Upload
arraghavan
View
219
Download
0
Embed Size (px)
Citation preview
8/10/2019 Section 24 - SCADA Rev 1.pdf
1/30
Wastewater Standard Technical Specification
Section 24SCADA
8/10/2019 Section 24 - SCADA Rev 1.pdf
2/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
ContentsPage
24 SCADA 1
24.1
Hardware Requirements 1
24.2 Software Requirements 2
24.3 Alarms 7
24.4 Security 9
24.5 Reports 10
24.6 SCADA System Tests 25
24.7 SCADA System Colour Coding 26
ppendices
Appendix A
SCADA Performance Requirements
A1
APPENDIX 1
8/10/2019 Section 24 - SCADA Rev 1.pdf
3/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 1
24 SCADA
This document details the standard requirements for the SCADA system.
SCADA systems provide detailed, local site and process alarm reporting, monitoring and
process control facilities for treatment works installations where specified.
Data collected by the SCADA system is retained locally and is not routinely transferred off
site. However, access to this data from a remote location shall be possible via a Wide Area
Network connection to a Corporate Network, and via the SCADA remote access facilities.
Data shall be continuously acquired by the SCADA system through a network interface(s) to
the PLC systems installed on the plant. This data shall be held in a real time database by
the SCADA system. Some or all of this data shall be stored to provide historical information.
SCADA data shall be displayed on either the local SCADA system or where specified, on a
remote workstation in the form of alarm lists, mimics, trends and reports.
Any SCADA system fitted with a remote terminal or client shall support at least two
simultaneous users.
24.1 Hardware Requirements
24.1.1 Computer Specification
The contractor shall provide a personal computer for use as a SCADA computer. The
personal computer shall include the following items:
3.5 inch 1.44MB floppy disk drive.
CD-RW compact disk writer for archive purposes.
PLC network interface card.
An appropriate number and type of serial and parallel interfaces for peripherals.
The contractor shall evaluate the performance requirements for the particular application
and shall ensure that the hardware specification does not unduly limit the performance of
the SCADA system, taking into consideration applications such as report generators running
concurrently with the SCADA software.
The contractor shall also confirm that the hardware platform meets the recommended
system requirements specified by the relevant software vendors.
The supplied PLC network interface card supplied shall be as recommended by the PLC
manufacturer. The relevant supporting software shall be installed and configured to enable
direct communications with the supplied PLCs.
Sufficient solid-state memory shall be provided so that swapping of data with disc store is
minimised and performance levels achieved. The computer shall be configured to operate
from 230/240V AC 50Hz supply.
Unless otherwise stated, all SCADA and associated equipment shall be supplied from a
UPS.
Unless otherwise stated, the specification of the computer shall be such that when fully
programmed and operational it complies fully with the performance requirements stated in
Appendix 1 of this specification.
The level of redundancy shall be as detailed in the Particular Specification.
24.1.2 Specification
The contractor shall supply printers for use as SCADA equipment.
All printers shall be capable of being supplied from a 230/240V AC 50Hz supply.
8/10/2019 Section 24 - SCADA Rev 1.pdf
4/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 2
Printers shall be provided with a suitable paper feed with the capacity of at least 100 sheets,
and a receptacle for printed output.
Screen Printer - An ink jet colour printer shall be provided complete with an A4 sheet feeder
mechanism and a suitable stand and configured so as to be able to produce full colour
accurate representations of screen displays, including mimics, trend displays and reports.
Alarm / Event Printer A dot matrix printer shall be provided complete with a paper feed
mechanism suitable for use with continuous feed paper and a suitable stand so as to be
able to print alarm print outs.
24.1.3 Equipment Environment Requirements
The environmental specification of the SCADA equipment (including associated peripherals)
and the specification of location in which it is to be located shall be matched such as to
ensure that the SCADA equipment environmental specification is not exceeded.
24.1.4 Furniture
The contractor shall provide furniture in accordance with the requirements of the particular
specification.
24.1.5 Equipment SecurityThe SCADA system shall be located in a suitable control room or other secure location.
24.2 Software Requirements
The following shall be provided:
PLC network interface software, as recommended by the PLC manufacturer
the operating system used on all SCADA installations shall be as agreed with the
Employer and as recommended by the SCADA application supplier
All documentation, including but not limited to software licences and licence keys,
associated with the above software shall be provided to the Employer.
All software shall be licensed to the Employer by the contractor.
Software licences shall cover application run time and configuration.
House keeping shall be automatically performed by the SCADA system. All operating
system temp (.tmp) files and other system temporary files shall be deleted automatically on
a regular basis.
Where a symbol and or a dynamo do not exist for a specific application a symbol or dynamo
shall be designed and submitted to the Engineer for approval.
24.2.1 Disaster Recovery
A disaster is defined as a complete failure of the SCADA system.
A disaster recovery system and procedure shall be provided. A description shall be
submitted in the FDS to the Engineer for approval.
An additional (back-up) hard disc drive shall be provided for each computer supplied. Upon
successful commissioning of the system, the complete contents of all active hard drives are
to be copied to back-up drives.
The disaster recovery procedure shall be fully described in the O&M manual.
As part of the FAT and SAT the contractor shall be required to demonstrate the disaster
recovery procedure as described in the O&M manual.
8/10/2019 Section 24 - SCADA Rev 1.pdf
5/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 3
Alternative disaster recovery methods may be offered by the contractor and shall be fully
described in the contractors tender / scope submission.
24.2.2 SCADA system configuration start up and power failure recovery
On start up or on resumption after power failure on the whole or any part of the plant, the
system shall automatically self start, configure, connect to all external communications links
and display the main menu.The user shall not have to enter configuration data or initialisation commands during the
start up process or operating period. The system shall retain all settings that have been
previously set by the user. The FDS (at the design stage) and the Operational and
Maintenance Manuals (at As Built stage) shall list all such settings for the Engineers
approval.
After shutdown or on loss of power, or on resumption after loss of power, all totalised and
other calculated values shall be retained and redisplayed. All log files and values shall also
be available and uncorrupted.
The system set-up shall include the disabling of the auto run facility for CD-ROM.
24.2.3 Configuration
The contractor shall be responsible for the configuration and integration of all hardware, and
communications, and shall also be responsible for all software installation and configuration
including disk and memory allocation to meet the functional requirements of the system.
The Contractor shall submit details of the database configuration displays, trends, reports
etc for approval as part of the Functional Design Specification (FDS).
24.2.4 Configuration Details
24.2.4.1 Mimics
All mimics shall display a menu tool bar at the top of the screen capable of providing the
following facilities: Login/logout, Alarm list summary Display, Event log display, Trend Menu
display, Main Menu Display, System Menu Display.
The contractor shall configure sufficient mimics to cover the entire plant. Mimic pages shall
show an overview of the whole plant.
The plant shall be broken up into logical areas with at least one mimic page per area. Each
mimic shall show all controlled and monitored plant within the area that it covers.
In general, the mimic shall resemble the P&I diagram. Unmonitored or uncontrolled plant
shall be shown where a contribution to the process is made by this plant.
All plant shown shall have its tag number displayed on screen as close as practicable to the
plant item icon.
The operator shall be able to move between mimic pages by two methods, either by directly
selecting the page from the overview graphic or by navigating through the plant using
graphical buttons on the input or output links of mimic pages. These buttons shall clearlyshow in graphics or text the screen that will be selected if the button is pressed.
Mimics pages shall be of 2 distinct types: process pages (chained from the Main Menu
Overview Screen) or system and diagnostic pages (chained from the System Menu
Overview Screen).
The contractor shall not locate his company name or logo or any other form of advertising
on any of the mimic screens. The contractors name and contact details shall be configured
on the system start up screen.
8/10/2019 Section 24 - SCADA Rev 1.pdf
6/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 4
The engineering units associated with each reported value on the mimic shall be displayed
beside the value.
Where the run / stop status of pumps is monitored, all pumps shall have their running hours
totalised. The run hours shall be displayed on a different mimic / graphic.
Diagnostic mimic pages shall be configured to monitor the status of all the PLC I/O modules
and all PLC network communications statistics. Each slot shall be clearly identified by slot
number and card type and the I/O signals identified by number and name. The mimic shall
also display for each I/O point:
The raw PLC value
Engineering unit value, default value (if a default is specified) and if the default is in use
24.2.4.2 Graphical User Interface
The graphical user interface will provide facilities for both process monitoring and control.
The facilities will be provided to monitor plant status, start and stop plant and change plant
process set-points.
It is intended that all mimics will have a common look and feel as far as is possible. Mimics
will consist of three main types.
24.2.4.3 Overview Mimics
The Overview Mimics are the 'gateway to the Detail Mimics. They will not display any
detailed information, although the Overview Mimic for an area of plant may indicate the most
important status information.
24.2.4.4 Detail Mimics
The Detail Mimics will show detailed status of all of the dynamic equipment on the plant. All
of the required monitoring and control facilities will be available from these screens.
24.2.4.5 Pop-up Mimics
Pop-up mimics will be partial page mimics that are selected from detail mimics. They will
normally be associated with plant items.The system structure will be such that all full-page mimics should be accessible within 4
selections from any other mimic in the system
The user interface will be via a keyboard and 'pointing device. Typically the 'pointing device
will be a mouse or tracker ball.
Plant items on detail mimics may be selectable items. Plant items, which are selectable, will
be outlined in grey when the pointing device is over them.
Selection of individual plant items will display a pop-up mimic. This would be a face plate
type mimic for most plant items, from which further pop-up mimics may be selected using
windows buttons. The faceplate would facilitate the calling of the following options.
Control Pop-up - will facilitate the manual control of plant items, when it is appropriate.
Trend Pop-up - will display a real time trend of a selected analogue plant instrument.
PID Pop-up - will display the current PID parameters associated to a control loop.
Statistics Pop-up - will display the current running hours, no. of starts etc. for a plant item.
Plant equipment which only has one option (i.e. an instrument may only have trend
information) will go directly to the appropriate pop-up without the need for a faceplate. Only
one pop-up mimic may be open at any time. When a detail mimic is closed any pop-up
mimic, which is displayed at the time must also be closed.
8/10/2019 Section 24 - SCADA Rev 1.pdf
7/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 5
24.2.4.6 General Mimic Discipline
This section will detail the general graphical rules for the generation of mimics, most will
also be relevant to pop-up mimics.
Each mimic will have a title bar, which, along with the mimic title, will display the time, date
and the numbers of unacknowledged and total alarms. The site name will also be displayed
within the title bar. Every full-page mimic will have a 'Help' button on the right hand side of
the title bar.
An alarm banner consisting of the three most recent alarms will exist at the bottom of the
page; the banner will be the full width of the screen. Above the alarm banner will be a
function key banner. The function keys F2 to F9 and F11 to F12 will be displayed. Function
keys F1 and F10 are not used as they have reserved functions within Windows.
The following rules should be observed in the creation of full-page mimics:
[1] The filenames used for graphics must be meaningful text
[2] All screen development shall be based upon a screen resolution of 1024 by 768 pixels.The screen size shall be 17"
[3] Graphics will be drawn in two dimensions
[4] All process flow lines shall be vertical or horizontal
[5] Process flow lines shall be the appropriate process colour. Process lines shall not beanimated in any way
[6] Process flow shall be from left to right, unless it is unavoidable or would reduce clarity.Sufficient process coloured direction arrows will be super-imposed on the process flowline to ensure clarity
[7] The crossing of flow lines shall be avoided. Where it is unavoidable, the vertical flow lineshall have breaks either side of the horizontal line. These breaks will be as small aspossible to maintain clarity and of a uniform size
[8] All process flow lines shall be of a uniform thickness; there shall be no increase in sizeat process flow lines junctions. Line thickness for process flow lines shall be 3 points(pixels)
[9] Text shall be lower case with leading upper case. The exception to this being equipmenttags names which shall be all upper case
[10] Equipment status shall be displayed in a graphical manner and through the use ofcolour of the appropriate symbol. Process critical and alarm conditions shall not beindicated by colour alone
[11] Tag names and status words shall both be inserted below or to the right of equipment
symbols. Where either position would be possible, the preferred position is below thesymbol
[12] Static symbols shall only be shown on mimics where they are necessary to aid overallclarity. When it is necessary to show static symbols they shall be drawn in black
[13] Selectable area on any screen will be highlighted in a grey rectangle when the pointingdevice passes over the area
8/10/2019 Section 24 - SCADA Rev 1.pdf
8/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 6
[14] Where possible common features on mimics shall be placed in consistent positions.This will include Help, Trend and Alarm summary selection
[15] Pop-up mimics will not be sizeable and should appear on detail mimics in such aposition so as not to obscure the plant item to which they refer
24.2.4.7 Main Overview
The Main Overview is the top-level mimic, which will be displayed when the system is firststarted. It should be possible to return to this Overview mimic from any other mimic by a
single action from the keyboard or pointing device. The 'F2' function key on every other
mimic shall be used for this purpose.
The main overview will be used as the 'gateway' to either detail mimic or to lower level
overview mimics, this will be dependent on the complexity of the installation.
The 'F4' function key on this mimic will be used to select the 'Operator Log-In' pop-up mimic.
24.2.4.8 Process Overview
Process overviews shall be provided for more complex installations, these will allow direct
access to the detail mimics. Smaller installations will have the functionality of the process
overview combined into the main overview.The process overview shall be developed in such a way as to portray the physical plant
layout. Each area of plant would be illustrated as a 'box' on the mimic, showing the main
process flow lines between the areas of plant. Essential information may also be
represented on the mimic.
The appropriate detail mimic will be selected by clicking the pointing device on the
appropriate box, which represents the required plant area. It should be possible to return to
the process overview from any given detail mimic by a single action from the keyboard or
pointing device. The 'F3' function key shall be used for this purpose.
The box representing each area of plant shall be a grey button, having a border, which will
only be visible when an alarm is present in that area of plant. The general area alarms for
this purpose shall be generated within the PLC and not within the SCADA. When clicked,
the button shall activate the appropriate screen.
24.2.5 Symbols
A standard symbols library shall be developed in conjunction with the Engineer.
24.2.6 Screen Navigation
Navigation shall be developed in conjunction with the Engineer.
This is the method by which the operator will select new full-page mimics and call up partial
page pop- up mimics from full-page mimics.
24.2.6.1 Function Key Bar
The function keys will be selectable using the keyboard or the pointing device. These keyswill generally be used to select the standard full page mimics that should be selectable fromevery mimic. They will include:
F2 Main Overview
F3 Process Overview (If required)
F4 Return / Login (on Main Overview)
F5 Spare (Project Configurable)
F6 Spare (Project Configurable)
F7 Communication Status
F8 Trends
8/10/2019 Section 24 - SCADA Rev 1.pdf
9/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 7
F9 Alarms Log
F10 Access to Supervisor level and above
F11 Alarm Summary
F12 Alarm Reset
The remaining function keys, which have not been specified, may be used on a project
specific basis. These keys shall not be used to navigate between detail mimics.
24.3 Alarms
Alarms of all types generated by the system shall be time-stamped at SCADA to an
accuracy of one second.
The SCADA system shall be able to receive and respond to incoming alarms at any time
and under any prevailing operating conditions, including the routine polling cycle, within the
response times defined by the specified performance requirements in Appendix 1.
The Contractor shall define the priority of all alarms and submit to the Engineer for approval.
Upon approval, the definitive list shall be incorporated into the FDS.
The Contractor shall define alarm groups and assign each alarm to an alarm group. This list
shall be submitted to the Engineer for approval. Upon approval, the definitive list shall be
incorporated into the FDS.
An alarm list shall be available to record all alarms and shall enable users to inspect or
recall alarms in various formats, with the aid of structured query facilities. The alarm list shall
have a capacity of at least 2000 alarms. The alarm list shall identify as a minimum, the
source, date and time of occurrence priority and status by colour code.
On an annunciation of an alarm condition, the operator shall be able to acknowledge alarms
whilst viewing the alarm list. Provided the condition causing the alarm is no longer present
the alarm shall be removed from the list and an alarm acknowledged message recorded in
the event log and if defined within the FDS, additionally sent to the alarm printer. If the
condition causing the alarm is still present a tick shall be shown beside the alarm message
on the list and the message will not be removed from the list.
All alarms shall remain active until acknowledged by the user and must remain on the alarmbanner and summary list in a form, which is clearly displayed until the source of the alarm
condition has been removed.
24.3.1 The Alarm Banner
As a minimum, the alarm messages shall contain the I/O tag name, the I/O point name, the
text status, Priority, Time and Date. Note that priority shall be indicated by different colours
for different priorities.
There shall be a simple means of navigating from the alarm message to the related mimic.
Only the three most recent active and unacknowledged alarms shall be displayed on the
alarm banner.
The format and detailed functionality shall be agreed in conjunction with the Engineer.
24.3.2 Alarm and Event Log
All events (including user log in / out and other user activity) and alarms / events detected
by the system shall be logged and stored in a permanent file, which shall be capable of
being accessed and viewed by operator level upwards. Event log viewing shall be initiated
by a button on the menu tool bar.
Log records shall be kept in a manner such that they are not alterable by any party.
8/10/2019 Section 24 - SCADA Rev 1.pdf
10/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 8
Any part of the event log (including during the current day and current time) shall be capable
of being viewed and/or printed at any time.
Search and locate facilities (including specification of date range) shall be provided to assist
the user to locate specific events, tag numbers etc.
The alarm log shall be divided into logical groups that represent the different elements of the
process, for example main alarm groups for primary treatment, secondary treatment,
electricity distribution, etc. Each main group shall be divided into sub-groups as appropriate,
for example primary treatment might be divided into inlet screens, grit removal, etc.
The alarm log shall incorporate the facility for the user to view specific alarm groups only as
well as all alarms.
The alarm log shall incorporate the facility for the user to view separately the alarms that fall
into the following categories:
Active and unacknowledged
Active and acknowledged
Inactive and unacknowledged
Inactive and acknowledged
For active alarms, the alarm log shall display when the alarm became active and, if
appropriate, when it was acknowledged.
For inactive and unacknowledged alarms, the alarm log shall display when the alarm last
became active and when it became inactive.
For inactive and acknowledged alarms, the alarm log shall display when the alarm became
inactive and when it was last acknowledged.
Log records shall be kept in a rolling event log file, which shall be stored in a reserved
portion of hard disk space. The amount of hard disk space reserved for the alarm log shall
be agreed with the Engineer. Alarms shall be stored on a first-in-first-out basis.
24.3.3 Printing Functionality
Printers shall be supplied as defined under the Hardware Requirements section of thisspecification. The contractor shall be responsible for the configuration of all printers
provided.
Alarm and event log to be printed on request.
24.3.4 Alarm Priority
There shall be a facility for defining alarm priorities.
If alarms are required to be prioritised, then this shall be stated in the Particular
Specification.
Alarm priorities shall be agreed with the Engineer.
24.3.5 Alarm GenerationIt is intended that all alarms shall be generated in the PLC, and then passed to the SCADA
system as digital signals. This shall include analogue alarm levels, which shall not be
generated within the SCADA system.
Plant items which have several alarms associated with them shall also have a general
failure alarm generated within the PLC. Plant Area general alarms shall also be generated.
These general alarms shall be used on the mimics to indicate plant item and plant area
alarms on the process overview mimics.
8/10/2019 Section 24 - SCADA Rev 1.pdf
11/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 9
In the event of a major alarm e.g. mains electricity supply failure, an alarm shall be raised
for this alarm but all consequential alarms shall be suppressed. The alarms to be classed as
major alarms shall be agreed with the Engineer.
24.3.6 Alarm Display
There shall be three separate ways of displaying alarms:
Alarm Banner This shall appear at the bottom of each full page mimic displaying thethree most recent alarms on the system. Acknowledged alarms shall remain on the
banner until they are cleared or replaced by more recent alarms
Alarm Summary This shall be accessible from every full page mimic and shall contain
up to a full page of the most recent alarms. Alarms shall remain on this page as long as
they are still current or have not been acknowledged
Alarm Log This shall show all the alarms regardless as to whether they are still current
or not. The length of this alarm log shall be configurable
24.4 Security
24.4.1 Security Codes
The contractor shall implement the passwords defined by the Engineer. These shall be
defined during the design phase.
24.4.2 Default / Guest
This user group will only have access to View screens. They will not be able to select
anything which may effect plant or system operation in any way. This will include the
inability to acknowledge or reset alarms.
24.4.3 Operator
The operator user group will have similar security access to the default and guest user
groups. In addition it will be possible to change duty selections for items of plant.
24.4.4 Supervisor
The supervisor user group will have similar security access to the operator, except that thesupervisor will be able to control all items of plant and change any system set-point. The
operator will also be able to acknowledge and reset alarms.
24.4.5 Developer
The Developer will have access to all areas of the system. This will include the ability to
close the SCADA application and return to the operating system. There will normally be only
one system administrator on any site installation. Any new user accounts or modifications to
the security codes, must be configured by the Developer.
24.4.6 General Security Considerations
All installations of the SCADA application will automatically enter the Run mode when the
system is started. The ability to switch applications, using Ctrl_Alt_Esc or Ctrl_Shift_Esc to
display the Windows start-up menu, will be disabled in Run mode.
24.4.7 Archiving and Retrieving
A utility shall be implemented to allow the supervisor to archive and retrieve data by
selecting options from a System menu via a button on the tool bar at the top of the screen.
When it is selected the system shall prompt the supervisor to insert the appropriate CD and
select the information which is to be archived, e.g. reports, data, events alarms, trends etc.
By default all trend data, all alarms (of all priorities) and all operator and supervisor actions
8/10/2019 Section 24 - SCADA Rev 1.pdf
12/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 10
shall be archived. The supervisor shall be able to retrieve data by selecting the date of the
archive file.
Archive data shall be held in a form that allows it to be retrieved and entered into an Excel
spreadsheet.
Data shall normally be archived onto optical disc, but floppy could be selected. Usually the
optical CD will reside in the SCADA PC ready to archive or retrieve data.
System data and events / alarms shall be stored on hard disk. The hard disk area reserved
for data storage shall be managed on a first-in-first-out basis. The amount of hard disk
space available for data storage shall be agreed with the Engineer.
Data archive shall be performed automatically by the SCADA system by writing weekly data
to the optical drive. This process shall be completely automatic, to ensure that the data
archive is successful, the system shall perform all checking of system devices as required
and prompting of the supervisor will be performed only to assist with fault diagnosis to
resolve problems associated with a failure to write archive data. The time at which data
archive takes place shall be capable of being changed by the supervisor.
An alarm shall be generated if for any reason the hard disk is nearing full capacity. This
warning shall be set at 80% of disk capacity. Additionally, an alarm shall also be generated
via the PLC system to telemetry.
24.5 Reports
The software shall provide Operational, Engineering and Management Reports. As a
minimum these shall include:
Daily / weekly summated flow
Min / max / average process data
Process trends
Chemical consumption
Power usage, etc.
Data on operational plant and process availability
Any other reports required arising from discussion with Scottish Water on a site basis.
The reports shall be generated using Microsoft Excel and shall be generated automatically
and on operator request. They will be stored in electronic format in addition to a printout.
Selection of the Report button will initiate an instance of Excel for the viewing of System
reports.
The printing, saving, closing etc of any report will be provided by the facilities provided
within Excel.
Note that it will be the Users responsibility to close any instance of Excel.
The system reports are to be constructed to a standard layout. These reports are to be
formatted within Excel. Within Excel the Page can be split into a number of sections. For
the purpose of these reports the following sections are to be used.
24.5.1 Page Header
This contains information that will appear on every page positioned below the report header
on page one and at the top of every other page. This section should contain the main report
title positioned centrally on the page.
8/10/2019 Section 24 - SCADA Rev 1.pdf
13/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 11
24.5.2 Details Section(s)
A 'details' section will appear on every page of the report with a new details section on every
page, i.e. three pages means three details sections. These sections contain all of the details
contained within each report. The 'details' section should be constructed to allow the
relevant information to be easily read. A 3pt horizontal Navy line should separate different
sections within the details section.
24.5.3 Page Footer
This will appear at the bottom of every page of the report. This section should contain the
page number and total number of pages in the format Page 1 of 5. This should be
positioned centrally on the page. A 3pt horizontal line should be positioned above the page
number to separate this from the main body of the report.
24.5.4 System Time
The SCADA system real time clock shall be synchronised to local time.
Where a real time clock is required in a PLC / SCADA control application, all PLCs/ SCADA/
Telemetry shall be synchronised to a single clock source.
24.5.5 Analogue Dead-bands
The dead-band of each analogue shall be defined and submitted to the Engineer for
approval in the FDS.
24.5.6 System Diagnostics
The SCADA system shall include internal diagnostics facilities. As a minimum the number of
communications statistics counters e.g. number of errors, number of packets/bytes sent and
received, shall be recorded, totalised and displayed on a diagnostic mimic until reset by the
operator. The reset shall be recorded by a message in the event log.
Screens shall be provided for I/O diagnostics. E.g. Raw digital inputs and outputs from the
PLC.
In PLC network systems, diagnostics screens shall be provided for all PLCs on the network.
Watchdog timers shall be implemented to monitor the communications for each PLC that
communicates with the SCADA system. On expiry of a watchdog, a communications alarm
(relevant to that particular failure) shall be annunciated on both the SCADA system and the
telemetry outstation.
24.5.7 Historical and Real Time Trend Graphs
All process analogues shall be configured for real time and historical trending and logging.
The system shall allow for one, two, three or four variables to be displayed on the same
trend. Following discussions with the Engineer, the groups of signals allocated to trends
shall be as defined in the FDS.
24.5.8 Standards for Programming
No programming shall be carried out unless the required functionality cannot be
implemented by configuration of the supplied software packages. In the event that
programming is required written approval from the Engineer must be obtained.
24.5.9 Performance of SCADA System
The table shown in Appendix 1 shall define the performance requirements.
8/10/2019 Section 24 - SCADA Rev 1.pdf
14/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 12
24.6 Fibre Optic Cable for SCADA System
24.6.1 Scope of this Document
This specification covers the general requirements to be applied to all Control & Automation
systems and equipments to be installed within Oman Wastewater Services Company
projects.
This document is a guide to the design, installation and testing of different types of fibre
optic cables including buried, ducted and blown. The Installation of fibre optic cables shall
be governed by, but not limited to, the provisions specified, and shall be undertaken to high
standards of workmanship and in a safe manner. This specification shall be utilised with one
or more of the referenced international standards to complete the COMPANY requirement
for installation Works. However, it remains the contractor responsibility to ensure the
complete installation of FOC. This specification shall be used in conjunction with the
separate related sections of the Electrical Standard Specifications as follows:
24.6.2 Applicable Standards, Specifications and Codes
The design of the projects shall comply with the following codes and standards
British Standards:
BS 89 Direct acting indicating analogue electrical measuring instruments and
their accessories.
BS 381C Colour for Identification, Coding and special purposes
BS 4794 Control Switches
BS 6231 PVC Insulated cables for switchgear
BS 381C Colour for Identification, Coding and special purposes
International Standards
EIA-455 Standard Test Procedures for Fibre Optic Fibres, Cables, Transducers,
Connecting and Terminating Devices.
EIA-598 Optical Fibre Colour Coding
IEC 529 Environmental protection
IEC 793-1 Generic Specification for Optical Fibres
IEC 794-1- General Specification for Optical Fibre Cables
IEC 794-2 Product Specifications for Optical Fibre Cables
IEC 874 Connector for Optical Fibres and Cables.
IEC 1073 Splices for optical fibres and cables.
IEC 1218 Fibre optic - Safety guide.
ITU-T G.652 International Telecommunication Union- Telephony: Characteristic of
Single mode Optical Fibre Cable
Omani Electrical Standards.
All relevant local and Omani regulations shall be complied with. Any item not specifically
detailed in this Specification, which are necessary to provide a safe and fully operational
working system, shall be deemed to be included.
8/10/2019 Section 24 - SCADA Rev 1.pdf
15/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 13
Company HSE Standards
All Company Health Safety and Environmental Protection Standards shall be complied with.
Refer the Document: Construction Safety Standards CSS 01, for further details.
Compliance with Standards
All requirement of this specification shall apply except where the manufacturers standards
are more stringent and then the latter shall apply. If a standard becomes old and a latest
issue of the same standard is available then the latest issue shall be followed. For any
deviation from these standards, the written agreement of the Company shall be obtained
prior to commencing associated engineering or construction work.
24.6.3 Service and Environmental Conditions
Temperature:
Recorded of extreme of site ambient temperature are: +5oC to +50
oC
Al ti tude:
Height above Sea level: 0 - 2000m
Relative humid ity:
Highest: 95%
Lowest: 40%
Atmosphere:
The equipment and material are to be suitable for installation in coastal industrial plant
where the atmosphere is subject to dust storms.
Mean annual rain fall: 100mm
Daily average wind speed: 4-5 m/sec
24.6.4 Priority
Standards shall take the following priority (in order of highest to lowest):
The project related technical specification (Shall be attached as Annexure)
This document ( Standard Specifications )
International Standards
Industry Standards
24.6.5 Safety regulations
Safety is the most important aspect of a fibre optic cable installation and highest priority
shall be assigned to the safety issues. These safety recommendations are meant to
supplement, not to replace, relevant local & national laws, company-specific safety practices
and other codes and regulations. Some of the key points are:
- To prevent eye damage, never look into the end of an optical fibre unless a power meter isused to verify that no optical signal is present.
- Testing for explosive gases and proper ventilation of underground facilities is vital.
- Capable ventilation equipment must be used according to local regulations & practices priorto installation of FOC cables in underground facilities.
- A running ground must be used whenever there is the possibility that a voltage may besomehow applied to the cable. The use of compressors for cable blowing requires carefulattention be paid to the safety instruction for the compressor and all compressed air fittings.
8/10/2019 Section 24 - SCADA Rev 1.pdf
16/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 14
24.6.6 Definitions
Technical Terminology
Macro bend
A relatively large-radius bend in an optical fibre, such as might befound in a splice organiser/enclosure tray or a fibre-optic cable thathas been bent. The definition of "sufficiently large" depends on thetype of fibre. Single-mode fibres have a low numerical aperture,typically less than 0.15, and are therefore are more susceptible tobend losses than other types. Normally, they will not tolerate aminimum bend radius of less than 6.5 to 7.5 cm (2.5 to 3 inches).
Macro bend loss
In an optical fibre, the loss attributable to macro bending. If a lossfound from OTDR test at 1550nm wavelength is greater than 0.05dB comparing with loss found at 1310nm wavelength for the samepoint then this considered to be a macro bend loss contributed todamages and bents done during installation or objects (e.g. stones)damaged the fibre.
Micro bend
In an optical waveguide, sharp curvatures involving local axialdisplacements of a few micrometers and spatial wavelengths of afew millimetres. Note: Micro bends can result from waveguidecoating, cabling, packaging, and installation. Micro bending cancause significant radiative loss and mode coupling.
Micro bend loss
In an optical fibre, the optical power loss caused by a micro bend. Ifa loss found from OTDR test at 1310 nm to be greater then 0.03 dBat a point, where there is no splice then this is considered to bemicro bend loss.
Abbreviations
AC Alternating Current
ADSS All Dielectric Self Supporting
BS British Standard
CCIR Committee Consultative International Radio
CCITT Committee Consultative International Telegraphy and Telephony
Db Decibel
DC Direct Current
24.6.7 Design Stages and Submissions
In the design stage, the following shall is mandatory:
A pre-survey of the route shall be conducted for all types of installations. Optical power loss budget shall be calculated for any FOC link.
Problem areas shall be identified & fixed and an installation plan should be clearly
defined prior to the start of the installation.
In addition, the Contractor shall submit the followings:
Catalogue Data: Catalogue data on conduit system, manholes, conduit fittings, conduit
plugs, pull rope, identification tape, and warning signs.
Detailed bill of materials.
8/10/2019 Section 24 - SCADA Rev 1.pdf
17/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 15
Drawings indicating the routes, total layout and locations of all manholes.
Catalogue data on all testing devices proposed for use plus certifications of accuracy,
calibration, and traceability to standards of the National Institute for Standards and
Testing.
In case of pressure blowing, detailed methodology of blowing FOC.
In case of HDPE duct installation, detailed installation methodology of the duct.
In case of cable pulling, pulling calculations for all conduit runs. A cable pulling and splicing work plan shall be submitted. Work plan shall include the
following. The name and qualifications of the supervisory personnel that will be directly
responsible for the installation of the cable and/or conduit system.
24.6.8 Route survey
The Contractor shall make a physical survey of the project site for the purpose of
establishing the exact cable routing, termination points, jointing locations and cutting lengths
prior to the commencement of any work or committing any materials. The Contractor shall
conduct the detailed survey and confirm the line route. If a change in route is required for
any practical reason, prior approval should be obtained from the Company. The contractor
shall ensure that clearances are maintained from the fibre optic cable to any part of the line
or surroundings.
24.6.9 Optical Power Loss Budget
The optical Power Budget presents the optical budget calculations. The link calculations
(OLTE - OLTE) shall be designed to give a bit error rate of better than 1 x 10-9, based on
the average expected joint loss. Table 1 shows the parameters to be included for calculating
the required System margin.
Table 1: Required System Margin
System Margin dB
Equipment Degradation (ageing of Laser lifetime 3
Design Noise 1
Operation Margin (Safety Margin) 1.5
Future Splice Margin (The system shall allow at
lease 10 additional joints)
0.1 per splice
The fibre optic link shall accommodate up to additional 10 joints (5 repairs) without
exceeding the error performance. Table 2 shows the recommended parameters to be
included for calculating the link losses.
Table 2: Recommended link losses parameters
1.1.
24.6.10 Testing
The Contractor shall perform pre-installation and post-installation FOC tests. The Company
Site Representative shall be notified a minimum of 10 days in advance so that these tests
are witnessed. The Contractor shall carry out all the Site Acceptance Tests (SAT) required
to prove that the FOC is free from damage, installed according to the Company
specifications and requirements and functioning properly. The contractor shall provide a
detailed Integration acceptance test document with the following information as a minimum
for approval by the Company before the scheduled test. The Company at its own discretion
Link Losses dB
Cable loss (G.652) 0.4 dB/km
Splice loss (G.652) 0.1
Connector Loss 0.5
FDF loss (Connector loss + Jumper loss) 0.75
8/10/2019 Section 24 - SCADA Rev 1.pdf
18/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 16
shall ask the contractor to include (or waive) any tests to ensure proper functionality of the
network
Test Plan
Schedule
Procedures
Equipment setup diagrams
Result Sheets
24.6.11 Specifications For FOC Network Materials And Accessories
The following sections comprise guidelines for the mostly used materials for FOC network
and its specifications. However, it remains the Contractor responsibility to identify and
procure all the required materials for the complete FOC installation work.
24.6.12 Fibre Optic Cable
It describes the construction, performance, acceptance criteria, and installation of
polyethylene sheathed armoured optical cables (PSA) and polyethylene sheathed
dielectric optical cables (PSD).
Design PSA : Armoured Cable
Design PSD : Dielectri c Cable
High molecular weight PE sheath
Water Blocking Tape
Ripcord
Dielectric Strength Yarn
Buffer Tubes & Fibers
Water Blocking Yarn
FRP Rod
High Molecular Weight PE Sheaths (2)
Corrugated Steel Tape
Water Blocking Tape
Ripcords (2)
Dielectric Strength Yarn
Buffer Tubes & Fibers
Water Blocking Yarn
FRP Rod
8/10/2019 Section 24 - SCADA Rev 1.pdf
19/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 17
For PSA cable, applications include pulling/blowing into ducts and direct burial by plowing or
by trench & backfill method. PSA designs should be well protected against attack by
rodents & termites and have excellent crush & impact resistance to provide protection
against the rigors of direct burial installation. For PSD cable, deployments are limited to duct
installation by pulling or blowing. The cables described herein have a stranded loose buffer
tube construction that is designed so that no net axial fibre strain occurs at maximum pulling
tension.
24.6.13 Cable Construction
The required cable is comprised of the following components listed radially from the centre.
A central strength & anti-buckling member made of 2.5 mm GRP.
Super absorbent polymer yarns wrapped around the central member (or super
absorbent polymer binders suitably located elsewhere in the cable structure)
SZ stranded loose buffer tube containing optical fibres and a thixotropic filling
compound.
Optionally, filler rods may be used in lower fibre count cables to keep the structure
round.
A layer of aramid yarn that is engineered to provide the required level of tensile
strength.
A super absorbent polymer tape wrapped around the aramid yarn
One or two ripcords
A PE inner sheath
A corrugated steel armour tape (PSA only)
A PE outer sheath (PSA only)
24.6.14 General Requirements
The cables must be circular in cross section and free from pinholes, joints, repairs and other
defects. Materials used in the construction of the cable shall not affect the physical or optical
properties of the fibres and shall be compatible with each other. The fibre and stranded
loose tubes shall be colour coded as specified below to provide easy identification at either
cable end.
The cable must be of stranded loose buffer construction where fibres are contained in aseries of tubes (6 or more). The fibres must have enough free space inside the tube to
provide the required level of mechanical and environmental performance. The inside of the
tubes must be filled with a thixotropic gel to prevent moisture ingress. The buffer tube-filling
compound must be non-toxic and dermatologically safe. It must free from foreign matter,
chemically and mechanically compatible with all cable components, non-nutritive to fungus,
non-hygroscopic, and electrically non-conductive.
For lower fibre counts, filler rods may be placed into any unused positions in the stranded
fibre optic core. The filler material must be made of a material compatible with other core
components. Each buffer tube in the finished cable is distinguishable from the others by
means of colour coding as follows:
Tube Number Buffer Tube Colour
1 Blue
2 Orange
3 Green
4 Brown
5 Gray
6 White
8/10/2019 Section 24 - SCADA Rev 1.pdf
20/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 18
24.6.15 Optical Fibres
All optical fibres must meet the requirements set forth in ITU-T Recommendation G.652 and
the detail specifications below. Each optical fibre must be protected with a dual layer
acrylate coating. The inner layer shall be optimised for adhesion to the cladding glass,
strippability and temperature performance while the outer coating shall be a harder material
optimised for abrasion performance. Each cable must have traceability of the optical fibre
back to the original fibre ID number and test parameters as provided by the fibremanufacturer.
Optical fibres shall have a high level of splice compatibility with optical fibres from other
manufacturers. No fibre splices are allowed in any continuous length of cable. Each fibre in
a tube must be distinguishable from other fibres in the same tube by means of colour coding
ink discernible throughout the design life of the cable. Required fibre colour sequence is as
follows:
Fibre Number Fibre Colour Fibre Number Fibre Colour
1 Blue 4 Brown
2 Orange 5 Gray
3 Green 6 White
24.6.16 Super-absorbent Polymer Materials
Cables must be water blocked with superabsorbent polymer water blocking yarns, tapes
and/or binders. The superabsorbent polymer materials must be safe, easy to remove and
require no special handling or solvents.
24.6.17 Inner Sheath
The sheath must be made of a high molecular weight linear PE meeting the requirements of
ASTM-1248, type III, Class C, Category 5, Grade J3. The inner sheath thickness should be
nominally 1.0 mm or to meet the required cable mechanical and environmental performance
characteristics.
24.6.18 Strength Yarns
The strength yarns for PSA and PSD cables shall be aramid yarns.
24.6.19 Outer Sheath
The sheath must be made of a high molecular weight linear PE meeting the requirements of
ASTM-1248, type III, Class C, Category 5, Grade J3. The nominal outer sheath thickness
shall be 1.8 mm. The average thickness of any cross section shall not be less than 90% of
the specified thickness. The minimum spot thickness shall not be less than 80% of the
specified thickness.
24.6.20 Sheath Markings
The outer sheath shall be marked with the following:
The words Oman Wastewater Services Company S.A.O.C Fibre Optic Cable.
The manufacturer name.
The year of manufacture (for example: Year 2007).
The fibre count (for example: 24 F).
Meter marks at a one meter interval with arrowhead indicating upward direction of meter
markings.
8/10/2019 Section 24 - SCADA Rev 1.pdf
21/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 19
24.6.21 Cable Performance Requirements
Mechanical Characteristics
Parameter Requirements
Maximum pulling tension (MPT) 3500N for PSA2700N for PSD
Minimum bend radius, no load 10 times the cable outside diameter
Min bend at max pulling tension 15 times the cable outside diameter
Compressive Load 5000N/10 cm for PSA2500N/10 cm for PSD
Impact Load 25 N-m for PSA15 N-m for PSD
Optical Performance for G.652 Single Mode Fibres
Parameter Requirement
Attenuation variation with wavelength (1285-1330 nm)
< 0.1 dB/km
Attenuation at water peak 2.1 dB/km
Attenuation with bending (100 turns on a 75mm dia mandrel)
0.1 dB at 1550 nm
Attenuation coefficient at 1310 nm 0.38 dB/kmAttenuation coefficient at 1550 nm 0.25 dB/km
Optical discontinuities at 1310 and 1550 nm < 0.1 dBChromatic dispersion between 1285 and1330 nm
3.5 ps/nmkm
Chromatic dispersion at 1550 nm 18 ps/nmkmCable cutoff wavelength 1260 nmPMD Coefficient 0.5 ps/km
Optical Performance for w ith 62.5/125 GI Multimode fibres
Parameter Requirement
Attenuation coefficient at 850 nm 3.0 dB/km
Attenuation coefficient at 1300 nm 0.7 dB/kmOptical discontinuities at 1310 and 1550 nm < 0.1 dB
Bandwidth Dist Product at 850 nm 160 MHzkm
Bandwidth Dist Product 1300 nm 500 MHzkmEnvironmental Performance of Cable
Parameter Requirement
Operating Temperature -20 to +70 C
Allowable change in attenuation 0.05 dB/kmInstallation Temperature -20 to +55 C
Storage Temperature -20 to +70 C
24.6.22 HDPE Duct Material
The raw material used for HDPE ducts shall meet the following requirements:
The anti-oxidants used shall be physiologically harmless.
Single pass rework material of the same composition produced from the manufacturers
own production shall be used and it shall not exceed 10% in any case. The raw material used for extrusion shall be dried to bring the moisture content to less
than 0.1%.
Suitable UV stabilizers shall be used for manufacture of the duct to protect against UV
degradation, when stored in open for a minimum period of 8 months.
The raw material used in the manufacture of the duct shall be such that the service life
of the duct and all its accessories can be expected to be more than 50 years including
the life of permanent lubricant.
8/10/2019 Section 24 - SCADA Rev 1.pdf
22/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 20
24.6.23 HDPE Standards
HDPE Ducts shall conform to the following standards & Specifications
A. IS: 4984 Specifications for HDPE Pipes
B. IS: 2530 Method for tests for polyethylene moulding materialsand compounds.
C. IS : 9938 Recommended colours for PVC insulation for LF wiresand cables.
D.TEC Specs no. G/CDS-08/01/Dec.99
HDPE Ducts for use as duct for optical fibre cable
E. IS : 7328 HDPE material for moulding and extrusion
F. ASTM D 1693 Test method for environmental stress cracking ofethylene plastics.
G. ASTM D 1505 Test method for density
24.6.24 HDPE Requirements
Visual Inspection: The ducts shall be checked visually for ensuring good workmanship that
the ducts shall be free from blisters, shrink holes, flaking, chips, scratches, roughness,
break and other defects. The ducts shall be smooth, clean, round. The ends shall be cleanly
cut and shall be square with axis of the duct. The ducts shall be of different colours and for
further identification, contrast striping shall be provided. These stripes shall be co-extruded
during the duct manufacturing. The material of the stripes shall be same as that of base
compound for the duct.
Identification Markings: The duct shall be prominently marked with indelible ink, with the
following information at intervals every meter to enable identification of the pipe. The size of
ink markings shall be distinct, clearly and easily visible.
Manufacturers name (Also can be in abbreviated form)
Oman Wastewater Services Company S.A.O.C
Name of the duct with size Specific serial number of the duct
Date of manufacture
Sequential length marking at every meter with Arrow mark in ascending order.
24.6.25 HDPE Duct Accessories
The following Accessories are required for jointing the ducts and shall be supplied along
with the ducts. The manufacturers shall provide complete design details, procedure for
method of installation and type/grade of the material used for the accessories. Some of the
accessories are:
Plastic Coupler: The coupler shall be of Push-fit type having Push-Lock mechanism,
which enables them to be installed on ducts without pre-dismantling. The design of this
shall be simple, easy to install and shall provide air tight and water tight leak proof joint
between the two ducts. It shall withstand the air pressure test of 15 Kg/cm2 for a
minimum period of 2 hours without any leakage.
End Plug: This is for sealing the ends of empty ducts, prior to installation of O.F. cable
and shall be fitted immediately after laying of duct, to prevent the entry of any dirt, water,
moisture, insects/rodents etc into ducts.
Cable Sealing Plug: This is used to seal the ends of ducts perfectly, after the cable is
installed in the duct, to prevent the entry of dirt, water, moisture, insects/rodents etc into
ducts.
8/10/2019 Section 24 - SCADA Rev 1.pdf
23/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 21
End Cap: These caps, made of hard rubber/plastics, shall be fitted on each end of duct
coil after manufacturing. These shall avoid ingress of dust, mud, rain water etc. into
ducts, during transit and storage.
24.6.26 Cable Markers
The markers shall be made from Aluminium with width of 100mm, height of 30mm and
thickness of 1mm. The text shall be engraved on the Aluminium marker. The text shall
provide details of the FOC type, the route, manhole number, start and end locations.
24.6.27 Duct or Conduit Seals
The Duct Sealing Kit prevents water and gas from entering a manhole through a cable duct.
24.6.28 Pull Rope
Low friction, polyethylene jacketed polypropylene rope with 1800 psi tensile strength.
24.6.29 Fan-Out Termination for Loose Tube Cables
Individual fibres within the loose tube cable require handling protection inside the
termination cabinets. Fan-out kits shall be installed in the patch panel enclosures to
transition the loose tube fibres to ruggedized tight-buffered fibre pigtail cables. Fan-out
tubes or furcation kits shall not be used. Optical fusion splices shall connect the loose tube
fibres to the tight-buffered pigtail cables. The optical splice loss shall comply with the
specifications for optical splices. Splice protection sleeves shall be employed on all splices
to protect the splices.
24.6.30 Pigtail Cable Specifications
Optical characteristics shall comply with the optical f ibre performance specifications.
Buffer material: Thermoplastic
Buffer O.D.: 900 um
Strength Member: Kevlar
Jacket Material: PVC
Jacket O.D.: 3.0 mm
Temperature Range: -20 to + 70 C
24.6.31 Fibre Optic Termination Patch Panels
The contractor shall supply the required quantities of pig tails, patch cords and patch panels.
The fibre optic cable shall terminate inside a communications cabinet on a termination patch
panel. All single mode fibre sub-cables or cores within the cable shall be terminated with E-
2000 compatible connectors. All Multimode fibre sub-cables or cores within the cable shall
be terminated with ST2 compatible connectors.
The patch panel shall have a fibre capacity equal to the total number of f ibres (connected
and spares) for all cables to be connected. All unused couplings shall have protective dust
covers. All panels shall be furnished with front removable door or cover, Factory-terminated,
tight-buffered, agamid-reinforced fibre optic jumper assemblies or interconnect cables,
standard 3.0 mm O.D., shall connect the optical cable terminations to the patch panel
couplings. The termination patch panel shall be equipped with a suitable means for routingand securing of cables and shall provide a suitable means of protection for the mounted
fibre connectors to prevent damage to fibres and connectors during all regular operation and
maintenance functions. All cables shall be provided with strain relief. Bend diameters on
cable fibres and jumpers must be greater than four (4) inches at all times to ensure optical
and mechanical integrity of the optical fibres.
8/10/2019 Section 24 - SCADA Rev 1.pdf
24/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 22
24.6.32 Optical Connectors
All connectors shall be field-installable and perfectly matched to the cable used. The
connectors shall provide tight fitting termination to the cladding and buffer coating. Epoxy
based or hot melt adhesives shall be used to bond the fibre and buffer to the connector
ferrule and body prior to polishing the end face. No dry-termination or quick crimp
connectors are allowed.
Connectors shall have a maximum allowable connection loss of 0.3 dB per mated pair, asmeasured per EA.-455-34. No index-matching gel is to be used, dry interfaces only. Single
mode connectors shall be capable of field installation on 9/125 micron fibres with 900
micron buffers (OD).
Each connector shall be of the industry standard E-2000 or ST2 type compatible, designed
for single mode or multimode tolerances, respectively, and shall meet or exceed the
applicable provisions of EIA.-455-5, 455-2A, and 455-34, and shall be capable of 100
repeated matings with a maximum loss increase of 0.1 dB. Connectors shall incorporate a
key-way design and shall have a zirconia ceramic ferrule. Connector bodies and couplings
shall be made of corrosion-resistant and oxidation-resistant materials, such as nickel plated
zinc, designed to operate in humid environments without degradation of surface finishes.
24.6.33 ManholesThe manhole shall have the followings:
Minimum size of 600 x 600mm (LxW) and a depth of 600 mm
Ductile iron covers with a galvanised steel frame. The covers will be tested to the
European standard EN124 B125. Security: Special "penta head" bolts shall be fitted.
These can only be opened & locked with a special socket, which is also available.
Duct Entry
Internal Cable furniture
24.6.34 Separation from non-Electrical Installations/Structures
For non-Electrical structures or installation, a minimum separation between FOC and the
structure shall be 300 mm, while running parallel. While crossing the structure, the minimum
separation shall be 200 mm. The structure can be a pipe for gas, oil, water, sewage or other
non- Electrical installation.
24.6.35 Separation from Electrical Installations/Structures
When installing a buried optical fibre cable near existing HV infrastructure, maintain a 3
metre separation between the fibre optic cable and poles, stays and existing HV electrical
cables. Where cable is being installed in the same trench with other electrical cables, the
minimum separation is given as follow:
Minimum separation from electrical cables is 750mm (LV), 1000mm (11kV) and
1500mm (33kV).
Note the requirements for vertical tiles between HV cables and the fibre optic cable.
24.6.36 MarkersCable route markers will be installed at the completion of the cable installation and generally
after the cable trench has been back filled and compacted. To enable the use of machines
to complete this backfilling operation, temporary off set pegs will be placed in the ground
with a recorded measurement to the cable. This measurement will then be used to establish
the cable route marker; 1 metre from the cable after the machines has finished their
activities.
8/10/2019 Section 24 - SCADA Rev 1.pdf
25/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 23
The cable markers shall be installed in accordance with the followings:
Along FOC independent route, at every 100m.
At every change in direction.
At both ends of every conduit.
At each joint or/and manhole.
The distance to the cable is to be recorded on each marker, together with the cable depth at
each point. The supply and installation shall include the route markers including plates,posts and all the necessary materials required for installation.
24.6.37 Direct Buried FOC/HDPE Duct
Normal soil trench shall be excavated up to 750mm deep. The trench shall be filled with
clean and soft sand up to 150mm from the bottom of the trench with the surface levelled
(flattened).
The trench shall be backfilled up to 500mm from the bottom of the trench with excavated
material (with no stones larger than 4mmx4mmx4mm size). A mesh filter shall be used to
remove big stones and sharp materials from the excavated material prior to backfilling. The
trench shall be backfilled with remaining excavated material with big and sharp stones
removed up to the normal ground level. The Contractor shall inform OWSC regarding
backfilling schedule to enable quality verification/inspection of cable installation andbackfilling for different layers.
The HDPE duct/conduit shall be of corrugated construction with a plain internal wall of
LDPE (low-density polyethylene) and an external corrugated wall of HDPE (High Density
Polyethylene). External colour shall be blue. Manufacturing shall be according to STD.
EN50086-1 and EN 50086-2-4. Conduit shall withstand 450N with maximum deflection of
5% of internal diameter and 750N with maximum deflection of 15%. Conduit shall withstand
impact test specified in EN 50086-2-4- sect. 10.3. Suitable jointing tubes with indented rings,
which mate with external corrugations, shall be utilised for all joints. Joints shall provide a
watertight seal.
During construction the ends of the conduit shall be closed to prevent foreign objects. Upon
completion the ends shall be sealed to prevent ingress of water and sand using a plug.
Sealing shall be achieved without use of glues, sealing compounds or foams. After its
installation, the conduit shall be cleaned on the inside from any kind of material (earth,
stones, etc.). A puling rope shall be provided in the conduit for future use.
The cable/duct drum shall be installed on the cable carrier (trailer). This cable carrier shall
move along the trench line with the cable being manually spooled off the drum. The drum
shall be turned by hand and the cable laid without any tension, directly into the trench. At no
stage is the cable to be pulled off the drum. The cable/duct shall not be over-stressed during
the unwinding and laying process. In cases where the cable or duct is drawn off the cable
reel a swivel joint and mechanical "fuse" of the correct capacity shall be used to avoid
exceeding the designed maximum pulling force for the cable.
Figure-8s shall be used for backfeed pulling or other situation where removal of the cable
from the drum is needed. The size of the figure-8 should be marked with cones or othersuitable devices. The figure-8 shall be at least 5 meters long with each loop at least 2 meter
minimum diameter.
24.6.38 Maximum Pulling Tension (MPT)
All Fibre Optic cables have a rated maximum. The MPT is clearly shown on cable
specification sheet issued by the Manufacturer. During installation, the tension applied to the
cable MUST be monitored with a calibrated load cell or tensiometer (dynamometer). Once
the cable tension reaches 90% of MPT, the installation must stop to troubleshoot the cause.
8/10/2019 Section 24 - SCADA Rev 1.pdf
26/30
8/10/2019 Section 24 - SCADA Rev 1.pdf
27/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 25
The area around the manhole shall be compacted. Upon final acceptance of the
conduit/duct system all manholes shall be free of debris and water, and be ready for
cable installation.
24.6.42 Drawings and Documents
The documents are an integral part of the equipment required to maintain and restore a fibre
optic system. The following information shall be included in the documentation package.
24.6.43 Test Results
Hard and electronic copy of test documentation shall be submitted to the Company. The
documentation shall include the trace plot, index, dB/km loss, cable length, date and time of
test, wavelength, pulse width, the test site, cable ID, fiber number and type, and operators
initials. The Contractor shall compare the pre-installation test results to the post-installation
results. If a deviation of greater than one dB occurs, the Company shall be notified in writing
by the Contractor.
24.6.44 Key Map
The key map is a geographical map showing the system route in relation to roads and
highways. Its purpose is to provide quick access to key areas of the system, such as field
splice points and major road crossings. Sheath metre marks should be indicated on the mapfor splice points, road crossings, etc. It shall also provide horizontal and vertical alignment of
FOC.
24.6.45 Circuit Diagram
The circuit diagram is a schematic that identifies the actual f ibre circuits, system number,
working and protected fibres, fibre/buffer colours, priority sequence during restoration and
other pertinent information such as transposed fibres.
24.6.46 Manufacturer provided documentation
The manufacturer provided documentation should include the cable data sheets of each
cable reel, documentation provided on the fibre, results of calculations of the field strength
levels relative to different structure types. The original copy should be maintained and
handed over to the Company representative for record.
24.6.47 As-Built Documentation
The as-built drawings and documents shall identify the actual apparatus units at each
structure and other information such as the structure type and dimensions, cumulative
distance to each termination point from the structure, any grounding or bonding detail, etc.
These drawings and documents are typically the construction detail sheets that have been
corrected to reflect any changes during construction. As built drawing shall record all
deviations, deletions and additions with respect to the original scope.
24.7 SCADA System Tests
The contractor shall develop a test schedule for the SCADA system. The test schedule
shall be submitted to the Engineer for approval.
SCADA system tests shall place particular emphasis on tests that demonstrate compliance
in the following areas:
I/O database
Mimic displays
Operator controls
Manual operations
Alarm generation
8/10/2019 Section 24 - SCADA Rev 1.pdf
28/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 26
Interlocks
Data entry (alarm and control set points)
Control simulation
PLC to SCADA communications
External interfaces
Memory backup
Archiving & retrieval of data Mains failure and recovery facilities
Event and alarm log/summary
Report generation
System performance
Automatic house keeping and file management
Disaster recovery
Unless otherwise stated, tests shall be demonstrated to the Engineer during both the FAT
and SAT.
In the event that the Engineer has stated that the testing shall not be witnessed, the
Contractor shall perform the testing without the Engineer present and upon completion,
submit the test results to the Engineer.
24.8 SCADA System Colour Coding
Color coding shall be in as provided below and where not stipulated in accordance with BS
EN 60073:2000:
Status of Operation Color Code
Equipment running and normal Green
Equipment stopped and normal White/Grey
Equipment tripped Yellow
Equipment selected on Auto Blue
Equipment or process unsafe / danger in operation Red
Panel Energized /isolator or ACB ON White
Process Flow ON (e.g. Valves open) Green
Process flow Stopped OFF (e.g. Valves closed) White
8/10/2019 Section 24 - SCADA Rev 1.pdf
29/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
Section 24 Page 1
Appendix A
SCADA PerformanceRequirements
8/10/2019 Section 24 - SCADA Rev 1.pdf
30/30
Oman Wastewater Service Group Wastewater Standard Technical Specification
A1 APPENDIX 1
Description Response in
SecondsChange in status of a plant item (Digital) and display on SCADA 5
Change in status of a plant item (Analogue) and display on SCADA 5
Annunciation of an alarm from alarm condition occurring at plant 5
Display of a real time trend (including the data) with 24-hour axis. 5
Display of an historic trend (including data) with 4 traces and 24 hour axis 5
Display of the alarm summary page with a screen of alarms. 3
Time to silence the audible alarm after acknowledgement of the alarm. 0.5
Time for mimic to update after the execution of a control output on SCADA 4
Time for a new mimic to be displayed after a request to chain or load a new
mimic (including new data)
3