)

CORRIDOR INFORMATION

Composite Grade

Excellent (A)

Good (B)

Satisfactory (C)

Unsatisfactory (D)

Poor (E)

Failing (F)

N/A

Failing Areas

MIT

Page 13: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

Project Goals

✓ Address safety

issues and reduce

crashes - Vision Zero

✓ Reduce transit

delays

✓ Enable/encourage

people of all ages

and abilities to choose sustainable

transportation

Page 14: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

Public Process✓Appointed Advisory Committee

✓ Met three times

✓Wikimap online

✓ Survey online and feedback at

public meetings

✓Outreach to Businesses

✓ Direct meetings with local businesses

✓ Coordination with CSBA

✓ Individual Stakeholder meetings

✓ Transit/Ped/Bike Committees

✓Communitywide Meetings

✓ Posted and electronic

announcements

Page 15: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

Public Feedback✓Need for safer conditions for bicyclists

✓ Motorists and delivery vehicles block bike lanes✓ Desire for greater separation from moving vehicles

✓Need for additional crosswalks traversing Mass

Ave

✓Desire to improve transit operations

✓Concerns about unpredictable ridesharing, tour

bus, food truck, commercial loading & pick-

up/drop-off activity

✓ Relocate MIT-related tour buses loading/unloading

✓Concerns about long vehicle queues, traffic at

Vassar Street

✓Minimize conflicts✓ Bus/bike conflicts✓ Bike/ped conflicts esp. at 77 Mass Ave.

Page 16: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

16

CORRIDOR INFORMATION

Transportation/Traffic Analysis

Corridor-wide transportation analysis to

determine where:

✓ Bus lanes can be added

✓ Vehicle lanes can be repurposed

✓ Signal operations can be modified

✓ Bicycle lanes can be separated

✓ Bicycle buffers can be added

✓ Parking can be re-located for better operations

Page 17: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

South Mass. Ave. Corridor

Draft Design – Before and After

Before After

Page 18: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

18

CORRIDOR INFORMATION

Transportation/Traffic AnalysisThree Main Sections

Corridor has been divided into 3 sections for clarity:

Sid

ney

St

Section 1:Sidney St to Albany St

Section 2:Albany St to Vassar St

Section 3:MIT

Page 19: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

19

CORRIDOR INFORMATION

Transportation/Traffic AnalysisCross Sections

• The three general cross sections (intersections vary)

1919

Section 1:Sidney St to Albany St

Section 2:Albany St to Vassar St

Section 3:MIT

19

Most Complicated

Page 20: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

20

Section 1:Sidney St to Albany St

Section 2:Albany St to Vassar St

Section 3:MIT

Sid

ney

St

20

CORRIDOR INFORMATION

Transportation/Traffic AnalysisBus Facilities

Bus lanes proposed for two sections, to address the key areas of delay

Page 21: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

21

CORRIDOR INFORMATION

Transportation/Traffic AnalysisBus Facility Details - Before

Page 22: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

22

CORRIDOR INFORMATION

Transportation/Traffic AnalysisBus Facility Details - After

Page 23: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

23

CORRIDOR INFORMATION

Transportation/Traffic AnalysisBus Facility Details

Bus lanes at intersections:

Right turning motorists may use bus lane

National Precedent

Design Sample

Page 24: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

24

CORRIDOR INFORMATION

Transportation/Traffic AnalysisBus Facility Details

Bus Lanes

with Parking

(example)

Boston, MA - Wikimedia Commons

Page 25: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

25

CORRIDOR INFORMATION

Transportation/Traffic AnalysisBicycle Facilities

For most of the corridor, separated bike lanes can be created using on-street parking and flex posts.

25

Section 1:Sidney St to Albany St

Section 2:Albany St to Vassar St

Section 3:MIT

Sid

ney

St

25Flexpost/Parking Protection

Bike Lanes

Page 26: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

Bicycle FacilitiesSeparated Bike Lane – Parking Protected

DESIGN OVERVIEW

Parking Protected Bicycle Lanes (examples)

Page 27: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

Bicycle FacilitiesBike Lane with Curbside Parking

DESIGN OVERVIEW

Curbside Parking / Accessible Parking (examples)

Page 28: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

28

DESIGN OVERVIEW

Parking Facilities

282828

Denver, CO

Floating Accessible Parking

Design follows federal and state standards

Page 29: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

Bus Stop OptionsDESIGN OVERVIEW

Bus stop at curbFloating bus stop

(possible future consideration)

Page 30: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

30

CORRIDOR INFORMATION

Bus Stop Options

Modular floating bus stop under evaluation

Los Angeles, CA

(possible future consideration)

Page 31: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

31

CORRIDOR INFORMATION

Vehicle Parking Analysis

Section 1:Sidney St to Albany St

Section 2:Albany St to Vassar St

Section 3:MIT

Sid

ney

St

• Two new loading zones

• Re-arranged loading zones

• Seven fewer metered spaces out of 51 metered spaces (due to added crosswalk, loading zones and sight lines)

• Sufficient parking availability on side streets

No Change

• No parking eastbound (six fewer)

• New pick-up/drop-off spaces

westbound

• Change metered parking westbound

(12) to loading, pickup-dropoff,

added space for bus stop

• Maintain food truck location

• Clearer MBTA boarding/alighting

areas

Parking Modifications

LZ LZMMM

Page 32: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

32

Proposed Design Three Main Sections

Section 1:Sidney St to Albany St

Page 33: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

33

Proposed Design Section 1: Sidney St to Albany St (A)

Sid

ney

St

Bla

nche

St

DRAFT

Page 34: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

34

Proposed Design Section 1: Sidney St to Albany St (B)

DRAFT

New Crosswalk

& RRFB (rectangular rapid flash beacon

Page 35: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

35

Proposed Design Section 1: Sidney St to Albany St (C)

DRAFT

New Crosswalk

& Rectangular Rapid Flash Beacon

Page 36: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

36

Proposed Design Section 2: Albany St & Vassar St

DRAFT

Bike signal

&

Right-turn lane

Page 37: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

37

Proposed Design

Mass. Ave

DRAFT

Potential future opportunity to

increase space for bicyclists by

modifying curb extensions

Bike signal &right-turn laneseparate movements

Page 38: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

38

Proposed Design

Mass. Ave

DRAFT

Bike signal &right-turn laneseparate movements

Vehicle Movement

Page 39: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

39

Proposed Design

Mass. Ave

DRAFT

Bike signal &right-turn laneseparate movements

Bicycle MovementPedestrian Movement

Page 40: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

40

CORRIDOR INFORMATION

Proposed Design Three Main Sections

Section 3:MIT

Page 41: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

41

Proposed Design Section 3: MIT (A)

DRAFT

Bike signal at 77 Mass Aveto ensure unconflictedcrossing for people walking.

Page 42: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

42

Proposed Design Section 3: MIT (B)

Mem

oria

l Dr

DRAFT

Am

hers

t St

Remove MBTA Bus Stop,

consistent with MBTA Service Plan

Page 43: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

43

CORRIDOR INFORMATION

Possible Future Additions

Section 1:Sidney St to Albany St

Section 2:Albany St to Vassar St

Section 3:MIT

Sid

ney

St Crosswalks?

Bus stop relocations?

Bus stop relocations?

To Be Evaluated

? Additional crosswalk/RRFB in Section 1

? Move bus stops to the far side of intersections (for better operations)

? Construct modular (or permanent) floating bus stops

? Remove/modify curb extensions to allow better bicyclist protection

? Work with state DCR and MassDOT on changes at Memorial Dr. and bridge

Page 44: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

ScheduleBicycle,

pedestrian,

traffic

counts

April

Refine design

May - August

Public

Meeting #1

May 3

Parking study

Week of April

30Implementation

Late Summer

2018

Evaluation

Advisory

Committee

Meetings #2-3

May, June

NEXT STEPS

Advisory

Committee

Meeting #1

April 11

Public Meeting

#2/Open House

June 19

Page 45: South Massachusetts Avenue Corridor Safety Improvements · South Mass Ave Corridor Safety Improvements Project: Community Meeting #2 Presentation 6-9-18 - Cambridge Massachusetts

South Mass. Ave. Corridor Safety Improvements

Breakout Discussion

45

NEXT STEPS

Project Website: http://www.cambridgema.gov/CDD/Projects/Transportation/southmassave

Contact: Bill Deignan, Community Development, [email protected]

Chris Balerna, Kleinfelder Project Manager, [email protected]

More Information and Contact

Section 1:Sidney St to Albany St

Section 2:Albany St to Vassar St

Section 3:MIT

Sid

ney

St

LZ LZMMM