32
September 5, 2012

September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Embed Size (px)

Citation preview

Page 1: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

September 5, 2012

Page 2: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

DisclaimerDisclaimer

These remarks may contain forward-looking statements relating to the Company’s operations or to its business environment. Such statements are based on the Company’s operations, estimates, forecasts and projections, but are not guarantees of future performance and involve risks and uncertainties that are difficult to predict or control.   A number of factors could cause actual outcomes and results to differ materially from those expressed. These factors include those set forth in the corporate filings.   

Although any such forward-looking statements are based upon what management believes to be reasonable assumptions, the Company cannot guarantee that actual results will be consistent with these forward-looking statements. In addition, the Company disclaims any intention or obligation to update or revise any forward-looking statements, for any reason.  We also do not commit in any way to guarantee that we will continue reporting on items or issues that arise. 

STK – TSX.V

2

Page 3: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Capital StructureCapital StructureSTK – TSX.V

3

Symbol/Exchange: STK/TSX Venture

Shares Outstanding*: 111,719,740

Fully Diluted: 149,777,509

Share Price*: $0.075

Market Capitalization: $8.4 million

52 Week High/Low: $0.17/$0.055

Management & Board Ownership: 12%

* As of September 5, 2012

Page 4: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

HighlightsHighlights

• Strike has the potential to be the key player in an emerging gold camp near Wawa, Ontario

• The Edwards Property is a past producer with significant gold mineralized zones• The Hemlo West Project provides significant gold exploration potential• The Company has arranged a $3.5 non dilutive million financing to enable

underground development and commence production• The Company is now seeking a minimum of $3.0 million to provide the initial

production capital:• Plans for the balance of 2012 include:

– Continuing the dewatering of the Edwards Mine– Continuing underground exploration on the 60m, 90m &120m levels– Commencing production on the Edwards #1 and #5 veins– Follow up of known mineralization at Harkness-Hays– Prioritize mineral zones at Hemlo West for drilling and exploration.

STK – TSX.V

4

Page 5: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Michael Newbury, B.Sc. M.Sc. P.Eng., CEO, Director - 40 years experience as a banker, engineer, and project finance specialist. Board member of Roscan Minerals and Ring of Fire Resources, Director, President and CEO of Greenock Resources.

Kerry Smith, P.Eng., MBA. President: 30 years experience in mining operations, equity analysis and financing, operation and acquisition analysis.

Bruce Staines, B.Sc., P. Eng., Vice President – Edwards Mine Project, 40 years of underground gold mining experience.

Denis Crane, B.Sc., P. Eng., Chairman - President County Heritage Forest Prod. Ltd.,

Michael S. Harrington, Director - Experienced in advising mining companies on financing. Vice-Chairman of the board of KWG Resources since 1998. Colorado, USA.

Bruce Edgar, H. B.Sc., P. Geo, Director - Extensive experience in gold exploration in the Goudreau-Lochalsh belt

Ian McColl, P.Eng, Director – Extensive experience in operations and management, project management and engineering for the minerals and other resource industries worldwide Independent business person.

Scott Jobin-Bevans, Ph.D., P. Geo., Director - Founding Partner and Director, Caracle Creek International Consulting Inc. (CCIC) and President and Director of Prospectors and Developers Association of Canada.

Wendy Kimmel, BES, Secretary & Director - Independent business person. President of Mansell Properties Ltd.

Management & BoardManagement & BoardSTK – TSX.V

5

Page 6: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Goudreau - Lochalsh Gold BeltGoudreau - Lochalsh Gold BeltSTK – TSX.V

6

EDWARDS MINEPRODIGY MAGINO PROJECT

PAST PRODUCER

ISLAND GOLD MINEEAGLE RIVER GOLD MINE

Page 7: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Edwards PropertyEdwards Property

• River Gold Mines Ltd. : Production 1996 - 2001 Produced 144,000+ oz Au from underground mining operations on three

zones with an average mined grade of 0.35 oz/ ton gold Ceased mining in 2001 due to low gold price Lower zones within the Carbonate and Porphyry veins were developed but

not mined.

• Strike subsequently completed 41,000+ ft of diamond drilling delineating: New North zones (I & II) Plowman zones (1,2,3) Rusty Weathered zone

• Property permitted for mining, including limited surface facilities and a ramp for access to underground

STK – TSX.V

7

Page 8: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Edwards PropertyEdwards PropertySURFACE DRILLING

8

Page 9: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

ZONE Oz / Ton Au Length (ft)

Plowman 3 0.900.98

2.31.0

Plowman 1 0.840.81

11.01.0

New North 1 1.122.170.46

2.01.04.0

New North 2 2.683.320.485.90

7.07.04.01.0

Hole 88 - 11 1.31 3.0

Edwards PropertyEdwards Property

Selected Drill Intercepts:

SURFACE DRILL INTERCEPTS

9

Page 10: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

UNDERGROUND MINERALIZATION

Back Sampling Results from zones previously prepared for mining

Edwards PropertyEdwards Property

• These are located on 280m level when mining ceased due to a low gold price ~$300/oz

• Subsequent drilling indicates that mineralization continues to greater depths

Porphyry Zone Carbonate Zone

Oz/Ton Au 0.293 0.506

Width (ft) 4.9 5.0

Length (ft) 196.0 262.4

STK – TSX.V

10

Page 11: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

HISTORICAL UNDERGROUND DEVELOPMENT

Edwards PropertyEdwards PropertyHISTORICAL MINING

11

Ramp

Porphyry Zone

Carbonate Zone

Shayne Zone

Page 12: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

UNDERGROUND PROJECTION OF NEW ZONES

Edwards PropertyEdwards PropertySTK – TSX.V

12

Historical Mining Zone

New North l & 2 Zones

Plowman 1, 2 & 3 Zones

Page 13: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Edwards PropertyEdwards PropertyGEOLOGIC MODEL

13

The development plan for the Edwards is the underground exploration of the new gold mineralized zones to achieve the near-term objective to commence production in 2012.

The gold mineralization occurs in a quartz vein system and is similar to other gold quartz vein type deposits in northern Ontario and Quebec. Gold mineralization in these types of deposits has a nugget effect that can result in very high assays immediately adjacent to portions of the vein having no significant values. The drilling at Edwards has a similar result in that some intersections have significant gold mineralization and some do not. Historical underground production indicates that the average grade for the mineralized zones is approximately 0.3 oz/ton of gold.

To obtain a more reliable estimate of the production potential of the new gold zones drifting along two of the new zones has commenced on the 60m level. This will allow underground bulk sampling to complete a full assessment on the production potential.

Page 14: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

60m Development Plan60m Development PlanSTK – TSX.V

14

Edwards #1 #5 #3

Rusty Weathered Zone

Plowman #1

60M Level Plan

Page 15: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

90m Development Plan90m Development PlanSTK- TSX.V

15

90M Level Plan

Edwards #1, #2, #3

Rusty Weathered Zone

Plowman #1

2012 Planned Drifting

Historical Driftl

Page 16: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Edwards PropertyEdwards Property

• The company has dewatered the old workings to below 140m;• 60m Level:

– Drifting of 57.3m along Edwards #1; Has exposed a 23.3m long section that averages 25.45 g/t over a 1.5m mining width.

– Drifting of 60.4m along Edwards #5; Has exposed a 24.0m long section that averages 15.14 g/t over a 1.5m mining width.

• Cross Cut Advance:– Approximately 87.5m on the 60m level and 30.7m on the 90m level. Rusty

Weathered Zone has been intercepted on the 60m level.

• Surface stockpile:– High grade – 1100 tonnes grading 13 g/t– Low grade – 1800 tonnes grading 2 gpt

STK – TSX.V

16

Page 17: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

17

Edwards Vein #1

23.3 m length averaging 25.45 gpt over 1.5 m mining width

Page 18: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Edwards Vein #5

18

24.0 m length averaging 15.14 gpt over 1.5 m mining width

Page 19: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Zones Tons Oz Grade (ounces / ton)

New North 1 58,121 18,698 0.322

New North 2 38,462 41,827 1.087

Plowman 1 46,719 9,725 0.208

Plowman 2 67,976 7,265 0.107

Plowman 3 30,820 5,542 0.179

Sub Total: 242,098 83,057 0.343

Additional Inventory

New North 1 81,463 26,231 0.322

New North 2 Not yet completed.

Plowman 1 171,896 26,241 0.15

Plowman 2 95,973 17,179 0.179

Sub Total: 349,333 69,651 0.199

Total: 591,432 152,703 0.258

Previous Mining Zones 47,000 19,560 0.42

GRAND TOTAL 638,432 172,263 0.28

Edwards PropertyEdwards Property

Inferred Resource Inventory (Non – 43-101)

Potential Resources

Page 20: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Other Drilling:• 2010 drilling: A sulphide-rich quartz vein was

encountered at vertical depth of 220 feet with Visible Gold returning a grade of 21.86 g/ton Au over 0.91 metres (0.641 oz/ton over 3.0’) and stringers within a Felsic Intrusive vertical depth of 260 feet returned a grade of 6.56 g/ton Au over 1.52 metres (0.191 oz/ton over 5.0’)

• This intercept indicates the continuity of an east-west trending shear/alteration zone with gold mineralization over some 2,500 feet from the Edwards property through the Cline property and on to the Pele Mountain gold property

• Hole 88-11 on the Edwards Mine property has intersected a siliceous section with quartz veining that assayed 40.0 g/ton over 0.66 metres (1.326 oz/ton over 2.0 feet) in a zone located near the North boundary of the claims. Additional follow up is required.

Edwards PropertyEdwards Property

20

Edwards Mine

Cline Property

2010 Drilling

EXPLORATION

Hole 88-11

Page 21: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Adjacent Properties in Goudreau Gold BeltAdjacent Properties in Goudreau Gold Belt

COMPANY STATUS PRODUCTION RESULTS RESOURCES G / T

Prodigy GoldMagino

Development Feasibility Study: Capital cost $242 million Op cost $521/oz

Indicated:Inferred:

20.2 m tonnes @ 1.925.8 m tonnes @ 1.77

Island Gold Producer 260,000/yr produce 52,000 oz(Cost $790.00/oz)

Proven/Prob:M/I

Inferred:

818,000 t @ 6.13800,000 t @ 7.36600,000 t @ 7.14

WestdomeEagle River

Producer 200,000 t/y produce 53,000 oz(cost $1,000/oz)

Proven/ProbInd/Inf

345,000 t @ 15.00410,000 t @ 6.80

Pele Mountain 10,000 bulk sample produced 1,702 oz.*Recently proposed production of 12,000 tonnes @ 6.6 g/t

n/a n/a

21

STK – TSX.V

Page 22: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

• A large property near Schreiber Ontario - approximately 35 km² regular claims and patented mining claims providing a strategic land position with excellent exploration potential

• Strike is acquiring a 100% interest in the property subject to some NSR royalties from previous property holders

• Historical production from four past producing gold mines (North Shore, Morely Mine, Harkness Hayes, Golden Range)

– Three diamond drill holes have recently been completed on the Harkness Hayes with assays pending on hole #3

• Recent exploration has identified in excess of 25 areas of surface high grade gold bearing zones that require detailed exploration

• The southern zone contains an extension of the Afric gold zone that Noranda Inc., in 1990, calculated a non-NI43-101 compliant, near surface “geological resource” 2.0 million tonnes grading 2.20 g/t gold (140,000 ounces) based on the completion of 20 drill holes

22

Hemlo West ProjectHemlo West ProjectSTK – TSX.V

Page 23: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

23

STK – TSX.V Hemlo West Project

STRIKE CLAIMS

Page 24: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

• In the 1990’s both Noranda and Cyprus Canada conducted significant drilling on the Afric zone that extends onto the property.

– This drilling on adjacent property delineates a near-surface historical resource of 2.0 million tonnes at 2.2 g/ton

– More recently Balmoral and GTA intersected 149.50 metres grading 1.20 g/t gold (capped) on Northshore property, majority of holes collar and end in mineralized zone; Caly-Caly north vein system returns 12.49 g/t gold over 33.20 metres, including 760.15 g/t gold over 0.40 metres; high-grade Audney vein returns 13.23 g/t gold over 6.50 metres.

– The western extension of the Afric zone carries onto the Strike claims.

Hemlo West ProjectHemlo West Project

24

STK – TSX.V

Page 25: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

25

Hemlo West Afric ZoneHemlo West Afric Zone

Strike Property

Afric Zone Extension

STK – TSX.V

Page 26: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

26

Strike Property

GTA /Balmoral

Current GTA Drilling Location

Afric Zone

Hemlo West Afric ZoneHemlo West Afric Zone

Page 27: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

• Located 48 km west of the Hemlo Gold Camp, gold was discovered and mined by Harkness-Hayes 1920 to 1940. Underground development included 1,730 ft drifting in 8 adits on high-grade gold bearing veins;

• There are other zones of gold mineralization that were exploited during that period; Morley, Gold Range, Longworth and Gale.

• Historical channel samples from Harkness-Hayes property have yielded significant values on veins 2 and 3. Historical channel sampling of Vein 3 values ranged from 1,396.7 g/t over a width of 25.4 cm to 2.63 g/t over a width of 25.4 cm. at 5 foot intervals over a 250 foot length.

• Vein 3 exposed near surface for approximately 125 metres available for bulk sampling.

• A diamond drill campaign has commenced, designed to test strike length, depth and continuity of the previously mined mineralized structures.

• (Note: These values are historical and are not compliant with NI 43-101)

Hemlo West ProjectHemlo West Project

27

STK – TSX.V

Page 28: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

28

Hemlo West ProjectHemlo West Project

Historic Vein Sampling – Harkness Hays Deposit

Hemlo West ProjectHemlo West ProjectSTK – TSX.V

Page 29: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Edwards

• The current goal is to have the Edwards in initial production by Q3/Q4 2012 based on the following milestones :

– Continue dewatering currently at 140m level– Drifting on the 60m level and the 90 metre level to crosscut the New North 1 & 2,

Edwards #1, #2, #3, and Rusty Weathered zones– Conduct initial mining on the Edwards #1 and #5 zones and prepare production– Negotiate a custom milling contract with a nearby producing Gold project– Conduct underground exploration at deeper levels to expand the mineralized

zonesHemlo West

– Commence surface exploration and sampling to locate and evaluate the known gold occurrences located on the property.

– Commence drilling to evaluate the extension of the Afric zone.

APPENDIX

29

Strategic Plan and ObjectivesStrategic Plan and Objectives

Page 30: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Edwards Development PlanEdwards Development Plan

30

Proposed Timeline and Budget for the Edwards Mine Development

2012 2013Aug Sept Oct Nov Dec Jan Feb Mar April May June July

Dewatering to 150m

Production Mining 60m Level

Exploration 60m Level

Production Mining 90m Level

Exploration 90m Level

Dewatering to 300m

Underground Development

Exploration on 120m Level

Schreiber Exploration

The exact time line and sequence of activity depend on factors outside the company’s control. These include: weather; equipment availability; financing; personnel; etc.

Page 31: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

SummarySummary

• Strike Minerals is a mining exploration and development company focused on the development of precious metal properties in Northern Ontario

• The flagship Edwards Property a formerly producing mine with new mineral resource targets. Permits and infrastructure are in place and low capex development has started to achieve production in 2012:

Historically produced 144,000 oz of gold by River Gold (‘96-’01) at an average grade 0.35 oz/ton Au from Carbonate and Porphyry zones

Subsequently Strike completed 41,000+ ft. of drilling that identified 5 new parallel and sub-parallel gold mineral zones in addition to those previously mined

Dewatering the Edwards Mine is below the 140m level and the property permitted for mining, Strike commenced in early 2012 an underground mining plan on the 60m and 90m levels to

delineate and expand current gold mineralized zones Strike expects to recommence mining Edwards by the end of 2012 Richmont’s Island Gold mill is located 10km to the West

• The Company has arranged a $3.5 million Gold Stream Debt financing with Waterton Global 

• Strike has highly prospective Hemlo West properties near Schreiber surrounding the GTA ground

• Strike’s management and board have the experience needed to develop the project and deliver value to shareholders.

STK – TSX.V

31

Page 32: September 5, 2012. Disclaimer These remarks may contain forward-looking statements relating to the Companys operations or to its business environment

Contact InformationContact Information

MICHAEL NEWBURY, KERRY D. SMITH

T: [email protected]

STK – TSX.V

80 RICHMOND STREET WEST, SUITE 1101 • TORONTO, ON • M5H 2A4T: 416-603-7200 • F: 416-603-9200 • E: [email protected]

32