PowerPoint PresentationSection 2 / Slide No : *
The DMAIC Improvement Process
Section 2 / Slide No : *
Put them into practice (i.e. Know-how)
Concepts
Process
Techniques
Section 2 / Slide No : *
Section 2 / Slide No : *
The DMAIC Process Steps
MEASURE
3
4
Section 2 / Slide No : *
10
Section 2 / Slide No : *
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
1. Identify Focus Areas
Focus limited resources on important areas.
The effort involves a working session with the participation of the
management team (the sponsors) where they examine the various
possible areas that impact the business results and, with the use
of a structured collective decision making process, decide the
critical areas to focus the improvement efforts.
Examples of focus areas include line reject rate, on-time shipment,
capacity utilization, inventory turns, response time and warranty
costs/customer complaints.
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Market Success Rate
A tool that is commonly used for this purpose is the Tree
Diagram
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
[Supplier – Inputs – Process – Outputs – Customers]
Alternatively, the SIPOC diagram is used. SIPOC is more suitable
for service organizations or supporting departments.
Suppliers
Inputs
Process
Outputs
Customers
Section 2 / Slide No : *
Recruiting
Section 2 / Slide No : *
Project Charters
Performance Gap
Section 2 / Slide No : *
Project A
Project B
Project G
Project D
Project E
Project F
Project C
Project H
Section 2 / Slide No : *
Develop the Project Charter
The project sponsor (usually with the help of his/her people)
defines the problem statement, decides the improvement goal, and
selects the project team members.
Project charter helps to make sure that due thoughts are given to
make sure that the project is properly set up.
The project should be scoped at the process level where specific
actions can be taken to realize the improvement in business
results.
The outcome of this step is an approved project charter.
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Project Charter
A Project charter is a document created at the start of a project
to assign the project to the team.
It is an important tool for getting commitments from the team
members.
A Team Charter should specify the following:
Project title and the project scope.
The business case and problem/opportunity statement.
The goal statement.
Estimated financial benefits.
Section 2 / Slide No : *
Example of Project Charter
To reduce late payments
Estimated 30% of payments are received later than the credit term
of 60 days
To reduce late payment percentage to less than 5%
Improve cash flow. Reduce bad debt risks
Account receivable process
Section 2 / Slide No : *
There should be an appointed member (sponsor) of
top management
Team members are to be selected based on the problem statement and
the scope involved.
Team members must have good working knowledge of the subject
matter.
Rule of thumb for the number of team members is 5 to 7
persons.
The team leader should be trained in:
Problem solving process steps
Section 2 / Slide No : *
Right project.
Section 2 / Slide No : *
Measure: Determine Process Capability
5. Determine process capability
Section 2 / Slide No : *
Why is it necessary to measure the process output?
To quantify the current performance level.
To objectively evaluate the gap.
To aid in the analysis of key input factors.
To verify the effectiveness of the improvement solutions.
Input
Process
Output
Section 2 / Slide No : *
Defect per unit / Error per unit / Callback per unit
Process capability ratio (Cpk, Ppk)
Cycle time / Turn- around-time / Service response time / Queue
time
On time delivery / Span (Order to Delivery)
Proportion of value adding activities
Availability of personnel / material / facility
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
4. Develop Data Collection Plan
To make sure the data collected are reliable and accurately
describes the process output characteristics.
Components of Data Collection Plan:
Definition of process output measures
Data collection method
Section 2 / Slide No : *
Process output measure
Cycle time (day) from the date of invoice issued to the date when
the payment is received
Data Collection Method
Sampling Time Frame
Sample Size
60 invoices
Sampling Method
Random Samples
Section 2 / Slide No : *
5. Determine Process Capability
Gather process output data according to the data collection
plan.
Translate the raw data into useful process information:
Use histogram to show the variation in process output
variable.
Estimate the process average and process variation using
descriptive statistics.
Compute the process capability figure.
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Mean is 57 days.
(Output From Minitab)
Section 2 / Slide No : *
Example: Process Capability Study
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Analyze: Investigate Root Causes
7. Decide the vital few suspected causes
8. Verify the causes
Section 2 / Slide No : *
List all possible factors causing the process performance
gap.
Team leader to facilitate the brainstorming process.
Leverage collective experiences of the team members.
Search thoroughly, do not leave out any possible cause.
Depending on the situation, choose the most suitable tool for this
purpose. (Cause and Effect diagram, Process FMEA, Process
Mapping)
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Identify possible causes using brainstorming and organize the
information using cause and effect diagram
Money Amount In Invoice
Don’t Match P.O.
Product Quality Problem
Relationship With Customers
Wrong Amount
Section 2 / Slide No : *
7. Decide the Vital Few Suspected Causes
Use structured discussion and team’s collective knowledge to narrow
the possible causes down to a few most probable causes.
Team leader to facilitate this narrowing process. It is important
for the team to gain a common understanding on the possible causes
before starting the narrowing process.
Choose the most suitable tool for this purpose. (Multi-voting,
nominal group technique, selection matrix)
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
8. Verify the Causes
Make sure the key suspect are actually root causes.
Discuss and decide how to confirm the key suspects.
The methods commonly used for this purpose include:
- Historical data analysis.
- Design of Experiments.
Section 2 / Slide No : *
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Using Dot Plot to verify whether error is a root cause
(Output From Minitab)
Section 2 / Slide No : *
Using Box Plot to verify whether location is a root cause
(Output From Minitab)
Section 2 / Slide No : *
Example: Hypothesis Testing
Ho: There is no difference in the means of payment days among the
different locations.
Ha: At least one of the means is different.
(Output From Minitab)
Cannot dismiss Ho
Section 2 / Slide No : *
Using Box Plot to verify whether payment method is a root
cause
Use ANOVA to confirm payment method is a root cause
Dismiss Ho, accept Ha.
Section 2 / Slide No : *
Using Scatter Diagram, it appears that money amount does not effect
days payment
Using Scatter Diagram with stratifications, it appears that money
amount has some correlation with days payment
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Using Multiple Regression to confirm the effect of money amount on
days payment
(Output From Minitab)
Section 2 / Slide No : *
Improve: Find Effective Solutions
10. Confirm Improvement Solutions
Section 2 / Slide No : *
Identify various possible solutions and evaluate their
effectiveness in solving the problem.
With the root causes identified, brainstorm all possible
improvement solutions. The first solution is usually not the best
solution.
Without any constraints, generate a list of possible solutions.
Choose the most suitable creativity technique for this
purpose.
Evaluate and select the best improvement solution.
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Challenging conventional thinking / assumptions:
Do not think Think
- It can’t be done. - How to get it done.
- It will not work. - Try and make it work.
- They’ll never buy it. - We can convince them.
- We’ve always done it this way. - Let’s find a better way.
- We’ve never tried this before. - If we don’t try, we won’t
know.
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Select Best Solution
Section 2 / Slide No : *
Contribute $xx to financial benefits.
- Restraining Forces
An estimated xx hrs of administrative efforts.
An estimated total cost of $xx will be incurred by the
company
Using Force Field Analysis to evaluate in detail the idea of giving
rebate if customers pay on time for those invoices with high dollar
values.
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Purpose: Make sure solutions are effective before
standardization.
Decide and develop an action plan to check solution
effectiveness.
Collect initial data to make sure the solutions are
effective:
- Check data distribution, compute the descriptive statistics,
calculate new process capability.
Perform potential risk assessment and stakeholder analysis to
anticipate and address possible problems when implementing the
solutions.
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Mean is 42 days.
Process Capability: Defect per million is 1,260
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
invoicing process.
customer to use payment
method other than check.
a rebate scheme
Establish Action Plan
Section 2 / Slide No : *
Control: Sustain the Improvements
11. Standardize Improvement Plan
12. Close the Project
Section 2 / Slide No : *
Purpose: Incorporate improvement solutions into process control
system.
Transfer the solutions from the team to the process owners.
Revise process control system / documents (control plan, procedure,
work instruction, etc.)
Train / brief staff on the revised process control system.
Implement a continual monitoring system.
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Get Champion’s approval to close the project.
Project can be closed when:
- The project phases have been completed.
- Project documentation have been completed.
- Improvement plan documented.
Share the lessons learned and knowledge gained with other related
processes / areas.
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Problem Statement :
The time taken from the moment production is completed to delivery
is 2 days. Some urgent orders require products to be delivered in 1
day.
Goal Statement :
Project scope:
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Measure: Determine Process Capability
Map the ‘As-Is’ Process
Common process mapping methods:
Relationship map
Validate the maps created by walking through the process and
collect the necessary data.
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Orders Fulfillment Process Cross Functional Map (As-Is)
8 9 10 11 12 1 2 3 4 5 6
QA Technician
Visual Inspector
Section 2 / Slide No : *
8 9 10 11 12 1 2 3 4 5 6
Sales Officer
Sales Manager
Store Supervisor
QA Clerk
Issue D.I.
Pick Lots
Prepare Shipments
Approve Test Cert
Section 2 / Slide No : *
QA Manager
Sales Office
Store Office
Visual Inspection
Quantity Accepted
Section 2 / Slide No : *
Analyze: Investigate Root Causes
Examine the ‘As-Is’ Process
Examples of process flaws:
Section 2 / Slide No : *
Analysis Summary
A] Waiting
- Visual inspection will not start unless laboratory tests have
been completed.
- Store supervisor waits for the test certificates before he can
prepare the shipment.
B] Duplications
- Packers record product names, lot numbers and quantities and send
these information to store. Store supervisor keys in the same
information into the finished goods inventory system.
C] Non-value Adding Activities
Section 2 / Slide No : *
Improve: Find Effective Solutions
B] Reduce non-value adding activities & duplications.
Packers key in product information into finished goods inventory
system.
Reduce document movements by installing a computerized workflow
system.
Empower QA technicians to decide lot acceptance based on the
specification.
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
A useful guide for redesigning work processes:
Organize work around results, not tasks.
Work parallel instead of sequentially.
Capture data only one time – when it is first created.
Allow decision where the work is performed.
Incorporate controls into information processing.
Make people who use a process do the work.
Treat geographical dispersed resources as one.
© Copyright Pera Neville Clarke Pte Ltd, 2004 Issue :
1.0/09-04
Section 2 / Slide No : *
Computerized workflow system.
Section 2 / Slide No : *
Control: Sustain the Improvement
Implement the ‘should-be’ process
8 9 10 11 12 1 2 3 4 5 6
QA Technician
Visual Inspector
Prepare Shipment
Deliver Shipment
Approve D.O.
Possible CausesIreneMaryJohnPeterAdelineScore
12Relationship With CustomersX1