55
A GUIDE FOR SELF-ERECTING TOWER CRANE OPERATORS WorkCover. Watching out for you. TRAINER’S EDITION 2005

Self Erecting Tower Crane Operators Guide

Embed Size (px)

DESCRIPTION

SELF ERECTING TOWER CRANE - OPERATOR GUIDE

Citation preview

  • A GUIDE FOR SELF-ERECTING

    TOWER CRANE OPERATORS

    WorkCover. Watching out for you.

    TRAINERS EDITION 2005

  • Disclaimer

    This publication contains information regarding occupational health, safety, injury management or workers compensation. It includes some of your

    obligations under the various workers compensation and occupational health and safety legislation that WorkCover NSW administers. To ensure you

    comply with your legal obligations you must refer to the appropriate legislation.

    This publication may refer to WorkCover NSW administered legislation that has been amended or repealed. When reading this publication you

    should always refer to the latest laws. Information on the latest laws can be checked at www.legislation.nsw.gov.au or contact 1300 656 986.

    WorkCover NSW

  • Page 1

    A GUIDE FOR SELF-ERECTING TOWER CRANE OPERATORS TRAINERS EDITION

    This guide outlines the information and requirements for a trainer to instruct a trainee on the facets

    of self-erecting tower crane operation.

    This guide follows the information supplied in the compiled learners edition.

    How to use this manual

    Each section related to the relevant sections in the accompanying learners guide. Both booklets are required to be utilised hand in hand. Related questions from the assessment instrument are included at the end of each section to

    facilitate easy understanding for the trainee.

    Some general questions are taken from the cranes National Certificate of Competency Written Assessment for Cranes August 2000.

  • Page 2

    CONTENTS SECTION 1 Competency for self-erecting tower crane operators 3

    SECTION 2 Types of self-erecting tower cranes 3

    SECTION 3 Features of self-erecting tower cranes 3

    SECTION 4 Crane controls 4

    SECTION 5 Set-up crane 4

    SECTION 6 Assembly/disassembly 6

    SECTION 7 Limit switches 8

    SECTION 8 Load/radius indicators 8

    SECTION 9 Brakes 9

    SECTION 10 Site/job planning 9

    SECTION 11 Maintenance procedures 13

    SECTION 12 Pre-operational 13

    SECTION 13 Crane operation 16

    SECTION 14 Loads and self-erecting tower 19

    SECTION 15 Special operations 26

    SECTION 16 Shutdown crane 27

    SECTION 17 Rule of thumb and working load limits 29

    SECTION 18 Load factors 31

    SECTION 19 Rules to follow when slinging and handling a load 34

    SECTION 20 Stacking 36

    SECTION 21 Personal protective equipment 36

    SECTION 22 Communication 36

    SECTION 23 Flexible steel wire rope 37

    SECTION 24 Wedge rope sockets 39

    SECTION 25 Sheaves and drums for flexible steel wire rope 40

    SECTION 26 Lifting chain 42

    SECTION 27 Flat webbing and round synthetic slings 44

    SECTION 28 Fibre rope 45

    SECTION 29 Accessories 46

    SECTION 30 Calculation 49

    APPENDIX (I) Tables of masses 52

  • Page 3

    SECTION 1

    COMPETENCY FOR SELF-ERECTING TOWER CRANE OPERATORS Points for trainer

    Explain to the trainee the process of obtaining an assessment for a self-erecting tower crane operators competencies.

    SECTION 2

    TYPES OF SELF-ERECTING TOWER CRANES Points for trainer

    Relate this section to the particular self-erecting tower crane to be used for the training practical sessions.

    Ensure the trainee understands crane terminology in relation to self-erecting tower cranes. Explain to the trainee the different types of self-erecting tower cranes. Describe to the trainee the main functions and motions of a self-erecting tower crane. Practical session

    Show the trainee the various components on the specific self-erecting tower crane used for the practical training.

    Media application

    Using a scale model, explain to the trainee the terminology for the various components on a self-erecting tower crane.

    Use overhead transparencies to explain terminology for a self-erecting tower crane. Trainers notes

    SECTION 3

    FEATURES OF SELF-ERECTING TOWER CRANES Points for trainer

    Explain to the trainee that some of these features may or may not be included for the particular self-erecting tower crane used in the training session.

    Explain to the trainee the specific features of the self-erecting tower crane used in the training session. Practical session

    Show the trainee the particular use of various features on the specific self-erecting tower crane used for the training sessions. Features include cabin (where applicable), the outriggers, electrical apparatus, hook blocks and sheaves.

    Trainers notes

  • Page 4

    SECTION 4

    CRANE CONTROLS Points for trainer

    Review this section to ensure the trainee understands the use of each crane control and their particular function.

    Practical session

    Demonstrate to the trainee the use of the crane controls and their application for the particular self-erecting tower crane used in the session.

    Explain to the trainee the use of the emergency stop button for the particular self-erecting tower crane used in the training session.

    Trainers notes

    SECTION 5

    SET-UP CRANE Points for trainer

    Review this section to ensure the trainee understands the issues involved in setting up/assembly of a self-erecting tower crane.

    Explain to the trainee the purpose and use of properly set-up outriggers. Explain to the trainee the hazards of unstable ground or footings and reason for adequate packing of

    outriggers.

    Explain to the trainee the importance of adequate bearing for support of the tower crane. Questions for trainee/s

    Question 1

    Explain the requirements for preventing personnel from entering the counterweight-slewing radius of the crane?

    Answer The area must be thoroughly barricaded.

    Reference: Oral/written assessment question 25

    Question 2

    Should a self-erecting tower crane be set-up/assembled next to open trenches or excavations? Explain your answer.

    Answer No. The self-erecting tower crane should not be set-up/assembled close to an excavation as the weight of the crane creates additional pressure to the adjoining soil and can cause the excavation to collapse resulting in the crane overturning. An engineer may need to approve the cranes position.

    Reference: Oral/written assessment question 39

  • Page 5

    Question 3

    What principles would apply to setting up/assembling a self-erecting tower crane next to an open trench/excavation?

    Answer The self-erecting tower crane base (ie pad) area should be certified by an engineer.

    Reference: Oral/written assessment question 40

    Question 4

    What action would be required if an excavation was dug adjacent to the base of the self-erecting tower crane?

    Answers -

    Stop operation and have the excavation immediately backfilled and compacted. Have the ground assessed by a qualified person. Barricade the area thoroughly to prevent a reoccurrence.

    Reference: Oral/written assessment question 41

    Question 5

    Where is the information found to determine the area of packing required under outriggers? Answer In the manufacturers manual or seek approval from an engineer.

    Reference: Oral/written assessment question 42

    Question 6

    List three points that should be considered when setting up outriggers? Answers -

    All outriggers must be used as per the manufacturers instructions. All beams must be fully extended or as per the manufacturers instructions. Correct selection of footplate or packing. Outrigger pads must be securely pinned or connected to the outrigger beams.

    Reference: Oral/written assessment question 43

    Question 7

    Why must the self-erecting tower crane be set-up/assembled level? Answer To ensure the self-erecting tower crane is stable and the crane can be operated at it rated capacity.

    Reference: Oral/written assessment question 45

    Question 8

    When setting up/assembling a self-erecting tower crane what items need to be considered in regards to crane clearances?

    Answers -

    Ensure the counterweight tail radius is clear to slew 360 degrees to satisfy safety requirements for the particular worksite.

    Ensure all site hazards in the slewing radius of the self-erecting tower crane have been assessed. Ensure barricades or fencing of a minimum one metre in height are used to prevent personnel gaining

    entry to the slewing counterweight area of the self-erecting tower crane.

    Reference: Oral/written assessment question 46

    Question 9

    When setting up/assembling a self-erecting tower crane where the ground or soil value cannot be identified (eg on a bitumen or concrete road), what precautionary methods would need to be taken?

    Answer Assess the situation and ensure the assembly is set-up as determined by an engineer.

    Reference: Oral/written assessment question 49

    Question 10

    What risks occur when packing is placed halfway along the outrigger beam to support the crane? Answer This creates an inside tipping point and reduces stability, possibly causing the self-erecting tower crane to overturn.

    Reference: Oral/written assessment question 50

  • Page 6

    Question 11

    A self-erecting tower crane has been set-up/assembled on a new site, which requires unloading of trucks from a street over a busy pedestrian footpath. What hazard controls are required to progress with the operation ensuring public safety?

    Answers -

    A hoarding and gantry must be in place that conforms to the relevant standard. Barricades, detours or pedestrian control could be utilised. Traffic control may be required.

    Reference: Oral/written assessment question 61

    Practical session

    Demonstrate to the trainee the procedure for location of hazard controls before setting up/assembling the crane.

    Demonstrate to the trainee the procedure for set-up/assembly of the particular self-erecting tower crane used in the training session.

    Explain to the trainee the preparations for set-up/assembly of the crane on a new site. The following points must be taken into consideration.

    The position of the self-erecting tower crane is satisfactory in relation to the task to be undertaken. Outriggers or stabilisers are extended, packed and set-up as per manufacturers specifications. Base levelled and bearing on all outriggers or stablisers. Counterweight is erected and adequate as per the manufacturers specifications or according to load

    chart requirements.

    Reference: Performance assessment section F

    Trainers notes

    SECTION 6

    ASSEMBLY/DISASSEMBLY Points for trainer

    Review this section to ensure the trainee understands the issues involved in assembly and disassembly of a self-erecting tower crane.

    Questions for trainee/s

    Question 1

    What qualification must be held by personnel to assemble a self-erecting tower crane? Answer An intermediate or advanced riggers certificate

    Reference: Oral/written assessment question 47

  • Page 7

    Question 2

    When can additional counterweight be added to the crane? Answer As per manufacturers recommendation that apply to the specific self-erecting tower crane.

    Reference: Oral/written assessment question 48

    Practical application

    Ensure the trainee understands the following points in assembly of the tower crane. Self erecting tower crane transported to site Assess hazards and implement a risk assessment or work method statement Assess individual environmental conditions such as weather and wind conditions Check engineers compliance certificate Erect barricades and ensure public safety Surface prepared for crane set-up Adequate clearances to assemble and unfold the crane as per manufacturers specifications Outriggers positioned and packed Self erecting tower crane levelled by using jacks Earth crane to the ground Connect the power supply Base counterweights installed or as per manufacturers specifications Trolley and hook block must be in correct position for unfolding of jib or as per manufacturers

    specifications

    The crane mast and jib must be unfolded in correct sequence against the prevailing wind. (Note: Extreme caution is necessary during the unfolding procedure to ensure each section is assembled correctly.) Follow the manufacturers specifications.

    Remainder of counterweights are installed or as per manufacturers specifications Complete unfolding remainder of jib sections as per the manufacturers specifications Check all limits and all governors for correct functioning Load testing self-erecting tower crane under the supervision of a competent person

    Reference: Performance assessment section G

    Ensure the trainee understands the following points in disassembly of the tower crane. Note: Particular attention must be considered for the correct sequence of counterweight removal.

    Trainers must use manufacturers manuals for each complete crane disassembly.

    Reference: Performance assessment section H

    Media application

    Use a scale model or use OHPS to display the system and procedure involved in assembly and disassembling of a self-erecting tower crane.

    Use a video supplied by the manufacturer to display the assembly and disassembling procedure for a specific self-erecting tower crane.

    Trainers notes

  • Page 8

    SECTION 7

    LIMIT SWITCHES Points for trainer

    Explain to the trainee the importance of checking limit switches for correct functioning on each operational workday of a self-erecting tower crane.

    Questions for trainee/s

    Question 1

    Why is it important to check the hoist limit or cut out switch prior to using the crane? Answer To ensure that it is operating correctly so that double blocking does not occur.

    Reference: Oral/written assessment question 36

    Question 2

    Why is it important that all motion limits are checked for correct functioning? Answer To ensure that all limits are working to avoid causing any damage or injury.

    Reference: Oral/written assessment question 75

    Question 3

    If you suspect a load sensor or limit switch is not functioning correctly, what action would you take? Answer Cease operation, report relevant personnel and await advice regarding action.

    Reference: Oral/written assessment question 81

    Practical session

    Demonstrate the role of limit switches and point out the common locations of these switches. Demonstrate how the limits work by slowly running each motion into the limit activation point. Trainers notes

    SECTION 8

    LOAD/RADIUS INDICATORS Points for trainer

    Explain to the trainee the importance of the load movement indicators and load weight indicators being in correlation with radius indicators. These devices must be accurate and correct for self-erecting tower crane operation.

    Ensure the trainee understands the term operating radius. Questions for trainee/s

    Question 1

    How often should the load mass (weight) indicator be calibrated? Answer Every six months or by picking up a known weight in accordance with the manufacturers specifications.

    Reference: Oral/written assessment question 97

  • Page 9

    Practical session

    Show the trainee the location of load radius indicator both electronic and mechanical where applicable. Show the trainee the connection between the load chart and the load radius indicators. Trainers notes

    SECTION 9

    BRAKES Points for trainer

    Explain to the trainee the importance of checking braking systems before starting operation. Inform the trainee on the procedure where any slippage or malfunction of braking systems is detected.

    Practical session

    Show the trainee the location of braking systems for the crane used in the training. Trainers notes

    SECTION 10

    SITE/JOB PLANNING Points for trainer

    Explain to the trainee the importance of rules and procedures for industry and how they relate to the trainees particular area of work.

    Explain to the trainee the responsibilities for crane operators and crane crews. Explain to the trainee the importance of understanding this section as this information relates to the

    occupational health and safety (OHS) requirements for industry.

    Explain to the trainee the importance of implementing an operational plan before work commences. Practical session

    Perform an onsite hazard assessment of the worksite with the trainee. With the trainee, draw up an operational plan for the particular crane operation.

  • Page 10

    Questions for trainee/s

    Question 1

    List four job and/or site procedures that should be considered before you set up a self-erecting tower crane?

    Answers -

    Job requirements Priorities Workplace rules Specific site procedures Identify hazards Hazard control measures Site specific induction Lifting plans including lifting radii requirements Emergency procedures

    Reference: Oral/written assessment question 12

    Question 2

    List six hazards that would need to be taken into account in your crane set up plan? Answers -

    Powerlines Trees Surrounding structures Overhead service lines (steam, gas, fuel lines) Underground services (phone, gas, power, drainage, sewage) Dangerous goods/hazardous substances Weather conditions Personnel working around the crane or near the counterweight slewing arc of the crane Obstructions (scaffolding, ladders, excavations, stored materials and other plant) Other equipment (cranes, piling rigs, forklifts, elevating work platforms) Facilities (office, amenities and lunch rooms) Soil conditions eg recently filled trenches Inadequate lighting for night operations.

    Reference: Oral/written assessment question 13 Question 3

    List five methods of reducing hazards on site. Answers -

    Identify/detect all site hazards Use barriers Use warning signs Utilise PPE for crane personnel Use spotters Use traffic control Use risk assessment processes Utilise hoardings and overhead gantries Implement adequate lighting for night operations Use visual identification on powerlines (eg tiger tails) Ensure awareness of public safety requirements Obtain relevant information (material safety data sheets, expert advice from councils and statutory

    authorities)

    Correct siting of crane. Reference: Oral/written assessment question 14

  • Page 11

    Question 4

    What precautions must be observed when working near powerlines? List four precautions. Answers

    Never work closer than the minimum distance specified in AS2550.1 or State regulations Ensure the crane is correctly earthed Barricades are erected around the work area and crane base for public safety PPE to be utilised Traffic signs/cones and barricades should be placed around the work area Follow procedures in AS2550.1.

    Reference: Oral/written assessment question 15 Question 5

    What is the minimum distance any part of a crane or load is allowed to approach live electrical parts? Answer Relevant distances must be obtained from State authority regulations.

    Note: Assessors must ensure that the applicant is aware of State authority regulations

    Reference: Oral/written assessment question 16 Question 6

    List five essential procedures, which must be followed if the crane was to come into contact with the powerlines?

    Answers

    Try to move the crane away from the conductors using the crane cabin/remote controls. Warn all other people nearby. Remain in the crane cabin until power is disconnected. If it becomes essential to leave the crane cabin (if applicable) or the immediate vicinity of the crane,

    jump clear as far away from the crane as possible and avoid touching the crane and the ground at the same. When moving away from the crane, shuffle or hop.

    Machine checked prior to future use. Reference: Oral/written assessment question 17

    Question 7

    A person dogging a load puts a hand on the hook and receives an electric shock. What would be your initial action and what would you do to ensure the hazard is investigated?

    Answers

    If possible, lift the hook clear of the person dogging the load to break contact with the earth. Follow relevant first aid procedure, as required. If required, get somebody to assist. Report the hazard to an authorised person. Report the hazard to the authorities.

    Reference: Oral/written assessment question 18

    Question 8

    Why is it important to consult with relevant workplace personnel and OHS officers before commencing work on sites?

    Answer To ensure that the operator is aware of any workplace site rules and procedures.

    Reference: Oral/written assessment question 22 Question 9

    What is the importance of having workplace emergency procedures? Answer To lay out a sequence that should be followed in case of an emergency.

    Reference: Oral/written assessment question 23

  • Page 12

    Question 10

    What must be provided for the crane working at night or in a darkened area? Answer There should be sufficient lighting over the whole work area.

    Reference: Oral/written assessment question 27

    Question 11

    In the case of an emergency, why is it important to communicate with the person dogging the load prior to leaving the crane?

    Answers

    To be made aware of any areas that be unsafe to pass. To be advised of the nature of the emergency. To ensure that someone is aware that the crane operator is making their way down to a predesignated

    muster point.

    To be advised if it is safer to stay in crane cabin until the emergency passes. Reference: Oral/written assessment question 31

    Question 12

    What is the importance of taking lighting of the workplace into account when planning your job? Answers

    To make sure work can be undertaken safely. To ensure lighted access and exit locations for emergency situations. To make sure adequate natural lighting or artificial lighting is provided to work safely under all

    conditions.

    Reference: Oral/written assessment question 32

    Practical session

    Show the trainee the pre-set up/assembly inspection requirements for the tower crane on arrival to the worksite for the first time. Included in this list is other information that must be sourced before operation of the tower crane.

    Check the site plan for working radii at given locations from the self-erecting tower crane. Check the self-erecting tower crane outrigger pad area for proper bearing and adequate packing in

    accordance with the manufacturers recommendation.

    Identify the maximum free-standing height of the self-erecting tower crane for the particular worksite.

    Obtain the manufacturers manual and daily operational logbook. Familiarise yourself with the manufacturers manual before operating.

    Check for engineers compliance certificate for the crane standing. Check for commissioning tests for the crane standing. Check for a dedicated safe operating area for the operator.

    Reference: Performance assessment section A

    Trainers notes

  • Page 13

    SECTION 11

    MAINTENANCE PROCEDURES Points for trainer

    Explain to the trainee the importance of proper maintenance procedures for the crane operation. Explain to the trainee the maintenance procedures for the particular crane used in the training. Explain to the trainee that all guards must be in place to restrict personnel from moving and rotating

    parts.

    Questions for trainee/s

    Question 1

    Why is it important to separate defective equipment? Answer To eliminate the possibility of further use of unsafe equipment.

    Reference: Oral/written assessment question 38

    Practical session

    Show the trainee the lubrication points on the crane; explain how often these points need to be greased. Trainers notes

    SECTION 12

    PRE-OPERATIONAL Points for trainer

    Put emphasis in regards to the trainees obligations in performing pre-operational checks and inspections to ensure the self-erecting tower crane is ready to operate in a safe condition.

    Review this section to ensure these points are covered as this section relates also to the performance assessment.

    Before starting the tower crane ensure all motion controls are disabled or in the neutral brake on position before turning on the main switch or power.

    Perform a test of all motion controls, brakes and limit switches before operation. Questions for trainee/s

    Question 1

    Why should the maintenance service logbook be used? Answer To record an accurate account of all services, maintenance and repairs of the self-erecting tower crane.

    Reference: Oral/written assessment question 1

    Question 2

    If you found a defect in one of the main controls that would place the crane and/or personnel at risk, what would you do?

    Answers

    Secure area and the machine and report to an authorised person. Ensure the machine is repaired before re-commencing work.

    Reference: Oral/written assessment question 2

  • Page 14

    Question 3

    On checking the tower/mast, you notice a loose bolt at one of the tower/mast connections. What action should you take?

    Answer Immediately stop work and contact an authorised person for a complete inspection of all tower/mast bolts and pins.

    Reference: Oral/written assessment question 3

    Question 4

    On a pre-inspection, you discover the gearbox is leaking oil. What action should you take? Answer tag the machine and report the defect to the supervisor or authorised person before commencing operation.

    Reference: Oral/written assessment question 4

    Question 5

    What action would you take if the crane is discovered to be out of level during a pre-operational check? Answers

    Check the screw jacks and footings Check ground conditions Check for structural damage to stabiliser/outrigger components

    Reference: Oral/written assessment question 6

    Question 6

    On checking the control panel you notice water in and around the panel. What action would you take? Answer Tag the machine and report to the supervisor or authorised person.

    Reference: Oral/written assessment question 7

    Question 7

    How do you ensure the self-erecting tower crane level? Answer By checking the inbuilt level gauge fitted to the self-erecting tower crane or by using a spirit level on the base section.

    Reference: Oral/written assessment question 8

    Question 8

    You notice loose and flaking paint on the mast of the crane. What action would you take? Answer Cease operation, tag the machine and immediately report to the supervisor or authorised person to arrange for an inspection of job welds for damage and wear.

    Reference: Oral/written assessment question 10

    Question 9

    You noticed that one of the job section connection pins was loose, what would you do? Answer immediately stop work, tag the machine and contact and authorised person for a complete inspection of all pins.

    Reference: Oral/written assessment question 33

    Question 10

    When interference (tampering) is identified, what action must be taken? Answer Tag the machine and report to an authorised person or supervisor.

    Reference: Oral/written assessment for cranes question 51

    Practical session

    Demonstrate the use of the service logbook for the particular type of self-erecting tower crane used for the training.

    Reference: Performance assessment section B

    Demonstrate the pre-operational checks for the particular type of self-erecting tower crane used for training. Checks include:

    Visually check for any maintenance personnel or servicemen working on or near the self-erecting tower crane.

    Ensure there are no safety tags on the main isolation switch.

  • Page 15

    Inspect the travel mechanism and bogies. Check for oil leaks on slewing platform or on the ground. Inspect the travel limits. Check that the counterweights are in place and secure. Inspect the slew mechanism. Check that the tower bolts are secure. Inspect for any structural damage to the mast or tower. Identify any structural damage to the crane jib or structure. Inspect access ladders and kick plates (cabin type). Access to the cabin (if applicable) is unobstructed. Disable weather vane mode. Inspect outrigger footings for adequate bearing. Connect pendant control (where applicable). Check that outrigger locking pins are in place. Check that limits and all governors are in place.

    Reference: Performance assessment section C

    Demonstrate the checks that should be made before the self-erecting tower crane is started. Checks include:

    Ensure barricades are in position around the counterweight slewing arc. Perform a visual check of the electrical cabinet and electrical system. Perform a visual check of the power supply. Examine all wire ropes, anchorages, splices and hooks. Check all oil levels eg hydraulic. Inspect the rope drums. Examine all brake mechanisms. Ensure there is adequate lubrication on all moving and rotating parts. Check the communication systems is operational. Ensure the rated capacity and manufacturers data plate is on the crane. Check the load radius indicator is in place. Check the load chart is in place. Ensure the fire extinguisher is present. Visual check of all mechanical equipment.

    Reference: Performance assessment section D

    Demonstrate the checks that should be made after the self-erecting tower crane is energised or started. Checks include:

    Start up the self-erecting tower crane as per the manufacturers instructions Emergency stop switch is operational Check wind gauge is operating correctly Communication system is operational The back up signalling system is operational Travel brakes (rail mounted) Horn/lights/drive indicator Clear vision from cabin All gauges are in correct operating ranges Radius indicator Load moment indicator Load indicator/weight gauge Slew brake/lock/pin

  • Page 16

    Hoist brake tested Trolley brake tested Maximum radius limit tested Minimum radius limit tested Hoist limit tested Warning systems/devices checked for correct operation

    Reference: Performance assessment section E

    Trainers notes

    SECTION 13

    CRANE OPERATION Points for the trainer

    Review this section to ensure these points are covered as this section relates to the performance assessment.

    Explain to the trainee the responsibilities of controlled load movement when operating the tower crane. Explain to the trainee that excessive wind speeds can restrict or abate crane operations. Wind speeds for

    in service operations are specified by the manufacturer and can be measured by an on-board anemometer.

    Ensure the trainee understands the limits of operation such as slewing, radii and load limits. Inform the trainee on worked near radio transmission towers as the crane can become charged thereby

    heating up certain components such as lifting slings.

    Explain to the trainee the aspects of cabin controlled and remote controlled operation. In cabin controlled operation the operator is an integral part of the crane with the operator being on board and sensing all movements whereas the remote control operation deprive the operator of any feel of the crane movements.

    Inform the trainee on keeping a watchful eye in all crane movements where possible. If the operator has to talk to somebody all crane motions must stop until full attention is back on the crane movements.

    Questions for trainee/s

    Question 4

    An outrigger pad sinks when lifting a load on the self-erecting tower crane. What immediate action should be taken?

    Answer Lower the load, assess the situation and seek assistance.

    Reference: Oral/written assessment question 52

    Question 5

    What is the maximum wind speed that self-erecting tower cranes can work in? Answer As per manufacturers recommendations

    Reference: Oral/written assessment question 53

    Question 6

    When crane operations are effected by extreme winds what should you do? Answers

    Lower the load to the ground Put counterweight to the wind Shut the self-erecting tower crane down as per the manufacturers instructions.

    Reference: Oral/written assessment question 55

  • Page 17

    Question 7

    If you heard abnormal noises coming from the crane what would you check? Answer Check all lifting gear, running gear, structural and mechanical components.

    Reference: Oral/written assessment question 56

    Question 8

    If any signals are observed through warning lights, cut outs or alarms, what actions would you take to have the problem rectified?

    Answer Identify the problem and take appropriate corrective action.

    Reference: Oral/written assessment question 57

    Question 9

    The crane will hoist up but will not hoist down. What action should be taken? Answer Identify the problem and take appropriate corrective action. A competent person may be required to assist or the load may need to be manually lowered with assistance.

    Reference: Oral/written assessment question 58

    Question 10

    What qualification must be held by a person directing a load out of view of the self-erecting tower crane operator?

    Answer A doggers certificate.

    Reference: Oral/written assessment question 60

    Question 11

    If you heard a loud noise or felt vibration coming from the jib section, what would do? Answer Lower the load, cease operation immediately and notify the person dogging the load. Have an inspection carried out to identify whether damage has occurred during the lift.

    Reference: Oral/written assessment question 63

    Question 12

    What hazards exist when using steel ladders or crane towers in wet weather? Answer The tower access ladder will be slippery and it would be easy for the operator to slip and fall.

    Reference: Oral/written assessment question 65

    Question 13

    During operation of the tower crane, electrical power failure/fault occurs. What would you do? Answer Communicate with the person dogging the load and advise of the problem for rectification.

    Reference: Oral/written assessment question 67

    Question 14

    Why is it important to have the jib head positioned correctly over the hook and load? Answer To reduce the risk of overloading or collapsing the crane and to precent the load from swinging on the lift.

    Reference: Oral/written assessment question 70

    Question 15

    Can you use the jib of a self-erecting tower crane as a ladder to access a worksite or as a work platform? Explain your answer.

    Answer No. Under no circumstances must the jib of a self-erecting tower crane be used as a method of access or as a work platform because it is unsafe and is not designed as an access route.

    Reference: Oral/written assessment for cranes question 73

    Question 16

    Are you permitted to allow a person to ride upon the lifting hook, sling attachment or suspended load? Explain your answer.

    Answer No. A person can only be suspended by a self-erecting tower crane in a suitable work box specifically designed to incorporate the necessary features.

    Reference: Oral/written assessment question 74

  • Page 18

    Question 17

    What would you do if you heard a sudden loud noise and felt a vibration coming from an area lower down on the base section of the tower crane?

    Answer Lower the load, immediately cease operation and communicate with the person dogging the load. Organise an inspection of the crane base and tower to identify whether some form of heavy plant has struck the crane. Check for damage and report to an authorised person.

    Reference: Oral/written assessment question 76

    Question 18

    List four precautions that must be taken when long travelling a self-erecting tower crane? Answers

    Prior to operating, ensure that there are no obstructions or personnel on the rails. Ensure that the working radius has been calculated prior to travelling. When travelling the self-erecting tower crane, siren and flashing lights must be operational. Ensure that the load is controlled by the person dogging the load with the use of taglines where

    necessary.

    Ensure that people pushers or wheel guards are in place. Travel at minimum speeds. Ensure that the travelling self-erecting tower crane is mechanically stopped prior to reaching end

    stops.

    Reference: Oral/written assessment question 77

    Question 19

    If you detected a defect in one of the main controls, who would you report this to for rectification and who would responsible for the rectification work?

    Answer To an authorised person or supervisor, who would then contact a competent person for corrective action.

    Reference: Oral/written assessment question 78

    Question 20

    If the hook has landed on the ground, causing a slack rope, what would the correct procedure when re-spooling the rope?

    Answer The weight of the hook or overhauling weight or applied weight must be on the rope when re-spooling. This can be achieved by luffing the jib or telescoping the angled jib outwards.

    Reference: Oral/written assessment question 79

    Question 21

    If the self-erecting tower crane is located near aircraft traffic zones, what action must be taken? Answers

    A red warning light should be installed at the upper most point of the crane. Directions from airport authority may state operational hours for the crane operation. Information from the airport authority may state maximum jib elevations for any luffing type

    operations.

    Reference: Oral/written assessment question 82

    Question 22

    If a heavy load is to be lifted what precautions would you take to work within a given radius? Answer Ensure the jib or boom deflection is taken into consideration. Adjust boom angle or trolley radius to maintain vertical lifting application.

    Reference: Oral/written assessment for cranes question ?

    Media application

    Use a whiteboard and make up a list of hazardous occurrences that could effect crane operation. Practical session

    Using close supervision allow the trainee to control the motions of the crane. Note: This must be performed under strict close supervision.

    Demonstrate to the trainee the process of catching the hook. (Use a scale model or other device.)

  • Page 19

    Demonstrate to the trainee the process of crane operation addressing the points below. Load secure Load correctly slung Conduct trial lift Lift conforms with load chart Jib positioned over load correctly Hoist load Move load Lower load Luff up (where applicable) Luff down (where applicable) Slew load Telescope boom Travel with load All movements smooth/adequate speed Tag line used Signals interpreted correctly Load placed correctly on dunnage Load unslung Raise hook and attachment to safe height.

    Reference: Performance assessment section J

    Trainers notes

    SECTION 14

    LOADS AND SELF-ERECTING TOWER CRANES Points for trainer

    Explain to the trainee how the operating radius is displayed on the crane. Show the trainee the methods of determining the load mass of various materials and loads. Show the trainee how multiple fall hoist reeving is applied. Explain to the trainee the dangers associated with snigging and dragging loads. Sling and lift and load slightly off the ground and show the trainee the checks that must be performed

    before lifting further.

    Explain to the trainee the application of lifting a personnel lifting box with personnel aboard. Show the trainee how to read and interpret a load chart on the crane. Explain the deductions required to

    calculate the net capacity. Deduct items such as the load mass, the weight of the hook block and attachments such as spreader beams and slings. Where specified the weight of the hoist rope may be deducted.

  • Page 20

    Questions for trainee/s

    Question 1

    Explain how the hook radius is indicated on the crane? Answer The hook radius is displayed on the control device and may also be displayed on flags or signs installed on the underside of the jib or as per specific crane design.

    Reference: Oral/written assessment question 5

    Question 2

    How do you determine the rated capacity if the self-erecting tower crane? Answer By checking the load chart plate fitted to the crane or control unit.

    Reference: Oral/written assessment question 9

    Question 3

    Who should be involved in the process of assessing the load before lifting? Answer A person dogging a load and the crane operator or rigger if applicable.

    Reference: Oral/written assessment question 29

    Question 4

    Who would be responsible for checking all lifting gear for example chains and slings? Answer The crane operator in conjunction with the person dogging the load.

    Reference: Oral/written assessment question 37

    Question 5

    How do you know when the multiple load falls are required? Answer As per the load cart specifications.

    Reference: Oral/written assessment question 44

    Question 6

    Give three different ways in which the mass (weight) of a load can be determined? Answers

    Delivery dockets Public weighbridge certification The manufacturers information Weight may appear on the load itself Calculate or estimate.

    Reference: Oral/written assessment for cranes question ?

    Question 7

    State three reasons why you are not permitted to drag or snig a load. Answers

    Load swing may occur The load may topple Damage to the sling may occur Structural damage to the crane by exceeding the rated capacity of the crane may occur.

    Reference: Oral/written assessment question 66

    Question 8

    With the load suspended just off the lifting surface, what three observations and checks need to be made? Answers

    The load is securely slung. All crane equipment is functioning correctly. Stabiliser/outrigger footing is secure.

    Reference: Oral/written assessment question 69

  • Page 21

    Question 9

    List six requirements that would permit you to lift personnel using the crane. Answers

    The unit must be specifically designed as a workbox. Tare weight of the workbox must be displayed on the box. The maximum number of occupants allowed in the box must be displayed on the box. The maximum mass that can be carried in kilograms must be displayed on the box. The identification reference must be displayed on the workbox. The workbox must not contain more than three persons, one of who must be competent in crane

    signals.

    The workbox must be in a safe working condition. Slings shall be permanently attached to the workbox by locked shackles or other similar means. The workbox must have a provision for attachment of safety harnesses for personnel. The workbox must be painted in high visibility colours. Where an access door is fitted, it shall open inwards and be provided with means to secure the door. The workbox is only to be used to lift persons and their equipment. The crane lifting the workbox shall be fitted with a safety hook. The crane lifting the workbox shall be equipped with controls that return to the neutral position when

    released the motion to stop.

    The crane lifting the workbox shall be equipped with power lowering. The crane lifting the workbox shall be equipped with a lockout control to prevent free-fall of the

    workbox and its contents.

    The crane lifting the workbox shall be fitted with an up limit switch on the hoist motion. The crane lifting the workbox shall be fitted with a down limit switch if the workbox is to be lowered

    below the cranes supporting surface.

    The crane operator shall remain at the controls of the crane when the workbox is suspended with personnel.

    The crane operator shall ensure that at the maximum radius of the task to be performed the crane has a minimum rated capacity of 1000kgs.

    The crane operator shall ensure that when the jib is at the maximum radius for the task to be performed, the rated capacity for the crane in this condition, when divided by two, is equal or greater than the total load of the workbox and its contents.

    The crane operator shall ensure that they have a means of communication with any person in the workbox.

    Reference: Oral/written assessment question 83

    Question 10

    State three essential items of information you would expect to obtain from a load chart. Answers

    The mass of the hook block The winch line pull measure in tonnes or kilograms The rated capacity for an applied crane configuration Multiple rope fall capacities (eg two fall and four fall hook block configurations). Note: Other answers may also be considered applicable.

    Reference: Oral/written assessment question 123

    Question 11

    List three items that need to be deducted from the (ie stated rated) capacity of a crane to determine its payload ie the load the crane can lift.

    Answers

    The mass of the hook block. The mass of any lifting attachments such as spreader beams, ladies or kibbles. The mass of the lifting slings.

    Reference: Oral/written assessment question 124

  • Page 22

    Question 12

    When dealing with a crane load chart, what is meant by the term operating radius? Answer The operating radius is the measurement from the cranes centre of rotation to the vertical freely suspended hoist line.

    Reference: Oral/written assessment question 125

    Question 13

    When the precise reading is between load chart capacities, do you increase or decrease the rated capacity?

    Answer Use the lower rated capacity.

    Reference: Oral/written assessment question 127

    Question 14

    If the jib is luffed up to a 10 degree angle does this alter the rated load capacities of the crane? Refer to load chart Q.

    Answer Yes

    Reference: Oral/written assessment question 128

    Question 15

    If the jib is in a folded configuration, where only the base section of the jib is available, does this alter the rated capacities of the crane compared to using a fully extended jib section? Refer to load chart Q.

    Answer Yes

    Reference: Oral/written assessment question 129

    Question 16

    Refer to load chart Q

    A self-erecting tower crane with load chart Q is set up as follows: Main jib length 30.00 metres Working radius 21.00 metres Work area 360 degrees Fitted with a two-fall hook block Jib fully extended

    i. What is the maximum load that can be raised on the hook block at the specified radius?

    ii. If the hook block is re-reeved to a four-part configuration, what is the new capacity at the same radius as question i?

    iii. What is the maximum capacity of the four-fall hook block configuration? (Do not take radius into consideration.)

    Answer Refer to load chart Q: 30.00 metre jib at a 21.00 metre radius with the jib fully extended using a two-fall hook block configuration.

    i. Rated capacity (SWL): 1530kgs

    Hook mass deductions: 120kgs

    Net load: 1410kgs

    ii. Rated capacity (SWL): 1480kgs

    Deductions: 205kgs

    Net load: 1275kgs

    iii. Rated capacity (SWL): 4000kgs

    Deductions: 205kgs

    Net load: 3795kgs

    Reference: Oral/written assessment question 133

  • Page 23

    Question 17

    Refer to load chart Q

    A self-erecting tower crane with load chart Q is set up as follows: Main jib length 30.00 metres Working radius 29.00 metres Work area 360 degrees Fitted with a four-fall hook block Jib fully extended

    i. What is the maximum load that can be raised on the hook block at the specified radius?

    ii. If the hook block is re-reeved to a two-part configuration, what is the new capacity at the same radius as in question i?

    iii. What is the maximum capacity of the two-fall hook block configuration? (Do not take radius into consideration.)

    Answer Refer to load chart Q: 30.00 metre jib at a 29.00 metre radius with the jib fully extended using a four-fall hook block configuration.

    i. Rated capacity (SWL): 1000kgs

    Hook mass deductions: 205kgs

    Net load: 795kgs

    ii. Rated capacity (SWL): 1050kgs

    Deductions: 120kgs

    Net load: 930kgs

    iii. Rated capacity (SWL): 2000kgs

    Deductions: 120kgs

    Net load: 1880kgs

    Reference: Oral/written assessment for cranes question ?

    Question 18

    Refer to load chart Q

    A self-erecting tower crane with load chart Q is set up as follows: Main jib length 30.00 metres Working radius 13.00 metres Work area 360 degrees Fitted with a four-fall hook block Jib folded

    i. What is the maximum load that can be raised on the hook block at the specified radius?

    ii. If the jib is unfolded and fully extended what is the new capacity at the same radius as question i?

    iii. What is the maximum capacity of the four-fall hook block configuration? (Do not take radius into consideration.)

    Answer Refer to load chart Q: 30.00 metre jib at a 13.00 metre radius with the jib folded using a four-fall hook configuration.

    i. Rated capacity (SWL): 3300kgs

    Hook mass deductions: 205kgs

    Net load: 3092kgs

  • Page 24

    ii. Rated capacity (SWL): 2380kgs

    Deductions: 205kgs

    Net load: 2175kgs

    Rated capacity (SWL): 4000kgs

    Deductions: 205kgs

    Net load: 3795kgs

    Reference: Oral/written assessment for cranes question ?

    Question 19

    Refer to load chart Q

    A self-erecting tower crane with load chart Q is set up as follows: Main jib 24.00 metres Working radius 21.00 metres Work area 360 degrees Fitted with a two-fall hook block Jib fully extended

    i. What is the maximum load that can be raised on the hook block at the specified radius?

    ii. If the hook block is re-reeved to a four-part configuration, what is the new capacity at the same radius as question i?

    iii. What is the maximum capacity of the two-fall hook block configuration? (Do not take radius into consideration.)

    Answer Refer to load chart Q: 24.00 metres jib at a 21.00 metre radius with the jib fully extended using a two-fall hook block configuration.

    i. Rated capacity (SWL): 1670kgs

    Hook mass deductions: 120kgs

    Net load: 1550kgs ii. Rated capacity (SWL): 1720kgs

    Deductions: 205kgs

    Net load: 1515kgs iii. Rated capacity (SWL): 2000kgs

    Deductions: 120kgs

    Net load: 1880kgs

    Reference: Oral/written assessment for cranes question ?

    Question 20 Refer to load chart Q

    A self-erecting tower crane with load chart Q is set up as follows: Main jib length 24.00 metres Working radius 23.00 metres Work area 360 degrees Fitted with two-fall hook block Jib fully extended

    i. What is the maximum load that can be raised on the hook block at the specified radius?

    ii. If the hook is re-reeved to a four-part configuration, what is the new capacity at the same radius as question i?

    iii. What is the maximum capacity if the four-fall hook block configuration? (Do not take radius into consideration.)

  • Page 25

    Answer Refer to load chart Q: 24.00 metre jib at a 23.00 metre radius with the jib fully extended using a two-fall hook block configuration.

    i. Rated capacity (SWL): 1500kgs

    Hook mass deductions: 120kgs

    Net load: 1380kgs

    ii. Rated capacity (SWL): 1550kgs

    Deductions: 205kgs

    Net load: 1345kgs iii. Rated capacity (SWL): 4000kgs

    Deductions: 205kgs

    Net load: 3795kgs

    Reference: Oral/written assessment question ?

    Question 21

    Refer to load chart Q

    A self-erecting tower crane with load chart Q is set up as follows: Main jib length 24.00 metres Working radius 13.00 metres Work area 360 degrees Fitted with a four-fall hook block Jib folded

    i. What is the maximum load that can be raised on the hook block at the specified radius?

    ii. If the jib is unfolded and fully extended, what is the new capacity at the same radius as question i?

    iii. What is the maximum capacity of the four-fall hook block configuration? (Do not take radius into consideration.)

    Answer Refer to load chart Q: 24.00 metre jib at a 13.00 metre radius with the jib folded using a four-fall hook block configuration.

    i. Rated capacity (SWL): 3300kgs

    Hook mass deductions: 205kgs

    Net load: 3095kgs ii. Rated capacity (SWL): 3180kgs

    Deductions: 205kgs

    Net load: 2975kgs iii. Rated capacity (SW): 4000kgs

    Deductions: 205kgs

    Net load: 3795kgs Reference: Oral/written assessment question ?

    Question 22 Refer to load chart Q

    A self-erecting tower crane with load chart Q is set up as follows: Main jib length 24.00 metres Working radius 14.00 metres Work area 360 degrees Fitted with a four-fall hook block Jib folded

  • Page 26

    i. What is the maximum load that can be raised on the hook block at the specified radius?

    ii. If the jib is unfolded and fully extended, what is the new capacity at the same radius as question i?

    iii. What is the maximum capacity of the four-fall hook block configuration? (Do not take radius into consideration.)

    Answer Refer to load chart Q: 24.00 metre jib at a 14.00 metre radius with the jib folded using a four-fall block configuration.

    i. Rated capacity (SWL): 3300kgs

    Hook mass deductions: 205kgs

    Net load: 3095kgs ii. Rated capacity (SWL): 3180kgs

    Deductions: 205kgs

    Net load: 2975kgs iii. Rated capacity (SWL): 4000kgs

    Deductions: 205kgs

    Net load: 3795kgs Reference: Oral/written assessment question 134

    Media application

    Use the load chart Q to explain the load chart applications required for written assessment. Use a variety of other load charts relating to different self-erecting tower cranes to assess the trainees

    understanding of load chart interpretation.

    Practical session

    Show the trainee how to lift loads with the crane, working within the rated capacity specified by the crane manufacturer.

    Explain to the trainee how the radius indicator is displayed. Show the trainee where the load radius is displayed.

    Explain the load chart and its capabilities to the trainee using different jib angles/configurations. Reference: Performance assessment section L

    Trainers notes

    SECTION 15

    SPECIAL OPERATIONS Points for trainer

    Explain to the trainee the regulations regarding multiple crane lifts. Explain to the trainee the system of climbing the crane where applicable. Questions for trainee/s

    Question 1

    How do you lower the load in the event of a power failure? Answer As per manufacturers recommendations.

    Note: This operation differs from crane to crane. Operators must know their particular crane and be able to describe to the assessor exactly how it is done. Operators have a responsibility to ensure that they can emergency lower on any self-erecting tower crane that they operate. It is essential for the applicant to know this. If not, then they should not be assessed as competent.

    Reference: Oral/written assessment question 96

  • Page 27

    Question 2

    Is it permitted to carry out a multiple crane lift with a self-erecting tower crane and another crane? Answer No.

    Reference: Oral/written assessment question 98

    Question 3

    Where is the information found to show how to climb the self-erecting tower crane (if applicable) by inserting extra tower sections?

    Answer In the manufacturers manual for the self-erecting tower crane.

    Reference: Oral/written assessment question 99

    Media application

    Show a video or scale model to the trainee regarding climbing of the crane where applicable. Practical session

    Show the trainee how to lower the hook manually using manual lowering techniques in case of an emergency situation.

    Describe to the trainee how to climb (jack the crane vertically) by demonstrating the procedure appropriate to the self-erecting tower crane, where applicable.

    Show the trainee how to unfold and fold the jib on a self-erecting tower crane by demonstrating the procedure appropriate to the tower crane, where applicable.

    Reference: Performance assessment section N

    Trainers notes

    SECTION 16

    SHUTDOWN CRANE Points for trainer

    Explain to the trainee the shutdown procedures for overnight out of service requirements. Ensure the hook is positioned appropriately for out of service conditions. Face the crane jib downwind (wind at the back of the crane) on shutdown before engaging weathervane

    mode.

    Questions for trainee/s

    Question 1

    Can any load remain suspended from the hook following shut down or when the crane is unattended? Explain your answer.

    Answer No, this is unsafe. If during the course of a lift the crane operator must leave the controls, the load should be placed on the ground with the crane shut down in the prescribed manner as per the manufacturers instructions.

    Note: No operator, no load.

    Reference: Oral/written assessment question 85

  • Page 28

    Question 2

    How should a self-erecting tower crane be left unattended overnight? Answers

    Load to be removed Jib folded to manufacturers specifications Crane is weathervaned to engineers recommendations or manufacturers specifications.

    Reference: Oral/written assessment question 86

    Question 3

    What would you do with the platform access hatch (if applicable) on shut down? Answer Ensure that it is securely closed and locked with a key lock.

    Reference: Oral/written assessment question 87

    Question 4

    What must be done to the base of a travelling tower self-erecting tower crane on shut down in regards to securing the crane.

    Answers

    Ensure that the blocks are placed at the base of wheels to prevent movement of self-erecting tower crane.

    Make sure that the electric motor to the travelling wheel mechanism is isolated and locked. Reference: Oral/written assessment for cranes question ?

    Question 5

    On shutting down an electric powered self-erecting tower crane, what is an important consideration? Answer Ensure that all electric circuits are fully isolated and locked off.

    Reference: Oral/written assessment question 89

    Question 6

    If the self-erecting tower crane is to be left in free slew, why is it important that you raise the jib and hook clear of obstructions for the full 360 degrees around the crane?

    Answer When in free slew the self-erecting tower crane can paravane (spin rapidly) in a severe storm or cyclonic winds. The crane must clear surrounding buildings and other obstructions or the jib or crane may be folded down.

    Reference: Oral/written assessment question 90

    Question 7

    You are operating a self-erecting tower crane that is on a travelling base. Why is it essential that travel locks be clipped to the rails as you leave the crane?

    Answer These locks stop the self-erecting tower crane from being blown uncontrollably down the rails by strong winds.

    Reference: Oral/written assessment question 93

    Question 8

    On a self-erecting tower crane why is the trolley and hook brought in close proximity to the tower for parking?

    Answer So that the trolley-hook assembly creates less wind resistance thereby eliminating excessive forces on the outriggers and foundations.

    Reference: Oral/written assessment question 94

    Question 9

    An operational self-erecting tower crane is situated very close to a neighbouring building. The building is under the jib-slewing radius of the self-erecting tower crane. What special precautions must be undertaken to shutdown?

    Answers

    The self-erecting tower crane must not be weathervaned as a collision with the building could occur. The crane jib may be luffed up to avoid collision with the building. The self-erecting tower crane may be locked off as per the manufacturers instructions. The self-erecting tower crane may be packed up as per manufacturers specifications. Guying of the crane jib may require an engineers approval.

    Reference: Oral/written assessment question 95

  • Page 29

    Practical session

    Explain to the trainee the process of shutting down the tower crane covering these points. Ensure barricades are in position. Ensure the hook block/trolley assembly is suitably positioned for stowing as per the manufacturers

    specifications.

    Lower/retract jib in accordance with the manufacturers specifications. Slings removed. Weathervane self-erecting tower crane in accordance with the manufacturers specifications. Raise hook to maximum height. Lock and secure remote control unit. Lock and secure self-erecting tower crane. Turn the isolator switch off and secure.

    Reference: Performance assessment section M

    Trainers notes

    SECTION 17

    RULE OF THUMB AND WORKING LOAD LIMITS Points for trainer

    Explain to the trainee the rule of thumb formulae used to identify working load limits (WLL) for all sling types such as fibre, flexible steel wire rope (FSWR) and lifting chain.

    Questions for trainee/s

    Question 1

    What is the formula or rule of thumb for determining the working load limit (WLL) for an unidentified synthetic rope?

    Answer Diameter in millimetres squared = the WLL in kilograms

    Note: If unknown, the formula for fibre rope should apply or be accepted.

    Reference: Written assessment for cranes question 1

    Question 2

    Calculate the WLL for one of the following i. 12mm diameter unidentified synthetic rope

    ii. 15mm diameter unidentified synthetic rope

    iii. 20mm unidentified synthetic rope.

    Answers

    i. Diameter in mm2 = 12mm = 12 x 12 = 144kg WLL

    ii. Diameter in mm2 = 15mm = 15 x 15 = 225kg WLL

    iii. Diameter in mm2 = 20mm = 20 x 20 = 400kg WLL

    Note: if unknown, formula for fibre rope should apply or be accepted.

    Reference: Written assessment for cranes question 2

  • Page 30

    Question 3

    What is the rule of thumb formula used to calculate the WLL of a flexible steel wire rope (FSWR)? Answer Diameter in millimetres squared x 8 = the WLL in kilograms

    Reference: Written assessment for cranes question 12

    Question 4

    Calculate the WLL of one of the following: i. 15mm diameter FSWR

    ii. 20mm diameter FSWR

    iii. 25mm diameter FSWR

    Answers

    i. Diameter in mm2 x 8 = 15 x 15 x 8 = 1800kg WLL

    ii. Diameter in mm2 x 8 = 20 x 20 x 8 = 3200kg WLL

    iii. Diameter in mm2 x 8 = 25 x 25 x 8 = 5000kg WLL

    Reference: Written assessment for cranes question 13

    Question 5

    What is the rule of thumb for calculating the WLL for a grade 80 high tensile chain? Answers

    Diameter in millimetres squared x grade x 0.4 = WLL in kilograms; or Diameter in millimetres squared x 32 = WLL in kilograms

    Reference: Written assessment for cranes question 20

    Question 6

    Calculate the WLL of grade 80 high tensile chain at one of the following diameters: i. 10mm

    ii. 12mm

    iii. 15mm

    Answers

    i. Diameter in mm2 x 32 = 10 x 10 x 32 = 3200kg WLL

    ii. Diameter in mm2 x 32 = 12 x 12 x 32 = 4608kg WLL

    iii. Diameter in mm2 x 32 = 15 x 15 x 32 = 7200kg WLL

    Reference: Written assessment for cranes question 21

    Practical session

    Demonstrate to the trainee the process of identifying WLLs for a specified sling type used on the tower crane.

    Trainers notes

  • Page 31

    SECTION 18

    LOAD FACTORS Points for trainer

    Discuss with trainee the application of utilising load and reeve factors for determining actual sling ratings on lifting.

    Questions for trainee/s

    Question 1

    A sling of 2.0 tonnes WLL is reeved around a circular load. What is the sling now capable of lifting? Answer 2.0 tonnes x 0.75 load factor = 1.5 tonnes

    Reference: Written assessment for cranes question 73

    Question 2

    A sling of 8.0 tonnes WLL is reeved around a circular load. What is the sling now capable of lifting? Answer 8.0 tonnes x 0.75 load factor = 6.0 tonnes

    Reference: Written assessment for cranes question 74

    Question 3

    A sling of 4.0 tonnes WLL is reeved around a circular load. What is the sling now capable of lifting? Answer 4.0 tonnes x 0.75 load factor = 3.0 tonnes

    Reference: Written assessment for cranes question 75

    Question 4

    A sling of 6.0 tonnes WLL is reeved around a circular load. What is the sling now capable of lifting? Answer 6.0 tonnes x 0.75 load factor = 4.5 tonnes

    Reference: Written assessment for cranes question 76

    Question 5

    A sling of 5.0 tonnes WLL is reeved around a square load. What is the sling now capable of lifting? Answer 5.0 tonnes x 0.5 load factor = 2.5 tonnes

    Reference: Written assessment for cranes question 77

    Question 6

    A sling of 4.0 tonnes WLL is reeved around a square load. What is the sling now capable of lifting? Answer 4.0 tonnes x 0.5 load factor = 2 tonnes

    Reference: Written assessment for cranes question 78

    Question 7

    A sling of 3.0 tonnes WLL is reeved around a square load. What is the sling now capable of lifting? Answer 1.5 tonnes x 2.00 load factor x 0.5 reduction factor square load = 1.5 tonnes

    Reference: Written assessment for cranes question 79

    Question 8

    A sling of 1.5 tonnes WLL is used in a basket hitch around a square load. What is the sling capable of lifting now?

    Answer 1.5 tonnes x 2.00 load factor x 0.5 reduction factor square load = 1.5 tonnes

    Reference: Written assessment for cranes question 83

    Question 9

    A sling of 1.5 tonne WLL is reeved around a square load. What is the sling now capable of lifting? Answer 1.5 tonnes x 0.5 load factor = 0.75 tonnes

    Reference: Written assessment for cranes question 84

  • Page 32

    Question 10

    A lifting beam with a mass (weight) of 300kg is supported by a two legged sling shackled to the beam forming an included angle of 90 degrees at the crane hook (see diagram). Two slings are shackled to the underside of the lifting beam and vertically down to lifting eyes on a machine if mass 2500kg. What is the minimum WWl required of each of the four slings?

    Answer

    Slings between the machine and beam =

    Total weight of 2500kg divided by the load factor of 2.00 = 2500 2.00 = 1250kgs for each sling.

    The slings between the beam and hook =

    A total weight of 2800kg divided by the load factor of 1.41 (for a 90 degree included sling angle) = 2800 1.41 = 1986kg for each of the upper slings.

    Upper slings require a WWL of 1986kgs each.

    Lower slings require a WWL of 1250kg each

    Reference: Written assessment for cranes question 85

    Question 11

    If two slings are spread at an included angle of 90 degrees, what is the load factor applied to the load being lifted?

    Answer For a 90 degree included angle the load factor is 1.41.

    Reference: Written assessment for cranes question 86

    Question 12

    If two slings are spread at an included angle of 30 degrees, what is the load factor applied to the load being lifted?

    Answer For a 30 degree included angle the load factor is 1.91.

    Reference: Written assessment for cranes question 87

    Question 13

    If two slings are spread at an included angle of 60 degrees, what is the load factor applied to the load being lifted?

    Answer For a 60 degree included angle the load factor is 1.73.

    Reference: Written assessment for cranes question 88

    Question 14

    If two slings are spread at an included angle of 120 degrees, what is the load factor applied to the load being lifted?

    Answer For a 120 degree included angle the load factor is 1.00.

    Reference: Written assessment for cranes question 89

  • Page 33

    Question 15

    From the drawings below select the included angle closest to 90 degrees.

    Answer D is the correct diagram

    Reference: Written assessment for cranes question 90

    Question 16

    What reduction must be made to the WLL of a FSWR sling when it is reeved on a round load? Answer A 25 per cent reduction.

    Reference: Written assessment for cranes question 91

    Question 17

    What reduction must be made to the WLL of a FSWR sling when a basket hitch is used to cradle a square load?

    Answer A 50 per cent reduction.

    Reference: Written assessment for cranes question 92

    Question 18

    What load factor must be applied to the WLL of a FSWR sling when a basket hitch is used to cradle a square load?

    Answer Load factor of 1 is applied. The rated capacity (SWL) remains the same as the WLL.

    Reference: Written assessment for cranes question 93

    Question 19

    What safety factor must be applied to the WLL of a FSWR sling when a basket hitch is used to cradle a round load?

    Answer Load factor 2 is applied. The rated capacity (SWL) is double the WLL.

    Reference: Written assessment for cranes question 94

    Practical session

    Demonstrate to the trainee how load factors effect operations in sling application and sling configurations. Trainers notes

  • Page 34

    SECTION 19

    RULES TO FOLLOW WHEN SLINGING AND HANDLING A LOAD Points for trainer

    Describe to the trainee approved methods of utilising lifting gear and equipment. Discuss with the trainee the benefits of using tag lines for load control. Discuss with the trainee the hazards involved with stuck loads such as formwork shutters, sheet pile or

    concrete pre-cast panels.

    Explain to the trainee the hazards involved with wind affected loads such as shutters, roofing iron and cladding.

    Discuss with the trainee the application of using multiple sling arrangements and which slings are taking the load.

    Questions for trainee/s

    Question 1

    What factors should be considered when using taglines? Give at least four examples. Answers

    Weather conditions Electrical hazards Tagline change over may be required at designated point in the lift. Person holding the tagline should wear PPE. Ensure that the line is not fouled. Taglines should be held correctly. Tagline length requirement. Tagline size requirements.

    Reference: Oral/written assessment question 34

    Question 2

    When lifting concrete formwork shutters in gusting wind conditions, what measures would you ensure are undertaken to control the load?

    Answers

    Load must be attached to taglines. Shutters may be laid down and lifted horizontally with taglines attached. Operations may have to cease until wind conditions reduce sufficiently.

    Reference: Oral/written assessment question 72

    Question 3

    A long load of reinforcement steel bars is to be lifted off a truck close to the sheeted scaffolding perimeters of the site. How can the load be controlled to prevent contact and subsequent snagging with the scaffold?

    Answer The person dogging the load should control the load with a hand held tagline.

    Reference: Oral/written assessment question 62

    Question 4

    An internal lift formwork shutter to green concrete weighing two tonnes is to be lifted. The weight is taken and the shutter does not budge, what should you do?

    Answers

    Stop hoisting if the load on the crane is over two tonnes. The shutter may be jammed; this may require some levering by the formworkers. Ensure all personnel are clear of the shutter in case the shutter springs off the lift shaft wall.

    Reference: Oral/written assessment question 64

  • Page 35

    Question 5

    List three reasons why packing or dunnage is used when slinging or landing a load. Answers

    To protect the load. To facilitate the connection/disconnection. To prevent damage to lifting gear.

    Reference: Oral/written assessment question 68

    Question 6

    You have formwork shutters to lower from the top of a building when a strong wind blows up. What are the hazards?

    Answer Shutters are large in area but light in weight, therefore they could flap/spin around in the wind so will need to be secured. The wind loading with such a large surface area could destabilise the self-erecting tower crane.

    Reference: Oral/written assessment question 71

    Question 7

    Why must you pack/lag the edges/corners of sharp loads? Answer To protect load slings and lifting gear from damage.

    Reference: Oral/written assessment question 42

    Question 8

    A four legged bridle sling arrangement is attached to a rigid load. How many sling legs would be assumed to support the load?

    Answer two diagonally opposite sling legs must be capable of supporting the load.

    Reference: Oral/written assessment question 80

    Question 9

    A three legged bridle sling arrangement is attached to a rigid load. How many sling legs would be assumed to support the load.

    Answer Any two legs of the sling arrangement.

    Reference: Oral/written assessment question 81

    Question 10

    A four legged bridle sling arrangement is attached to a flexible load. How many sling legs would be assumed to support the load?

    Answer The entire four sling legs.

    Reference: Oral/written assessment question 82

    Practical session

    Demonstrate to the trainee the application of various sling loads. The loads should be lifted using different sling arrangements to cover this section.

    Trainers notes

  • Page 36

    SECTION 20

    STACKING Points for trainer

    Explain to the trainee the process of stacking loads allowing for proper clearance whilst ensuring stability of the load.

    Trainers notes

    SECTION 21

    PERSONNEL PROTECTIVE EQUIPMENT Points for trainer

    Ensure the trainee understands the requirements for personnel protective equipment (PPE) whilst operating a self-erecting tower crane.

    Trainers notes

    SECTION 22

    COMMUNICATION Points for trainer

    Converse with the trainee regarding the use of communication techniques where a dogger is used with provide signals.

    Questions for trainee/s

    Question 1

    What communication equipment can the crane operator utilise other than two-way radio? Answers

    Hand signals Whistles, hooters Light signals

    Reference: Oral/written assessment question 28

  • Page 37

    Question 2

    If given a stop signal by someone other than the person dogging the load, what would you do? Answer Stop operations immediately and await further directions.

    Reference: Oral/written assessment question 80

    Practical session

    Ensure the trainee understands and knows the applicable crane whistle signals for operation. Reference: Performance assessment section I

    Trainers notes

    SECTION 23

    FLEXIBLE STEEL WIRE ROPE Points for trainer

    Discuss with the trainee the application of wire rope usage in hoist ropes, suspension ropes and sling configurations.

    Questions for trainee/s

    Question 1

    What is the minimum allowable size FSWR for load handling purposes? Answer 5mm diameter

    Reference: Written assessment question 14

    Question 2

    What is the maximum allowable temperature that FSWR can be exposed to before it is unsafe for lifting purposes?

    Answer 950C

    Reference: Written assessment question 15

    Question 3

    What is the formula that indicates the maximum amount of broken wires permitted in FSWR? Answer Where 10 per cent of the total numbers of wires are broken in one rope lay or in eight diameters of rope.

    Reference: Written assessment question 16

    Question 4

    Using the formula for maximum amount of broken wires in FSWR, work out one of the following: i. The construction of the rope is 6/19 and 12mm diameter.

    ii. The construction of the rope of is 6/24 and 20mm diameter.

    iii. The construction of the rope is 6/36 and 54mm diameter.

    Answers

    i. 6/19 = 6 x 19 = 114 wires

    10% x 114 = 11.4 wires

    Therefore, in one rope lay 11 wires.

    Rope length to inspect = 12mm x 8 = 96mm

  • Page 38

    ii. 6/24 = 6 x 24 = 144 wires

    10% x 144 = 14.4 wires

    Therefore, in one rope lay 14 wires.

    Rope length to inspect = 20mm x 8 = 160mm

    iii. 6/36 = 6 x 36 = 216 wires

    10% x 216 = 21.6 wires

    Therefore, in one rope lay 21 wires.

    Rope length to inspect = 54mm x 8 = 432mm

    Reference: Written assessment for cranes question 17

    Question 5

    What is meant by the term core slippage? Answer Core slippage occurs when the outer wire strands slip over the inner core of the opposite lay.

    Reference: Written assessment for cranes question 18

    Question 6

    What will condemn a FSWR sling from safe use? List at least six defects. Answers

    Kink or fractures from bending or reeving Crushed or jammed strands Damaged splice Exposure to high temperatures Core collapse Bird-caging - where the strands loosen from their proper tight lay Stretched or overloaded High stranding Corrosion loose and springy wires indicate serious corrosion Knotted sections Wear caused by badly maintained or aligned sheaves The number of broken wire exceeding allowable limit.

    Reference: Written assessment for cranes question 19

    Question 7

    Explain the use and advantages of a wire rope thimble? Answer Thimbles are designed to protect the load bearing area inside the crown of the eye from chafing and distortion and to form a hard eye in a rope.

    Reference: Written assessment for cranes question 50

    Question 8

    Explain the reason for using swaged aluminium alloy fitting or a thimble fitting. Answer to form an eye splice or thimble eye in a wire rope (FSWR).

    Reference: Written assessment for cranes question 70

    Question 9

    What are the most obvious indications of a defective swage fitting? Answers

    The tail of the FSWR has slipped inside the swage fitting. The steel collar thimble is loose on the rope. The fitting is loose. There is a broken wire at either end of the swaged fitting.

    Reference: Written assessment for cranes question 71

  • Page 39

    Practical session

    Using a number of defective slings, have the trainee determine the defects that cause condemnation of a FSWR sling.

    Trainers notes

    SECTION 24

    WEDGE ROPE SOCKETS

    Points for trainer

    Converse with the trainee regarding the proper use of wedge sockets. Questions for trainee/s

    Question 1

    From the diagrams below, select the correct methods of reeving a hoist rope in a wedge rope socket.

    Answer Correct answer is D or E.

    Reference: Written assessment for cranes question 48

    Question 2

    Are you permitted to use wire rope (bulldog) grips to connect two lengths of wire rope for lifting purposes? Explain your answer.

    Answer No, the wire rope could crush or pull through the bulldog grip.

    Reference: Written assessment for cranes question 49

    Question 3

    Should the wedge protrude outside the narrow end of the socket fitting? (As shown in the diagram.)

    Answer Under no circumstances should the wedge protrude at the narrow end of the socket.

    Reference: Written assessment for cranes question 67

    Question 4

    What is the minimum amount of tail projection for the dead end of a rope used with a wedge socket? Answer In most cases, the tail on the dead end of the rope should project at least 200mm.

    Reference: Written assessment for cranes question 68

  • Page 40

    Question 5

    What should be secured to the tail of a rope when in use with a wedge socket fitting to indicate slippage? Answer A bulldog grip must be applied only to the tail of the rope below the socket.

    Reference: Written assessment for cranes question 69

    Practical session

    Demonstrate to the trainee the correct assembly of a wedge socket and a bulldog grip. Trainers notes

    SECTION 25

    SHEAVES AND DRUMS FOR FLEXIBLE STEEL WIRE ROPE Points for trainer

    Converse with the trainee regarding the application of sheaves and wind drums for FSWR. Explain the defects that can affect a sheave. Explain the occurrence of two blocking. Explain to the trainee the process of inspecting sheaves, drums and running ropes on the crane before

    starting the operation.

    Show the trainee the process of changing the hook block from a two fall to a four fall reeving configuration.

    Question for trainee/s

    Question 1

    What will condemn a sheave from safe use? List at least three defects. Answers

    Excessive wear in the groove of the sheave. Cracks or any damage in the flange of the sheave. Twisted/deformed or out of shape. Worn sheave pins, hinge pin wear. Damaged cheek plates or cheek plate wall/partition is too close to too far from sheave.

    Reference: Written assessment for cranes question 29

    Question 2

    List two effects double blocking can have on the crane and equipment. Answers

    Can cause the FSWR to break. Can cause the load to drop. Can damage the sheave. Can cause structural damage to the crane.

    Reference: Written assessment for cranes question 30

    Question 3

    When the rope construction is unknown, what is the rule of thumb method used to calculate a sheave size?

    Answer the basic rule of thumb used to calculate sheave size is rope diameter x 20.

    Reference: Written assessment for cranes question 31

  • Page 41

    Question 4

    How much of the FSWR should sit neatly in the base of the groove of a sheave? Answer one third or 120 degrees.

    Reference: Written assessment for cranes question 32

    Question 5

    How deep must the sheave groove be in relation to the rope diameter being used? Answer the sheave groove should not be less than 1.5 times the diameter of the FSWR being used.

    Reference: Written assessment for cranes question 33

    Question 6

    When the maximum number of turns is wound on a drum, how far must the flange of the drum extend about the outer layer of rope?

    Answer The drum flange must extend above the outer layer of the wire rope by at least two rope diameters.

    Reference: Written assessment for cranes question 34

    Question 7

    What is the advantage of using a jockey sheave? Answer A jockey sheave ensure that the hoist rope remains at the correct fleet angle to the winch drum.

    Reference: Written assessment for cranes question 35

    Question 8

    What will occur if the sheave groove is too large for the diameter of the given rope? Answer This will cause rope flattening of the rope.

    Reference: Written assessment for cranes question 36

    Question 9

    What will occur if the sheave groove is too small for the diameter of the given rope? Answer This will cause rope pinching and sever abrasion.

    Reference: Written assessment for cranes question 37

    Question 10

    How is the diameter of a sheave measured? Answer A sheave is measured across the face of the sheave to the inside of the grooves on either side in millimetres.

    Reference: Written assessment for cranes question 38

    Question 11

    When the hook or the block is at the lowest possible point, what is the minimum amount of full turns of wire rope that must remain on the winch drum?

    Answer A minimum of two full turns.

    Reference: Written assessment for cranes question 39

    Question 12

    What happens if the fleet angle of the hoist rope is incorrect? Answers

    Spooling or uneven coiling of the hoist rope on the hoist drum. The hoist rope may be pulled off the sheave and subsequently jam.

    Reference: Written assessment for cranes question 40

    Question 13

    What problem would occur if the jockey sheave seized? Spooling or uneven coiling of the hoist rope on the hoist drum. The hoist rope may be pulled off the sheave and subsequently jam.

    Reference: Written assessment for cranes question 41

  • Page 42

    Question 14

    What are the approved methods of fixing the hoist wire to the boom head? List two methods. Answers

    By using a hambone wedge socket. By using hand splice or machine splice with thimble. By using wire adjusters.

    Reference: Written assessment for cranes question 44

    Question 15

    List two methods used to secure/fix the tail of the hoist rope to the winch drum. Answers

    Socket and wedge Clamp and bolts.

    Reference: Written assessment for cranes question 47

    Practical session

    Have the trainee inspect each sheave on the crane where applicable. The trainee can state which defects can affect sheaves.

    Trainers notes

    SECTION 26

    LIFTING CHAIN Points for trainer

    Use a high tensile lifting chain set for the trainee to inspect for defects. Questions for trainee/s

    Question 1

    What is the smallest size diameter chain allowable for safe load handling for: i. Grade 30 chain?

    ii. High tensile grade 80 chain?

    Answers

    i. Basic grade 30 = 8mm

    ii. High tensile grade 80 = 5.5mm

    Reference: Written assessment for cranes question 22

    Question 2

    What is the maximum temperature that a sling can be subjected to before the rated capacity (SWL) is affected for:

    i. Grade 30 chain sling?

    ii. High tensile grade 80 chain sling?

    Answers

    i. Basic grade 30 2600C

    ii. High tensile grade 800C 4000C

    Note: If 2600C is exceeded, the WLL of the chain is reduced.

    Reference: Written assessment for cranes question 23

  • Page 43

    Question 3

    What is the maximum amount of wear permitted in the link of a chain? Answer The maximum amount of wear permitted in a chain is ten per cent of the diametrical cross section.

    Reference: Written assessment for cranes question 24

    Question 4

    Where on a chain link is wear most likely to occur? List two points. Answers

    Links will wear at the link ends from the metal wear down. Links will wear on the outer sides of the link from being dragged.

    Reference: Written assessment for cranes question 25

    Question 5

    What will condemn a chain fr