    DAKSHIN HARYANA BIJL I VITRAN NIGAM

    Sales Circu lar No . D-11/2014

    FromCE/Commercial,DHBVN, Hisar.

    To All CEs/SEs/XENs/SDOs/OP,JEs-I, Incharge Sub office, in DHBVN.

    Memo No. Ch-11/GM/Comml./ R-16/346/2005/F-27 Dated 31/1/2014

    Subject: Single point Supply to Residential Colonies or Office cum residentialComplexes of Employers, Group Housing Societies and Commercial cum Residential Complexes of Developers, Regulation s.

    Please refer to Sale Circular No. D-04/2013 dated 19.01.2013 was issued in

    compliance to the HERC notification dated 09.01.2013 vide which the detailed guidelines for single

    point supply were circulated. Now, it has been decided that all Power Colonies (having more than 20

    nos. houses) to be issued bills on Single Point Metering w.e.f. 01 .04.2014.

    The procedure for implementation of the regulation are as under please.

    The procedure for implementation of supply of electricity on single point is to be

    completed by 15 th

    1. All Head of the State Power Utilities / BBMB / Power grid shall issue directions for appointment of

    Nodal Officer for the colonies under their jurisdiction.

    February.

    2. The designated officers names be intimated to the office of XEN/Monitoring DHBVN, Hisar

    by 5 th

    3. The Nodal officer will map the colony on the enclosed format-I by 15

    February . th

    4. The SDO (OP) will get prepared a separate meter blank as per the list supplied by the Nodal

    officer.

    February and will hand

    over to the SDO (OP) concerned.

    5. The bills will be issued as usual in the month of February / March and the final reading in the

    bills of February / March 2014 will also be supplied to the Nodal officer and that meter reading

    will be entered in the meter blanks as IR. for the next bills.

    6. All the meters in that colony will be read on the same day in the month of February / March andsimultaneously reading of Single Point meter will be recorded.

    7. On First April, the reading of Single Point Meter and all meters will be read

    simultaneously.

    8. On the basis of reading of 1 st April, the bills of Single Point Supply and consumers will be

    generated, will be issued by 7 th April and to be distributed by 10 th

    9. All residents have to deposit their bills to the Nodal Officer by 17

    of April. th April and the Nodal

    Officer will deposit Single Point bill to the SDO (OP) by 25 th

    Initially the SDO (OP) will provide services for:-

    April.

    1. Preparation of Meter Blank as per survey to be submitted by the Nodal officer.2. Preparation of bill on the reading to be submitted by Nodal Officer.

    3. Mtc. of the LD system and Distribution transformer.

    4. Replacement of any defective meter on deposit of meter cost by the Nodal officer.

    5. The facility for testing of individual meters for accuracy / tempering or calibration /

    sealing on the request of Nodal officer.

    The above instructions should be brought to the notice of all concerned for careful and

    meticulous compliance please.

    SE/Commercial,For CE/Commercial,

    DHBVN, His ar.

  • 8/11/2019 SC.2014-11

    2/2

    Name of S/Div.

    Format- 1

    Name of Colony:-

    Sr.No House

    No.

    Name of person

    Residing

    Designations Account No.