Upload
vukien
View
216
Download
0
Embed Size (px)
Citation preview
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-05-2018)
BUDGET - $ 72,000,000
• 2020 PROJECTED COMPLETION DATE• ARCHITECT – MARMON MOK• GENERAL CONTRACTOR – Bartlett Cocke• CONSTRUCTION MGMT. – AG|CM
• 33% COMPLETE
SAMUEL CLEMENS ADDITIONS & RENOVATIONS
As part of the Bond 2016 Program, Samuel Clemens High School Additions and Renovations will consist of expansion of square footage and renovation of existing spaces to meet current educational/industry standards. Some main points regarding scope of work included in this project:
• New Event Center (connected to Beard Gym) to house new auditorium, new auxiliary gym, new choir and dance areas, new locker rooms and support spaces.
• New Career & Technology (CTE) Building (near Baseball Field) to house welding, woodshop, floral design, small animal, and other learning spaces, including new classrooms.
• The existing Auxiliary Gym will be renovated to include additional CTE classrooms and labs, including a new culinary kitchen, health occupations spaces and other learning areas.
• The existing auditorium will be removed and the courtyard space will be enlarged.• New Front Addition (facing Elbel Rd.) which will include new classrooms and new administration and
support spaces.• Renovation of JROTC spaces and existing spaces.• Additional renovated spaces throughout the building, such as art rooms, teacher work spaces, nurse’s
clinic.• Additional parking space, to include new parking along Elbel and near stadium.• ESTIMATED PROJECT COMPLETION – SPRING 2020.
SAMUEL CLEMENS ADDITIONS & RENOVATIONSSCHEDULE
ACTION/EVENT PROJECTED DATEFINAL DESIGN APPROVED (BOT) January 2017BIDS OUT FOR CONTRACTORS February 22, 2017
BIDS RECIEVED March 30, 2017EVALUATION OF BIDS March 30 – April 5, 2017CONTRACTOR RECOMMENDATION TO BOT April 18, 2017NOTICE TO PROCEED May 24, 2017PROJECT COMPLETION February 2020
ONGOING ACTIVITIESCTE Building• Exterior Site work
Event Center (Locker Rm Facilities)• Forming up Mezzanine slab
Classroom / Admin Add• MEP rough-ins• Exterior sheathing & waterproofing• Roofing installation
Event Center (Auditorium)• Formwork for suspended slab
Practice Gym• Roofing• Electrical rough-ins• Exterior masonry
Greenhouse• Structural framing• MEP rough-ins
SAMUEL CLEMENS ADDITIONS & RENOVATIONS
02-05-2018
Located near baseball field on what used to be old tennis courts.
This building will house welding, woodshop, small animal and other Career & Technology classes.
New Career, Technology, and Engineering building has ongoing punch-list finish out and perimeter site work.
Career, Technology, and Engineering Building – Site Work Expected Completion Feb. 2018
SAMUEL CLEMENS ADDITIONS & RENOVATIONSClassroom and Administration Addition – Expected Completion August 2018
New Classroom and Administration addition. Metal stud framing, interior masonry, prep for exterior masonry, sheathing/waterproofing, roofing, ongoing MEP work.
This building will be an addition to the front of the main high school front entry.
This building will include nineteen instructional classrooms and support additional administration offices
02-05-2018
SAMUEL CLEMENS ADDITIONS & RENOVATIONSClassroom and Administration Addition – Expected Completion August 2018
New Classroom and Administration addition. Metal stud framing, interior masonry, prep for exterior masonry, sheathing/waterproofing, roofing, ongoing MEP work.
This building will be an addition to the front of the main high school front entry.
This building will include nineteen instructional classrooms and support additional administration offices
02-05-2018
SAMUEL CLEMENS ADDITIONS & RENOVATIONSAuxiliary Gym Addition – Expected Completion August 2018
New Auxiliary Gym addition has metal stud framing, exterior sheathing, MEP work, & roofing
02-05-2018
This building will be an addition to Beard Gym and the future Event Center
Gym will support as the new practice gym and seat approximately 300 people
SAMUEL CLEMENS ADDITIONS & RENOVATIONSEvent Center – Expected Completion August-November 2018
The New Event Center area will consist of: new auditorium, new dance/cheer studio, new choir room and new locker room facilities.
New Event Center continues with support framing/concrete columns for mezzanine slab and formwork for auditorium slab.
02-05-2018
SAMUEL CLEMENS ADDITIONS & RENOVATIONSBuffalo Drive Parking Lot – Expected Completion February 2018
New Parking Lot on the NE side of the property along Buffalo Drive will bring added parking spaces for the Clemens students.
New Buffalo Drive Paring Lot is underway with curbs in place and asphalt paving to follow
02-05-2018
SAMUEL CLEMENS ADDITIONS & RENOVATIONSGreenhouse– Expected Completion March 2018
New Greenhouse is located north of the baseball field.
New Greenhouse is underway with structural framing & MEP rough-ins.
02-05-2018
SAMUEL CLEMENS ADDITIONS & RENOVATIONSTwo Week Look Ahead
CTE Building1. Exterior site work continues – south side of Bldg. J
Classroom /Admin Addition1. MEP installation continues2. Metal stud framing/sheathing/waterproofing3. Roofing installation
Auxiliary Gym1. Metal stud framing/sheathing/waterproofing2. MEP work continues3. Roofing installation 4. Exterior masonry
Event Center1. P Bldg. supports/concrete columns for mezzanine slab2. Q Bldg. formwork for auditorium slab3. Steel erection to start up
Samuel Clemens High SchoolSchedule Overview
*Schedule is subject to change throughout the construction lifecycle
Phase Description Start Date Finish Date
1A Summer 1 (MDF, D-Wing Admin, S-Wing Admin, Utilities, Beard Gym HVAC Units) 6/5/2017 8/25/2017
1B North East Parking Lot 6/5/2017 Mid-January 2018
2 New CTE Building 6/5/2017 12/29/2017
3A Classroom and Admin Addition (Front of Building) 6/5/2017 7/31/2018
3B Renovate Existing Admin 6/4/2018 12/28/2018
4A New Auxiliary Gym 6/5/2017 7/31/2018
4B Event Center (Locker Rooms, Choir, Dance, Bridge to B-Wing) 6/5/2017 7/31/2018
4C New Auditorium 6/5/2017 11/1/2018
5A Summer 2 (Renovate ROTC, Campus Lighting Replacement, Terrazzo Floor) 6/4/2018 8/17/2018
5B ROTC Renovation (Start Early) 1/1/2018 8/15/2018
5C Alt #3. Construct New Stair on West Side of Building 6/4/2018 12/28/2018
6A Demo Existing Auditorium and Auxiliary Gym 6/4/2018 8/2/2018
6B Culinary Arts, HOSA, Forensics, Courtyard, Science Renovation, Bridge Addition 8/3/2018 8/16/2019
7A A-Wing Renovation 6/3/2019 8/16/2019
7B B-Wing Renovation 6/3/2019 8/16/2019
7C Remove Portables and Complete Parking Lot Near Schertz Pkwy 6/10/2019 12/31/2019