Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
SEATTLE CITY LIGHT DISTRIBUTION
AUTOMATION Ryan Pham
Project manager
01/27/2016
| 2 | 2
AGENDA
1. Distribution automation background
2. Seattle City Light pilot project
3. System performance – windstorm 08/29/15
4. Lessons learned
| 3 | 3
FAULT LOCATION, ISOLATION AND SERVICE
RESTORATION (FLISR) SYSTEM
• Self-healing grid
• Distribution Automaton
| 4 | 4
RESTORATION TIME LINE WITH AND WITHOUT DA
00:00
00:00 00:50 04:50FAULTOCCURS
Fault LocatedFeeder Back
To Normal
FAULTOCCURS
Without DA
With DA
00:00 - 00:30
00:00 - 00:05
15-30 minutesCrews Travel Time
00:00 - 00:30
15-30 minutes
Travel Time
00:30 - 00:5110-15 minutes Patrol Time
00:30 - 01:01
01:01 - 02:01
02:01 - 06:0115-30 minutes
Fault Investigation& Patrol Time
00:51 - 04:49
Repair Time1-4 hours
Repair Time
01:01Fault Located 02:02POWER
RESTORED TO CUSTOMERS ON
HEALTHY SECTIONS
OF FEEDER
1-4 hours
Repair Time
06:02Feeder Back
To Normal
00:05POWER RESTORED TO
CUSTOMERS ON HEALTHY SECTIONS
OF FEEDER
<5 minutes
20-60 minutesTime to Perform Manual Switching
Power restored to 40%-80% customers in 50-120 minutesPower restored remaining customers in 1-4hours later
Power restored to 50%-90% customers within 5 minutes(Seattle City Light scheme: within 30 seconds)
Power restored to remaining customers in 30-75 minutes earlier than non-DA feeders.
| 5 | 5
1 1 1 1 1
1
1 1 1 1 1
1
1
SW 52 SW 1189 SW 1751 SW 2303 SW 487
SW 597 SW 1092 SW 936
SW 2297 SW 1583 SW 1814 SW 536 SW 1685
1
SW 607
Shoreline Substation
Feeder
Breaker
2705
Feeder
Breaker
2703
Event: System Normal
| 6 | 6
1 1 1 1 1
1
1 1 1 1 1
1
1
SW 52 SW 1189 SW 1751 SW 2303 SW 487
SW 597 SW 1092 SW 936
SW 2297 SW 1583 SW 1814 SW 536 SW 1685
1
SW 607
Shoreline Substation
Feeder
Breaker
2705
Feeder
Breaker
2703
Time : 0 Seconds Event: Fault appear-
FDR BKR Trip
| 7 | 7
1 1 1 1 1
1
1 1 1 1 1
1
1
SW 52 SW 1189 SW 1751 SW 2303 SW 487
SW 597 SW 1092 SW 936
SW 2297 SW 1583 SW 1814 SW 536 SW 1685
1
SW 607
Shoreline Substation
Feeder
Breaker
2705
Feeder
Breaker
2703
Time : 4 Seconds Event: FDR BKR
Reclose Attempt #1
Fault Still
Present
| 8 | 8
1 1 1 1 1
1
1 1 1 1 1
1
1
SW 52 SW 1189 SW 1751 SW 2303 SW 487
SW 597 SW 1092 SW 936
SW 2297 SW 1583 SW 1814 SW 536 SW 1685
1
SW 607
Shoreline Substation
Feeder
Breaker
2705
Feeder
Breaker
2703
Time : 4 Seconds Event: FDR BKR Trip
| 9 | 9
1 1 1 1 1
1
1 1 1 1 1
1
1
SW 52 SW 1189 SW 1751 SW 2303 SW 487
SW 597 SW 1092 SW 936
SW 2297 SW 1583 SW 1814 SW 536 SW 1685
1
SW 607
Shoreline Substation
Feeder
Breaker
2705
Feeder
Breaker
2703
Time : 19 Seconds Event: FDR BKR
Reclose Attempt #2
Fault Still
Present
| 10 | 10
Time : 19 Seconds Event: FDR BKR Trip
1 1 1 1 1
1
1 1 1 1 1
1
1
SW 52 SW 1189 SW 1751 SW 2303 SW 487
SW 597 SW 1092 SW 936
SW 2297 SW 1583 SW 1814 SW 536 SW 1685
1
SW 607
Shoreline Substation
Feeder
Breaker
2705
Feeder
Breaker
2703
| 11 | 11
1 1 1 1 1
1
1 1 1 1 1
1
1
SW 52 SW 1189 SW 1751 SW 2303 SW 487
SW 597 SW 1092 SW 936
SW 2297 SW 1583 SW 1814 SW 536 SW 1685
1
SW 607
Shoreline Substation
Feeder
Breaker
2705
Feeder
Breaker
2703
Time : 25 Seconds Event: SW 52 Trip
Fault Isolated
| 12 | 12
1 1 1 1 1
1
1 1 1 1 1
1
1
SW 52 SW 1189 SW 1751 SW 2303 SW 487
SW 597 SW 1092 SW 936
SW 2297 SW 1583 SW 1814 SW 536 SW 1685
1
SW 607
Shoreline Substation
Feeder
Breaker
2705
Feeder
Breaker
2703
Time : 30 Seconds Event: Close tie SW,
restore power
Close tie switch
| 13 | 13
DA- TWO BIG QUESTIONS:
• DA Intelligence Style
• Communication option
| 14 | 14
CENTRALIZED VS SUBSTATION CENTERED VS
DISTRIBUTED INTELLIGENCE - 1
• Centralized intelligence
o Distribution Management System (DMS) serves as the “brain” of the
DA system
o Full system view for restoration, optimize the restoration in the
large scale.
o Integrate with other system and applications.
o Cons:
• Longest deployment time
• Integration with DMS, fine-tuning, are time-consuming
• Expensive
• Slowest restoration times
• A point-to-multi-point system can be overwhelmed.
| 15 | 15
CENTRALIZED VS SUBSTATION CENTERED VS
DISTRIBUTED INTELLIGENCE - 2
• Substation centered intelligence
o Use main logic controls at the distribution substations
o Pros and Cons are somewhere between Centralized and Distributed
| 16 | 16
CENTRALIZED VS SUBSTATION CENTERED VS
DISTRIBUTED INTELLIGENCE - 3
• Distributed intelligence
o Peer-to-Peer Devices
o Fastest restoration
o Fastest to deploy
o Able to be deployed with or without DMS or GIS.
o Cons:
• Less efficient in large scale restoration optimization
| 17 | 17
COMMUNICATION
•Main Criteria:
oCapacity & latency
oReliability
oCost
oSecurity
oTraffic types & networking standards
oReputation
oCoverage
oOther Smart Grids usage
| 18 | 18
COMMUNICATION OPTIONS FOR DA
• Fiber
oWide bandwidth, fast, secure, reliable, well-
established technology, lot of rooms for future
growth, applications and for other Smart grid
projects
o Expensive
• Radio
oLeast expensive
| 19 | 19
DA PILOT SYSTEM OVERVIEW
• Deployed on two feeders out of Shoreline substation: 2703 and
2705 at Shoreline & Lake Forest Park
• Utilizing distributed intelligence
• S&C ScadaMate switches
• Communication: fiber optics loop
• Integrated with EMS, PI historian
• Fully automated, supervisory and remote control
• Fast, secured remote access for relay technicians
• Online since 6:30 am 06/27/2015
| 20 | 20
DA PILOT SYSTEM – GOOGLE EARTH MAP
| 21 | 21
SIMPLIFIED NETWORK DIAGRAM
2703
2705
EMS
Relay Room
Backbone Fiber
Shoreline Substation
| 22 | 22
SHORELINE DA NETWORK DIAGRAM
| 23 | 23
LOOP COMMUNICATION FAULT RECOVER
• IEEE 802.1D Spanning Tree Protocol (STP)
oFault recovery time is too slow ~ one minute
• IEEE 802.1w Rapid Spanning Tree Protocol (RSTP)
oFaster than STP, but still low for our scheme ~ few
seconds
• Vendors’ proprietary protocols
• Siemens’ enhanced RSTP
oFast recovery time: in ms
• Interoperability
| 24 | 24
TEST LAB – DA BLOCK DIAGRAM
Router
Test EMS
RTAC
Test Lab DA block diagram with 3 controllers
DIGITerminalserver
KEY
Ethernet
Serial
J-MUX
J-MUX
EthernetSW
fiber
SOC
NSC Com lab
EthernetSW
EthernetSW
EthernetSW
| 25 | 25
STANDARDIZATION
• Allows to program and configure devices in an
efficient manner with minimal errors
• Familiarity from job to job for engineers,
constructions crews, communication and relay
technicians
• Reduce debugging time.
• IP, DNP, Modbus, point lists
•Naming convention
• Equipment, constructions.
| 26 | 26
| 27 | 27
| 28 | 28
| 29 | 29
NEW DESIGN SCADAMATE SWITCH WITH
GROUND LEVEL DISCONNECT HANDLE
| 30 | 30
GROUND LEVEL DISCONNECT HANDLE
| 31 | 31
SUMMER STORM 08/29/2015
• http://cliffmass.blogspot.com/2015/08/the-
strongest-summer-storm-in-northwest.htm
• The Strongest Summer Storm In Northwest
History
• Saturday was a historic day during a historic
summer.
On that day western Oregon and Washington was
lashed by the strongest summer windstorm in
its historic record.
• l
| 32 | 32
WINDSTORM 08/29/2015 WIND SPEED
| 33 | 33
DA System Response:
Isolated affected
sections, and shifted
unaffected load on
FDR2705 to FDR2703.
DA System Response:
Isolated affected
sections, kept power
service to other
segments.
WINDSTORM DIAGNOSTIC OVERVIEW
• The DA system handled four different storm contingencies and executed logic to mitigate as many
customer outages as possible.
• In both automatic and manual modes, the system functioned properly.
Event 1: Two faults
appeared on
FDR2705.
Automatic Mode
Manual Mode
Event 2: Two new
faults
appeared on
FDR2703.
Event 3: Fault near
substation,
FDR2703 is
lost.
Event 4: Dispatcher
located new
fault while
restoring
FDR2705.
DA System Response:
No available source to
route power. Do not
attempt to close.
5m 32m
DA System Response:
Dispatcher remotely
isolated fault, restored
power to 80% of total
customers on FDR2705.
| 34 | 34
08/2015 WINDSTORM
Diagnostics
System Normal
| 35 | 35
Diagnostics
Fault between
SW2303 and SW487.
Fault between
Feeder Breaker 2705,
SW52, and SW936.
Feeder Breaker 2705
opened.
8/29/15, 12:27pm
08/2015 WINDSTORM
Event 1: Faults Appear On System
| 36 | 36
Team 2303-487
isolated the fault.
Team 2705-52-936
isolated the fault.
Diagnostics
08/2015 WINDSTORM
Event 1 (cont.): DA System Isolates The Faults
| 37 | 37
808
Customers
1001
Customers
323
Customers
351
Customers
SW1092 closed to
transfer power from
Feeder 2703.
SW597 closed to
transfer power from
Feeder 2703.
>DA System Alert:
2483/3869 customers
successfully restored
on Feeder 2705.
Diagnostics
08/2015 WINDSTORM
Event 1 (cont.): DA System Transfers Power
| 38 | 38
Fault between
SW1189, SW1092,
SW1751.
Feeder Breaker 2703
opened.
8/29/15, 12:32pm
Fault between SW536
and SW1685.
Diagnostics
08/2015 WINDSTORM
Event 2: Faults Appear On System
| 39 | 39
Team 1092-1189-1751
isolated the fault.
Team 1685-536
isolated the fault.
Diagnostics
08/2015 WINDSTORM
Event 2 (cont.): DA System Isolates The Faults
| 40 | 40
266
Customers
Feeder Breaker 2703
closed and restored
power.
>DA System Alert:
1817/3148 customers
successfully restored on
Feeder 2703.
115
Customers
74
Customers
255
Customers
Diagnostics
08/2015 WINDSTORM
Event 2 (cont.): Power is restored
1107
Customers
| 41 | 41
Fault between
Feeder Breaker 2703
and SW607.
Feeder Breaker 2703
opened.
8/29/15, 01:04pm
>ALERT:
115 KV line fell onto
26 KV line.
Diagnostics
08/2015 WINDSTORM
Event 3: Fault Appears On System
>DA System Alert:
No available power
sources to reroute.
| 42 | 42
08/2015 WINDSTORM
Event 4: Crews Work On Restoring Feeder 2705
Diagnostics
| 43 | 43
Fault between SW487
and SW597.
08/2015 WINDSTORM
Event 4 (cont.): Fault Appears On System
Remote Action:
Dispatcher has sent
remote command to
close SW487.
Diagnostics 8/30/15, 12:34pm
| 44 | 44
1001
Customers
323
Customers
351
Customers
Feeder Breaker 2705
closed and restored
power.
>DA System Alert:
3061/3869 customers
successfully restored on
Feeder 2705.
983
Customers
403
Customers
08/2015 WINDSTORM
Event 4 (cont.): Feeder 2705 is successfully
restored
Diagnostics
| 45 | 45
WINDSTORM 8/29/15 –
DISTRIBUTION AUTOMATION (DA) SYSTEM PERFORMANCE
3869
3148
3869
1386 1331
808
0
500
1000
1500
2000
2500
3000
3500
4000
4500
Event 1 - Feeder 2705 Event 2 - Feeder 2703 Event 4 - Feeder 2705
Number of
outage
customers
Customer Outage Analysis
Without DA With DA
Assuming the event 3 which involved 115 kV outage had not occurred
| 46 | 46
WINDSTORM 8/29/15
5,598,443
7,901,480
299,204
2,005,542
3,340,810
115,544
0
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
8,000,000
9,000,000
Event 1 - feeder 2705 Event 2 - feeder 2703 Event 4 - feeder 2705
Outage
customer
minutes
Outage Customer Minutes Analysis
Without DA With DA
Assuming the event 3 which involved 115 kV outage had not occurred
| 47 | 47
LESSONS LEARNED
• A lab, even small one, is critical for testing, troubleshooting and
training.
• Fiber optics loop was intact throughout the serve storm
• The fast, secure remote access greatly reduce crew times for event
data retrieval and configuration update
• Secure WIFI is a nice feature, reduce operation cost, and enhanced
crew safety
• The system performed as intended. The Distribution Automation
scheme identified, isolated, and rerouted after the faults appeared.
• Dispatchers were able to identify and send line crews to fix affected
line segments faster than conventional methods.
QUESTIONS? THANK YOU