Setraco Nig.Ltd. 1 st Bi-Monthly Project Report Of EDO- State ( Auchi ) Prepared By: Checked By: Engr. Amaresh Dhibar Engr. Pedro Chami Technical Office Engineer Project Manager Approved By: Engr. Zakhia Akl Regional Manager

Setraco EDO State project presentation

Embed Size (px)

Citation preview

Page 1: Setraco EDO State project presentation

Setraco Nig.Ltd.

1st Bi-Monthly Project Report Of

EDO- State ( Auchi )

Prepared By: Checked By: Engr. Amaresh Dhibar Engr. Pedro Chami Technical Office Engineer Project Manager

Approved By:Engr. Zakhia Akl

Regional Manager

Page 2: Setraco EDO State project presentation

PROJECTSEDO- State consist of Three different Project Named-CONSTRUCTION OF JATTU - AFOWA - IYORA - AKPANA - AYOGWIRI ROAD (11+772 KM) INCLUDING ONE BRIDGE OF 1X15 M SPAN IN EDO STATE.

CONSTRUCTION OF AYOGWIRI-APANA-IMIEKBA-IMIEKIBU ROAD (18+730 KM) WITH ONE BRIDGE OF 3X20M SPAN INCLUDING IGBODOR-OKPEKPE-SPUR ROAD (7+56O KM) WITH ONE BRIDGE OF 2X20M SPAN.

CONSTRUCTION OF EKPERI-ANEGBETTE ROAD (30+100 KM) WITH TWO BRIDGES 3X15 M SPAN & 4X15 M SPAN.

Setraco Nig.Ltd.

Page 3: Setraco EDO State project presentation

PROJECT DETAILSPROJECTS LENGTH

OF ROAD

CLIENT CONSULTANT BRIDGES

Jattu Road 11+772 Km

EDO STATE GOVERNMENT OF NIGERIA ,EDO STATE MINISTRY OF WORKS,

BENIN , EDO STATE.

CYPRESS KONSULT LIMITED

1 NBR.1X15 M SPAN

Ayogwiri & okpekpe

Road

18+730 Km&

7+560 Km

CYPRESS KONSULT LIMITED

1 NBR. 3X20M SPAN & 1 NBR. 2X20

M SPAN

Ekperi- Anegbette

Road30+100 KM NOBA NIG. LTD.

1 NBR 3X15M SPAN &

1 NBR 4X15 M SPAN

Setraco Nig.Ltd.

Page 4: Setraco EDO State project presentation

CONTRACT DETAILSSetraco Nig.Ltd.

PROJECT CONTRACT TYPE

DATE OF AWARD

COMMENCEMENT OF

WORK

CONTRACT SUM IN MILLION NAIRA ( N ) DURATION

IN WEEKSORIGINAL REVISED

Jattu Road Item Rate Dec. 2009 12thJan.2010 2717.72 3029.83 72

Ayogwiri &

okpekpe

Road

Item Rate Dec. 2009 28thDec.2009 6162.98 6793.74 72

Ekperi- Anegbett

e RoadItem Rate Dec.2009 14th Jan.2010 7667.71 7927.84 120

Page 5: Setraco EDO State project presentation

Organogram Of EDO ProjectSetraco Nig.Ltd.

Engr. Pedro Chami Project Manager

Engr. Zakhia Akl Regional Manager

Carlos

Haddad

Commerci

al Adm

n.

Engr. Geor

ge Badd

er Site

Engineer

Wiliam Tayar Road-superintendent

K.B.AryaLab S/v

George

nouhiely Snr.

Store Keep

er

Engr. Amaresh

Dhibar

Tech. Offic

e Engineer

Jad Chahada Sr.

Plant Engineer

Yusuf Wetwet Camp Manager

Page 6: Setraco EDO State project presentation

General layout of jattu-apana road projectSetraco Nig.Ltd.

JATTUCH0+000

APANACH11+772

AFOWA

IYORA

BRIDGE CH 8+232

IMIEKEBU

JATTU-APANA ROAD

AYOGWIRI

AYO

GWIR

I-IM

IEKI

BU R

OAD

Page 7: Setraco EDO State project presentation

General layout of ayogwiri & okpekpe project

Setraco Nig.Ltd.

JATTU AYOGWIRICH0+000

IMIEKIEBUCH0+18+786

IGODOR CH-0+000

SPOURCH-7+563

APANA

IMIEKBA

OKPEKPE-SPOUR

ROAD

AYOGWIRI-IMIEKIBU

ROAD

OKPEKPE

BRIDGE CH-5+325BRIDGE

CH-11+825

Page 8: Setraco EDO State project presentation

General layout of ekperi-anegbette road project

Setraco Nig.Ltd.

EKPERI CH 0+000

ANEGBETTE CH-30+100

BRIDGE CH18+197

BRIDGE CH19+100

EKPERI-ANEGBETTE ROAD

Page 9: Setraco EDO State project presentation

Progress layout of jattu-apana road projectActivity

ChainageColorID

Site Clearing0+000 – 11+772

Sub- Grade0+000 – 8+110

8+256-11+772

Setraco Nig.Ltd.

JATTUCH0+000

APANACH11+772

AFOWA

IYORA

BRIDGE CH 8+232

IMIEKEBU

JATTU-APANA ROAD

AYOGWIRI

AYO

GWIR

I-IM

IEKI

BU R

OAD

Activity Chainage Color ID

Site Clearing 0+000-11+772

Page 10: Setraco EDO State project presentation

Progress layout of jattu-apana road projectActivity

ChainageColorID

Site Clearing0+000 – 11+772

Sub- Grade0+000 – 8+110

8+256-11+772

Setraco Nig.Ltd.

JATTUCH0+000

APANACH11+772

AFOWA

IYORA

BRIDGE CH 8+232

IMIEKEBU

JATTU-APANA ROAD

AYOGWIRI

AYO

GWIR

I-IM

IEKI

BU R

OAD

Activity Chainage Color ID

Site Clearing 0+000-11+772

Sub- Grade0+000-8+110

8+256 -11+772&

Page 11: Setraco EDO State project presentation

Progress layout of jattu-apana road projectActivity

ChainageColorID

Site Clearing0+000 – 11+772

Sub- Grade0+000 – 8+110

8+256-11+772

Setraco Nig.Ltd.

JATTUCH0+000

APANACH11+772

AFOWA

IYORA

BRIDGE CH 8+232

IMIEKEBU

JATTU-APANA ROAD

AYOGWIRI

AYO

GWIR

I-IM

IEKI

BU R

OAD

Activity Chainage Color ID

Site Clearing 0+000-11+772

Sub- Grade0+000-8+110

8+256 - 11+772&

Sub- Base 0+000-8+110&

8+256 -11+772

Page 12: Setraco EDO State project presentation

Progress layout of jattu-apana road projectActivity

ChainageColorID

Site Clearing0+000 – 11+772

Sub- Grade0+000 – 8+110

8+256-11+772

Setraco Nig.Ltd.

JATTUCH0+000

APANACH11+772

AFOWA

IYORA

BRIDGE CH 8+232

IMIEKEBU

JATTU-APANA ROAD

AYOGWIRI

AYO

GWIR

I-IM

IEKI

BU R

OAD

Activity Chainage Color ID

Site Clearing 0+000-11+772

Sub- Grade0+000-8+110

8+256 - 11+772&

Sub- Base 0+000-8+110&

8+256 - 11+772

Base 0+000-8+110&

8+256 - 11+772

Page 13: Setraco EDO State project presentation

Progress layout of jattu-apana road projectActivity

ChainageColorID

Site Clearing0+000 – 11+772

Sub- Grade0+000 – 8+110

8+256-11+772

Setraco Nig.Ltd.

JATTUCH0+000

APANACH11+772

AFOWA

IYORA

BRIDGE CH 8+232

IMIEKEBU

JATTU-APANA ROAD

AYOGWIRI

AYO

GWIR

I-IM

IEKI

BU R

OAD

Activity Chainage Color ID

Site Clearing 0+000-11+772

Sub- Grade0+000-8+110

8+256 -11+772&

Sub- Base 0+000-8+110&

8+256 - 11+772

Base 0+000-8+110&

8+256 - 11+772

Wearing Course

0+000-8+100

&8+375 -11+772

Page 14: Setraco EDO State project presentation

Progress layout of jattu-apana road projectActivity

ChainageColorID

Site Clearing0+000 – 11+772

Sub- Grade0+000 – 8+110

8+256-11+772

Setraco Nig.Ltd.

JATTUCH0+000

APANACH11+772

AFOWA

IYORA

BRIDGE CH 8+232

IMIEKEBU

JATTU-APANA ROAD

AYOGWIRI

AYO

GWIR

I-IM

IEKI

BU R

OAD

Activity Chainage Color ID

Site Clearing 0+000-11+772

Sub- Grade0+000-8+110

8+256 -11+772&

Sub- Base 0+000-8+110&

8+256 - 11+772

Base 0+000-8+110&

8+256 -11+772

Wearing Course

0+000-8+100&

8+375= 11+772

Surface Dressing

0+000-8+100&

8+375 - 11+772

Page 15: Setraco EDO State project presentation

Progress of Drain jattu-apana road projectActivity

ChainageColorID

Site Clearing0+000 – 11+772

Sub- Grade0+000 – 8+110

8+256-11+772

Setraco Nig.Ltd.

JATTUCH0+000

APANACH11+772

AFOWA

IYORA

BRIDGE CH 8+232

IMIEKEBU

JATTU-APANA ROAD

AYOGWIRI

AYO

GWIR

I-IM

IEKI

BU R

OAD

Description Chainage Color ID

U- drain ( 75x75x10)cm

0+070-0+267,0+269-1+064, 6+797-7+703, 11+138-11+770

Side

LHS

U- drain ( 75x75x10)cm

RHS 5+675-6+198, 6+797-7+702, 11+138-11+378

U- drain ( 75x90x10)cm

LHS & RHS 7+700-8+010

V- drain ( 140x60x50x10)cm LHS & RHS 8+010- 8+105,

8+382-8+600, 9+945-10+370

Page 16: Setraco EDO State project presentation

Progress of Culvert jattu-apana road projectActivity

ChainageColorID

Site Clearing0+000 – 11+772

Sub- Grade0+000 – 8+110

8+256-11+772

Setraco Nig.Ltd.

JATTUCH0+000

APANACH11+772

AFOWA

IYORA

BRIDGE CH 8+232

IMIEKEBU

JATTU-APANA ROAD

AYOGWIRI

AYO

GWIR

I-IM

IEKI

BU R

OAD

Description Chainage Color ID

Ring Culvert

Size

1X.9 m

4+592, 9+900, 10+700

10+150, 3+315, 2+425

Ring Culvert 2X.9 m 7+700

Ring Culvert

1X1.2 mRing Culvert

2X1.2 m

6+175, 9+000, 11+150, 5+475, 3+814, 1+343, 1+200, 0+265

Page 17: Setraco EDO State project presentation

Progress layout of ayogwiri & okpekpe projectSetraco Nig.Ltd.

JATTU

AYOGWIRICH0+000

IMIEKIEBUCH0+18+786

IGODOR CH-0+000

SPOURCH-7+563

APANA

IMIEKBA

OKPEKPE-SPOUR

ROAD

AYOGWIRI-IMIEKIBU

ROAD

OKPEKPE

BRIDGE CH-5+325

BRIDGE

CH-11+825

Activity Chainage Color ID

Site Clearing

Ayogwiri-: 0+000-18+725&

Okpekpe:- 0+000-4+350

Page 18: Setraco EDO State project presentation

Progress layout of ayogwiri & okpekpe projectSetraco Nig.Ltd.

JATTU

AYOGWIRICH0+000

IMIEKIEBUCH0+18+786

IGODOR CH-0+000

SPOURCH-7+563

APANA

IMIEKBA

OKPEKPE-SPOUR

ROAD

AYOGWIRI-IMIEKIBU

ROAD

OKPEKPE

BRIDGE CH-5+325

BRIDGE

CH-11+825

Activity Chainage Color ID

Site Clearing

Ayogwiri-: 0+000-18+725&

Okpekpe:- 0+000-4+350

Sub-Grade0+000-11+750

& 12+175-12+975

Page 19: Setraco EDO State project presentation

Progress layout of ayogwiri & okpekpe projectSetraco Nig.Ltd.

JATTU

AYOGWIRICH0+000

IMIEKIEBUCH0+18+786

IGODOR CH-0+000

SPOURCH-7+563

APANA

IMIEKBA

OKPEKPE-SPOUR

ROAD

AYOGWIRI-IMIEKIBU

ROAD

OKPEKPE

BRIDGE CH-5+325

BRIDGE

CH-11+825

Activity Chainage Color ID

Site Clearing

Ayogwiri-: 0+000-18+725&

Okpekpe:- 0+000-4+350

Sub-Grade0+000-11+750

& 12+175-12+975

Sub-Base 0+000-10+500

Page 20: Setraco EDO State project presentation

Progress layout of ayogwiri & okpekpe projectSetraco Nig.Ltd.

JATTU

AYOGWIRICH0+000

IMIEKIEBUCH0+18+786

IGODOR CH-0+000

SPOURCH-7+563

APANA

IMIEKBA

OKPEKPE-SPOUR

ROAD

AYOGWIRI-IMIEKIBU

ROAD

OKPEKPE

BRIDGE CH-5+325

BRIDGE

CH-11+825

Activity Chainage Color ID

Site Clearing

Ayogwiri-: 0+000-18+725&

Okpekpe:- 0+000-4+350

Sub-Grade0+000-11+750

& 12+175-12+975

Sub-Base 0+000-10+500

Base 0+000-9+700

Page 21: Setraco EDO State project presentation

Progress layout of ayogwiri & okpekpe projectSetraco Nig.Ltd.

JATTU

AYOGWIRICH0+000

IMIEKIEBUCH0+18+786

IGODOR CH-0+000

SPOURCH-7+563

APANA

IMIEKBA

OKPEKPE-SPOUR

ROAD

AYOGWIRI-IMIEKIBU

ROAD

OKPEKPE

BRIDGE CH-5+325

BRIDGE

CH-11+825

Activity Chainage Color ID

Site Clearing

Ayogwiri-: 0+000-18+725&

Okpekpe:- 0+000-4+350

Sub-Grade0+000-11+750

& 12+175-12+975

Sub-Base 0+000-10+500

Base 0+000-9+700

Wearing Course 0+000-9+680

Page 22: Setraco EDO State project presentation

Progress layout of ayogwiri & okpekpe projectSetraco Nig.Ltd.

JATTU

AYOGWIRICH0+000

IMIEKIEBUCH0+18+786

IGODOR CH-0+000

SPOURCH-7+563

APANA

IMIEKBA

OKPEKPE-SPOUR

ROAD

AYOGWIRI-IMIEKIBU

ROAD

OKPEKPE

BRIDGE CH-5+325

BRIDGE

CH-11+825

Activity Chainage Color ID

Site Clearing

Ayogwiri-: 0+000-18+725&

Okpekpe:- 0+000-4+350

Sub-Grade0+000-11+750

& 12+175-12+975

Sub-Base 0+000-10+500

Base 0+000-9+700

Wearing Course 0+000-9+680

Surface Dressing

0+000-9+680

Page 23: Setraco EDO State project presentation

Progress of Drain ayogwiri & okpekpe projectSetraco Nig.Ltd.

JATTU

AYOGWIRICH0+000

IMIEKIEBUCH0+18+786

IGODOR CH-0+000

SPOURCH-7+563

APANA

IMIEKBA

OKPEKPE-SPOUR

ROADAY

OGW

IRI-I

MIE

KIBU

RO

AD OKPEKPE

BRIDGE CH-5+325

BRIDGE

CH-11+825

Description Side Chainage Color ID

U- drain ( 75x75x10)cm

LHS 0+025-0+118, 2+843-3+174, 3+203-3+323, 3+343- 3+653

U- drain ( 75x75x10)cm

RHS 0+025-0+114, 2+795-3+321, 3+345-3+681

V- drain ( 140x60x50x10)cm LHS 1+188- 1+448, 1+758-

2+089, 4+547- 4+643, 5+488- 5+735

V- drain ( 140x60x50x10)cm

RHS 1+260- 1+465, 1+758- 2+031, 2+580- 2+683, 4+548- 4+641, 5+488- 5+749, 4+510- 4+539, 9+095- 9+185.

U- drain ( 75x90x10)cm

1+448- 1+752LHS

Page 24: Setraco EDO State project presentation

Progress of Culvert ayogwiri & okpekpe projectSetraco Nig.Ltd.

JATTU

AYOGWIRICH0+000

IMIEKIEBUCH0+18+786

IGODOR CH-0+000

SPOURCH-7+563

APANA

IMIEKBA

OKPEKPE-SPOUR

ROADAY

OGW

IRI-I

MIE

KIBU

RO

AD OKPEKPE

BRIDGE CH-5+325

BRIDGE

CH-11+825

Description Size Chainage Color ID

Ring Culvert 1x.9 m 0+975, 1+760, 4+950, 7+640, 8+100, 3+185

Ring Culvert 2x.9 m 3+075

Ring Culvert 1x1.2 m 1+200, 5+325

Ring Culvert 2x1.2 m 2+175, 8+380, 3+328

Box Culvert 1x2x2 m 4+548, 5+475

Page 25: Setraco EDO State project presentation

Progress layout of ekperi-anegbette road project

Setraco Nig.Ltd.

EKPERI CH 0+000

ANEGBETTE CH-30+100

BRIDGE CH18+167

BRIDGE CH19+100

EKPERI-ANEGBETTE ROAD

Activity

Chainage

Color ID

Site Clearing

0+750-19+159

Page 26: Setraco EDO State project presentation

Progress layout of ekperi-anegbette road project

Setraco Nig.Ltd.

EKPERI CH 0+000

ANEGBETTE CH-30+100

BRIDGE CH18+167

BRIDGE CH19+100

EKPERI-ANEGBETTE ROAD

Activity

Chainage

Color ID

Site Clearing

0+750-19+159

Sub-grade

0+800-18+175 &

18+220- 19+025

Page 27: Setraco EDO State project presentation

Progress layout of ekperi-anegbette road project

Setraco Nig.Ltd.

EKPERI CH 0+000

ANEGBETTE CH-30+100

BRIDGE CH18+167

BRIDGE CH19+100

EKPERI-ANEGBETTE ROAD

Activity

Chainage

Color ID

Site Clearing

0+750-19+159

Sub-grade

0+800-18+175 &

18+220- 19+025

Sub-Base

0+800-7+950

Page 28: Setraco EDO State project presentation

Progress layout of ekperi-anegbette road project

Setraco Nig.Ltd.

EKPERI CH 0+000

ANEGBETTE CH-30+100

BRIDGE CH18+167

BRIDGE CH19+100

EKPERI-ANEGBETTE ROAD

Activity

Chainage

Color ID

Site Clearing

0+750-19+159

Sub-grade

0+800-18+175 &

18+220- 19+025

Sub-Base

0+800-7+950

Base

0+800-5+925

Page 29: Setraco EDO State project presentation

Progress layout of ekperi-anegbette road project

Setraco Nig.Ltd.

EKPERI CH 0+000

ANEGBETTE CH-30+100

BRIDGE CH18+167

BRIDGE CH19+100

EKPERI-ANEGBETTE ROAD

Activity

Chainage

Color ID

Site Clearing

0+750-19+159

Sub-grade

0+800-18+175 &

18+220- 19+025

Sub-Base

0+800-7+950

Base

0+800-5+925

Wearing Course

0+800-5+403

Page 30: Setraco EDO State project presentation

Progress layout of ekperi-anegbette road project

Setraco Nig.Ltd.

EKPERI CH 0+000

ANEGBETTE CH-30+100

BRIDGE CH18+167

BRIDGE CH19+100

EKPERI-ANEGBETTE ROAD

Activity

Chainage

Color ID

Site Clearing

0+750-19+159

Sub-grade

0+800-18+175 &

18+220- 19+025

Sub-Base

0+800-7+950

Base

0+800-5+925

Wearing Course

0+800-5+403

Surface Dressing

0+800-5+403

Page 31: Setraco EDO State project presentation

Progress of Culvert ekperi-anegbette road project

Setraco Nig.Ltd.

EKPERI CH 0+000

ANEGBETTE CH-30+100

BRIDGE CH18+167

BRIDGE CH19+100

EKPERI-ANEGBETTE ROAD

Description

Chainage

Color ID

Ring Culvert

8+063, 14+840

Size 1X.9m

Ring Culvert

1X.9/2m

12+910

Ring Culvert

1X1.2m

6+513, 9+710, 13+425, 15+400, 15+825, 16+175

Ring Culvert

1/2X1.2m

2+475

Ring Culvert

2X1.2m

11+500, 14+175

Box Culvert

2X2X2m

7+400

Box Culvert

2X2.4X2.4m

3+500, 18+500, 18+675, 18+850

Page 32: Setraco EDO State project presentation

Jattu Bridge @ch- 8+232 Progress detailsSetraco Nig.Ltd.

Date as on 1st sep’11

Page 33: Setraco EDO State project presentation

Ekperi Bridge @ch-18+197 Progress detailsSetraco Nig.Ltd.

Date as on 1st sep’11

Page 34: Setraco EDO State project presentation

Ekperi Bridge @ch-19+099 Progress detailsSetraco Nig.Ltd.

Date as on 1st sep’11

Page 35: Setraco EDO State project presentation

SummAry of % of Progress Setraco Nig.Ltd.

0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% 90.00%

79.89%

31.07%

34.14%

Ekperi Ayogwiri Jattu

% OF COMPLETION

PROJECT

Page 36: Setraco EDO State project presentation

Detailed % of ProgressSetraco Nig.Ltd.

Side Drain

Site Clearing

Sub-Grade

Sub-Base

Base

Surface Dressing

Wearing Coarse

48%

100%

100%

100%

98%

96%

98%

41.25%

71.10%

49.40%

41.17%

36.45%

35.70%

36.81%

0.00%

71.73%

63.30%

24.49%

23.32%

15.34%

15.10%

Ekperi Ayogwiri Jattu

% OF COMPLETION

ACTIVITY

Page 37: Setraco EDO State project presentation

Forcasted vs. executed cumulative turnoverSetraco Nig.Ltd.

Feb'10

March'10

April"10

May'10

June'10

July'10

Aug'10Se

p'10Oct'

10

Nov'10Dec'1

0Jan

'11Fe

b'11

March'11

April"11

May'11

June'11

July'11

Aug'11

0500000000

10000000001500000000200000000025000000003000000000

JATTU- AKPANA ROAD PROJECTCum. Forcasted Turnover Cum. Executed Turnover

Month of Progress

Turnover

Million

Page 38: Setraco EDO State project presentation

Forcasted vs. executed cumulative turnoverSetraco Nig.Ltd.

Feb'10

March'10

April"10

May'10

June'10

July'10

Aug'10Se

p'10Oct'

10

Nov'10Dec'1

0Jan

'11Fe

b'11

March'11

April"11

May'11

June'11

July'11

Aug'11

0

500000000

1000000000

1500000000

2000000000

2500000000

AYOGWIRI-OKPEKPE- IMIEKIBU ROAD PROJECTCum. Forcasted Turnover Cum. Executed Turnover

Month of Progress

Turnover

Million

Page 39: Setraco EDO State project presentation

Forcasted vs. executed cumulative turnoverSetraco Nig.Ltd.

Feb'10

March'10

April"10

May'10

June'10

July'10

Aug'10Se

p'10Oct'

10

Nov'10Dec'1

0Jan

'11Fe

b'11

March'11

April"11

May'11

June'11

July'11

Aug'11

0500000000

100000000015000000002000000000250000000030000000003500000000

EKPERI-ANEGBETTE ROAD PROJECTCum. Forcasted Turnover Cum. Executed Turnover

Month of Progress

Turnover

Million

Page 40: Setraco EDO State project presentation

Executed Turnover vs.Certified AmountSetraco Nig.Ltd.

Jattu Ayogwiri Ekperi0.00

500.00

1000.00

1500.00

2000.00

2500.00

3000.00

3500.00

4000.00

4500.00

Million

Jattu Ayogwiri Ekperi

Adv. Payment in

MN647.076 856.45 1825.65

Previously Certified

in MN

2386.19 2321.54 3856.38

Retention Money

in MN

144.28 212.32 330.25

Contract Sum in

MN3029.83 6793.74 7927.84

Page 41: Setraco EDO State project presentation

Progress photograph Of

jattu-akpana road project

Setraco Nig.Ltd.

Page 42: Setraco EDO State project presentation

Setraco Nig.Ltd.

Cut to fill @ 9+950- 10+075

Site clearance and earth work

Borrow to fill @ Ch- 10+375-11+050

Page 43: Setraco EDO State project presentation

Setraco Nig.Ltd.

Site clearance and earth work

Remove Unsuitable @ Ch- 7+900-8+025 Cut to spoil @ 8+000 – 8+225

Page 44: Setraco EDO State project presentation

Setraco Nig.Ltd.

Pavement and surfacing work

Stone Base laying @ 9+187 – 11+200Sub-Base Base laid @6+450 – 8+150

Page 45: Setraco EDO State project presentation

Setraco Nig.Ltd.

Pavement and surfacing work

Laying Mc1 @ Ch- 6+910-8+110 laying Mc1 at shoulder @ 8+375 – 11+200

Page 46: Setraco EDO State project presentation

Setraco Nig.Ltd.

Pavement and surfacing work

Laying S-125 at shoulder @ 8+375 – 11+200 Surface dressing @ 8+375 – 11+200

Page 47: Setraco EDO State project presentation

Setraco Nig.Ltd.

Pavement and surfacing work

Finish Road SurfaceLaying of Asphalt @ 8+375 – 11+200

Page 48: Setraco EDO State project presentation

Setraco Nig.Ltd.

Concrete work

U- drain ( 75x75x10) cm and Precast slab Precast Kerb wall fixing

Page 49: Setraco EDO State project presentation

Setraco Nig.Ltd.

Concrete work

Pile cap & abutment with wing wall casting @ Bride 8+232

Cyclopean Concrete below pile cap @ Bridge 8+232

Page 50: Setraco EDO State project presentation

Setraco Nig.Ltd.

Concrete work

Deck slab Concreting @ Bridge 8+232

Head wall with wing wall casting @ Bride 8+232

Page 51: Setraco EDO State project presentation

Progress photograph Of

Ayogwiri-Imiekibu road project

Setraco Nig.Ltd.

Page 52: Setraco EDO State project presentation

Setraco Nig.Ltd.

Massive Earth cutting @ Ch- 11+300- 12+577

Page 53: Setraco EDO State project presentation

Setraco Nig.Ltd.

Casting of Ring culvert @ Ch- 1+200

Page 54: Setraco EDO State project presentation

Setraco Nig.Ltd.

Compaction of subgrade Ch-0+350 -1+650 Remove unsuitable.

Page 55: Setraco EDO State project presentation

Setraco Nig.Ltd.

Sub-base Ch-0+000 -0+825 Laying of asphalt @ ch- 0+000- 1+370.

Page 56: Setraco EDO State project presentation

Setraco Nig.Ltd.

U-drain (75x90x10) @ ch- 1+580- 1+760 Stone pitching @ch-3+075

Page 57: Setraco EDO State project presentation

Setraco Nig.Ltd.

Precast kerb fixing @ ch- 0+500- 0+783 Culvert 2X2 m @ch-4+547.7

Page 58: Setraco EDO State project presentation

Setraco Nig.Ltd.

Casting of V-drain (140x60x50x10) cm Stone Base laying @ ch-7+000- 8+400

Page 59: Setraco EDO State project presentation

Progress photograph Of

Ekperi-Anegbette road project

Setraco Nig.Ltd.

Page 60: Setraco EDO State project presentation

Setraco Nig.Ltd.

Subgrade preparationSite clearing @ ch- 0+750 – 8+475

Page 61: Setraco EDO State project presentation

Setraco Nig.Ltd.

Lateritic Base Laying of MC1 & surface dressing.

Page 62: Setraco EDO State project presentation

Setraco Nig.Ltd.

Casting of Precast Beam Laying of Asphalt.

Page 63: Setraco EDO State project presentation

Setraco Nig.Ltd.

Pile cap in progress.Drilled Piling @Ch 18+197 Bridge

Page 64: Setraco EDO State project presentation

Setraco Nig.Ltd.

Construction of Cross beam Abutment and retaining wall at Bridge

Page 65: Setraco EDO State project presentation

Setraco Nig.Ltd.

Launching of precast Beam at Bridge@ Ch-18+197 & 19+099

Page 66: Setraco EDO State project presentation

Setraco Nig.Ltd.

Fixing of precast slab and casting of Deck slab at Bridge@ Ch-18+197 & 19+099

Page 67: Setraco EDO State project presentation

Setraco Nig.Ltd.

Box and Ring culvert

Page 68: Setraco EDO State project presentation

Setraco Nig.Ltd.

Dredged Sand filling from Ch-18+220 – 19+025

Page 69: Setraco EDO State project presentation

Progress photograph Other than

project

Setraco Nig.Ltd.

Page 70: Setraco EDO State project presentation

Setraco Nig.Ltd.

Bush-Bar Under construction at Life camp Emulsion plant under construction

Page 71: Setraco EDO State project presentation

Thank You

Setraco Nig.Ltd.