1 st Project Workshop and Kick-Off Meeting. Improvements in the Harmonized Seismic Hazard Maps for the Western Balkan Countries| SfP 984374 |. Skopje, 04-05 Oct 2012. Improvements in the Accelometric Data Bank and Selection of GMPEs. Radmila Salic, MSc. BSHAP | NATO SfP 984374 - PowerPoint PPT Presentation
Citation preview
Skopje, 04-05 Oct 2012
Radmila Salic, MSc.
1st Project Workshop and Kick-Off Meeting
Improvements in the Harmonized Seismic Hazard Maps for the Western Balkan Countries| SfP 984374 |
Improvements in the Accelometric Data Bank and Selection of GMPEs
Improvements in the Harmonized Seismic Hazard Maps for the Western Balkan Countries| SfP 984374 Skopje, 04-05 October 2012
BSHAP | NATO SfP 984374Working Packages
Improvements in the Harmonized Seismic Hazard Maps for the Western Balkan Countries| SfP 984374 Skopje, 04-05 October 2012
WP 2: STRONG GROUND MOTION DATA BASE AND GROUND MOTION PREDICTION MODELS
Leading Countries: Macedonia, Montenegro and TurkeyWP Duration: 21 months
1) Compiling the available strong ground motion data recorded by the improved seismic networks during BSHAP or previously occurred earthquakes using the outputs of earlier scientific projects;
2) Building a harmonized acceleometric databank by unifying the formats of the collected strong ground motion data;
3) Improving the databank by adding ground motion recording station information;
4) Investigation of available ground motion prediction models and their applicability to the region, comparison of results from different prediction models;
5) Final decision on the ground motion prediction models and their weights to be used in PSHA.
Improvements in the Harmonized Seismic Hazard Maps for the Western Balkan Countries| SfP 984374 Skopje, 04-05 October 2012
PHASE 1: COMPALING AVAILABLE STRONG GROUND MOTION DATA
Oct 2012 – June 2013
PHASE 1B2: Compiling the available strong ground motion data recorded by previously occurred earthquakes using the outputs of earlier scientific projects
PHASE 1B1: Compiling the available strong ground motion data recorded by the improved seismic networks during BSHAP project
PHASE 1A: Strong Motion Station Inventory(geographic location, field/building, instrument technical characteristics, soil type)BSHAP project stations & Other Stations
Improvements in the Harmonized Seismic Hazard Maps for the Western Balkan Countries| SfP 984374 Skopje, 04-05 October 2012
PHASE 2: BUILDING A HARMONISED ACCELEROMETRIC DATA BANK
Jan 2013 – Dec 2013
PHASE 2A1: Adopt common software for processing of the raw accelerogram data, developed and verified by wider Seismological Community; defining the component parameter values (peak, spectral values, duration, various intensity values…)
PHASE 2B: Creating a strong motion data base
PHASE 2C: Strong Motion Data Base – Web Access
PHASE 2A2: Software /Processing Training
Improvements in the Harmonized Seismic Hazard Maps for the Western Balkan Countries| SfP 984374 Skopje, 04-05 October 2012
PHASE 3: DATA BANK IMPROVMENTS BY ADDING GROUNG MOTION STATION INFORMATION
Oct 2012 – June 2013
PHASE 3A: Compiling the available ground motion stations information's
PHASE 3B: Site stations characterization (physical & mechanical parameters: vp, vs, γ, T)
Abu Dhabi Project exampleStation Book
Improvements in the Harmonized Seismic Hazard Maps for the Western Balkan Countries| SfP 984374 Skopje, 04-05 October 2012
PHASE 4: INVESTIGATION OF AVAILABLE GROUNG MOTION PREDICTION MODELS
Oct 2013 – June 2013
PHASE 4A: Collecting of available regional developed ground motion prediction models
PHASE 4C: Comparison of the results
PHASE 4B: Collecting of available developed ground motion prediction models for similar geographical regions
Akkar and Bommer (2010)Boore and Atkinson (2008)Cauzzi and Faccioli (2008)Bindi et al., (2009)
BSHAP-983054
Improvements in the Harmonized Seismic Hazard Maps for the Western Balkan Countries| SfP 984374 Skopje, 04-05 October 2012
PHASE 5: FINAL SELECTION OF GMPE’s
April 2013 – June 2013
PHASE 5A: Final Decision on GMPE’s
PHASE 5B: Assigning of weighting factors to be used in PSHA
Improvements in the Harmonized Seismic Hazard Maps for the Western Balkan Countries| SfP 984374 Skopje, 04-05 October 2012
Dynamic Plan for WP2
1
2
3
4
5