Upload
lekhue
View
214
Download
1
Embed Size (px)
Citation preview
Environmental Assessment Page 1 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
Section 3.8 Watershed and Soils
Introduction The spatial scope of this analysis includes 23 watersheds at approximately the HUC8 scale
(ranging from approximately 550 to 3000 acres in size), for a total of approximately 42,520
acres included in the analysis. These watersheds are the established scale at which the Sierra
NF conducts Cumulative Watershed Effects (CWE) analysis. Possible downstream
accumulation of effects in connected watersheds is also considered. The Watershed Specialist
Report and it‟s Appendices are incorporated by reference.
The temporal scope of the analysis includes „short-term‟, up to 5 years after project
implementation, and „long-term‟, 5 -30 years after implementation.
The technical scope of this analysis includes information related to the existing condition of
watershed resources (in this project area, soils and stream channels), and the direct and
indirect effects of the alternatives. Indicators include erosion, soil quality, streambank stability,
stream bank disturbance, water quality, water quantity, and ERAs. The Disturbed WEPP model
(Elliot et al 2000) was used to estimate potential erosion and sediment delivery. The Cumulative
Watershed Effects (CWE) analysis follows direction in FSH 2509.22 R5 Amendment 2.
The methodology used for the analysis of the environmental consequences of the alternatives,
including the scope of the report, assumptions made in the analysis, and the indicators of
effects, is described in this section. The discussion of the direct and indirect effects of the
alternatives is organized by resource (soils, streams, subdrainages) and by activity (hand
cutting, mastication, dozer piling, etc), then reviewed for each fuelbreak unit. The discussion of
cumulative effects integrates the effects on soils and streams in subdrainages.
Affected Environment
Soils
Soils in the project area are characterized based on an Order 3 soil survey (USDA Forest
Service 1986). The project area contains 20 Soil Map Units, which are combinations of nine
different soil families and rock outcrop. The soil map units are shown in Table 2. The soils that
are considered to have a moderate or high sensitivity to disturbance are indicated by a symbol
(†) after the map unit number. They include the Auberry, Holland, Coarsegold, and Shaver
families. The sensitivity rating of a soil describes its level of susceptibility to a loss of productivity
as a result of ground-disturbing activities. It considers the thickness of the A horizon, depth to
bedrock, and the maximum erosion hazard rating of the map unit.
The acreages shown in Table 3.8-1 are approximate, and were derived from GIS analysis.
Environmental Assessment Page 2 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
Table 3.8-1. Acres of treatments proposed on each soil type within the project area. Rock outcrops
(approx. 250 acres) will not actually be treated. (Acres shown are the maximum potential treated
areas, and could include re-treating the same area within the life of the document.)
Soil
Map
Unit
Soil Families
Hand
Line
(ac)
Hand
Cutting
(ac)
Mastication
w/Shar (ac)
Tractor
w/Brush
Rake (ac)
Pile
Burning
(ac)
Herbicide
(ac)
101 Ahwahnee 0.2 13 - 60 73 68
102 Ahwahnee - 0.2 4 - 0.2 5
103 Ahwahnee – Rock Outcrop - 0.3 - - 0.3 0.3
105† Auberry 0.3 10 48 51 61 108
106† Auberry 0.8 110 221 41 151 368
107† Auberry - Ahwahnee - 2 189 - 2 191
108† Auberry - Ahwahnee 0.4 43 98 0.2 43 111
110† Auberry – Tollhouse - 7 221 - 7 221
126 Chawanakee – Rock Outcrop - - 104 - - 104
136† Holland - - 66 - - 66
137† Holland - 12 - - 12 12
138† Holland - Chaix - 1 336 121 122 336
139† Holland - Chaix - 418 472 460 878 889
140† Holland - Chawanakee - 22 4 - 22 26
141† Holland - Chawanakee - - 23 - - 23
147 Rock Outcrop - - 204 40 40 204
156† Shaver - 5 - 5 -
166 Tollhouse – Rock Outcrop - 16 313 53 70 328
167 Tollhouse – Rock Outcrop - - - - - -
169† Typic Argixerolls - Coarsegold - - 210 - - 210
The soil families are briefly described below.
Ahwahnee family soils are moderately deep to deep coarse, sandy loams formed in material
weathered from granitic rock. Sensitivity is high on slopes over 50%.
Auberry family soils are moderately deep to deep coarse sandy loams at the surface with a
sandy clay loam subsoil. They formed in material weathered from granitic rock. Sensitivity is
high on slopes over 50%. If the coarse sandy loam surface layer is removed and the sandy
clay loam subsoil is exposed, it is prone to gully erosion.
Tollhouse family soils are generally shallow coarse sandy loams that formed in material
weathered from granitic rock. Sensitivity is high because of the shallow soil profile – soil loss
can affect total productivity.
Chaix (pronounced „shay‟) family soils are moderately deep to deep coarse sandy loams
formed in material weathered from granitic rock. Sensitivity is high on slopes over 50%.
Chawanakee family soils are shallow coarse sandy loams formed in material weathered
from granitic rock. Sensitivity is high because of the shallow soil profile – soil loss can affect
total productivity.
Environmental Assessment Page 3 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
Coarsegold family soils are moderately deep to deep loam with a gravelly clay loam subsoil,
formed in material eroded from metasedimentary rocks. These soils have a high sensitivity
on slopes over 50%, and their fine surface texture makes them prone to gully erosion on
bare slopes.
Holland family soils are deep sandy loams with a sandy clay loam subsoil, formed in
material weathered from metamorphic rock. These soils are susceptible to compaction when
moist or wet, and roads and skid trails are highly susceptible to gully erosion if proper
drainage is not maintained.
Shaver family soils are deep coarse sandy loams formed in material weathered from granitic
rock. Sensitivity is moderate.
Typic Argixerolls are deep to moderately deep sandy loams with a gravelly sandy clay loam
or clay loam subsoil. They are formed in material weathered from gabbro or
metasedimentary rock. They generally occur in association with Auberry and Coarsegold
family soils, and are similarly prone to gully erosion on unsurfaced roads that lack proper
drainage.
Streams
The project area contains approximately 114 miles of streams, as shown in Table 3.8-2
Table 3.8-2. Miles of stream, by stream order, in the Fuelbreaks.
Stream Order Miles Flow Regime
1 76.1 Ephemeral
2-3 33.6 Intermittent
4+ 4.5 Perennial
Total 114.2 Miles
None of the streams in the fuelbreak areas have had physical channel data collected, including
bank disturbance information. The stream channels in this project area are generally steep,
bedrock- or boulder-controlled, brushy, and not easily accessible. Limited field observations
suggest that direct stream bank disturbance is limited to road crossing impacts, and has not
been observed to exceed 20%.
There has been no water quality data collected in the project area streams. The steeper gradient stream channels are predominantly bedrock or boulder, and generally do not hold fine sediment. Some lower-gradient reaches are gravel-bed streams that contain some sand. These streams are more likely to show a response in sediment accumulations or stream channel adjustments as a result of increases in streamflow or sediment. Water temperatures have not been measured in these fuelbreaks. Late summer temperatures up to 27°C (80°F) are considered to be normal in low-elevation streams. Chemical constituents of interest in this project are glyphosate, oil, and grease. There is no data on chemical constituents in these areas. They may be introduced in small quantities at discrete points due to incidents at or near road crossings or due to herbicide application by the FS, PG&E, or private landowners. Other than an ongoing remediation effort for historically leaking underground gasoline storage tanks adjacent to Little Sandy Creek in the town of Auberry, there are no known issues with chemical constituents in any of these areas.
Environmental Assessment Page 4 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
The beneficial uses of water in the project area are shown in Table 3.8-3. Descriptions of the beneficial use codes follow the table. Water bodies tributary to these rivers fall under the same beneficial use criteria (i.e. the „Tributary Rule‟). Assuming that the water quality currently meets or exceeds water quality standards, the water is subject to the Anti-degradation Policy, which requires that wherever existing water quality is better than the established objectives, the existing quality will be maintained (CVRWCB 2004, 2009).
Table 3.8-3. Designated Beneficial Uses for the Streams in the Project Area, by Fuelbreak
Major River Segments and Associated Fuelbreaks M
UN
AG
R
PO
W
RE
C-1
RE
C-2
RA
RE
WA
RM
CO
LD
MIG
R
SP
WN
FR
SH
WIL
D
San Joaquin River @ Millerton, including: Powerhouse and Powerhouse Rd Jose Basin Rd Lerona Beal – NW portion
X X X X X X X X
Kings River @ Pine Flat, including: Shaver Springs Upper Sycamore Vincent Burrough Beal – SE portion
X X X X X X X
Municipal and Domestic Supply (MUN) - Uses of water for community, military, or individual water supply systems including, but not limited to, drinking water supply.
Agricultural Supply (AGR) - Uses of water for farming, horticulture or ranching including, but not limited to, irrigation (including leaching of salts), stock watering, or support of vegetation for range grazing.
Hydropower Generation (POW) - Uses of water for hydropower generation.
Water Contact Recreation (REC-1) - Uses of water for recreational activities involving body contact with water, where ingestion of water is reasonably possible. These uses include, but are not limited to, swimming, wading, water-skiing, skin and scuba diving, surfing, white water activities, fishing, or use of natural hot springs.
Non-Contact Water Recreation (REC-2) - Uses of water for recreational activities involving proximity to water, but where there is generally no body contact with water, nor any likelihood of ingestion of water. These uses include, but are not limited to, picnicking, sunbathing, hiking, beachcombing, camping, boating, tidepool and marine life study, hunting, sightseeing.
Rare, Threatened, or Endangered Species (RARE) - Uses of water that support habitats necessary, at least in part, for the survival and successful maintenance of plant or animal species established under State or Federal law as rare, threatened or endangered.
Warm Freshwater Habitat (WARM) - Uses of water that support warm water ecosystems including, but not limited to, preservation or enhancement of aquatic habitats, vegetation, fish, or wildlife, including invertebrates.
Environmental Assessment Page 5 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
Cold Freshwater Habitat (COLD) - Uses of water that support cold water ecosystems including, but not limited to, preservation or enhancement of aquatic habitats, vegetation, fish, or wildlife, including invertebrates.
Migration of Aquatic Organisms (MIGR) – Uses of water that support habitats necessary for migration or other temporary activities by aquatic organisms, such as anadromous fish.
Spawning, Reproduction, and/or Early Development (SPWN) – Uses of water that support high quality habitats suitable for reproduction and early development of fish.
Freshwater Replenishment (FRSH) – Uses of water for natural or artificial maintenance of surface water quantity or quality.
Wildlife Habitat (WILD) - Uses of water that support terrestrial or wetland ecosystems
including, but not limited to, preservation and enhancement of terrestrial habitats or
wetlands, vegetation, wildlife (e.g., mammals, birds, reptiles, amphibians, invertebrates)
or wildlife water and food sources.
Water quantity in these streams has generally not been measured. The majority of the streams
in the project area are ephemeral (76 miles) or intermittent (34 miles) (see Table 3.8-2). The
perennial streams have very low flows during the summer months. The mean annual
precipitation of the fuelbreak areas ranges from about 22 inches at Powerhouse and Jose Basin
to about 32 inches at the upper portion of Vincent. The majority of the project area receives
most of its precipitation in the form of rain, transitioning into a mixed rain-snow zone at around
3600 ft (Shaver Springs, Upper Sycamore, Vincent, and the upper portions of Burrough and
Beal).
There is little stream stability data for the fuelbreak areas. Most of the existing information on
channel stability is from reaches downstream of the project area. It was collected using the
Pfankuch channel stability rating (USDA Forest Service 1975), which is a qualitative visual
method based on ratings of 15 different indicators. The conversion of the indicator ratings into
an overall reach stability rating of „good‟, „fair‟ or „poor‟ has been modified to reflect the expected
characteristics of different stream types (Rosgen 1996). Existing stream stability
characterizations range from excellent to poor in and downstream of the project area.
Subdrainages
The fuelbreak treatment areas lie within 23 subdrainages (HUC8s), as displayed in Table 3.8-4.
The natural watershed sensitivity and a determination of the presence of existing CWE
concerns are also shown. Table 3.8-5 shows the approximate acreage of each treatment type
by subdrainage. These acreages were derived from GIS analysis.
Table 3.8-4. The 23 HUC8 subdrainages in the project area, their natural sensitivity, and the
fuelbreaks within them.
HUC8 # Watershed
Sensitivity
Existing
CWE
Concerns? Fuelbreaks
Environmental Assessment Page 6 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
HUC8 # Watershed
Sensitivity
Existing
CWE
Concerns? Fuelbreaks
518.0005 Moderate N Burrough
518.0010 High Y Beal, Burrough, Shaver Springs, Upper
Sycamore
518.0011 High Y Upper Sycamore, Vincent
518.0012 High Y Burrough
518.0054 High N Burrough
518.0055 Moderate N Burrough, Vincent
518.2001 High Y Vincent
519.3053 Moderate Y Vincent
523.0001 High Y Burrough
523.0003 High Y Burrough
523.0005 High Y Powerhouse
523.0006 Moderate N Powerhouse, Powerhouse Rd
523.0010 High N Jose Basin Rd, Powerhouse
523.0011 High N Jose Basin Rd
523.0012 High N Jose Basin Rd, Lerona
523.0015 High N Jose Basin Rd, Lerona
523.0052 High N Powerhouse, Powerhouse Rd
523.0053 High N Powerhouse, Powerhouse Rd
523.3001 High N Jose Basin Rd
525.0002 High N Beal
525.0003 High N Beal, Burrough
525.0052 High N Beal, Burrough
525.0053 High Y Burrough
Environmental Assessment Page 7 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
Table 3.8-5. Acres of treatments proposed within each subdrainage (HUC8) in the analysis area.
(Acres shown are the maximum potential treated areas. Some areas will be treated more than once, e.g.,
piles are constructed by a tractor with brush rake, the piles are burned, then the area is sprayed with
herbicide.)
HUC8 #
Total
WS
Size
(ac)
Total
(Gross)
Treatment
(ac)
Hand
Line
(ac)
Hand
Cutting
(ac)
Mastication
w/Shar (ac)
Tractor
w/Brush
Rake
(ac)
Pile
Burning
(ac)
Herbicide
(ac)
518.0005 2037 387 - - 387 - - 387
518.0010 2520 943 - 34 261 647 681 943
518.0011 2173 236 - 42 169 25 67 236
518.0012 2771 211 - - 211 - - 211
518.0054 1607 76 - - 76 - - 76
518.0055 1779 469 - - 469 - - 469
518.2001 2530 1009 - - 744 - - 744
519.3053 2083 9 - - 9 - - 9
523.0001 1586 85 - - 85 - - 85
523.0003 1516 53 - - 53 - - 53
523.0005 537 12 - - - 12 12 12
523.0006 1058 49 0.6 23 - 26 49 49
523.0010 2436 11 - 5 - 6 11 -
523.0011 3068 2 - 2 - - 2 -
523.0012 1849 76 - 7 69 - 7 69
523.0015 1536 141 - 16 125 - 16 141
523.0052 2019 38 1.2 22 - 17 38 38
523.0053 2553 105 - 13 - 92 105 -
523.3001 546 12 - 12 - - 12 -
525.0002 1378 113 - - 113 - - 113
525.0003 893 113 - 15 97 1 16 113
525.0052 1613 299 - 33 32 33 65
525.0053 2432 53 - - 287 - 287
Environmental Assessment Page 8 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
The current condition of these subdrainages is described below. The effects of all the past,
present, and foreseeable activities listed in the EA are included in the descriptions.
518.0005 – This subdrainage contains a fourth order tributary to Sycamore Creek. NAIP
imagery shows a landscape that is somewhat modified, especially in the lower portion of the
area where roads, cleared areas, and homes are prevalent. The upper portion of the area has
some roads, and previously treated areas (and untreated stream buffers) are visible. A CWE
analysis conducted in 2009 using ERAs concluded that this area is probably not experiencing
CWEs. Almost 20% of this subdrainage is in the Burrough Fuelbreak.
518.0010 – This subdrainage contains a fifth order tributary to Sycamore Creek. Disturbances
include roads (Highway 168, Tollhouse Road, and many smaller roads and driveways), cleared
areas, homes, the Shaver Springs subdivision sewage disposal ponds, powerlines, etc. At least
one large gully from Tollhouse Road is connected to the drainage system. Previously treated
areas are visible on the NAIP imagery. A 2009 CWE analysis using ERAs concluded that this
area was probably not at risk for CWEs: however, the current review suggests that CWEs could
be occurring. This area has one of the highest proportions of proposed treatment areas,
including portions of Beal, Burrough, Shaver Springs, Upper Sycamore, and Vincent fuelbreaks.
518.0011 – This subdrainage contains the upper portion of Sycamore Creek and its tributaries.
Disturbances include portions of Cressman Road, Peterson Mill Road, and Cripe Road, and the
associated cleared areas, man-made ponds, and homes, as well as powerlines. Previously
treated areas are visible on NAIP imagery.
518.0012 – This subdrainage contains the headwaters of Little Dry Creek, including Duncan
Canyon and Burrough Valley. Visible disturbances include development in Burrough Valley
(roads, cleared areas, homes) and the Burrough Fuelbreak. There are some first order channels
in the Burrough Fuelbreak, which are visible on the imagery because of untreated buffer areas
around them.
518.0054 – This subdrainage contains middle Sycamore Creek and tributaries. Disturbances
visible on NAIP include roads and some cleared areas with homes, particularly in the lower
portion of the subdrainage. A 2009 CWE assessment concluded, using ERAs, that this
subdrainage is probably not experiencing CWEs. Previously treated areas are visible on the
imagery.
518.0055 – This subdrainage contains middle Sycamore Creek and tributaries, upstream of
518.0054. NAIP imagery shows a largely unmodified landscape, with a few roads and
previously treated areas comprising the only visible disturbances. A 2009 CWE assessment
concluded that the area is probably not experiencing CWEs.
518.2001 – This subdrainage contains South Fork Sycamore Creek and its tributaries. Existing
disturbances include a portion of Peterson Mill Road and associated cleared areas, driveways,
and homes. Previous vegetation management, including fuel reduction treatment, has also
occurred. A 2009 evaluation concluded that this area is not experiencing CWEs.
519.3053 – This subdrainage includes lower Rush Creek and its tributaries. On NAIP this area
appears to be only slightly modified, with some roads and homes. However, previous ERA
analyses in 2006 and 2009 concluded that this area is above its threshold for CWEs. Existing
Environmental Assessment Page 9 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
information and recent stream channel observations note stream channel instability and
excessive sediment deposition in pools, which support this conclusion.
523.0001 – This subdrainage includes an unnamed fifth order tributary to Big Sandy Creek and
its tributaries. Prominent disturbances in this area include cleared areas in and near Big Sandy
Valley, homes, and roads including portions of the 4-Lanes and of Auberry Road. The Auberry
Fire burned here in 2008 in the area between the 4-Lanes and Auberry Road.
523.0003 – This subdrainage contains a fourth order tributary to Big Sandy Creek. On NAIP,
visible disturbances include cleared areas in Big Sandy Valley, roads including a portion of the
4-Lanes, and homes in Big Sandy Valley and along the Beal Fire Road. Previously treated
areas are visible on the imagery.
523.0005 – This subdrainage includes a reach of Little Dry Creek and tributaries in the vicinity of
the town of Auberry. NAIP imagery shows a highly modified landscape with extensive areas of
clearing and many homes, roads, man-made ponds, etc. The stream is obviously impacted
through the town of Auberry, where encroachment, channelization and incision are apparent.
Historically, a railroad switchyard existed on the terrace adjacent to the creek just upstream of
town, which now hosts homes and the sewage treatment ponds for the New Auberry
subdivision.
523.0006 – This subdrainage contains an unnamed tributary to Kerckhoff and its tributaries.
NAIP imagery shows large cleared areas with man-made ponds that are used for grazing
animals, homes, roads including Powerhouse Road, and powerlines. 2006 and 2009 CWE
evaluations concluded that this area was not experiencing CWEs.
523.0010 – This subdrainage includes Backbone Creek and tributaries. In NAIP, visible
disturbances appear along Auberry Road, including the Big Sandy Rancheria and associated
clearing and developments, homes, and roads. A 2009 CWE evaluation based on ERAs
concluded that this area was not experiencing CWEs.
523.0011 – This subdrainage includes Bald Mill Creek and tributaries. In NAIP, the upper
portion of this subdrainage appears highly modified, with housing subdivisions (Meadow Lakes,
Corlew Meadows), an orchard, numerous ponds and roads including Auberry Road. Much of the
lower drainage is steep and covered with dense brush. A 2009 CWE evaluation based on ERAs
concluded that this area was not experiencing CWEs.
523.0012 – This subdrainage includes unnamed third and fourth order streams that flow into
Redinger Lake, and their tributaries. Disturbances including roads, homes, man-made ponds,
and several cleared areas are visible on NAIP. A 2009 evaluation concluded that this area is not
experiencing CWEs.
523.0015 – This subdrainage includes Italian Creek and tributaries. Disturbances include roads
and a portion of the Sugarloaf brush conversion project that was implemented in the 1960s for
range improvement. The area is not part of the surrounding CARs, although Italian Creek is
perennial. A 2009 evaluation concluded that this area is not experiencing CWEs.
523.0052 – This subdrainage includes the reach of the San Joaquin River through Kerckhoff
Lake and tributaries. NAIP imagery shows a moderate level of disturbance including the
Environmental Assessment Page 10 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
reservoir and powerhouse, roads and lakeside recreation facilities, a landing strip, homes, and
other cleared areas. Part of the Powerhouse Fuelbreak and the Powerhouse Road treatments
are in this area. A 2006 evaluation concluded that CWEs were not occurring. Since that time, a
power company ditch failure in 2009 resulted in extreme gullying and sediment delivery to
Kerkhoff Lake which may constitute an existing CWE response.
523.0053 – This subdrainage includes a reach of the San Joaquin River upstream of
Powerhouse 4, and tributaries. The predominant disturbances visible on NAIP include roads,
the powerhouse substation, the Wish-I-Ah inpatient facility, and an area of mass wasting into
the river. A 2006 evaluation concluded that CWEs were not occurring, and other than the
relatively small and low to moderate severity Powerhouse Fire in 2008, there have been no
significant disturbances since that time.
523.3001 – This subdrainage includes a third order tributary to Jose Creek, and is located in the
Jose Basin CAR for Foothill yellow-legged frog. NAIP imagery shows disturbances including
roads, areas converted from brush to grassland in the 1960s for range improvement, and man-
made ponds associated with the grazing project. The known watershed problems in this area
are related to the roads. A 2006 evaluation concluded that CWEs were not occurring, and no
significant projects have been implemented since that time.
525.0002 – This subdrainage includes tributaries to Dry Creek. NAIP imagery shows a
moderately modified landscape, with roads (including a portion of the 4-Lanes), homes, and
some cleared areas, surrounded by brush and rock outcrop areas. It contains portions of the
Beal Fuelbreak near Buckeye Heliport and the Messenger Spur. These units contain some first-
order channels and sensitive soils.
525.0003 – This subdrainage includes Tollhouse Creek and tributaries. NAIP imagery shows a
moderately modified landscape with disturbances such as roads, including Tollhouse Road and
a section of the Highway 168 „4-Lanes‟, homes, and powerlines. A 2009 evaluation using ERAs
concluded that this area is not experiencing CWEs.
525.0052 – This subdrainage includes a reach of Dry Creek and tributaries upstream of and
including the town of Tollhouse. Disturbances in this area include the town, roads including
Tollhouse Road and a short section of the Highway 168 „4-Lanes‟, and powerlines. Roads are
probably the disturbance with the greatest influence on watershed condition. Other than these
disturbances which are limited in area, NAIP imagery shows a mostly intact landscape of brush
with large rock outcrops.
525.0053 – This subdrainage includes a reach of Dry Creek and tributaries located downstream
of the town of Tollhouse. The majority of this area is on private property. NAIP imagery shows a
modified landscape that is affected by roads (including Tollhouse Road), homes, a school, and
various clearings and developments. The previous fuelbreak treatments are visible on the
imagery.
Affected Environment by Treatment Area
The streams in the Jose Basin Road brushing area are generally steep tributaries to the San
Joaquin River, including several perennial streams and their tributaries (Backbone, Bald Mill,
Environmental Assessment Page 11 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
Italian, and Jose Creeks). The road treatment crosses 5 subdrainages, all with High natural
watershed sensitivity. The majority of the project area, and much of the subdrainages the
project area is in, lie on sensitive soil types (mostly Auberry and Ahwahnee families). The
subdrainages in this project area do not appear to be experiencing CWEs.
Streams crossed by the Powerhouse Road brushing area are steep to very steep first- and
second-order tributaries to the San Joaquin River. No data has been collected in these streams,
but portions of the area were visited in 2006 for the Patterson Bend Allotment EA (Gott 2006).
The streams in this area generally alternate between steep channels in fine-grained substrates
(such as A5 channel types) and steep rocky reaches (A1-A2). Localized instabilities were
observed, and most were attributed to the natural instability of A5 channels or to impacts from
roads. Some of the potentially affected streams may be perennial. Almost all of the treatment
area is on sensitive soils (Auberry and Ahwahnee families). Three subdrainages contain
portions of this treatment area, two of which have High sensitivity and one (523.0006) which has
Moderate sensitivity. The subdrainages in this treatment area are not thought to be experiencing
CWEs.
The Powerhouse Fuelbreak intersects some first order streams according to the streams gis
data, however observations during field review of the NFS portion of the area indicated that
these are unchanneled swales with channel initiation occurring near the boundary of the
fuelbreak. Only one observed channel contained flow and supported riparian vegetation. About
half of the fuelbreak is on sensitive soils (Auberry family). The area spans 5 subdrainages, four
with High sensitivity and one (523.0006) with Moderate sensitivity. The southern portion of this
treatment area, on private land, lies in subdrainage 523.0005, which has been identified for
CWE concerns related to private land development and impacts from historic land uses.
The streams in the Lerona Fuelbreak are unchanneled swales and steep, first-order tributaries
to Italian Creek and Redinger Lake (the San Joaquin River). The treatment area lies in two
subdrainages, both with High natural sensitivity. No data exists for the streams, and none of
them are thought to be perennial. The main equipment access route along the ridgeline was
evaluated in 2008 for possible addition to the NFTS as a motorized trail. This evaluation
documented severe erosion along this access route because unauthorized motor vehicle use
had breached the constructed drain dips. However, the material was deposited near the route,
and no sediment delivery to any channel was noted. The northern half of this treatment area is
located on sensitive soils (Auberry-Awahnee families). Neither of the subdrainages in this area
is thought to be experiencing CWEs.
Beal Fuelbreak streams are mostly first- with some second-order streams, tributary to Big
Sandy Creek or Tollhouse / Dry Creeks, with about 60 acres tributary to Sycamore Creek. The
treatment areas lie in 6 subdrainages which all have High natural sensitivity. Portions of the
main access road (10S307) are maintained by private land owners. Year-round use of this
native surface road for access to homes on private land results in rutting, erosion, and sediment
movement off of the road. Drain dips have large quantities of sediment deposited in them, but
none was observed to enter stream channels. There is one known severe gully related to road
runoff in this area. Previous fuels treatments are visible on NAIP imagery, and the existing
vegetation pattern generally shows untreated areas in the vicinity of most of the streams on the
Environmental Assessment Page 12 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
GIS layer. The treatment areas in the eastern portion of Beal have predominantly sensitive soils
(Holland-Chaix families), while these soils are present in only a small part of the western
treatment areas. An existing landslide area on Highway 168 is located downslope from a portion
of Beal, but based on the topography of this area and the fact that the surface drainage from the
treatment area flows away from the landslide location rather than towards or through it, this was
not identified as a concern for the effects of the proposed treatments. The small units of Beal
that are east of Tollhouse Road are in subdrainage 518.0010, which has been identified for
CWE concerns related primarily to private land development and roads.
Streams in the Vincent Fuelbreak are mostly first and second-order streams, with some third-
order channels along the western and southern edges, tributary to Sycamore Creek in
subwatersheds 518.2001, 518.0011, and 518.0055. These subdrainages have High and
Moderate (518.0055) natural sensitivity. Some of these streams may be perennial. Some data
was collected in 1991 in North Fork Sycamore Creek within the project area, and in 1995 in
Sycamore Creek about 1.5 miles downstream of the project area. The data indicates that North
Fork Sycamore Creek is an A4 channel type, dry on the survey date of May 2, with a stability
rating of Poor. Sycamore Creek surveyed reaches, flowing on the survey date of July 12, are A1
type with Good stability and B4 type with Poor stability. The main access road 10S06 has
several ford crossings that provide opportunities for improvement, but this work is outside the
scope of this project. The stream reach visited at the downstream edge of the treatment area is
a bedrock slot channel (probably A1). The majority of the treatment area lies on sensitive soils
(Auberry, Awahnee, and Holland-Chaix families). Three of the four subdrainages associated
with this treatment area have been identified for CWE concerns: 518.0011 and 518.2001
primarily for private land development and roads, and 519.3053 (Rush Creek) for various
reasons including roads and past FS land management actions. Only 9 acres of this treatment
area lie in 519.3053.
Streams in the Upper Sycamore and Shaver Springs Fuelbreaks are first, second, and third-
order streams with some fourth order reaches near the lower boundaries, that are tributary to
Sycamore Creek in subdrainages 518.0010 and 518.0011. These subdrainages have High
natural sensitivity. The fourth order reach that I observed on May 27, 2010 had a substrate of
boulders, cobbles, and sand, and appeared to be perennial (although this may be due to an
unusually late and wet spring season in 2010). These project areas are located about 4 miles
upstream of the reaches where stream data was collected in 1995. The streams that cross the
powerline access road (10S408A) just south of the Shaver Springs subdivision support riparian
areas near the road and will require SMZs. One severe gully caused by drainage from
Tollhouse Road (a paved county road) is connected to the stream channel network. Almost all
of these treatment areas are located on sensitive soils (Holland-Chaix families complex). Both of
the subdrainages have been identified for possible CWE concerns related primarily to roads and
private land development.
Burrough Fuelbreak streams are mostly first- and second-order tributaries to Sycamore Creek
and Dry Creek in eight subdrainages with Moderate to High natural sensitivity. The only existing
data is the Sycamore Creek data described above, which is farther downstream from this
fuelbreak than it is from Vincent. The main access roads (10S009, 10S009A, 10S009B, and
10S009BA) have sections with severe ruts and gullies, and are in need of maintenance.
Environmental Assessment Page 13 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
Previous treatments are visible on NAIP imagery, and the existing vegetation pattern generally
shows untreated areas in the vicinity of most of the streams on the GIS layer. Sensitive soils in
the northern portion of this treatment area include Holland-Chaix families. Auberry-Awahnee
family soils underlay most of the central portion, and the southern portion has only a small area
of sensitive soils. Four of the subdrainages (518.0010, 518.0012, 523.0003, and 525.0053)
have been identified for possible CWE concerns, primarily due to private land development and
roads.
Alternative 1 Proposed Action
Direct and Indirect Effects on Soils, by Activity
Hand Line – Hand line construction causes soil disturbance by removing cover (including
surface organic matter). Slight displacement of the soil surface is also typical. However,
because the line will be only about 3 feet wide, the effects will be minimal. BMP 1-17 directs the
construction of cross-drains for erosion control on hand lines.
Hand Cutting – Cutting of brush with a chainsaw will have minimal impacts to soils (Robichaud
and others 2010). The material may be left on-site for later underburning, or piled by hand for
later pile burning. The impacts of the burning are discussed under headings for those activities.
In the short-term, preparing for underburning leaves more soil cover and organic matter on site
than piling the material. However, because understory vegetation will not be removed, the
minimum groundcover of 50% will easily be met. Porosity will not be appreciably modified by
foot traffic.
Mastication with Shar – The effects of mastication have the potential to disturb or compact soil
and have not been widely studied (Robichaud and others 2010). However, the studies that have
been conducted have concluded that this type of treatment has minimal effects on soils.
Hatchett and others (2006) concluded that erosion and compaction on their study area‟s coarse
sandy loam were minimal, but that their findings were probably the result of the equipment being
operated on masticated material rather than on bare ground. In an unpublished paper
examining the effects of a rubber-tracked mulching machine on a gravelly fine sandy loam,
Tepler (unpublished, 2005) measured some increases in bulk density, but they did not exceed
the NRCS threshold for detrimental disturbance of that soil. He noted a concern that the
remaining mulched woody material, up to 5 inches deep in some places, might restrict the
regrowth of vegetation. Moghaddas and Stephens (2007) found that commercial thinning of a
mixed conifer forest followed by mastication did not increase compaction of the Holland and
Musick series soils in the study area. Based on these studies and previous experience with the
treatment on the Sierra NF, mastication is expected to increase soil cover and organic matter
and cause slight / minimal decrease in porosity.
Tilling – Most of the research that has been done on the effects of tilling have examined the
practice when applied for the amelioration of soil compaction (restoration of roads, landings, or
skid trails) rather than as a method of eliminating vegetation for fuel reduction. Porosity is
increased by tilling. However, Luce (1997) suggested that ripping compacted surfaces provides
only marginal and temporary improvements in soil bulk density, porosity, and infiltration capacity
that could be improved by incorporating organic material into the soil as part of the treatment.
Kolka and Smidt (2004) found that subsoiled road surfaces had similar soil bulk densities,
Environmental Assessment Page 14 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
runoff, and sediment production as roads with revegtated but otherwise untreated surfaces.
Both of those road surfaces produced greater runoff and sediment than adjacent undisturbed
areas. Kane and others (2009) studied the effects of tilling masticated material for fuels
reduction on understory vegetation response; although their study did not focus on impacts to
soils, they did note that the treatment increased bare mineral soil compared to mastication
alone. This information suggests that the proposed tilling would increase sediment production
compared to the present condition and compared to mastication alone, but not as much as
traditional tilling without the incorporation of organic matter into the soil. Moisture regime can be
affected if soil cover and organic matter are reduced enough that the soil dries out quickly due
to exposure to sunlight and air circulation. Because a minimum of 50% soil cover will be
maintained, impacts will be minimized. This treatment could occur on slopes of up to 35%, but
by operating on the contour, the tilled areas will provide for adequate infiltration, reduce runoff,
and minimize the potential for overland flow to initiate rill erosion. Tilling disturbs the soil, but
when adequate soil cover and organic matter remain, does not impair soil productivity.
Glyphosate Herbicide – Glyphosate rapidly attaches to organic matter and soil particles on the
ground surface and on plant surfaces (Ghassemi and others 1981). Its mobility is very limited. It
does not become mobile again with precipitation and does not leach through the soil. Because
of its very low mobility in soil, the only mechanism for off-site movement of glyphosate would be
if it were attached to soil particles that were eroded and transported to another location. If
sediment with glyphosate bonded to it reaches water, it would not be in a form that can be taken
up by plants or released through digestion by animals - normal hydrolysis in a stream will not
break the attachment of glyphosate to soil particles
Glyphosate application causes little or no direct soil disturbance. Dead foliage and leaf drop
onto the soil surface continues provides groundcover. The herbicide biodegrades within weeks
of application into natural products including: carbon dioxide, nitrogen, phosphate and water.
The half-life of glyphosate can range from 20 to 60 days (SERA 2003). The primary metabolite
of glyphosate is aminomethylphosphonate (AMPA). The position taken by U.S. EPA/OPP
(2002) that AMPA is not of toxicological concern, regardless of its levels in food, appears to be
reasonable and is well-supported (SERA 2003; p.3-25). The only potential impact to the soil
resources is from direct disturbance and displacement of the soil by applicators walking on the
ground.
Effects on soil micro flora are minimal and not pronounced (Ghassemi and others 1981). There
is very little information suggesting that glyphosate will be harmful to soil microorganisms under
field conditions, and a substantial body of information indicating that glyphosate is likely to
enhance or have no effect on soil microorganisms (SERA 2003; p.4-7). There are numerous
reports of harmful effects of herbicides to microorganisms in laboratory studies. Contrary to
laboratory results, most agriculture field studies have shown either no effect or a slight
stimulation of soil microorganisms by glyphosate. Because most of the information regarding
affects of glyphosate on soil microorganisms comes from agricultural studies, a recent study
(Busse and others 2001) was conducted to investigate the effects of glyphosate on forest soils
and microorganisms. Their findings suggest that laboratory studies are of limited relevance in
predicting glyphosate toxicity to soil organisms, and that common field rate applications should
have little or no effect on soil microbial communities. “Long-term, repeated applications of
Environmental Assessment Page 15 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
glyphosate had minimal affect on microbial characteristics despite substantial changes in
vegetation composition and growth.”
A suite of BMPs (5-7, 5-8, 5-10, 5-11, 5-12, 5-13) have been specified for herbicide use in order
to control and minimize impacts.
Broadcast Burning – Broadcast burning has the potential to affect soil cover, organic matter, soil
hydrologic function, and moisture regime. Soil cover and organic matter will be reduced as a
result of being consumed by the fire. In a low to moderate severity underburn, soil cover and
organic matter would be reduced at the surface, but organic matter within the soil profile would
not be consumed. The reduction in organic matter will be within the normal variability for the
project area. The effects of broadcast burning are similar to the effects of low to moderate
severity underburning, except that the proportions of low, moderate, and high burn severity are
shifted towards higher severities. The overall burn pattern mosaic is expected to be similar, but
the majority of the area that actually burns will experience moderate burn severity effects rather
than the low severity effects that are created by underburning. High burn severity is expected to
occur on less than 5% of the treated area.
Burning has the potential to affect soil hydrologic function by increasing soil hydrophobicity,
which results in increased runoff and decreased infiltration. If this occurs over large areas, it can
reduce soil moisture enough to affect the soil moisture regime. Natural hydrophobicity exists in
some soils, and project area soils are likely among these. The chaparral vegetation type is the
classic location for hydrophobicity to occur. Both natural and fire-induced hydrophobicity tend to
be spatially discontinuous. A low to moderate severity underburn is not expected to dramatically
increase hydrophobicity in any soil. The mosaic burn pattern that will result from prescribed fire
provides areas of soils that will be slightly burned or unburned, and which serve as infiltration
areas for any excess runoff that is generated in the intervening hydrophobic areas. Fire induced
hydrophobicity is expected to return to pre-fire levels within 3 years of the burn, except in
severely burned areas where it can be more persistent. Some area may burn at high severity,
although this is expected to be a small part (<5%) of the treated area.
Pile Burning – Pile burning essentially results in small isolated areas of high-severity soil
impacts located beneath the piles, with unburned areas between the piles. High-severity
impacts include loss of ground cover, destruction of soil organic matter, alteration of soil
structure, dramatic changes in soil chemistry, and in some cases, increased hydrophobicity
(Clark 2001). The associated effects on runoff and erosion would be mitigated by the small size
of the burned patches, the unburned areas between them, and buffers along streams where
piles will not be burned to ensure a filter stirp between these areas and streams (BMP 1-22).
Grubbing by Hand – This treatment would have minimal effects to soil resources because
disturbance would be targeted at the base of sprouting vegetation. Removal of cover would be
patchy and localized at the base of individual plants. Porosity would not be reduced, and would
be increased at the locations of the individual plants if the roots are pulled out. Organic matter
would be left on site, and moisture regime would not be altered through this maintenance
activity.
Environmental Assessment Page 16 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
Goats – No literature regarding the effects on soils from the use of goats for brush control in fuel
breaks was found. Green and others (1979) concluded that goats will not readily browse mature
brush, and stated that they did so only when fenced, and after problems with fencing, health of
the animals, and soil disturbance. If goats are used on the fuelbreaks, real-time monitoring
would be needed to ensure that soil disturbance standards are met.
Tractor with Brush Rake – Tractors with brush rakes cause more direct soil disturbance than the
other proposed methods. This treatment has the potential to affect soil cover, porosity, organic
matter, and hydrologic function (which is related to porosity and organic matter).
Soil cover will be reduced by piling of brush using a tractor with rake. The activity will follow
BMP 5-1 in Appendix 1, and a minimum of 50% well-distributed groundcover will remain after
project completion. This meets applicable standards, which were developed in order to protect
soil from accelerated erosion.
Soil porosity will be slightly reduced. The weight of the machinery passing over soils will cause
some packing of soil particles. Moist soils are more prone to compaction. In order to limit the
change in porosity that occurs, moist soils will be evaluated by a soil scientist prior to equipment
operation, and operation will not be permitted until soil moisture is low enough to minimize
compaction (see BMP 5-6 in Appendix 1).
Soil organic matter will be reduced, but not enough to affect physical or biological soil processes
or the nutrient cycle. Disruption of topsoil will be minimized to a maximum of 15%, so that 85%
of the topsoil will remain undisturbed. Surface organic matter will be maintained through the soil
cover standard.
Soil hydrologic function could be altered by this treatment. If significant reductions in porosity
and organic matter occur, hydrologic function will be affected. The possible effects include
decreased infiltration capacity, increased runoff, and increased erosion that could result in rilling
or gullying, especially on the soils that are sensitive to disturbance. The design criteria in
Appendix 1 are expected to limit the reductions in porosity and organic matter to levels below
those that would result in changes to soil hydrologic function. Soil cover will limit runoff and
erosion. Implementation of those measures is crucial for preventing changes in hydrologic
function.
Road Maintenance – Roads are considered to be dedicated land where the maintenance of soil
productivity does not apply. None of the soil quality indicators apply to road surfaces. Since road
maintenance does reduce erosion and sediment movement off the road, it could improve soil
conditions adjacent to the road. The routine road maintenance described for this project falls
under a Categorical Exclusion for NEPA documentation – it could proceed regardless of any
decision for the fuelbreaks being analyzed in this report.
Direct and Indirect Effects on Streams, by Activity
Hand Line – Hand lines will cross streams. However, BMP 1-17 requires cross drains for
erosion control and should minimize runoff, erosion, and sediment delivery. BMP 2-19 ensures
that any brush removed during construction is not discarded in stream channels, which protects
channel cross sectional area and function. The effects of hand line construction on water
quantity, water quality, and channel stability will be minimal.
Environmental Assessment Page 17 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
Hand Cutting – Cutting vegetation with chainsaws could result in minor stream bank
disturbance, as cut vegetation that falls into channels is pulled out for disposal. This disturbance
would be minimal compared to the potential disturbance that would result from treatment with
heavy equipment. S&G 103 from the SNFPA ROD (USDA-FS 2004) requires that such
disturbance would not impact more than a maximum of 20% of any given stream reach. In these
channel types, this level of disturbance is not expected to trigger channel adjustments or
significantly increase channel erosion in the long-term. Water quality could be affected if fuel or
other petroleum products leak or are spilled into or near stream channels, but BMP 2-12
minimizes these already low risks. Water quantity will not be affected by hand removal of
vegetation because the scale of removal will be relatively small, and in this moisture limited
area, other vegetation will quickly take up any additional groundwater. Runoff is not expected to
increase since soil cover will be maintained. Because bank disturbance will be within
management guidelines (no more than 20%), and runoff and hillslope erosion will not be
increased, stream channel stability will not be affected.
Mastication with Shar – Since the effects on soils are minimal, effects to hydrology are also
slight. The treatment leaves good groundcover and does not significantly increase erosion, so
increases in runoff or erosion are not expected to occur. Although the effects of mastication on
water resources has not been well-studied, researchers expect that this treatment would not
result in changes to water yield since thinning treatments generally require 20% of basal area
removal before detectable effects are found in the short-term (Troendle and others 2010).
Hibbert and others (1982) found increases in water yield after brush removal, but their study
removed almost all brush from entire drainages, including streamside areas. They concluded
that shrubs should be eradicated and treatments should be adjacent to channels in order to
increase water yield; this treatment will leave a mosaic of live brush, particularly along stream
channels in the SMZs. This treatment is not expected to measurably increase water quantity,
and any increase would be short-lived because the excess moisture will be taken up by other
plants in these moisture limited areas. Hatchett and others (2006) found that the precipitation
simulations in their study did not produce runoff on the plots with masticated material for
groundcover. Water quality could be affected if equipment leaks fuel or other fluids into a
stream, but this is not expected, and an approved spill plan that addresses this situation will be
in place. Sediment is not expected to increase from mastication since stream disturbance will be
limited, operation must occur outside of SMZs, no activity-generated debris will be left in
channels, and operations will be almost entirely on top of a mat of masticated brush rather than
on the ground. Mastication will have no direct effects on stream bank disturbance or stream
channel stability, because it will not occur in SMZs. The equipment will cross stream channels
within the mastication units, but will follow direction in BMP 1-19. Any damage to streambanks
will be repaired if practicable. Because stream bank disturbance will be very limited and other
impacts are not expected, there will be no effect on stream channel stability resulting from this
activity.
Tilling – Since tilling is likely to increase runoff and sediment production (Kolka and Smidt 2004;
Luce 1997), there is potential for delivery of increased runoff and sediment to streams. The
effects are expected to be short-term, since vegetation would colonize the sites within 2 years.
The potential effects will be minimized by application of no-equipment SMZs, as well as the
Environmental Assessment Page 18 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
slope limitation of equipment which in many places will limit equipment access to greater
distances from the channels than the SMZs.
Glyphosate Herbicide – The effects of glyphosate on water resources was covered in the soils
section, above. Because of its affinity for organic material and soil particles, glyphosate is not
mobile once it is applied by ground application, so it does not affect either surface or ground
water quality. The greatest risk of introducing glyphosate into the water would be by accidental
spills. This risk would be minimized by implementation of BMP 5-7 that would limit transportation
of herbicides to designated routes and specify batching and mixing locations, and BMP 5-10
that provides for a Spill Contingency Plan. A suite of BMPs (5-7, 5-8, 5-10, 5-11, 5-12, 5-13)
have been specified for herbicide use in order to control and minimize impacts.
From 1991 to 2000, surface water adjacent to projects involving the use of glyphosate was
monitored on seven projects on the Sierra, Stanislaus and Eldorado National Forests. All
resulted in no detections (Bakke 2001).
Broadcast Burning – Because prescribed fire is planned and implemented in a manner to
control burn severity and specifically to limit high burn severity, the effects of prescribed fire are
much smaller in magnitude than those of wildfire. In a study comparing sediment production
from different sources, MacDonald and others (2004) found that severely burned areas
produced 1,000 times more sediment than prescribed burn areas. Little sediment yield was
found in a study in the northern Sierra Nevada where ignition was allowed within the riparian
area; Beche and others (2005) found that V* did not change significantly. Zwolinski (2000)
reports that low-severity fires (such as most prescribed fires) generally have little or no
hydrologic impacts, even though most contain a small proportion of high burn severity.
Robichaud‟s investigations of post-timber harvest prescribed fires in Montana and Idaho found 5
and 15% of those areas burned at high severity (Robichaud and others 2010). For this project,
high burn severity is expected to occur on less than 5% of the treated area.
Broadcast burning could result in short-term water quality effects, but is not likely to result in
stream bank disturbance, increased water quantity, or changes in stream channel stability. High
burn severity is considered to be stream bank disturbance. There will be no ignition within
SMZs. Although fire may back into SMZs, it is not expected to burn to a stream bank at high
severity over large areas, due to the fuel moistures that are likely to be present according to the
conditions of the Burn Plan. In order for a fire to increase water quantity, ground cover removal
and vegetation mortality must occur to increase overland flow in response to precipitation and
ambient soil moisture conditions. These prescribed burns will leave at least 50% groundcover
and are not expected to kill enough vegetation to increase soil moisture. The remaining
vegetation will utilize any soil moisture increases that result from vegetation mortality. In order
for stream channel stability to be affected, either direct effects to stream channels or changes in
the water and sediment provided to them would need to occur on a large enough scale to
initiate channel adjustment. Direct effects to stream channels and increases in water quantity
are not expected, as just described. The effects to water quality are described in the following
paragraph. They will not be great enough to reduce channel stability.
Short-term water quality effects could result from the deposition of smoke and ash into surface
water in and near the project area during the burn operation. Following the burn, runoff will likely
Environmental Assessment Page 19 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
carry some ash and sediment into project area stream channels. The amount of material carried
to streams will likely be greater than occurs in an average year in these areas, however, it will
be far less than would occur after a wildfire, and will be well within the range of natural variability
for these streams.
Water quantity is not likely to be affected – as described under Direct and Indirect Effects on
Soils, vegetation in this area is moisture limited, so although killing brush may result in higher
soil moisture and therefore more streamflow in the short-term, vegetation will quickly take up the
excess moisture. Dissmeyer (1965) concluded that the Haslett Fire did not affect peak flows in
Big Creek, although it may have increased base flows slightly during the late summer dry
period. This prescribed broadcast burn is expected to create a smaller, lower severity burn and
have smaller hydrologic effects than the Haslett Fire.
Pile Burning – Pile burning essentially results in small isolated areas of high-severity soil
impacts located beneath the piles, with unburned areas between the piles. High-severity
impacts include increased runoff and erosion (MacDonald and others 2004). The associated
effects on runoff and erosion would be mitigated by the small size of the burned patches, the
unburned areas between them, and buffers along streams where piles will not be burned to
ensure a filter strip between these areas and streams (BMP 1-22).
Grubbing by Hand – This treatment is expected to have no impacts to stream bank disturbance,
water quality, water quantity, or stream channel stability. Streambank vegetation and riparian
vegetation will not be treated, so it will not create stream bank disturbance. The soil disturbance
that results will occur in small discontinuous patches that will not increase runoff, erosion, or
sediment delivery. There will be no chemicals used in this treatment, including oil and grease
(no chainsaws). This is a treatment for maintenance of brush removal, so in itself, it will not
affect water quantity, though it will perpetuate the effects created by the initial brush reduction
treatments. Because there will be no impacts to streams, it will not affect stream channel
stability.
Goats – No literature regarding the effects on water resources from the use of goats for brush
control in fuelbreaks was found. A section about providing water for the animals in Green and
Newell (1982) noted that they can require 1gal/goat/day, and that providing water is often the
most expensive part of the operation. If goats are used on the fuelbreaks, real-time monitoring
would be needed to ensure that BMPs are employed and water quality impacts are minimized.
Tractor with Brush Rake – Creating piles using a tractor with brush rake will have no direct
effects on stream bank disturbance, water quality, water quantity, or stream channel stability,
because it will not occur within any SMZ (BMP 1-22). The equipment will cross stream channels
within the dozer crushing units, but will follow direction in BMP 1-19. Crossings on all streams
with a scoured channel will be approved by the hydrologist and aquatic biologist, even if the
channels are dry (BMP 1-19). Damage to streambanks will be repaired if practicable. Water
quality could be affected if equipment leaks fuel or other fluids into a stream, but this is not
expected, and an approved spill plan that addresses this situation will be in place. Indirect
effects on streams from dozer piling could include increases in runoff (water quantity) and
sediment (affecting water quality) delivered from upslope treated areas. However, as described
in the Direct and Indirect Effects to Soils, runoff and erosion are not expected to increase. If
Environmental Assessment Page 20 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
runoff and erosion do increase in treated areas, untreated SMZs are designed to act as buffers
to disperse flow and deposit sediment prior to reaching stream channels. Should increased
runoff and sediment reach streams, the quantity is not likely to be enough to impact water
quality, overall stream water quantity, or stream channel stability, even in reaches that are
sensitive to disturbance.
Road Maintenance – Luce and Black (1999) found that road maintenance can cause a short-
term increase in sediment yield from roads due to ground disturbance, particularly in the ditch
where stabilizing vegetation is lost during maintenance. However, roads generally require
maintenance in order for the water drainage and erosion control elements of the road design
(e.g. rolling dips, ditches) to continue to function through time - lack of maintenance can result in
increased erosion (Gucinski et al 2001). The routine road maintenance described for this project
is needed to correct problems with the drainage structures and to repair erosion that has
occurred as a result (rilling and gullying). This work falls under a Categorical Exclusion for
NEPA documentation – it could proceed regardless of any decision for the fuelbreaks being
analyzed in this report. Overall, it will benefit water quality.
Direct and Indirect Effects on Soils and Streams, by Treatment Area
The effects conclusions are based on the description of the effects of the individual activities,
above, and on WEPP modeling presented in Table 3.8-6.
Table 3.8-6. Summary of Disturbed WEPP modeling results for selected fuelbreaks. The sediment
delivered estimate is for a 15-year return period event.
Fuelbreak
Pre-Treatment
(Existing Condition) Post-Treatment
Sediment
delivered
(t/ac)
Probability of
sediment
delivery
Sediment
delivered
(t/ac)
Probability of
sediment
delivery 1st
yr
Powerhouse 0.0163 13% 0.0023 10%
Beal 0.0139 17% 0.0005 13%
Vincent 0.0000 3% 0.0416 10%
Burrough 0.0003 20% 0.1685 23%
Lerona 0.0010 17% 0.0006 13%
Shaver Springs 0.0000 3% 0.0668 17%
Jose Basin Road Brushing –Because hand cutting, hand piling, and pile burning would have limited effects on soils and streams, the treated area will be small, and piles will not be burned in channels or on streambanks (see BMP 1-22), the effects in this treatment area will be minimal. This fuelbreak was not modeled with WEPP.
Powerhouse Road Brushing and Powerline Fire Line – Within 50 feet of the road on both sides (a total of 48 acres on NFS lands), brush would be cut with a chainsaw, hand piled, and burned. The Powerline Fire Line would be created by hand scraping to create a 3-foot wide fire line above the road, in the right-of-way (within 20 feet of the road), for a total of less than 1 acre cleared. Roads 9S313 and 9S313A would be maintained following normal road
Environmental Assessment Page 21 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
maintenance practices. Because hand cutting, hand piling, pile burning, and constructing hand line have limited effects on soils and streams, the effects in this treatment area will be minimal. Hand line construction near streams will follow BMPs 1-17 and 6-3 (see Appendix 1) to ensure that effects are minimized. Routine road maintenance may increase sediment movement in the short-term, but in the long-term will minimize erosion and sediment delivery from the treated roads. This fuelbreak was not modeled with WEPP.
Powerhouse Fuelbreak - This new fuelbreak would be created with dozer treatments. The dozer work will result in soil displacement, possibly a decrease in porosity, and decreased groundcover/organic matter. Because the work will be conducted when soil moisture conditions will limit soil disturbance and loss of porosity, and a minimum of 50% well-distributed groundcover will be left on the site, impacts to soils will be minimized. The WEPP model shows essentially no effect on sediment delivery to an adjacent spring channel post-treatment, with results indicating the probability decreased from 13% to 10% in the first year after treatment, and the quantity also decreased slightly. Burning of the piles is not expected to result in stream channel or off-site effects.
Beal Fuelbreak – This existing fuelbreak encompasses 361 acres. It would be maintained using the most practicable of the described possible treatment techniques, depending on the condition of the vegetation when implemented. At this time, mastication is the anticipated treatment. Disturbed WEPP modeling results for a slope draining to a perennial stream channel shows no increase in the potential for erosion or sediment delivery following treatment. Routine road maintenance of 10S307 may increase sediment movement in the short-term, but in the long-term will minimize erosion and sediment delivery from the treated roads.
Vincent Fuelbreak – This existing fuelbreak encompasses 1276 acres. It would be maintained using the most practicable of the described possible treatment techniques, depending on the condition of the vegetation when implemented. Hand work will be used upslope of Peterson Mill Road. Mastication is the anticipated treatment on the remainder of the area. Disturbed WEPP modeling shows an increase in the probability of some sediment delivery through a 25 foot SMZ to a stream channel, from 3% under the existing condition to 10% the year following treatment, assuming 50% groundcover remaining. This is the minimum required groundcover: however, mastication typically leaves a higher percent ground cover than this, which would minimize this change.
Burrough Mountain Fuelbreak – This existing fuelbreak encompasses 1666 acres. It would be maintained with a mastication treatment. Disturbed WEPP modeling results for a masticated swale draining to the downslope stream channel shows an increase in both the quantity and the probability of sediment delivery to the channel, from 20% under the existing condition to 23% the year following treatment, assuming only 50% groundcover remains. Mastication typically leaves a higher percentage of groundcover than this, which would minimize this change. Routine road maintenance of roads 10S09, 10S09A. 10S09B, and 10S09BA may increase sediment movement in the short-term, but in the long-term will minimize erosion and sediment delivery from the treated roads.
Lerona Fuelbreak – This existing fuelbreak encompasses 200 acres. It would be maintained using the most practicable of the described possible treatment techniques, depending on the condition of the vegetation when implemented. At this time, mastication is the anticipated treatment. Disturbed WEPP modeling results of a 200 foot slope draining to a channel with a 50 foot SMZ shows no increase in either the quantity of sediment eroded by a 15-yr event or in the probability of sediment delivery, even assuming 50% cover which is probably lower than will result from mastication. Repairing the drainage structures on the
Environmental Assessment Page 22 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
dozer trail through this area would greatly reduce erosion; however, the sediment being eroded is not currently affecting water quality, so there would be no decrease in impacts to streams or to CWEs as a result of this work.
Upper Sycamore Fuelbreak – This is an existing fuelbreak that would be maintained with dozer treatments. This fuelbreak was not modeled with WEPP because it is very similar to Shaver Springs (see below) and is expected to have similar effects.
Shaver Springs Fuelbreak – This existing fuelbreak encompasses 773 acres. It would be maintained using the most practicable of the described possible treatment techniques, depending on the condition of the vegetation when implemented. This is expected to be dozer piling. Disturbed WEPP modeling results for a continuous 675 foot long treated slope draining through a 75 foot SMZ to a stream channel shows an increase in the probability of sediment delivery to the stream from 3% under the existing condition to 17% in the year following treatment. This illustrates the importance of treating long slopes discontinuously / in patches to avoid creating a disturbance along such a long flow path.
Cumulative Effects on Soils and Streams, at the Subdrainage Scale (CWEs)
A CWE Assessment was conducted following FSH 2509.22. All of the past, present, and
reasonably foreseeable activities listed in the EA, and the existing condition of each
subdrainage, were considered in an evaluation of existing CWE concerns. Previous ERA
analyses were utilized where available. Based on this information, 9 of the 23 subdrainages in
the project area may currently be experiencing CWEs. In addition, each subdrainage was
considered to determine whether this project would increase the likelihood or severity of CWEs.
For this determination, the natural watershed sensitivity, percent of the watershed planned for
treatment and the anticipated effects of treatment, and what is known about the existing
condition including existing data, NAIP imagery, recent channel and subdrainage observations,
and field assessment of the proposed treatment areas was used.
This project may influence CWEs in 2-3 of the 23 subdrainages. A summary of these
evaluations is displayed in Table 3.8-7, and a paragraph containing rationale for each
subdrainage follows the table. The rationale builds on the beneficial uses and the description of
the current condition in the Affected Environment section.
Table 3.8-7. Summary of the CWE Evaluation of the High Sierra Fuelbreak Project.
HUC8 # Total
Acres
Gross
Treatment
Acres
Max.
Percent
Treated
Natural
Sensitivity
Existing
CWE
Concerns?
Project May
Contribute to
a CWE
Response?
518.00051 2037 387 19% Moderate N Y*
518.00101 2520 943 37% High Y Y
518.0011 2173 236 11% High Y N
Environmental Assessment Page 23 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
HUC8 # Total
Acres
Gross
Treatment
Acres
Max.
Percent
Treated
Natural
Sensitivity
Existing
CWE
Concerns?
Project May
Contribute to
a CWE
Response?
518.0012 2771 211 8% High Y N
518.00541 1607 76 5% High N N
518.00551 1779 469 26% Moderate N N
518.20011 2530 1009 40% High Y Y*
519.30531,2
2083 9 0.4% Moderate Y N
523.0001 1586 85 5% High Y N
523.0003 1516 53 4% High Y N
523.0005 537 12 2% High Y N
523.00061,3
1058 49 5% Moderate N N
523.00101,3
2436 11 0.4% High N N
523.0011 3068 2 <0.1% High N N
523.00121 1849 76 4% High N N
523.00151 1536 141 9% High N N
523.00521,3
2019 38 2% High N N
523.00531,3
2553 105 4% High N N
523.30011,4
546 12 2% High N N
525.0002 1378 113 8% High N N
525.00031 893 113 13% High N N
525.0052 1613 299 18% High N N
525.0053 2432 53 2% High Y N
* If dozer treatment is used instead of the anticipated mastication treatment. 1 These subdrainages were evaluated for the Travel Management Project CWE analysis in 2009.
2 This subdrainage was evaluated for the Kings River Project CWE analysis in 2006.
3 These subdrainages were evaluated for the Patterson Bend Range Allotment CWE analysis in
2006. 4 This subdrainage was evaluated in the Sugarloaf Range Allotment CWE analysis in 2006.
Environmental Assessment Page 24 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
518.0005 – Although almost 20% of the subdrainage is in the Burrough Fuelbreak area,
because areas steeper than 35% and stream buffers will not be mechanically treated, the actual
proportion of disturbed area will be smaller. The anticipated treatment of mastication is expected
to have minimal impacts on erosion and hydrology because it leaves adequate groundcover.
Because of this, and considering the BMPs that will be implemented, this project is not likely to
influence CWEs in this subdrainage. If tilling or dozer piling treatment is used instead of
mastication, following BMPs for remaining groundcover and stream buffers will be even more
important for minimizing impacts. With these treatments, there is a slight risk of this project
increasing the potential for CWEs in the short term (approximately 2 years), until ground cover
is reestablished by grass and other vegetation.
518.0010 – Because Shaver Springs and Upper Sycamore are both anticipated to be treated by
dozer piling, and these units are almost entirely on sensitive soils, careful operation and strict
adherence to BMPs are critical for minimizing impacts and preventing contributions to CWEs.
This subdrainage has a short-term risk of treatment influencing CWEs (for about 2 years after
treatments). The effects could be expressed as short-term sedimentation impacts to aquatic
habitat in Sycamore Creek. The risk would be reduced by minimizing the total disturbed area,
distributing ground disturbing treatment in a mosaic pattern, strict adherence to SMZs and other
BMPs, and leaving as much groundcover as possible (with 50% being the minimum allowable,
but 60-70% being more desirable from a soil and hydrology standpoint).
518.0011 – Proposed treatments in this area include a portion of Vincent, proposed for
mastication, and a small piece of Upper Sycamore, planned as a dozer piling treatment.
Because this portion of Upper Sycamore is small and has only a few first order channels which
will receive SMZs if warranted, this is not likely to influence CWEs. The mastication in Vincent
will leave adequate groundcover as well as adhering to SMZs, making it unlikely to influence
CWEs.
518.0012 – Since the untreated stream buffers currently visible in the Burrough Fuelbreak will
remain, and a portion of the remaining area is greater than 35% and will not be treated, the
limited amount of disturbance that will result from this project combined with the BMPs that will
be implemented make it unlikely that this project will influence CWEs in this subdrainage.
518.0054 – A portion of the Burrough Fuelbreak is in this area, and contains first order channels
and one second order reach. Given the BMPs that will be implemented, it is unlikely that this
project will influence CWEs in this subdrainage.
518.0055 – A large amount of the Burrough Fuelbreak is in this subdrainage, but almost half of
the area is over 35% slope and will not be mechanically treated. These steep slopes appear as
dense brush areas on the imagery. A portion of Vincent is also in this subdrainage. All
anticipated treatments are mastication, which leave adequate groundcover. Combined with
SMZs and other BMPs, these treatments are not likely to influence CWEs in this subdrainage.
518.2001 – The majority (about 1000 ac) of the Vincent Fuelbreak is in this subdrainage. About
300 ac of the total treated area will be hand cut and piled for burning. The remaining 700 ac
(minus SMZs and rock outcrop areas) is anticipated to be treated by mastication. With careful
Environmental Assessment Page 25 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
implementation of all applicable BMPs, this project is not likely to influence CWEs in this
subdrainage. Because of the large proportion of this subdrainage that will be treated, if tilling or
dozer piling treatment is used instead of mastication, following BMPs for remaining groundcover
and stream buffers will be even more important for minimizing impacts. With these treatments,
there is a slight risk of this project increasing the potential for CWEs in the short term
(approximately 2 years), until ground cover is reestablished by grass and other vegetation. The
effects could be expressed as short-term sedimentation impacts to aquatic habitat in Sycamore
Creek.
519.3053 – Although CWEs are currently occurring here, due to the very small amount of
treatment that will occur here, associated with the Vincent Fuelbreak, the location of the
treatment area near a ridgeline, and implementation of BMPs, it is unlikely that this project will
influence CWEs in this subdrainage.
523.0001 – Portions of the Beal Fuelbreak are in the area, and previously treated areas are
visible on imagery. WEPP modeling supports that the project is not likely to influence CWEs in
this subdrainage.
523.0003 – This area contains portions of the Beal Fuelbreak, which include some first order
channels. Given the limited amount of treatment, its location in relation to channels, and the
BMPs that will be implemented, it is unlikely that this project will influence CWEs in this
subdrainage.
523.0005 – This subdrainage contains a portion of the Powerhouse Fuelbreak. Given the
location and limited amount of treatment in this subdrainage, the BMPs that will be implemented
during the treatment, and the highly disturbed context, it is unlikely that this project will influence
CWEs here.
523.0006 – A portion of the Powerhouse Fuelbreak and the Powerhouse Road treatments will
occur in this area. The Powerhouse Road treatments are hand work with limited potential for
impacts. The Powerhouse Fuelbreak contains a few first order channels. However, given the
BMPs specified for their protection, it is unlikely that this project will affect CWEs.
523.0010 – A small portion of the Powerhouse Fuelbreak and a section of the Jose Basin Road
treatment are in the area. Because of the very small percentage of the subdrainage being
treated, and given the BMPs that will be implemented, it is unlikely that this project will influence
CWEs in this subdrainage.
523.0011 – The Jose Basin Road treatments that will occur in this subdrainage involve hand
work and pile burning in a limited area comprising a very small portion of the subdrainage – it is
very unlikely that this project will influence CWEs in this subdrainage.
523.0012 – The Jose Basin Road treatments that will occur in this subdrainage involve hand
work and pile burning in a limited area – it is very unlikely that this project will influence CWEs in
this subdrainage.
523.0015 – The subdrainage contains part of the Lerona Fuelbreak and a portion of the Jose
Basin Road treatment area. Previously treated portions of Lerona are visible on the NAIP
imagery. Given the location of the Lerona fuelbreak with respect to stream channels, and the
Environmental Assessment Page 26 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
limited impacts that will result from the hand treatments in the road treatment area, it is unlikely
that this project will influence CWEs in this subdrainage.
523.0052 – Although excess sediment from the ditch failure may have triggered a CWE
response, the anticipated effects of this project, given the location with respect to stream
channels, the specified BMPs, and the limited impacts associated with the hand work along the
road, are not likely to influence CWEs in this subdrainage.
523.0053 – The Powerhouse Fuelbreak lies along the ridgeline between this subdrainage and
523.0006. Part of the Powerhouse Road work is also in this subdrainage. The Powerhouse
Fuelbreak contains a few first order channels. However, given the BMPs specified for their
protection, it is unlikely that this project will affect CWEs.
523.3001 – Given the limited area and nature of the treatments in this area (hand piling and
burning in a narrow road corridor) and the low natural sensitivity, it is unlikely that this project
will influence CWEs here.
525.0002 – Given the locations of the treatment areas, the BMPs for the project, and the
relatively small amount of area to be treated, it is unlikely that the effects of this project will
influence CWEs in this subdrainage.
525.0003 – Proposed treatments in this subdrainage include the portions of Beal near Buckeye
Heliport and along Tollhouse Road, and the northern tip of Burrough. The previously treated
areas are visible on the imagery. Given the locations of the treatment areas and the BMPs for
the project, it is unlikely that the effects of this project will influence CWEs in this subdrainage.
525.0052 – About 30 ac of Beal and 270 ac of Burrough are in this subdrainage, and previously
treated areas are visible on the imagery. Some of the treatment areas are on sensitive soils. A
portion of the Burrough acreage is the hand-treatment area, and some is greater than 35%
slope and will receive no treatment. Given the locations of the treatment areas and the BMPs for
the project, it is unlikely that the effects of this project will influence CWEs in this subdrainage.
525.0053 –Two percent of the area is in the Burrough Fuelbreak. The treatment area contains
one first order channel that has an untreated buffer area surrounding it. A portion of the area is
greater than 35% slope and will not be treated. Given the extensive modification of this
subdrainage and the small area to be treated, as well as the BMPs for the project, it is unlikely
that the effects of this project will influence CWEs in this subdrainage.
RCO Consistency
RCO Consistency is discussed fully in the Riparian Conservation Objectives Consistency
Report for this project (Appendix 2 of the Watershed Specialist‟s Report). This project will
involve mechanical treatments and burning within the RCAs. Mitigation measures were
developed and incorporated as design criteria to be implemented under all action alternatives.
These design criteria were developed specifically to minimize the risk to the aquatic and riparian
systems. The Riparian Conservation Objectives Consistency Report (Appendix 2) concludes
that the project is consistent with RCOs.
Environmental Assessment Page 27 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
Alternative 2 No Action
Direct and Indirect Effects on Soils and Streams
There would be no direct or indirect effects on soils or streams as a result of the No Action
alternative. Soil quality and stream indicators would remain unchanged.
There is however a greater risk of high burn severities resulting from wildfire in untreated areas
than from either prescribed burning (MacDonald and others 2004) or from wildfire on treated
fuelbreak areas (Graham and others 2009). Many investigations of wildfire effects on hydrologic
processes have found increases in stream flows and in sedimentation. MacDonald and Stednick
(2003) state that wildfire poses the biggest threat to water quality in forested areas. Changes in
soil properties such as removal of organic ground cover and creation of water repellent,
(hydrophobic) conditions result in decreased infiltration capacity and increased runoff, which
leads to larger and flashier peak flows and more erosion on hillslopes. Robichaud and others
(2000) state that surface runoff can increase by 70% and erosion by three orders of magnitude
when ground cover is reduced from 75% to 10%. Fire severity has a large effect on erosion and
sediment yields. In a study of post-fire erosion from simulated rainfall, Benavides-Solorio and
MacDonald (2001) found that sediment yield from high burn severity plots was 10-26 times
greater than from low severity and unburned plots. Ground cover accounted for 81% of the
variability, including lower sediment yields found in older, recovering burned areas. Sediment
yield increases are usually the highest the first year following a fire (Robichaud and others
2000), then decease as groundcover increases, vegetation becomes established, and water
repellency recovers. Robichaud and others (2000) found that summer peak flows in chaparral in
Arizona increased 5 – 15 fold after a wildfire, but winter peak flows did not change. They
attribute this to less intense precipitation and less water repellency during the winter season.
Cumulative Effects on Soils, Streams, at the Subdrainage Scale (CWEs)
Although there would be no incremental direct or indirect effects to soils or streams that would
contribute to cumulative effects under this alternative, there would be an increased likelihood of
intensive fire suppression techniques, such as multiple-pass dozer lines and heavy retardant
drops, being utilized in and around the fuelbreaks. Minimum Impact Suppression Techniques
(MIST) are recommended, but they are not required, and are often not employed in areas where
homes are at risk. Direct impacts to stream channels are more likely to occur from these
suppression activities than from the proposed treatments, for which BMPs are required.
For these reasons, the long-term risk of CWEs may be higher without fuelbreak maintenance
(under this alternative) than with fuelbreak maintenance (in Alternative 1 or 3).
RCO Consistency
This alternative is consistent with RCOs. The Riparian Conservation Objectives Consistency
Report for this project does not specifically analyze the No Action alternative, however, no
disturbance would result in RCAs from this alternative.
Environmental Assessment Page 28 of 28 August 2011 High Sierra Fuelbreak Maintenance Project USDA Forest Service
Alternative 3 No Herbicide Treatment
Direct and Indirect Effects on Soils
The direct and indirect effects on soils would be the same as described under the effects of
Alternative 1, with the exception that no herbicides would be used. This would result in repeated
entry with mechanical treatments such as mastication and dozer piling, which have a higher
potential for causing soil disturbance.
Direct and Indirect Effects on Streams
The direct and indirect effects on streams would be the same as described under the effects of
Alternative 1, with the exception that no herbicides would be used. This would result in repeated
entry with mechanical treatments such as mastication and dozer piling, which have a greater
potential for causing impacts to streams.
Cumulative Effects on Soils, Streams, at the Subdrainage Scale (CWEs)
The cumulative effects on soils, watershed, and water quality could be different than described
for Alternative 1. More repeated entries of mechanical equipment could result in incremental
changes in cover, porosity, and organic matter that would cumulatively result in changes in soil
quality. Individual direct disturbances to stream banks that result from each entry could present
a similar scenario, with a few added during each entry that over time could begin to exert some
influence on water quality (sediment supply) or even localized channel stability. More frequent
equipment entries equate to more frequent risk of chemical constituents such as oil and grease
being accidentally introduced into streams, and if introduced into adjacent channel or to one
channel numerous times, could have a larger impact on beneficial uses than an isolated incident
would have.
In terms of downstream CWE response, this alternative would be very similar to described for
Alternative 1. Even if the cumulative effects described above do occur, the impacts would likely
be on-site or in the same stream reach. Implementation of BMPs is expected to prevent
widespread or severe cumulative effects from occurring that would propagate downstream and
cause perceptible cumulative impacts off-site.
RCO Consistency
This alternative is consistent with RCOs for the same reasons described in Alternative 1. See
the RCO Consistency Analysis (Appendix 2 of the Watershed Specialist‟s report) for the full
analysis rationale.