Simulator r&m

  • Upload
    sam

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

  • 7/31/2019 Simulator r&m

    1/19

    PROPOSALFOR

    SIMULATORR&M

    NTPC

  • 7/31/2019 Simulator r&m

    2/19

    COMPUTER : 32 bit GOULD SEL 32/77

    SUPPLIER : GOULD/ENCORE COMPUTER USA

    SOFTWARE : MPX-32 Rev. 1.5CSUPPLIER : SINGERLINK USA

    200 MW

    COMPUTER : 32 bit GOULD SEL 32/67

    SUPPLIER : GOULD/ENCORE COMP. USA

    SOFTWARE : MPX-32 Rev. 3.U02

    SUPPLIER : GOULD USA,SIEMENS GERMANY

    TEC/TEDS BANGLORE

    500 MW

    ABOUT THE SIMULATOR

    NTPC

  • 7/31/2019 Simulator r&m

    3/19

    OPERATING SYSTEM MPX 32

    PLANT SIMULATION SOFTWARE

    PLANT SIMULATION SOFTWARE CONSISTSOF MATH MODELS IN FORTRAN- &ASSEMBLY

    200 MW PLANT SOFTWARE HAS 32 MATHMODEL IN FORTRAN-77

    500 MW PLANT SOFTWARE HAS 85 MATHMODEL IN FORTRAN-77

    SOFTWAREDETAILSNTPC

  • 7/31/2019 Simulator r&m

    4/19

    SIM.COMPUTER MASTERCOMPUTER

    Dos/AOs

    DIs /AIs

    LAYOUT OF 200 MW

    SIMULATOR

    NTPC

  • 7/31/2019 Simulator r&m

    5/19

    DOs /AOs

    DIs / AIs

    COMPUTER

    SYSTEM

    LAYOUT OF 500 MW

    SIMULATOR

    NTPC

  • 7/31/2019 Simulator r&m

    6/19

    DOs /AOs

    DIs / AIs

    COMPUTER

    SYSTEM

    INTER FACE

    UNIT-1

    INTER FACE

    UNIT-1

    - - -4,3,2

    SOFT PANEL

    PROPOSED LAYOUT FOR

    200 / 500 MW SIMULATOR

    NTPC

  • 7/31/2019 Simulator r&m

    7/19

    PROBLEM BEING FACED

    OBSOLESCENCE

    CONTROL TECHNOLOGYDEVELOPMENT

    FREQUENT FAILURES

    HIGH MAINTENANCE COST

    NTPC

  • 7/31/2019 Simulator r&m

    8/19

    NEED FOR R&M

    As regards 500MW simulator is concerned,the computer and hard panel with instructorstation were supplied by M/s Siemens AG .Theyare no more in the simulator business.I/O

    interface system were supplied by M/s TataPower. They are not in a position to give timelysupply of I/O cards and reliability is notfoolproof. Procurement and proper functioningof these cards have been taking even 2 years.The

    prices of I/O cards are very high, on the groundthat most of the components used are nowobsolete & have to be procured at a higher cost.

    We are facing same problem in 200MW

    simulator.

    NTPC

  • 7/31/2019 Simulator r&m

    9/19

    Views about R&M: Minutes on the discussion of technical team in NTPC

    held on 06/08/04-R&M of the existing 200mw & 500MWsimulator are required as advised by D(Opn.) and ED(OS).

    Letter ref 01/PMI/Sim.upg/2004-Minutes of meeting,where D(HR) was present-It was felt that simulator200MW & 500MW are panel based and new technology(CRT based) simulators have come up in the market,wewould immediately go to renovate both the simulator.

    M/s RTEDELTEC Corp. ,supplier of UPS system onKorba visits-Your unit have been out of production over20 years and there are no spares/parts available for them.My suggestion for you to replace your unit with a current

    model.

    NEED FOR R&MNTPC

  • 7/31/2019 Simulator r&m

    10/19

    NEED FOR R&MNTPC

    New NTPC projects & other power utilities areoperated from LVS/OWS system and olderstations either from a totally hardwired UCB or

    a mix of both. Thus operators tuned with bothtypes of experience are required over at leastten years from now.Hence, R&M of thesimulator by porting of existing software intonew hardware platform and augmenting it by

    adding LVS/OWS based platform is the mostfeasible solution to the problem.

    In view of foregoing, it is suggested thatR&M both the simulator may please be taken up

    at the earliest

  • 7/31/2019 Simulator r&m

    11/19

    R&MACTIVITIES

    The proposed R&M activities includes :

    Replacement of existing ENCORE/GOULDsimulation and DAS computers by latest

    servers.Replacement of I/O interface system with

    latest DCS/PLC based system.

    Replacement of obsolete panel hardware as on

    required basis. Incorporating the LVS/OWS based operator

    HMI.

    Establishing network connectivity to PMI, so

    that training may be provided at PMI.

    NTPC

  • 7/31/2019 Simulator r&m

    12/19

    R&M PROCEDURES

    As has been done in our DAS R&M cases,thewhole R&M activity is proposed to be done inseveral phases/steps in order to minimize thedown time.

    Most of the software work can be done onthe new hardware platform and connectivityto the panel can be done with minimum down

    time of say 15 days or less.During that time training will be continued

    with existing configuration.

    NTPC

  • 7/31/2019 Simulator r&m

    13/19

    PHASE-Replacement of existing ENCORE/GOULD

    DAS and simulation computers by latest

    PCs,servers,LAN switches,laser printers etc.Porting of the existing software system on to

    the new hardware platform.

    Replacement of I/O interface with latest

    DCS/PLC based system .Up-gradation of panel hardware like meter,

    recorders,indicator etc. on as required basis.

    Replacement of annunciation system with

    LED based system.

    NTPC

    R&M PROCEDURE(contd.)

  • 7/31/2019 Simulator r&m

    14/19

    R&M PROCEDURE (contd.)

    PHASE- Fine tuning of simulation models to the present

    state of the plant incorporating all modification

    and up-gradation of plant, that may have beenimplemented over the years.

    Up-gradation of instructor station facility likeautomated trainee exercise,grading functions.

    One set of LVS/OWS based system may beinstalled in the existing computer room.

    Connection will have to be established betweenthe simulator & plant DAS for analyzing plant

    data.

  • 7/31/2019 Simulator r&m

    15/19

    R&M PROCEDURE (contd.)

    PHASE- After the completion of all the R&M

    activities the network connectivity may beprovided to PMI, so that both the simulatoroperation may be demonstrated at PMI.

    Connectivity of Sipat simulator with PMI is

    already envisaged so it can be extended toKorba.

    NTPC

  • 7/31/2019 Simulator r&m

    16/19

    BENEFITS WITH R&M

    TANGIBLE BENEFITSAfter R&M we will have 4 panel, that will

    accommodate more no. of trainees.

    Simulator training cost (for 2 weeks) withLVS/OWS system is Rs.50,000/- as comparedto Rs.30,000/- with conventional system.

    As on previous available data no. of traineesfor 2 weeks program = 1100(aprox.).,assuming that half of these traineesare for LVS/OWS based system.

    Approx. cost of simulator training

    =Rs.4,40,00000/-

    NTPC

  • 7/31/2019 Simulator r&m

    17/19

    BENEFITS WITH R&M

    INTENGIBLE BENEFITS :The simulator training gives a feeling of

    operating a real power plant with no fuel cost,

    no wastage of time,no losses and repairs. It rises the level of proficiency and

    confidence.

    Training in emergency handling helps in

    saving down time of plant.Training in efficient operation helps the

    operator in improvement of overall efficiencyand life expectancy of plant equipment.

    NTPC

  • 7/31/2019 Simulator r&m

    18/19

    THANK YOU

    NTPC

  • 7/31/2019 Simulator r&m

    19/19