32
MS0114 21 13 13.00 10-1 SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION PART 1 GENERAL 1.01 SYSTEM DESCRIPTION Furnish piping offsets, fittings, and any other accessories as required to provide a complete installation and to eliminate interference with other construction. Install sprinkler system over and under ducts, piping and platforms when such equipment can negatively effect or disrupt the sprinkler discharge pattern and coverage. Provide wet pipe sprinkler system in areas indicated on the drawings . Except as modified herein, the system shall be designed and installed in accordance with NFPA 13, UFC 3-600-01, and UFC 4-211-01. Pipe sizes which are not indicated on drawings shall be determined by hydraulic calculation. Design any portions of the sprinkler system that are not indicated on the drawings including locating sprinklers, piping and equipment, and size piping and equipment when this information is not indicated on the drawings or is not specified herein. The design of the sprinkler system shall be based on hydraulic calculations, and the other provisions specified herein. 1.1.2 Hydraulic Design Hydraulically design the system per the schedule on the drawings. Hydraulic calculations shall be in accordance with the Area/Density Method of NFPA 13. Water velocity in the piping shall not exceed 20 ft/s. 1.1.1.1 Basis for Calculations The design of the system shall be based upon the existing fire pump capacity. Hydraulic calculations shall be based upon the Hazen-Williams formula with a "C" value of 120 for steel piping, 140 for new cement-lined ductile- iron piping, and 100 for existing underground piping. 1.2.1.2 Hydraulic Calculations Submit hydraulic calculations, including a drawing showing hydraulic reference points and pipe segments and as outlined in NFPA 13, except that calculations shall be performed by computer using software intended specifically for fire protection system design using the design data shown on the drawings. Software that uses k-factors for typical branch lines is not acceptable. Calculations shall be based on the water supply data shown on the drawings to substantiate that the design area used in the calculations is the most demanding hydraulically. Water supply curves and system requirements shall be plotted on semi-logarithmic graph paper so as to present a summary of the complete hydraulic calculation. Provide a summary sheet listing sprinklers in the design area and their respective hydraulic reference points, elevations, actual discharge pressures and actual flows. Elevations of hydraulic reference points (nodes) shall be indicated. Documentation shall identify each pipe individually and the nodes connected thereto. Indicate the diameter, length, flow, velocity, friction loss, number and type fittings, total friction loss in the pipe, equivalent pipe length and Hazen-Williams coefficient for each pipe. For gridded systems, calculations shall show peaking of demand area friction loss to verify that the hydraulically most demanding area is being used. Also for gridded systems, a flow diagram indicating the quantity and direction of flows shall be included. A drawing showing hydraulic reference points (nodes) and pipe designations used in the calculations shall be included and shall be independent of shop drawings. 1.2.2 Sprinkler Coverage Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall provide coverage throughout 100 percent of the building. This includes, but is not limited to, telephone rooms, electrical equipment rooms, boiler rooms, switchgear rooms, transformer rooms, and other electrical and mechanical spaces. Coverage per sprinkler shall be in accordance with NFPA 13, but shall not exceed 100 square feet for extra hazard occupancies, 130 square feet for ordinary hazard occupancies, and 225 square feet for light hazard occupancies.

SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

  • Upload
    others

  • View
    2

  • Download
    1

Embed Size (px)

Citation preview

Page 1: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

21 13 13.00 10-1

SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

PART 1 GENERAL

1.01 SYSTEM DESCRIPTION

Furnish piping offsets, fittings, and any other accessories as required to provide a complete installation and to eliminate interference with other construction. Install sprinkler system over and under ducts, piping and platforms when such equipment can negatively effect or disrupt the sprinkler discharge pattern and coverage. Provide wet pipe sprinkler system in areas indicated on the drawings . Except as modified herein, the system shall be designed and installed in accordance with NFPA 13, UFC 3-600-01, and UFC 4-211-01. Pipe sizes which are not indicated on drawings shall be determined by hydraulic calculation. Design any portions of the sprinkler system that are not indicated on the drawings including locating sprinklers, piping and equipment, and size piping and equipment when this information is not indicated on the drawings or is not specified herein. The design of the sprinkler system shall be based on hydraulic calculations, and the other provisions specified herein.

1.1.2 Hydraulic Design

Hydraulically design the system per the schedule on the drawings. Hydraulic calculations shall be in accordance with the Area/Density Method of NFPA 13. Water velocity in the piping shall not exceed 20 ft/s.

1.1.1.1 Basis for Calculations

The design of the system shall be based upon the existing fire pump capacity. Hydraulic calculations shall be based upon the Hazen-Williams formula with a "C" value of 120 for steel piping, 140 for new cement-lined ductile-iron piping, and 100 for existing underground piping.

1.2.1.2 Hydraulic Calculations

Submit hydraulic calculations, including a drawing showing hydraulic reference points and pipe segments and as outlined in NFPA 13, except that calculations shall be performed by computer using software intended specifically for fire protection system design using the design data shown on the drawings. Software that uses k-factors for typical branch lines is not acceptable. Calculations shall be based on the water supply data shown on the drawings to substantiate that the design area used in the calculations is the most demanding hydraulically. Water supply curves and system requirements shall be plotted on semi-logarithmic graph paper so as to present a summary of the complete hydraulic calculation. Provide a summary sheet listing sprinklers in the design area and their respective hydraulic reference points, elevations, actual discharge pressures and actual flows. Elevations of hydraulic reference points (nodes) shall be indicated. Documentation shall identify each pipe individually and the nodes connected thereto. Indicate the diameter, length, flow, velocity, friction loss, number and type fittings, total friction loss in the pipe, equivalent pipe length and Hazen-Williams coefficient for each pipe. For gridded systems, calculations shall show peaking of demand area friction loss to verify that the hydraulically most demanding area is being used. Also for gridded systems, a flow diagram indicating the quantity and direction of flows shall be included. A drawing showing hydraulic reference points (nodes) and pipe designations used in the calculations shall be included and shall be independent of shop drawings.

1.2.2 Sprinkler Coverage

Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall provide coverage throughout 100 percent of the building. This includes, but is not limited to, telephone rooms, electrical equipment rooms, boiler rooms, switchgear rooms, transformer rooms, and other electrical and mechanical spaces. Coverage per sprinkler shall be in accordance with NFPA 13, but shall not exceed 100 square feet for extra hazard occupancies, 130 square feet for ordinary hazard occupancies, and 225 square feet for light hazard occupancies.

Page 2: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

21 13 13.00 10-2

1.4 QUALITY ASSURANCE

Compliance with referenced NFPA standards is mandatory. This includes advisory provisions listed in the appendices of such standards, as though the word "shall" had been substituted for the word "should" wherever it appears. In the event of a conflict between specific provisions of this specification and applicable NFPA standards, this specification shall govern. Reference to "authority having jurisdiction" shall be interpreted to mean the Contracting Officer.

1.4.1 Fire Protection Specialist

Perform work specified in this section under the supervision of and certified by the Fire Protection Specialist who is an individual registered professional engineer who has passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveys (NCEES) or in a related engineering discipline with a minimum of 5 years experience, dedicated to fire protection engineering that can be verified with documentation or who is certified as a Level III Technician by National Institute for Certification in Engineering Technologies (NICET) in the Automatic Sprinkler System Layout subfield of Fire Protection Engineering Technology in accordance with NICET 1014-7. Submit the name and documentation of certification of the proposed Fire Protection Specialists, no later than 14 days after the Notice to Proceed and prior to the submittal of the sprinkler system drawings and hydraulic calculations. The Fire Protection Specialist shall prepare and submit a list of the fire protection related submittals, no later than 7 days after the approval of the Fire Protection Specialist, from the Contract Submittal Register that relate to the successful installation of the sprinkler systems(s). The submittals identified on this list shall be accompanied by a letter of approval signed and dated by the Fire Protection Specialist when submitted to the Government. The Fire Protection Specialist shall be regularly engaged in the design and installation of the type and complexity of system specified in the contract documents, and shall have served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months.

1.4.2 Sprinkler System Installer

Work specified in this section shall be performed by the Sprinkler System Installer who is regularly engaged in the installation of the type and complexity of system specified in the contract documents, and who has served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months. Submit the name and documentation of certification of the proposed Sprinkler System Installer, concurrent with submittal of the Fire Protection Specialist Qualifications.

1.4.3 Shop Drawings

Shop Drawings shall conform to the requirements established for working plans as prescribed in NFPA 13. Submit 3 copies of the Sprinkler System shop drawings, no later than 21 days prior to the start of sprinkler system installation. Drawings shall include plan and elevation views demonstrating that the equipment will fit the allotted spaces with clearance for installation and maintenance. Each set of drawings shall include the following:

a. Descriptive index of drawings in the submittal with drawings listed in sequence by drawing number. A legend identifying device symbols, nomenclature, and conventions used.

b. Floor plans drawn to a scale not less than 1/8" = 1'-0" which clearly show locations of sprinklers, risers, pipe hangers, seismic separation assemblies, sway bracing, inspector's test connections, drains, and other applicable details necessary to clearly describe the proposed arrangement. Each type of fitting used and the locations of bushings, reducing couplings, and welded joints shall be indicated.

c. Actual center-to-center dimensions between sprinklers on branch lines and between branch lines; from end sprinklers to adjacent walls; from walls to branch lines; from sprinkler feed mains, cross-mains and branch lines to finished floor and roof or ceiling. A detail shall show the dimension from the sprinkler and sprinkler deflector to the ceiling in finished areas.

Page 3: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

21 13 13.00 10-3

d. Longitudinal and transverse building sections showing typical branch line and cross-main pipe routing as well as elevation of each typical sprinkler above finished floor.

e. Details of each type of riser assembly; pipe hanger; sway bracing for earthquake protection, and restraint of underground water main at point-of-entry into the building, and electrical devices and interconnecting wiring. Submit load calculations for sizing of sway bracing, for systems that are required to be protected against damage from earthquakes.

1.5 DELIVERY, STORAGE, AND HANDLING

All equipment delivered and placed in storage shall be housed in a manner to preclude any damage from the weather, humidity and temperature variations, dirt and dust, or other contaminants. Additionally, all pipes shall either be capped or plugged until installed.

1.6 EXTRA MATERIALS

Submit spare parts data for each different item of material and equipment specified. The data shall include a complete list of parts and supplies, with current unit prices and source of supply, and a list of parts recommended by the manufacturer to be replaced after 1 year and 3 years of service. Include a list of special tools and test equipment required for maintenance and testing of the products supplied.

PART 2 PRODUCTS

2.1 STANDARD PRODUCTS

Provide materials and equipment which are standard products of a manufacturer regularly engaged in the manufacture of such products and that essentially duplicate items that have been in satisfactory use for at least 2 years prior to bid opening.

2.2 NAMEPLATES

All equipment shall have a nameplate that identifies the manufacturer's name, address, type or style, model or serial number, and catalog number.

2.3 REQUIREMENTS FOR FIRE PROTECTION SERVICE

Provide Materials and Equipment that have been tested by Underwriters Laboratories, Inc. and are listed in UL Fire Prot Dir or approved by Factory Mutual and listed in FM APP GUIDE. Where the terms "listed" or "approved" appear in this specification, such shall mean listed in UL Fire Prot Dir or FM APP GUIDE. Submit manufacturer's catalog data included with the Sprinkler System Drawings for all items specified herein. The data shall be highlighted to show model, size, options, etc., that are intended for consideration. Data shall be adequate to demonstrate compliance with all contract requirements. In addition, provide a complete equipment list that includes equipment description, model number and quantity.

2.4 UNDERGROUND PIPING COMPONENTS

2.4.1 Pipe

Piping from a point 6 inches above the floor to a point 5 feet outside the building wall shall be ductile iron with a rated working pressure of 150 psi conforming to AWWA C151/A21.51, with cement mortar lining conforming to AWWA C104/A21.4.

2.4.2 Fittings and Gaskets

Fittings shall be ductile iron conforming to AWWA C110/A21.10 with cement mortar lining conforming to AWWA C104/A21.4. Gaskets shall be suitable in design and size for the pipe with which such gaskets are to be used. Gaskets for ductile iron pipe joints shall conform to AWWA C111/A21.11.

Page 4: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

21 13 13.00 10-4

2.4.3 Gate Valve and Indicator Posts

Gate valves for underground installation shall be of the inside screw type with counter-clockwise rotation to open. Gate valves and indicator posts shall be listed in UL Fire Prot Dir or FM APP GUIDE.

2.5 ABOVEGROUND PIPING COMPONENTS

Aboveground piping shall be Schedule 40 steel.

2.5.1 Steel Piping Components

2.5.1.1 Steel Pipe

Except as modified herein, steel pipe shall be black as permitted by NFPA 13 and shall conform to applicable provisions of ASTM A795/A795M, ASTM A53/A53M, or ASTM A135/A135M. Pipe in which threads or grooves are cut or rolled formed shall be Schedule 40 or shall be listed by Underwriters' Laboratories to have a corrosion resistance ratio (CRR) of 1.0 or greater after threads or grooves are cut or rolled formed. Pipe shall be marked with the name of the manufacturer, kind of pipe, and ASTM designation.

2.5.1.2 Fittings for Non-Grooved Steel Pipe

Fittings shall be cast iron conforming to ASME B16.4, steel conforming to ASME B16.9 or ASME B16.11, or malleable iron conforming to ASME B16.3. Fittings into which sprinklers, drop nipples or riser nipples (sprigs) are screwed shall be threaded type. Plain-end fittings with mechanical couplings, fittings that use steel gripping devices to bite into the pipe and segmented welded fittings shall not be used.

2.5.1.3 Grooved Mechanical Joints and Fittings

Joints and fittings shall be designed for not less than 175 psi service and shall be the product of the same manufacturer;segmented welded fittings shall not be used. Fitting and coupling houses shall be malleable iron conforming to ASTM A47/A47M, Grade 32510; ductile iron conforming to ASTM A536, Grade 65-45-12. Gasket shall be the flush type that fills the entire cavity between the fitting and the pipe. Nuts and bolts shall be heat-treated steel conforming to ASTM A183 and shall be cadmium plated or zinc electroplated.

2.5.1.4 Flanges

Flanges shall conform to NFPA 13 and ASME B16.1. Gaskets shall be non-asbestos compressed material in accordance with ASME B16.21, 1/16 inch thick, and full face or self-centering flat ring type.

2.5.1.5 Bolts, Nut, and Washers

Bolts shall be conform to ASTM A449, Type 1 and shall extend no less than three full threads beyond the nut with bolts tightened to the required torque. Nuts shall be hexagon type conforming to ASME B18.2.2. Washers shall meet the requirements of ASTM F436. Flat circular washers shall be provided under all bolt heads and nuts.

2.5.2 Pipe Hangers

Hangers shall be listed in UL Fire Prot Dir or FM APP GUIDE and of the type suitable for the application, construction, and pipe type and sized to be supported.

2.5.3 Valves

2.5.3.1 Control Valve and Gate Valve

Manually operated sprinkler control valve and gate valve shall be outside stem and yoke (OS&Y) type and shall be listed in UL Bld Mat Dir or FM APP GUIDE.

2.5.3.2 Check Valve

Page 5: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

21 13 13.00 10-5

Check valve 2 inches and larger shall be listed in UL Bld Mat Dir or

FM APP GUIDE. Check valves 4 inches and larger shall be of the swing type with flanged cast iron body and flanged inspection plate, shall have a clear waterway and shall meet the requirements of MSS SP-71, for Type 3 or 4.

2.6 ALARM INITIATING AND SUPERVISORY DEVICES

2.6.1 Sprinkler Waterflow Indicator Switch, Vane Type

Switch shall be vane type with a pipe saddle and cast aluminum housing. The electro-mechanical device shall include a flexible, low-density polyethylene paddle conforming to the inside diameter of the fire protection pipe. The device shall sense water movements and be capable of detecting a sustained flow of 10 gpm or greater. The device shall contain a retard device adjustable from 0 to 90 seconds to reduce the possibility of false alarms caused by transient flow surges. The switch shall be tamper resistant and contain two SPDT (Form C) contacts arranged to transfer upon removal of the housing cover, and shall be equipped with a silicone rubber gasket to assure positive water seal and a dustproof cover and gasket to seal the mechanism from dirt and moisture.

2.6.2 Valve Supervisory (Tamper) Switch

Switch shall be suitable for mounting to the type of control valve to be supervised open. The switch shall be tamper resistant and contain one set of SPDT (Form C) contacts arranged to transfer upon removal of the housing cover or closure of the valve of more than two rotations of the valve stem.

2.7 SPRINKLERS

Sprinklers with internal O-rings shall not be used. Sprinklers shall be used in accordance with their listed coverage limitations. Temperature classification shall be ordinary. Sprinklers in high heat areas including attic spaces or in close proximity to unit heaters shall have temperature classification in accordance with NFPA 13. Extended coverage sprinklers shall not be used.

2.7.1 Pendent Sprinkler

Pendent sprinkler shall be of the fusible strut or glass bulb type, quick-response type with nominal 1/2 inch orifice. Pendent sprinklers shall have a polished chrome finish.

2.7.2 Upright Sprinkler

Upright sprinkler shall be brass quick-response type and shall have a nominal 1/2 inch or 17/32 inch orifice.

2.8 ACCESSORIES

2.8.1 Sprinkler Cabinet

Spare sprinklers shall be provided in accordance with NFPA 13 and shall be packed in a suitable metal or plastic cabinet. Spare sprinklers shall be representative of, and in proportion to, the number of each type and temperature rating of the sprinklers installed. At least one wrench of each type required shall be provided.

2.8.2 Pendent Sprinkler Escutcheon

Escutcheon shall be one-piece metallic type with a depth of less than 3/4 inch and suitable for installation on pendent sprinklers. The escutcheon shall have a factory finish that matches the pendent sprinkler heads. 2.8.3 Pipe Escutcheon

Escutcheon shall be polished chromium-plated zinc alloy, or polished chromium-plated copper alloy. Escutcheons shall be either one-piece or split-pattern, held in place by internal spring tension or set screw.

2.8.4 Sprinkler Guard

Page 6: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

21 13 13.00 10-6

Guard shall be a steel wire cage designed to encase the sprinkler and protect it from mechanical damage.

2.8.5 Identification Sign

Valve identification sign shall be minimum 6 inches wide by 2 inches high with enamel baked finish on minimum 18 gauge steel or 0.024 inch aluminum with red letters on a white background or white letters on red background. Wording of sign shall include, but not be limited to "main drain," "auxiliary drain," "inspector's test," "alarm test," "alarm line," and similar wording as required to identify operational components.

2.8.6 Automatic Air Vents

The automatic air vents shall be provided with shut off valves to allow for service.

PART 3 EXECUTION

3.1 FIELD MEASUREMENTS

After becoming familiar with all details of the work, verify all dimensions in the field, and advise the Contracting Officer of any discrepancy before performing the work.

3.2 INSTALLATION REQUIREMENTS

The installation shall be in accordance with the applicable provisions of NFPA 13, NFPA 24 and publications referenced therein. Installation of in-rack sprinklers shall comply with applicable provisions of NFPA 13. Al wet pipe sprinkler systems shall have automatic air vents so that all air will be vented from the pipe.

3.3 INSPECTION BY FIRE PROTECTION SPECIALIST

Prior to ceiling installation and concurrent with the Final Acceptance Test Report, certification by the Fire Protection Specialist that the sprinkler system is installed in accordance with the contract requirements, including signed approval of the Preliminary and Final Acceptance Test Reports. The Fire Protection Specialist shall: 1) inspect the sprinkler system periodically during the installation to assure that the sprinkler system is being provided and installed in accordance with the contract requirements, 2) witness the preliminary and final tests, and sign the test results, 3) after completion of the system inspections and a successful final test, certify in writing that the system has been installed in accordance with the contract requirements. Any discrepancy shall be brought to the attention of the Contracting Officer in writing, no later than three working days after the discrepancy is discovered.

3.4 ABOVEGROUND PIPING INSTALLATION

3.4.1 Protection of Piping Against Earthquake Damage

Seismically protect the system piping against damage from earthquakes. This requirement is not subject to determination under NFPA 13. Install the seismic protection of the system piping in accordance with UFC 3-310-04, NFPA 13 and Annex A. Include the required features identified therein that are applicable to the specific piping system.

3.4.2 Piping in Exposed Areas

Install exposed piping without diminishing exit access widths, corridors or equipment access. Exposed horizontal piping, including drain piping, shall be installed to provide maximum headroom.

3.4.3 Piping in Finished Areas

In areas with suspended or dropped ceilings and in areas with concealed spaces above the ceiling, piping shall be concealed above ceilings. Piping shall be inspected, tested and approved before being concealed. Risers and similar vertical runs of piping in finished areas shall be concealed.

3.4.4 Pendent Sprinklers

Page 7: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

21 13 13.00 10-7

Drop nipples to pendent sprinklers shall consist of minimum 1 inch pipe with a reducing coupling into which the sprinkler shall be threaded. Hangers shall be provided on arm-overs to drop nipples supplying pendent sprinklers when the arm-over exceeds 12 inches for steel pipe or 6 inches for copper tubing. Where sprinklers are installed below suspended or dropped ceilings, drop nipples shall be cut such that sprinkler ceiling plates or escutcheons are of a uniform depth throughout the finished space. The outlet of the reducing coupling shall not extend more than 1 inch below the underside of the ceiling. On pendent sprinklers installed below suspended or dropped ceilings, the distance from the sprinkler deflector to the underside of the ceiling shall not exceed 4 inches. Recessed pendent sprinklers shall be installed such that the distance from the sprinkler deflector to the underside of the ceiling shall not exceed the manufacturer's listed range and shall be of uniform depth throughout the finished area. Pendent sprinklers in suspended ceilings shall be a minimum of 6 inches from ceiling grid.

3.4.5 Upright Sprinklers

Riser nipples or "sprigs" to upright sprinklers shall contain no fittings between the branch line tee and the reducing coupling at the sprinkler. Riser nipples exceeding 30 inches in length shall be individually supported.

3.4.6 Pipe Joints

Pipe joints shall conform to NFPA 13, except as modified herein. Not more than four threads shall show after joint is made up. Welded joints will be permitted, only if welding operations are performed as required by NFPA 13 at the Contractor's fabrication shop, not at the project construction

site. Flanged joints shall be provided where indicated or required by NFPA 13. Grooved pipe and fittings shall be prepared in accordance with the manufacturer's latest published specification according to pipe material, wall thickness and size. Grooved couplings, fittings and grooving tools shall be products of the same manufacturer. For copper tubing, pipe and groove dimensions shall comply with the tolerances specified by the coupling manufacturer. The diameter of grooves made in the field shall be measured using a "go/no-go" gauge, vernier or dial caliper, narrow-land micrometer, or other method specifically approved by the coupling manufacturer for the intended application. Groove width and dimension of groove from end of pipe shall be measured and recorded for each change in grooving tool setup to verify compliance with coupling manufacturer's tolerances. Grooved joints shall not be used in concealed locations, such as behind solid walls or ceilings, unless an access panel is shown on the drawings for servicing or adjusting the joint.

3.4.7 Reducers

Reductions in pipe sizes shall be made with one-piece tapered reducing fittings. The use of grooved-end or rubber-gasketed reducing couplings will not be permitted. When standard fittings of the required size are not manufactured, single bushings of the face type will be permitted. Where used, face bushings shall be installed with the outer face flush with the face of the fitting opening being reduced. Bushings shall not be used in elbow fittings, in more than one outlet of a tee, in more than two outlets of a cross, or where the reduction in size is less than 1/2 inch.

3.4.8 Pipe Penetrations

Cutting structural members for passage of pipes or for pipe-hanger fastenings will not be permitted. Pipes that must penetrate concrete or masonry walls or concrete floors shall be core-drilled and provided with pipe sleeves. Each sleeve shall be Schedule 40 galvanized steel, ductile iron or cast iron pipe and shall extend through its respective wall or floor and be cut flush with each wall surface. Sleeves shall provide required clearance between the pipe and the sleeve per NFPA 13. The space between the sleeve and the pipe shall be firmly packed with mineral wool insulation. Where pipes penetrate fire walls, fire partitions, or floors, pipes shall be fire stopped. In penetrations that are not fire-rated or not a floor penetration, the space between the sleeve and the pipe shall be sealed at both ends with plastic waterproof cement that will dry to a firm but pliable mass or with a mechanically adjustable segmented elastomer seal.

3.4.9 Escutcheons

Page 8: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

21 13 13.00 10-8

Escutcheons shall be provided for pipe penetration of ceilings and walls. Escutcheons shall be securely fastened to the pipe at surfaces through which piping passes.

3.4.10 Inspector's Test Connection

Unless otherwise indicated, test connection shall consist of 1 inch pipe connected to the remote branch line; a test valve located no higher than 72 inches above finished grade; a smooth bore brass outlet equivalent to the smallest orifice sprinkler used in the system; and a painted metal identification sign affixed to the valve with the words "Inspector's Test." The discharge orifice shall be located outside the building wall directed so as not to cause damage to adjacent construction or landscaping during full flow discharge.

3.4.11 Drains

Main drain piping shall be provided to discharge at the location indicated. Auxiliary drains shall be provided as required by NFPA 13.

3.4.12 Installation of Fire Department Connection

Connection shall be mounted on the exterior wall 3 to 4 feet above finished grade per Eglin AFB requirements. The piping between the connection and the check valve shall be provided with an automatic drip in accordance with NFPA 13 and arranged to drain to the outside.

3.4.13 Identification Signs

Signs shall be affixed to each control valve, inspector test valve, main drain, auxiliary drain, test valve, and similar valves as appropriate or as required by NFPA 13. Hydraulic design data nameplates shall be permanently affixed to each sprinkler riser as specified in NFPA 13.

3.5 UNDERGROUND PIPING INSTALLATION

The fire protection water main shall be laid, and joints anchored, in accordance with NFPA 24. Minimum depth of cover shall be 3 feet. The supply line shall terminate inside the building with a flanged piece, the bottom of which shall be set not less than 6 inches above the finished floor. A blind flange shall be installed temporarily on top of the flanged piece to prevent the entrance of foreign matter into the supply line. A concrete thrust block shall be provided at the elbow where the pipe turns up toward the floor. In addition, joints shall be anchored in accordance with NFPA 24 using pipe clamps and steel rods from the elbow to the flange above the floor and from the elbow to a pipe clamp in the horizontal run of pipe. Buried steel components shall be provided with a corrosion protective coating in accordance with AWWA C203.

3.6 ELECTRICAL WORK

Except as modified herein, electric equipment and wiring shall be in accordance with Division 26 and 28.

3.7 PRELIMINARY TESTS

The system, including the underground water mains, and the aboveground piping and system components, shall be tested to assure that equipment and components function as intended. Submit proposed procedures for Preliminary Tests, no later than 14 days prior to the proposed start of the tests and proposed date and time to begin the preliminary tests. The underground and aboveground interior piping systems and attached appurtenances subjected to system working pressure shall be tested in accordance with NFPA 13 and NFPA 24. Upon completion of specified tests, submit 3 copies of the completed Preliminary Test Report, no later than 7 days after the completion of the Tests. The Report shall include both the Contractor's Material and Test Certificate for Underground Piping and the Contractor's Material and Test Certificate for Aboveground Piping. All items in the Preliminary Tests Report shall be signed by the Fire Protection Specialist.

3.8. Underground Piping

Page 9: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

21 13 13.00 10-9

3.8.1. Flushing

Underground piping shall be flushed in accordance with NFPA 24. This includes the requirement to flush the lead-in connection to the fire protection system at a flow rate not less that the calculated maximum water demand rate of the system.

3.8.1.2 Hydrostatic Testing

New underground piping shall be hydrostatically tested in accordance with NFPA 24. The allowable leakage shall be measured at the specified test pressure by pumping from a calibrated container. The amount of leakage at the joints shall not exceed 2 quarts per hour per 100 gaskets or joints, regardless of pipe diameter.

3.8.2 Aboveground Piping

3.8.2.1 Hydrostatic Testing

Aboveground piping shall be hydrostatically tested in accordance with NFPA 13 at not less than 200 psi or 50 psi in excess of maximum system operating pressure and shall maintain that pressure without loss for 2 hours. There shall be no drop in gauge pressure or visible leakage when the system is subjected to the hydrostatic test. The test pressure shall be read from a gauge located at the low elevation point of the system or portion being tested.

3.8.3 Testing of Alarm Devices

Each alarm switch shall be tested by flowing water through the inspector's test connection. Each water-operated alarm devices shall be tested to verify proper operation.

3.8.4 Main Drain Flow Test

Following flushing of the underground piping, a main drain test shall be made to verify the adequacy of the water supply. Static and residual pressures shall be recorded on the certificate specified in paragraph SUBMITTALS. In addition, a main drain test shall be conducted each time after a main control valve is shut and opened.

3.9 FINAL ACCEPTANCE TEST

Begin the Final Acceptance Test only when the Preliminary Test Report has been approved. Submit proposed procedures for Final Acceptance Test, no later than 14 days prior to the proposed start of the tests, and proposed date and time to begin the Test, submitted with the procedures. Notification shall be provided at least 14 days prior to the proposed start of the test. Notification shall include a copy of the Contractor's Material & Test Certificates. The Fire Protection Specialist shall conduct the Final Acceptance Test and shall provide a complete demonstration of the operation of the system. This shall include operation of control valves and flowing of inspector's test connections to verify operation of associated waterflow alarm switches. After operation of control valves has been completed, the main drain test shall be repeated to assure that control valves are in the open position. Submit as-built shop drawings, at least 14 days after completion of the Final Tests, updated to reflect as-built conditions after all related work is completed. Drawings shall be on reproducible full-size mylar film. In addition, the representative shall have available copies of as-built drawings and certificates of tests previously conducted. The installation shall not be considered accepted until identified discrepancies have been corrected and test documentation is properly completed and received. Submit 3 copies of the completed Final Acceptance Test Report no later than 7 days after the completion of the Final Acceptance Tests. All items in the Final Acceptance Report shall be signed by the Fire Protection Specialist.as specified.

3.10 ONSITE TRAINING

The Fire Protection Specialist shall conduct a training course for operating and maintenance personnel as designated by the Contracting Officer. Submit proposed schedule, at least 14 days prior to the start of related training. Training shall be provided for a period of 4 hours of normal working time and shall start after the system is functionally complete and after the Final Acceptance Test. Submit 6 Operating and Maintenance Manuals listing

Page 10: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

21 13 13.00 10-10

step-by-step procedures required for system startup, operation, shutdown, and routine maintenance, at least 14 days prior to field training. The manuals shall include the manufacturer's name, model number, parts list, list of parts and tools that should be kept in stock by the owner for routine maintenance including the name of a local supplier, simplified wiring and controls diagrams, troubleshooting guide, and recommended service organization (including address and telephone number) for each item of equipment. The Onsite Training shall cover all of the items contained in the approved manuals.

END OF SECTION

Page 11: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 1

SECTION 21 13 39: LOW-LEVEL HIGH EXPANSION FOAM FIRE EXTINGUISHING SYSTEMS FOR AIRCRAFT HANGARS

PART 1 GENERAL

1.01 SECTION INCLUDES A. High expansion foam System.

B. System design, installation, and certification.

1.02 REFERENCES A. ASTM A53/A53M – Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded

and Seamless

B. ASTM D709 – Laminated Thermosetting Materials

C. FM APP GUIDE – (updated on-line) Approval Guide http://www.approvalguide.com/

D. NFPA 11 - Standard for Low-, Medium- and High- Expansion Foam

E NFPA 13 - Standard for the Installation of Sprinkler Systems

F. NFPA 15 - Standard for Water Spray Fixed Systems for Fire Protection

G. NFPA 16 - Standard for Installation of Foam-Water Sprinkler and Foam-Water Spray Systems

H. NFPA 24 - Standard for the Installation of Private Fire Service Mains and Their Appurtenances

I. NFPA 70 - National Electrical Code

J. NFPA 72 - National Fire Alarm and Signaling Code

K. NFPA 409 - Standard on Aircraft Hangars

L. NFPA 704 - Standard System for the Identification of the Hazards of Materials for Emergency Response

M. SSPC Paint 25 - Zinc Oxide, Alkyd, Linseed Oil Primer for Use Over Hand Cleaned Steel, Type I and Type II

N SSPC SP 11 - Power Tool Cleaning to Bare Metal

O. UFC 3-520-01 - (2015) Interior Electrical Systems

P. UFC 3-600-01 - (Change 4, 8 August 2016) Fire Protection Engineering for Facilities

Q. UFC 4-211-01 - (29 Feb 2016; Pre-Decisional: Not for Public Release) Aircraft Maintenance Hangars

R. CID A-A-2962 - Enamel, Alkyd, Gloss, Low VOC Content

S. CID A-A-58092 -Tape, Antiseize, Polytetrafluoroethylene

1.03 SYSTEM DESCRIPTION A. Design Requirements: Design and provide a new automatic low-level high expansion foam (Hi-Ex) fire

suppression system including electronic detection, control, and release systems. The low-level fire suppression system must provide uniform distribution of aerated high expansion solution to provide complete coverage throughout the areas indicated. The electronic detection, control, and release system must include wiring, raceways and other accessories and miscellaneous items required for a complete operating system even though each item is not specifically mentioned or described. The design, equipment, materials, installation, and workmanship must be in strict accordance with the required and advisory provisions of NFPA 11, NFPA 13, NFPA 15, NFPA 16, NFPA 24, NFPA 70, NFPA 72, NFPA 409, UFC 3-600-01, UFC 4-211-01 and criteria changes (Appendix B) except as modified herein. Each

Page 12: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 2

system must include all materials, accessories and equipment necessary to provide each system complete and ready for use. Design and install each system to give full consideration to blind spaces, piping, electrical equipment, ductwork, and all other construction and equipment to provide complete coverage in accordance with the drawings to be submitted for approval. Devices and equipment for fire protection service must be of a make and type listed by the Underwriter's Laboratories Inc. in the UL Fire Protection Equipment Directory, approved by the Factory Mutual System in FM APP GUIDE, or other Nationally Reorganized Testing Laboratory listing unless otherwise specified. In the publications referred to herein, the advisory provisions must be considered to be mandatory, as though the word "must" had been substituted for "should" wherever it appears; reference to the "authority having jurisdiction" must be interpreted to mean Air Force Civil Engineer Center Operations Directorate (AFCEC/CO). Begin work at the point indicated.

B. System Operation: Flow of water must be controlled by flow control valves. Foam proportioning equipment must activate automatically upon tripping of the flow control valve for the corresponding foam system. The flow control valve must be tripped by independent detection systems. No valve will be operated by the building fire evacuation alarm system. Use of motor-operated valves is prohibited. Once activated, the system must remain activated until reset manually, however, foam flow may be interrupted/stopped momentarily by depressing and holding the "foam stop" button strategically placed on the hangar bay walls. 1. Overhead System: Overhead wet pipe sprinkler systems are specified under Section 21 13 00 WET

AND DRY PIPE SPRINKLER SYSTEMS.2. Hose System: Hose systems including hose reels must not be provided.

1.04 SUBMITTALS A. Submittals shall be made under provisions of Section 01 33 00.

B. The AFCEC/CO fire protection engineer will review and approve all submittals in this section requiring Government approval.

C. Preconstruction Submittals 1. Environmental protection: Submit high expansion foam solution containment and disposal plan as

required under paragraph entitled "Environmental Protection."

D. Shop Drawings 1. Sprinkler System Shop Drawings

E. Product Data: Submit data on proposed equipment, including, but not limited to the items listed below. Include UL or FM listing cards for equipment provided. Data which describe more than one type of item must be clearly marked to indicate which type the Contractor intends to provide. Submit only originals. Photocopies will not be accepted. Partial submittals will not be accepted. 1. Pipe, fittings, and mechanical couplings2. Flow control valves3. Valves, including gate, check, and globe4. Low-level high expansion foam generators5. Pipe hangers and supports6. Pressure switch7. Surge Arrester8. Foam System Control Panel (FSCP)9. Optical flame detectors10. Terminal cabinets/assemblies11. Storage batteries12. Annunciator panel13. High expansion foam visual notification devices14. Visual alarms15. Foam concentrate storage tanks16. Proportioning inductor equipment17. High expansion foam concentrate18. Strainers19. Manual foam release stations20. Stop station21. Battery charger

Page 13: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 3

F. Design Data 1. Hydraulic calculations2. Foam delivery calculations: Submit foam delivery calculations demonstrating foam solution is

delivered to the most remote High Expansion Foam generator within 30 seconds of system activation.3. Pressure discharge graphs or tables: Submit pressure discharge graphs or tables showing pressure

discharge relationship for discharge nozzles.4. Battery standby power requirements calculations:

a. Substantiate battery standby power requirements with calculations showing battery capacity,supervisory and alarm power requirements.

b. Provide complete battery calculations for both the alarm and supervisory power requirements.Ampere hour requirements for each system component must be submitted with the calculations.

5. System hydraulic surge analysis: System hydraulic transit (surge) analysis showing hydraulic transitpressure occurring throughout the system at both design flow and non-flow conditions.

G. Test Reports 1. Preliminary Test Report: Four copies of the completed Preliminary Test Report, no later than 7 days

after the completion of the Preliminary Tests. The Preliminary Tests Report must include both theContractor's Material and Test Certificate for Underground Piping and the Contractor's Material andTest Certificate for Aboveground Piping. All items in the Preliminary Tests Report must be signed bythe Fire Protection Engineer specified in this Section.

2. Final Acceptance Test Reporta. Submit for all inspections and tests specified under paragraph entitled "Field Quality Control."b. Concurrent with the Final Acceptance Test Report, certification by the Fire Protection Engineer

specified in this Section that the low-level high expansion foam fire extinguishing system isinstalled in accordance with the contract requirements, including signed approval of thePreliminary and Final Acceptance Test Reports.

H. Certificates 1. Qualifications of installer2. Qualifications of System Technician3. Submit installer and systems technician qualifications as required under paragraphs entitled

"Qualifications of Installer" and "Qualifications of System Technician."4. Fire Protection Engineer: The name and documentation of certification of the proposed Fire

Protection Engineer, no later than 14 days after the Notice to Proceed and prior to the submittal of thesprinkler system drawings and hydraulic calculations.

5. Inspection by Fire Protection Engineer: Concurrent with the Final Acceptance Test Report,certification by the Fire Protection Engineer specified in this Section that the sprinkler system isinstalled in accordance with the contract requirements, including signed approval of the Preliminaryand Final Acceptance Test Reports.

I. Operation and Maintenance Data: Furnish one complete set of data prior to the time that final acceptance tests are performed, and furnish the remaining sets before the contract is completed. 1. Flow control valves, Data Package 32. Proportioning equipment, Data Package 33. Foam System Control panel, Data Package 34. High expansion concentrate storage tanks, Data Package 35. Low-level high expansion foam generators, Data Package 36. Surge Arrester, Data Package 37. Instructions for operating the fire extinguishing system, Data Package 4

J. Closeout Submittals 1. As-built Drawings for the fire extinguishing system: Upon completion, and before final acceptance of

the work, submit a complete set of as-built drawings for the fire extinguishing system, includingcomplete as-built circuit diagrams. Provide electronic drawings in dwg and pdf format. Submit as-builtdrawings in addition to the record drawings required by Division 1.

1.05 QUALIFICATIONS A. Fire Protection Engineer: A Fire Protection Engineer is a registered professional engineer (P.E.) who has

passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveys (NCEES). The engineer hired by the sprinkler contractor shall be the designer of record for the submittal drawings.

Page 14: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 4

B. Qualifications of Installer: Prior to commencing work, submit data showing that the Contractor has successfully installed automatic high expansion foam fire extinguishing systems of the same type and design as specified herein, or that he has a firm contractual agreement with a subcontractor having the required experience. Include the names and locations of at least two installations where the Contractor, or the subcontractor referred to above, has installed such systems. Indicate the type and design of each system, and certify that the system has performed satisfactorily for a period of at least 18 months.

C. Qualifications of System Technician: Installation drawings, shop drawing and as-built drawings must be

prepared, by or under the supervision of, an individual who is experienced with the types of works specified herein, and is currently certified by the National Institute for Certification in Engineering Technologies (NICET) as an engineering technician with minimum Level-IV certification in Special Hazard System program. Contractor must submit data for approval showing the name and certification of all involved individuals with such qualifications at or prior to submittal of drawings.

1.06 QUALITY ASSURANCE A. Sprinkler System Shop Drawings: Prepare shop drawings in accordance with the requirements for "Plans"

as specified in NFPA 11, "Working Plans" as specified in NFPA 13, and "Shop Drawings" as specified in NFPA 72. Each drawing must be 24 by 36 inches. Unless otherwise noted, floor plans must be drawn to a scale not less than 1/8" = 1'-0". Show data essential for proper installation of each system. Show details, plan view, elevations and sections of the systems supply and piping. Show piping schematic of systems supply, devices, valves, pipe and fittings. Show point to point electrical wiring diagrams. Submit drawings signed by a registered fire protection engineer.

B. Provide four copies of the Sprinkler System Shop Drawings, no later than 21 days prior to the start of

sprinkler system installation. C. Do not commence work until the design of each system and the various components have been

approved. Show: 1. A descriptive index with drawings listed in sequence by number. A legend sheet identifying device

symbols, nomenclature, and conventions used in the package. 2. Room, space or area layout and include data essential to the proper installation of each system.

Floor plans must be drawn to a scale not less than 1/8 inch equals 1 foot clearly showing locations of devices, equipment, risers, electrical power connections, areas covered by each generator, and other details required to clearly describe the proposed arrangement.

3. Piping plan for foam generator system. Generators and associated piping must be shown. Abbreviated presentation forms will not be accepted. Each type of fitting used and the locations of bushings, reducing fitting, and welded joints must be identified. A separate plan must be provided for the foam generator system.

4. Piping plan and isometric drawing of the high expansion concentrate system and details of all associated valves, fittings, and other components. Shop drawings must indicate the K-factor of each inductor. Drawing must indicate all operational features.

5. Equipment room layout drawings drawn to a scale of not less than 1/2 inch equals 1 foot to show details of each system component, clearances between each other and from other equipment and construction in the rooms.

6. Details of each inductor, generator and mounting details, high expansion foam system control valve header and related components.

7. Details of all components required for support of the sprinkler piping from the building structural system, including hangers and bracing, and details of all connections to the components of the metal building system. Provide plans, elevation drawings, and details as required to fully convey the clearances required for the floor and wall penetrations.

8. Connection drawings and control diagrams indicating overall mechanical operation of the high expansion system. This must include identification and operation of each major component of the system. Diagrams must be supplemented with a narrative description of the system. Indicate foam system control panel, make and model of devices and equipment to which the system is connected.

9. Point-to-point wiring diagrams showing the points of connection and terminals used for electrical field connections in the system, including interconnections between the equipment or systems which are supervised or controlled by the system. Diagrams must show connections from field devices to the Foam System Control Panel (FSCP) and remote foam system control units, initiating circuits, switches, relays and terminals.

10. Field wiring diagrams showing locations of devices and points of connection and terminals used for all electrical field connections in the system, with wiring color code scheme.

Page 15: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 5

11. Interfacing with fire suppression control components must be clearly indicated on drawings. Solenoids must be FM approved for release by the releasing panel.

12. Optical flame detector manufacturer's recommended detector layout (plan view) including horizontal and vertical angles for correct aiming.

D. Fire Protection Engineer: The Fire Protection Engineer specified in this Section, must perform the

inspection services specified in Part 3 of this section. E. Material and Equipment Qualifications: Provide materials and equipment that are standard products of

manufacturers regularly engaged in the manufacture of such products, which are of a similar material, design and workmanship. Standard products must have been in satisfactory commercial or industrial use for 2 years prior to bid opening. The 2-year use must include applications of equipment and materials under similar circumstances and of similar size. The product must have been for sale on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2 year period.

F. Alternative Qualifications: Products having less than a two-year field service record will be acceptable if a

certified record of satisfactory field operation for not less than 6000 hours, exclusive of the manufacturer's factory or laboratory tests, can be shown.

G. Manufacturer's Nameplate: Each item of equipment must have a nameplate bearing the manufacturer's

name, address, model number, and serial number securely affixed in a conspicuous place; the nameplate of the distributing agent will not be acceptable.

H. Field Fabricated Nameplates: ASTM D709. Provide laminated plastic nameplates for each equipment

enclosure, relay, switch, and device; as specified in the technical sections or as indicated on the drawings. Each nameplate inscription must identify the function and, when applicable, the position. Nameplates must be melamine plastic, 0.125 inch thick, white with black center core. Surface must be matte finish. Corners must be square. Accurately align lettering and engrave into the core. Minimum size of nameplates must be one by 2.5 inches. Lettering must be a minimum of 0.25 inch high normal block style.

1.07 SPARE PARTS A. Furnish the following spare parts:

1. 2 of each type of detector installed. 2. 1 of each type notification appliance installed. 3. 4 of each type of fuse required by the system. 4. 1 each foam system manual release station and stop station 5. 6 complete sets of system keys.

1.08 DESIGN OF LOW-LEVEL HIGH EXPANSION FOAM SYSTEM A. Design and provide a new automatic low-level high expansion fire extinguishing system as indicated on

drawings. Systems must provide uniform distribution of high expansion foam solution to provide complete coverage over the protected area as indicated on drawings. System must be balanced to operate both independently and with simultaneous operation of the overhead wet-pipe sprinkler system specified in Section 21 13 00 WET AND DRY PIPE SPRINKLER SYSTEMS.

B. System Activation: System activation must be controlled by an addressable foam system control panel

(FSCP) listed for releasing service. High expansion foam discharge must occur upon activation of either of the following:

1. Any single manual foam release station. 2. The activation of an alarm condition in any two or more optical flame detectors. C. Flow Control Valves: Water flow thru the foam concentrate proportioning system and to the foam

generator system must be controlled by flow control valves. Flow control valves must be listed and include control of the opening and closing speed of the valve, provide pressure regulation to the discharge devices, and provide for remote resetting of the valve.

D. Foam Solution Distribution: Foam application must be from foam generators providing not less than a

700:1 expansion ratio by aeration specified herein and as indicated on the drawings. Design must be such that foam solution must begin discharging at the most remote foam nozzle within 30 seconds from system activation. Submit foam delivery calculations demonstrating compliance.

Page 16: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 6

1. Low-level high-expansion foam systems shall cover 90 percent of the aircraft silhouette areaprojected on the floor in one minute or less.

2. Within 240 seconds from activation not less than 3.28 feet of aerated foam solution throughout thehangar servicing area.

E. Foam Concentrate Proportioning System: Foam proportioning must be by a foam inductor taking suction from an atmospheric high expansion foam concentrate storage tank located directly beneath/adjacent the inductor.

F. Hydraulic Design: Design of low-level high expansion foam systems must be by hydraulic calculations for uniform distribution of HIGH EXPANSION FOAM solution over the protected area as defined on the drawings and must conform to the NFPA standards listed above and to the requirements specified herein. Calculations must include pressure discharge graphs or tables showing pressure discharge relationship for discharge nozzles. Hydraulic calculations must assume a minimum 20 psi pressure loss for the flow control valve or the minimum pressure loss necessary for flow/pressure regulation as published by the manufacturer's literature, whichever is greater. Include "Demand Calculations" and "Supply Calculations". 1. Overhead Systems: Hydraulic design must consider simultaneous operation of the overhead sprinkler

systems specified under Section 21 13 00 WET AND DRY PIPE SPRINKLER SYSTEMS.2. Water Supply: Base hydraulic calculations on the flow to supply the high-expansion generators and

the sprinkler design area.a. Base hydraulic calculations on the operation of the minimum number of pumps running necessary!

to supply the high-expansion generators and the sprinkler design area. Pumps are existing to remain.

G. Duration of Discharge: System must apply foam solution over the protected area for a minimum of 15 minutes while simultaneously discharging water through the overhead wet pipe sprinkler system specified in Section 21 13 00 WET AND DRY PIPE SPRINKLER SYSTEMS.. Reduction of the discharge duration based on a discharge rate higher than the specified minimum is not permitted.

PART 2 PRODUCTS

2.01 FOAM GENERATION PRODUCTS AND EQUIPMENT A. Low-Level High Expansion Foam Generators

1. Generator must be capable of producing not less than the scheduled cubic feet of expanded foam-water solution per minute.

2. Generator discharge characteristics must not result in any foam solution being discharged on aircraftfuselage and wing components from direct impingement. Generator operating pressure must be suchthat high pressure fittings and system components are not required. Generator nozzle hydraulicsmust be compatible with simple inductor proportioning. Total nozzle obstruction must not negativelyimpact the distribution system hydraulics or foam induction capabilities.

B. Proportioning Equipment: Foam proportioning must be by a single foam inductor for each foam-water riser. Inductor must, through a venturi, take concentrate and proportion such concentrate into the flow steam reliably at the designed system flow rate. Inductor must be specifically tuned for the system required flow rate, inlet pressure, back pressure, concentrate type, proportioning ratio, and lift height (at the near empty tank level). The inductor must be equipped with the exact orifice at the entry of the foam pipe. Off the shelf pre-tuned generic model inductors are not permitted. Shop drawings must be accompanied with an inductor datasheet fully annotated with the flow rate, inlet pressure, back pressure, and concentrate lift height (at the near empty tank level). Inductor will be fitted with a low loss bronze or brass check valve assembly by the manufacturer that is included in the device's hydraulic design. Known manufacturers of such products include Fomtec (distributed by Viking in US), Matre Maskin, Wilson Foam, and Delta Fire. The inductor must be elevated above the maximum fill level of the concentrate tank and have no automatic control valves in the concentrate line. Inductors must be installed with not less than 48 inches (1200mm) straight pipe up and down stream of the inductor Provide gauge cocks with oil-filled gauges (0-200 psi, 2.5 percent accuracy) 3 feet before and after the inductor. Provide permanent engraved rigid plastic or corrosion-resistant metal constructed label for each control device. 1. Foam Concentrate Piping and Fittings: Foam concentrate piping and fittings stainless steel. Each

inductor must be provided with a separate individual pipe from the tank to the inductor. Fittings mustbe of the same material as the pipe. Acceptable pipe joining methods are TIG welded, or gasketedwelded flanges. Provide quarter turn ball valves at each inductor on the concentrate line to permit

Page 17: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 7

low-level nozzle system flushing without proportioning foam. Valve must be lockable in the open position or equipped with an integral tamper switch for electric supervision. Valve must be brass, bronze or stainless steel. Foam concentrate pipe must also be fitted with capped tee-fitting as surrogate foam concentrate test connection. Refer to the drawings for details. Pre-priming of any foam solution piping is NOT acceptable. All solution piping must be slopped to be self-draining back to the riser. During commissioning, the responsible FPE must seal or otherwise install tamper proof guards on the pressure regulator adjusting stem and the two small globe valves on the speed control assembly. It is crucial these settings not be changed after commission; least the system may be impaired. Safety-wire these devices in those positions and label them "DO NOT ADJUST". Any other trim valves which must be open or closed for the FCV to function also must be safety wired in position.

C. Flow Control Valves: Provide flow control valve as shown on the drawings with trim package for electric releasing, remote re-setting, and opening/closing speed control. Use of any other flow control valve requires approval from the service criteria office. If flow control valve of a size greater than or less than the risers, provide smoothly tapered inlet and outlet connections. In addition to automatic operation, arrange each valve for manual release at the valve. Provide pressure gages and other appurtenances at the flow control valves as required by NFPA 13. All trim piping must be brass with compatible fittings. Trim piping must be factory configured and installed. The manual release for the flow control valve will be installed no higher than 5 feet above finished floor. Hydraulic calculations must include a minimum pressure drop across flow control valves of 20 psi, or the listed pressure drop, whichever is greater. Valves must be operated by a control system listed for releasing service and independent of the building fire alarm system. . Valves located in electrical classified locations must be listed for the classification of the area where located. 1. Pressure Regulation: Pressure regulation maintaining a constant pressure at the inductor and the

discharge device (foam generator). Pressure deviation must not exceed ± 10 psig.2. Electrical Actuation and Remote Resetting: Electrical solenoid valve used to actuate the water control

valve must be an integral component of the valve releasing control panel manufacturer. Solenoidvalve must be of the normally closed, de-energized type, which opens when energized upon receiptof an electrical signal from the foam system control panel to which it is connected. Solenoid valvesused with diaphragm-type valves must be rated for a maximum pressure differential of 175 psi.Electronic solenoids used for high expansion foam release must be listed for fire service applicationsand approved by the flow control valve manufacturer for use with the specific valve. Water controlvalve must be capable of recycling to the closed position at an adjustable speed. Assembly must becomplete with the gauges and other appurtances at the flow control valve as required by the NFPA.

3. Opening/Closing Speed Control: Provide manufacturer's optional valve opening/closing speedcontrol. Flow control valves must open within 5 seconds. Speed control setting must be adjustedsuch that valve will not exceed 15 seconds.a. Primary water control valve OS&Y or butterfly must be electrically supervised.b. All trim valves and drain valves must be locked/sealed in the normal operating position.c. All valves must have an attached metal tag or engraved plastic tag identifying purpose and

normal operating position.

D. Foam Concentrate Storage Tanks: Foam Concentrate Storage Tank must be a vertical, double-walled, high density cross-linked polyethylene storage tank compatible with the required concentrate. Tank capacity must be the volume required to fully submerge the inductor dip tube plus the design volume to operate the foam generators for not less than 15 minutes plus 60 gallons. The inductor dip tube must enter through the top of the tank, and no taps are permitted in the bottom or sides of the tank. Provide a closeable fill opening and vent assembly. Provide either a translucent shell or clear vertical window to indicate fill level with permanent capacity markings at least every 50 gallons. The capacity markings will not include the unsuckable amount of concentration at the bottom of the tank. Mount concentrate tank on a 2 inch concrete housekeeping pad. The double wall tank does not require spill or secondary containment. For testing purposes, equip the concentrate supply system with fittings to accommodate an auxiliary tank of alternate test liquid is to be used during testing. A second foam concentrate tank or reserve concentrate supply is not required. 1. Concentrate Storage Tank Level Sensor: Provide an ultrasonic level sensor in concentrate tank with

low level alarm. Level monitoring system must have SPDT contacts for connection with the buildingfire alarm system specified in Section 28 31 00 FIRE DETECTION AND ALARM SYSTEMS.

2. Tank Markinga. Permanently label each tank with its capacity, concentrate manufacturer, and concentrate type

and percentage of concentrate induction. The label must specifically identify the requiredconcentrate manufacturer's name, concentrate name, concentrate identifying product

Page 18: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 8

numbers/codes, concentrate manufacturer's contact information including process to obtain 24-hour concentrate re-supply. The label must include a warning statement indicating only this specific concentrate is permitted to be used in this system.

b. Tank must have an English compliant "WARNING" sign indicating PPE protection is required for dermal, respiratory, and eye protection when handling foam concentrate.

c. Tank must have an English compliant "WARNING" sign indicating spilled concentrate is an extreme slipping hazard.

d. Tank must have a NFPA 704 diamond sign indicating Health = 1; flammability = 2; and instability = 0.

2.02 ELECTRONIC CONTROL AND DETECTION COMPONENTS A. Provide a foam system alarm and control consisting of an addressable foam system control panel

(FSCP), multi-spectrum infrared (IR) flame detectors, manual releasing stations, manual stop stations, signage panels, visual notification appliances, and miscellaneous appurtenances and circuit wiring in conduit, as required for a complete, operational, and fully functioning system. All components comprising the foam system alarm and control must be sourced through Det-Tronics, the manufacturer of the required FSCP and optical flame detectors, to ensure compatibility. For the purposes of this Contract, all Det-Tronics installation recommendations must be considered as mandatory requirements. All devices must be grounded in strict accordance with the Det-Tronics installation instructions. All circuit wiring must be installed as part of shielded cable assemblies, in rigid galvanized steel conduit, and grounded in strict conformance with the Det-Tronics installation instructions.

B. Foam System Control Panel (FSCP): FSCP must be Det-Tronics Eagle Quantum Premier Fire Detection/

Releasing System, must be furnished complete with minimum 60-node Safety Systems Software (S3) configuration/logic programming/diagnostic tools software package including USB dongle key and RS232 cable. FSCP alarm, supervisory, and trouble signal reporting to the Fire Alarm Control Panel must be via discrete dry contact output points. Modular type panel installed in a surface mounted NEMA Type 4 painted steel cabinet with hinged door and cylinder lock. All detectors must be listed for use with that panel. IR detectors must be networked with the panel so that during commission IR detectors can be calibrated from the releasing panel. The FSCP must provide a real time display of current IR levels at any detector, have the ability to set the detector sensitivity for each detector from the panel, be able to download detector level log history, have remote test and diagnostics capability (manual self-test, lens dirty, sensor failure, power out of tolerance, device non-responsive), and remote setup and programming of detector options (lens heater power level, detector alarm LED function, alarm latching or non-latching, device address, sensitivity level, timing and gate count for alarm). FSCP must be electro-magnetic interference/radio frequency interference (EMI)/(RFI) tolerant and rated to SIL level 2 capability (IEC 61508), a safety assessment evaluation which evaluates critical fault paths, redundancies, and statistical measurement/prediction to ensure a specific level of long term reliable performance and stability to co-exist with aircraft radar systems. In certain situations a redundant foam suppression control panel may be need, verify redundancy requirements with agency and mission. FSCP shall be furnished with an external in-line surge protection device for the input voltage (120 VAC). The surge protector shall be equal to EDCO# HSP-121A.

C. Auxiliary Power Supply

1. Storage Batteries: Provide sealed lead acid, or gel cell batteries and charger. Drycell batteries are not acceptable. House batteries in a well-constructed vented steel rack-style cabinet with cylinder lock, non-corrosive base, and louvered vents. Floor mounted racks are permitted provided all battery components and conductors are no less than 12 inches above finished floor. Rack must be secured to the wall or floor slab. Locate wall-mounted cabinet such that the top of the cabinet not more than 4 feet above floor level. Provide batteries of adequate ampere-hour rating to operate the system under supervisory conditions for 90 hours, at the end of which time batteries must be capable of operating the entire system in a full alarm condition for not less than 30 minutes. Provide battery standby power requirements calculations substantiating the battery capacity. Provide reliable separation between cells to prevent contact between terminals of adjacent cells and between battery terminals and other metal parts.

2. Provide batteries with post-and-nut, "L"-blade, or similar terminals. Slip-on tab type terminals are not acceptable. When a separate battery cabinet is used, provide a fuse block for battery leads within the cabinets. Finish the cabinet on the inside and outside with enamel paint.

3. Battery Charger: Provide completely automatic high/low charging rate type charger capable of recovery of the batteries from full discharge to full charge in 24 hours or less. Provide an ammeter for recording rate of charge and a voltmeter to indicate the state of battery charge under load. Meters must be factory installed, or factory-supplied plug-in modules. Field installation of meters other than

Page 19: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 9

the panel manufacturer's plug-in modules is prohibited. Provide a trouble light to indicate when batteries are manually placed on a high rate of charge as part of the unit assembly if a high-rate switch is provided. House charger in the control panel or battery cabinet.

D. Foam System Release Circuit Devices

1. Optical Flame Detectors: Optical flame detection will be the X3301 Multispectrum IR Flame Detector manufactured by Det-Tronics. Optical flame detection system will use triple infrared (IR) flame detectors listed/approved for the expected fuel hazards in the hangar bay. The triple IR flame detectors must be in hangar mode. The detectors will be immune to radar and radio frequency emissions. Provide shielding for the detectors and their circuits from radio frequency interference. All circuiting from the FACP or FSCP to the detectors will be shielded, and shielding will be grounded at one end. Optical flame detector alarm signals to the FACP or FSCP will be latching. Detectors must be mounted in accordance with their listing at approximately 8 feet (2.4 m) above the finished floor of the hangar. The specifics for each design must take into account facility construction, type of aircraft, aircraft configuration and positioning, fixed and mobile equipment within the aircraft servicing area, and all other relevant factors. Do not mount optical detectors in inaccessible locations. The detectors will be angled and blinds will be provided such that the cone-of-vision does not extend more than 5 feet (1.5 m) outside the hangar bay. The horizontal and vertical axis of the detector determined during commissioning will be permanently marked on each detector. The optical flame detectors will be installed with 5 feet (1.5 m) of flexible conduit to allow for any minor adjustments during testing or changes in mission of the hangar. Provide a sufficient number of optical flame detectors such that a fire at any position within the hangar bay will be within the range and cone-of vision of at least two detectors. With the exception of a manual foam release station, the cross-zoning of two optical flame detectors in the hangar bay is required to release the foam suppression system.

2. Manual Foam Release Stations: Provide low-level high expansion manual foam release stations where shown. Stations must be of a type not subject to operation by jarring or vibration. Stations must be of all metal construction and have a dual action release configuration to prevent accidental system discharge. Break-glass-front stations are not permitted. Station must provide positive visible indication of operation. Restoration must require use of a key. Place warning signs at each station indicating that operation of the station will cause immediate high expansion foam discharge. Where a building fire alarm manual pull station is also mounted in the vicinity of a manual foam release station, separate the stations by at least 5 feet horizontally. Place fire alarm manual pull stations and manual release stations on opposite sides of exit doors. Mount station on signage panel as specified herein and detailed on drawings. Manual foam releasing stations must be locking type that, when activated, require a key to be reset. Manual releasing stations must be surface mount. Manual foam releasing stations must be yellow in color, distinctly different from manual fire alarm stations, and must be mounted on a signage panel. Manual foam releasing stations must have the word "FOAM" on the front exterior of the enclosure. Manual foam releasing stations must be equipped with clear plastic tamper covers. The tamper covers must have the word "FOAM" on the front. No other words must appear anywhere on the exterior of tamper covers. Stations including associated surface mount back boxes must be weatherproof type (NEMA 4 or 6 as indicated on the drawings) with bottom conduit entry only. Stations with top conduit entry hubs are not acceptable.

3. Stop Station: Provide foam stop stations of the "dead-man" type. The stop stations must be used in conjunction with valves and equipment that will prohibit or stop the discharge of foam/water from the foam suppression system. The stations must have distinctive signage at each device. Provide a red mushroom type push button and include the word "PUSH". Colored portions of tamper cover must be blue and lettering on the cover must be "STOP"; the words "FIRE", "ALARM", or "AGENT" must not appear on the cover. A manual foam stop station will be provided at each manual foam releasing station. Once depressed, and so long as the button is held down, the stop station will prevent/stop discharge from the foam system regardless of whether or not the foam system was activated automatically or manually and whether or not the activation occurs prior to or after the stop station is pressed and held. Unless the FSCP has been reset and all activation alarms (manual and automatic) have been cleared; when the foam stop station button is released, the FSCP will instantaneously restore system operation and foam discharge. When the foam stop station button is depressed under full flow, the time to fully close the flow control valve will not exceed 15 seconds. The time for the flow control valve to fully open upon release of the foam stop station button will not exceed 5 seconds. Manual foam stop stations will be protected from mechanical damage and water infiltration (minimum NEMA 4). Manual foam stop stations will be provided with a clear plastic tamper cover that must be lifted prior to actuating the station. Conduits will enter the station back box from the bottom. Back box and conduits will not be placed in front of signage, and a breather and drain (at the low point in the conduit) will be provided. Where manual stop stations and foam releasing stations are provided at an exit door, they will be located on opposite sides of doorway from fire alarm manual pull station.

Page 20: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 10

Where not located at an exit door opening, the manual stop stations and foam releasing stations will be located at least 5 feet apart. a. Provide two separate but adjacent 24 inch (610 mm) high by 18 inch (457 mm) wide metal signs.

There will be no more than 12 inches of separation between the two signs. The words "FIRE", "ALARM", or "AGENT" will not appear on these signs. The sign for the manual releasing station will have a yellow or lime-yellow background with "START FOAM SYSTEM" in red lettering not less than 3 inches (76 mm) high. The manual release station with tamper cover will be located on the lower center portion of the sign. The word "START" will be written in minimum 1 inch (25.4 mm) high green lettering placed directly above the activation station. The sign for the manual stop station will have a white background with a minimum 1/2 inch wide blue boarder with "STOP FOAM SYSTEM" in blue lettering not less than 3 inches (76 mm) high. The manual stop station with tamper cover will be located on the lower center portion of the sign. The word "STOP" will be written in minimum 1 inch (25.4 mm) high red lettering placed directly above the manual stop station.

2.03 FOAM CONCENTRATE A. Foam concentrate will be a synthetic based foaming agent designed for use with high expansion foam

generating equipment provided. The expansion ratio basis of design is 884 to 3. The Contractor's final shop drawings and calculations shall not exceed 1,000 to 1. The shelf life shall be a minimum of 20 years.

2.04 ELECTRICAL WORK A. Electrical work is specified in Division 26 except for control and fire alarm wiring. Fire alarm system is

specified in Section 28 31 00 FIRE DETECTION AND ALARM SYSTEMS. B. System Field Wiring: Provide control wiring and connections to fire alarm systems, under this section and

conforming to NFPA 70 and NFPA 72. All wiring must be color coded. Wiring, conduit and devices exposed to water or foam discharge must be NEMA 4X (IP65). Wiring, conduit and devices located in hazardous atmospheres, as defined by NFPA 70 and as shown, must be NEMA 7 (explosion proof). Conduits shall enter all boxes and devices in the hangar from the bottom. All conduit must be minimum 3/4 inch size. 1. Wiring Within Cabinets, Enclosures, Boxes, Junction Boxes, and Fittings: Provide wiring installed in a

neat and workmanlike manner and installed parallel with or at right angles to the sides and back of any box, enclosure, or cabinet. Conductors which are terminated, spliced, or otherwise interrupted in any enclosure, cabinet, mounting, or junction box must be connected to terminal blocks. Mark each terminal in accordance with the wiring diagrams of the system. Make connections with approved pressure type terminal blocks, which are securely mounted. The use of wire nuts or similar devices must be prohibited.

2.05 ALARMS A. Fire Alarm: Provide equipment and interconnections for the automatic transmittal of an alarm over the

building fire alarm system as specified in Section 28 31 00 FIRE DETECTION AND ALARM SYSTEMS. Arrange so that actuation of any alarm initiating device (OFD or manual release station), trouble and supervisory conditions must cause activation of the fire alarm and reporting systems. 1. Pressure Switch: Provide switch with SPDT contacts to automatically transmit alarm condition to the

building fire alarm system upon flow of water or high expansion foam. Alarm actuating device must instantly recycle.

2.06 ALARM SIGNALING DEVICES A. Provide the aircraft hangar area with visual alarms located where shown. All alarm circuits must be

electrically supervised. Each signal device must be provided with a rigid plastic or metal identification sign with lettering a minimum of 1.5 inches high. The signaling devices must be labeled "FOAM SYSTEM FLAME DETECTOR ACTIVATION."

B. High Expansion Foam Visual Notification Devices: Provide blue beacons not less than 400 cd

(208/120VAC) powered from a dedicated emergency panel provided in accordance with UFC 3-520-01. This requirement does not justify an emergency generator for the facility. The FSCP will control beacon initiation. A backup power supply or supervision of the power supply feeding the beacons is not required when fed from the dedicated emergency panel. Beacons will be mounted 20 - 30 feet (3 - 9.1 m) above the floor of the hangar bay. For single door hangars, provide one beacon centered on each of the three walls. Provide additional beacons where at least one beacon is not viewable from normally occupied areas of the hangar bay. Design will take into account facility construction, type of aircraft, aircraft configuration and positioning, fixed and mobile equipment within the aircraft servicing area.

Page 21: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 11

2.07 ABOVEGROUND PIPING SYSTEMS A. Pipe, Fittings, and Mechanical Couplings: NFPA 13, except steel piping must be Schedule 40. Rubber

gaskets used with grooved-end fittings must be UL listed for use in dry-pipe sprinkler systems.Use of restriction orifices, reducing flanges, and plain-end fittings with mechanical couplings (which utilize steel gripping devices to bite into the pipe when pressure is applied) are not permitted. Pipe and fittings in contact with high expansion foam concentrate must be material resistant to the corrosive effects of high expansion foam concentrate as approved by the manufacturer of the proportioning system. 1. Foam Solution Piping: All pipe, fittings, fasteners, hangars, and stands downstream of the flow control

valve must be hot dip galvanized and a minimum schedule 40 wall thickness. Do not roll groove galvanized pipe. Any cut groves, threaded ends and areas where the zinc coating has been damaged must be cleaned of cutting oils and debris, dried, and painted with two full coats of a cold galvanizing primer containing a minimum of 95% zinc.

B. Jointing Material: CID A-A-58092, Polytetrafluoroethylene (PTFE) tape. Pipe joint compound (pipe dope)

is not acceptable. C. Basket Strainers: The Strainer shall be a basket type strainer UL listed for 175 psi and FM approved. The

strainer shall be with high flow capacity and low pressure loss. The strainer body and cover shall be steel with anti-corrosion epoxy coating internally and externally. The screen shall be inline removable closed basket type, made of stainless steel 304 with screen holes meeting the requirements of NFPA 13, NFPA 15 and NFPA 24. The total screen area and the total area of the screen openings will give a ratio of 6 to 1 compared to the cross-sectional area of the pipeline. The strainer screen shall withstand 125 psi when plugged. Friction loss shall not exceed 10 psi when tested with foreign materials (gravel) equal to 21/2' of filled pipe trapped in the strainer. Friction loss shall not exceed 3 psi at rated flow when tested with clean strainer screen and clean water. Strainer maintenance, inspection or service shall be carried out in-line and without disassembly of the strainer body from the pipeline. A flush outlet shall be provided with each strainer. The Strainer shall be supplied pre-assembled with stainless steel bolting, hydraulically tested by the factory.

D. Pipe Hangers and Supports: Provide galvanized or stainless steel pipe hangars and supports as required

by NFPA 13. E. Valves: Provide valves as required by NFPA 13 and of types approved for fire service. Gate valves must

open by counterclockwise rotation. Check valves must be flanged clear opening swing check type with flanged inspection and access cover plate for sizes 4 inches and larger. Provide an OS&Y or butterfly valve beneath each flow control valve in each riser, when more than one valve is supplied from the same water supply pipe.

F. Identification Signs: Attach properly lettered approved metal signs conforming to NFPA 13 to each valve

and alarm device. Permanently affix design data nameplates to the riser of each system. G. Main Drains: Provide drain piping to discharge at safe points outside each building or to sight cones

attached to drains of adequate size to readily receive the full flow from each drain under maximum pressure. Provide auxiliary drains as required by NFPA 13.

H. Pipe Sleeves: Provide where piping passes through walls, floors, roofs, and partitions. Secure sleeves in

proper position and location during construction. Provide sleeves of sufficient length to pass through entire thickness of walls, floors, roofs, and partitions. Provide not less than 1/4 inch space between exterior of piping and interior of sleeve. Firmly pack space with insulation and calk at both ends of the sleeve with plastic waterproof cement. 1. Sleeves in Masonry and Concrete Walls, Floors, Roofs: ASTM A53/A53M, schedule 40 or standard

weight, zinc-coated steel pipe sleeves. Extend sleeves in floor slabs 3 inches above the finished floor. 2. Sleeves in Partitions: Provide zinc-coated steel sheet having a nominal weight of not less than 0.90

pounds per square foot. I. Escutcheon Plates: Provide one piece or split hinge type plates for piping passing through floors, walls

and ceilings, in both exposed and concealed areas. Provide chromium plated metal plates where pipe passes through finished ceilings. Provide other plates of steel or cast iron with aluminum paint finish. Securely anchor plates in place.

Page 22: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 12

J. Surge Arrester: Provide a bladder type surge arrester (expansion tank) for each separate foam riser. Tanks must be floor mounted or wall supported. Tanks must be listed/approved as a surge arrester with a rated working pressure not less than 275 psi. Provide a system hydraulic surge analysis showing surge pressure occurring throughout the system do not exceed maximum design operating pressure at both design flow and nonflow conditions.

PART 3 EXECUTION 3.01 INSPECTION BY FIRE PROTECTION ENGINEER A. The Fire Protection Engineer specified in this Section must inspect the sprinkler system periodically

during the installation to assure the sprinkler system is being provided and installed in accordance with the contract requirements and the approved sprinkler system submittal(s). This Fire Protection Engineer must attend both the preliminary and final tests, and must sign the test results. After the preliminary testing has been completed, the Fire Protection Engineer must certify in writing the system is ready for the final inspections and tests. This report must document any discrepancies found and what actions will be taken to correct. Any discrepancy noted during the periodic site visits or the preliminary testing must be brought to the attention of the Contracting Officer in writing, no later than three working days after the discrepancy is discovered. Pre-priming of any foam solution piping is NOT acceptable. All solution piping must be slopped to be self-draining back to the riser. During commissioning, the responsible FPE must seal or otherwise install tamper proof guards on the pressure regulator adjusting stem and the two small globe valves on the speed control assembly. It is crucial these settings not be changed after commissioning; so that the system will operate correctly. Safety-wire these devices in those positions and label them "DO NOT ADJUST". Any other trim valves which must be open or closed for the FCV to function also must be safety wired in position.

3.02 HIGH EXPANSION FOAM SYSTEM INSTALLATION A. Equipment, materials, installation, workmanship, fabrication, assembly, erection, examination, inspection,

and testing must be in accordance with the NFPA standards referenced herein. Install piping straight and true to bear evenly on hangers and supports. Conceal piping to the maximum extent possible. Piping must be inspected, tested and approved before being concealed. Provide fittings for changes in direction of piping and for all connections. Make changes in piping sizes through standard reducing pipe fittings; do not use bushings. Cut pipe accurately and work into place without springing or forcing. Ream pipe ends and free pipe and fittings from burrs. Clean with solvent to remove all varnish and cutting oil prior to assembly. Make screw joints with PTFE tape applied to male thread only.

3.03 FIELD PAINTING A. Clean, prime, and paint new foam systems including valves, piping, conduit, hangers, miscellaneous

metal work, and accessories. Apply coatings to clean dry surfaces using clean brushes. Clean the surfaces in accordance with SSPC SP 11. Immediately after cleaning, prime the metal surfaces with one coat of SSPC Paint 25 or SSPC Paint 25 primer applied to a minimum dry film thickness of 1.5 mils. Exercise care to avoid the painting of sprinkler heads and operating devices. Upon completion of painting, remove materials which were used to protect sprinkler heads and operating devices while painting is in process. Remove sprinkler heads and operating devices which have been inadvertently painted and provide new clean sprinkler heads and operating devices of the proper type. Finish primed surfaces as follows:

B. Foam Systems in Unfinished Areas: Unfinished areas are defined as attic spaces, spaces above

suspended ceilings, crawl spaces, foam rooms, pump rooms, pipe chases, and other spaces where ceilings are not painted or not constructed of a prefinished material. Paint primed surfaces with two coats of CID A-A-2962 red enamel applied to a minimum dry film thickness of 1.5 mils.

C. Foam Systems in All Other Areas: Paint primed surfaces with two coats of paint to match adjacent

surfaces, except paint valves and operating accessories with two coats of CID A-A-2962red enamel applied to a minimum dry film thickness of 1.5 mils. Provide piping with 2 inch wide red bands spaced at maximum 20 foot intervals throughout the piping systems. Bands must be red enamel or self adhering red plastic tape.

D. Piping Labels: Provide permanent labels in foam rooms, spaced at 20 foot maximum intervals along pipe,

indicating "WATER" and "FOAM SOLUTION" on corresponding piping. 1. Fire Protection Water 2. Foam Concentrate 3. Foam Solution

Page 23: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 13

4. Sprinkler 5. Test

E. Field Touch-Up: Clean damaged areas of shop coated tanks in accordance with SSPC SP 11 and coat

cleaned areas with the same materials used for the shop applied coating system. 3.04 ELECTRICAL WORK A. Electrical work is specified in Division 26, except for control and fire alarm wiring. The fire alarm system is

specified in Section 28 31 00 FIRE DETECTION AND ALARM SYSTEMS. B. Wiring: Provide control wiring, and connections to fire alarm systems, under this section in accordance

with NFPA 70 and NFPA 72. Provide wiring in rigid metal conduit or intermediate metal conduit, except electrical metallic tubing may be used in dry locations not enclosed in concrete or where not subject to mechanical damage. Do not run low voltage DC circuits in the same conduit with AC circuits. Run wiring to optical flame detectors alone in separate conduit if required by the detector manufacturer. Optical flame detectors, manual release stations, and abort stations must must be provided with watertight connections with conduit runs entering the station backbox from the bottom.

3.05 FLUSHING A. Flush the piping system in accordance with NFPA 13. Continue flushing operation until water is clear, but

for not less than 10 minutes. Flushing of low-level system must be accomplished with low-level nozzle covers removed. System isolation valve must be secured prior to the start of flow control valve operation, then slowly opened to assure flushing is conducted in a controlled and safe manner. Once flushing has been completed, low-level nozzle diffusers must be reinstalled in accordance with manufacturer's specifications.

3.06 FIELD QUALITY CONTROL A. Prior to initial operation, inspect equipment and piping systems for compliance with drawings,

specifications, and manufacturer's submittals. Perform tests in the presence of the Contracting Officer to determine conformance with the specified requirements. Contact the AFCEC Hangar Fire Protection Engineer, Ms. Judy Biddle ([email protected]), for the current testing checklist at the time of testing. See Appendix A of this section for a preliminary checklist.

B. Preliminary Tests: Each piping system must be hydrostatically tested at 200 psig in accordance with

NFPA 13 and must show no leakage or reduction in gage pressure after 2 hours. The Contractor must conduct complete preliminary tests, which must encompass all aspects of system operation. Individually test all detectors, manual actuation stations, alarms, control panels, and all other components and accessories to demonstrate proper functioning. Test water flow alarms by flowing water through the inspector's test connection. When tests have been completed and all necessary corrections made, submit to the Contracting Officer a Preliminary Test Report signed and dated by the Fire Protection Engineer, similar to that specified in NFPA 13, attesting to the satisfactory completion of all testing and stating that the system is in operating condition. Also include a written request for a formal inspection and test.

C. Formal Inspection and Tests: The Fire Protection Engineer will witness formal tests and approve all

systems before they are accepted. The system must be considered ready for such testing only after all necessary preliminary tests have been made and all deficiencies found have been corrected to the satisfaction of the equipment manufacturer's technical representative and written certification to this effect is received by the Fire Protection Engineer. 1. Formal Inspection and Testing Requests: Submit the request for formal inspection at least 30 working

days prior to the date the inspection is to take place. a. All Certification that preliminary testing has been completed and a copy of the preliminary test

report must accompany the request for formal inspection. b. The control panel(s) and detection system(s) must be in continuous service for a "break-in" period

of at least 15 consecutive days prior to the formal inspection. c. Experienced technicians regularly employed by the Contractor in the installation of both the

mechanical and electrical portions of such systems must be present during the inspection and must conduct the testing.

d. All high expansion foam concentrate, instruments, including optical flame detector test lamp and function test kit, personnel, appliances and equipment for testing must be furnished by the Contractor.All necessary tests encompassing all aspects of system operation must be made including the following, and any deficiency found must be corrected and the system retested at no cost to the Government.

Page 24: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 14

e. The Contractor must submit the Final Acceptance Test. f. Provide protection for all electrical fixtures and equipment exposed to possible damage during

tests and protect doors and other openings leading from the protected area(s), to prevent migration of foam solution into other areas or spaces. Install plastic sheeting over all wall and door surfaces from the finish floor to not less than 20 feet above the finish floor.

g. Report as specified in the Submittals paragraph. 2. Systems Functional and Device Testing: Every feature and function of the foam system control panel,

including initiating, alarm, and actuation systems must be operated. As a minimum, operation and supervision of the following functions and devices must be demonstrated: a. All operational and supervisory functions of the control and annunciator panels. b. Each foam system manual release and abort stations and associated circuit(s). c. All optical flame detectors and associated circuits. The Contractor must engage the services of

the optical flame detector manufacturer to conduct actual pan fire tests in the presence of the Contractor, Contracting Officer, AFCEC FPE and the base fire department. The Contractor must provide a liquid tight 3.28 foot square by 4 inch high welded steel fire pan with detached removable steel cover, and steel sub-frame with rollers/casters to allow for convenient relocation of the fire pan. The Contractor must obtain JP-8/JET-A/JET/A1 fuel from the Government for use in the fire pan, and must conduct pan fire tests to demonstrate the performance of the optical flame detectors. Detector pass/fail status must be determined by comparison of detector performance during pan fire tests relative to the detector manufacturer's published performance data for the specific type detector being tested. Pan fire tests must be conducted in up to 12 separate locations to be determined by the Government. No foam must be discharged during pan fire tests. Coordinate with the AFCEC FPE and the base fire department prior to conducting any pan fire tests.

d. Each general alarm initiating device (manual pull stations, flow switches, pressure switches, and associated circuit(s).

e. Each supervisory initiating device or function (valve tamper switch, tank level supervisory panels, fire pump controllers, etc) and associated circuit(s).

f. All alarms and associated circuits. g. All actuator circuits and system control valve(s) (without foam discharge). h. Activation of the building fire evacuation alarm system. i. Activation of the Base fire alarm system (receipt of fire alarm at alarm office). j. All of the above tests must then be repeated with the system on battery power only. k. Flow control valve (FCV) functional testing. Operate flow control valves and adjust valve

open/closure speed and discharge pressure settings as specified. Demonstrate proper pressure settings and valve peration speed by utilizing the nozzle test/drain assembly at the most remote nozzle to record system pressure and by using the system abort station to stop and restart flow. Seal the pressure regulator, opening speed, and closure speed valves in their final "set" position with safety wire. Wire seals must prohibit casual movement of valves. Permanently record the final FCV discharge pressure setting on each valve.

3. High Expansion Foam Discharge and Inductor Testing: When all of the initiating, alarm, actuation, and supervisory functions of the system operate to the satisfaction of the system manufacturer's technical representative and the Fire Protection Engineer, and the AFCEC Fire Protection Engineer; the contractor must conduct a full discharge test of the system servicing each separated fire area. The test must be performed to demonstrate satisfactory performance, proper HIGH EXPANSION FOAM concentration, mechanical operation and operation of valves, release devices, alarms, and interlocks which control the protected areas. These tests must be conducted by experienced personnel according to the equipment and high expansion foam manufacturers' recommendations. a. Contractor must prepare a plan for conducting the test and the duties of the test team. Contractor

must remove any mobile / portable equipment from the hangar servicing area. Contractor must cover the hangar walls and surface mounted equipment with plastic sheeting from the finished floor to 20 feet above the finished floor. Doors into adjacent areas must be protected to prevent foam-water solution leaking into the adjacent areas during the test and subsequent clean-up. The test and any re-test will begin with the system in normal configuration; no recharging of the system piping is allowed. Hangar doors will be closed and will remain closed until the hangar is released to the contractor's clean-up team.

b. Test must be initiated by activating one of the manual foam start stations located throughout the hangar bay.

c. Test low-level fire extinguishing system by full flow of foam-water solution through the foam generators to demonstrate the following: - 90% Coverage of the aircraft silhouette projected on the floor (marked with painter's tape) within

60 seconds of the opening of the water control valve.

Page 25: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 15

- No foam falls from the foam generators within the projected aircraft silhouette. - Foam fills the hangar servicing area to a level of not less than 1 meter in not less than 4 minutes

or less. - Once the test director indicates the 1 meter depth has been achieved, depress a "Stop Foam

System" button on a station remote to the activation station used to initiate the discharge. The water control valve must close not faster than 5 seconds and not more than 15 seconds.

d. During the test, failure to achieve a performance requirement in sequence (subparagraph c above) will stop the tests.

e. During the test (c above) the foam concentrate manufacturer's representative must collect samples from not less than two remotely located generators of the discharged expanded foam-water solution and using the conductivity method determine the foam concentrate proportioning rate (percentage).

4. Flushing and Rinsing: After completion of tests flush all piping carrying HIGH EXPANSION FOAM solution with fresh water. Rinse with fresh water all equipment and building surfaces exposed to high expansion foam discharge.

D. Environmental Protection: The concentrate shall be biodegradable, low in toxicity, and treatable in

sewage plants. E. Additional Tests: When deficiencies, defects or malfunctions develop during the tests required, all further

testing of the system must be suspended until proper adjustments, corrections or revisions have been made to assure proper performance of the system. If these revisions require more than a nominal delay, the Contracting Officer must be notified when the additional work has been completed, to arrange a new inspection and test of the system. All tests required must be repeated prior to final acceptance, unless directed otherwise.

F. High Expansion Foam Concentrate: High expansion foam concentrate must be approved by the

generator manufacturer as appropriate for use with the specific generators installed. Contractor must provide high expansion foam concentrate for all testing (initial and acceptance) and any required retesting. Concentrate tanks must be full (not less than the minimum quantity intended to provide the 15 minute operating time) for all tests. Foam concentrate removed from the tank for repairs or adjustments must not be reused unless the concentrate manufacturer certifies the removed concentrate is of the same quality as original new concentrate. Following approval of all testing by the Contracting Officer and completion of all "punch list items" the contractor must replenish the concentrate storage tank with not less than the minimum design quantity to provide 15 minutes of operating time.

G. Manufacturer's Representative: Provide the services of representatives or technicians from the

manufacturers of the low-level high expansion foam generators system, foam system control panel, and optical flame detectors experienced in the installation and operation of the type of system being provided, to supervise installation, adjustment, preliminary testing, and final testing of the system and to provide instruction to Government personnel. The foam system control panel manufacturer must provide a minimum of 4-days startup assistance.

3.07 OPERATING INSTRUCTIONS A. Provide instructions for operating the fire extinguishing system at control equipment and at each remote

control station. Instructions must clearly indicate all necessary steps for the operation of the system. Submit the proposed legend for operating instructions for approval prior to installation. Instructions must be in engraved white letters on red rigid plastic or red enameled steel backgrounds and must be of adequate size to permit them to be easily read.

3.08 TRAINING REQUIREMENTS A. Prior to final acceptance, the Contractor must provide two sessions of 4 hours each of operation and

maintenance training to the installation Civil Engineering; Installation Fire Emergency Service; and Installation Ground Safety Activity personnel on two different days to accommodate both shifts of the Installation Fire Emergency Services. Each training session must include emergency procedures, and unique maintenance and safety requirements. Training areas will be provided by the Government in the same building as the protected areas. The training conducted must use operation and maintenance manuals specified in paragraph entitled "Operations and Maintenance Manuals". Dates and times of the training period must be coordinated through the Contracting Officer not less than two weeks prior to the sessions.

Page 26: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

1016

21 13 39 – 16

3.09 APPENDICES A. The following are included at the end of this section.

1. Appendix A - Preliminary and Final Hangar Fire Suppression/Detection Acceptance Testing Requirements

2. Appendix B – Criteria changes. END OF SECTION

Page 27: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

28 31 00 - 1

SECTION 28 31 00: FIRE DETECTION AND ALARM SYSTEMS PART 1 GENERAL 1.01 APPLICABLE PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only. 1. Factory Mutual System (FM) Publication

a) Approval Guide (Equipment, Materials, Services for Conservation of Property) 1989 with Quarterly Supplements.

2. National Fire Protection Association (NFPA) Standards: a) NFPA 70 National Electrical Code. b) NFPA 72 National Fire Alarm Code. c) NFPA90A Installation of Air Conditioning and Ventilating System.

3. Underwriters Laboratories, Inc. (UL) Publications: a) Fire Protection Equipment Directory (Jan 1989 with Quarterly Supplements). b) UL 38 Manually Actuated Signaling Boxes for Use with Fire-Protective Signaling Systems c) UL 228 Door Closers-Holders, with or without Integral Smoke Detector. d) UL 268 Smoke Detectors for Fire Protective Signaling Systems.

(1) e) UL 268A Smoke Detectors for Duct Application e) UL 464 Audible Signal Appliances. f) UL 521 Heat Detectors for Fire Protective, Signaling Systems. g) UL 864 Control Units for Fire-Protective Signaling Systems.

4. Unified Facility Criteria (UFC) 3-600-01, Design: Fire Protection Engineering for Facilities 5. Unified Facility Criteria (UFC) 4-021-01 Design and O&M: Mass Notification Systems (dated 9 April 08, change 1, January 2010)

B. National Fire Protection Association: 1. NFPA 72 - National Fire Alarm Code. 2. NFPA 262 - Standard Method of Test for Flame Travel and Smoke of Wires and Cables for Use in

Air-Handling Spaces. 1.02 SUBMITTALS

A. Submit shop drawings showing all system components under provisions of Section 01 33 00. Plans and calculations must be prepared by a registered professional fire protection engineer or individual that has obtained National Institute for Certification in Engineering Technologies, Fire Alarm Systems Level IV. All fire alarm system designs must be reviewed and stamped by a registered professional fire protection engineer. If the MNS portion is used to notify occupants of fire condition than it to must adhere to this provision.

B. Submit manufacturer’s data on all components used in the system under provisions of Section 01 33 00. C. The authority having jurisdiction and the alarm shop 1 SOCES/CEOFA shall be notified prior to

installation or alteration of equipment or wiring. Complete information regarding the system or system alterations, including specifications, type of system or service, shop drawings, input/output matrix, battery calculations, and notification appliance circuit voltage drop calculations shall be submitted for approval.

D. Under no circumstances will installation begin prior to approval of SUBMITTALS. E. Submit Qualification of Installer per PART 2, Paragraph 2.05.

1.03 SCOPE A. The existing microprocessor controlled fire detection system shall be modified in accordance to the project specifications and drawings. B. Basic Performance: 1. Alarm, trouble and supervisory signals from all intelligent reporting devices shall be encoded on NFPA Style 6 (Class A) Signaling Line Circuits (SLC). 2. Initiation Device Circuits (IDC) shall be wired Class A as part of an addressable device connected by the SLC Circuit.

Page 28: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

28 31 00 - 2

3. On Style 6 (Class A) configurations a single ground fault or open circuit on the system Signaling Line Circuit shall not cause system malfunction, loss of operating power or the ability to report an alarm. 4. Alarm signals arriving at the FACP shall not be lost following a primary power failure (or outage) until the alarm signal is processed and recorded.

C. Basic System Functional Operation 1. When a fire alarm condition is detected and reported by one of the system initiating devices, the following functions shall immediately occur: a. The system alarm LED on the system display shall flash. b. A local piezo electric signal in the control panel shall sound. c. A backlit LCD display shall indicate all information associated with the fire alarm condition, including the type of alarm point and its location within the protected premises. d. The fire alarm strobe horns shall sound or if MNS, the clear strobe shall flash and the fire message shall be announced through the fire/MNS speakers. e. Printing and history storage equipment shall log the information associated each new fire alarm control panel condition, along with time and date of occurrence. f. All system output programs assigned via control by event interlock programming to be activated by the particular point in alarm shall be executed, and the associated system outputs (notification appliances and/or relays) shall be activated. g. An associated signal is sent VIA Monaco transceiver to the fire department. PART 2 PRODUCTS 2.01 General Requirements A. Materials and equipment shall be new standard products of the manufacturer's latest design, and suitable

to perform the function intended. Materials and equipment shall be compatible with the existing fire alarm system in the facility. Components of two or more models will not be combined to form a single control unit. This equipment shall be in service and supported by the manufacture for five years after the install date. Where two or more pieces of equipment must perform the same functions, the same manufacturer shall produce this equipment. The name of the manufacturer shall appear on all major components.

2.02 Quality Requirements A. All materials and equipment shall conform to the requirements of the UL, or the FMS for fire-alarm

systems of the type indicated. The Contractor shall submit proof that the items furnished under this specification conform to these requirements. The UL label or seal, or listing in the UL Fire Protection Equipment Directory will be accepted as evidence that the items conform to UL requirements. The FMS label or seal, or listing in the Factory Mutual Approval Guide will be accepted as sufficient evidence that the items conform to the FMS requirements.

2.03 Shop Drawing and System Designer Qualifications A. Within 30 days after receipt of notice to proceed and prior to starting installation, the Contractor shall

submit to the Contracting Officer for approval a complete set of shop drawings to include all material and equipment proposed for installation Sealed by a registered fire protection engineer, by a registered professional engineer having at least four years of current experience in the design of fire protection and detection systems, or by an engineering technologist qualified at NICET Level IV in fire systems. The individual’s name, signature, and professional engineer number or NICET certification number shall be included on all final design documents. All fire alarm system designs must be reviewed and stamped by a registered professional fire protection engineer. Include manufacturer's name(s), model numbers, ratings, power requirements, equipment layout, device arrangement, device addresses.

2.04 Qualifications of Installer A. System Installer: Installation personnel shall be qualified or shall be supervised by persons who are

qualified in the installation, inspection, and testing of fire alarm systems and shall be on-site at all times during system installation, modification or upgrade. Evidence of qualifications or certification shall be provided when requested by the authority having jurisdiction. Qualified personnel shall include, but not be limited to, one or more of the following:

Page 29: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

28 31 00 - 3

1. Personnel who are factory trained and certified for fire alarm system installation of the specific type and brand of system installed

2. Personnel who are certified by a nationally recognized fire alarm certification organization acceptable to the authority having jurisdiction

3. Personnel who are registered, licensed, or certified by a state or local authority. The Contracting Officer shall reject any proposed installer who cannot show evidence of such

qualifications. PART 3 EXECUTION 3.01 Pre-Construction Test A. Prior to starting any work on existing systems the contractor shall schedule through the contracting office

a fire alarm system pre-test to establish the baseline for the alarm system. Any discrepancies identified shall be signed off by the contractor, 1 SOCES/CEOFA Alarm Shop, and contracting officer or his/her representative. Failure to conduct this test will hold the contractor solely responsible for all discrepancies during final inspection.

3.02 Installation and Wiring A. 1. The FACP and control units shall be installed in a room directly accessible from the building exterior

and shall be condition as office space. 2. Runs of conduit, tubing, wire and cable shall be straight, neatly arranged, properly supported, red in color and parallel or perpendicular to walls and partitions. Installation of wiring shall conform to NFPA 70. NOTE: 300.11 3. Wiring located within the cavity of a non–fire-rated floor–ceiling or roof–ceiling assembly shall not be secured to, or supported by, the ceiling assembly, including the ceiling support wires. An independent means of secure support shall be provided and shall be permitted to be attached to the assembly. 4. All wiring shall be installed in conduit (minimum ¾” EMT). The sum of the cross-sectional areas of Individual conductors shall not exceed 40 percent of the interior cross-sectional area of the conduit. 5. All wiring for the system shall be solid wires. The fire alarm system wiring shall not share the same conduit as other low voltage wiring, such as cameras, access control, etc. 6. Wiring for audible visual circuits shall be color-coded red for positive and black for negative. 7. Cable must be separated from any open conductors of Power, or Class 1 circuits, and shall not be placed in any conduit, junction box or raceway containing these conductors, as per NEC Article 760-29. 8. Conduits shall not enter the Fire Alarm Control Panel, or any other remotely mounted Control Panel equipment or back boxes, except where conduit entry is specified by the FACP manufacturer. 9. Wiring shall be in accordance with local, state and national codes (e.g., NEC Article 760) and as recommended by the manufacturer of the fire alarm system. 10. Number and size of conductors shall be as recommended by the fire alarm system manufacturer, but not less than 18 AWG for Initiating Device Circuits and signaling Line Circuits, and 14 AWG for Notification Appliance circuits. 11. The Fire Alarm Control Panel shall be connected to a separate dedicated branch circuit, maximum 20

amperes. This circuit shall be labeled at the Main Power Distribution Panel as Fire Alarm; circuit breaker shall be protected from operation by unauthorized personnel by a circuit breaker guard. Fire

Alarm Control Panel primary power wiring shall be 12 AWG. The control panel cabinet shall be grounded. Label all wire termination with shrink wrap labels, clearly marked with the circuit information.

12. All wire and cable shall be listed and/or approved by recognized testing agency for use with a protective signaling system. Wiring used for the multiplex communication circuit (SLC) shall be twisted and unshielded and support a minimum wiring distance of 12,500 feet. 13. System components shall be securely fastened to their supports independently of the wiring. 14. All equipment and conduit in the Hangar bay shall be NEMA 4. B. Twist-on connectors (wire nuts) shall not be used. Connections shall be permitted to be made using a set-screw, pressure-type conductor connector, provided a means is used to prevent the set screw from bearing directly on the conductor. C. All circuits shall be installed CLASS A, wiring and conduit shall comply with NFPA 72 CH. 6.4.2.2.2. D. All modules shall have their address clearly and permanently labeled on the outside of the devices.

Page 30: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

28 31 00 - 4

E. All address modules shall be integrated with the device. F. Fire circuits shall not be run in the same raceway, cable or conduit as high voltage circuits (120vac). G. Fire alarm circuits derived from the fire alarm panel shall not be terminated on the same device with 120VAC power unless it is a relay designed for the use. 3.03 Audible and Visual Alarm Devices

A. Audible and Visual devices are existing to remain. 3.04 Mass Notification Systems A. The Mass Notification System is existing to remain. The Voice Messages shall be modified in the existing

Mass Notification System Panel, as indicated on the Contract Drawings. 3.05 Drawings and Manuals A. Upon completion of the installation and prior to final inspection, the Contractor shall furnish two copies of "as-built" drawings. Drawings shall show equipment configuration, control panel equipment and subassembly locations, and the location of all connecting Wiring. Drawings shall include all wiring color codes and terminal numbers and termination points for all wires. In addition, the Contractor shall furnish two copies of a manual giving complete instructions for the operation, inspection, testing, and maintenance of the system including wiring diagrams. The drawings shall include a detailed wiring layout showing all junction boxes and all system wiring, including number of wires, with speaker and strobe circuits identified with speaker taps and candela ratings. Show module location and address. The layout shall be done on the building floor plans and combined with fire detection and alarm system. See section 01 70 00 CONTRACT CLOSE OUT. 3.06 System Components Addressable Devices A. Addressable Devices General 1. Addressable devices shall use simple to install and maintain decade, decimal address switches. Devices shall be capable of being set to an address in a range of 001 to 159. 2. Addressable devices, which use a binary coded address setting method, such as a DIP switch, are not an allowable substitute.

B. Water-flow Indicator: 1. Water-flow Switches shall be an integral, mechanical, non-coded, non-accumulative retard type. 2. Water-flow Switches shall have an alarm transmission delay time which is conveniently adjustable from 0 to 60 seconds. Initial settings shall be 30 to 45 seconds. 3. All water-flow switches shall come from a single manufacturer and series. 4. Water-flow switches shall be provided and connected under this section but installed by the mechanical contractor. 5. Where possible, locate water-flow switches a minimum of one (1) foot from a fitting which changes the direction of the flow and a minimum of three (3) feet from a valve. 6. Water flow switches shall be wired to an addressable monitoring module, shall activate a non silenceable alarm at the FACP and transmit a signal from the BTXM on a dedicated Zone. C. Sprinkler and Standpipe Valve Supervisory Switches: 1. Each sprinkler system water supply control valve riser, zone control valve, and standpipe system riser control valve shall be equipped with a supervisory switch. Standpipe hose valves, and test and drain valves shall not be equipped with supervisory switches. 2. PIV (post indicator valve) or main gate valves shall be secured with a chain and lock. 3. Each valve supervisory switches shall be provided and connected as separate addressable points to the fire alarm system and shall report a separate and distinct supervisory alarm to the fire department (SPRINKLER TAMPER). Rope type tamper switches are not permitted.

3.07 Suppression Systems A. Control Valve Supervisory Signal-Initiating Device. 1. Two separate and distinct signals shall be initiated: one indicating movement of the valve from its normal position (off-normal) and the other indicating restoration of the valve to its normal position. The off-normal signal shall be initiated during the first two revolutions of the wheel or during one- fifth of the travel distance of the valve control apparatus from its normal position. The off-normal signal shall not be restored at any valve position except normal.

Page 31: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

28 31 00 - 5

Initiating device for supervising the position of a control valve shall not interfere with the operations of the valve, obstruct the view of its indicator, or prevent access for valve maintenance. 2. Control valve supervisor signals shall be sent to the fire station as a separate supervisor signal via the Monaco BTX-M radio transceiver. 3.08 Drawing and Manuals

A. Upon completion of the installation and prior to final inspection, the Contractor shall furnish two copies of "as-built" drawings on CD or DVD and shall be in CAD format. Drawings shall show equipment configuration, control panel equipment and subassembly locations, and the location of the transceiver and all connecting Wiring. Drawings shall include all wiring color codes and terminal numbers and termination points for all wires. They shall include a detailed wiring layout showing all junction boxes, all system wiring, including number of wires, with zones and alarm sounding circuits, initiating and alarm sounding devices identified by module number and strobes with candela rating. In addition, the Contractor shall furnish two copies of a manual giving complete instructions for the operation, inspection, testing, and maintenance of the system including wiring diagrams. The layout shall be done on the building floor plans. The final inspection cannot take place without the drawings.

3.09 Special Tools

A. All special tools or equipment necessary for the operation and maintenance of the equipment including testing shall be furnished this includes but not limited to a laptop, software, cables and hardware keys (dongle) if required. The items furnished will be new/unused items with packaging and manuals.

3.10 Repair of Existing Work A. The work shall be carefully laid out in advance. Cutting, channeling, chasing, or drilling of floors, walls,

partitions, ceilings or other surfaces as necessary for the proper installation, support, or anchorage of the conduit or other work shall be carefully done. Damage to buildings, piping or equipment shall be repaired and refinished by skilled mechanics of the trades involved.

3.11 Tests

A. After all equipment for this system has been installed and made operational, and at a time directed by the Contracting Office, the contractor shall conduct tests to demonstrate that the installation and the system operation is in accordance with the plans and specifications. Testing of the system shall include remote annunciation of alarms and trouble conditions to the fire department. In addition to the request letter, the Contractor shall submit a test plan/procedure to the Contracting Officer to indicate his proposed method to demonstrate compliance with the plans and specifications. The contractor will also certify in writing that the work accomplished meets all contractual requirements. The government will provide one retest. Subsequent testing will result in reimbursement of expenses to the Government. Satisfactory operation of each of the following devices shall be demonstrated during the test: 1. Each automatic detector. 2. Each manual fire alarm station. 3. Each transceiver, all functions. 4. Each audible alarm device. 5. Each visual alarm device. 6. Supervision of each device such as; heat detectors, pull stations, smoke detectors, etc; and alarm

zone circuits to include ground faults. 7. Satisfactory operation after loss of primary power supply. 8. Satisfactory operation of each device shut down circuit with correct zone correspondence. This shall

not be simulated but shall actually be demonstrated by actual device/equipment shutdown. 9. All control panel functions, alarm and trouble, audible and visual indicators, silence switches and their

resound function and alarm resound features of the control unit. 10. In each zone containing automatic smoke detectors, each detector will be put into the alarm mode

and stay in that mode for 10 minutes after the last detector goes into alarm, to verify satisfactory operation of the detectors and the detector power supply module under alarm load. Smoke is expressly forbidden for this test.

11. Supervision of DC power on each automatic detector circuit. B. Documentation Required. Every system shall include the following documentation, which shall be

delivered to the contracting officer two weeks prior to any initial inspections the system: 1. An owner’s manual and manufacturer's published instructions covering all system equipment. Provide

all manuals, drawings, technical/programming manual on a DVD disk. 2. Record drawings

Page 32: SECTION 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE ... · Sprinklers shall be uniformly spaced on branch lines. In buildings protected by automatic sprinklers, sprinklers shall

MS0114

28 31 00 - 6

3. For software-based systems, provide programming software, database, dongle key and computer cable to connect to fire panel.

3.12 Quality Control A. The Contractor shall establish and maintain quality control for operations under the section to assure

compliance with contract requirements, and maintain records of his quality control for all materials, equipment, and construction operations, including but not limited to the following:

1. Preparatory Inspection: (To be conducted prior to commencing work.) 2. Submittal of all materials and shop drawings necessary for accomplishment. 3. Have in hand equipment and wiring layout-showing sequence of wiring. 4. Qualifications of installing firm. B. Initial inspection: (To be conducted after a representative sample of the work is complete.) 1. Check mounting heights, supports, accessibility of all items. 2. Check temperature ratings of detection against ceiling temperatures anticipated at detector locations. 3. Check size of conduit, boxes, and wires for proper sizing in accordance with National Electrical Code

and Contracts. C. Follow-Up Inspection: (to be conducted daily to assure compliance with results of initial inspection.) 1. Determine that noted deficiencies are corrected. 2. Make corrections for "as-built" fire alarm system drawings. 3. Determine that all installed equipment is functional and in accordance with the contract requirement. 4. Operational test performed. 5. Damages or defects corrected. A copy of these records and Contractor tests as well as records of corrective action taken, shall be furnished the government as directed by the contracting officer. 3.13 Final Inspection A. At the final inspection, a factory trained representative of the manufacturer of the major equipment shall demonstrate that the system functions properly in every respect.

END OF SECTION