SAP Note 1012486 - Important Information on upgrading SAPSystems in HA-Setups
Note Language: English Version: 5 Validity: Valid Since 10.03.2008
Summary
Symptom
You consider upgrading an SAP system, which has been configured to run
inside a highly available (switch over) hardware environment. This note
contains important additional information on how to plan the upgrade in
such an environment.
Other terms
hardware cluster, HA, High Availability, ERP2005, ECC 6.0, mySAP ERP
Reason and Prerequisites
Your SAP system is installed in an HA environment using a failover hardware
cluster.
Solution
Upgrade Planning
o HA Solution Provider/Hardware Partner Involvement
Make sure to involve your hardware and HA solution provider in your
upgrade planning. You may need to update the cluster software or
cluster hardware so that it can support the new SAP release. Such
3rd party updates are not part of the upgrade paths described in
the SAP upgrade guides. Carefully plan the complete system upgrade
procedure with your HA solution provider and hardware partner
before starting the upgrade.
Involving the partners can dramatically shorten the support times
in case of an unexpected upgrade problem.
Recommended Upgrade Preparations
o Disabling/Enabling cluster failover capabilities
At the beginning of the upgrade downtime phases you will be
requested to disable the cluster failover capabilities. This is
required to allow the upgrade tools to stop and restart clustered
instances. Otherwise, the cluster software might detect the stop of
a clustered instance as an instance failure and will start it again
on the failover host.
Switching off the cluster failover capabilities should only disable
the automatic failover mechanism of your cluster solution, but
should not take the related ressources offline. For example, the
upgrade tool must still be able to start and stop the instances,
and the file systems assigned to the clustered instance must be
read/write accessible.
To reduce the overall system outage time, prepare the required
procedures to disable/enable cluster failover features before youstart the upgrade.
8/8/2019 sapnote_0001012486
http://slidepdf.com/reader/full/sapnote0001012486 2/3
05.12.2010 Page 2 of 3
SAP Note 1012486 - Important Information on upgrading SAPSystems in HA-Setups
o Creating an optimal upgrade starting point
To create a reliable starting point for the upgrade it is crucial
to implement an HA system configuration recommended by SAP. Below
you find a list of known problems with other configurations:
- If you have manually set up a standalone enqueue, you should
revert this configuration prior to the execution of the
downtime phases of the upgrade, latest prior to kernel switch
phase. The upgrade tool is unable to detect a manual set up of
standalone enqueue servers and, therefore, cannot update them.
This might cause problems when the system is started for the
first time after the kernel switch. This only applies to
standalone enqueue servers (separately started enserver
process), NOT to officially supported (A)SCS instances.
- Clean up the profile directory. Remove any old, unused profiles
and backup copies. The directory should only contain activeprofile files. Also links to local profiles with different
names should be avoided. Only files are expected.
o Removing Java 6.30 Add-In from 6.20 ABAP instances
Remove Add-in installations of SAP Web AS Java 6.30 from the SAP
Web AS ABAP 6.20 instances. These Java Add-Ins cannot be updated.
You can re-install the Add-In after the upgrade has succeeded.
Perform Standard Upgrade
o Perform the standard upgrade process as described in the respective
SAP software upgrade guide and the related central SAP Note for the
upgrade.
Post-Upgrade Activities
o Installing Enqueue Replication Server (ERS) instances
If you are running an ASCS or SCS setup, make sure to have an
Enqueue Replication Server (ERS) installed. More information on how
to set up an ERS with your cluster failover software can beprovided by your HA solution implementation partner.
Header Data
Release Status: Released for Customer
Released on: 25.03.2008 08:33:52
Master Language: English
Priority: Recommendations/additional info
Category: Upgrade informationPrimary Component: BC-UPG Upgrade - general
8/8/2019 sapnote_0001012486
http://slidepdf.com/reader/full/sapnote0001012486 3/3
05.12.2010 Page 3 of 3
SAP Note 1012486 - Important Information on upgrading SAPSystems in HA-Setups
Valid Releases
Software Component Release From
Release
To
Release
and
Subsequent
SAP_APPL 600 600 600 XSAP-JEE 60 6.40 6.40
SAP-JEE 7.00 7.00 7.01
SAP_BASIS 60 620 640
SAP_BASIS 70 700 701
SAP_BASIS 71 710 711
Related Notes
Number Short Text
1061649 Upgrade to SAP NetWeaver Process Integration 7.1