Upload
others
View
14
Download
0
Embed Size (px)
Citation preview
IEEE ICC Education SessionOctober 23, 2019
Presenter: Michael Smalley, Principal Engineer, WEC Energy Group
Co Authors: Steven Schott, Ross Barrette, Michael Smalley
SMRP - System Modernization
and Reliability Project
System Information
• 446,000 Electric Customers
• 98% of Electrical System is 24.9 kV
• ASCC: 3,600 Amps, RMS, Sym.
1
Project background
2
SAIDI COMPARISONS
WPS 6-year SAIDI average (336.39)
was higher than the averages
of other state utilities
over the same period
(160.17 minutes)
3
Outage comparisons by territory• 33,167 customers (7.6%)
experienced an average of
5+ outages per year
• 72% of those outages were located
in high density forest areas
• 5,413 customers (1.2%)
experienced an average of
10+ outages per year
• 90% of those outages were located
in high density forest areas
4
Lines to be replaced
• Distribution feeders are radial
• Typical 24.9 KV distribution feeder in rural areas can
run up to 50 circuit miles in one direction
• Advantages
– Fewer substations
– Improved voltage profile
– Fewer losses
• Disadvantages
– Longer radial lines
5
SMRP Phase 1• Optimize performance and cost
• Reliability improvement of 25%
• Move from 3rd/4th quartile to 2nd
quartile
• Add Distribution Automation –
400 miles
• Replace overhead primary
distribution with underground,
focus on areas and feeders
with the worst SAIDI (1000 to
1200 miles over 5 years)
• Total project cost $218 million
• Construction in years 2014
through 2018
6
SMRP Phase 2
• Underground an additional 960 miles
• No distribution automation
• Reliability improvement of 17%
• Project cost $211.5 million
• Construction in years 2018 through 2021
• Yes, we’re in Phase 2 already!
7
PROJECT CYCLE
• Identify and prioritize the overhead
circuits that would provide the
maximum reliability benefit for the
cost investment
• Begin to contact customers and
gauge overall interest in project• Begin Field Design, Collecting
assets, and creation of Construction
Prints
• Environmental Walk-throughs
• General Permitting and Applications• Send out Easement Drawings to
Customers and Begin to Acquire
Necessary Easements• Staking and Construction
• Removal of Existing Overhead
Facilities
• Complete As-Builts and update
GIS
8
Project challenges• Safety
• Customer communications
• Easement obtainment
• No locates for design
• Environmental constraints
• Weather – local and nationwide
• Other facilities in the ground
9
Rock
Availability of skilled workforce
Contractors are performing energization
and cutovers
Quality of installations (PD testing)
Indian reservation construction
9
• Wood turtle
• Bald eagle
• Osprey
• Loggerhead shrike
• Red shouldered hawk
• Little brown bat
• Hine’s emerald dragonfly
• Blanchard’s cricket frog
• Spruce grouse
• Cerulean warbler
• Eastern ribbon snake
• Black tern, Foster’s tern
• Kirtland’s warbler
• Hooded warbler
• Henslow’s sparrow
Threatened and endangered animals encountered
10
Environmental monitoring
11
SMRP safety performance to date• 1,200,000 hours of installation
• 7 OSHA incidents
• 2 Lost Time Incident
• OSHA RIR = 1.19
• Industry avg. RIR = 2.80
12
Installation Techniques• Open Cutting (2%)
• Plowing (50%)
• Vibratory plowing(>75%)
• Plug plowing (<25%)
• Boring (48%)
• Directional
• Pneumatic boring
13
Vibratory Plowing
14
“Plug” Plowing Equipment
15
16
17
18
Typical DA Scheme
19
Total
Phase I & II1994 382 434 155 (46%)
SMRP Year Miles URD
Cable
Miles Main
Line
w/DA
Spend
(million $)
Projected
SAIDI
(minutes)
Phase I
2012-2013 - - 6 -
2014 203 48 33 18
2015 229 103 47 19
2016 228 78 56 22
2017 283 99 61 23
2018 151 54 39 10
Phase II
2017 - - 2.5 -
2018 137 - 18 6
2019 274 - 64 26
2020 273 - 64 14
2021 216 - 35 17
2022 - - 2 -
20
System Modernization and Reliability Project
• 2014 – 2021 Segments replaced with underground cable (all districts)
• Percent improvement 16% Outage events
34% CMI
11% CI
Actual 2017
Outage Events
Avoided 2017
Outage Events
Actual 2017
Customer
Minutes of
Interruption
(CMI)
Avoided 2017
Customer
Minutes of
Interruption
(CMI)
Actual 2017
Customers
Interrupted (CI)
Avoided 2017
Customers
Interrupted (CI)
8,986 1410 215,148,840 72,000,000 508,521 60,000
21
System Modernization and Reliability Project
• 2014 – 2018 distribution automation schemes (all 13 schemes)
• Percent improvement 0% Outage events
2% CMI
8% CI
Actual 2017
Outage Events
Avoided 2017
Outage Events
Actual 2017
Customer
Minutes of
Interruption
(CMI)
Avoided 2017
Customer
Minutes of
Interruption
(CMI)
Actual 2017
Customers
Interrupted (CI)
Avoided 2017
Customers
Interrupted (CI)
8,986 0 215,148,840 6,000,000 508,521 36,000
22
System Modernization and Reliability Project
• Total SMRP underground installation and distribution
automation
• Percent improvement 16% Outage events
36% CMI
20% CI
23
System Modernization and Reliability Project
24
Additional Estimates for PH I (2014 – 2018)
• 1015 route miles of primary circuit
• 2,533 actual miles of primary
cable
• 80 route miles of secondary
• 128 miles of secondary cable
• 6,400 easements
• 3,680 new underground services
• Warehousing material throughput
doubled for the entire WPS
company
25
SMRP Cable System Materials
• 1 PH Transformers (15, 25, and 50 kVA)• Set on fiberglass box pads
• But flat pads not completely off the table yet
• Formerly included under oil arresters; now using elbow arresters
• Joints• Cold shrink with integral metallic shield and jacket exclusively
• Some push on joints were used in earlier years of PH 1
• Recently converted CS joints to 100% shear bolt connectors
• Terminations• 100% cold shrink silicone rubber terminations
• Separable Connectors• 200 A Loadbreak
• 600 Amp Dead Break having 200 bushings for testing and grounding purposes
• Junction Enclosures - Fiberglass• 200 A and 600 A
26
SMRP Materials - Cable
• Cable Sizes/Designs (all use 100% insulation levels)
• #1 Sol Al (Full Neutral) 25 kV JCN – Most Common Cable used
• #4/0 Strd Al (90% neutral and 1/3rd neutral) 25 kV JCN
• 750 kcmil Al (1/6th Neutral) 25 kV JCN
• Basic cable design as shown below:
• Note: Insulation is mostly TRXLPE, but EPR is also used
27
Solid or Sealed
Conductor
Interesting SMRP Facts
1. Contract installers are certified for installation of cable
accessories prior to working on site.
2. Shunt reactors are sometimes employed on long cable
lengths to control the “Ferranti Effect” due to cable
capacitance
3. When the PSCW approved the project, the use of
unjacketed (bare) concentric neutral cable was allowed
(and used)
• BCN cable is no longer being installed
4. On the application for the CA, the expected life for new
cable was indicated as:
60 years
28
• Some Examples of what we find:
SMRP Materials – New Cable Inspection
29
New Cable Inspection Data
30
• Inspecting new cable allows us
to monitor trends in cable
manufacture with time such as:
• Cable Insulation Thickness
• Eccentricity
• Insulation Cure
Project challenges
• Number 1 quality risk identified as
terminations and splices
• Put into place a system to hold
contractors accountable
• Partial discharge (PD) testing for all
personnel doing terminating
• Over 2,000 terminations/splices/ risers
tested
• One cable failure – due to backfill
material, one splice failure
• Contractors initialize each device they
terminate
31
PD (partial discharge) testing
32
Questions?
•
33