Upload
lythu
View
215
Download
0
Embed Size (px)
Citation preview
Copyright (C) Mitsubishi Research Institute, Inc.
Sendai Microgrid
- Introduction and Use Case
July, 2012
Hiroshi Irie (Mr.), Mitsubishi Research Institute, Inc.
1
Outline
Today’s topic - Sendai Microgrid Constructed for the purpose of demonstration project
Still in operation after finishing demonstration project
Has two aspects
MPQM (Multiple Power Quality Microgrid)
Microgrid which supplies electricity in islanded mode – “Earthquake”
Contents
Introduction of Sendai Microgrid
Use Case
What is MPQM, and how it works
Change in configuration after the demonstration project
Earthquake experience of Sendai Microgrid
To be presented by Dr. Hirose after this presentation
Copyright (C) Mitsubishi Research Institute, Inc.
By Me
By Dr. Hirose
2 Copyright (C) Mitsubishi Research Institute, Inc.
Sendai Microgrid Overview
3
Sendai Microgrid
Constructed as a 4-year demonstration project (FY 2004 – 2007)
Entrusted by NEDO
Technical feature = MPQM (Multiple Power Quality Microgrid)
Desired power quality varies by customer in the Microgrid.
MPQM enables power supply with different levels of power quality for each
customer within the area.
Copyright (C) Mitsubishi Research Institute, Inc.
PV Panels 50 kWp
(IPS) Integrated
Power Supply DVRs
200 kVA 600 kVA
MCFC 250 kW Gas Gen-sets
350 kW X 2
Sendai City
Overview of Sendai Microgrid Geographical location of Sendai City
4
Coverage Area
One connecting point (PCC) with Utility Grid
Divided into 2 areas:
University area
City-owned area
Copyright (C) Mitsubishi Research Institute, Inc.
App. 0.5 km (0.3 mile)
High School
Water Plant Facility
Connecting Point with Utility Grid
Cable Routes
Buildings
N
University Zone
City-owned Zone
Energy Center
5
Power Quality Definition and the Loads
Different classes of power quality
In the Sendai Microgrid, five classes of power quality (DC Supply, A, B1, B2 & B3)
have been defined according to each consumer’s needs.
Copyright (C) Mitsubishi Research Institute, Inc.
Requirements
CLASS
DC
Power
AC Power
A B1 B2 B3
Interruption NI NI < 15 ms < 15 ms < 15 ms
Voltage Dip Y Y Y Y Y
Outage Y Y Y Y* -
Voltage Fluctuations Y Y - - -
Voltage Harmonics Y Y - - -
Voltage Unbalance N/A Y - - -
Frequency Variation N/A Y - - -
Note. NI: No Interruption, Y: With compensation-: Without compensation,
*: When Gas engine sets generated
Power quality classes of the Sendai Microgrid
CLASS Capacity Consumers (Load)
A 200 kVA Clinic (MRIs)
Laboratory (servers)
B1 20 kVA Nursing Care Facilities
(lighting, PCs)
B2 600 kVA
High School
(lighting, PCs, elevators)
Water plant (induction motors)
B3 200 kVA Nursing Care Facilities
(lighting, clinic equipment)
DC 20 kW Energy Center
(servers, lighting, fans)
Normal N/A
Nursing Care Facilities
Training Center
Dormitories
Power quality classes and Loads
6
System Configuration
Generation Facility
Integrates generation facilities in coordination with power from area EPS
Generation Facilities inside the Microgrid
Two Gas Engines (350kW × 2)
Photovoltaic Generation (50kW)
Fuel Cell (250kW)
Copyright (C) Mitsubishi Research Institute, Inc.
DVR*#2
NormalQuality
Load
B3Quality
Load
130 kW700 kW
350 kW350 kW 50 kW
18 kW
6.6 kVac Bus
Point of Common
Coupling PVGE GE
250 kW
MCFC
420 kW
B1Quality
Load
DVR*#1
B2Quality
Load
20 kW180 kW
AQuality
Load
DCQuality
Load
Integrated Power Supply
IPS
200 k
VA
600 k
VA
DGs
PQ
Improvement
Different
PQ Levels’
Loads
Resale Prevention Relay
Key Energy Devices
IPS (Integrated Power Supply)
Provides the highest level of quality
DVR (Dynamic Voltage Restorers)
Compensates Voltage Dip
2 Switches
Point of Common Coupling
Resale Prevention Relay
Manages islanding operation of the
Microgrid by changing the switch
status to Open or Close in the event
of power outage/recovery.
Configuration of Sendai Microgrid
7 Copyright (C) Mitsubishi Research Institute, Inc.
Use Case -What is MPQM and
How it works
8
Definition of MPQM and Model Simplification
Definition
. The Multi Power Quality Microgrid (MPQM) enables the supply of power to critical loads at multiple levels
of power quality at higher levels than are supplied normally by the distribution utility.
The Microgrid does this by utilizing Distributed Energy Resources (DER) and power from the distribution
utility (grid) in a mutually complementary manner
Functions
The MPQM can continue to supply power at a high power quality level, when grid connected, when the
DER is grid-connected, or when the grid suffers from an outage and the DER is in an islanding operation
mode.
Simplified Model MPQM”:
Focuses on the functionality of “Multiple Power Quality Supply”
Describes the supply of three classes of power quality, as follows:
Copyright (C) Mitsubishi Research Institute, Inc.
Class Voltage Dip
Compensation
Waveform
Compensation
Power-failure Compensation
A-Class Compensation
by IPS
Compensation
of waveform.
In case of power outage in grid: DER shifts to islanding operation.
In case of power outage of DER: Power continues to be supplied
from the UPS (battery) embedded in the IPS.
B-Class Compensation
by DVR
No waveform
compensation
In case of power outage in grid: DER shifts to islanding operation.
In case of power outage of DER: No compensation for outage.
Normal
Class
No voltage dip
compensation
No waveform
compensation
No compensation or back up for outage.
9
Configuration of the Simplified Model
Simplified Configuration
The below diagram shows a configuration of the Microgrid offering three classes of
power quality shown in the previous page.
Copyright (C) Mitsubishi Research Institute, Inc.
Generation Facility
Microgrid has DERs
Two operational modes
Grid Connection Mode
Islanding Mode
Two Switches
Switch 1
PCC between MPQM and
commercial grid
Switch 2
Boundary point of the
microgrid’s Islanding
Operation Model Configuration
A ClassLoad
A ClassLoad
A ClassLoad
NormalClassLoad
NormalClassLoad
NormalClassLoad
B ClassLoad
B ClassLoad
B ClassLoad
DVR IPS
Grid DERs
Optimized operation between the grid power and DGs
Power Quality
ImprovementNormalQuality
A Class Quality SystemB Class Quality System
SWITCH1SWITCH2
10
Configuration of the Simplified Model (Cont.)
IPS
Able to supply A-Class
Power quality compensation system
with battery storage
Copyright (C) Mitsubishi Research Institute, Inc.
Three operational modes:
Grid-Connection Mode
DER-Islanding Mode
Battery-Supply Mode
DVR
Able to supply B-Class
Compensates Voltage dip
Implemented in STATCOM
Integrated Power Supply
PV AC Power Source
BatteryACSW
Bypass Circuit
Byp
ass C
ircu
it
50 kWp
DCDC
50 kW 600 Ah
DC Bus
430 Vdc
DCAC
ALoad
B1Load
DCLoad
ACDC
DCDC
300 Vdc
Bidirectional
Converter20 kW
200 kVA
(180 kW)
300 kVA
(270 kW)
3P 400 Vac 3P 200 Vac
IPS System used in Sendai Microgrid
11
MPQM’s Behavior – Four Stages
Four Stages Comprising MPQM’s Behavior
Stage 1: Demand and generation forecast, generation scheduling and on-the-day
review
Develop generation schedule of the Microgrid
Monitor supply-demand status
Copyright (C) Mitsubishi Research Institute, Inc.
Stage 2-1:A-CLASS POWER
QUALITY SUPPLY
Supply A-Class loads with A-
Class quality of power.
Stage 2-2:B-CLASS POWER
QUALITY SUPPLY
Supply B-Class loads with B-
Class quality of power.
Stage 3: Automatic shift to
connected operation at grid
restoration
Manage the grid’s outage/
restoration with two switches Four Stages of Function
A ClassLoad
A ClassLoad
A ClassLoad
NormalClassLoad
NormalClassLoad
NormalClassLoad
B ClassLoad
B ClassLoad
B ClassLoad
DVR IPS
Grid Power DGs
NormalQuality
A Class Quality SystemB Class Quality System
SWITCH1SWITCH2
Stage 1
Stage 3
Stage 2-1Stage 2-2
12
Stage 1:
Demand and generation forecast, generation scheduling and on-the-day review
Precondition
Reverse flow from MPQM to Grid is prohibited according to the grid connection agreement
between MPQM owner/operator and the electric utilities.
Therefore, it is required for the Microgrid to set a target for the power flow at the PCC and
incorporate it into the operational plan of DER.
Copyright (C) Mitsubishi Research Institute, Inc.
EMS
Demand Archive
DER
1.1:demand record
1.2:demand forecast value1.3: PCC reference1.4:output reference3.1:revised output reference
Customer RTU
2.1:output reference3.2:revised output reference
2.2:demand record
Flow of DER Dispatch
Flow1: Development of generation
schedule
Develop generation schedule
based on the past demand
data, demand forecast and
PCC flow target value.
Flow2: Command and monitoring
Send commands to DER and
also monitor demand data
Flow3: Correction of discrepancy
Change the planned value in
case there is a discrepancy
between supply & demand.
Communication Diagram of Stage 1
13
Stage 2-1:
A-CLASS POWER QUALITY SUPPLY
In the Event of Instantaneous Voltage Dip (Case 1)
IPS shifts into Battery-Supply Mode as it detects an occurrence of instantaneous voltage dip
from the grid voltage.
Copyright (C) Mitsubishi Research Institute, Inc.
DER
IPS1:Grid Voltage
Grid
Switch2
2.1:Grid Voltage
EMS
2.2a: Switch 2 signal
2.3: DER-Islanding mode command
2.2b: Switch 2 signal
2.4: DER islanding operation signal
2.5: IPS-DER Islanding mode command
3: DER STOP SIGNAL
In the event of grid outage (Case 2)
Switch 2 automatically
opens as it detects an
outage.
DER shifts to Islanding
mode as it detects the
opening of Switch 2.
EMS sends IPS a
command to shift to
Islanding mode as it
detects the opening
of Switch 2.
IPS shifts into Islanding mode.
In the event of DER stop (Case 3)
IPS shifts into battery supply mode as it
detects the stop of DER. Communication Diagram of Stage 2-1
14
Stage 2-2:
B-CLASS POWER QUALITY SUPPLY
B-Class power quality cannot be supplied when DER is no longer available.
In the event of Instantaneous Voltage Dip (Case 1)
DVR compensates the voltage as it detects an occurrence of instantaneous
voltage dip from the grid voltage.
Copyright (C) Mitsubishi Research Institute, Inc.
DER
DVR1:Grid Voltage
Grid
Switch2
2.1:Grid Voltage
2.2: Switch 2 signal
2.3: DER-Islanding mode command
In the event of grid
outage (Case 2)
Switch 2 automatically
opens as it detects an
outage
DER shifts to Islanding
mode as it detects the
opening of Switch 2.
Communication Diagram of Stage 2-2
15
Stage 3:
Automatic shift to connected operation at grid restoration
Microgrid automatically shifts to islanding operation at time of grid outage.
Microgrid automatically shifts to grid connected operation at time of grid restoration.
Copyright (C) Mitsubishi Research Institute, Inc.
DER
Switch 11.1b:grid voltage2.1: grid voltage
Grid
Switch2
1.1a:grid voltage
1.2: Switch 2 signal2.5: Switch 2 signal
1.3: DER-Islanding mode command2.3b:islanding system voltage
islanding system frequency2.6: Grid connection mode command
2.2:grid voltagegrid frequency
2.3a:grid voltagegrid frequency
2.4: Switch 2 close operation
Communication Diagram of Stage 3
At time of grid outage (Case 1)
Switch 2 opens as it immediately
detects an outage from the grid
voltage information.
Simultaneously, Switch 1 opens.
DER shifts to Islanding mode as it
detects the opening of Switch 2.
At time of grid restoration (Case 2)
Switch 1 closes as it detects power
restoration from the grid voltage
information.
DER synchronizes the voltage and
frequency of the islanding system
with the grid’s voltage and
frequency.
DER closes Switch 2 as soon as it
detects the synchronization.
16 Copyright (C) Mitsubishi Research Institute, Inc.
Configuration Update After the Demonstration
(Introduction to Hirose-san’s Presentation)
17
Coverage Area of Sendai Microgrid after the Demonstration
Copyright (C) Mitsubishi Research Institute, Inc.
Coverage area and configuration of the Sendai Microgrid changed during and after
the demonstration project.
GE is now also used for emergency power generation, starting to supply the C-Class power
to emergency system in (newly-built) hospitals.
Fuel Cell (MCFC) has been removed.
Supply of B2-Class (Sendai High School Water Plant Facility) has been finished.
DVR has been also removed.
Coverage Area During Demonstration
New Hospital Opened- Deriver C-Class
High School
Water Plant Facility
Connecting Point with Utility Grid
Energy CenterStop electricity Supply to City Owned Zone(B2 Class)High School
Water Plant Facility
Connecting Point with Utility Grid
N
Energy Center
Coverage Area After
Demonstration
18
Changes in Configuration
Configuration during the demonstration project
DVR*#2
NormalQuality
Load
B3Quality
Load
130 kW700 kW
350 kW350 kW 50 kW
18 kW
6.6 kVac Bus
Point of Common
Coupling PVGE GE
250 kW
MCFC
420 kW
B1Quality
Load
DVR*#1
B2Quality
Load
20 kW180 kW
AQuality
Load
DCQuality
Load
Integrated Power Supply
IPS
200 k
VA
600 k
VA
Resale Prevention Relay
DVR*
#2
NormalQuality
Load
B3Quality
Load
130 kW700 kW
350 kW350 kW 50 kW
18 kW
6.6 kVac Bus
Point of Common
Coupling PVGE GE
B1Quality
Load
20 kW180 kW
AQuality
Load
DCQuality
Load
Integrated
Power Supply
IPS
200 k
VA
C’Quality
Load
SW
170 kW
DVR*
#2
NormalQuality
Load
B3Quality
Load
130 kW700 kW
350 kW350 kW 50 kW
18 kW
6.6 kVac Bus
Point of Common
Coupling PVGE GE
B1Quality
Load
20 kW180 kW
AQuality
Load
DCQuality
Load
Integrated
Power Supply
IPS
200 k
VA
C’Quality
Load
SW
170 kW
Configuration after the demonstration project
There is more B2-Class load.
C’-Class load (supply to new hospital) has been added, instead.
19 Copyright (C) Mitsubishi Research Institute, Inc.
Thank you for your attention! [email protected]