Upload
phungdieu
View
215
Download
1
Embed Size (px)
Citation preview
Simulating contestability in freight transportation – The
Canadian grain handling and transportation system
Russell Lawrence
James Nolan*
Richard Schoney
*Corresponding author
Dept. of Agricultural and Resource Economics
University of Saskatchewan
Saskatoon, SK Canada S7N 5A8
Abstract: Modern supply chains are characterized by multiple interactions among individuals
and evolving temporal patterns of interaction. The grain handling and transportation system
(GHTS) in Canada is a good example of a large modern supply chain. In this paper, we develop
an agent-based simulation model of this regional supply chain and use the simulation output to
assess the viability of an open rail access policy designed to mitigate railway market power in
the system. We find that if open rail access in the Canadian GHTS were to be implemented, at
best profitable entry opportunities would be very limited.
Date of this version: May, 2016
Keywords: agent based simulation, rail, contestability, grain transportation, Canada.
1
1. Introduction
Modern supply chains are characterized by numerous interactions among individuals as well
as evolving temporal patterns of interaction. The grain handling and transportation system
(GHTS) of Western Canada is a good example of a large scale, modern supply chain. While
almost all grain grown in Western Canada is ultimately exported, grain entering the Canadian
GHTS comes from numerous individual farms. During the crop year, Prairie farms harvest
grain and transport their product to grain elevators by truck. Grain is blended at the elevator to
specification, and is then put into railcars for transport to port elevation facilities. Once at port,
grain is finally loaded onto cargo ships for delivery to overseas customers.
Mostly due to economies of scale, rail has been the dominant mode for transporting grain across
the region. This dominance is so complete that in spite of almost complete deregulation of the
entire freight transportation sector in Canada through the 1970’s, there remains residual
regulatory oversight over grain movement with the potential for exertion of market power by
rail in this supply chain. While the form of this regulation has changed over time, currently, a
policy of revenue limits on grain movement is still used to control the behavior of the two
major Class 1 rail carriers serving the Canadian grain handling system.
With continuing modernization of the supply chain, there remains considerable controversy
over whether and how much the current revenue based formula for regulating grain
transportation benefits either grain shippers or the railways. Neither grain shippers nor railways
are entirely satisfied with the current regulatory framework, while both sides seem to want a
competitive supply chain that requires minimal regulatory oversight. Future policy intervention
in this sector will need to better accommodate the kinds of spatial and temporal shocks that are
endemic to the vast Canadian grain handling supply chain.
2
In the rail sector, one approach to create more competition that has been attempted in other
jurisdictions is a policy referred to as ‘open’ or ‘competitive’ access (Carlson & Nolan, 2005).
Similar to policies in other network industries, open rail access accommodates priced entry by
competing railways on existing rail infrastructure. Rail entrants are permitted to lease rail right-
of-way and also solicit traffic over existing track. Due to complications related to issues of
track ownership and infrastructure management, to date the evidence on societal benefits
stemming from implementation of open rail access in other countries has been mixed
(Mitzutani, 2013). In Canada and the U.S., open access in freight rail is further complicated
because the freight rail network is privately owned (Bonsor, 1995). Implementation of such a
policy would entail considerable operational and financial risks to both carriers and shippers.
Even today, open access regimes in rail are still essentially public policy “experiments”,
implemented with little prior practical understanding of the likely economic and financial
consequences to the rail industry. In this paper, we build upon the expanding literature in
computational economics and develop an agent-based simulation model of a complex regional
supply chain served by a concentrated rail network. We then use the simulation output to assess
the viability of open access to mitigate rail market power in this supply chain. From a public
policy perspective, this type of analysis should allow a rail regulator to effectively pre-test both
the feasibility and sustainability of rail access policies prior to implementation.
The simulation data allows us to evaluate the feasibility of implementing an open or
competitive access policy on wheat/grain movement over a large regional freight rail network.
On one hand, while the type of access policy considered here is an effort to address on-going
concerns of agricultural shippers about market power in grain transportation, the regulator must
3
also ensure that both entrant and incumbent railway remain financially viable. In this regard,
we will define “entry opportunity” in the system as that moment when wheat is loaded at an
elevator into hopper rail cars ready to be transported to final destination, but for some reason
the incumbent railway is not able to move the cars in a timely manner. Any delay or opportunity
cost arising from immobile cars in the rail network represents not only a lost marketing
opportunity for the shipper, but also creates a window of opportunity for a rail competitor to
access the loaded cars and subsequently transport them to final destination. It is this opportunity
which constitutes open access in our simulated grain handling and transportation system.
2. The Canadian grain handling and transportation system
The current Canadian grain handling and transportation system has evolved from a web of
mainlines and branch lines serving numerous small wooden grain elevators, into a modern
supply chain composed largely of a few dozen large concrete elevators served by the two
Canadian Class 1 railways. In any given year, about 75-80% of all Western Canadian grain is
sent for export through one of the ports of Vancouver, Thunder Bay, Churchill, or Prince
Rupert.
The current system is also dominated by large volume trains and increasingly efficient elevator
throughput. The economics of grain elevation and commodity movement means that although
newer large concrete elevators have higher fixed costs, they also have much lower marginal
costs than the bygone wooden elevators (White et al., 2015). Both grain companies and
railways have strong incentives to move large quantities of grain from elevators to port position
in a timely manner. With large economies of scale in grain movement, the two Canadian Class
1 railways are effectively natural monopolies in their respective markets (see Figure 1) and this
4
market power has led to a history of regulatory policies in order to mitigate this behavior (Nolan
and Carlson, 2005).
Even so, with respect to system logistics things are very much the same as they have been since
the system was built decades ago. Grain companies order and receive rail cars from the
railways. The information used to determine these orders includes prior grain deliveries, world
prices, and ability of the railway to transport demanded hopper cars. Once at port, grain cars
must be emptied either directly into ships, into terminal grain elevators for future loading, or
moved to adjacent rail yards (if space is available) to be loaded when a suitable ship arrives.
After unloading, grain cars are returned to the Prairies for re-allocation and re-loading
(Canadian Transportation Agency, 2008). While there is variation year to year, as an example
in the 2008-2009 crop year it took an average of 50.1 days for Canadian grain to move from an
inland elevator to port position. This can be broken down into an average of 27.7 days in store
on the Prairies, 5.7 days of loaded transit time, 16.7 days at a terminal elevator at port, and then
4.6 days of vessel time in port (Quorum Corporation, 2010).
Contestability in freight transportation
In order to develop policies to improve competition among firms possessing market power, we
briefly review the concept of contestable markets (Baumol et al., 1982). A market is defined as
contestable when a single (or few) firms in a market face explicit or implicit pressure on prices
from other firms that could potentially operate in that market. Contestability also implies the
existence of conditions such that firms operating outside the market can readily enter (or exit)
that market if they perceive an opportunity to earn economic profit. A market is therefore
contestable if there are any similar firms capable of entering, producing output and then exiting
that particular market (Carlton, 1994).
5
For a market to be perfectly contestable, the following conditions are necessary (Baumol et al.,
1982): 1) entry must be costless and without limit, so that any entrant should be able to entirely
displace an incumbent firm if this situation obtains the lowest industry cost; 2) entry needs to
be absolute, meaning that an entrant should be able to enter without it being possible for the
incumbent to reduce price in response to entry; and 3) the firm with the lowest costs should
always displace a higher cost firm. The purest form of a contestable market is called “ultra-free
entry” or “hit-and-run entry”, meaning that the purest form of a contestable market is often
called “ultra-free entry” or “hit-and-run entry”.
Contestability theory has already been utilized within the U.S. rail sector to help formulate
regulatory policy. The U.S. Surface Transportation Board uses a pricing test founded in
contestability theory (the “stand alone cost” or SAC test) to compute upper limits on rates in
rate disputes (Carlson & Nolan, 2005). However, continued shipper dissatisfaction with the
SAC test and the allowable rate levels it has permitted has led to criticism about the use of
contestability theory as applied to the rail sector (Tye, 1990). These critiques focus on the fact
that the conditions necessary for a perfectly contestable market are often very difficult to meet
in a vertically integrated rail industry. Contestability theory applied to rail policy should instead
help lead to situations where viable potential entrants become credible competitors, thereby
imposing some (possibly incomplete) price discipline on the incumbent railway(s).
In this analysis, we simulate a situation where a concentrated freight rail sector is instead
mandated to operate using “competitive” or “open” access rail policies (BTRE, 2003). Such
access policies set prices for entrant access on the incumbent rail bed, with the goal of fostering
greater competition in the rail sector according to the spirit of contestability theory.
6
One key issue to resolve is how to share and pay for the use of rail infrastructure. Prior
experience with other access regimes has shown that designing a fair and sustainable pricing
regime for the use of track infrastructure by competing railways is not a simple task (BTRE,
2003). The fixed cost of the track infrastructure is common for all users of the track, but
apportioning these costs across users is complicated at best because differences in track
condition and trains create difficulties in determining those costs associated with a particular
train using particular sections of track.
3. Simulating the Canadian grain handling and transportation system
In contrast to equilibrium models that rely on assumptions about aggregate behavior, agent
based economic simulation models (ABM) use individually programmed computer agents that
act according to their own individual objectives, while every agent also interacts with others in
a changing operational environment. Agent based modeling provides something akin to a
controlled laboratory setting to test certain dynamic characteristics of a system, as well as a
method for empirical examination of counterfactual scenarios of interest (Gintis, 2005).
While the scope of our study is novel, the agent based simulation approach is founded upon
prior research in both the social sciences and the economics of competition. For example,
simulated competition has been used to examine the coordination effects of mergers (Davis &
Garces, 2010), while intra and intermodal transport competition has been simulated using a
game theoretic approach (Ivaldi & Vibes, 2008). In supply chain analysis, agent based
simulation has been used to develop better intermodal container transport handling schedules
by exploring the inland exchanges between modes (Gambardella, Rizzoli, & Funk, 2002). And
novel work by Preston et al. (1999) developed a related (but not agent based) numerical
7
simulation model that evaluated the potential for on track rail competition in the UK. This work
is closely related to our research in it attempt to assess the potential for rail competition under
a priced track access regime (Preston, Whelan, & Wardman, 1999).
The software used to perform the simulations is known as NetLogo© (Wilensky, 1999).
Among a growing number of available agent-based software packages, NetLogo© is relatively
easy to implement and has been used by a number of researchers to simulate various social and
natural phenomena. With the incorporation of a geographic information system (GIS)
extension capability, real physical landscapes and associated characteristics (like transportation
networks) can be more accurately modeled and represented in Netlogo models.
The scope and complexity of this particular research led to the development of a multi-tiered
simulation environment built upon both agent-based software and a GIS application. The
simulation uses both Netlogo and GIS data to accurately represent key locations as well as the
spatial interactions between participants in the Canadian grain handling system. We calibrated
the simulation to specific real world data in order to validate the simulation, then ran the model
over multiple replicates to generate output. It is these results which we report here, along with
a discussion of the implications of our findings for concentrated supply chains and grain
transportation.
The region and the agents in the simulation
To keep the analysis tractable yet relevant, the scope of the simulation is limited to the major
grain/wheat producing province of Saskatchewan (see Figure 1). Note that wheat output is not
homogeneous across the province, so that each of the sub-regions (called census agricultural
8
regions or CARs) shown on the provincial map differ by soil type and productivity. A detailed
map of this information was incorporated into the simulation.
The agents in the simulation consist of farms, grain elevators and the railways. In the model,
farms deliver wheat to elevators, then elevators assemble delivered product into shipments that
are to be moved by rail to final port destination (see Figure 1). Due to their large numbers
relative to the other participants, farms are assumed to be distributed randomly across each
agricultural sub-region, and remain there for the duration of each simulation run. In addition,
each farm is given an initial store of wheat to move into the system.
For simplicity, the number of trains moving on rail lines in the simulation were randomized.
Testing revealed there were few gains from using proxy schedules to emulate railway behavior
within the supply chain. Actual grain elevators in the region were located with the aid of a GIS
shape file that also contained the locations of rail lines. Elevators are assumed to start the
simulation with no inventory, but the elevator agents constantly try to obtain wheat from the
network of farms across the region.
Furthermore, we assume in the simulation that a monoculture of wheat is grown across the
region (Lawrence, 2011) and is directly seeded on all arable acres of each farm every year.
While this was done for tractability and does approximate historical reality, in fact the
simulation does not account for other significant regional crops (like canola) or summer fallow,
nor is there a specific accounting for adverse weather events.1 While we feel that these
assumptions do not fundamentally affect the qualitative outcomes of the model, future work
1 The wheat production data we use effectively contains built-in weather adjustments by time of year and
season.
9
will incorporate other commodities into the analysis since other crops have assumed growing
importance in regional crop rotations over time.
Figure 1.
Rail network and census agricultural region (crop districts) boundaries (Saskatchewan).
Simulation initialization
The initialization process used actual production, in tonnes, for all wheat produced in
Saskatchewan from 1977 to 2006, by CAR (see Lawrence, 2011). Regional level production
was assumed to be divided equally among the farms in each farming district, meaning
simulated farms within the sub-regions are necessarily assumed to be the same size (Statistics
Canada, Agricultural Division, 2006). Based on this information, each farmer agent makes its
own production and delivery decisions, with each agent accessing relevant information for the
appropriate year of the simulation.
10
Train lengths used in the simulation are set according to the capacities of three most common
lengths of grain/wheat trains serving the region. These comprise a 100 car unit train, a 50 car
train, and a smaller 25 car train. Using hopper car capacities, these trains have capacities
(respectively) of 10,000 tonnes, 5,000 tonnes, and 2,500 tonnes. In addition, we assume world
wheat prices are known to the agents. In the simulation, the offer made to farms by elevators
to obtain wheat is a cash price.
In turn, actual production levels were used to determine the percentage of each type of wheat
produced in each year. This computed percentage was converted to a weighted average in order
to determine an average price for wheat to be offered to farms in the simulation. Finally, this
latter price was adjusted according to a Farm Product Price Index for Saskatchewan grains to
ensure the simulated wheat prices were indexed relative to each other (Lawrence, 2011).
The total number of farms initialized within the simulation was determined using the 2006
Census of Agriculture. To give a sense of the scale of the model, the number of farms located
on the simulated landscape was just over 25,000. This closely matches farm numbers listed in
publicly available data on grain farming (Statistics Canada, 2006).
In order to maximize gross margins, farms are assumed to plant wheat with all acreage seeded
every year.2 Since almost all of the production costs are sunk by the time wheat is harvested,
we further assume the farm agents do not take cost of production into account when pricing
their wheat.3 In summary, every simulated farm within each separate sub-region is identical in
2 This assumption simplifies the model, but in fact for many years, wheat has been by far the most common crop
grown in the province. Very recently, other similar crops (like canola) have gained importance on Saskatchewan
farms, but this assumption is valid across the data and time covered in this analysis. 3 This assumption stems from the experience of field experts (including one of the authors).
11
size and harvests the same amount of wheat as every other farm in the same sub-region. Since
actual agricultural yields vary across the province, the model generates yield variability through
the randomized location of farm agents in each replicate of the simulation.
The supply chain for wheat
Trucking rates for moving wheat from farm to elevator are a function of distance (Weyburn
Inland Terminal, 2011). This required using a grid distance calculation to determine applicable
road distance from farms to elevators. Given the structure of the regional road network
modeled, a grid calculation more accurately simulates actual truck routings.
Over the latter time periods covered by the simulation, there were approximately 185 grain
elevator locations (Canadian Grain Commission, 2009) across the province. These were
operated by 37 companies, while 22 of these companies possessed primary handling facilities.
Next, we excluded grain processing facilities because they do not collect grain for the purpose
of export, so this left grain delivery facilities in the simulation with a capacity of 2.91 million
tonnes, or about 90% of total elevator capacity in Saskatchewan (Canadian Grain Commission,
2009). A complete listing of the elevators used in the simulation, listed by company as well as
total capacity, can be found in Lawrence (2011).
For tractability and to best capture reality within the simulation, we distinguished between three
primary sizes of grain elevator. Based on industry information, elevator capacities were
configured as follows – those less than 7,000 tonnes (small), those between 7,000 and 25,000
tonnes (medium), and those greater than 25,000 tonnes (large). Drawing upon real elevator
capacities, these discrete size categories were then imposed on the (over 150) primary elevator
locations located within the province.
12
Using average capacities and the actual number of handling facilities falling within each
category, we then generated a “synthetic” population of grain elevators matching actual
capacity distribution for a representative crop year (2006; see Table 1). The categories
generated 51 small elevators, 57 medium elevators, and 49 large elevators, each of which had
average simulated capacities of 4,076 tonnes, 13,829 tonnes, and 38,961 tonnes respectively.
Simulated total grain elevator capacity was 2,913,000 tonnes, only fractionally higher than
actual capacity at that time. Details on other particular aspects of the grain elevator calibration
exercise, including handling fees, storage and elevator tariff rates are contained in Lawrence
(2011). Topographically, it is worth noting that each elevator in the simulated landscape was
accessible from just a single Class 1 railway.
Table 1.
Simulated elevator capacities in Saskatchewan, by Grain Company
Finally, rail rates for wheat from Saskatchewan to the port of Vancouver applicable to the
simulated period were obtained from the Saskatchewan Ministry of Agriculture (Saskatchewan
Ministry of Agriculture, 2009), while data from the Government of Alberta’s Agriculture and
Rural Development website (Mah, 2010) were also used to match each Class 1 railway with
appropriate rate data for various elevator locations across the region.
Served by CN Served by CP Served by CN Served by CP
Cargill 11 2 8.9% 1.8% 312,000 10.7%
Parrish & Heimbecker 7 3 4.7% 4.0% 255,000 8.8%
Richardson Pioneer 19 15 7.4% 9.6% 496,000 17.0%
Viterra 27 25 20.7% 17.2% 1,103,000 37.9%
Remainder 13 35 8.0% 17.7% 747,000 25.6%
Total 77 80 49.7% 50.3% 2,913,000 100.0%
Simulated Elevator Capacities in Saskatchewan by Company
Company# of Locations % of Capacity Sum of Primary
Capacity (tonnes)%
13
System and delivery efficiency – delays and penalties
The simulation tracks delivery delays and associated costs within the grain supply chain in
order to assess the viability of another rail operator transporting any delayed grain shipments.
While demurrage costs can be significant in the industry, in fact any costs incurred through
wheat not moving in a timely manner can be greater than any demurrage costs at destination.
For example, if the market price for wheat varies dramatically, there is the possibility of
significant foregone profits if grain does not move reliably to export position. The full cost to
the shipper in this case is not only the pre-contracted demurrage fee, but also the foregone
opportunity of not being able to sell wheat at a desired price. For this reason, our simulated
total delayed wheat volume is a essentially a proxy for shipper costs due to transportation
delays.
In the simulation, we define a delivery penalty “event” as a situation in which wheat does not
move in a timely or reliable fashion from grain elevator (origin) to port (destination). Like
many industries where time is money, grain shipment delays generate additional costs for
shippers. In this sense, our delivery penalty is similar to demurrage or delay costs, but in the
simulation the penalty is calculated over commodity volume instead of value. In effect, we are
assuming the delay penalty is equivalent to the capacity of a train serving a particular size of
elevator in the regional grain handling system.
Grain elevators are collection points. In the simulation, farm agents can deliver into the elevator
system all the wheat they choose to deliver. In turn, wheat gathered and stored in an elevator
must be moved out as soon as possible in order to minimize storage and holding costs. In the
simulation, elevators do not want to hold wheat for too long before shipping it out by rail
because delays also generate losses for the elevator. While these decisions are important, in
14
fact, the extant literature provides surprisingly little guidance regarding formal modeling of
elevator behavior in this respect. Therefore we made some assumptions about what constituted
“too much” wheat carried over in an elevator for a defined period of time in the simulation.
Delivery penalties are computed for grain elevators using a heuristic that is a function of the
capacity of an individual elevator.4 If at the end of a simulated time period the actual wheat
level in a large or medium elevator is greater than 75% of its total capacity, then a delivery
penalty is imposed for carrying over too much stock. But for small elevators, the measured
wheat level in the elevator must fall at 85% or greater of total capacity to incur a penalty. Note
that the different penalty percentages reflect the different relative train capacities that can serve
the elevator sizes used in the simulation.
For delay to be “flagged” in the simulation, the serving railway must not have delivered a train
to that elevator in the simulated time period (month). If a particular elevator satisfies the
conditions necessary in its size class to create a delivery penalty event, the simulation records
the amount of tonnage that did not move, the location of the elevator, the elevator company,
and the month this happened.
Simulation heuristics were validated by checking and comparing carryout stocks of wheat.5
Table 2 summarizes the data used for initialization of the simulation environment. Farms are
not evenly distributed across the province, and farms are endowed with a starting wheat
inventory so that deliveries can start entering the supply chain prior to the first harvest.
4 This heuristic was chosen based on industry knowledge, and to approximate basic inventory optimization
solutions. 5 Carryout stock is the amount of wheat left over once all demand is satisfied.
15
Table 2.
Simulation initialization summary
Additional information about the simulation
This section lists several other important elements and assumptions that were important to the
development of the simulation framework. Aside from time scale, each of these points better
describes governing behavior of the agents as programmed in the simulation. The interested
reader is referred to Lawrence (2011) for more exact details about the simulation
environment beyond those provided here, including a flowchart of the model sequence and
the Netlogo code used to conduct the analysis.
Elevator
Size
Number
of
Elevators
Total
Capacity
(Tonnes)
Percent
Capacity at
Initialization
Train
Capacity
(Tonnes)
Small 49 4,000 0% 2,500
Medium 57 14,000 0% 5,000
Large 51 39,000 0% 10,000
1A 1017 3BS 717 7A 1403
1B 770 4A 313 7B 1212
2A 906 4B 696 8A 1377
2B 1587 5A 1978 8B 1685
3AN 644 5B 2077 9A 1766
3AS 1208 6A 2102 9B 958
3BN 1422 6B 1584
Initialzation Information Summary
Number of Farmers by CAR
Farmer Starting Inventory N ~ (300, 50)
16
1) Time scale - The simulation is replicated for 360 individual months, with 12 months
equating to one calendar year and each replicate proceeding for 30 years. This is repeated for
a total of 1,024 iterations, yielding 368,640 months of data.
2) Railway behavior – The railways charge rates based on historical data (see Appendix for a
listing). Due to the large scale of the rail network and considering on-going complaints in the
sector about rail service (for example, see Transport Canada, 2011; Annand & Nolan, 2003)
we assume that from the perspective of shippers, rail car allocation to each elevator is
effectively a random process. In the simulation, trains arrive randomly at every elevator, with
arrivals are drawn from a uniform distribution.
The parameters of the (uniform) train arrival distribution were set in the following manner.
The average number of trains delivered in a year to grain elevators was determined by
calculating average total wheat production from 1977 to 2006 (about 13.5 million tonnes;
Statistics Canada, 2007), while the yearly number rail cars available for each elevator was
computed such that this average wheat production could be transported from all elevators
within a single crop year. Using the amount of each category (large, medium, and small) of
elevators in the simulation, we then assigned grain car spots of 100, 50, and 25 cars to each
respective size of grain elevator. From this, we found that on average the large elevator
locations receive 21 trains per year, medium sized elevators get an average of 12 trains per
year, and small elevators receive six trains in an average year. Table 3 summarizes this basic
grain system information.
17
Table 3.
Number of elevators and average total simulated tonnes of wheat transported per year
There is an additional model calibration done within train allocation that allows elevators to
reject one train spot under certain conditions, including a situation when a train arrives at the
elevator but too little wheat is in the elevator to move it cost effectively.6 Furthermore,
measured elevator capacity changes slightly every month as a consequence of the number of
trains actually allocated to the elevator. This is due to the fact that the more trains actually
received by an elevator, the greater the real capacity of the elevator since the train also acts as
additional storage for the elevator within the base time period of one month.
3) Farmer behavior - Farmer agent decisions to deliver wheat to an elevator are fixed for all
months of the year, and are the same for each year of the simulation. Like reality, we assume
farms do not make any September deliveries, unless they are queried by an elevator short of
grain. In every period, each farmer chooses a percentage of their total wheat inventory that they
will deliver to an elevator. In turn, these amounts are based roughly upon historical data and
are tied to cycles of the wheat crop year. This information is listed in Table 4. Ultimately, based
6 This was done to better approximate real world delivery conditions. If a shipper has a low volume of inventory,
they will not call for rail cars. If the shipper does make a call for cars, the number of cars they actually receive is
effectively random since they may or may not get all of the rail cars they requested in the time specified.
Small 49 25 6 735,000
Medium 57 50 12 3,420,000
Large 51 100 21 10,710,000
Total 14,865,000
(Statistics Canada, 2007)
Number of Elevators and Average Total Simulated Tonnes of Wheat Transported per Year
# of Elevators # of Rail Cars per TrainAverage # of Trains per
Year
Average Total Tonnes
Transported per YearElevator Size
18
on these parameters and other minor heuristics, farms in the simulation move approximately
98% of simulated wheat production to the region’s elevators in a given simulated year.
Table 4.
Attempted delivery volumes, by percentage of inventory per month
In order to keep the model temporally efficient, farm grain deliveries are done in the following
manner. Each time period, ten thousand randomly chosen farms try to deliver wheat to their
closest (in this case, assessed as the “crow flies”) large capacity elevator, regardless of offered
prices. Next, twenty five hundred randomly chosen farms attempt to deliver to their closest
medium sized elevator. Finally, two thousand randomly selected farms do the same and try to
deliver wheat to the closest small elevator. The remainder of farms who were not selected to
deliver to a set location make their delivery choices to the elevator (regardless of size) with the
largest differential between offered price and transportation cost (using computed trucking
distance) from their farm to that elevator (Hoover & Giarratani, 1985). For simplicity, we also
MonthDelivery
Volume
January 40%
February 40%
March 40%
April 50%
May 50%
June 80%
July 90%
August 100%
September 0%
October 10%
November 20%
December 30%
19
assume that individual farmer deliveries cannot be divided, so that farms deliver all or none of
their desired delivery volume.
4) Elevator behavior - Once all farms have attempted deliveries, that month their wheat is
moved to the appropriate elevators and levels deducted from individual farm storage
inventories. Once all deliveries are made, the elevator compares current inventory against the
amount the serving railway is scheduled to load in that particular month. If the elevator has
sufficient inventory to fill what the railway can load that month, then the elevator allocates that
amount for rail movement. If the elevator does not have enough to cover what the railway can
load, the elevator is allowed to call farms again for more wheat (this is similar to heuristics
used by Bunn and Olivera (2001) to model the electricity industry).
Once all farms called to help fill elevator capacity shortfalls have delivered their wheat, those
elevators that were short add up their inventories again. If the elevator’s inventory is large
enough to cover what the railway will take away, then it allocates the amount the railway will
move and deducts this from inventory. But if an elevator is still short of wheat to transport, it
delivers whatever amount sits in inventory to the railway and reports how many tonnes it was
short in meeting the specified delivery amount.
Railways take delivery of wheat from the elevators and subsequently transport it to port
destination, the final action in the simulated time interval. Deliveries at port are assumed to be
filled and shipping tonnage is allocated in similar proportions to elevator capacity. One of the
major grain companies is allocated a fixed amount (almost 40 percent) of a given ship capacity,
while the other major companies receive declining capacities. Finally, the remaining smaller
grain companies and elevators are assumed to fill the remaining 25 percent of the ship. Total
20
port delivery is summed according to company and compared to the percentage allocated to
each grain company. Finally, the number of ships needed to move wheat is determined after
the total port deliveries are tallied.
4. Model Validation and Results
We conducted a very basic validation exercise to determine if our simulation results were
broadly consistent with reality. The volume of wheat stock in the province of Saskatchewan
was chosen as our validation metric. Figure 2 shows real and simulated provincial wheat stock
data from 1981 up to the final year of the simulated model run (2006).
While the simulation consistently overestimates carryout stocks of wheat, we note that carryout
stocks generated with the simulation track actual carryout stocks quite closely. In fact, the
simulation consistently overestimates carryout stocks because in the simulation, while trains
arrive at elevators randomly, they are ultimately configured to transport long run average
provincial wheat production. The simulated railways can adjust for years where production is
lower than the long run average by reducing the number of cars delivered. However, due to
efforts to avoid congestion in the simulated rail system, the railways were given limited ability
to increase car deliveries in those years with greater than average production. See Figure 3. A
year with higher wheat production means that carryout stocks remain high until a point where
wheat production drops towards the long run average.
As an ambitious simulation framework, our efforts to build it led to many simplifications, some
of which may not mirror system behavior for the full duration of the simulation. But given the
limitations as discussed, we conclude that the ability of the simulation to closely track, if not
exactly emulate, real wheat carryout stock data is indicative that the model is a reasonable
21
representation of the regional grain handling and transportation system. While certain
assumptions and heuristics have affected the long-term accuracy of the simulation, the model
generates realistic output for many other measures of system performance.
Figure 2.
Wheat Stocks in Saskatchewan (simulated vs. actual), 1981 to 2006
(Statistics Canada, 2006)
22
Figure 3.
Simulated rail deliveries to port, compared to wheat production.
Delivery penalty events
The amount of data generated by the simulation means that we had to develop parsimonious
yet effective representations of system performance. We opted to track and compute the
approximate chance of delivery penalty events happening within the entire simulated grain
handling system, both through space and time. This particular representation is actually a
measure of system ‘failure’ (from a logistics perspective) but offers a concise way to track and
visualize overall system (in)efficiency.
Over the entire simulation timeline (30 years by 1,024 iterations, or 368,640 months of data)
the model generated over 57 million elevator delivery events, with almost 12 million delivery
penalty events in the system.7 In turn, each elevator yielded about 96 delivery penalty events
7 The data generated for Year 1 in the simulation was somewhat lower than other years because elevators were
assumed to start the simulation with zero inventories.
23
per run (i.e. a simulated year). The total wheat volume associated with delivery penalties over
all runs averaged just over eighty-five thousand tonnes per month, which translates into
approximately seventeen 50 car unit trains for transport. Subject to the various assumptions
and heuristics used in the model, the overall odds of a delivery penalty event occurring at any
given time and location were approximately one in five.8
Grain transportation delays in the simulation could also be broken down according to the train
size required to move the commodity. The likelihood of a 2,500 tonne penalty event occurring
at any given time was 19.3%, while that for a 5,000 tonne penalty event occurring was 1.25%.
Finally, the likelihood of a 10,000 tonne penalty event in the simulation was about 0.01%. So
as in reality, simulated grain handling system delivery penalty events occured most often at
small elevator locations and only rarely at medium and large elevator locations.
Examples of delivery penalty events
Staying mindful of our efforts to assess the viability of contestability policies in grain
transportation, we next describe some specific delivery penalty tonnage events in more detail.
These events help us to determine the feasibility of a rail entrant seeking to move delayed grain
in the supply chain.
Examining the broader simulation output, the amount of wheat that did not move in a timely
manner appears to be significant. But given the sheer expanse of this supply chain, the location
of any delayed wheat is crucial in assessing the viability of rail entry. To this end, GIS mapping
tools were used to illustrate the likelihood of a delay penalty event occurring at any particular
8 To the knowledge of the authors, this kind of data has never been tracked in Canada. However, anecdotal
evidence from local shippers indicates that this likelihood of delivery “failure” is close to that historically
experienced by grain shippers in the system.
24
elevator location in the simulation. This analysis generates a visual representation we refer to
as “probability maps”. These indicate where delivery delays occurred in a given time period,
along with the associated frequency of occurrence. To see more of these maps over several
years of the simulation, see Lawrence (2011). Figure 4 is just one of these maps, chosen to
represent a typical year of the simulation (2006).
Figure 4.
Map of regional delivery delay probability or likelihood, 2006
In the simulated 2006 crop year, average total wheat volume delayed throughout the system
was 981,121 tonnes. The lighter shaded areas represent locations with a lower likelihood of a
delivery penalty event occurring, while the darker shaded areas represent locations with a
25
greater likelihood. We can see that delivery events and penalties are somewhat localized and
often occurred at the edges of the modelled region.
As noted on the map, specific examples in 2006 include a high 65 percent chance of a delivery
penalty event at the elevator in Shellbrook (operated by Pioneer), whereas the elevator at
Tribune (also operated by Pioneer) had just a 52 percent chance of a delivery penalty event. In
fact, all the grain elevator companies were affected similarly in that each of them had varying
likelihoods of delay events for their elevator networks. For instance, the elevator at Wadena
(Viterra) had a 38 percent chance of a delivery penalty event, while the elevator at Maple Creek
(Viterra) had just a one in 100 chance of a delivery penalty event. Since it is well known that
many smaller elevators have limited connectivity to the trunk rail network that (over the time
of the simulation) continues to prioritize high volume unit trains (Nolan and Skotheim, 2008),
it is not surprising that for smaller outlying grain elevators, the simulation generated a higher
likelihood of a delay event.
5. Evaluating the possibility of rail entry into this grain transportation system
Carlson and Nolan (2005) evaluated the costs of third party access for a potential entrant into
the Canadian rail system who wanted (or was restricted) to move wheat. That research offers a
foundation for computing access prices for a potential entrant in the simulated network, where
an entrant in our context is defined as a railway that can readily identify delay events and then
exploit these through the transport of that delayed wheat.
Using the access pricing mechanism in the Carlson and Nolan paper (adjusted for inflation),
we generate a total charge for access of C$0.015883685 per tonne kilometre, broken down
between C$0.009089376 per tonne kilometre compensation for the use of track, and
26
$0.006794309 per tonne kilometre for track access (Lawrence, 2011). A single EMD SD40-2
diesel locomotive (a commonly used type) has an approximate market value of C$225,000.
Using available data, we assume these locomotives can be leased by the entrant for C$250 per
day (Simmons-Boardman Publishing Corporation, 2008). Furthermore, grain cars are assumed
to have a tare weight of 20 tonnes, while carrying 100 tonnes of wheat.
Locomotives employed by an entrant might not be used every day, but the entrant would need
to have access to them at all times due to the uncertain nature of when, and more importantly
where, a delay event might occur. To this end, we assume a crew of three is needed to operate
each unit train and that labour is compensated at C$65,000 per year. We also assume that 25
and 50 car trains require only two locomotives and one crew, while the large 100 car spots need
three locomotives and one crew.
In conducting this analysis, we also assume that a potential entrant has access to very good
information. This implies the following: 1) the entrant knows the likelihood of each elevator
possessing delayed rail car spots; 2) the entrant is informed immediately where and when those
events occur; and 3) the entrant can readily purchase (at a regulated rate) track capacity on the
host railway to move delayed grain cars in a timely manner. Using conservative business rules,
we also assume the entrant railway requires a 15 percent rate of return on their investment.9
We offer that this rate of return is reasonable since some of the risk associated with operating
as a competing railway purchasing access over a very large rail network is reduced because
potential entrants know where delivery penalty events are most likely to occur.
9 The rate of return was assumed to be 15% based on average venture capital rates of return, combined with the
potential cost savings that a rail entrant would have under perfect information.
27
Potential entrant feasibility: Entrant serves all delivery penalty events
Next, we generated a basic financial statement for the entrant using the assumptions in
association with the simulated system data on wheat deliveries and delays. This exercise is
done to evaluate under what conditions contestable entry in the grain transportation system
might be profitable. To start, an accounting breakeven threshold with a net income of zero was
used, along with assumptions of an (average) C$41.85 per tonne freight rate10 with an average
shipment distance from origin to destination of 1,857 kilometres.11 An economic breakeven
point was identified by adjusting the freight rate to a level that generated a 15 percent return
on investment.12 Table 5 lists relevant parameters used in the entry calculation.
In 2006, the simulation generated an average just over 1 million tonnes of wheat that was either
outright delayed or not moved in a timely manner. Given the structure of the elevator industry
in 2006, we assumed that approximately 950,000 tonnes (about 94 percent) of this total would
need to be moved in smaller 25 rail car spots, while the remaining tonnage (about 6 percent)
would be moved in larger 50 car spots (based on the simulated likelihood of a 100 car spot
delay as near zero). We also assumed that average railway car cycle in 2006-2007 for all car
spot sizes was 14.7 days (Quorum Corporation, 2007).
10 Average freight rate in the system (2006) 11 Average distance to Vancouver of all elevator locations used in the simulation 12 Return on Investment was calculated as: Net Income / Expenditures
28
Table 5.
Parameter settings, determination of potential entrant viability (Canadian dollars)
Average Distance by Rail to Vancouver (Km) 1,857
Inflation 2%
Operating Charge ($ / Tonne) 0.00909
Access Charge ($ / Tonne) 0.00679
Total Charge ($ / Tonne) 0.01588
Empty Railcar Weight (Tonnes) 20
Loaded Railcar Weight (Tonnes) 120
Locomotive Mass (Tonnes) 120
Lease Cost of EMD SD40-2 ($ / Day) 250
Cost of One Labourer ($ / Year) 65,000
Average Car Cyle Length 14.7
Number of Sets* 16
*The number of locomotive sets needed to move all of the delivery penalties.
Assumptions used for Determining Revenues and Expenses for Potential Rail Entrant
29
Table 6.
Income statement for the rail entrant (2006 data, Canadian dollars)
REVENUE
Freight Rate ($ / Tonne) 41.85
Tonnes 1,017,500
Total Revenue 42,582,375
EXPENSES
Fixed Cost
Locomotive Cost
Lease Cost / Day ($ / Day) 250
Number of Sets 16
Locomotives / Set 2
Days / Year 365
2,920,000
Labour
Wages / Month ($) 65,000
Members / Crew 3
Number of Sets 16
3,120,000
Variable Cost
Access
Locomotive Mass
Mass / Locomotive 120
Locomotives / Set 2
Number of Sets 16
Trips / Year 24
92,160
Railcar Mass (Tonnes) 1,221,000
Dist to Vancouver (km) 1,857
Tonne-km 2,438,538,120
38,732,971
Total Expenses 44,772,971
Net Income -2,190,596
Return on Investment -4.9%
Income Statement for Potential Railway Entrant
30
Table 6 shows that a single entrant trying to move delayed wheat throughout the full system
will incur significant costs not only in the form of track access fees, but also from leasing costs
of the locomotives necessary to move that wheat. As the simulation generated an average of
395 yearly delivery delay events, considering the turnaround time for trains and the size of
trains needed to move the delayed grain/wheat, we computed that a minimum of sixteen sets
of dual locomotives would be needed to transport all the wheat delayed in the system in the
given time period. We conclude that under these assumed parameters, a single rail entrant
cannot earn a positive rate of return trying to serve the entire system for every delayed wheat
shipment.
Examination of critical control variables in this analysis (Table 7) yields some interesting
information about potential rail competition in this market. Most importantly, we find that
under our assumed conditions, if an entrant could increase the freight rate charged to
approximately C$51 per tonne (about a 20% increase over the rates assumed in the simulation)
this would generate an economic break-even point. Alternatively, if an entrant could somehow
shorten its average length of grain haul to less than 1,500 kilometers (meaning that many of
the more distant small elevators in the system would not be served), the same economic break-
even outcome would be achieved with the lower freight rates from the simulation. While freight
rates are certainly adjustable, the likelihood of enough penalty events by happenstance
occurring close enough to destination to permit the latter situation to occur on behalf of an
entrant is small. Finally, we also note that if a rail entrant into the entire system could instead
decrease average car cycle length to approximately 10 days, it would also achieve a zero net
income result, all else equal.
31
Table 7.
Critical control variables
Considering this analysis, we find that by charging either greater freight rates (i.e. greater than
the incumbent railway in this case) or by chance only needing to access wheat delay events that
happen to be located relatively close to final destination, a potential rail entrant into this grain
transportation system might break even. Given the layout of the grain handling system, the
latter situation is not likely to occur within any given time period. In a similar fashion, it would
be very difficult for an entrant to decrease average car cycle length independently of other
factors in the network.
Alternate potential entry conditions: Focus on large elevator delay events
Now we consider if an entrant railway could operate under a true “hit-and-run” approach at the
largest delay events. Using the same assumptions as above, all else equal we find that an entrant
would be slightly better off conducting hit and run entry on larger delay events than serving all
wheat delay events. Over the duration of the entire 30 year simulation period, we generated
approximately eight delay events per crop year where the volume of wheat delayed was very
large, at 10,000 tonnes or greater. Specifically, we know that such events occurred at just 37
elevator locations in the region. The highest likelihood of such an event occurring was at the
major grain elevator hub of Moose Jaw, SK (located in the Western part of the province), which
generated a large volume delay event in the simulation approximately once every two years.
Base Case
Accounting Economic
Freight Rate ($/T) $41.85 $44.00 $50.60
Distance to Vancouver (km) 1,857 1,752 1,486
Car Cycle Length 14.7 ~ 10 NA
Break Even
32
Table 8.
Income statement for potential railway entrant transporting 100 rail car spots, 2006
REVENUE
Freight Rate ($ / Tonne) 41.85
Tonnes 80,000
Total Revenue 3,348,000
EXPENSES
Fixed Cost
Locomotive Cost
Lease Cost / Day ($ / Day) 250
Number of Sets 1
Locomotives / Set 3
Days / Year 365
273,750
Labour
Wages / Month ($) 65,000
Members / Crew 3
Number of Sets 1
195,000
Variable Cost
Access
Locomotive Mass
Mass / Locomotive 120
Locomotives / Set 3
Number of Sets 1
Trips / Year 8
2,880
Railcar Mass (Tonnes) 96,000
Dist to Vancouver (km) 1,857
Tonne-km 183,620,160
2,916,565
Total Expenses 3,385,315
Net Income -37,315
Return on Investment -1.1%
Income Statement for Potential Railway Entrant
(Only transporting 100 rail car spots)
33
As was found in the case of a full system entrant, distance to final port destination is a crucial
control variable for determining the success of a potential entrant under hit and run entry even
for larger penalty events. In effect, those elevators located closest to port were the most likely
locations for profitable hit and run entry.
Table 8 is the income statement for a hit and run entrant in this supply chain, staying mindful
of our model assumptions. Similar to the case of system wide entry, we see that if a rail entrant
instead employed a hit and run approach on the larger delay events, it could still not earn a
positive return by transporting only the infrequent large grain car shipments. But a potential
entrant could be profitable in the latter case if it could increase the (average) freight rate charged
on shipments to about C$49.00 per tonne (approximately 18% greater than those rates assumed
in the simulation).
In summary, using both spatial and temporal freight data generated by the simulation and a
single representative year (2006) along with our base set of assumptions, we found that the
overall return on investment for a single potential entrant attempting to transport all generated
delivery penalty events in the region would be approximately -4.9% (loss). In fact, wheat that
does not move in a timely manner is widely dispersed across the region, both through time and
space. Alternatively, hit and run entry in this market on limited large volume events yields a
ROI of approximately minus 1.1%. In either case, we find that an entrant into the system would
necessarily need to raise freight rates (compared to the actual rates used in the simulation) by
about 20% to become profitable.
An entrant trying to locate and then serve all delayed wheat shipments would require a
considerable amount of timely information. Without considerable oversight and co-ordination
34
by shippers, it is difficult to envision how an entrant could both process and act on this diffuse
(both in time and space) information in a timely and effective fashion. Considering the
difficulties this situation could present, we did discover that a more limited hit and run entrant
serving only the largest penalty events from those points closest to port destination could be
profitable. The latter is a less complicated and more profitable set of entry conditions than
having an entrant attempting to serve all wheat penalty events in a given time period across the
entire region.
In spite of continued complaints about freight rates from the agricultural sector in the region,
we find that in most cases freight rates for grain as used in the simulation approximate levels
consistent with competition. Further, our analysis shows that for much of the region and its
elevator network, the freight rates charged do not permit easy nor profitable entry by another
contesting carrier. If policies permitting open rail access in the Canadian grain handling and
transportation system were to be implemented, at best profitable and contestable rail entry
opportunities would be very limited.
6. Conclusion
The primary purpose of this research was to assess the viability of (contestable) rail entry into
the vast grain handling and transportation system in Canada. This was achieved by building a
detailed agent based simulation of the grain handling system serving the arable portion of the
Canadian province of Saskatchewan. For tractability and realism, standard varieties of wheat
were assumed to be the only commodity moving through the supply chain. Then using the
simulation output, we identified (over both time and space) instances where delivery of wheat
from grain elevators in the region gets delayed due to lack of timely railway availability.
35
The simulation generated an annual average of approximately one million tonnes of wheat (out
of a typical volume of 13 million tonnes moved annually in the region) delayed in delivery by
a lack of timely railway availability. The wheat volume delayed averaged approximately
85,000 tonnes per month, translating to about 30 rail shipments across the province.
Delayed wheat movement is not randomly distributed across the elevator locations in the
region, but instead possesses particular characteristics. For example, the model generated a
high (94 percent) chance that delayed shipment events occur at small elevators, noting that
these elevators are frequently located at the edge of the province. In addition, small elevators
are also often located a great distance from the main Class 1 rail lines, and in areas with lower
grain production per farm. On the other hand, the simulation generated a 6% chance that any
given delay event will require a medium sized 50 car spot, while the chance of a significant
transportation delay at the largest elevators spotting 100 or more cars (i.e. a typical unit train
size today) is negligible. Overall, the capacity of both medium and large elevators combined
with the available rail car spots dramatically decreased the likelihood of wheat being delayed
in transportation at these elevators.
Tracking where and when delivery delay events occurred in the simulation, we then conducted
an economic break-even analysis to determine if a hypothetical entrant railway could be
profitable by serving delayed wheat shipments in the system. We found that even under ideal
conditions, an entrant moving delayed wheat and serving the entire system would be
unprofitable under extant rail rates. Referring to simulation data from 2006, the freight rates
charged by a hypothetical entrant into the system would need to increase by about 20 percent
in order to make entry profitable. Alternatively, an entrant transporting delayed grain from
36
those large grain elevators closest to the port destination would be profitable under the extant
freight rate structure.
Our findings also help clarify long-standing but heretofore unanswerable questions about the
future of policies governing the Canadian grain handling and transportation system. In effect,
we find that the system works well for larger and well located elevators in the region. But not
surprisingly, for an entrant railway to profitably serve the more distant and smaller elevators
would require the entrant to charge higher relative freight rates, a situation that will not alleviate
the concerns of the agricultural community about grain rates. And from a broader supply chain
perspective, our findings also seem to indicate that additional consolidation (both in volume
and location) of the grain elevator system in the region is likely to occur as the system moves
towards increased efficiency and throughput.
37
REFERENCES
Annand, M., & Nolan, J. (2003). Rail Regulation and Competition in Canada: A Policy
Perspective. Journal of Transportation Law, Logistics and Policy 71(1), 65-84.
Baumol, W, J. Panzar and R. Willig (1982). Contestable Markets and the theory of market
structure. Harcourt, Brace, Jovanovic.
Bonsor, N. (1995). Competition, Regulation and Efficnency in the Canadian Railway and
Highway Industries. Ch. 2 In Essays in Canadian Surface Transportation. Vancouver,
B.C.: Fraser Institute.
Bunn, D. W., & Oliveira, F. S. (2001). Agent-Based Simulation - An Application to the New
Electricity Trading Arrangements of England and Wales. IEEE Transactions on
Evolutionary Computation, (5) 5: 193-503.
Bureau of Transport and Regional Economics. (2003). Rail Infrastructure Pricing: Principles
and Practice - Report 109. Canberra, ACT.
Canadian Grain Commission. (2009). Grain Elevators in Canada: Crop Year 2009-2010.
Available online: http://www.grainscanada.gc.ca/statistics-statistiques/geic-sgc/2009-
08-01.pdf.
Canadian Grain Commission. (2010). Primary Elevators in Western Canada from 1962 to
2010. Available online: www.grainscanada.gc.ca.
Canadian Transportation Agency. (2008). Decision No. 20-R-2008. Available online:
https://www.otc-cta.gc.ca/eng/ruling/20-r-2008
Carlson, L., & Nolan, J. (2005). Pricing Access to Rail Infrastructure. Canadian Journal of
Administrative Sciences, 45-57.
Carlton, D. J. (1994). Modern Industrial Organization. Harper Collins.
Davis, P., & Garces, E. (2010). Quantitative Techniques for Competition and Antitrust
Analysis. Princeton, NJ: Princeton University Press.
Gambardella, L. M., Rizzoli, A. E., & Funk, P. (2002). Agent-based Planning and Simulation
of Combined Rail/Road Transport. Simulation, 78(5): 293-303.
Gintis, H. (2005). The dynamics of general equilibrium. Economic Journal, 117(523):1280-
1309.
Hoover, E. M., & Giarratani, F. (1985). An Introduction to Regional Economics. Toronto,
ON: Random House of Canada Limited.
38
Ivaldi, M., & Vibes, C. (2008). Price Competition in the Intercity Passenger Transport
Market: A Simulation Model. Journal of Transport Economics and Policy, 42(2):
225-254.
Lawrence, R. (2011). Grains, Chains and Trains: An Agent-based model of the Western
Canadian grain handling and transportation supply chain. Saskatoon: University of
Saskatchewan. Available online:
http://ecommons.usask.ca/bitstream/handle/10388/ETD-2011-08-142/LAWRENCE-
THESIS.pdf?sequence=3
Mah, M. (2010). 2004-2009 Western Canadian Rail Rates and CWB Deductions. Available
online: http://www1.agric.gov.ab.ca/$department/deptdocs.nsf/all/econ1523
Mitzutani, F. S. (2013). Does vertical separation reduce cost? An empirical analysis of the
rail industry in European and East Asian OECD countries. Journal of Regulatory
Economics V 43, 31 - 59.
Nolan, J., & Skotheim, J. (2008). Spatial competition and regulatory change in the grain
handling and transportation system in western Canada. Annals of Regional Science,
42:929-944.
Preston, J., Whelan, G., & Wardman, M. (1999). An Analysis of the Potential for On-track
competition in the British Passenger Rail Industry. Journal of Transport Economics
and Policy, 33(1): 77-94.
Quorum Corporation. (2007). Monitoring the Canadian Grain Handling and Transportation
System: Annual Report 2006-2007 Crop Year. Edmonton, Alberta: Quorum
Corporation.
Quorum Corporation. (2010). Grain Monitoring Program Dashboard Q3 2009-2010 Crop
Year. Available online: http://quorumcorp.net/
Saskatchewan Ministry of Agriculture. (2009). Canadian Wheat Board Final Price for
Wheat, basis in-store Saskatoon. Available online:
http://www.agriculture.gov.sk.ca/Default.aspx?DN=d044a25c-9c11-4927-b275-
74668172ee2c.
Simmons-Boardman Publishing Corporation. (2008). Locomotive leasing: what's power
worth today? Available online:
http://findarticles.com/p/articles/mi_m1215/is_6_209/ai_n27944848/pg_3/?tag=mantl
e_skin;content
Statistics Canada. (2006). Farms classified by farm type (NAICS). 2006 Census of
Agriculture, Government of Canada, Ottawa.
39
Statistics Canada. (2007). Saskatchewan Farm Stocks 1980 to 2006. Available thorugh
CANSIM database (CHASS).
Transport Canada (2011) Rail Freight Service Review: Interim Report TP 15042. Minister of
Transport, Ottawa.
Tye, W. (1990). The Theory of contestable markets: Applications to rail and anti-trust
problems in the rail industry. Greenwood Press.
Vercammen, J. (1996). The freight rate setting process. The Economics of Western Grain
Transportation and Handling. Module B-2. Van Vliet Publication Series.
Weyburn Inland Terminal. (2011). Dial-a-Truck Rates. Available online:
http://www.wit.ca/index.php/Rates.html
White, P., C. Carter and R. Kingwell (2015) The Puck Stops Here! Canada Challenges
Australia’s Grain Supply Chains. Research Report, Australian Export Grains
Innovation Centre (AEGIC), Perth, Australia.
Wilensky, U. (1999). NetLogo. Center for Connected Learning and Computer-Based
Modeling, Northwestern U., Evanston, Ill.
40
APPENDIX
Rail rates
The following is a list of the rail freight rates used in the simulation. Actual historical freight
rates for all delivery points could not be found, so efforts were made to build realistic rates and
compare them to data that could be found. In fact, our rate data tracks what we know about
actual rates very well, including tracking a major increase from 1994 to 1995 reflecting the
removal of direct grain transportation subsidies from the system.
Some recent freight rate data was obtained from the Parrish & Heimbecker grain company in
Saskatoon (the largest city in the region), moving grain on CN lines. Calculated applicable CP
rates used in the simulation are based on a simple regression on freight rates, with a differential
applied against the known CN data. In addition, freight rate data from Saskatoon were used as
a benchmark and then other rates were adjusted based on the distance by rail from the delivery
point to Vancouver. Finally, Alberta Agriculture Ministry data was used to help determine the
average differential between CN and CP freight rates across other locations in the province.
41
Table A1.
Base freight rates used in the simulation in $ per tonne, 1977 to 2006
Base Freight
Rate
CN Rail Rate,
in $/t/km
CP Rail Rate,
in $/t/km
Year $ / tonne
1977 4.85 0.0032 0.0034
1978 4.85 0.0032 0.0034
1979 4.85 0.0032 0.0034
1980 4.85 0.0032 0.0034
1981 4.85 0.0032 0.0034
1982 4.85 0.0032 0.0034
1983 5.33 0.0035 0.0037
1984 7.57 0.0050 0.0052
1985 5.90 0.0039 0.0041
1986 5.87 0.0039 0.0041
1987 6.23 0.0041 0.0043
1988 7.15 0.0047 0.0049
1989 8.86 0.0058 0.0060
1990 10.03 0.0066 0.0068
1991 10.37 0.0068 0.0070
1992 11.23 0.0074 0.0076
1993 12.86 0.0085 0.0087
1994 13.37 0.0088 0.0090
1995 33.01 0.0194 0.0196
1996 35.37 0.0208 0.0210
1997 36.08 0.0212 0.0214
1998 35.67 0.0210 0.0212
1999 35.74 0.0210 0.0212
2000 34.31 0.0202 0.0204
2001 35.68 0.0210 0.0212
2002 37.11 0.0218 0.0220
2003 37.85 0.0223 0.0225
2004 35.65 0.0210 0.0212
2005 38.52 0.0227 0.0221
2006 41.85 0.0246 0.0241
$ / tonne / km