Upload
ars10207
View
215
Download
1
Embed Size (px)
Citation preview
PROJECTS AND TASKSA Work Experience Paper
by
Alexis Stacy Chemical Engineering Department
Classification- SeniorSecond Co-op Work Term
ValsparFall, 2012
presented to
Benjamin WilhiteTexas A&M University
January 16, 2013
Approved by: Barry Parker
Engineering Manager Valspar
701 S. Shiloh Rd. Garland, TX 75042
972-487-7266
ABSTRACT
Throughout the second term my main focus was to complete as many projects that I scoped
and started during my first term before coming back to school. I will discuss and describe the
completion of my first project, Installation of Eyewash Filters, a larger project which I worked in
a team to scope, and lastly several plant support tasks that I completed throughout the second
term.
2
TABLE OF CONTENTS
Table of Figures…………………………………………………………………………………………………………………4
Background………………………………………………………………………………………………………………………5
Objectives………………………………………………………………………………………………………………………..6
Activities and Results……………………………………………………………………………………………………….6
Installation of Eyewash Filters……………………………………………………………………………………..7
Fire System Improvements………………………………………………………………………………………….9
Plant Support Tasks……………………………………………………………………………………………………11
Conclusion…………………………………………………………………………………………………………………….14
3
TABLE OF FIGURES
Figure 1: Valspar Logo and Slogan……………………………………………………………………………………5
Figure 2: Example of Industrial Eyewash Filter…………………………………………………………………7
Figure 3: Overhead View of Press Building……………………………………………………………………….9
Figure 4: Example LOTO Procedure…………………………………………………………………………………11
Figure 5: Containment Calculation………………………………………………………………………………….13
4
Figure 1: Valspar Logo and Slogan
BACKGROUND
Valspar is currently the fifth largest manufacturer for paint and coatings in North America and is
a global company with several different products. I accepted my first Cooperative Education job
at Valspar over a year ago, and since then I have learned an abundance of valuable information.
For the first and second term I moved to Garland, TX, one of the larger plants located in the
United States which is made up of three smaller plants: Consumer, Industrial, and Packaging.
First, the Consumer plant, also known as
the Latex plant, mainly works with water
based products. The Consumer plant
packages the products into the gallons of
paint you would see at Lowe’s. Several automated assembly lines glue the labels onto the cans,
fill them with paint, put the lids on, and shrink wrap them to be shipped off. Second, the
Industrial branch is a majority of solvent based products which produces coil and extrusion
coating. The Industrial plants coatings are provided to large industrial companies to range from
the coil you would find on a refrigerator to the metal coatings on the outside of sky scrapers or
the new Dallas Cowboys stadium. Lastly, Packaging, or more commonly referred to as Resin, is
in reference to the packaging coatings used on several name brand cans and bottles such as
Gerber baby food, Bud Light, and Campbell’s Chunky Soup. Packaging is also referred to as the
Resin plant because they manufacture the intermediates and resins that are shipped off to
costumers and other Valspar plants. I had the opportunity to spend my first and second term
with the Packaging plant which is actually made up of several smaller departments: Process
5
Floor, Reactor 6 Building, Monomer Bunker, RT-Tank Farm, E-coat Room, GEN VI, Quality
Control, Shipping and Receiving, and several others. To give a little background information on
some of the departments, the RT-Tanks located in a tank farm hold the bulk raw materials that
are needed for production, the E-coat room makes electrical coatings for metal applications, R-
6 Building is where all body sprays and canned/bottle coatings are made, and the GEN VI room,
the most recent department, makes the canned and bottle coatings like R-6, but they are
Bisphenol A (BPA) free. Quality Control, also known as QC Lab, is where all products are tested
in different stages of production to ensure that they are made properly and turn out with the
correct specifications which it comes to viscosity, solids, etc.
OBJECTIVES
The objective of this paper is to describe in detail my personal experience here in the Packaging
plant, to discuss the projects and tasks carrying over from the first term that I completed
throughout my second term, and the outcome and attributes I gained.
ACTIVITIES AND RESULTS
While the first term was about scoping, writing Appropriation Requests, and the approval
process, my second term at Valspar focused on completing projects.
6
Figure 2: Example of Industrial Eyewash Filters
INSTALLATION OF EYEWASH FILTERS
A recent HSE audit finding stated that several of the Packaging plants eyewash stations/safety
showers are using carbon steel piping to supply water which is deemed unsafe. Carbon steel
piping in a water system introduces rust and sediment which means the water is not clean
when the stations are being used. My first term
consisted of completing and auditing on all
thirty-one eyewash stations, scoping the project
to install filter housings or to replace carbon
steel pipe with galvanized in nine of the stations,
bringing out contractors to bid the project, and
writing up the Appropriation Request to receive
capital funding. Once the AR was complete, the
approval process began. When all signatures
were received the contractors could begin. EPCO
quoted the cost to install all filter housings,
replace carbon steel piping with galvanized on and outside station, and reroute the piping in
the boiler/utility room with galvanized pipe. One of the eyewash stations is located outside
with insulation currently around the carbon steel piping, so C.W. quoted to replace the
insulation and heat trace once the galvanized piping is installed to prevent freezing during the
winter. EPCO began their work first starting on the reroute of the piping in the utility building.
One major conflict was EPCO needed to install a galvanized tee in the main city water supply to
7
the plant which took continuous planning with production. The best time to shut off the water
supply was discussed and a Lockout/Tagout Permit was required for all valves and pump power
supply as well as a Line Breaking Permit where the galvanized tee would be installed. Once the
galvanized tee was installed and all other piping was complete a Pressure Test took place which
meant the new installed pipe had to hold 80 psi for at least thirty minutes. The Pressure Test is
to ensure no leaks due to cracks or loose fittings are in the new piping. EPCO then moved on to
the other eyewash stations and installation of eyewash filter housings. Same steps took place
for each station: Lockout/Tagout, Line Break, installation, and pressure test. After all piping and
filters were installed, CW Insulation completed the reroute of the heat trace and insulation.
Now that the project is completed, all eyewash stations/safety showers in the Packaging Plant
will be up to HSE standards; therefore, when the next audit rolls around they can see Valspar
took initiative to fix the finding. This project taught me a lot about effective communication
with contractors to ensure they fully understood what I was trying to get completed with the
project. I needed to be very detailed when discussing the scope so that nothing is left out of the
quote which would cause the project to go over budget. Also I learned to work with production,
which is of utmost importance, to ensure the project is not hindering their schedule or pushing
them back to where they miss a shipment rather it be trailers or totes.
FIRE SYSTEM IMPROVEMENTS
One of the larger projects, currently still in scoping and bidding phase, was the Packaging Plant
part of the Fire System Improvements project. The Garland site, including Packaging, Industrial
and Consumer, are all part of the Fire System upgrade for the whole site but each plant had
8
additional projects to complete alongside the upgrade. Packaging’s main add on was to move
all loading and unloading to one central, covered location. Currently, tank wagons, totes, and
drums are loaded throughout the plant: in the alley, next to buildings, etc. This poses a hazard
to the plant. If a fire were to ever occur while loading out in the open it would take quite a
while for the heat and smoke to build up and set off the fire alarm. By moving the location of
loading and unloading under a covered area allows the heat to be trapped which will signal the
fire alarms quicker. The idea is to turn the current Press Building, which is made up of several
solvent and finished good manifolds for loading totes and drums, into the loading and
unloading station. The first step of scoping this project was to discuss what is currently located
in the Press Building and what will be moved into the Press Building. The discussion took place
and the decision was made on what would stay in the Press Building and what could be
removed. The discussion included operators from all three shifts to finalize what is in use and
what is not before any demo took place. Then the next decision took place to move all
loading/unloading of Raw Material tanks, Thin Down Tank 3, reactor 7, reactor 5, and Weigh
Tank 5B into the Press Building. Next, we had to update all P&ID’s for each tank and come up
with a design of how everything will fit on the inside of the Press Building. Operators were
approached regarding new equipment, what would be easiest, and how they would use the
equipment to ensure they were on board as well. Once drawings were updated and there was a
concrete idea of how manifolds, pumps, etc. would be moved around in the Press Building an
equipment list began to take shape. The equipment list included check valves, ball valves,
actuated valve packages, plug valves, safety relief valves, pressure gauges, dual bag filters,
pumps, mass meters, and etc. As soon as the equipment list was made, the P&ID bids from
9
various suppliers were obtained. For example, valves were quoted by EADS, Genesis Systems,
and Hatfield & Co. Next, the focus turned to mechanical, electrical, and programming scopes. I
had the opportunity to analyze and write up a mechanical scope for contractors such as EPCO,
DanCar, and Dynaten. The scope was a basic outline of the work that was necessary for each
tank whether it be an addition or demo, also step by step what needed to be completed in the
current Press Building from laying/demoing concrete to installing pumps, pipes, etc. Each
mechanical contractor took over an hour long walk through the project to see current state and
talk through what the final product should look like. This project was by far the largest and
most difficult project to grasp in reference to the electrical and programming concept. I learned
quite a bit about starters, amps, and MCC’s. Unfortunately, this is a long term project that will
not be completed for a few years and will take several other engineers inputs but I thoroughly
enjoyed the experience of learning about mechanical, electrical, and programming and how
they intertwine in a project to come together in the end.
PLANT SUPPORT TASKS
10
Throughout the second term a handful of smaller tasks, also known as plant support, were
assigned to me. Three of the most
memorable tasks: Visual
Lockout/Tagout Procedures,
AutoCAD practice, and Containment
Areas. The Visual Lockout/Tagout
Procedures were the most time
consuming and required several
steps before they could be
complete. Lockout/Tagout
Procedures are used by
maintenance when tanks, mixers,
equipment, etc. are necessary to be
shut down and power supply shut off
before maintenance work can take place. I completed nine Equipment Specific LOTO
Procedures starting with seven categories for each step: the source of power, the location, the
method of LOTO, how to try, what equipment is necessary to LOTO, and lastly the “locked
by” /“unlocked” for initials. The source states how the equipment is powered (hydraulic,
electrical, and pneumatic), location states where in reference to the equipment a certain part is
located, the method describes how to lock out each part of the machinery, and the try section
describes how to test the part once it is locked out for a double check. Once the list of parts and
all sections were filled out, I worked with a maintenance guy to walk through step by step and
11
Figure 4: Example LOTO Procedure
double check that the instructions were accurate. When all of the instructions were correct, I
filled out Hotwork Permits to take pictures of the equipment. The pictures were uploaded and
labeled everything was ready to insert into a document. Each LOTO Procedure begins with a list
of equipment needed to lockout the piece of equipment, shows each part of the equipment,
and lastly the instructions tell maintenance exactly what to do step by step. Visual is more
specific and clear for others to comprehend and follow. The last time I used AutoCAD was back
in ENGR 111/112 so brushing up on my skills took some time in its self. My two major
assignments in AutoCAD besides the drawings for the Fire System Improvements was to create
a drawing for the Packaging Plant Control System and to create a Hot Work map for the
Packaging Plant to specify which tools are allowed in the different classified areas. The Control
system was already laid out for a majority of the plant but part of the assignment was to add
the new GEN VI Delta V system. The Hot Work map was not nearly as challenging because there
was already an Electrical Classification map that divides up the Class I Div I areas from Class I Div
II areas and Unclassified areas. I was able to take the original map and modify by adding a
couple notes and shaded areas. They were both terrific assignment to brush up on the AutoCAD
skills. My last project was to calculate the containment volumes for all of the berms on the
packaging side. This project came about due to a safety huddle topic regarding containment
volumes. One of the safety huddles for the operators and staff questioned their knowledge
regarding the volumes of certain berms throughout the plant and a majority of them were
unaware of the answer. There were a total of twenty-one berms and the calculations took a lot
of prep work. I started off with a sketch of each berm with the different tanks located inside
and the volume of each tank. After the sketches were complete I went out to the plant and took
12
measurements: length, width, and height of each berm. The main steps were to calculate
Figure 5: Containment Calculation
the total volume of the berm and then subtract tank pad volumes from the total volume. Once
all sketches and calculations were complete I printed yellow hazard labels to put on each berm.
This was beneficial for maintenance and operators because they will now pass these labels
throughout the workday. I enjoyed plant support task the most because of the timeline being
shorter. A project being assigned, the chance to work on the project, complete the project, and
see the final results is extremely satisfying.
CONCLUSIONS
After the second term, approximately eight months total, I have retained vital information
regarding the importance of safety in the plant environment, proper communication skills
between contractors and coworkers, engineering knowledge, and the most suitable way to
manage several projects at once. I have enjoyed the time here as well as the experience on the
13
Packaging side of the plant. I am most definitely looking forward to the third term to absorb
and learn more from the Industrial or Consumer plant.
14