Saeed Hassan (Graduate Civil Engineer) Professional Progress Report (Jan 2012 – August 2012) (Jan 2012- August 2012 )

Shafqat Rasool Ppp

Embed Size (px)

DESCRIPTION

A presentation of Shafqat

Citation preview

Page 1: Shafqat Rasool Ppp

Saeed Hassan (Graduate Civil Engineer)

Professional Progress Report (Jan 2012 –August 2012)

(Jan 2012- August 2012 )

Page 2: Shafqat Rasool Ppp
Page 3: Shafqat Rasool Ppp

299012 WME 001 000

C:\Documents and Settings\has60385\Desktop\persona\saeed_hassan_60385-

04 Sep 2012

Saeed Hassan (Graduate Civil Engineer)

Professional Progress Report (Jan 2012 – August 2012)

September 2012

Mott MacDonald, PO Box 47094, Al Hashmi Tower, Airport Road, Abu Dhabi, United Arab Emirates

T +971 (0)2 4457 470 F +971 (0)2 4457 490 , W www.mottmac.com

Page 4: Shafqat Rasool Ppp
Page 5: Shafqat Rasool Ppp

Saeed Hassan (Graduate Civil Engineer)

Mott MacDonald, PO Box 47094, Al Hashmi Tower, Airport Road, Abu Dhabi, United Arab Emirates

T +971 (0)2 4457 470 F +971 (0)2 4457 490 , W www.mottmac.com

Revision Date Originator Checker Approver Description

001 17-July-2012 Saeed Hassan Mr.Shuja A Zaidi

002 4-Sep-2012 Saeed Hassan

Issue and revision record

This document is issued for the party which commissioned it

and for specific purposes connected with the above-captioned

project only. It should not be relied upon by any other party or

used for any other purpose.

We accept no responsibility for the consequences of this

document being relied upon by any other party, or being used

for any other purpose, or containing any error or omission

which is due to an error or omission in data supplied to us by

other parties

This document contains confidential information and proprietary

intellectual property. It should not be shown to other parties

without consent from us and from the party which

commissioned it.

Page 6: Shafqat Rasool Ppp
Page 7: Shafqat Rasool Ppp

299012/MWE //001/000 04 Sep 2012 Professional Progress Report

Saeed Hassan (Graduate Civil Engineer)

Title Page

1. Introductory Note

2.Executive Summary i

3. Projects iii

3.1. Background iii

3.2. Al-Markaz Development iv

3.3. Al-Watani Residential Development vi

4.Visits vii

5.A Typical Day On Site vii

5.1. Checklist Table viii

6. Experience ix

6.A. Personal Development ix

6. A.1. Seminars ix

6. A.2. Training

6. A.3. Workshop

6.B. Future Ambitions ix

7. End Note x

Content

Page 8: Shafqat Rasool Ppp

299012/MWE //001/000 04 Sep 2012 Professional Progress Report

Saeed Hassan (Graduate Civil Engineer)

1. Introductory Note:

“Climbing to the top demands strength, whether it is to the top of Mount Everest or to

the top of your career”

‘Career’ as it can be described as an occupation undertaken for a significant period of a person's life and with opportunities for progress. Career can also pertain to an occupation or a profession that usually involves special training or formal education, and is considered to be a person’s lifework. Deciding to move your career forward or to choose a new career, usually that is the hardest part, making the decision to do just that to take action. Then comes the second part, deciding on how you’re going to set goals and maximize your career potential also termed as career development plan.

Career Development Plan is the main key to set realistic expectations of career growth by suggesting time frames for certain milestones to happen (like acquisition of higher knowledge through further training & courses resulting in promotion of skills) and identifying areas that need to develop before becoming eligible for their next career milestone.

These are some terms and facts that really impact one‘s job life or work life from traditional way to a competitive way of progress where every time you have to face challenges that enhance your abilities and help to achieve goals for better career growth. I don’ want to skip the same methodology directed by Project Director Mr. Mubashir Niaz and Project Manager Mr. Anjum Javed that you have not to bound yourself to the work assigned to you but you must prepare yourself for upcoming challenges by setting your short term and long term objectives/goals that actually are related to,

• Education and training

• Job assignments

• Developmental activities

So, for better career development these things should go hand in hand with each other.

This report is also a reflection of their motivation and guidance.

I am very grateful to all my colleagues and seniors for providing such an excellent environment for better career growth/development and also hope the same in the future.

Saeed Hassan (Employee # 60385)

Page 9: Shafqat Rasool Ppp

i 299012/MWE //001/000 04 Sep 2012 Professional Progress Report

Saeed Hassan (Graduate Civil Engineer)

After completion of my graduate studies as a Civil Engineer in July, I started my first job in Pervad Const. as a Junior Infrastructure Engineer from (2009-2010) in Pakistan.

1. Pervad Construction ( 2009-2010):

The responsibilities that assigned to me were,

• Planning and design of water supply scheme and sewerage system (teamwork)

for design build projects.

• Developed hydraulic model for sewerage system using excel spread sheet.

• Review and preparation of monthly/weekly progress reports.

• Participation in weekly progress review and co ordination meetings.

• Coordination with other contractors, consultants and relevant authorities.

• Involved in the review of shop-drawings, method statements, as built drawing and

material submittals as per clients specifications.

2. Bulgu Insaat Ve Ticaret Ltd (Feb 2010- Sep 2011) :

After short duration I realized that to work with international company has more exposure to career development. So, I applied for job in Saudi Arabia and got an offer to work as a Structural Engineer in Riyadh.

I joined Bulgu Insaat Ve Ticaret Ltd, Saudi Arabia (2010 -2011) and mobilized for the

project of Harisulwatani (Special Security Brigade) which was consisted of 151

buildings. The responsibilities assigned were,

� To check Design calculations and prepare design reports using structural

software such as (ETABS & SAFE).

� Prepare the shop drawing and design reports for all buildings according to

site condition that included:

o Footing plan & sections detail

o Slab on grade plan & sections detail

o Grade beam layout plan & sections

o Detail of structure slab(Roof, F.F) and beam elevations

o Detail of parapet & sections

o Drawing to be prepared with co-ordination of mechanical &

electrical plans.

3. Mott MacDonald Consultant Group ( Jan 2012 - Present ) :

I joined Mott MacDonald Consultant Group (Water and Environmental Division) in

January 2012 as a Graduate Civil Engineer and first mobilized to Al-Markaz

Development that is fifty five km southwest of the main Abu-Dhabi Island and adjacent

to the development known as Abu-Dhabi Industrial City V (ICAD V), which consist of

gravity lines and also pressure lines for collection of sewage. There is also one main

Pumping Station designed to collect the discharge and pumped towards external

network by pressure.

2. Executive Summary 2

Page 10: Shafqat Rasool Ppp

ii 299012/MWE //001/000 04 Sep 2012 Professional Progress Report

Saeed Hassan (Graduate Civil Engineer)

As an overview Consultant appointed by ADSSC our main work at site from kick off

meeting and end till the handing over of the project, all of this is a sequence of

learning new things practically and technically.

I was trained in reference with the ADSSC’ Specifications at site by RE Mr.Shuja A

Zaidi and ARE Mr.Iftikhar Ali. As I had never worked for Pumping Station and pressure

line in past, so they helped me on each and every stage of project to handle the

situation and proceeding of work in smooth way in the lights of specification and

standards.

After 4 months I was mobilized to project of Al-Watani Residential Development

pahse-1A and phase-2 in Abu Dhabi Main Island which consists of gravity network

only.

To summarize my experience in seven (7) months with MML is very good as I have

learned many things that can’t be counted but in big scope I experienced that how to

learn and implement technical experience in every field. I gained a good

communication approach between different parties and mostly between the site office

and home office. I have learned different ways for establishing a better connection with

concerned parties by maintaining documentation require during the stage of

construction of a project which is very helpful for me and will surely help in future.

The use of GIS As. Built Drawing and Microsoft Database System in maintaining

record of all the data related to sewer network is one of the latest technologies that I

learned and furthermore PIMS Project Information Management System is a system

first implemented by Mott MacDonald in the region of United Kingdom and is now

extended to MESA. The most advantage of this system is one can have access to all

information about his data throughout the World.

These are some fractions of that I have learned in Mott MacDonald up till now but

journey has not ended, it is now to begin. There are still more to go that actually

depends upon the self esteem and honesty with profession.

Page 11: Shafqat Rasool Ppp

iii 299012/MWE //001/000 04 Sep 2012 Professional Progress Report

Saeed Hassan (Graduate Civil Engineer)

3. Projects: 3.1. Background:

As I was recruited for the Water and Environmental Division in MML and mainly

wastewater works of Abudhabi area where the client is Abu Dhabi Sewerage Services

Company (ADSSC) and under the contract of O-1054 where the responsibilities of

Mott MacDonald is limited to over-seeing the sewerage works for the development.

Contract O-1054 contains almost 20 different projects and I am working on two

projects as a Site Staff amongst them.

Before taking responsibilities of site work and starting work in company everyone has

to go through and passed some courses that are necessary to do work consciously

and safely as Mott MacDonald motto is “COMMITTED TO SAFETY”. I have completed

all of courses and the major are.

1. Welcome to Mott MacDonald (GPEL0139-826)

2. Business Ethics: Getting It Right - Policy Compliance (IMS0071-826A)

3. PiMS Training - Introduction and Overview of PiMS Live link (GPEL0237)

4. Your Performance and Development Review [PDR] (GPEL0149-826)

5. Health and Safety Risk Assessment Training (IMS0051-826)

6. Site Safety Awareness [REST OF WORLD] (IMS0001)

7. The Safe Way to Work (IMS0008-826)

Mott MacDonald has divided the waste water works scope for contract O-1054 in to

four (4) stages.

Stage 1: Review of Conceptual Design

Stage 2: Detailed Design and Tendering Document

Stage 3: Tender Evaluation

Stage 4: Construction Supervision & Handing over the developments

The main concern for me in these stages is construction stage because I am working

as a site staff. The first three stages are mainly handled by home office support

personnel but I often involve in this stage as I am working in developing hydraulic

statement on spread sheet and applying x-checks with Developer consultant’s

statement that mostly include population, sewage load, design flow, gradient, diameter

of pipe used and ratio of Qp/Qf and Vf final velocity by keeping in view the ADSSC

Design Guidelines. I developed following hydraulic statement with support of home

office personnel.

Page 12: Shafqat Rasool Ppp

iv 299012/MWE //001/000 04 Sep 2012 Professional Progress Report

Saeed Hassan (Graduate Civil Engineer)

1. Garden Crescent Zone K

2. Golf Garden Phase-2

3. ARG Attached housing

I am also in involved in updating the monthly progress report for contract O-1054.The

main work assigned to me is,

1. Maintain record regarding Minutes of Meeting (MOM)

2. Location Maps

3. Sub-Project Schedules and Status

4. Site Visit Reports including Fortnightly Visit Reports for ADSSC

5. Monthly progress report and material submittal for different sites of contract O-

1054.

The construction overview work has been further divided in to Material submittals

review and material inspections, Method statement review and supervising the

construction work on site, testing supervision, monthly progress report, material

submittal log, fortnight reports etc.

ADSSC has a set of specification as well as Standard Details Drawings for the

review/supervision of its work that describe about each and every aspect of the project

stage/phase. These are the guidelines for everyone to get a better end result for all

types of sewerage work.

3.2. Al-Markaz Development, Abu Dhabi: a) Introduction:

The Al Markaz development is located close to the Mussafah Industrial area

approximately fifty five km southwest of the main Abu-Dhabi Island and adjacent to the

development known as Abu-Dhabi Industrial City V (ICAD V). The population of Al

Markaz development will be approximately 22, 215 diverse occupants, consisting of

residential, business and industrial components of the development. Al Markaz covers

approximately 600 hectares and it has been split into four phases each of 150

hectares. Phase 1 being 1st stage started in November, 2011 and is in progress now.

The sewage will be discharged to the proposed pumping station near Hameem

Roundabout that connects to Industrial Effluent treatment plant located within vicinity.

A main pumping station with the total capacity of 38 l/s will be located at the boundary b/w phase 1 and 2. The sewerage network has a total of approximately 7.5 km gravity pipe lines ranging from 160mm to 300mm diameter with a depths varying from 1.00m to 11.00m.

Page 13: Shafqat Rasool Ppp

v 299012/MWE //001/000 04 Sep 2012 Professional Progress Report

Saeed Hassan (Graduate Civil Engineer)

b) Responsibilities:

• Inspection of construction work and verifying with the procedures mentioned in the accepted method statement.

• Inspection of the material and testing on site and factories and the third party laboratories.

• Maintaining all types of logs i.e. Material submittal log, Method statement logs, Shop drawings log, Pipeline progress log, Manhole log.

• Prepare the Monthly Progress report on the basis BOQ and Fortnight Reports.

• Review of the shop drawings for the network i.e. layout plan and profile.

• Inspection and testing on site for the construction of sewer line by Hydrostatic testing for any leakage and Deflection test for any deformation in pipe in accordance with ADSSC specification.

• Maintenance of all the documents in the PIMS database server i.e. includes scanning and maintaining record on each specified location in database.

• Maintenance of all related documents at site that more or less include material submittal ,method statement, shop drawings, MIR, inspection request for testing of line, HSE related document.

• Inspection of site safety procedures and implementations on site.

• Report to ARE for day to day progress.

• Inspection of HDPE sewer pressure line.

c) Experience Gained:

Al-Markaz Development was my first project and gained lot of experience from my

seniors who guided and taught me most of the aspects and technical issues related to

work and also managing the data that is very valuable at the end of time i.e. for

Handing over procedures. Every day I learned new skills including technical or non

technical and also managerial skills to manage the project. This project is not mere a

gravity network but it also contain HDPE pressure lines for sewerage line and one

pumping station that has great influence on my experience . The main areas of

concern are.

• ADSSC specification’s implementation on site

• Document management system

• Testing and inspection procedure for ongoing work

• Dewatering procedure

• Material Inspection procedure

• Daily work reporting

• Pump station drawings and components

• Pressure line testing

Page 14: Shafqat Rasool Ppp

vi 299012/MWE //001/000 04 Sep 2012 Professional Progress Report

Saeed Hassan (Graduate Civil Engineer)

Watani Location Plan Proposed Final Plan On going Work

3.3. Al-Watani Development, Abu Dhabi: a) Introduction:

Al- Watani, Sorouh’s first master-developed community dedicated to Emirati citizens,

is located in Khalifa City “A” and close to the Abu Dhabi Golf Course.

This residential community, which is being constructed to meet the standards and

requirements of UAE national family living, will also offer a superb range of amenities,

including mosques and retail facilities housed within a mall.

Under the patronage of the Government of Abu Dhabi, this development will bring

to life a community that caters specifically to UAE Nationals.

Mott MacDonald scope of work in this project is as an overview consultant for

sewerage system. At present two phases are in progress that contains a gravity

system for transport and disposal. The sewerage system is comprised of a length of

5.9km and 5.7km approximately for Watani phase-1 and phase-2 respectively.

b) Responsibilities:

• Inspection of construction work and verifying with the procedures mentioned in the accepted method statement.

• Inspection of the material and testing on site and factories and the third party laboratories.

• Maintaining all types of logs i.e. Material submittal log, Method statement logs, Shop drawings log, Pipeline progress log, Manhole log.

• Prepare the Monthly Progress report on the basis BOQ and Fortnight Reports.

• Review of the shop drawings of the network such as layout and profile and pumping station with concept design.

• Inspection and testing on site for the construction of sewer line by Hydrostatic testing for any leakage and Deflection test for any deformation in pipe in accordance with ADSSC specification.

• Maintenance of all the documents in the PIMS database server i.e. includes scanning and maintaining record on each specified location in database.

Page 15: Shafqat Rasool Ppp

vii 299012/MWE //001/000 04 Sep 2012 Professional Progress Report

Saeed Hassan (Graduate Civil Engineer)

• Maintenance of all related documents at site that more or less include material submittal ,method statement, shop drawings, MIR, inspection request for testing of line, HSE related document.

• Inspection of site safety procedures and implementations on site.

• Review of As Built drawings with accepted shop drawings.

• Preparation of logs and documents for handing over procedure.

• Report to ARE for day to day progress.

c) Experience Gained:

Presently I am working on Watani Development project and gained lot of experience

up till now under the guidance of my seniors ARE Mr. Saddar-ul-Islam and RE Mr.

Shuja A Zaidi, who taught me most of the aspects and technical issues related to

work and also managing the data that is very valuable at the end of time i.e. for

Handing over procedures. As this project is not same as previous project in most of

aspects so every day I learned new things that I had not experienced in past. Some

of important things are

• Working with double skin liner for GRP Manhole and Inspection Chambers.

• GRP lamination and Jointing System for external and internal Liner.

• Soil improvement technique.

• Temporary connection works with existing Manhole/line.

• PAC form data elaboration (Handing over Form) before ADSSC final inspection.

• Review of Material submittals

4. Visits: • Visit to Anabeeb Factory for the testing of Upvc pipes located in Musaffah Abu

Dhabi UAE.

• Visit to Exova limited (Abu Dhabi) for the testing of Steel Reinforcement.

5. A Typical Day on Site:

Refer to Checklist below:

Page 16: Shafqat Rasool Ppp

viii 299012/MWE //001/000 04 Sep 2012 Professional Progress Report

Saeed Hassan (Graduate Civil Engineer)

SR # Description Status

1 Get ready and communicate with other colleagues.

2 Take all required PPE (i.e. Hard hat, High visibility Jacket, Safety shoes

and Mask etc).

3 Visit Head Office to take all document/Correspondence if any for site

record.

4 Coordination with other site members before going to site in case of

multiple sites.

5 Visit that site for which ongoing work require more attention as directed

by Senior site staff.

6 Schedule all inspection requests in a way so maximum work can be

inspected.

7 Daily visit to all sites to inspect the progress, quality and Safety of work.

8 If any non-compliances observed regarding site safety or quality of work

immediately report to Senior site staff.

9 Collect all data required i.e. progress photos, MIR, Test inspection

request.

10 Report to Senior site staff for all activities for respective day.

11 Take necessary actions as directed by Senior site staff for ongoing site

work and other issues regarding materials and data management/record

if any.

12 Record all instructions and data by updating all related log, and

maintaining it continuously.

13 Arranging all data in a way that can be access at any time and without

wastage of time.

14 Prepare progress drawing by highlighting all proceeding work on

drawings.

15 Prepare Fortnight and Monthly progress report.

Page 17: Shafqat Rasool Ppp

ix 299012/MWE //001/000 04 Sep 2012 Professional Progress Report

Saeed Hassan (Graduate Civil Engineer)

6. Experience: A) Personal Development:

Working with a multi national company like Mott MacDonald who have a slogan of ‘committed to Safety’ is a great achievement for me and here I am learning lots of things technically and managerially i.e.

• Completion of task within limited timeframe.

• Data Management system.

• Safety procedure and courses/Training.

• Knowledge development in terms of short courses.

• Planning of work etc.

A.1) Seminars:

• Key Concepts in Project Management ( 3FOLD Education Centre Abu Dhabi UAE )

A.2) Training:

• Confined Space Entry (Emirates Technical & Safety Development Centre

Abu Dhabi UAE).

• Authorised Gas Tester (Emirates Technical & Safety Development Centre Abu Dhabi UAE).

A.3) Workshop:

• Scheduling and Cost Control ( 3FOLD Education Centre Abu Dhabi UAE )

B) Future Ambitions:

• Master in Engineering Management

• Master degree in Infrastructure work.

• PHD in Engineering Management

• To be a part of higher Management in company

Page 18: Shafqat Rasool Ppp

X

Saeed Hassan (Graduate Civil Engineer)

7. End Note:

Success is simple. Do what’s right, the right way, at the right time.

Arnold H. Glasgow

I understand that the key to success is to look forward, perform with sheer hard

work, total commitment to assigned duties/ responsibilities and honesty in all walks

of life.

I personally feel that this is the right time for me to move forward towards my career goal by working and learning with such an amazing and wonderful team that I have. I am very grateful to Peter Hall (Divisional Manager), Mubashir Niaz (PD) , Anjum Javed (PM), Shuja Abbas Zaidi (RE), Saddar-ul-Islam (ARE), Iftikhar Ali (ARE), Amanullah (ARE), Nasir Mehmood, Zahid Hussain , Javed Khokhar, Ibrar Farooq and Waseem Abbasi.