Schematic Design-Cheyenne Regional Airport

Embed Size (px)

DESCRIPTION

Schematic Design summary of Cheyenne Regional Airport

Citation preview

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    1/33

    Schematic Design SummaryCheyenne Regional Airport09 February 2011

    Report prepared by Architectural Alliance International, Inc

    EXPE

    COMM

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    2/33

    Schematic Design SCheyenne Region

    09 Febru

    Table of Contents

    1. Executive Summary

    2. Sense of Place

    . Sense of Place Design Process

    . Cheyenne Sense of Place Research

    . Architectural Design Research

    3. Design Process

    . Workshop 1

    . Workshop 2

    . Workshop 3

    4. Schematic Design

    . Building Plans

    . Room Schedule by Department

    . Exterior Elevations

    . Building sections

    . Building Renderings

    . Interior Material and Color Palette

    5. Site Design

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    3/33

    Schematic Design SCheyenne Region

    09 Febru

    1. Executive Summa

    Executive Summary1.00

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    4/33

    Schematic Design SCheyenne Region

    09 Febru

    Executive Summary

    From September 2010 through February 2011, SEH and Architectural

    Alliance International were engaged by the Cheyenne Regional Airport to

    develop a schematic design option for a potential new terminal.

    The basis of this design was the 10 March 2008 Cheyenne Regional

    Airport Terminal Feasibility Study, which studied projected future demand

    to determine the appropriate size and scope of a future terminal. The

    Feasibility Study projected annual enplanements to reach 28,900 by

    the year 2027. In addition, the Feasibility Study examined a number of

    potential locations for the future terminal, including redevelopment of the

    existing terminal site as well new potential sites. The Feasibility Study

    recommended Site 3A, located due East of the existing terminal site,

    accessed from the redeveloped Airport Parkway. A Conceptual Design was

    proposed as part of the Feasibility Study.

    The Schematic Design effort took the recommendation of Site 3A and

    the programming and Conceptual Design work of the Feasibility Study as

    a launching point. The Schematic Design addresses operational needs

    for the airlines and passenger service improvements such as adequate

    gate hold seating, pre-security waiting areas, security checkpoint layoutscapable of handling current and potential future needs, mechanical and

    electrical system upgrades, more easily maintainable and aesthetically

    pleasing finishes, and a strong design presence for the terminal as a

    representation of the city of Cheyenne and its surrounding region.

    Desired capacity was based upon service of two simultaneous Regional

    Jet departures in regularly scheduled domestic passenger traffic (60 seats

    per aircraft for a total of 120 seat gate hold capacity). This capacity was

    further supported by the potential to service narrow body jets in charter

    operations and the potential to handle diverted flights from Denver.

    Executive Summary1.01

    Working from the Conceptual Design solution, the preferred Schema

    Design was developed through a series of Design Workshops with th

    full Airport Board and additional meetings with Airport Staff. Throug

    refinements based both on current conditions and reassessments o

    previous decisions, a revised program was reached to better meet lo

    term facility needs. After three workshops, Scheme 2C was selected

    by the Airport Board as the preferred alternative. A two-level facility

    (with additional partial basement) and accommodations for significa

    concession space is proposed, with accommodations for additional

    future expansion. The proposed Schematic Design totals 36,000 sf.

    compares to 30,400 sf in the Feasibility Study program document, an

    35,000 sf in the Conceptual Design.

    Probable construction costs for the terminal building are projected to

    $297 per square foot, for a total construction cost of $10,700,000. (

    Connico Preliminary Rough Order of Magnitude Estimate, provided u

    separate cover, for detailed information regarding terminal project c

    Probable construction costs have been estimated at $3,200,000 for

    new parking lot and related access improvements and $2,500,000 fo

    new apron. (See SEH supporting documents, provided under separcover, for detailed information regarding site work costs.) Together,

    probable construction costs for the new terminal and site work are

    estimated at a total of $16,400,000. Probable construction costs do

    include design fees.

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    5/33

    Schematic Design SCheyenne Region

    09 Febru

    2. Sense of Plac

    Sense of Place2.00

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    6/33

    Schematic Design SCheyenne Region

    09 Febru

    Sense of Place Design Process

    VISION AND SENSE OF PLACE

    A communitys airport plays an important role in communicating the

    regions image to the rest of the world. The airport is the gateway to

    region for a great number of visitors each year and the first and last t

    travelers see. It is also the place that welcomes home residents of th

    Cheyenne region, and it should be a great source of pride. An overa

    coordinated vision benefits the long-term and incremental growth of

    airport facilities and helps unite planning and design efforts over ma

    years.

    Developed concurrently with the terminals programming an d early

    building and site design, Sense of Place research was conducted t

    inform how the design relates to the site, as well as inspire the build

    forms and materials.

    Sense of Place Boards

    Anchorage, AlaskaMemphis , Tennessee

    Examples of Sense of Placeintegration

    Sense of Place Boards

    Examples of Sense of Placeintegration

    Sense of Place2.01

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    7/33

    Schematic Design SCheyenne Region

    09 Febru

    Sense of Place2.02

    Cheyenne Sense of Place Research

    Referred to as The Magic City of the Plains Cheyenne, the capital o

    ming, is the gateway to natural wonders, relics of the frontier, and ou

    recreation. Research was conducted to identify historical, cultural a

    physical attributes important to the city and region resulting in a co

    tion of representative imagery ranging from industry, architecture, to

    raphy and cultural influences. The goal of this task was to determin

    most appropriate and meaningful imagery that best conveys the sp

    Cheyenne.

    Key Findings:

    A Junction of Railroads- influencing history (first transcontin

    railroad) industry, and culture

    Topography/Landscape - unique landforms , arid plains, an

    wildlife

    Architecture - style, material, and form

    Culture/Heritage - western frontier and cowboy heritage

    The development of an all-encompassing design concept relating to

    certain physical or cultural aspects of the area can contribute greatly

    making the airport experience an inviting and memorable one. Fromregions unique topography and landscape to its frontier heritage an

    deeply rooted western culture, it offers a vast breadth from which to

    inspiration that embodies the most unique aspects of Cheyenne and

    region.

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    8/33

    Schematic Design SCheyenne Region

    09 Febru

    Sense of Place2.03

    Cheyenne Sense of Place Research

    Topography and Landscape

    The topography and unique landscape of endless horizons, vast pla

    and outcropping landforms inspired the development of a color an

    material palette reflective of Cheyenne and the surrounding region.

    Important man made elements also characteristic of the landscape w

    used to inform pattern, texture and form. Railroad tracks create a un

    and linear rhythm and pattern cutting through the landscape while s

    fences follow the contours of the landscape creating weathered visu

    texture and unique shadows . All of these elements contribute to a d

    that is rich with sense of place and meaningful to Cheyenne.

    Western Icon

    Cheyennes deep western frontier heritage is an important part of th

    citys past and present. There is strong iconic and identifiable image

    associated with the cowboy and the cowboy culture. The craftsmans

    and design associated with saddles, cowboy boots, and western gea

    very artistic and beautiful. The tooled and embossed leathers, the s

    accents and the filigree patterns can all inspire materials , colors an

    patterns for the interior design.

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    9/33

    Schematic Design SCheyenne Region

    09 Febru

    Architectural Design Research

    At the beginning of Schematic Design, A rchitectural Alliance Internat

    researched the unique qualities of the City of Cheyenne, its history, c

    ture, and its relationship to the natural surroundings. Four main con

    were identified, which in turn informed the main concepts for the de

    the terminal building:

    Context

    Both the local context of the immediate site and the larger context o

    City of Cheyenne and the Upper Great Plains were carefully studied.

    the natural context, weve identified the regional weather, the prevai

    ing NW winds, and the strong solar orientation as important element

    Moreover, man-made structures like the snow fences and the railroa

    well as the vernacular buildings became a source of inspiration for p

    the design.

    Porch

    The concept of a porch can be found at both regional vernacular buil

    and more contemporary designs, and functionally relates to the tran

    tional space between the inside and the outside of the building. Exp

    entially, a porch functions as the front door for arriving and depart

    passengers.

    Screen

    Screens are architectural elements used to modulate and filter sun l

    control winds, and filter or screen views. Inspired by the local snow f

    and railroad cattle cars, these screens also have the potential of intr

    ing dynamic and controlled patterns of shadow and light into the bu

    Sustainability

    With the belief that every buiding design is a careful response to its

    and cultural sites, the schematic design represents an energy efficie

    building that implements the sustainable strategies of daylighting, w

    efficiency, use of local and renewable materials, and highly efficient

    chanical systems among others.

    Context

    Porch

    Screen

    Sustainability

    Sense of Place2.05

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    10/33

    Schematic Design SCheyenne Region

    09 Febru

    3. Design Proces

    Design Process3.00

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    11/33

    Schematic Design SCheyenne Region

    09 Febru

    Program Refinement

    During the course of the workshops with Airport Staff and the Airport

    Board, a number of changes were made to programming assumptions

    developed during the 2008 Feasibility Study. These changes were driven

    by changes in current conditions and reassessments of previous decisions.

    Among the critical changes that impacted the Schematic Design:

    Restaurant Size, Location, and Scope

    The Feasibility Study assumed a large, signature restaurant and bar lo-

    cated on the second floor of the terminal that would be directed primarily

    at Cheyenne residents rather than passengers. Based on the financial

    difficulties of the existing restaurant at the current terminal, the recent

    expansion of restaurant offerings within Cheyenne, and the significant in-

    vestment involved in a large restaurant, the Board ultimately decided that

    a smaller restaurant with more limited offerings, located to serve primarily

    passengers would be more appropriate.

    Multi-story Building

    The Level Two program in the Conceptual Design was dominated by the

    restaurant component, and when this was relocated, there was a question

    as to whether or not the building should remain a multi-story building. The

    Board determined that the multi-story building was still justified because

    the cost difference was determined to be insignificant, the second story

    gave the building additional presence on the site, it programmatically

    made sense to separate the administrative functions, and because of the

    efficiencies allowed by the partial basement.

    Gate Hold and Security

    The Gate Hold area was increased from a capacity of 60 in the Feasibility

    Study to 120 in Schematic Design to allow it to accommodate two simul-

    taneous regional jet departures (the ability to accommodate narrow-body

    jets and to handle diverted planes from Denver was also a factor in this

    decision). The Security Checkpoint was enlarged to allow it to accommo-

    date the latest TSA requirements.

    Additional Concession Space

    The Board directed that additional concession space (beyond the res

    rant) should be included as part of the Schematic Design. These ten

    spaces may not be strictly driven by passenger traffic, so the spaces

    located at the east end of the terminal, where they are adjacent to th

    short term parking lot. This location also allows for the spaces to be

    repurposed for future terminal expansion. Further, this location wou

    allow the concession space to be modified or eliminated during futu

    design phases without significantly impacting the terminal layout. T

    current layout shows three spaces totaling approximately 500 sf each

    capable of accommodating office or small retail tenants.

    Airline Ticket Offices

    Based on the success of the recently instituted American Eagle servi

    DFW, the Board directed that the Schematic Design should a ccommo

    three full Airline Ticket Offices in addition to a dedicated TSA space.

    Conceptual Design had shown TSA occupying a future ATO space, bu

    would have required TSA to relocate should a third Airline be recruite

    and left no swing space for charter operations.

    Design Process3.01

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    12/33

    Schematic Design SCheyenne Region

    09 Febru

    Workshop 1

    Workshop 1 was held on 27 September 2010 at the offices of the Che

    Regional Airport. Present were representatives of Architectural Allia

    International, SEH, Airport Director David Haring, and Airport Staff.

    The Feasibility Study was validated, especially relative to changes in

    airport operations driven by the addition of American Eagle service a

    closure of the existing restaurant.

    The design process was explained, and examples of previous project

    were shown.

    Results of initial Sense of Place and Architectural Design Research w

    presented.

    Sustainability was identified as an important consideration, especia

    to the extent that careful building design, orientation, and selection

    appropriate building systems could reduce long-term operating cost

    Design Process3.02

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    13/33

    Schematic Design SCheyenne Region

    09 Febru

    Four plans were presented that demonstrated options for the restau

    within the new terminal.

    Schemes 1A and 1B are both one level schemes. Scheme 1A locates

    restaurant adjacent to the Gate Hold for easy passenger access. Sch

    1B locates the restaurant to the west, for adjacencies to the Loading and Short Term Parking and ease of after-hours access.

    Design Process3.03

    Floor Plan Scheme 1B

    Floor Plan Scheme 1A

    Workshop 2

    Workshop 2 was held on 10 November 2010 at the offices of the Cheyenne

    Regional Airport as a part of the regularly scheduled Airport Board meeting.

    Present were representatives of Architectural Alliance International, SEH,

    Airport Director David Haring, and the Airport Board.

    The Sense of Place and Architectural Design Research was presented to the

    Airport Board.

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    14/33

    Schematic Design SCheyenne Region

    09 Febru

    Design Process3.04

    Sketches were presented demonstrating both a two level option and

    level option with a high-roofed volume over the public spaces.

    The Airport Board selected Scheme 2A as their preferred option,

    demonstrating strong support for a two level option. There was, how

    some concern about whether the terminal could support a large, sign

    restaurant. They requested another alternative be prepared demons

    a smaller scale restaurant located on Level One, but still retaining

    administrative functions on Level Two.

    Concept Sketches

    Floor Plan Scheme 2BFloor Plan Scheme 2A

    Workshop 2

    Schemes 2A and 2B are both two level schemes. Unlike the Conceptual

    Design, which show the two level massing located to the East, these

    schemes shift the two level massing to the West, still retaining a generous

    double-height space at the Arrivals and Departures Hall and the Gate

    Hold space. Both show a large, signature Restaurant space located at the

    Northwest of the terminal to maximize views to the airfield. Scheme 2A

    shows the Security Checkpoint oriented East-West, whereas Scheme 2B

    shows it oriented North-South.

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    15/33

    Schematic Design SCheyenne Region

    09 Febru

    Design Process3.05

    Scheme 2C is an alternative showing a smaller restaurant located im

    ately to the west of the Gate Hold space, but still retaining an upper

    for the administrative functions and public viewing space. Scheme 2

    the advantage of offering better service for passengers, while still m

    taining strong views to the airfield.

    Scheme 2C was ultimately selected by the Airport Board.

    Workshop 3

    Workshop 3 was held on 08 December 2010 at the offices of the Cheyenne

    Regional Airport as a part of the regularly scheduled Airport Board meet-

    ing. Present were representatives of Architectural Alliance International,

    SEH, Airport Director David Haring, and the Airport Board.

    As requested by the Board at the previous workshop, two schemes were

    presented. Scheme 2A is a refinement of the preferred plan presented

    at the previous meeting with a large, signature restaurant located in the

    northwest corner of Level Two.

    Floor Plan Scheme 2CFloor Plan Scheme 2A

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    16/33

    Schematic Design SCheyenne Region

    09 Febru

    Workshop 3

    Interior renderings were presented, showing how the public spaces

    terminal are impacted by the changes between the 2A and 2C schem

    Design Process3.06

    SCHEME 2CSCHEME 2A

    SECTION

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    17/33

    Schematic Design SCheyenne Region

    09 Febru

    Design Process3.07

    Workshop 3

    Two alternate exterior expressions were presented. Both options sh

    curbside faade dominated by glazing with vestibules projecting thro

    the faade, and both are anchored by large stone or concrete panels

    Option 1 utilizes a random patterned metal screening element along

    the upper stories, used to moderate the solar exposure into the spa

    Option 2 shows a more consistent upper faade of metal panels,

    interrupted by large glass openings crowned by projecting roof forms

    which act to shield the sun.

    The options demonstrate two possible treatments of a curbside cano

    one a solid projecting element and the other made up of glass and s

    The Board preferred Option 2, but expressed some concern that the

    was still too heavy or boxy, and further expressed concern about the

    building being dominated by flat roofs. This concern was addressed

    subsequent refinements of the final Schematic Design.

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    18/33

    Schematic Design SCheyenne Region

    09 Febru

    4. Schematic Desig

    Schematic Design4.00

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    19/33

    Schematic Design SCheyenne Region

    09 Febru

    UP

    DN

    UP

    DN

    2754 S F

    Gat e H o l d44

    1457 S F

    P as s enger S c reen i ng

    61

    3307 S F

    D epar t u re / A r r i v a l H a l l

    62

    3116 S F

    B aggage C l a i m

    64

    629SF

    DeplaningCorridor

    65

    n ri

    r i n

    li

    n i n

    i l i n m

    152 S F

    V es t i bu l e

    2

    524 S F

    B aggage

    3

    429 S F

    D oc k / R ec e i v i ng

    9

    152 S F

    V es t i bu l e

    16

    266 S F

    K i t c hen17

    1

    157 S F

    Lobby

    21

    68 SF

    V es t i bu l e22

    981 S F

    R es t au ran t

    26

    63 SF

    M on i t o r

    31

    69 S F

    S c reen i ng

    32109 S F

    V end i ng

    33

    73 SF

    V es t i bu l e

    35 50 S F

    Gat e 1

    41

    50 S F

    Gat e 2

    42

    31 SF

    Jan

    43

    95 S F

    U n i s ex

    50

    305 S F

    Men

    51

    305 S F

    W om en

    52

    160 S F

    R en t a l C ar

    53

    160 S F

    R en t a l C ar

    55

    161 S F

    R en t a l C ar

    59

    160 S F

    R en t a l C ar

    66

    322 S F

    ATO

    68

    322 S F

    ATO

    69

    322 S F

    ATO

    70

    323 S F

    T S A B ag S c reen i ng

    71

    487 S F

    TSA Office72

    2128 S F

    B aggage M ak e-U p

    73

    2723 S F

    T i c k e t i ng H a l l63

    361 S F

    Circ

    74

    454 S F

    C onc es s i ons

    75

    502 S F

    C onc es s i ons

    76

    529 S F

    C onc es s i ons

    77

    92 SF

    V es t i bu l e

    79

    54 SF

    Toilet

    80

    54 SF

    Toilet

    8141 S F

    Jan

    82

    JIHGFCBA K L M N O Q R S

    4

    55

    6

    2

    33

    0.9 1

    1

    D.5

    1'-6"

    27

    '-0"

    28'-0"

    10'-0"

    20'-0"

    10'-0"

    20' -0" 20' - 0" 30' - 0" 30' - 0" 20' - 0" 20' -0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 30' - 0" 20' - 0" 20' - 0"

    FUTURE

    GATEHOLD

    EXPANSION

    FUTURE

    EXPANSION

    1.8

    32'-0"

    23'-0"

    30'-0"

    597 S F

    C onc es s i on C i rc u l a t i on

    97

    DN

    DN

    663 SF

    Conf Room10

    li

    i

    i l i n m

    708 SF

    Upper Gallery

    15

    69 SF

    Lobby23

    230 SF

    Stair 224

    O PEN T O BELO W

    O PEN T O BELO W641 SF

    Break-Out36

    ROOF

    O PEN T O BELO W

    67 SF

    Buffet84

    83 SF

    Toilet85

    JIHGFCBA K L M N O Q R S

    4

    5

    6

    2

    33

    0.9 1

    1

    43 SF

    Jan86

    46 SF

    Storage87

    D.5

    1'-6"

    27'-0"

    28'-0"

    10'-0"

    20'-0"

    10'-0"

    20' -0" 20' -0" 30' -0" 30' -0" 20' -0" 20' - 0" 20' -0" 20' - 0" 20' -0" 20' - 0"

    187 SF

    Kitchen88

    139 SF

    Office

    89118 SF

    Office90

    118 SF

    Office91

    314 SF

    Director92

    157 SF

    Admin Storage93 582 SF

    Reception / Circ94

    72 SF

    Intern95

    64 SF

    Copy96

    1.8

    32'-

    0"

    23'-0"

    1095 SF

    Circ99

    UP

    UP

    1368 SF

    Mechanical Room37

    n i n

    i l i n m

    520 SF

    Concession Storage38

    1719 SF

    Utility Tunnel39

    1306 SF

    Storm Refuge83

    JIHGFCBA K L M N O Q R S

    4

    55

    6

    2

    33

    0.9

    1

    D.5

    1'-6"

    27'-

    0"

    28'-0"

    10'-0"

    20'-0"

    10'-0"

    20' - 0" 20' - 0" 30' - 0" 30' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 30' - 0" 20' - 0" 20' - 0"

    1.8

    23'-0"

    30'-

    0"

    359 SF

    Storage98

    level 2

    level 1

    lower level

    Plan Description

    Level One, 25,300 sf

    The Schematic Design proposes a facility with primary public and airport

    operations on the ground level, with public access from two entrances

    along the curbside (one at Ticketing and one at Bag Claim) and additional

    entrances from both the East and West Short Term Parking Lots. The

    Ticketing Hall, Arrivals and Departures Hall, and Bag Claim together form agenerous public space that would be populated with welcoming soft seat-

    ing and a fireplace lounge for waiting passengers and the public.

    In the Ticketing Hall, the facility is designed to accommodate three Airline

    Ticket Offices (ATO) with adjacent Baggage Make-Up spaces. There is

    dedicated space for Transportation Security Administration (TSA) of-

    fices. The Security Checkpoint is designed to accommodate the latest

    TSA requirements and to provide flexibility f or future changes in security

    requirements. The Gate Hold contains seating for 120 and two departure

    gates with room for easy expansion to a third departure gate or the option

    to add a passenger boarding bridge. There is a fully separated Deplaning

    Corridor. The Bag Claim provides 50 linear feet of flat plate baggage claim

    area, with space to accommodate a future T shaped device to provide

    additional capacity.

    Located immediately adjacent to the Gate Hold, a Restaurant conces-

    sion space is open to the public but primarily oriented towards meeting

    the needs of flight passengers. The Restaurant and associated Kitchen

    totals 1250 sf. In addition to the Restaurant space, the Schematic Design

    accommodates three additional concession spaces at the east end of

    the terminal, totaling 1500 sf of leasable space and 600 sf of associated

    circulation space (this space is designed to be easily convertible to future

    Airline Ticket Offices should future passenger demand require it). There

    are also four Rental Car Offices provided, totaling 640 sf.

    Level Two, 5,400 sf

    A second floor over the west portion of the building would be served

    elevator and provide administrative space and a large Conference Ro

    capable of holding Airport Board meetings with public seating. Ther

    Upper Gallery providing views to the airfield and the Arrivals and Dep

    tures Hall for the general public and a Breakout Space with soft seatThe Administration area contains four office spaces and support fun

    including a Kitchen. The Kitchen, Upper Gallery, and Breakout Spac

    work in conjunction with the Conference Room to host public functio

    Lower Level, 5,300 sf

    A partial basement is designed for provision of Mechanical space an

    distribution to the upper floors through a Utility Tunnel. Storage spa

    provided both for the Airport and for concession users. Additional s

    provided for storm refuge of up to 260 people. As the design progre

    the exact extents of the partial basement will need to be determined

    on Mechanical and Storage needs (in concert with budget refinemen

    Schematic Design4.01

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    20/33

    Schematic Design SCheyenne Region

    09 Febru

    UP

    DN

    UP

    DN

    2754 SF

    Gate Hold44

    1457 SF

    Passenger Screening61

    3307 SF

    Depar ture / A r r i val Hal l62

    3116 SF

    Baggage Claim64

    629SF

    DeplaningCorridor

    65

    Gate Lob

    Operation

    Public Sp

    Concessio

    Building S

    152 SF

    Vesti bule2

    524 SF

    Baggage

    3

    429 SF

    Dock / Recei v i ng

    9

    152 SF

    Vesti bule

    16

    266 SF

    K i tchen17

    LEVEL 1

    157 SF

    Lobby21

    68 SF

    Vesti bule22

    981 SF

    Restaurant26

    63 SF

    Moni tor 31

    69 SF

    Screening32

    109 SF

    Vending33

    73 SF

    Vesti bule35 50 SF

    Gate 141

    50 SF

    Gate 242

    31 SF

    Jan43

    95 SF

    Unisex50

    305 SF

    Men51

    305 SF

    Women52

    160 SF

    Rental Car

    53160 SF

    Rental Car 55

    161 SF

    Rental Car 59

    160 SF

    Rental Car

    66

    0 32 48 64

    322 SF

    ATO

    68

    322 SF

    ATO

    69

    322 SF

    ATO

    70

    323 SF

    TSA Bag Screening71

    487 SF

    TSA Office72

    2128 SF

    Baggage Make-Up73

    2723 SF

    Ticketi ng Hal l63

    361 SF

    Ci rc

    74

    454 SF

    Concess ions75

    502 SF

    Concess ions76

    529 SF

    Concess ions77

    92 SF

    Vesti bule79

    54 SF

    Toi l et80

    54 SF

    Toi l et81

    41 SF

    Jan82

    JIHGFCBA K L M N O Q R S

    4

    55

    6

    2

    33

    0.9 1

    1

    D.5

    1'-6"

    27'-0"

    28'-0"

    10'-0"

    20'-0"

    10'-0"

    20' - 0" 20' - 0" 30' - 0" 30' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 30' - 0" 20' - 0" 20' - 0"

    FUTURE

    GATEHOLD

    EXPANSION

    FUTURE

    EXPANSION

    1.8

    32'-0"

    23'-0"

    30'-0"

    597 SF

    Concess ion Ci rculati on97

    Schematic Design4.02

    S h i D i S

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    21/33

    Schematic Design SCheyenne Region

    09 Febru

    DN

    DN

    663 SF

    Conf Room10

    Public Spa

    Offices

    Building Sy

    708 SF

    Upper Gal l ery

    15

    LEVEL 2

    69 SF

    Lobby

    23

    230 SF

    Stai r 224

    OPEN T O BEL OW

    OPEN T O BEL OW641 SF

    Break-Out36

    ROOF

    OPEN T O BEL OW

    67 SF

    Buffet

    84

    83 SF

    Toi l et

    85

    JIHGFCBA K L M N O Q R S

    4

    5

    6

    2

    33

    0.9 1

    1

    43 SF

    Jan86

    46 SF

    Storage87

    D.5

    0 32 48 64

    1'-6"

    27'-0"

    28'-0"

    10'-0"

    20'-0"

    10'-0"

    20' - 0" 20' - 0" 30' - 0" 30' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0"

    187 SF

    K i tchen

    88139 SF

    Office

    89118 SF

    Office90

    118 SF

    Office91

    314 SF

    Di rec tor 92

    157 SF

    Admin S torage93 582 SF

    Recepti on / Ci rc

    94

    72 SF

    Intern95

    64 SF

    Copy96

    1.8

    32'-0"

    23'-0"

    1095 SF

    Ci rc99

    Schematic Design4.03

    S h ti D i S

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    22/33

    Schematic Design SCheyenne Region

    09 Febru

    UP

    UP

    1368 SF

    Mechani cal Room37

    Concessions

    Building Systems

    520 SF

    Concess ion S torage

    38

    1719 SF

    Uti l i ty Tunnel39

    LOWER LEVEL

    1306 SF

    Storm Refuge

    83

    JIHGFCBA K L M N O Q R S

    4

    55

    6

    2

    33

    0.9

    1

    0 32 48 64

    D.5

    1'-6"

    27'-0"

    28'-0"

    10'-0"

    20'-0"

    10'-0"

    20' - 0" 20' - 0" 30' - 0" 30' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 30' - 0" 20' - 0" 20' - 0"

    1.8

    23'-0"

    30'-0"

    359 SF

    Storage98

    Schematic Design4.04

    Schematic Design S

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    23/33

    Schematic Design SCheyenne Region

    09 Febru

    Schematic Design4.05

    Operations

    Baggage Make-Up Level 1 2128 SF

    Baggage Level 1 524 SF

    TSA Office Level 1 487 SF

    Circ Level 1 361 SF

    TSA Bag Screening Level 1 323 SF

    ATO Level 1 322 SF

    ATO Level 1 322 SFATO Level 1 322 SF

    4790 SF

    Public Space

    Departure / Arrival Hall Level 1 3307 SF

    Baggage Claim Level 1 3116 SF

    Ticketing Hall Level 1 2723 SF

    Circ Level 2 1095 SF

    Upper Gallery Level 2 708 SF

    Break-Out Level 2 641 SF

    Concession Circulation Level 1 597 SF

    Men Level 1 305 SF

    Women Level 1 305 SF

    Stair 1 Level 1 230 SF

    Stair 2 Level 2 230 SF

    Lobby Level 1 157 SF

    Vestibule Level 1 152 SF

    Vestibule Level 1 152 SF

    Unisex Level 1 95 SF

    Vestibule Level 1 92 SF

    Toilet Level 2 83 SF

    Lobby Level 2 69 SF

    Vestibule Level 1 68 SF

    14126 SF35993 SF

    Building Systems

    Utility Tunnel Lower Level 1719 SF

    Mechanical Room Lower Level 1368 SF

    Storm Refuge Lower Level 1306 SF

    Dock / Receiving Level 1 429 SF

    Storage Lower Level 359 SF

    Jan Level 2 43 SF

    Jan Level 1 31 SF5255 SF

    Concessions

    Restaurant Level 1 981 SF

    Concessions Level 1 529 SF

    Concession Storage Lower Level 520 SF

    Concessions Level 1 502 SF

    Concessions Level 1 454 SF

    Kitchen Level 1 266 SF

    Rental Car Level 1 161 SF

    Rental Car Level 1 160 SF

    Rental Car Level 1 160 SF

    Rental Car Level 1 160 SF

    3893 SF

    Gate Lobby and Security

    Gate Hold Level 1 2754 SF

    Passenger Screening Level 1 1457 SF

    Deplaning Corridor Level 1 629 SF

    Vending Level 1 109 SF

    Vestibule Level 1 73 SF

    Screening Level 1 69 SF

    Monitor Level 1 63 SF

    Toilet Level 1 54 SFToilet Level 1 54 SF

    Gate 1 Level 1 50 SF

    Gate 2 Level 1 50 SF

    Jan Level 1 41 SF

    5403 SF

    Offices

    Conf Room Level 2 663 SF

    Reception / Circ Level 2 582 SF

    Director Level 2 314 SF

    Kitchen Level 2 187 SF

    Admin Storage Level 2 157 SF

    Office Level 2 139 SF

    Office Level 2 118 SF

    Office Level 2 118 SF

    Intern Level 2 72 SF

    Buffet Level 2 67 SF

    Copy Level 2 64 SF

    Storage Level 2 46 SF

    2526 SF

    Room Schedule

    Shows the Schematic Design building program broken out into the fo

    ing departments:

    Building Systems Mechanical and building support spaces

    Concessions Leasable spaces, including Restaurant, Rental Car Offiand other Tenant Spaces

    Gate Lobby and Security Gate Hold, Security Checkpoint, and asso

    support spaces

    Offices Administrative Offices, Conference Room, and support spa

    Operations Airline Ticket Offices, Baggage Make-Up, Baggage Claim

    support spaces

    Public Space Public gathering, circulation, and support spaces

    Schematic Design S

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    24/33

    Schematic Design SCheyenne Region

    09 Febru

    south elevation0 5 15 30 FT

    west elevation0 5 15 30 FT

    Building Elevations

    The Schematic Design proposal orients the curbside faade to appro

    mately due south, aligning it with the runway beyond. This orientati

    allows for favorable solar access, bringing in south light which can b

    modulated by sunscreening elements and deep overhangs, allowing

    more sun in the winter months when it is needed, and less in the sum

    months when it isnt.

    The south faade is grounded by light colored precast concrete pane

    the east end. These are envisioned to relate to the tones of the light

    stone that is found regionally, and will have texture and tones to enl

    them. At the ground level, there will be extensive glazing that is shie

    by the deep roadside canopy. The glazing will be penetrated by the t

    vestibules and the rental car offices, which are envisioned to be clad

    wood on both the interior and exterior.

    The building massing steps up to its m ulti-story massing, and at the west end is terminated by the stair and elevator tower, which is agai

    in the precast concrete panels.

    Schematic Design4.06

    Schematic Design S

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    25/33

    Schematic Design SCheyenne Region

    09 Febru

    north elevation0 5 15 30 FT

    east elevation0 5 15 30 FT

    Building Elevations

    The upper story of the terminal is clad in a mix of copper metal panelin select locations, large expanses of glazing that bring daylighting d

    into the space. These windows will be carefully located to take adva

    of views, and will be treated with sunscreening elements as their exp

    requires. Windows on the buildings north faade are able to bring i

    daylight without concern about heat gain or glare.

    The precast panels and metal panels wrap the more utilitarian portio

    the terminals airside, but the Gate Hold, Restaurant, and Upper Gal

    have expansive views out to the airside and are treated with glazing

    articulated copper panels.

    Schematic Design4.07

    Schematic Design S

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    26/33

    Schematic Design SCheyenne Region

    09 Febru

    cross section at cafe

    cross section at gate hold

    Building Sections

    In response to the Boards concerns about a flat-roofed terminal des

    and that the building looked too boxy or heavy during Workshop 3, t

    exterior design was reevaluated. A Butterfly roof was determined

    good fit for the terminal, providing a light feeling roof with deep overto provide sun protection. This roof form allows water to be controlle

    fectively, keeping it from running onto either the curbside or the airs

    also allows for rain water to be collected and retained for site irrigati

    Schematic Design4.08

    Schematic Design S

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    27/33

    gCheyenne Region

    09 Febru

    Building Renderings

    A continuous clerestory window immediately below the deep overha

    makes the roof appear to float over the building. The continuous gla

    ing at the curbside makes for an easy transition between the interior

    the exterior spaces, with the fireplace visible and inviting. A smaller

    monitor over the ticketing hall brings sunlight into these spaces.

    view of terminal from parking

    Schematic Design4.09

    view of terminal from access road

    Schematic Design S

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    28/33

    gCheyenne Region

    09 Febru

    view of curb side at baggage claim

    view of curb side from SW

    Schematic Design4.10

    view of curb side

    Schematic Design S

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    29/33

    Cheyenne Region

    09 Febru

    view of gate hold from NE

    view of gate hold from NW

    Schematic Design4.11

    Schematic Design S

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    30/33

    Cheyenne Region

    09 Febru

    view of arrival/departure hall

    Schematic Design4.12

    Schematic Design SCh i

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    31/33

    Cheyenne Region

    09 Febru

    Interior Material and Color Concept A

    Schematic Design4.13

    Interior Material and Color Concept B

    Schematic Design SCh R i

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    32/33

    Cheyenne Region

    09 Febru

    Schematic Design4.14

    Concrete Floor Pattern

    Schematic Design SCheyenne Region

  • 7/18/2019 Schematic Design-Cheyenne Regional Airport

    33/33

    Cheyenne Region

    09 Febru

    5. Site Desig

    Site Design5.00