Weekly Bridge Inspection – No change

Design – 100% Complete

Permits◦ UPRR has approved plans; now developing agreementpp p ; p g g◦ USCOE and KDWR permit application submitted/under review◦ Environmental: NEPA “Categorical Exclusion”

R-O-W R-O-W ◦ Terms for all ROW purchases have been negotiated/agreed upon

Utility RelocationAll utility companies have been contacted/provided plans and ◦ All utility companies have been contacted/provided plans and preparations being made for relocations (2017)

Page 3: Shawnee County Willard Bridge Presentation September 24, 2015

Funding◦ USDOT TIGER Grant –

i i d i b Anticipate award announcements in October◦ KDOT – In receipt of LOR from BCC; In process of developing No Interest

Loan Agreementg◦ Inter-local Agreement – COT reviewed/discussed; Anticipate return in next few weeks

with comments/requested revisions◦ Wabaunsee County Agreement: Develop after TIGER Grant Wabaunsee County Agreement: Develop after TIGER Grant

determination

Schedule◦ Still hoping for a December 2015 bid letting/December 2017 ◦ Still hoping for a December 2015 bid letting/December 2017

completion◦ Dependent upon funding availability and type

SCDPW tl i “W iti ” M d SCDPW currently in “Waiting” Mode