Section 24 - SCADA Rev 1.pdf

Embed Size (px)

Citation preview

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    1/30

    Wastewater Standard Technical Specification

    Section 24SCADA

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    2/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    ContentsPage

    24 SCADA 1

    24.1

    Hardware Requirements 1

    24.2 Software Requirements 2

    24.3 Alarms 7

    24.4 Security 9

    24.5 Reports 10

    24.6 SCADA System Tests 25

    24.7 SCADA System Colour Coding 26

    ppendices

    Appendix A

    SCADA Performance Requirements

    A1

    APPENDIX 1

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    3/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 1

    24 SCADA

    This document details the standard requirements for the SCADA system.

    SCADA systems provide detailed, local site and process alarm reporting, monitoring and

    process control facilities for treatment works installations where specified.

    Data collected by the SCADA system is retained locally and is not routinely transferred off

    site. However, access to this data from a remote location shall be possible via a Wide Area

    Network connection to a Corporate Network, and via the SCADA remote access facilities.

    Data shall be continuously acquired by the SCADA system through a network interface(s) to

    the PLC systems installed on the plant. This data shall be held in a real time database by

    the SCADA system. Some or all of this data shall be stored to provide historical information.

    SCADA data shall be displayed on either the local SCADA system or where specified, on a

    remote workstation in the form of alarm lists, mimics, trends and reports.

    Any SCADA system fitted with a remote terminal or client shall support at least two

    simultaneous users.

    24.1 Hardware Requirements

    24.1.1 Computer Specification

    The contractor shall provide a personal computer for use as a SCADA computer. The

    personal computer shall include the following items:

    3.5 inch 1.44MB floppy disk drive.

    CD-RW compact disk writer for archive purposes.

    PLC network interface card.

    An appropriate number and type of serial and parallel interfaces for peripherals.

    The contractor shall evaluate the performance requirements for the particular application

    and shall ensure that the hardware specification does not unduly limit the performance of

    the SCADA system, taking into consideration applications such as report generators running

    concurrently with the SCADA software.

    The contractor shall also confirm that the hardware platform meets the recommended

    system requirements specified by the relevant software vendors.

    The supplied PLC network interface card supplied shall be as recommended by the PLC

    manufacturer. The relevant supporting software shall be installed and configured to enable

    direct communications with the supplied PLCs.

    Sufficient solid-state memory shall be provided so that swapping of data with disc store is

    minimised and performance levels achieved. The computer shall be configured to operate

    from 230/240V AC 50Hz supply.

    Unless otherwise stated, all SCADA and associated equipment shall be supplied from a

    UPS.

    Unless otherwise stated, the specification of the computer shall be such that when fully

    programmed and operational it complies fully with the performance requirements stated in

    Appendix 1 of this specification.

    The level of redundancy shall be as detailed in the Particular Specification.

    24.1.2 Specification

    The contractor shall supply printers for use as SCADA equipment.

    All printers shall be capable of being supplied from a 230/240V AC 50Hz supply.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    4/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 2

    Printers shall be provided with a suitable paper feed with the capacity of at least 100 sheets,

    and a receptacle for printed output.

    Screen Printer - An ink jet colour printer shall be provided complete with an A4 sheet feeder

    mechanism and a suitable stand and configured so as to be able to produce full colour

    accurate representations of screen displays, including mimics, trend displays and reports.

    Alarm / Event Printer A dot matrix printer shall be provided complete with a paper feed

    mechanism suitable for use with continuous feed paper and a suitable stand so as to be

    able to print alarm print outs.

    24.1.3 Equipment Environment Requirements

    The environmental specification of the SCADA equipment (including associated peripherals)

    and the specification of location in which it is to be located shall be matched such as to

    ensure that the SCADA equipment environmental specification is not exceeded.

    24.1.4 Furniture

    The contractor shall provide furniture in accordance with the requirements of the particular

    specification.

    24.1.5 Equipment SecurityThe SCADA system shall be located in a suitable control room or other secure location.

    24.2 Software Requirements

    The following shall be provided:

    PLC network interface software, as recommended by the PLC manufacturer

    the operating system used on all SCADA installations shall be as agreed with the

    Employer and as recommended by the SCADA application supplier

    All documentation, including but not limited to software licences and licence keys,

    associated with the above software shall be provided to the Employer.

    All software shall be licensed to the Employer by the contractor.

    Software licences shall cover application run time and configuration.

    House keeping shall be automatically performed by the SCADA system. All operating

    system temp (.tmp) files and other system temporary files shall be deleted automatically on

    a regular basis.

    Where a symbol and or a dynamo do not exist for a specific application a symbol or dynamo

    shall be designed and submitted to the Engineer for approval.

    24.2.1 Disaster Recovery

    A disaster is defined as a complete failure of the SCADA system.

    A disaster recovery system and procedure shall be provided. A description shall be

    submitted in the FDS to the Engineer for approval.

    An additional (back-up) hard disc drive shall be provided for each computer supplied. Upon

    successful commissioning of the system, the complete contents of all active hard drives are

    to be copied to back-up drives.

    The disaster recovery procedure shall be fully described in the O&M manual.

    As part of the FAT and SAT the contractor shall be required to demonstrate the disaster

    recovery procedure as described in the O&M manual.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    5/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 3

    Alternative disaster recovery methods may be offered by the contractor and shall be fully

    described in the contractors tender / scope submission.

    24.2.2 SCADA system configuration start up and power failure recovery

    On start up or on resumption after power failure on the whole or any part of the plant, the

    system shall automatically self start, configure, connect to all external communications links

    and display the main menu.The user shall not have to enter configuration data or initialisation commands during the

    start up process or operating period. The system shall retain all settings that have been

    previously set by the user. The FDS (at the design stage) and the Operational and

    Maintenance Manuals (at As Built stage) shall list all such settings for the Engineers

    approval.

    After shutdown or on loss of power, or on resumption after loss of power, all totalised and

    other calculated values shall be retained and redisplayed. All log files and values shall also

    be available and uncorrupted.

    The system set-up shall include the disabling of the auto run facility for CD-ROM.

    24.2.3 Configuration

    The contractor shall be responsible for the configuration and integration of all hardware, and

    communications, and shall also be responsible for all software installation and configuration

    including disk and memory allocation to meet the functional requirements of the system.

    The Contractor shall submit details of the database configuration displays, trends, reports

    etc for approval as part of the Functional Design Specification (FDS).

    24.2.4 Configuration Details

    24.2.4.1 Mimics

    All mimics shall display a menu tool bar at the top of the screen capable of providing the

    following facilities: Login/logout, Alarm list summary Display, Event log display, Trend Menu

    display, Main Menu Display, System Menu Display.

    The contractor shall configure sufficient mimics to cover the entire plant. Mimic pages shall

    show an overview of the whole plant.

    The plant shall be broken up into logical areas with at least one mimic page per area. Each

    mimic shall show all controlled and monitored plant within the area that it covers.

    In general, the mimic shall resemble the P&I diagram. Unmonitored or uncontrolled plant

    shall be shown where a contribution to the process is made by this plant.

    All plant shown shall have its tag number displayed on screen as close as practicable to the

    plant item icon.

    The operator shall be able to move between mimic pages by two methods, either by directly

    selecting the page from the overview graphic or by navigating through the plant using

    graphical buttons on the input or output links of mimic pages. These buttons shall clearlyshow in graphics or text the screen that will be selected if the button is pressed.

    Mimics pages shall be of 2 distinct types: process pages (chained from the Main Menu

    Overview Screen) or system and diagnostic pages (chained from the System Menu

    Overview Screen).

    The contractor shall not locate his company name or logo or any other form of advertising

    on any of the mimic screens. The contractors name and contact details shall be configured

    on the system start up screen.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    6/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 4

    The engineering units associated with each reported value on the mimic shall be displayed

    beside the value.

    Where the run / stop status of pumps is monitored, all pumps shall have their running hours

    totalised. The run hours shall be displayed on a different mimic / graphic.

    Diagnostic mimic pages shall be configured to monitor the status of all the PLC I/O modules

    and all PLC network communications statistics. Each slot shall be clearly identified by slot

    number and card type and the I/O signals identified by number and name. The mimic shall

    also display for each I/O point:

    The raw PLC value

    Engineering unit value, default value (if a default is specified) and if the default is in use

    24.2.4.2 Graphical User Interface

    The graphical user interface will provide facilities for both process monitoring and control.

    The facilities will be provided to monitor plant status, start and stop plant and change plant

    process set-points.

    It is intended that all mimics will have a common look and feel as far as is possible. Mimics

    will consist of three main types.

    24.2.4.3 Overview Mimics

    The Overview Mimics are the 'gateway to the Detail Mimics. They will not display any

    detailed information, although the Overview Mimic for an area of plant may indicate the most

    important status information.

    24.2.4.4 Detail Mimics

    The Detail Mimics will show detailed status of all of the dynamic equipment on the plant. All

    of the required monitoring and control facilities will be available from these screens.

    24.2.4.5 Pop-up Mimics

    Pop-up mimics will be partial page mimics that are selected from detail mimics. They will

    normally be associated with plant items.The system structure will be such that all full-page mimics should be accessible within 4

    selections from any other mimic in the system

    The user interface will be via a keyboard and 'pointing device. Typically the 'pointing device

    will be a mouse or tracker ball.

    Plant items on detail mimics may be selectable items. Plant items, which are selectable, will

    be outlined in grey when the pointing device is over them.

    Selection of individual plant items will display a pop-up mimic. This would be a face plate

    type mimic for most plant items, from which further pop-up mimics may be selected using

    windows buttons. The faceplate would facilitate the calling of the following options.

    Control Pop-up - will facilitate the manual control of plant items, when it is appropriate.

    Trend Pop-up - will display a real time trend of a selected analogue plant instrument.

    PID Pop-up - will display the current PID parameters associated to a control loop.

    Statistics Pop-up - will display the current running hours, no. of starts etc. for a plant item.

    Plant equipment which only has one option (i.e. an instrument may only have trend

    information) will go directly to the appropriate pop-up without the need for a faceplate. Only

    one pop-up mimic may be open at any time. When a detail mimic is closed any pop-up

    mimic, which is displayed at the time must also be closed.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    7/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 5

    24.2.4.6 General Mimic Discipline

    This section will detail the general graphical rules for the generation of mimics, most will

    also be relevant to pop-up mimics.

    Each mimic will have a title bar, which, along with the mimic title, will display the time, date

    and the numbers of unacknowledged and total alarms. The site name will also be displayed

    within the title bar. Every full-page mimic will have a 'Help' button on the right hand side of

    the title bar.

    An alarm banner consisting of the three most recent alarms will exist at the bottom of the

    page; the banner will be the full width of the screen. Above the alarm banner will be a

    function key banner. The function keys F2 to F9 and F11 to F12 will be displayed. Function

    keys F1 and F10 are not used as they have reserved functions within Windows.

    The following rules should be observed in the creation of full-page mimics:

    [1] The filenames used for graphics must be meaningful text

    [2] All screen development shall be based upon a screen resolution of 1024 by 768 pixels.The screen size shall be 17"

    [3] Graphics will be drawn in two dimensions

    [4] All process flow lines shall be vertical or horizontal

    [5] Process flow lines shall be the appropriate process colour. Process lines shall not beanimated in any way

    [6] Process flow shall be from left to right, unless it is unavoidable or would reduce clarity.Sufficient process coloured direction arrows will be super-imposed on the process flowline to ensure clarity

    [7] The crossing of flow lines shall be avoided. Where it is unavoidable, the vertical flow lineshall have breaks either side of the horizontal line. These breaks will be as small aspossible to maintain clarity and of a uniform size

    [8] All process flow lines shall be of a uniform thickness; there shall be no increase in sizeat process flow lines junctions. Line thickness for process flow lines shall be 3 points(pixels)

    [9] Text shall be lower case with leading upper case. The exception to this being equipmenttags names which shall be all upper case

    [10] Equipment status shall be displayed in a graphical manner and through the use ofcolour of the appropriate symbol. Process critical and alarm conditions shall not beindicated by colour alone

    [11] Tag names and status words shall both be inserted below or to the right of equipment

    symbols. Where either position would be possible, the preferred position is below thesymbol

    [12] Static symbols shall only be shown on mimics where they are necessary to aid overallclarity. When it is necessary to show static symbols they shall be drawn in black

    [13] Selectable area on any screen will be highlighted in a grey rectangle when the pointingdevice passes over the area

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    8/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 6

    [14] Where possible common features on mimics shall be placed in consistent positions.This will include Help, Trend and Alarm summary selection

    [15] Pop-up mimics will not be sizeable and should appear on detail mimics in such aposition so as not to obscure the plant item to which they refer

    24.2.4.7 Main Overview

    The Main Overview is the top-level mimic, which will be displayed when the system is firststarted. It should be possible to return to this Overview mimic from any other mimic by a

    single action from the keyboard or pointing device. The 'F2' function key on every other

    mimic shall be used for this purpose.

    The main overview will be used as the 'gateway' to either detail mimic or to lower level

    overview mimics, this will be dependent on the complexity of the installation.

    The 'F4' function key on this mimic will be used to select the 'Operator Log-In' pop-up mimic.

    24.2.4.8 Process Overview

    Process overviews shall be provided for more complex installations, these will allow direct

    access to the detail mimics. Smaller installations will have the functionality of the process

    overview combined into the main overview.The process overview shall be developed in such a way as to portray the physical plant

    layout. Each area of plant would be illustrated as a 'box' on the mimic, showing the main

    process flow lines between the areas of plant. Essential information may also be

    represented on the mimic.

    The appropriate detail mimic will be selected by clicking the pointing device on the

    appropriate box, which represents the required plant area. It should be possible to return to

    the process overview from any given detail mimic by a single action from the keyboard or

    pointing device. The 'F3' function key shall be used for this purpose.

    The box representing each area of plant shall be a grey button, having a border, which will

    only be visible when an alarm is present in that area of plant. The general area alarms for

    this purpose shall be generated within the PLC and not within the SCADA. When clicked,

    the button shall activate the appropriate screen.

    24.2.5 Symbols

    A standard symbols library shall be developed in conjunction with the Engineer.

    24.2.6 Screen Navigation

    Navigation shall be developed in conjunction with the Engineer.

    This is the method by which the operator will select new full-page mimics and call up partial

    page pop- up mimics from full-page mimics.

    24.2.6.1 Function Key Bar

    The function keys will be selectable using the keyboard or the pointing device. These keyswill generally be used to select the standard full page mimics that should be selectable fromevery mimic. They will include:

    F2 Main Overview

    F3 Process Overview (If required)

    F4 Return / Login (on Main Overview)

    F5 Spare (Project Configurable)

    F6 Spare (Project Configurable)

    F7 Communication Status

    F8 Trends

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    9/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 7

    F9 Alarms Log

    F10 Access to Supervisor level and above

    F11 Alarm Summary

    F12 Alarm Reset

    The remaining function keys, which have not been specified, may be used on a project

    specific basis. These keys shall not be used to navigate between detail mimics.

    24.3 Alarms

    Alarms of all types generated by the system shall be time-stamped at SCADA to an

    accuracy of one second.

    The SCADA system shall be able to receive and respond to incoming alarms at any time

    and under any prevailing operating conditions, including the routine polling cycle, within the

    response times defined by the specified performance requirements in Appendix 1.

    The Contractor shall define the priority of all alarms and submit to the Engineer for approval.

    Upon approval, the definitive list shall be incorporated into the FDS.

    The Contractor shall define alarm groups and assign each alarm to an alarm group. This list

    shall be submitted to the Engineer for approval. Upon approval, the definitive list shall be

    incorporated into the FDS.

    An alarm list shall be available to record all alarms and shall enable users to inspect or

    recall alarms in various formats, with the aid of structured query facilities. The alarm list shall

    have a capacity of at least 2000 alarms. The alarm list shall identify as a minimum, the

    source, date and time of occurrence priority and status by colour code.

    On an annunciation of an alarm condition, the operator shall be able to acknowledge alarms

    whilst viewing the alarm list. Provided the condition causing the alarm is no longer present

    the alarm shall be removed from the list and an alarm acknowledged message recorded in

    the event log and if defined within the FDS, additionally sent to the alarm printer. If the

    condition causing the alarm is still present a tick shall be shown beside the alarm message

    on the list and the message will not be removed from the list.

    All alarms shall remain active until acknowledged by the user and must remain on the alarmbanner and summary list in a form, which is clearly displayed until the source of the alarm

    condition has been removed.

    24.3.1 The Alarm Banner

    As a minimum, the alarm messages shall contain the I/O tag name, the I/O point name, the

    text status, Priority, Time and Date. Note that priority shall be indicated by different colours

    for different priorities.

    There shall be a simple means of navigating from the alarm message to the related mimic.

    Only the three most recent active and unacknowledged alarms shall be displayed on the

    alarm banner.

    The format and detailed functionality shall be agreed in conjunction with the Engineer.

    24.3.2 Alarm and Event Log

    All events (including user log in / out and other user activity) and alarms / events detected

    by the system shall be logged and stored in a permanent file, which shall be capable of

    being accessed and viewed by operator level upwards. Event log viewing shall be initiated

    by a button on the menu tool bar.

    Log records shall be kept in a manner such that they are not alterable by any party.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    10/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 8

    Any part of the event log (including during the current day and current time) shall be capable

    of being viewed and/or printed at any time.

    Search and locate facilities (including specification of date range) shall be provided to assist

    the user to locate specific events, tag numbers etc.

    The alarm log shall be divided into logical groups that represent the different elements of the

    process, for example main alarm groups for primary treatment, secondary treatment,

    electricity distribution, etc. Each main group shall be divided into sub-groups as appropriate,

    for example primary treatment might be divided into inlet screens, grit removal, etc.

    The alarm log shall incorporate the facility for the user to view specific alarm groups only as

    well as all alarms.

    The alarm log shall incorporate the facility for the user to view separately the alarms that fall

    into the following categories:

    Active and unacknowledged

    Active and acknowledged

    Inactive and unacknowledged

    Inactive and acknowledged

    For active alarms, the alarm log shall display when the alarm became active and, if

    appropriate, when it was acknowledged.

    For inactive and unacknowledged alarms, the alarm log shall display when the alarm last

    became active and when it became inactive.

    For inactive and acknowledged alarms, the alarm log shall display when the alarm became

    inactive and when it was last acknowledged.

    Log records shall be kept in a rolling event log file, which shall be stored in a reserved

    portion of hard disk space. The amount of hard disk space reserved for the alarm log shall

    be agreed with the Engineer. Alarms shall be stored on a first-in-first-out basis.

    24.3.3 Printing Functionality

    Printers shall be supplied as defined under the Hardware Requirements section of thisspecification. The contractor shall be responsible for the configuration of all printers

    provided.

    Alarm and event log to be printed on request.

    24.3.4 Alarm Priority

    There shall be a facility for defining alarm priorities.

    If alarms are required to be prioritised, then this shall be stated in the Particular

    Specification.

    Alarm priorities shall be agreed with the Engineer.

    24.3.5 Alarm GenerationIt is intended that all alarms shall be generated in the PLC, and then passed to the SCADA

    system as digital signals. This shall include analogue alarm levels, which shall not be

    generated within the SCADA system.

    Plant items which have several alarms associated with them shall also have a general

    failure alarm generated within the PLC. Plant Area general alarms shall also be generated.

    These general alarms shall be used on the mimics to indicate plant item and plant area

    alarms on the process overview mimics.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    11/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 9

    In the event of a major alarm e.g. mains electricity supply failure, an alarm shall be raised

    for this alarm but all consequential alarms shall be suppressed. The alarms to be classed as

    major alarms shall be agreed with the Engineer.

    24.3.6 Alarm Display

    There shall be three separate ways of displaying alarms:

    Alarm Banner This shall appear at the bottom of each full page mimic displaying thethree most recent alarms on the system. Acknowledged alarms shall remain on the

    banner until they are cleared or replaced by more recent alarms

    Alarm Summary This shall be accessible from every full page mimic and shall contain

    up to a full page of the most recent alarms. Alarms shall remain on this page as long as

    they are still current or have not been acknowledged

    Alarm Log This shall show all the alarms regardless as to whether they are still current

    or not. The length of this alarm log shall be configurable

    24.4 Security

    24.4.1 Security Codes

    The contractor shall implement the passwords defined by the Engineer. These shall be

    defined during the design phase.

    24.4.2 Default / Guest

    This user group will only have access to View screens. They will not be able to select

    anything which may effect plant or system operation in any way. This will include the

    inability to acknowledge or reset alarms.

    24.4.3 Operator

    The operator user group will have similar security access to the default and guest user

    groups. In addition it will be possible to change duty selections for items of plant.

    24.4.4 Supervisor

    The supervisor user group will have similar security access to the operator, except that thesupervisor will be able to control all items of plant and change any system set-point. The

    operator will also be able to acknowledge and reset alarms.

    24.4.5 Developer

    The Developer will have access to all areas of the system. This will include the ability to

    close the SCADA application and return to the operating system. There will normally be only

    one system administrator on any site installation. Any new user accounts or modifications to

    the security codes, must be configured by the Developer.

    24.4.6 General Security Considerations

    All installations of the SCADA application will automatically enter the Run mode when the

    system is started. The ability to switch applications, using Ctrl_Alt_Esc or Ctrl_Shift_Esc to

    display the Windows start-up menu, will be disabled in Run mode.

    24.4.7 Archiving and Retrieving

    A utility shall be implemented to allow the supervisor to archive and retrieve data by

    selecting options from a System menu via a button on the tool bar at the top of the screen.

    When it is selected the system shall prompt the supervisor to insert the appropriate CD and

    select the information which is to be archived, e.g. reports, data, events alarms, trends etc.

    By default all trend data, all alarms (of all priorities) and all operator and supervisor actions

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    12/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 10

    shall be archived. The supervisor shall be able to retrieve data by selecting the date of the

    archive file.

    Archive data shall be held in a form that allows it to be retrieved and entered into an Excel

    spreadsheet.

    Data shall normally be archived onto optical disc, but floppy could be selected. Usually the

    optical CD will reside in the SCADA PC ready to archive or retrieve data.

    System data and events / alarms shall be stored on hard disk. The hard disk area reserved

    for data storage shall be managed on a first-in-first-out basis. The amount of hard disk

    space available for data storage shall be agreed with the Engineer.

    Data archive shall be performed automatically by the SCADA system by writing weekly data

    to the optical drive. This process shall be completely automatic, to ensure that the data

    archive is successful, the system shall perform all checking of system devices as required

    and prompting of the supervisor will be performed only to assist with fault diagnosis to

    resolve problems associated with a failure to write archive data. The time at which data

    archive takes place shall be capable of being changed by the supervisor.

    An alarm shall be generated if for any reason the hard disk is nearing full capacity. This

    warning shall be set at 80% of disk capacity. Additionally, an alarm shall also be generated

    via the PLC system to telemetry.

    24.5 Reports

    The software shall provide Operational, Engineering and Management Reports. As a

    minimum these shall include:

    Daily / weekly summated flow

    Min / max / average process data

    Process trends

    Chemical consumption

    Power usage, etc.

    Data on operational plant and process availability

    Any other reports required arising from discussion with Scottish Water on a site basis.

    The reports shall be generated using Microsoft Excel and shall be generated automatically

    and on operator request. They will be stored in electronic format in addition to a printout.

    Selection of the Report button will initiate an instance of Excel for the viewing of System

    reports.

    The printing, saving, closing etc of any report will be provided by the facilities provided

    within Excel.

    Note that it will be the Users responsibility to close any instance of Excel.

    The system reports are to be constructed to a standard layout. These reports are to be

    formatted within Excel. Within Excel the Page can be split into a number of sections. For

    the purpose of these reports the following sections are to be used.

    24.5.1 Page Header

    This contains information that will appear on every page positioned below the report header

    on page one and at the top of every other page. This section should contain the main report

    title positioned centrally on the page.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    13/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 11

    24.5.2 Details Section(s)

    A 'details' section will appear on every page of the report with a new details section on every

    page, i.e. three pages means three details sections. These sections contain all of the details

    contained within each report. The 'details' section should be constructed to allow the

    relevant information to be easily read. A 3pt horizontal Navy line should separate different

    sections within the details section.

    24.5.3 Page Footer

    This will appear at the bottom of every page of the report. This section should contain the

    page number and total number of pages in the format Page 1 of 5. This should be

    positioned centrally on the page. A 3pt horizontal line should be positioned above the page

    number to separate this from the main body of the report.

    24.5.4 System Time

    The SCADA system real time clock shall be synchronised to local time.

    Where a real time clock is required in a PLC / SCADA control application, all PLCs/ SCADA/

    Telemetry shall be synchronised to a single clock source.

    24.5.5 Analogue Dead-bands

    The dead-band of each analogue shall be defined and submitted to the Engineer for

    approval in the FDS.

    24.5.6 System Diagnostics

    The SCADA system shall include internal diagnostics facilities. As a minimum the number of

    communications statistics counters e.g. number of errors, number of packets/bytes sent and

    received, shall be recorded, totalised and displayed on a diagnostic mimic until reset by the

    operator. The reset shall be recorded by a message in the event log.

    Screens shall be provided for I/O diagnostics. E.g. Raw digital inputs and outputs from the

    PLC.

    In PLC network systems, diagnostics screens shall be provided for all PLCs on the network.

    Watchdog timers shall be implemented to monitor the communications for each PLC that

    communicates with the SCADA system. On expiry of a watchdog, a communications alarm

    (relevant to that particular failure) shall be annunciated on both the SCADA system and the

    telemetry outstation.

    24.5.7 Historical and Real Time Trend Graphs

    All process analogues shall be configured for real time and historical trending and logging.

    The system shall allow for one, two, three or four variables to be displayed on the same

    trend. Following discussions with the Engineer, the groups of signals allocated to trends

    shall be as defined in the FDS.

    24.5.8 Standards for Programming

    No programming shall be carried out unless the required functionality cannot be

    implemented by configuration of the supplied software packages. In the event that

    programming is required written approval from the Engineer must be obtained.

    24.5.9 Performance of SCADA System

    The table shown in Appendix 1 shall define the performance requirements.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    14/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 12

    24.6 Fibre Optic Cable for SCADA System

    24.6.1 Scope of this Document

    This specification covers the general requirements to be applied to all Control & Automation

    systems and equipments to be installed within Oman Wastewater Services Company

    projects.

    This document is a guide to the design, installation and testing of different types of fibre

    optic cables including buried, ducted and blown. The Installation of fibre optic cables shall

    be governed by, but not limited to, the provisions specified, and shall be undertaken to high

    standards of workmanship and in a safe manner. This specification shall be utilised with one

    or more of the referenced international standards to complete the COMPANY requirement

    for installation Works. However, it remains the contractor responsibility to ensure the

    complete installation of FOC. This specification shall be used in conjunction with the

    separate related sections of the Electrical Standard Specifications as follows:

    24.6.2 Applicable Standards, Specifications and Codes

    The design of the projects shall comply with the following codes and standards

    British Standards:

    BS 89 Direct acting indicating analogue electrical measuring instruments and

    their accessories.

    BS 381C Colour for Identification, Coding and special purposes

    BS 4794 Control Switches

    BS 6231 PVC Insulated cables for switchgear

    BS 381C Colour for Identification, Coding and special purposes

    International Standards

    EIA-455 Standard Test Procedures for Fibre Optic Fibres, Cables, Transducers,

    Connecting and Terminating Devices.

    EIA-598 Optical Fibre Colour Coding

    IEC 529 Environmental protection

    IEC 793-1 Generic Specification for Optical Fibres

    IEC 794-1- General Specification for Optical Fibre Cables

    IEC 794-2 Product Specifications for Optical Fibre Cables

    IEC 874 Connector for Optical Fibres and Cables.

    IEC 1073 Splices for optical fibres and cables.

    IEC 1218 Fibre optic - Safety guide.

    ITU-T G.652 International Telecommunication Union- Telephony: Characteristic of

    Single mode Optical Fibre Cable

    Omani Electrical Standards.

    All relevant local and Omani regulations shall be complied with. Any item not specifically

    detailed in this Specification, which are necessary to provide a safe and fully operational

    working system, shall be deemed to be included.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    15/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 13

    Company HSE Standards

    All Company Health Safety and Environmental Protection Standards shall be complied with.

    Refer the Document: Construction Safety Standards CSS 01, for further details.

    Compliance with Standards

    All requirement of this specification shall apply except where the manufacturers standards

    are more stringent and then the latter shall apply. If a standard becomes old and a latest

    issue of the same standard is available then the latest issue shall be followed. For any

    deviation from these standards, the written agreement of the Company shall be obtained

    prior to commencing associated engineering or construction work.

    24.6.3 Service and Environmental Conditions

    Temperature:

    Recorded of extreme of site ambient temperature are: +5oC to +50

    oC

    Al ti tude:

    Height above Sea level: 0 - 2000m

    Relative humid ity:

    Highest: 95%

    Lowest: 40%

    Atmosphere:

    The equipment and material are to be suitable for installation in coastal industrial plant

    where the atmosphere is subject to dust storms.

    Mean annual rain fall: 100mm

    Daily average wind speed: 4-5 m/sec

    24.6.4 Priority

    Standards shall take the following priority (in order of highest to lowest):

    The project related technical specification (Shall be attached as Annexure)

    This document ( Standard Specifications )

    International Standards

    Industry Standards

    24.6.5 Safety regulations

    Safety is the most important aspect of a fibre optic cable installation and highest priority

    shall be assigned to the safety issues. These safety recommendations are meant to

    supplement, not to replace, relevant local & national laws, company-specific safety practices

    and other codes and regulations. Some of the key points are:

    - To prevent eye damage, never look into the end of an optical fibre unless a power meter isused to verify that no optical signal is present.

    - Testing for explosive gases and proper ventilation of underground facilities is vital.

    - Capable ventilation equipment must be used according to local regulations & practices priorto installation of FOC cables in underground facilities.

    - A running ground must be used whenever there is the possibility that a voltage may besomehow applied to the cable. The use of compressors for cable blowing requires carefulattention be paid to the safety instruction for the compressor and all compressed air fittings.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    16/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 14

    24.6.6 Definitions

    Technical Terminology

    Macro bend

    A relatively large-radius bend in an optical fibre, such as might befound in a splice organiser/enclosure tray or a fibre-optic cable thathas been bent. The definition of "sufficiently large" depends on thetype of fibre. Single-mode fibres have a low numerical aperture,typically less than 0.15, and are therefore are more susceptible tobend losses than other types. Normally, they will not tolerate aminimum bend radius of less than 6.5 to 7.5 cm (2.5 to 3 inches).

    Macro bend loss

    In an optical fibre, the loss attributable to macro bending. If a lossfound from OTDR test at 1550nm wavelength is greater than 0.05dB comparing with loss found at 1310nm wavelength for the samepoint then this considered to be a macro bend loss contributed todamages and bents done during installation or objects (e.g. stones)damaged the fibre.

    Micro bend

    In an optical waveguide, sharp curvatures involving local axialdisplacements of a few micrometers and spatial wavelengths of afew millimetres. Note: Micro bends can result from waveguidecoating, cabling, packaging, and installation. Micro bending cancause significant radiative loss and mode coupling.

    Micro bend loss

    In an optical fibre, the optical power loss caused by a micro bend. Ifa loss found from OTDR test at 1310 nm to be greater then 0.03 dBat a point, where there is no splice then this is considered to bemicro bend loss.

    Abbreviations

    AC Alternating Current

    ADSS All Dielectric Self Supporting

    BS British Standard

    CCIR Committee Consultative International Radio

    CCITT Committee Consultative International Telegraphy and Telephony

    Db Decibel

    DC Direct Current

    24.6.7 Design Stages and Submissions

    In the design stage, the following shall is mandatory:

    A pre-survey of the route shall be conducted for all types of installations. Optical power loss budget shall be calculated for any FOC link.

    Problem areas shall be identified & fixed and an installation plan should be clearly

    defined prior to the start of the installation.

    In addition, the Contractor shall submit the followings:

    Catalogue Data: Catalogue data on conduit system, manholes, conduit fittings, conduit

    plugs, pull rope, identification tape, and warning signs.

    Detailed bill of materials.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    17/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 15

    Drawings indicating the routes, total layout and locations of all manholes.

    Catalogue data on all testing devices proposed for use plus certifications of accuracy,

    calibration, and traceability to standards of the National Institute for Standards and

    Testing.

    In case of pressure blowing, detailed methodology of blowing FOC.

    In case of HDPE duct installation, detailed installation methodology of the duct.

    In case of cable pulling, pulling calculations for all conduit runs. A cable pulling and splicing work plan shall be submitted. Work plan shall include the

    following. The name and qualifications of the supervisory personnel that will be directly

    responsible for the installation of the cable and/or conduit system.

    24.6.8 Route survey

    The Contractor shall make a physical survey of the project site for the purpose of

    establishing the exact cable routing, termination points, jointing locations and cutting lengths

    prior to the commencement of any work or committing any materials. The Contractor shall

    conduct the detailed survey and confirm the line route. If a change in route is required for

    any practical reason, prior approval should be obtained from the Company. The contractor

    shall ensure that clearances are maintained from the fibre optic cable to any part of the line

    or surroundings.

    24.6.9 Optical Power Loss Budget

    The optical Power Budget presents the optical budget calculations. The link calculations

    (OLTE - OLTE) shall be designed to give a bit error rate of better than 1 x 10-9, based on

    the average expected joint loss. Table 1 shows the parameters to be included for calculating

    the required System margin.

    Table 1: Required System Margin

    System Margin dB

    Equipment Degradation (ageing of Laser lifetime 3

    Design Noise 1

    Operation Margin (Safety Margin) 1.5

    Future Splice Margin (The system shall allow at

    lease 10 additional joints)

    0.1 per splice

    The fibre optic link shall accommodate up to additional 10 joints (5 repairs) without

    exceeding the error performance. Table 2 shows the recommended parameters to be

    included for calculating the link losses.

    Table 2: Recommended link losses parameters

    1.1.

    24.6.10 Testing

    The Contractor shall perform pre-installation and post-installation FOC tests. The Company

    Site Representative shall be notified a minimum of 10 days in advance so that these tests

    are witnessed. The Contractor shall carry out all the Site Acceptance Tests (SAT) required

    to prove that the FOC is free from damage, installed according to the Company

    specifications and requirements and functioning properly. The contractor shall provide a

    detailed Integration acceptance test document with the following information as a minimum

    for approval by the Company before the scheduled test. The Company at its own discretion

    Link Losses dB

    Cable loss (G.652) 0.4 dB/km

    Splice loss (G.652) 0.1

    Connector Loss 0.5

    FDF loss (Connector loss + Jumper loss) 0.75

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    18/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 16

    shall ask the contractor to include (or waive) any tests to ensure proper functionality of the

    network

    Test Plan

    Schedule

    Procedures

    Equipment setup diagrams

    Result Sheets

    24.6.11 Specifications For FOC Network Materials And Accessories

    The following sections comprise guidelines for the mostly used materials for FOC network

    and its specifications. However, it remains the Contractor responsibility to identify and

    procure all the required materials for the complete FOC installation work.

    24.6.12 Fibre Optic Cable

    It describes the construction, performance, acceptance criteria, and installation of

    polyethylene sheathed armoured optical cables (PSA) and polyethylene sheathed

    dielectric optical cables (PSD).

    Design PSA : Armoured Cable

    Design PSD : Dielectri c Cable

    High molecular weight PE sheath

    Water Blocking Tape

    Ripcord

    Dielectric Strength Yarn

    Buffer Tubes & Fibers

    Water Blocking Yarn

    FRP Rod

    High Molecular Weight PE Sheaths (2)

    Corrugated Steel Tape

    Water Blocking Tape

    Ripcords (2)

    Dielectric Strength Yarn

    Buffer Tubes & Fibers

    Water Blocking Yarn

    FRP Rod

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    19/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 17

    For PSA cable, applications include pulling/blowing into ducts and direct burial by plowing or

    by trench & backfill method. PSA designs should be well protected against attack by

    rodents & termites and have excellent crush & impact resistance to provide protection

    against the rigors of direct burial installation. For PSD cable, deployments are limited to duct

    installation by pulling or blowing. The cables described herein have a stranded loose buffer

    tube construction that is designed so that no net axial fibre strain occurs at maximum pulling

    tension.

    24.6.13 Cable Construction

    The required cable is comprised of the following components listed radially from the centre.

    A central strength & anti-buckling member made of 2.5 mm GRP.

    Super absorbent polymer yarns wrapped around the central member (or super

    absorbent polymer binders suitably located elsewhere in the cable structure)

    SZ stranded loose buffer tube containing optical fibres and a thixotropic filling

    compound.

    Optionally, filler rods may be used in lower fibre count cables to keep the structure

    round.

    A layer of aramid yarn that is engineered to provide the required level of tensile

    strength.

    A super absorbent polymer tape wrapped around the aramid yarn

    One or two ripcords

    A PE inner sheath

    A corrugated steel armour tape (PSA only)

    A PE outer sheath (PSA only)

    24.6.14 General Requirements

    The cables must be circular in cross section and free from pinholes, joints, repairs and other

    defects. Materials used in the construction of the cable shall not affect the physical or optical

    properties of the fibres and shall be compatible with each other. The fibre and stranded

    loose tubes shall be colour coded as specified below to provide easy identification at either

    cable end.

    The cable must be of stranded loose buffer construction where fibres are contained in aseries of tubes (6 or more). The fibres must have enough free space inside the tube to

    provide the required level of mechanical and environmental performance. The inside of the

    tubes must be filled with a thixotropic gel to prevent moisture ingress. The buffer tube-filling

    compound must be non-toxic and dermatologically safe. It must free from foreign matter,

    chemically and mechanically compatible with all cable components, non-nutritive to fungus,

    non-hygroscopic, and electrically non-conductive.

    For lower fibre counts, filler rods may be placed into any unused positions in the stranded

    fibre optic core. The filler material must be made of a material compatible with other core

    components. Each buffer tube in the finished cable is distinguishable from the others by

    means of colour coding as follows:

    Tube Number Buffer Tube Colour

    1 Blue

    2 Orange

    3 Green

    4 Brown

    5 Gray

    6 White

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    20/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 18

    24.6.15 Optical Fibres

    All optical fibres must meet the requirements set forth in ITU-T Recommendation G.652 and

    the detail specifications below. Each optical fibre must be protected with a dual layer

    acrylate coating. The inner layer shall be optimised for adhesion to the cladding glass,

    strippability and temperature performance while the outer coating shall be a harder material

    optimised for abrasion performance. Each cable must have traceability of the optical fibre

    back to the original fibre ID number and test parameters as provided by the fibremanufacturer.

    Optical fibres shall have a high level of splice compatibility with optical fibres from other

    manufacturers. No fibre splices are allowed in any continuous length of cable. Each fibre in

    a tube must be distinguishable from other fibres in the same tube by means of colour coding

    ink discernible throughout the design life of the cable. Required fibre colour sequence is as

    follows:

    Fibre Number Fibre Colour Fibre Number Fibre Colour

    1 Blue 4 Brown

    2 Orange 5 Gray

    3 Green 6 White

    24.6.16 Super-absorbent Polymer Materials

    Cables must be water blocked with superabsorbent polymer water blocking yarns, tapes

    and/or binders. The superabsorbent polymer materials must be safe, easy to remove and

    require no special handling or solvents.

    24.6.17 Inner Sheath

    The sheath must be made of a high molecular weight linear PE meeting the requirements of

    ASTM-1248, type III, Class C, Category 5, Grade J3. The inner sheath thickness should be

    nominally 1.0 mm or to meet the required cable mechanical and environmental performance

    characteristics.

    24.6.18 Strength Yarns

    The strength yarns for PSA and PSD cables shall be aramid yarns.

    24.6.19 Outer Sheath

    The sheath must be made of a high molecular weight linear PE meeting the requirements of

    ASTM-1248, type III, Class C, Category 5, Grade J3. The nominal outer sheath thickness

    shall be 1.8 mm. The average thickness of any cross section shall not be less than 90% of

    the specified thickness. The minimum spot thickness shall not be less than 80% of the

    specified thickness.

    24.6.20 Sheath Markings

    The outer sheath shall be marked with the following:

    The words Oman Wastewater Services Company S.A.O.C Fibre Optic Cable.

    The manufacturer name.

    The year of manufacture (for example: Year 2007).

    The fibre count (for example: 24 F).

    Meter marks at a one meter interval with arrowhead indicating upward direction of meter

    markings.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    21/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 19

    24.6.21 Cable Performance Requirements

    Mechanical Characteristics

    Parameter Requirements

    Maximum pulling tension (MPT) 3500N for PSA2700N for PSD

    Minimum bend radius, no load 10 times the cable outside diameter

    Min bend at max pulling tension 15 times the cable outside diameter

    Compressive Load 5000N/10 cm for PSA2500N/10 cm for PSD

    Impact Load 25 N-m for PSA15 N-m for PSD

    Optical Performance for G.652 Single Mode Fibres

    Parameter Requirement

    Attenuation variation with wavelength (1285-1330 nm)

    < 0.1 dB/km

    Attenuation at water peak 2.1 dB/km

    Attenuation with bending (100 turns on a 75mm dia mandrel)

    0.1 dB at 1550 nm

    Attenuation coefficient at 1310 nm 0.38 dB/kmAttenuation coefficient at 1550 nm 0.25 dB/km

    Optical discontinuities at 1310 and 1550 nm < 0.1 dBChromatic dispersion between 1285 and1330 nm

    3.5 ps/nmkm

    Chromatic dispersion at 1550 nm 18 ps/nmkmCable cutoff wavelength 1260 nmPMD Coefficient 0.5 ps/km

    Optical Performance for w ith 62.5/125 GI Multimode fibres

    Parameter Requirement

    Attenuation coefficient at 850 nm 3.0 dB/km

    Attenuation coefficient at 1300 nm 0.7 dB/kmOptical discontinuities at 1310 and 1550 nm < 0.1 dB

    Bandwidth Dist Product at 850 nm 160 MHzkm

    Bandwidth Dist Product 1300 nm 500 MHzkmEnvironmental Performance of Cable

    Parameter Requirement

    Operating Temperature -20 to +70 C

    Allowable change in attenuation 0.05 dB/kmInstallation Temperature -20 to +55 C

    Storage Temperature -20 to +70 C

    24.6.22 HDPE Duct Material

    The raw material used for HDPE ducts shall meet the following requirements:

    The anti-oxidants used shall be physiologically harmless.

    Single pass rework material of the same composition produced from the manufacturers

    own production shall be used and it shall not exceed 10% in any case. The raw material used for extrusion shall be dried to bring the moisture content to less

    than 0.1%.

    Suitable UV stabilizers shall be used for manufacture of the duct to protect against UV

    degradation, when stored in open for a minimum period of 8 months.

    The raw material used in the manufacture of the duct shall be such that the service life

    of the duct and all its accessories can be expected to be more than 50 years including

    the life of permanent lubricant.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    22/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 20

    24.6.23 HDPE Standards

    HDPE Ducts shall conform to the following standards & Specifications

    A. IS: 4984 Specifications for HDPE Pipes

    B. IS: 2530 Method for tests for polyethylene moulding materialsand compounds.

    C. IS : 9938 Recommended colours for PVC insulation for LF wiresand cables.

    D.TEC Specs no. G/CDS-08/01/Dec.99

    HDPE Ducts for use as duct for optical fibre cable

    E. IS : 7328 HDPE material for moulding and extrusion

    F. ASTM D 1693 Test method for environmental stress cracking ofethylene plastics.

    G. ASTM D 1505 Test method for density

    24.6.24 HDPE Requirements

    Visual Inspection: The ducts shall be checked visually for ensuring good workmanship that

    the ducts shall be free from blisters, shrink holes, flaking, chips, scratches, roughness,

    break and other defects. The ducts shall be smooth, clean, round. The ends shall be cleanly

    cut and shall be square with axis of the duct. The ducts shall be of different colours and for

    further identification, contrast striping shall be provided. These stripes shall be co-extruded

    during the duct manufacturing. The material of the stripes shall be same as that of base

    compound for the duct.

    Identification Markings: The duct shall be prominently marked with indelible ink, with the

    following information at intervals every meter to enable identification of the pipe. The size of

    ink markings shall be distinct, clearly and easily visible.

    Manufacturers name (Also can be in abbreviated form)

    Oman Wastewater Services Company S.A.O.C

    Name of the duct with size Specific serial number of the duct

    Date of manufacture

    Sequential length marking at every meter with Arrow mark in ascending order.

    24.6.25 HDPE Duct Accessories

    The following Accessories are required for jointing the ducts and shall be supplied along

    with the ducts. The manufacturers shall provide complete design details, procedure for

    method of installation and type/grade of the material used for the accessories. Some of the

    accessories are:

    Plastic Coupler: The coupler shall be of Push-fit type having Push-Lock mechanism,

    which enables them to be installed on ducts without pre-dismantling. The design of this

    shall be simple, easy to install and shall provide air tight and water tight leak proof joint

    between the two ducts. It shall withstand the air pressure test of 15 Kg/cm2 for a

    minimum period of 2 hours without any leakage.

    End Plug: This is for sealing the ends of empty ducts, prior to installation of O.F. cable

    and shall be fitted immediately after laying of duct, to prevent the entry of any dirt, water,

    moisture, insects/rodents etc into ducts.

    Cable Sealing Plug: This is used to seal the ends of ducts perfectly, after the cable is

    installed in the duct, to prevent the entry of dirt, water, moisture, insects/rodents etc into

    ducts.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    23/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 21

    End Cap: These caps, made of hard rubber/plastics, shall be fitted on each end of duct

    coil after manufacturing. These shall avoid ingress of dust, mud, rain water etc. into

    ducts, during transit and storage.

    24.6.26 Cable Markers

    The markers shall be made from Aluminium with width of 100mm, height of 30mm and

    thickness of 1mm. The text shall be engraved on the Aluminium marker. The text shall

    provide details of the FOC type, the route, manhole number, start and end locations.

    24.6.27 Duct or Conduit Seals

    The Duct Sealing Kit prevents water and gas from entering a manhole through a cable duct.

    24.6.28 Pull Rope

    Low friction, polyethylene jacketed polypropylene rope with 1800 psi tensile strength.

    24.6.29 Fan-Out Termination for Loose Tube Cables

    Individual fibres within the loose tube cable require handling protection inside the

    termination cabinets. Fan-out kits shall be installed in the patch panel enclosures to

    transition the loose tube fibres to ruggedized tight-buffered fibre pigtail cables. Fan-out

    tubes or furcation kits shall not be used. Optical fusion splices shall connect the loose tube

    fibres to the tight-buffered pigtail cables. The optical splice loss shall comply with the

    specifications for optical splices. Splice protection sleeves shall be employed on all splices

    to protect the splices.

    24.6.30 Pigtail Cable Specifications

    Optical characteristics shall comply with the optical f ibre performance specifications.

    Buffer material: Thermoplastic

    Buffer O.D.: 900 um

    Strength Member: Kevlar

    Jacket Material: PVC

    Jacket O.D.: 3.0 mm

    Temperature Range: -20 to + 70 C

    24.6.31 Fibre Optic Termination Patch Panels

    The contractor shall supply the required quantities of pig tails, patch cords and patch panels.

    The fibre optic cable shall terminate inside a communications cabinet on a termination patch

    panel. All single mode fibre sub-cables or cores within the cable shall be terminated with E-

    2000 compatible connectors. All Multimode fibre sub-cables or cores within the cable shall

    be terminated with ST2 compatible connectors.

    The patch panel shall have a fibre capacity equal to the total number of f ibres (connected

    and spares) for all cables to be connected. All unused couplings shall have protective dust

    covers. All panels shall be furnished with front removable door or cover, Factory-terminated,

    tight-buffered, agamid-reinforced fibre optic jumper assemblies or interconnect cables,

    standard 3.0 mm O.D., shall connect the optical cable terminations to the patch panel

    couplings. The termination patch panel shall be equipped with a suitable means for routingand securing of cables and shall provide a suitable means of protection for the mounted

    fibre connectors to prevent damage to fibres and connectors during all regular operation and

    maintenance functions. All cables shall be provided with strain relief. Bend diameters on

    cable fibres and jumpers must be greater than four (4) inches at all times to ensure optical

    and mechanical integrity of the optical fibres.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    24/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 22

    24.6.32 Optical Connectors

    All connectors shall be field-installable and perfectly matched to the cable used. The

    connectors shall provide tight fitting termination to the cladding and buffer coating. Epoxy

    based or hot melt adhesives shall be used to bond the fibre and buffer to the connector

    ferrule and body prior to polishing the end face. No dry-termination or quick crimp

    connectors are allowed.

    Connectors shall have a maximum allowable connection loss of 0.3 dB per mated pair, asmeasured per EA.-455-34. No index-matching gel is to be used, dry interfaces only. Single

    mode connectors shall be capable of field installation on 9/125 micron fibres with 900

    micron buffers (OD).

    Each connector shall be of the industry standard E-2000 or ST2 type compatible, designed

    for single mode or multimode tolerances, respectively, and shall meet or exceed the

    applicable provisions of EIA.-455-5, 455-2A, and 455-34, and shall be capable of 100

    repeated matings with a maximum loss increase of 0.1 dB. Connectors shall incorporate a

    key-way design and shall have a zirconia ceramic ferrule. Connector bodies and couplings

    shall be made of corrosion-resistant and oxidation-resistant materials, such as nickel plated

    zinc, designed to operate in humid environments without degradation of surface finishes.

    24.6.33 ManholesThe manhole shall have the followings:

    Minimum size of 600 x 600mm (LxW) and a depth of 600 mm

    Ductile iron covers with a galvanised steel frame. The covers will be tested to the

    European standard EN124 B125. Security: Special "penta head" bolts shall be fitted.

    These can only be opened & locked with a special socket, which is also available.

    Duct Entry

    Internal Cable furniture

    24.6.34 Separation from non-Electrical Installations/Structures

    For non-Electrical structures or installation, a minimum separation between FOC and the

    structure shall be 300 mm, while running parallel. While crossing the structure, the minimum

    separation shall be 200 mm. The structure can be a pipe for gas, oil, water, sewage or other

    non- Electrical installation.

    24.6.35 Separation from Electrical Installations/Structures

    When installing a buried optical fibre cable near existing HV infrastructure, maintain a 3

    metre separation between the fibre optic cable and poles, stays and existing HV electrical

    cables. Where cable is being installed in the same trench with other electrical cables, the

    minimum separation is given as follow:

    Minimum separation from electrical cables is 750mm (LV), 1000mm (11kV) and

    1500mm (33kV).

    Note the requirements for vertical tiles between HV cables and the fibre optic cable.

    24.6.36 MarkersCable route markers will be installed at the completion of the cable installation and generally

    after the cable trench has been back filled and compacted. To enable the use of machines

    to complete this backfilling operation, temporary off set pegs will be placed in the ground

    with a recorded measurement to the cable. This measurement will then be used to establish

    the cable route marker; 1 metre from the cable after the machines has finished their

    activities.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    25/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 23

    The cable markers shall be installed in accordance with the followings:

    Along FOC independent route, at every 100m.

    At every change in direction.

    At both ends of every conduit.

    At each joint or/and manhole.

    The distance to the cable is to be recorded on each marker, together with the cable depth at

    each point. The supply and installation shall include the route markers including plates,posts and all the necessary materials required for installation.

    24.6.37 Direct Buried FOC/HDPE Duct

    Normal soil trench shall be excavated up to 750mm deep. The trench shall be filled with

    clean and soft sand up to 150mm from the bottom of the trench with the surface levelled

    (flattened).

    The trench shall be backfilled up to 500mm from the bottom of the trench with excavated

    material (with no stones larger than 4mmx4mmx4mm size). A mesh filter shall be used to

    remove big stones and sharp materials from the excavated material prior to backfilling. The

    trench shall be backfilled with remaining excavated material with big and sharp stones

    removed up to the normal ground level. The Contractor shall inform OWSC regarding

    backfilling schedule to enable quality verification/inspection of cable installation andbackfilling for different layers.

    The HDPE duct/conduit shall be of corrugated construction with a plain internal wall of

    LDPE (low-density polyethylene) and an external corrugated wall of HDPE (High Density

    Polyethylene). External colour shall be blue. Manufacturing shall be according to STD.

    EN50086-1 and EN 50086-2-4. Conduit shall withstand 450N with maximum deflection of

    5% of internal diameter and 750N with maximum deflection of 15%. Conduit shall withstand

    impact test specified in EN 50086-2-4- sect. 10.3. Suitable jointing tubes with indented rings,

    which mate with external corrugations, shall be utilised for all joints. Joints shall provide a

    watertight seal.

    During construction the ends of the conduit shall be closed to prevent foreign objects. Upon

    completion the ends shall be sealed to prevent ingress of water and sand using a plug.

    Sealing shall be achieved without use of glues, sealing compounds or foams. After its

    installation, the conduit shall be cleaned on the inside from any kind of material (earth,

    stones, etc.). A puling rope shall be provided in the conduit for future use.

    The cable/duct drum shall be installed on the cable carrier (trailer). This cable carrier shall

    move along the trench line with the cable being manually spooled off the drum. The drum

    shall be turned by hand and the cable laid without any tension, directly into the trench. At no

    stage is the cable to be pulled off the drum. The cable/duct shall not be over-stressed during

    the unwinding and laying process. In cases where the cable or duct is drawn off the cable

    reel a swivel joint and mechanical "fuse" of the correct capacity shall be used to avoid

    exceeding the designed maximum pulling force for the cable.

    Figure-8s shall be used for backfeed pulling or other situation where removal of the cable

    from the drum is needed. The size of the figure-8 should be marked with cones or othersuitable devices. The figure-8 shall be at least 5 meters long with each loop at least 2 meter

    minimum diameter.

    24.6.38 Maximum Pulling Tension (MPT)

    All Fibre Optic cables have a rated maximum. The MPT is clearly shown on cable

    specification sheet issued by the Manufacturer. During installation, the tension applied to the

    cable MUST be monitored with a calibrated load cell or tensiometer (dynamometer). Once

    the cable tension reaches 90% of MPT, the installation must stop to troubleshoot the cause.

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    26/30

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    27/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 25

    The area around the manhole shall be compacted. Upon final acceptance of the

    conduit/duct system all manholes shall be free of debris and water, and be ready for

    cable installation.

    24.6.42 Drawings and Documents

    The documents are an integral part of the equipment required to maintain and restore a fibre

    optic system. The following information shall be included in the documentation package.

    24.6.43 Test Results

    Hard and electronic copy of test documentation shall be submitted to the Company. The

    documentation shall include the trace plot, index, dB/km loss, cable length, date and time of

    test, wavelength, pulse width, the test site, cable ID, fiber number and type, and operators

    initials. The Contractor shall compare the pre-installation test results to the post-installation

    results. If a deviation of greater than one dB occurs, the Company shall be notified in writing

    by the Contractor.

    24.6.44 Key Map

    The key map is a geographical map showing the system route in relation to roads and

    highways. Its purpose is to provide quick access to key areas of the system, such as field

    splice points and major road crossings. Sheath metre marks should be indicated on the mapfor splice points, road crossings, etc. It shall also provide horizontal and vertical alignment of

    FOC.

    24.6.45 Circuit Diagram

    The circuit diagram is a schematic that identifies the actual f ibre circuits, system number,

    working and protected fibres, fibre/buffer colours, priority sequence during restoration and

    other pertinent information such as transposed fibres.

    24.6.46 Manufacturer provided documentation

    The manufacturer provided documentation should include the cable data sheets of each

    cable reel, documentation provided on the fibre, results of calculations of the field strength

    levels relative to different structure types. The original copy should be maintained and

    handed over to the Company representative for record.

    24.6.47 As-Built Documentation

    The as-built drawings and documents shall identify the actual apparatus units at each

    structure and other information such as the structure type and dimensions, cumulative

    distance to each termination point from the structure, any grounding or bonding detail, etc.

    These drawings and documents are typically the construction detail sheets that have been

    corrected to reflect any changes during construction. As built drawing shall record all

    deviations, deletions and additions with respect to the original scope.

    24.7 SCADA System Tests

    The contractor shall develop a test schedule for the SCADA system. The test schedule

    shall be submitted to the Engineer for approval.

    SCADA system tests shall place particular emphasis on tests that demonstrate compliance

    in the following areas:

    I/O database

    Mimic displays

    Operator controls

    Manual operations

    Alarm generation

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    28/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 26

    Interlocks

    Data entry (alarm and control set points)

    Control simulation

    PLC to SCADA communications

    External interfaces

    Memory backup

    Archiving & retrieval of data Mains failure and recovery facilities

    Event and alarm log/summary

    Report generation

    System performance

    Automatic house keeping and file management

    Disaster recovery

    Unless otherwise stated, tests shall be demonstrated to the Engineer during both the FAT

    and SAT.

    In the event that the Engineer has stated that the testing shall not be witnessed, the

    Contractor shall perform the testing without the Engineer present and upon completion,

    submit the test results to the Engineer.

    24.8 SCADA System Colour Coding

    Color coding shall be in as provided below and where not stipulated in accordance with BS

    EN 60073:2000:

    Status of Operation Color Code

    Equipment running and normal Green

    Equipment stopped and normal White/Grey

    Equipment tripped Yellow

    Equipment selected on Auto Blue

    Equipment or process unsafe / danger in operation Red

    Panel Energized /isolator or ACB ON White

    Process Flow ON (e.g. Valves open) Green

    Process flow Stopped OFF (e.g. Valves closed) White

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    29/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    Section 24 Page 1

    Appendix A

    SCADA PerformanceRequirements

  • 8/10/2019 Section 24 - SCADA Rev 1.pdf

    30/30

    Oman Wastewater Service Group Wastewater Standard Technical Specification

    A1 APPENDIX 1

    Description Response in

    SecondsChange in status of a plant item (Digital) and display on SCADA 5

    Change in status of a plant item (Analogue) and display on SCADA 5

    Annunciation of an alarm from alarm condition occurring at plant 5

    Display of a real time trend (including the data) with 24-hour axis. 5

    Display of an historic trend (including data) with 4 traces and 24 hour axis 5

    Display of the alarm summary page with a screen of alarms. 3

    Time to silence the audible alarm after acknowledgement of the alarm. 0.5

    Time for mimic to update after the execution of a control output on SCADA 4

    Time for a new mimic to be displayed after a request to chain or load a new

    mimic (including new data)

    3