73
8/14/2019 Session 6, 7 MRP http://slidepdf.com/reader/full/session-6-7-mrp 1/73 1

Session 6, 7 MRP

Embed Size (px)

Citation preview

Page 1: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 1/73

1

Page 2: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 2/73

2

Page 3: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 3/73

Managing production system includes

materials management, sourcing, follow up,

controlling productivityComplexities of producing numerous

different products can cause

confusion, inefficiencies & inferior

customer service

MATERIAL REQUIREMENT PLANNING

3

Page 4: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 4/73

To control such an environment, timely

and accurate information is required

MRP system can provide this vital info

MATERIAL REQUIREMENT PLANNING

4

Page 5: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 5/73

Managers using reactive systems

ask, “What should I do now?”

Managers using planning

systems ask, “What will I need in

the future? How much and

when ?”

MATERIAL REQUIREMENT PLANNING

5

Page 6: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 6/73

simple to manage

high inventory cost OR ordering cost

unreliable delivery performance

Reactive systems

6

Page 7: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 7/73

complex to manage

reduced inventory cost (it carries only those

items & components that are needed – no

more/no less)

Reduces order processing delays => reduced LT=> better deliveries => better customer service

accurate information required

Planning system

7

Page 8: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 8/73

requires a lot of discipline

Commitment by scheduler, supervisor, managers,

etc.

Planning system

8

Page 9: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 9/73

It is the degree to which demand of an item is

dependent on demand for another item

E.g. demand for tea/coffee will determine the

quantity of sugar/milk, etc. required

MRP obviates the need of large safety stocks for

dependent demand items

Demand Dependency

9

Page 10: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 10/73

It is a software based production, planning and

inventory control system used to manage the

manufacturing processIt generates time-phased materials requirements

for production operations (provides due dates for

components)

MRP : a scheduling & ordering system

10

Page 11: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 11/73

Operations Planning & Scheduling System

Aggregate outputplanning

Master production

scheduling

Material requirementsplanning

Loading

Sequencing

DetailedScheduling

Expediting

Aggregate capacityplanning

Rough-cut capacity

planning

Detailed capacityplanning

Short-termcapacity control

Operations

Output planning Capacity planning

Shopfloor control

11

Page 12: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 12/73

MRP enables to estimate dept.-wise

capacity requirement

Operations Planning & Scheduling System

12

Page 13: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 13/73

Inventory reduction – how much of what and

when? No extra inventory

Reduction in production & delivery LT – prioritiesproduction activities. Ensures smooth production

due to efficient inventory management

MRP : Objective & Methods

13

Page 14: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 14/73

Realistic commitments – WYSIWYG – better

customer satisfaction. New orders are added to the

system and revised total load plan is generated and

given to production manager.

Increased efficiency – MRP ensures close

coordination among various departments as

products progress through them. Fewer unplanned

interruptions, better production efficiency.

MRP : Objective & Methods

14

Page 15: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 15/73

Main sources of information (input) are:

1. Master Production Schedule

2. Inventory Status File3. BOM

4. Purchase orders outstanding5. Lead times

MRP : System Components

15

Page 16: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 16/73

3 kinds of information

1. Order release requirements (orders to

be released now)

2. Order re-scheduling (expedite, de-

expedite, cancel open orders)

3. Planned orders (future)

MRP provides……

16

Page 17: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 17/73

MRP system

Masterproductionschedule (MPS)

BOM fileInventorystatus file

MRPprocessing

logic

Plannedorders

(future)

Order releaserequirements (ordersto be released now)

Orders rescheduling(expedite, de-expedite,

cancel open orders)

17

Page 18: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 18/73

Initially developed from (a) existing orders OR

(b) demand forecast

MPS provides input to MRP system

MPS includes replacement (service) components

for customers

MPS ultimately governs MRP on sourcing plan &

producing sub-components, to meet deliveries

MPS (master production schedule)

18

Page 19: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 19/73

It contains the following:

identification number,

quantity on hand,

safety stock level,

quantity disbursed and

sourcing LT for every item

Inventory Status File

19

Page 20: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 20/73

Identifies manufacturing process (sequence of

build up)

Identifies quantities of finished unit & thedepartments performing the build up sequence

*Primary info to MRP from BOM is the product

structure

BOM

20

Page 21: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 21/73

Product structures for 2 assembled products

21

Page 22: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 22/73

Product structures for 2 assembled products

A&D are upper level end items Components are lower-level items Each item is given unique identification number MRP schedules & time-phases the orders for lower

level component items 22

Page 23: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 23/73

MRP processing logic

23

Page 24: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 24/73

It accepts the Master Production Schedule

Determines components schedules

Calculates for each item in each product for each

time period (normally 1 week) in the planning

horizon

How much is required Vs. how much is already

available in-house

MRP processing logic

24

Page 25: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 25/73

Data processing determines the overall

requirements to meet deliveries

MRP processing logic

25

Page 26: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 26/73

Bicycle components

26

Page 27: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 27/73

The report clearly identifies the sourcing actions required for on-scheduleproduction

Can notify the suppliers in advanceWeekly updating – expedite , de-expedite , cancel

**Information system is valuable when thousands of sub-components mustbe coordinated among numerous suppliers & work centers

Management info from MRP

MRP report for one item

27

Page 28: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 28/73

Page 29: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 29/73

1. Allocated quantity : in-house quantity but alreadyallocated to some other order

2. Gross requirements : ‘overall quantity needed’ to

meet planned output levels. *Planned output for end

items come from MIS . *Planned output for

components come from MRP

3. Scheduled receipts : quantity that will be received at

the start of time period against previously placed

orders

Terminology of MRP

29

Page 30: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 30/73

4. Available quantity : quantity expected to be availableat the end of a time period for production in

subsequent periods

Terminology of MRP

• Available qty = qty available from the previous period +

schedule receipts + planned order receipts - grossrequirement

30

Page 31: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 31/73

5. Net requirements : net quantity to be acquired to

meet production requirements for the period

6. Planned order receipts – quantity that is planned to

be ordered for receiving at the start of the period.

The order has not yet been placed

Terminology of MRP

net requirements = gross requirement – scheduled receipts –

qty. available from previous period

31

Page 32: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 32/73

7. Planned order release : it’s a release that shows

the order plan of items vis-à-vis time period.

What, how much & when. When this order is

released, it becomes a ‘scheduled receipt’

Terminology of MRP

32

Page 33: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 33/73

MRP - example

33

Page 34: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 34/73

Chair – manufacturing sequence

34

Page 35: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 35/73

Chair – manufacturing sequence

35

Page 36: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 36/73

MRP - example

36

Page 37: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 37/73

Determine & plan for end products

Determine and plan for lower level items

Info Processing System (Reverse T&A)

37

Page 38: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 38/73

Q. When must the order be placed so that the

item arrives when it is needed?

A. The processing system responds by ‘offsetting ’

the length of LT as indicated in the inventory

status file for that item

Lead-time off-setting

38

Page 39: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 39/73

Provides the information regarding relationshipbetween product and its components

It’s easy to see how many of which component isrequired at which level

Indented BOM

indented BOM for Model ‘H’ chair

39

Page 40: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 40/73

To produce a product, often multiple units of a

lower level item is required.

E.g. 1 unit of H requires 4 units of E.450 units of H requires 450 x 4 = 1800 units of E

This process of multiplication is called Product

Explosion or BOM explosion

Product Explosion

40

Page 41: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 41/73

A single item may be used at several points of

production. E.g. nut-bolts

MRP by convention assigns the item to thelowest level in which it occurs in the product

structure

Low Level Coding

41

Page 42: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 42/73

In order to maintain the schedule, planned order

releases must be acted upon in the relevant weeks

The cells which represent the weeks are theACTION BUCKETS.

*The ‘action’ is to release the order.

Using MRP outputs for material decisions

42

Page 43: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 43/73

MRP is not staticChanges with (i) new orders (ii) current production

floor conditions (iii) anticipated changes for the

future

MRP must be updated with current information

BUT should also provide stability for productionoperations

Keeping MRP ‘current’ in a changing environment

43

Page 44: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 44/73

(i) Pegging

(ii) Cycle Counting

(iii) Updating

(iv) Time Fences

Four aspects of MRP

44

Page 45: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 45/73

“tracing upward in the BOM from the components tothe parent item”

In real life material plans get disrupted every now

and then

Pegging identifies which components get affected

by such disruptions

(i) Pegging

45

Page 46: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 46/73

Pegging shows the level-by-level linkages among

components and their

time-phased status in the

MRP records

(i) Pegging

pegging the MRP records 46

Page 47: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 47/73

(ii) Cycle Counting

Components are counted, deducting defective units at

each stage of production and in storage area on a regular

basis

System data should be same as actual physical inventory

MRP records are updated, weekly or daily

Updated records highlight excesses or shortages andthereby indicated how the production schedules need to

be adjusted 47

Page 48: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 48/73

(iii) Updating

Updating is required when new jobs arrive OR

when technology changes the production design

Two updating approaches are used

(a) regenerative

(b) net change

48

Page 49: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 49/73

(iii) Updating

Regenerative completely reprocesses the

entire set of information & recreates the complete

MRP from start to end

Net change reprocesses only those portions

that are affected by informational changes

49

Page 50: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 50/73

allows a part of the master schedule to be

designated as ‘not to be rescheduled’

Dynamics of MRP environment can create

potential confusion => system nervousness

(iv) Time Fences

50

Page 51: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 51/73

Stability is gained by using ‘time fence’

Time fence = shortest LT from raw material to

finished productWithin the time fence, add longest LT at each

level of product structure + longest LT for sourcing

*frozen part of MPS is called firm planned orders

(iv) Time Fences

51

Page 52: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 52/73

(iv) Time Fences

52

Page 53: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 53/73

(iv) Time Fences

The longest LT at levels 0, 1 & 2 are 1, 2 and 4 = 7 weeks + sourcing LT 53

Page 54: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 54/73

MRP system generates planned order releases

which triggers P.O. for vendors

Set up costs(cost of ordering) + holding costa. LOT-FOR-LOT ORDERING (dynamic)

b. E.O.Q. TECHNIQUE (static)

LOT sizing

54

LOT SIZING L4L TECHNIQUE

Page 55: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 55/73

LOT SIZING – L4L TECHNIQUE

Lot sizing technique that generates exactly what is

needed

No safety stock or anticipation of further orders

Works most efficiently when

– Frequent orders are economical (low set-up or

ordering costs)

– JIT inventory techniques has been implemented

55

LOT SIZING L4L TECHNIQUE

Page 56: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 56/73

Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8

50 60 70 60 95 75 60 55

Consider the given lot sizing problem, the netrequirement are given for 8 weeks

Cost per item Rs 10

Order/Setup cost Rs 47

Inventory carrying cost/week 0.5 %

LOT SIZING – L4L TECHNIQUE

56

LOT SIZING L4L TECHNIQUE

Page 57: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 57/73

Week Net Requirement ProductionQuantity

EndingQuantity

Holding Cost Set up Cost Total Cost

1 50 50 0 Rs 0.00 Rs 47 Rs 47

2 60 60 0 0.00 47 94

3 70 70 0 0.00 47 141

4 60 60 0 0.00 47 188

5 95 95 0 0.00 47 235

6 75 75 0 0.00 47 282

7 60 60 0 0.00 47 329

8 55 55 0 0.00 47 376

Lot-for-Lot Run Size for an MRP schedule

LOT SIZING – L4L TECHNIQUE

57

LOT SIZING E O Q TECHNIQUE

Page 58: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 58/73

Annual demand = D = 525 x 52 = 3412.5 units8

Annual holding cost =H= 0.5%xRs 10x52 weeks=2.60units

Setup cost = S = Rs 47

EOQ = √2DS = 351 units√ H

LOT SIZING – E.O.Q. TECHNIQUE

58

LOT SIZING E O Q TECHNIQUE

Page 59: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 59/73

Week Net Requirement ProductionQuantity

EndingInventory

Holding Cost Set up Cost Total Cost

1 50 351 301 Rs 15.05 Rs 47 Rs 62.05

2 60 0 241 12.05 0 74.10

3 70 0 171 8.55 0 82.65

4 60 0 111 5.55 0 88.20

5 95 0 16 0.80 0 89.00

6 75 351 292 14.60 47 150.60

7 60 0 232 11.60 0 162.20

8 55 0 177 8.85 0 171.05

EOQ Run Size for an MRP schedule

∑=525

LOT SIZING – E.O.Q. TECHNIQUE

59

D il d C i Pl i (DCP)

Page 60: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 60/73

a.k.a. capacity requirements planning

Each time the MRP system is updated, it is

imperative to check whether sufficient capacity isavailable

DCP addresses this question

Detailed Capacity Planning (DCP)

60

D il d C i Pl i

Page 61: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 61/73

*E.g. detailed capacity analysis for component A(the front legs)Step 1: route sheet is developed for component A

Detailed Capacity Planning

route sheet for component A

61

D t il d C it Pl i

Page 62: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 62/73

Step 2 : construct the operation set-back chart

Detailed Capacity Planning

partial operation set-back chart for chair model H

62

Li it ti f MRP

Page 63: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 63/73

A computer is necessary Product structure must be assembly oriented

BOM + inventory status information must be

recorded & computerised

Valid master schedule must be prepared

Data integrity Training people else ad hoc methods resurfaces

Limitations of MRP

63

Ad t g f MRP

Page 64: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 64/73

Dynamic nature Reacts well to changing activities (real time

adjustments for thousands of components)

Better PPC

Better inventory management

Shorter delivery LT – sourcing Better deliveries

Advantages of MRP

64

M k

Page 65: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 65/73

Least accurate information is available on

capacity, market forecasts, production control

Most accurate information on BOM, MPS,

inventory records

Managers speak……

65

Man fact ring Reso rce Planning (MRPII)

Page 66: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 66/73

‘closed loop’ MRPMRP systems was developed on a segregated

basis

MRPII connects many of the information

subsystems to the MRP system

Synchronises all aspects of the business ( sales ,purchasing , manufacturing , finance , engineering ) by

adopting a focal production plan

Manufacturing Resource Planning (MRPII)

66

MRPII

Page 67: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 67/73

MRPII involves developing a production plan fromthe business plan to specify monthly projections for

each product line over next 1 to 5 years.

Developed by consensus of all executives

Production dept. produce (PS)

Sales dept. sell (PSFPD)Finance ??

MRPII

67

Rough Cut Capacity Planning (RCCP)

Page 68: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 68/73

Used to evaluate capacity with availability

A repeating occurrence of an abundance amount

of inventory being created or pulled through a

supply chain is a big problem

RCCP prevents over production and determines

the appropriate amount of capacity that should be

used in the system

Rough Cut Capacity Planning (RCCP)

68

MRPII: an integrated system for planning & control

Page 69: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 69/73

BUSINESS PLAN

PRODUCTIONPLAN

M.P.S.

ROUGH CUTCAPACITY

PLAN

M.R.P.

DETAILED

CAPACITYPLAN

SHOP FLOOR CONTROL;PURCHASES CONTROL

MANUFACTURING(materials, capacity,

production schedules

Purchasing(vendor orders)

Engineering(process &

product design)

Marketing (salesorder entry, delivery

projections)

Finance (capitalrequirements for

capacity, working capitalrequirements)

Accounting (a/cpayable; a/creceivable) 69

Purchasing

Page 70: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 70/73

1. Purchasing activities related to procuringmaterials and supplies consumed during production

2. Materials management activities relating to

managing the flow of materials into and through the

firm

3. Physical distribution activities relating to (2) aswell as to storing & transporting finished products

through distribution system to customers

Purchasing

70

Purchasing : objectives

Page 71: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 71/73

1. Good value – price & quality combo2. Reliable schedule – on time, JIT

3. Minimised investment – depends on economies

of order size, carrying costs, stock out costs

4. Efficient admin – keeping the cost of buying at

low levels, coordinate with other depts.effectively

Purchasing : objectives

71

Effective purchasing

Page 72: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 72/73

a. Purchasing requirement – description, qty, del.date, etc.

b. Sources of supply – personnel knowledge,

salespersons, ads, trade & industry associations,

peers, company records, etc. (sometimes

vendors must be developed)c. Cost of supply – cost per transaction, inventory

carrying costs, make or buy

Effective purchasing

72

Effective purchasing

Page 73: Session 6, 7 MRP

8/14/2019 Session 6, 7 MRP

http://slidepdf.com/reader/full/session-6-7-mrp 73/73

d. Prices & Value – buy at better prices (commonsources of price – lists , quotations , market px. ,

competitive bids , direct negotiations )

e. Administering the purchase – requisition costs are

evaluated sources identified price & values

established P.O. is raised supplies are receivedpayments

authorised records are kept

Effective purchasing