38
Settlement System under ABT Regime

Settlement System under ABT Regime

  • Upload
    dick

  • View
    29

  • Download
    1

Embed Size (px)

DESCRIPTION

Settlement System under ABT Regime. WHAT IS SETTLEMENT ?. “ Settlement means finalisation of payment bill after consumption” To be FAIR and EQUITABLE To RECOVER DUES at the EARLIEST (Billing Cycle) TRANSPERANCY Dispute Resolution Reconciliation. AVAILABILITY TARIFF(ABT). - PowerPoint PPT Presentation

Citation preview

Page 1: Settlement System  under ABT Regime

Settlement System under ABT Regime

Page 2: Settlement System  under ABT Regime

WHAT IS SETTLEMENT ?

• “ Settlement means finalisation of payment bill after consumption”• To be FAIR and EQUITABLE• To RECOVER DUES at the EARLIEST

(Billing Cycle)• TRANSPERANCY• Dispute Resolution• Reconciliation

Page 3: Settlement System  under ABT Regime

AVAILABILITY TARIFF(ABT)(a) CAPACITY CHARGE(b) ENERGY CHARGE(c) ADJUSTMENT FOR DEVIATIONS

(UI CHARGE)

(a) = a function of Ex-bus MW avilability of power plant for the day declared before the day starts x SEB’s % share

.(b) = MWh for the day as per ex=bus drawal schedule for the

SEB finalized before the day starts x Energy charge rate

(c) =Σ(Actual energy interchange in a 15 min time block – scheduled energy interchange for the time block) x UI rate for the time block.

TOTAL PAYMENT FOR THE DAY =(a) + (b)± ( c)

Page 4: Settlement System  under ABT Regime

Capacity charge:

Capacity charge is based on Annual Fixed Charge and will be related to availability of generating station. Availability means the readiness of the generating station to deliver ex-bus output expressed as a percentage of its rated ex-bus output capability.

Energy charge:

Energy charge is related to the scheduled ex-bus energy to be sent out from the generating station and will be worked out on the basis of paise per KWh.

Page 5: Settlement System  under ABT Regime

Settlement Systems* On weekly basis : For seven day period ending on penultimate Sunday

•RLDC to furnish Scheduling & Metering data to REB• Sectt. by Thursday noon

•REB Sectt. to issue Weekly UI a/c by Tuesday

•Pool a/c operated by RLDC•Settlement for UI on weekly basis•All accounts open for 20 days

On monthly basis : REB to issue REA specifying % Avb, % Net Entitlement, % Energy charges, Wt. Avg. Ent. for Tr. Ch. etc.

Capacity and Energy Charges, Incentive etc. –billed directly by ISGS based on REA issued by REB

SRLDC/Comml/IEGC/34

Page 6: Settlement System  under ABT Regime

WEEKLY ENERGY ACCOUNTING:

WEEKLY CYCLE : 00 HRS OF EACH MONDAY TO 24 HRS; OF THE THE FOLLOWING SUNDAY

ACTIVITIES MONDAY MORNING : SEM DATA DOWNLOADED TO DCD

: DCD DATA LOADED TO A LOCAL PC: DATA SENT TO RLDC via E-MAIL

(LATEST TUESDAY MORNING )THURSDAY NOON : RLDC CONVEYS PROCESSED DATA TO

REBTues day : WEEKLY UI a/c & Reactive charges

issued BY REBBILLING

Cap. Charge : BILLED MONTHLY based on DAILY DC BY ISGS

ENERGY CHARGE : BILLED MONTHLY based on DAILY DRAWL SCHEDULES ISSUED BY RLDC

UI a/c Paid/Disbursed as per UI a/c issued by REB

REACTIVE a/c

Page 7: Settlement System  under ABT Regime

SETTLEMENT SYSTEMFor the day: 0000 hrs. to 2400 hrs.

Central Generating Stations 1 2 3

Ex-Bus Capability x1 x2 x3(Forecast) ____ ___ ___

SEB-A’s share a1 a2 a3SEB-B’s share b1 b2 b3SEB-C’s share c1 c2 c3

For a particular 15 minute time block

SEB-A’s requisition a’1 a’2 a’3SEB-B’s requisition b’1 b’2 b’3SEB-C’s requisition c’1 c’2 c’3

___ ___ ___CGS’s schedule x1’ x2’ x3’

MW

SRLDC/Comml/IEGC/37

Page 8: Settlement System  under ABT Regime

1000MW

800

600

400

200

00 6 12 18 HRS 24

Forecast ex-bus capability of power plant

SEB - A’s entitlement (40%)

Entitlement for which Capacity chargesAre payable by SEB-A

Schedule for which Energy chargesAre payable by SEB- A

Declared Capability for which Capacity chargesAre recieveable by ISGS

Gen.Sched. for which Energy chargesAre recieavable by ISGS

Page 9: Settlement System  under ABT Regime

SETTLEMENT SYSTEM

Total capacity charge payable to CGS-1 for the day= x1 * capacity charge rate of CGS-1

Total Energy charge payable to CGS-1 for the day

= x1’ * Energy charge rate of CGS-1 4

Total capacity charge payable by SEB-A for the day

= a1 * capacity charge rate of CGS-1

+ a2 * -do- CGS-2

+ a3 * -do- CGS-3Total Energy charge payable by SEB-A for the day

= (a1’) * Energy charge rate of CGS-1 ( 4 )

+ (a2’) * -do- CGS-2 ( 4 )

+ (a3’) * -do- CGS-3 ( 4 )

All capacity charge and Energy charge payments to be made by SEBs directly to CGS.

SRLDC/Comml/IEGC/38

Page 10: Settlement System  under ABT Regime

SETTLEMENT SYSTEM

Actual (metered) injection of CGS-1 in the time block = X1 MWh.

Excess injection = (X1 – x1’ ) MWh.

4

Amount payable to CGS-1 for this =(X1-x1’) * pool price for the block.

4

SEB-A’s scheduled drawl for time block = a1’+a2’+a3’ = a’ MW (ex-CGS Bus)

SEB-A’s NET drawal schedule = (a’ – Notional Transm. Loss) MW

= (a’ – Notional Transm. Loss) = A’ MWH

4

Actual (metered) net drawal of SEB-A during time block = A MWH

Excess drawal by SEB-A = (A-A’) MWh.

Amount payable by SEB-A for this = (A-A’) * pool price for the block.

All above payments for deviations from schedules to be routed through a pool A/C operated by RLDC

SRLDC/Comml/IEGC/39

Page 11: Settlement System  under ABT Regime

Previous definition of Capacity charges% Availability for ISGS =

∑ SOC +CL 100

h x IC

Where SOC = Sent Out capability for the I th block n = total no. of blocks in the period under consideration aux = normative % auxiliary consumption as % of gross Gen. CL = Gross MWh of capacity kept closed on a/c of Gen. Sched order IC= installed capacity in MW

h = no. of hours during the period = n/4

% Availability forms the basis for calculations

n

i=1

(1-aux/100)

i

i

Page 12: Settlement System  under ABT Regime

Present Definition Capacity charges

% Availability = i=1

N

DCi/ {NxICx(100-Auxn) }%10000

Where DCi = Average Declared Capacity for i th day of the period in MW N = Total no. of days during the period Auxn = Normative Auxiliary Consumption as % of gross Gen.

IC= installed capacity in MW

% Availability forms the basis for calculations

i=1

N

SGi/ {NxICx(100-Auxn) }%10000PLF =

Page 13: Settlement System  under ABT Regime

Recovery of Annual fixed charges100% recovery

if % Availability >=Target Availability

- Pro-rata reduction

if %Avb<T.Avb.

- Target Avb. For Fixed ch recovery

- Target PLF for incentive

-Both to be Notified by CERC

-Financial Year forms the basis for calculations

Target Avb. Target PLF

RSTPS 80% 80%

NLC 75% 75%

Page 14: Settlement System  under ABT Regime

Monthly Capacity charges receivable by an ISGS:1 st Month = (1xACC1)122 nd Month = (2xACC2-1ACC1)12….….12 th month = (12xACC12-11ACC11)12where ACC1,ACC2…….ACC12 = Annual capacity charges corresponding to the cum. Availability up to the corresponding month.

Monthly Capacity charges payable by a beneficiary :1 st Month = (1xACC1xWB1)122 nd Month = (2xACC2xWB2-1ACC1xWB1)12….….12 th month = (12xACC12xWB12-11xACC11xWB11)12where WB1,WB2…..WB12 = Weighted average % share up to the corresponding month.

Page 15: Settlement System  under ABT Regime

Name Of ISGS

Aux.

Consumption

Variable

Charges (Ps)

RSTPS 8.43% 85.96

NLC II/1 10.00% 67.99

NLC II/2 10.00% 94.61

NLC TPS 1 (EXP)

9.50% 98.11

TALCHER-

STAGE II

8.50% 44.02

Fixed/Variable

Page 16: Settlement System  under ABT Regime

Energy charges

The Energy Charges Payable by beneficiary to the ISGS =

Variable Charge of ISGS X

Requisition of beneficiary from The ISGS

The Energy Charges Receivable by ISGS from beneficiaries =

Variable Charge of ISGS X

Despatch schedule of ISGS

Page 17: Settlement System  under ABT Regime

Incentive as per old norms

PLF = scheduled energy

IC x no. of hours

Incentive rate beyond 90%PLF =

25% Annual Fixed charges

Energy per anum at target PL

Incentive rate up to 90%PLF =

50% Annual Fixed charges

Energy per anum at target PLF

Incentive rate up to 90%PLF =

50% Annual Fixed charges

Energy per anum at target PLF

Incentive rate up to 90%PLF =

50% Annual Fixed charges

Energy per anum at target PLF

Page 18: Settlement System  under ABT Regime

• Flat rate of 25ps/u

• For ex-bus Schedule Energy in Excess of ex-bus energy corresponding to Target PLF

Incentive as per New norms

Page 19: Settlement System  under ABT Regime

Variations in actual generation/drawal and scheduled generation /drawal are accounted through UI. This is a frequency linked charge which is worked out for each 15 minute time block.

Charges for all UI transaction, based on average frequency have following rate of paise per KWh from 01.01.03 up to 31.03.04.

UI rate (Paise per KWh)

Average Frequency of time block50.5 Hz. and above 0.0Below 50.5 Hz. and upto 50.48 Hz. 5.6Below 49.04 Hz. and upto 49.02 Hz. 414.4Below 49.02 Hz. 420.0Between 50.5 Hz. and 49.02 Hz. Linear in 0.02 Hz. step

Unscheduled Interchanges (UI)

Page 20: Settlement System  under ABT Regime

UI rate w.e.f 01.04.04 to 30.09.04 UI rate (Paise per KWh)

Average Frequency of time block50.5 Hz. and above 0.0Below 50.5 Hz. and upto 50.48 Hz. 8.0Below 49.04 Hz. and upto 49.02 Hz. 592.0Below 49.02 Hz. 600.0Between 50.5 Hz. and 49.02 Hz. Linear in 0.02 Hz. step

Page 21: Settlement System  under ABT Regime

• UI rate w.e.f 01.10.04 UI rate (Paise per KWh)

Average Frequency of time block (Hz,)Below Not below ----- 50.50 0.050.50 50.48 6.050.48 50.46 12.0----- ----- ----- ----- ----- ----- 49.84 49.82 204.049.82 49.80 210.049.80 49.78 219.049.78 49.76 228.0----- ----- ----- ----- ----- ----- 49.04 49.02 561.049.02 ----- 570.0(Each 0.02 Hz. Step is equivalent to 6.0 paise/kWh in the 50.5-49.8 Hz. Frequency range and to 9.0 paise/kWh in the 49.8-49.0 Hz. Frequency range).

Page 22: Settlement System  under ABT Regime

Energy transactions of UI from/to Pool

Over Gen. By ISGS-1

Under drawl by SEB-A

UI import from IR-1

Under gen. By ISGS-2

No one to one correspondence

System frequency UI

RateRegional Pool

Over drawl by SEB-BUI Export to IR-2

Page 23: Settlement System  under ABT Regime

Operation of Pool

Separate Pool a/cs operated by RLDCs on behalf of REBs for UI, IRE and Reactive charges

Regional Pool

Payable by ISGS-2

Payable by SEB-BPayable by IR-2at its UI rate

Receivable by ISGS-1 (up to DC) Receivable by SEB-A Receivable by IR-1

at its UI rateNo one to one correspondence

No cross adjustments allowed between the constituents

Page 24: Settlement System  under ABT Regime

Where do SEMs come into picture?

• Only measuring Deviations from Schedulei.e. UI

• To measure 15 min block-wise Energy and Frequency

Issues concerned :-Specifications-Location criterion-Main/Check/Standby philosophy

Page 25: Settlement System  under ABT Regime

SEMs Specification

• Static type• Composite meter • Highest accuracy available in the power industry• 3 Phase – 4 wire connections/measurement• Direct measurement in whrs and varh on the CT/PT

secondaries– 110 V Ph to Ph /63.51 V Ph – N– 1 amp or 5 amp– VA burden not more than 10 on any of the phases

• Works on real time clock• No calibration required

Page 26: Settlement System  under ABT Regime

FEATURES OF SPECIAL ENERGY METERS :• ACCURACY : 0.2 S AS PER OEC -687, 1992

• STATIC, TOTALLY TAMPER - PROOF, SEALED FOR LIFE

• GALVANIC ISLATION AND SURGE SUPRESSION

• TWO STANDARD MODELS : 110V, 1A AND 110V, 5A

• NON - VOLATILE MEMORY FOR 10 DAYS

• HARMONICS FILTERED OUT AND ONLY FUNDAMENTAL ENERGY RECORDED

• ALL MEASUREMENTS, RECORIDNG IN SECONDARY QUANTITIES. CT AND VCT RATION APPLIED IN REGIONAL COMPUTATION

• NET ENERGY ( WH) EXCHANGE IN EACH 15 MIN. BLOCK

• CUMULATIVE WH TRANSMITTAL AT EACH MIDNIGHT

• AVERAGE FREQUENCY IN EACH 15 MIN. BLOCK

• CUMULATIVE REACTIVE ENERGY EXCHANGE WHILE VOLTAGE IS 97% OR BELOW

• CUMULATIVE REACTIVE EXCHANGE WHILE VOLTAGE IS 103% OR ABOVE.

Page 27: Settlement System  under ABT Regime

FEATURES OF SPECIAL ENERGY METERS : contd….

• HIGH-ACCURACY OF INTERNAL CLOCK: ONE MINUTE/MONTH,WITH RESTRICTED ADVANCE/ RETARD FACILITY

• TAGGING OF DATA WITH DATE, TIME METER NO. IDENTIFICATION OF TIME BLOCK WHEN VT SUPPLY DISTRUBED

• NO SEPARATE AUXILIARY SUPPLY ; ONLY OPTICAL COUPLER FOR DATA COLLECTION ( WEEKLY)

• DISPLAYS TO APPRISE THE SUBSTATION OPERATOR AS TO WHAT IS BEING RECORDED IN METERS MEMORY

Page 28: Settlement System  under ABT Regime
Page 29: Settlement System  under ABT Regime

Raw dataWEEK FROM 0000 HRS OF 06-01-01 TO 0837 HRS OF 15-01-01NP-0185-A 91858.5 99968.5 39195.5 06-01-01 00 51 +21.57 48 +21.68 50 +21.71 49 +21.33 04 19 +20.61 23 +20.80 19 +21.05 00 +21.3508 00 +24.95 00 +24.95 00 +25.09 00 +24.38 12 71 +24.38 52 +23.98 30 +23.81 13 +24.0316 00 +23.37 00 +23.52 00 +22.87 00 +21.66 20 00 +25.75 00 +25.32 00 +25.40 00 +25.37 NP-0185-A 94117.2 99968.5 40313.5 07-01-01 00 59 +20.94 54 +21.01 59 +20.79 58 +21.05 04 33 +20.05 38 +20.17 37 +20.49 28 +20.9008 00 +22.99 06 +23.10 00 +22.81 00 +22.94 12 85 +20.93 51 +20.65 21 +20.79 00 +19.89 16 07 +20.14 01 +20.53 00 +20.72 00 +20.6620 05 +23.62 08 +23.23 16 +23.25 27 +23.40 NP-0185-A 96172.2 99968.5 41236.9 08-01-01 

Page 30: Settlement System  under ABT Regime

Computed Mwh data230 kV Neyveli line at PondicherryCTR = 600 PTR = 2091PO-02 NP-0185-A 06-01-01 2833.8145 0.0 1402.60000 27.061722 27.199728 27.237366 26.760618 0100 26.911171 26.547337 26.735525 25.907490 0200 26.196047 25.932583 26.522243 26.622612 0300 26.509697 26.321507 25.844761 25.644024 0400 25.857307 26.095678 26.409328 26.798256 0500 26.785711 27.839575 28.567242 28.780525 0600 29.458008 29.269817 30.072762 30.198221 0700 31.126625 31.314816 31.289724 31.214447 0800 31.302271 31.302271 31.477915 31.603374 0900 31.603374 31.289724 31.402639 31.553190 1000 30.775339 31.201902 31.565735 31.515553 1100 31.603374 30.198221 30.424049 30.235861 1200 30.587147 30.085308 29.872025 30.148039 …. ….. ….. ….. …..2300 27.726660 27.350279 26.760618 26.346600  

Page 31: Settlement System  under ABT Regime

Active energyENERGY ACCOUNTING USING SPECIAL ENERGY METER FOR 15-12-00--------------------------------------------TIME PONDY YANAM Net Drawal PO-02 PO-06 IN Mwhr--------------------------------------------00:00 +31.77 +1.83 +33.6000:15 +31.68 +1.83 +33.5100:30 +32.06 +1.85 +33.9000:45 +31.59 +1.77 +33.3601:00 +31.11 +1.54 +32.6501:15 +30.76 +1.62 +32.3901:30 +30.94 +1.57 +32.5101:45 +31.06 +1.79 +32.8502:15 +31.04 +1.85 +32.88-------------------------------------------------------------------------------------23:15 +27.38 +1.90 +29.2723:30 +27.00 +1.91 +28.9023:45 +26.48 +1.89 +28.37--------------------------------------------TOTAL +3060.16 +176.12 +3236.28---------------------------------------------

Page 32: Settlement System  under ABT Regime
Page 33: Settlement System  under ABT Regime

REACTIVE ENERGY CHARGE :

PAYABLE FOR :

1. VAR DRAWALS AT VOLTAGES BELOW 97%2. VAR INJECTION AT VOLTAGES ABOVE 103%

RECEIVABLE FOR:

1. VAR INJECTION AT VOLTAGES BELOW 97%2. VAR DRAWAL AT VOLTAGES ABOVE 103%

APPLIED FOR VAR EXCHANGES BETWEEN :

A) BENEFICIARY SYSTEM AND ISTS- THROUGH A POOL ACCOUNT

B) TWO BENEFICIARY SYSTEMS ON INTER-STATE TIES- BY THEMSELVES

RATE: @ Rs. 48.62/MVArh (for 2004-05)Basic Rate : 4 paise/kvArh ( for the year 2000-01 )

5% ESCALATION PER YEAR

Page 34: Settlement System  under ABT Regime

Issues in Reactive Energy charges

• Deficit in pool (SR & ER)-due to continuous High voltages in SR

Surplus in Pool (NR &WR)

Utilization of Accruals

Disputes in payments between Beneficiaries for Reactive charges in Inter-state Lines

Page 35: Settlement System  under ABT Regime

SOUTHERN REGIONAL ELECTRICITY BOARDABT based U.I. Account

FOR THE PERIOD 25.10.2004 to 31.10.2004A.      ABSTRACT OF UNSCHEDULED INTERCHANGES ( UI

figures in Rs. Lakhs)

Utilities UI Payable Utilities UI Receivable

KPTCL 1172.68548 APTRANSCO 759.45210PONDY 93.76627 TNEB 310.25146KSEB 62.34445 ER 297.73327GOA 35.18813 RSTPS 72.80693NLC MINES 35.16922 Talcher 34.27954NLC II - 1 8.36314 NLC-1-EXP 14.82175NLC II - 2 4.33511 PG-HVDC 10.05435WR 4.13279Total 1415.98459 Total 1499.39940

Page 36: Settlement System  under ABT Regime

NOTE:1.       Revised UI rates w.e.f. 1/10/2004 vide CERC

(Terms and Conditions of Tariff) (First Amendment) Regulations 2004.

2.       MAPS & KGS not covered under ABT; hence UI reduced to zero, under all conditions.

3.       UI for Talcher STPS Stage-II has been calculated at ER frequency.

4.       IR Exchanges:i)    Metering points – For WR it is Chandrapur South

Bus. - For ER it is Gazuwaka East Bus &

Talcher stage I&II I/C bus.ii)            UI for IR exchanges with ER has been

calculated at SR frequency as per the decision taken in Special TCC meeting held at Bangalore on

23.08.2004.iii)      UI charges with WR and ER has been taken as first charge, as per decision taken in Special

Committee meeting held on 17.12.2002. 

Page 37: Settlement System  under ABT Regime

A.      ABSTRACT OF UNSCHEDULED INTERCHANGES (restricting to the lesser of the two as per the

126th SRE Board decision).

(UI figures in Rs. Lakhs)  Utilities UI Payable Utilities UI Receivable

KPTCL 1172.68548 APTRANSCO 706.73400

PONDY 93.76627 TNEB 288.71506

KSEB 62.34445 ER 297.73327

GOA 35.18813 RSTPS 67.75297

NLC MINES 35.16922 Talcher 31.89999

NLC II - 1 8.36314 NLC-1-EXP 13.79288

NLC II - 2 4.33511 PG-HVDC 9.35642

WR 4.13279TOTAL 1415.98459 TOTAL 1415.98459

Page 38: Settlement System  under ABT Regime

Payable to Pool

Receivable from Pool

APTRANSCO 2275540

KPTCL 2939838

KSEB 565089

TNEB 3138559

B.NET REACTIVE ENERGY CHARGES BETWEEN BENEFICIERIES:

PONDY APTRANSCO 3,705GOA KPTCL 0

TNEBAPTRANSCO 92KPTCL 0KSEB 0

KSEBKPTCL 0TNEB 348,399

KPTCL

APTRANSCO 10,526KSEB 22,443TNEB 69,931GOA 0

APTRANSCOKPTCL 0TNEB 0PONDY 0

BY BENEFICIERY

FROM BENEFICIERY

AMOUNT RECEIVABLE

in Rupees

( Amount in Rupees)

Beneficiaries Beneficiaries

(as per decision in the 132nd meeting of SRE Board)

SOUTHERN REGIONAL ELECTRICITY BOARD

Reactive Energy Charges AccountFOR THE PERIOD 25-10-2004 to 31-10-2004

A.REACTIVE ENERGY CHARGES WITH THE POOL :