Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
SC RF Studies in Europe
Carlo PaganiINFN Milano and DESY
On leave from University of Milano
HIF0531 May 2005Carlo Pagani 2
SRF before TESLA
“Livingston Plot” from Hasan Padamnee
HIF0531 May 2005Carlo Pagani 3
Limiting Problems
Poor material propertiesModerate Nb purity (Niobium from the Tantalum production)Low Residual Resistance Ratio, RRR Low thermal conductivityNormal Conducting inclusions Quench at moderate field
Poor cavity treatments and cleannessCavity preparation procedure at the R&D stagePoor rinsing and clean room assembly not yet introduced
Microphonics Mechanical vibrations in low beta structures High RF power required
MultipactoringMajor limit for HEPL and electron linacs to 1984 Poor codes and surface status
Quenches/Thermal breakdownLow RRR and NC inclusions
Field EmissionGeneral limit at those time because of poor cleaning and material defects
HIF0531 May 2005Carlo Pagani 4
R&D waiting for big projects
MultipactoringA few computer codes developedSpherical shape realized at Genova and qualified at Cornell & Wuppertal
Field EmissionEmitters were localized and analyzedImproved treatments and cleanness
Quenches/Thermal BreakdownHigher RRR NbDeeper control for inclusions
1984/85: First great successA pair of 1.5 GHz cavities developed andtested (in CESR) at Cornell
Chosen for CEBAF at TJNAF for a nominal Eacc = 5 MV/m
Eacc
> 5 MV/m
HIF0531 May 2005Carlo Pagani 5
Large project impact on SRF technology
In 1985 the successful test of a pair of SC cavities in CERS opened the door to the large scale application of SRF for electrons
The decision of applying this unusual technology in the largest HEP accelerators forced the labs to invest in Research & Development, infrastructures and quality control
The experience of industry in high quality productionshas been taken as a guideline by the committed labs
At that time TJNAF and CERN played the major rolein SRF development, mainly because of the project size
The need of building hundreds of cavities pushed the labs to transfer to Industry a large part of the production
The large installations driven by HEP produced a jump in the field
R&D and basic research on SRF had also a jump thanks to the work of many groups distributed worldwide
LEP
CEBAF
HIF0531 May 2005Carlo Pagani 6
CEBAF and LEP II
LEP II & CERN
32 bulk niobium cavitiesLimited to 5 MV/mPoor material and inclusions
256 sputtered cavitiesMagnetron-sputtering of Nb on CuCompletely done by industryField improved with time<Eacc> = 7.8 MV/m (Cryo-limited)
352 MHz, Lact=1.7 m
1.5 GHz, Lact=0.5 m5-cell cavities
4-cell cavities
CEBAF
338 bulk niobium cavitiesProduced by EU industryProcessed at TJNAF in a dedicated infrastructure
HIF0531 May 2005Carlo Pagani 7
Important technological steps
Use of the best niobium (and copper) allowable in the market at the time Industrial fabrication of cavity components with high level quality controlAssembly of cavity components by Industry via Electron Beam welding in clean vacuum Use of ultra pure water for all intermediate cleaning Use of close loop chemistry with all parameters specified and controlledCavity completion in Class 100 Clean Room
– Final cleaning and drying (UV for bacteria and on line resistivity control)
– Integration of cavity ancillaries
That is
New level on Quality Control
HIF0531 May 2005Carlo Pagani 8
A great success for LEP II
0
5
10
15
20
25
30
4 4.2 4.4 4.6 4.8 5 5.2 5.4 5.6 5.8 6 6.2 6.4 6.6 6.8 7 7.2 7.4 7.6 7.8 8 8.2 8.4 8.6 8.8 9 9.2 9.4
Accelerating field [MV/m]
Num
ber o
f cav
ities
96 GeV100 GeV104 GeV
96 GeV:Mean Nb/Cu6.1 MV/m
100 GeV: 3500MVMean Nb/Cu6.9 MV/m 104 GeV: 3666MV
Mean Nb/Cu7.5 MV/m
design
Accelerating Field Evolution with time Final energy reach limited by
allowable cryogenic powerfrom G. Geschonke’s Poster for the ITRP visit to DESY
HIF0531 May 2005Carlo Pagani 9
Same lessons learned
Bulk Niobium is preferred to push for gradient and quality factor
Magnetron sputtering looks better in some cases (LHC) when beam current is more important than accelerating field
Cryogenics systems are highly reliable and produced by industry
SRF ancillaries can be designed to be as reliable as the one required by the Normal Conducting RF technology
– 2 K operation and SRF quality controls end to be a plus
For high gradient, Eacc, and high quality factor, Q, Niobium quality has to be pushed to the possible limit
Quality control during cavity production and surface processing has to be further improved. High Pressure Rinsing can make the difference
Basic R&D and technological solutions must move together
When fabrication procedures are fully understood and documented,Industry can do as well and possibly better
HIF0531 May 2005Carlo Pagani 10
The TESLA Mission
TTF: TESLA Test Facility• Full Prototype of the TESLA Linac: components and operation• Infrastructure: for cavity development and module assembly
Basic goals• Increase gradient by a factor of 5 (Physical limit for Nb at ~ 50 MV/m)• Reduce cost per MV by a factor 20 (New cryomodule concept and industrialization)• Make possible pulsed operation (Combine SRF and mechanical engineering)
as in 1995
Björn Wiik
Develop SRF for the future TeV Linear Collider
HIF0531 May 2005Carlo Pagani 11
RSF for Higher Luminosity
yx
e
c.m.
b
σσN
EPL ×∝
nb = # of bunches per pulsefrep = pulse repetition ratePb = beam powerEc.m.= center of mass energy
L = LuminosityNe = # of electron per bunchσx,y = beam sizes at IPIP = interaction point
yx
2e
σσNL ∝ xσ
yσrepb fnL ×∝
Parameters to play withReduce beam emittance (εx
.εy ) for smaller beam size (σx.σy )
Increase bunch population (Ne )Increase beam powerIncrease beam to-plug power efficiency for cost
( )repbb fnNP ××∝ e
Potential advantages of SRF Technology• Higher conversion efficiency: more beam power for less plug power consumption• Lower RF frequency: relaxed tolerances and smaller emittance dilution
HIF0531 May 2005Carlo Pagani 12
laser driven electron gun
photon beam diagnostics
undulatorbunch
compressor
superconducting accelerator modules
pre-accelerator
e- beam diagnostics
e- beam diagnostics
240 MeV 120 MeV 16 MeV 4 MeV
The TTF I Linac – 6 Year exp.
HIF0531 May 2005Carlo Pagani 13
TTF II – VUV FEL
RF gun
400 MeV 120 MeV800 MeV
ACC 1ACC 2ACC 3ACC 4ACC 5
4 MeV
TESLA like tunnel for ACC 6 & ACC 7
Second BunchCompressor
ACC 4 & ACC 5 ACC 2 & ACC 3
VUV FEL User Facility• Linac Commissioning done
• SASE FEL Commissioning• High Gain done• Saturation coming soon
HIF0531 May 2005Carlo Pagani 14
First 7 year balance (1992-98)(TESLA Cold Technology)
Funding
Major European Contributions(including personel)
DESY (+Germany) ~ 50%
France (CEA + IN2P3) 10-15%
Italy (INFN) 10-15%
and FNAL for US 10-15%
Design
Major European Contributions(in alphabetic order)
CEA/IN2P3
CERN
DESY
INFN
HIF0531 May 2005Carlo Pagani 15
The TESLA Cavity
Hz/(MV/m)2≈ -1KLorentz
kHz/mm315∆f/∆l
mT/(MV/m)4.26Bpeak/Eacc
2.0Epeak/Eacc
Ω1036R/Q
TESLA cavity parameters
- Niobium sheets (RRR=300) are scanned by eddy-currents to detect avoid foreignmaterial inclusions like tantalum and iron- Industrial production of full nine-cell cavities:
- Deep-drawing of subunits (half-cells, etc. ) from niobium sheets- Chemical preparation for welding, cleanroom preparation- Electron-beam welding according to detailed specification
- 800 °C high temperature heat treatment to stress anneal the Nband to remove hydrogen from the Nb- 1400 °C high temperature heat treatment with titanium getter layerto increase the thermal conductivity (RRR=500)- Cleanroom handling:
- Chemical etching to remove damage layer and titanium getter layer- High pressure water rinsing as final treatment to avoid particlecontamination
Figure: Eddy-current scanning system for niobium sheets Figure: Cleanroom handling of niobium cavities
9-cell, 1.3 GHz
Major contributions from: CERN, Cornell, DESY, CEA-Saclay & INFN
HIF0531 May 2005Carlo Pagani 16
A dedicated new infrastructure at DESY
Scanning niobium material for inclusionClean closed loop chemistry (Buffer Chemical Polishing – BCP)High Pressure Rinsing, HPR, and clean room dryingClean Room handling and assembling (Class 10 and 100)
HIF0531 May 2005Carlo Pagani 17
Learning curve with BCP
3 cavity productions from 4 European industries: Accel, Cerca, Dornier, ZanonBCP = Buffered Chemical Polishing
Cornell1995
5-cellModule performance in the TTF LINAC
Improved weldingNiobium quality control
<Eacc> @ Q0 ≥ 1010 <Eacc> @ Q0 ≥ 1010
at Q = few 109
<1997>
<1999>
<2001>
HIF0531 May 2005Carlo Pagani 18
Electro-Polishing & Baking for 35 MV/mThe AC 70 example
Electro-Polishing (EP)instead of
Buffered Chemical Polishing (BCP)• less local field enhancement• High Pressure Rinsing more effective • Field Emission onset at higher field
In Situ Baking
@ 120-140 ° C for 24-48 hours
• to re-distribute oxygen at the surface
• cures Q drop at high field
EP at the DESY plant• Low Field Emission 800°C annealing
120°C, 24 h, Baking• high field Q drop curedHigh Pressure Water Rinsing
Vertical and System Test in 1/8th Cryomodule
HIF0531 May 2005Carlo Pagani 19
Radiation Dose from the fully equipped cavities while High Power Tested in “Chechia”“Chechia” is the horizontal cryostat equivalent to 1/8 of a TTF Module
Field Emission pushed to very high fieldBCP Cavities used in Modules 4 & 5 are in red, EP cavities in blue
BCP Cavities @ Eacc = 25 MV/m
EP Cavities @ Eacc = 35 MV/m
BCP = Buffered Chemical Polishing
EP = Electro-Polishing
Radiation dose producing50 nA of captured DarkCurrent: that is the TESLA safe limit giving200 mW of induced cryo-losses at 2 K
HIF0531 May 2005Carlo Pagani 20
Performing Cryomodules
Required plug power for static losses < 5 kW/(12 m module)
Reliable Alignment Strategy
Sliding Fixtures @ 2 K
“Finger Welded” Shields
Three cryomodule generations to:improve simplicity and performances minimize costs
HIF0531 May 2005Carlo Pagani 21
ACC4 & ACC5 Met Specs
Still some work at the module interconnectionCavity axis to be properly defined
HIF0531 May 2005Carlo Pagani 22
Cold time[months]
Installation date
Type
13
161616
278
35
44
12
5
50
Feb 04M2*
Apr 03M3*M4M5
Jun 02M1*MSS
Jun 99M3
Sep 98M2
Jan 98M1 rep.
Mar 97M1
Oct 96CryoCap
Extensive Operation Experience
1
22
2
22
332
2
HIF0531 May 2005Carlo Pagani 23
LCH and TESLA/ILC Module Comparison
From an LHC Status Report by Lyndon R. Evans
ACC 4 & ACC 5 in TTF ACC 2 & ACC 3 in TTF
∅ = 38”
∅ = 38” ∅ = 42”
HIF0531 May 2005Carlo Pagani 24
TESLA Cryomodule Concept Peculiarities
PositiveVery low static lossesVery good filling factor: Best real estate gradientLow cost per meter in term both of fabrication and assembly
Project DependentLong cavity strings, few warm to cold transitionsLarge gas return pipe inside the cryomodule Cavities and Quads position settable at ± 300 µm (rms)Reliability and redundancy for longer MTTR (mean time to repair)Lateral access and cold window natural for the coupler
Negative ?Longer MTTR in case of non scheduled repairModerate (± 1 mm) coupler flexibility required
HIF0531 May 2005Carlo Pagani 25
DA
C
DA
C
ReIm
Cavity 32......8x
Cavity 25
klystronvector
modulator masteroscillator
1.3 GHz Cavity 8......8x
Cavity 1
cryomodule 4
...cryomodule 1
. . . .
LO 1.3 GHz + 250 kHz
250 kHz
AD
C
f = 1 MHzs
. . . . ...
vector-sumΣ( )ab
a -b
1 8( )ab
a -b
25( )ab
a -b
32( )ab
a -b
DSPsystemsetpoint
tablegaintable
feed
tableforward
++digital
low passfilter
ImReImRe ImRe
clock
LOA
DC
LO
AD
C
LO
AD
C
ImRe
power transmission line
1.3GHzfield probe
3
cavity 36cavity 1 cavity 12
36
cavity 24
24121
Principle of RF Control
200 400 600 800 1000 1200 1400 1600 18000
5
10
15
400 600 800 1000 120011
11.5
12
12.5
zoomed region
acce
lera
ting
vol
tage
[M
V]
only feedback
(gain = 70)
with feedback and feedforward
control
beam
0 500 1300900 1700
300 700 1100
75
50
25
0
62.5
60.0
55.5
57.5
time [µs]
200 400 600 800 1000 1200 1400 1600 1800
−15−10
−50
5
with feedback and feedforward
control
only feedback
(gain = 70)
400 600 800 1000 1200
−1
−0.50
0.51
beam
300 700 1100
1
0
-1
zoomed region
15
10
5
0
-5
acce
lera
ting
pha
se[d
eg]
0 500 1300900 1700
time [µs]
Contributions to Energy Fluctuations
1. Lorentz Force2. Microphonics3. Bunch-to Bunch Charge Fluctuations4. Calibration error of the vector-sum5. Phase noise from master oscillator6. Non-linearity of field detector7. Klystron Saturation8. RF curvature (finite bunch length)9. Wakefield and HOMs
−80 −60 −40 −20 0 20 400
1
2
3
4
5
6
7∆f = - K · Eacc
2
grad
ient
[M
V/m
]
∆f [Hz]
K = 0.9 Hz(MV/m)2
0 500 1000 1500 2000−300
−200
−100
0
100
200
300
time [µs]
detu
nin
g [H
z]
Lorentz Force Detuning of D39 in Chechia
fill: 500 µs
flat: 800 µs
15 MV/m20 MV/m25 MV/m30 MV/m
Figure 3: Influence of radiation pressure on the resonance curve of a sc cavity. a) Static detuning during cw oper-ation and b) dynamical detuning during nominal TESLA pulse.
17:30 18:00 18:30−30
−25
−20
−15
−10
−5
cavity 1
time [h]
detu
nin
g [
Hz]
−40 −30 −20 −10 00
10
20
30
40
detuning [Hz]
no
. o
f m
easu
rem
en
ts
cavity 1 σ = 4 Hz∆f
Figure 2: Fluctuations of the cavity resonance frequency. a) Slow drifts over a period of one hour and b) prob-ability density of the cavity resonance frequency with an rms width of 2Hz - 7Hz.
Microphonics
Lorentz Force Detuning
Operation with Final State Machine
Measure Step Response
T11 T12 … T1n
T21 T22 … T2n
… … … …Tn1 Tn2 … Tnn
Closed LoopIdentification
WaveletFilter
new FFTable
calculateCorrection ofold FF Table
measure Control-Error
Adaptive Feed Forward can handle nonlinear systems throughlinarisation around the operating point.
0 500 1000 1500
−150
−100
−50
0
50
100
150
0 500 1000 1500
−3000
−2000
−1000
0
1000
2000
3000
4000
5000
0 500 1000 1500
−2000
0
2000
4000
6000
8000
10000
12000
14000
16000
tt
t t
∆ff
ffff∆E
few seconds.The calculation of a new feed forward table needs only a
0 500 1000 1500
−2000
0
2000
4000
6000
8000
10000
12000
14000
16000
Adaptive Feedforward
from TTF Console in Milano
Ancillaries: LLRF
HIF0531 May 2005Carlo Pagani 26
Ancillaries: Power Coupler
• TTF III Coupler has a robust and reliable design.
• Extensively power tested with significant margin
• New Coupler Test Stand at LAL, Orsay
10 + 30 New Couplers in construction by industry
Pending Problems
• Long processing time: ~ 100 h
• High cost (> cavity/2)
• Critical assembly procedure
Dedicated laboratory at LAL/Orsay
HIF0531 May 2005Carlo Pagani 27
Ancillaries: Cavity Tuners
The Saclay Tuner in TTF The INFN Blade-Tuner
Successfully operated with superstructures
HIF0531 May 2005Carlo Pagani 28
The X-FEL
50%-60% funded by the German Government - European consensus establishedGreat opportunity for all TESLA Technology based Projects
– Machine reliability according to SRL standards– Industrial mass production of cavities (~ 1000) and modules (> 120)
HIF0531 May 2005Carlo Pagani 29
feed cap
end cap cryomodule
supports
feed box
feed cap transfer line
Cryomodule Test Stand @ DESY
•Under construction
• Commissioning 2005/06
HIF0531 May 2005Carlo Pagani 30
Cry3 adaptation in progress
HIF0531 May 2005Carlo Pagani 31
The Ciemat 2K Quadrupole
HIF0531 May 2005Carlo Pagani 32
Industrial Study
• Technology transfer from Research to Industry
• Review with industry of the cryomodule design and assemblyto focus:
• Cost drivers
• Critical steps of the assembly procedure
• Suggestion based on industrial experience in term of:
• Similar productions
• Labor organization
• Quality control
HIF0531 May 2005Carlo Pagani 33
New QC in cavity production
From Valdemar Singer
HIF0531 May 2005Carlo Pagani 34
EU Funding: CARE-JRA1
JRA1–SRF 5M€ from EU
Improved cavity fabrication
Thin film cavity production
Seamless cavity fabrication
Surface preparation
Materials analysis
Power couplers
Cavity tuners
Low level RF control
Cryostat integration test
Beam diagnostics
CARE is funded at the level of 15.2 M€ over 5 years
HIF0531 May 2005Carlo Pagani 35
TTF: Raw data for trendsEsurf = 2 Eacc for β=1 (TESLA)
Taking into account all data from 1995
1/1/1995 1/1/1997 1/1/1999 1/1/2001 1/1/2003 1/1/2005
0
10
20
30
40
50
60
70
80
90
Emax FE start
Esurf [MV/m]
Date
HIF0531 May 2005Carlo Pagani 36
Average of “best” > 40 MV/mAverage of “safe” (no FE)> 30 MV/m
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.00
10
20
30
40
50
60
70
80
ANL
ANLIPN
MSU
LNL
LANL
LANL
Average TTFChemically etched cavitiesMax Eacc = 28 MV/mFE onset @ 21 MV/m
CEA/CNRS
SNS production
Sur
face
Ele
ctric
Fie
ld [M
V/m
]
β
Field Emission region Field Emission free operation
5 cavitiesTRASCO/RIA
Peak electric field on surface
?
Cavities hitting high magnetic field limitations, as well as TTF, are not taken into account in these averages
HIF0531 May 2005Carlo Pagani 37
Coupler Development at LAL-Orsay
TTF III
Clean room assemblyHigh Power Coupler Test Stand
Alternative Designs
HIF0531 May 2005Carlo Pagani 38
New design with piezos• CARE/JRA-SRF
• SOLEIL upgrades
• larger rigidity
• Fabrication of 2 tuners since beginning of 2005• 12 NOLIAC piezos, 2 PHYTRON stepping motors ordered• Coll. with IPN Orsay: CEA send NOLIAC piezos to IPN for
characterization, and IPN send P.I. piezos for tests on tuners• Coll. with INFN-Milano for measurement with stress sensors @ 2K
New Saclay Tuner for XFEL
HIF0531 May 2005Carlo Pagani 39 Status as on February 1st, 2005
New INFN Blade-Tuner
• Integration of piezos for Lorentz forces and microphonics completed.
• Final Drawing delivered for fabrication.
• Two prototype, including the modified helium tank, were expected by end of June 2005
• Cold tests results by fall 2005 (DESY, BESSY, Cornell?)
HIF0531 May 2005Carlo Pagani 40
CryHoLab at Saclay/Orsay
HIF0531 May 2005Carlo Pagani 41
HIPPI for SPL
HIF0531 May 2005Carlo Pagani 42
HIPPI for SPL
HIF0531 May 2005Carlo Pagani 43
SRF TESLA Technology for ADS
Spallation target & Spallation target & subsub--critical corecritical core
∼5 MeV100 keV
~ 100 MeV ~ 500 MeV~ 200 MeV
β = 0.65β = 0.47 β = 0.85
600 MeV
SC elliptical cavities (700 MHz, 3 sections)SC elliptical cavities (700 MHz, 3 sections)
RFQRFQ
Sour
ceSo
urce
β = 0.35SC or warm CH
SC or warm CH--DTL DTL
structure ? structure ?
RFQRFQ
Sour
ceSo
urce
« X MeV » (between 5 &
50 MeV)
SC or warm CH
SC or warm CH--DTL DTL structure ? structure ?
SC spoke cavities SC spoke cavities (350 MHz, 1 or 2 sections)(350 MHz, 1 or 2 sections)
Beam Beam dumpdump
17
12
13
27
4
825
1
2
26
22
20
28
3
24
9
16
7
6
5
15
23
1831
30
10
19
29
8
1110
21
1411
29
High Energy SectionHigh Energy Section
EU Program named PDS-XADS now moving to EuroTrans
0 2 4 6 8 10 12 14 16 18 20
109
1010
start of electron emission
Test #1 limited by strong field emission
Q0
Eacc [MV/m]
Z501 Z502 - before conditioning Z502 - after conditioning Design Value
multipacting barriers
The accelerator design has been developed for Nuclear WasteTransmutation by an INFN-CEA-CNRS collaboration.
The high energy section is now used by HIPPI and SPL too
HIF0531 May 2005Carlo Pagani 44
A Few Remarks
The interest for the SRF Technology is wide and growing in Europe like in the other two Regions
The TESLA Collaboration achievements with TTF were sufficient to convince ITRP to recommend cold for ILC
EU is plying a positive role in coordinating some SRF activities in different labs and for different projects
That’s fine, but not enough